Juliano Pamplona, Oceana Shipyard discusses the ‘Changing Concept of Production Planning and Control with AVEVA ERM’ at the AVEVA World Summit, 2016 in New Orleans. Learn how planning concept and interface activities between Engineering, Procurement, Warehouse, and Planning departments are planned through AVEVA ERM. Juliana also explains the challenges on shipyard implementation, ERM selection process and the steps of AVEVA ERM implementation and integration with SAP. As a result, AVEVA were able to support shipbuilding processes at Oceana through the use of ERM.
Find out more about how AVEVA can support your business >> www.aveva.com
2. 2
OCEANA SHIPYARD: Changing Concept of
Production Planning and Control with AVEVA ERM
AVEVA World Summit 2016
Juliano Pamplona
3. 3
Main Achievements
High cooperation between departments on Production Planning and Control
(Changing Planning Concept);
Reliable information from Projects whenever required (shipyard, group
presidency and shareholders);
Efficient planning and execution:
Release work orders closer to the execution date (Job Cards);
Use one integrated system to simplify access to information;
Accurate delivery of the right material, at the right time, to the right place;
Continuously monitor man-hour usage;
Report Project status on time to update the Project plan.
4. 4
Agenda
Institutional
Planning and Control System
Choosing ERM: Challenges to Overcome
Deployment
Information Flow / Integration with SAP
Strong Points / Opportunities
Next Steps
Institutional
6. 6
Institutional - Group CBO Portfolio
ORSV
Length Overall
Deadweight
Service Speed
Year Built
CBO Vitória
CBO Guanabara
CBO CamposCBO Rio
CBO Chiara CBO Isabella
CBO Anita CBO ManoellaCBO Carolina CBO Valentina CBO A. Gabriella
PSV 4500
CBO Flamengo
PSV 3000
CBO Pacífico CBO Atlântico CBO Renata CBO Alessandra CBO Ana Luisa CBO Bianca
CBO has a fleet of 26 vessels:
CBO Copacabana CBO IpanemaCBO Arpoador
PSV 3000
67.0 m
3,020 T
11 KNOTS
2002
76.7 m
3,300 T
13 KNOTS
2005
67.0 m
3,050 T
11 KNOTS
2000
76.7 m 67.0 m
3,400 T 3,050 T
13 KNOTS 11 KNOTS
2010 2001
80.5 m
2,850 T
13 KNOTS
2005
76.7 m
3,200 T
13 KNOTS
2009
75.5 m
3,400 T
13 KNOTS
2010
76.7 M
3,400 T
13 KNOTS
2008
76.7 m
3,400 T
13 KNOTS
2009
74.3 m
3,600 T
13 KN0TS
2007
74.3 m
3,690 T
13 KNOTS
2007
88.8 m
4,550 T
13 KNOTS
2012
76.3 m 76.3 m
3,400 T 3,400 T
13 KNOTS 13 KNOTS
2012 2012
76.0 m 76.0 m
3,400 T 3,400 T
13 KNOTS 13 KNOTS
2011 2011
76.7 m
3,400 T
13 KNOTS
2010
88.8 m
4,550 T
13 KNOTS
2012
88.8 m
4,550 T
13 KNOTS
2014
88.8 m
4,550 T
13 KNOTS
2013
RSV
Length Overall
Deadweight
Service Speed
Year Built
AHTS
12000
Length Overall
Deadweight
Service Speed
Year Built
Length Overall
Deadweight
Service Speed
Year Built
Length Overall
Deadweight
Service Speed
Year Built
Length Overall
Deadweight
Service Speed
Year Built
88.8 m
4,550 T
13 KNOTS
2016
88.8 m
4,550 T
13 KNOTS
2016
CBO Oceana CBO Itajaí
CBO Niterói
67.0 m
3,050 T
11 KNOTS
2014
67.0 m
3,050 T
11 KNOTS
2014
ChallangeVegas
67.0 m
3,020 T
11 KNOTS
2016
11. 11
Agenda
Planning and Control System
Choosing ERM: Challenges to Overcome
Deployment
Information Flow / Integration with SAP
Strong Points / Opportunities
Next Steps
15. 15
SAP
Project Planning
Information Flow
ERM
ENG PLAN
PROC
&
WARE
Production Planning
Issue DRL
(Delivery Request
List)
Issue Job
Card
Bom List
Issue TMR
(Technical Mat. Requisition)
Fabricate list and Drawing
Catalogue
WP and WO Material
Association
Material Control
Picking
PROD
Job Progress
Man-Hour
Back Reporting