SlideShare a Scribd company logo
1 of 29
Download to read offline
Project Quality Mangement

4/3/2011

Project Management
Knowledge Areas
Section – 3
Chapter – 8

Project Quality Management
Session Objectives…
1. To identify the project quality management
knowledge area‟s processes
2. How to plan quality for the project
3. How to implement quality assurance
4. How to monitor and control quality

PMP Prep Course

1
Project Quality Mangement

4/3/2011

Project Quality Management
Exam Objectives…
1. What is Quality
2. Preparing for Quality
3. Planning for Quality
4. Creating the Quality Management Plan
5. Performing Quality Assurance
6. Implementing Quality Control

Project Quality Management
What makes quality to suffer?
 Overworking the project team in order to
complete the project.


◦ May result in unacceptable work due to decline in
team morale


A hurry to complete the project work by
speeding through quality inspections
◦ May result in unacceptable deliverables

PMP Prep Course

2
Project Quality Mangement

4/3/2011

Project Quality Management
Quality Vs Grade
 Quality and Grade are not the same
 Quality is the sum of the characteristics of a
product that meet the specifications /
expectations of the project
 Grade is the category or rank given to entities
having the same functional use but different
characteristics


Quality management characteristics
 Customer satisfaction
 Prevention

Act

Plan

 Management responsibility
 Continuous improvement:-

Plan

Act

PMP Prep Course

Check

Do

– Do – Check –

3
Project Quality Mangement

4/3/2011

Quality Gurus


Phillip B Crosby

 Crosby devised

the “Zero Defects” practice
 That is, DO IT RIGHT THE FIRST TIME
 He says, that costs will increase when quality
planning isn‟t performed upfront, which means,
rework, affecting productivity
 Prevention is the KEY

Quality Gurus


Joseph M Juran

 Is

known for his “FITNES FOR USE”
 That is, stakeholders and customers‟ expectations
are met or exceeded
 Conformance to Specifications

PMP Prep Course

4
Project Quality Mangement

4/3/2011

Quality Gurus
 W Edwards Deming
 Suggested that as much as 85% of quality issues is
management problem
 Deming proposed that workers cannot figure out
quality on their work and thus cannot perform at
their best
 Workers need to be shown what acceptable quality
is
 Deming is major contributor of Total Quality
Management (TQM)

Total Quality Management


Total Quality Management (TQM )

 Says that the process is the problem, not people
 TQM stipulates that quality must be managed in and

that quality improvement should be a continuous
way of doing business



Six Sigma

 Is a quality management approach
 Mostly used in manufacturing and services industries
 Is a measurement based strategy that focuses on

process improvement and variation reduction by
applying Six Sigma methodologies

PMP Prep Course

5
Project Quality Mangement

4/3/2011

Six Sigma
Six Sigma
 It follows methodologies
 DMADV


Define, Measure, Analyze, Design, and Verify
 DMAIC

Define, Measure, Analyze, Improve, and Control
 Six

Sigma aims to eliminate defects and stipulates
that no more than 3.4 defects for million
operations

Project Quality Management


Kaizen technology:
A quality philosophy of applying continuous small
improvements to reduce costs and ensure
consistency



Marginal analysis:
The cost of the incremental improvements to a
process or a product are compared against the
increase in revenue made from the improvements

PMP Prep Course

6
Project Quality Mangement

4/3/2011

Project Quality Management
The project team should adopt the quality policy of
the organization to guide the project implementation
 Project manager should document how the project
will fulfill the quality policy in project management
and deliverables
 If quality policy is not adoptable to the project or the
organization does not have a quality policy, the
project team should create a quality policy for the
project
 Quality is planned, designed, and built in – not
inspected


Plan Quality


The quality management plan addresses
Quality control
Quality assurance
Quality improvement



PMP Prep Course

The process identifies and documents the
quality requirements & standards for project

7
Project Quality Mangement

4/3/2011

Plan Quality
INPUTS
1. Scope Baseline
2. Stakeholder
Register
3. Cost Performance
Baseline
4. Schedule Baseline
5. Risk Register
6. Enterprise
Environmental
Factors
7. Organizational
Process Assets

TOOLS & TECHNIQUES

OUTPUTS

1. Cost-Benefit
Analysis
2. Cost of Quality
3. Control Charts
4. Benchmarking
5. Design of
Experiments
6. Statistical Sampling
7. Flowcharting
8. Proprietary Quality
Management
Methodologies
9. Additional Quality
Planning Tools

1. Quality Management
Plan
2. Quality Metrics
3. Quality Checklists
4. Process
Improvement Plan
5. Project Document
Updates

Plan Quality


Inputs
1. Scope Baseline
2. Stakeholder Register
3. Cost Performance Baseline
4. Schedule Baseline
5. Risk Register
6. Enterprise Environmental Factors
7. Organizational Process Assets

PMP Prep Course

8
Project Quality Mangement

4/3/2011

Plan Quality


Tools and Techniques
1. Cost-Benefit analysis
2. Cost of quality (COQ)
3. Control Charts
4. Benchmarking
5. Design of experiments
6. Statistical Sampling
7. Flowcharting
8. Proprietary Quality Management Methodologies
9. Additional quality planning tools

Plan Quality


Outputs
1. Quality Management Plan
2. Quality Metrics
3. Quality Checklists
4. Process Improvement Plan
Process Boundaries
Process Configuration
Process Metrics
5. Project Document Updates

PMP Prep Course

9
Project Quality Mangement

4/3/2011

Tools & Techniques
Benefit-Cost Analysis
 Benefit:


Completing quality work increases productivity


Costs
Completing quality work may cost little more



Gold plating
Is process of adding extra features that may
increase cost

Cost of Quality


Cost of Quality
The cost of quality is cost of all the activities
within a project to ensure the quality



Cost of conformance to requirements:The cost of completing the project work to satisfy
the project scope and expected quality



Cost of nonconformance
The cost of completing the project without quality

PMP Prep Course

10
Project Quality Mangement

4/3/2011

Cost of Quality
There are three types of Cost of Quality
 1. Prevention Costs


The costs associated with satisfying customer
requirements by producing a product without
defects. Includes quality planning, training

Cost of Quality
 2. Appraisal Costs

The costs expended to examine the product or
process and make certain the requirements are
being met. Includes inspections and testing
 3. Failure Costs

The costs when things don‟t work as expected.
Two types or failure costs are 1. Internal Failure
Costs and 2. External Failure Costs
Ex. 1.Rework – 2. Liabilities, Warranty work, Lost
business

PMP Prep Course

11
Project Quality Mangement

4/3/2011

Control Chart







Used to objectively define a process and variation
Process containing only common causes of
variation is considered stable, implying that the
variation is predictable within the established
control limits
Processes containing special as well as common
causes of variation are considered unstable. In
such cases the special causes fall outside the
established control limits
Control charts can be plotted for tracking
Production failures, defects by schedule/effort/cost
and variances

Control Chart

No. of Defects

Upper Control Limit

Lower Control Limit
Days

Stable Process

PMP Prep Course

12
Project Quality Mangement

4/3/2011

Control Chart

No. of Defects

Upper Control Limit

Lower Control Limit
Days

Unstable Process

Benchmarking
Is comparison among two projects, processes or
performance of organizations
The goal is to evaluate the differences between
two projects and to make corrective actions to the
current project
Is also used as a measurement against industry
standards, competitors‟ level of performance

PMP Prep Course

13
Project Quality Mangement

4/3/2011

Design of Experiments


The approach relies on statistical what-if
scenarios to determine what variables within a
project will result in the best outcome.
Most often used on the product of project rather
than the project
Is also used as a method to identify which variables
within a project or product , are causing failures

Flowcharting



PMP Prep Course

The flowchart shows the logical steps
required to accomplish an objective.
The flowchart steps through a logical
sequence and checks for “YES” or „NO”
branching

14
Project Quality Mangement

4/3/2011

Flowcharting
Measure attributes
of Deliverable

Deliverable
Ready for
Quality check

Conformance
To
Requirements

YES

Deliverable is
Ready for
Dispatch

NO
Return to
owner

Quality Check

Additional Quality Tools
 1. Brainstorming

 2. Nominal Group Techniques

PMP Prep Course

15
Project Quality Mangement

4/3/2011

Perform Quality Assurance
Quality assurance (QA) is the sum of the
planning and the implementations of the plan
that ensures the project meets the quality
demand
 Involved in continuous process improvement,
for improving the quality of all processes


Perform Quality Assurance
INPUTS
1. Project
Management Plan
2. Quality Metrics
3. Work Performance
Information
4. Quality Control
Measurements

PMP Prep Course

TOOLS & TECHNIQUES
1. Plan Quality &
Perform
Quality Control
Tools &
Techniques
2. Quality Audits
3. Process
Analysis

OUTPUTS
1. Organizational
Process Assets
Updates
2. Change Requests
3. Project
Management Plan
Updates
4. Project Document
Updates

16
Project Quality Mangement

4/3/2011

Perform Quality Assurance


Inputs
 1. Project Management Plan
 Quality Management Plan
 Process Improvement Plan

 2. Quality Metrics
 3. Work Performance Information
 4. Quality Control Measurements

Perform Quality Assurance


Tools and Techniques
 1. Plan Quality and Perform Quality Control
Tools & Techniques
 2. Quality Audits
 3. Process Analysis

PMP Prep Course

17
Project Quality Mangement

4/3/2011

Perform Quality Assurance


Outputs





1. Organizational Process Assets Updates
2. Change Requests
3. Project Management Plan Updates
4. Project Document Updates

Perform Quality Control





PMP Prep Course

Quality Control is to monitor and measure
project results to determine that the results
are as per quality standards
QC measures performance, scheduling and
cost variances
QC occurs throughout the life of project

18
Project Quality Mangement

4/3/2011

Perform Quality Control


Project team should do the following QC
activities
 Conduct statistical quality control
 Inspect the product to minimize errors
 Study special causes to determine anomalies to
quality
 Check the tolerance range to determine if the
results are within acceptable level of quality

Perform Quality Control


Project team should know the differences
between the following terms
Prevention
Keeping errors out of the
process
Attribute Sampling
The result either conforms or
does not conform

Variable Sampling
The result is rated on a continuous
scale that measures the degree
conformity

Tolerances

Control Limits

Specified range of accepted
results

PMP Prep Course

Inspection
Keeping errors out of the hands
of the customer

Thresholds, which can indicate
whether the process is out of
control

19
Project Quality Mangement

4/3/2011

Perform Quality Control
INPUTS
1. Project
Management Plan
2. Quality Metrics
3. Quality Checklists
4. Work Performance
Measurements
5. Approved change
Requests
6. Deliverables
7. Organizational
Process Assets

TOOLS & TECHNIQUES
1. Cause and Effect
Diagrams
2. Control Charts
3. Flowcharting
4. Histogram
5. Pareto Chart
6. Run Chart
7. Scatter Diagram
8. Statistical sampling
9. Inspection
10. Approved Change
Requests Review

OUTPUTS

1. Quality Control
Measurements
2. Validated changes
3. Validated
Deliverables
4. Organizational
Process Assets
Updates
5. Change Requests
6. Project Management
Plan Updates
7. Project Document
Updates

Perform Quality Control











PMP Prep Course

Inputs
1. Project Management Plan
2. Quality Metrics
3. Quality Checklists
4.Work Performance Measurements
5. Approved Change Requests
6. Deliverables
7. Organizational Process Assets

20
Project Quality Mangement

4/3/2011

Perform Quality Control








Tools and Techniques
1. Cause and Effect Diagrams
2. Control Chart
3. Flowcharting
4. Histogram
5. Pareto Chart

Perform Quality Control







PMP Prep Course

Tools and Techniques
6. Run Chart
7. Scatter Diagram
8. Statistical sampling
9. Inspection
10. Approved Change Requests Review

21
Project Quality Mangement

4/3/2011

Perform Quality Control


Outputs








1. Quality Control Measurements
2.Validated Changes
3.Validated Deliverables
4. Organizational Process Assets Updates
5. Change Requests
6. Project Management Plan Updates
7. Project Document Updates

Tools & Techniques


Quality Tools








PMP Prep Course

1. Cause and Effect Diagram
2. Control Charts
3. Flowcharting
4. Histogram
5. Pareto Chart
6. Run Chart
7. Scatter Diagram

22
Project Quality Mangement

4/3/2011

Cause and Effect Diagram
To visualize





clarify
link
identify and
classify possible causes of problems in processes,
products and services.

Also known as Fishbone diagrams or
Ishikawa diagrams
Examples
 Identifying sources of defect causes


Cause and Effect Diagram
Product

Process
Cause7

Cause1

Cause3

Cause9

Cause2
Cause8

Customer
Satisfaction
Cause4

Cause6

Cause5
Resources

PMP Prep Course

23
Project Quality Mangement

4/3/2011

Cause and Effect Diagram





Identify a problem (effect) with a list of
potential causes
Write the Effect at the rightmost side of the
paper
Identify Major Causes of the problem, which
become “Big Branches”
Cause Categories are Measurement,
Methods, Materials, Machines, People and
Environment

Cause and Effect Diagram






PMP Prep Course

Fill in the “Small branches” with sub-clauses till
the lowermost level
Review the diagram with the work process
Work on the Most important causes
Collect the data related to identified Root
Causes and study relationship
Continue for all Root Causes

24
Project Quality Mangement

4/3/2011






Also known as Frequency
Distribution Chart
A bar graph that groups the
data by predetermined
intervals to show the
frequency of the data set
Used to measure and analyze
the data and identify Defect
Classification, Delivery Times,
Survey Findings

Y-Axis

Histogram

X-Axis

Pareto Chart







PMP Prep Course

Is also known as 80 – 20 rule
Provides the ability to Categorize Items, usually by
content (type of defect, position, process, time, etc.)
or cause (materials, operating methods, manpower,
measurement, etc.) factors
Identify the causes or characteristics that
contribute most to a problem
Decide which basic causes of a problem to work
on first
Understand the effectiveness of the improvement
by doing pre- and post improvement charts

25
Project Quality Mangement

4/3/2011

Pareto Chart





Define the problem clearly
Collect sufficient Sample Size
Sort the data in descending order by
occurrence/frequency of cause/characteristics

Run Chart









PMP Prep Course

A graph of data in a chronological order, which
displays changes and trends in the central
tendency
Used to monitor and quantify process outputs
prior to control charts
Decide which output of a process to measure
Label the chart vertically and horizontally
Plot the individual measurements over time
Connect Data points
Monitor the data points for Trends

26
Project Quality Mangement

4/3/2011

No. of Defects

Run Chart

Average

Days

Scatter Diagram


It is used for problem solving and
understanding cause-and-effect relationships
 It shows if a relation exists between Two variables
 Also known as Correlation Diagrams

PMP Prep Course

27
Project Quality Mangement

4/3/2011

Scatter Diagram
Scatter Diagram
Car Age & Price

Price

3000
2000
1000

1

3
2
Age Years

4

5

Project Quality Management
To Sum Up….
1. We identified the project quality
management knowledge area‟s processes
2. We know how to plan quality for the project
3. We know how to implement quality
assurance
4. We know how to monitor and control
quality

PMP Prep Course

28
Project Quality Mangement

4/3/2011

Questions ?

PMP Prep Course

29

More Related Content

What's hot

Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpointDjamadaMuhamedKAGUSU
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality ManagementGiO Friginal
 
The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industryRaghavendra Rachamadugu
 
Total construction quality management by mobile technology mtech
Total construction quality management by mobile technology   mtechTotal construction quality management by mobile technology   mtech
Total construction quality management by mobile technology mtechStephen Au
 
Quality management templates
Quality management templatesQuality management templates
Quality management templatesselinasimpson371
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management BhuWan Khadka
 
00 safety_quality_construction
00  safety_quality_construction00  safety_quality_construction
00 safety_quality_constructionAdhitomo Wirawan
 
Project Quality Planning and KickOff
Project Quality Planning and KickOffProject Quality Planning and KickOff
Project Quality Planning and KickOffkaushikanirudh
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesSlideTeam
 
Ensuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesEnsuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesSlideTeam
 
Quality management @ ppt DOMS
Quality management @ ppt DOMSQuality management @ ppt DOMS
Quality management @ ppt DOMSBabasab Patil
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Jayson Narito
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...AELC
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA ProgramDan Stehling
 
How to take organizations to higher testing maturity suresh bose anagha mahaj...
How to take organizations to higher testing maturity suresh bose anagha mahaj...How to take organizations to higher testing maturity suresh bose anagha mahaj...
How to take organizations to higher testing maturity suresh bose anagha mahaj...Anagha Mahajan
 

What's hot (20)

Project Quality Management powerpoint
Project Quality Management powerpointProject Quality Management powerpoint
Project Quality Management powerpoint
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
The Implementation of QMS in construction industry
The Implementation of QMS in construction industryThe Implementation of QMS in construction industry
The Implementation of QMS in construction industry
 
Total construction quality management by mobile technology mtech
Total construction quality management by mobile technology   mtechTotal construction quality management by mobile technology   mtech
Total construction quality management by mobile technology mtech
 
Quality management forms
Quality management formsQuality management forms
Quality management forms
 
Quality management templates
Quality management templatesQuality management templates
Quality management templates
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
10. Project Quality Management
10. Project Quality Management 10. Project Quality Management
10. Project Quality Management
 
00 safety_quality_construction
00  safety_quality_construction00  safety_quality_construction
00 safety_quality_construction
 
Project Quality Planning and KickOff
Project Quality Planning and KickOffProject Quality Planning and KickOff
Project Quality Planning and KickOff
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Project Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation SlidesProject Quality Management Plan Checklist PowerPoint Presentation Slides
Project Quality Management Plan Checklist PowerPoint Presentation Slides
 
Quality Management
Quality ManagementQuality Management
Quality Management
 
Ensuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation SlidesEnsuring Project Quality Powerpoint Presentation Slides
Ensuring Project Quality Powerpoint Presentation Slides
 
Project quality management
Project quality managementProject quality management
Project quality management
 
Quality management @ ppt DOMS
Quality management @ ppt DOMSQuality management @ ppt DOMS
Quality management @ ppt DOMS
 
Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)Construction quality management plan (Construction Productivity Analysis)
Construction quality management plan (Construction Productivity Analysis)
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
 
EPC Construction CQA Program
EPC Construction CQA ProgramEPC Construction CQA Program
EPC Construction CQA Program
 
How to take organizations to higher testing maturity suresh bose anagha mahaj...
How to take organizations to higher testing maturity suresh bose anagha mahaj...How to take organizations to higher testing maturity suresh bose anagha mahaj...
How to take organizations to higher testing maturity suresh bose anagha mahaj...
 

Similar to Project managment 7

PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptAhtashamArshad4
 
quality_management_plan_4108_ppt_final.pptx
quality_management_plan_4108_ppt_final.pptxquality_management_plan_4108_ppt_final.pptx
quality_management_plan_4108_ppt_final.pptxHardikPatel611017
 
quality_management_plan_4108 ppt final.pptx
quality_management_plan_4108 ppt final.pptxquality_management_plan_4108 ppt final.pptx
quality_management_plan_4108 ppt final.pptxHardikPatel611017
 
Quality management slides
Quality management slidesQuality management slides
Quality management slidesSaba Afaq
 
PROJECT QUALITY KNOLEDGE AREA.ppt
PROJECT QUALITY KNOLEDGE    AREA.pptPROJECT QUALITY KNOLEDGE    AREA.ppt
PROJECT QUALITY KNOLEDGE AREA.pptRandolphRodrigues2
 
CMMi level 3 presentation
CMMi level 3 presentationCMMi level 3 presentation
CMMi level 3 presentationadinmani
 
Amod Prakash Resume
Amod Prakash ResumeAmod Prakash Resume
Amod Prakash ResumeAmod Prakash
 
Антон Мужайло, «Using the test process improvement models. Case study based o...
Антон Мужайло, «Using the test process improvement models. Case study based o...Антон Мужайло, «Using the test process improvement models. Case study based o...
Антон Мужайло, «Using the test process improvement models. Case study based o...Sigma Software
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality ManagementSerdar Temiz
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Nam Trung
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfHuyNguyen657394
 
Quality assurance
Quality assuranceQuality assurance
Quality assuranceSahil Shah
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagementDhamo daran
 
Running head QUALITY TRAINING MANUAL .docx
Running head QUALITY TRAINING MANUAL                             .docxRunning head QUALITY TRAINING MANUAL                             .docx
Running head QUALITY TRAINING MANUAL .docxtoltonkendal
 

Similar to Project managment 7 (20)

Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
5) PQM.pptx
5) PQM.pptx5) PQM.pptx
5) PQM.pptx
 
PMP_Project Quality Management
PMP_Project Quality ManagementPMP_Project Quality Management
PMP_Project Quality Management
 
PROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.pptPROJECT QUALITY MANAGEMENT for Project.ppt
PROJECT QUALITY MANAGEMENT for Project.ppt
 
quality_management_plan_4108_ppt_final.pptx
quality_management_plan_4108_ppt_final.pptxquality_management_plan_4108_ppt_final.pptx
quality_management_plan_4108_ppt_final.pptx
 
quality_management_plan_4108 ppt final.pptx
quality_management_plan_4108 ppt final.pptxquality_management_plan_4108 ppt final.pptx
quality_management_plan_4108 ppt final.pptx
 
Quality management slides
Quality management slidesQuality management slides
Quality management slides
 
PROJECT QUALITY KNOLEDGE AREA.ppt
PROJECT QUALITY KNOLEDGE    AREA.pptPROJECT QUALITY KNOLEDGE    AREA.ppt
PROJECT QUALITY KNOLEDGE AREA.ppt
 
CMMi level 3 presentation
CMMi level 3 presentationCMMi level 3 presentation
CMMi level 3 presentation
 
Amod Prakash Resume
Amod Prakash ResumeAmod Prakash Resume
Amod Prakash Resume
 
Антон Мужайло, «Using the test process improvement models. Case study based o...
Антон Мужайло, «Using the test process improvement models. Case study based o...Антон Мужайло, «Using the test process improvement models. Case study based o...
Антон Мужайло, «Using the test process improvement models. Case study based o...
 
Project Quality Management
 Project Quality Management Project Quality Management
Project Quality Management
 
Software Quality Assurance
Software Quality AssuranceSoftware Quality Assurance
Software Quality Assurance
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8Smsvn pmp training_slides_chapter_8
Smsvn pmp training_slides_chapter_8
 
Topic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdfTopic 8 - Project Quality Management.pdf
Topic 8 - Project Quality Management.pdf
 
Quality assurance
Quality assuranceQuality assurance
Quality assurance
 
08 projectqualitymanagement
08 projectqualitymanagement08 projectqualitymanagement
08 projectqualitymanagement
 
Running head QUALITY TRAINING MANUAL .docx
Running head QUALITY TRAINING MANUAL                             .docxRunning head QUALITY TRAINING MANUAL                             .docx
Running head QUALITY TRAINING MANUAL .docx
 
csc 510 Project
csc 510 Projectcsc 510 Project
csc 510 Project
 

More from Абдулазіз Мухаммед (9)

Project managment 10
Project managment  10Project managment  10
Project managment 10
 
Project managment 9
Project managment  9Project managment  9
Project managment 9
 
Project managment 8
Project managment  8Project managment  8
Project managment 8
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Project managment 6
Project managment 6Project managment 6
Project managment 6
 
Project managment 4
Project managment 4Project managment 4
Project managment 4
 
Project managment 3
Project managment 3Project managment 3
Project managment 3
 
Project managment 2
Project managment 2Project managment 2
Project managment 2
 
Project managment 1
Project managment 1Project managment 1
Project managment 1
 

Recently uploaded

Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 

Recently uploaded (20)

Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 

Project managment 7

  • 1. Project Quality Mangement 4/3/2011 Project Management Knowledge Areas Section – 3 Chapter – 8 Project Quality Management Session Objectives… 1. To identify the project quality management knowledge area‟s processes 2. How to plan quality for the project 3. How to implement quality assurance 4. How to monitor and control quality PMP Prep Course 1
  • 2. Project Quality Mangement 4/3/2011 Project Quality Management Exam Objectives… 1. What is Quality 2. Preparing for Quality 3. Planning for Quality 4. Creating the Quality Management Plan 5. Performing Quality Assurance 6. Implementing Quality Control Project Quality Management What makes quality to suffer?  Overworking the project team in order to complete the project.  ◦ May result in unacceptable work due to decline in team morale  A hurry to complete the project work by speeding through quality inspections ◦ May result in unacceptable deliverables PMP Prep Course 2
  • 3. Project Quality Mangement 4/3/2011 Project Quality Management Quality Vs Grade  Quality and Grade are not the same  Quality is the sum of the characteristics of a product that meet the specifications / expectations of the project  Grade is the category or rank given to entities having the same functional use but different characteristics  Quality management characteristics  Customer satisfaction  Prevention Act Plan  Management responsibility  Continuous improvement:- Plan Act PMP Prep Course Check Do – Do – Check – 3
  • 4. Project Quality Mangement 4/3/2011 Quality Gurus  Phillip B Crosby  Crosby devised the “Zero Defects” practice  That is, DO IT RIGHT THE FIRST TIME  He says, that costs will increase when quality planning isn‟t performed upfront, which means, rework, affecting productivity  Prevention is the KEY Quality Gurus  Joseph M Juran  Is known for his “FITNES FOR USE”  That is, stakeholders and customers‟ expectations are met or exceeded  Conformance to Specifications PMP Prep Course 4
  • 5. Project Quality Mangement 4/3/2011 Quality Gurus  W Edwards Deming  Suggested that as much as 85% of quality issues is management problem  Deming proposed that workers cannot figure out quality on their work and thus cannot perform at their best  Workers need to be shown what acceptable quality is  Deming is major contributor of Total Quality Management (TQM) Total Quality Management  Total Quality Management (TQM )  Says that the process is the problem, not people  TQM stipulates that quality must be managed in and that quality improvement should be a continuous way of doing business  Six Sigma  Is a quality management approach  Mostly used in manufacturing and services industries  Is a measurement based strategy that focuses on process improvement and variation reduction by applying Six Sigma methodologies PMP Prep Course 5
  • 6. Project Quality Mangement 4/3/2011 Six Sigma Six Sigma  It follows methodologies  DMADV  Define, Measure, Analyze, Design, and Verify  DMAIC Define, Measure, Analyze, Improve, and Control  Six Sigma aims to eliminate defects and stipulates that no more than 3.4 defects for million operations Project Quality Management  Kaizen technology: A quality philosophy of applying continuous small improvements to reduce costs and ensure consistency  Marginal analysis: The cost of the incremental improvements to a process or a product are compared against the increase in revenue made from the improvements PMP Prep Course 6
  • 7. Project Quality Mangement 4/3/2011 Project Quality Management The project team should adopt the quality policy of the organization to guide the project implementation  Project manager should document how the project will fulfill the quality policy in project management and deliverables  If quality policy is not adoptable to the project or the organization does not have a quality policy, the project team should create a quality policy for the project  Quality is planned, designed, and built in – not inspected  Plan Quality  The quality management plan addresses Quality control Quality assurance Quality improvement  PMP Prep Course The process identifies and documents the quality requirements & standards for project 7
  • 8. Project Quality Mangement 4/3/2011 Plan Quality INPUTS 1. Scope Baseline 2. Stakeholder Register 3. Cost Performance Baseline 4. Schedule Baseline 5. Risk Register 6. Enterprise Environmental Factors 7. Organizational Process Assets TOOLS & TECHNIQUES OUTPUTS 1. Cost-Benefit Analysis 2. Cost of Quality 3. Control Charts 4. Benchmarking 5. Design of Experiments 6. Statistical Sampling 7. Flowcharting 8. Proprietary Quality Management Methodologies 9. Additional Quality Planning Tools 1. Quality Management Plan 2. Quality Metrics 3. Quality Checklists 4. Process Improvement Plan 5. Project Document Updates Plan Quality  Inputs 1. Scope Baseline 2. Stakeholder Register 3. Cost Performance Baseline 4. Schedule Baseline 5. Risk Register 6. Enterprise Environmental Factors 7. Organizational Process Assets PMP Prep Course 8
  • 9. Project Quality Mangement 4/3/2011 Plan Quality  Tools and Techniques 1. Cost-Benefit analysis 2. Cost of quality (COQ) 3. Control Charts 4. Benchmarking 5. Design of experiments 6. Statistical Sampling 7. Flowcharting 8. Proprietary Quality Management Methodologies 9. Additional quality planning tools Plan Quality  Outputs 1. Quality Management Plan 2. Quality Metrics 3. Quality Checklists 4. Process Improvement Plan Process Boundaries Process Configuration Process Metrics 5. Project Document Updates PMP Prep Course 9
  • 10. Project Quality Mangement 4/3/2011 Tools & Techniques Benefit-Cost Analysis  Benefit:  Completing quality work increases productivity  Costs Completing quality work may cost little more  Gold plating Is process of adding extra features that may increase cost Cost of Quality  Cost of Quality The cost of quality is cost of all the activities within a project to ensure the quality  Cost of conformance to requirements:The cost of completing the project work to satisfy the project scope and expected quality  Cost of nonconformance The cost of completing the project without quality PMP Prep Course 10
  • 11. Project Quality Mangement 4/3/2011 Cost of Quality There are three types of Cost of Quality  1. Prevention Costs  The costs associated with satisfying customer requirements by producing a product without defects. Includes quality planning, training Cost of Quality  2. Appraisal Costs The costs expended to examine the product or process and make certain the requirements are being met. Includes inspections and testing  3. Failure Costs The costs when things don‟t work as expected. Two types or failure costs are 1. Internal Failure Costs and 2. External Failure Costs Ex. 1.Rework – 2. Liabilities, Warranty work, Lost business PMP Prep Course 11
  • 12. Project Quality Mangement 4/3/2011 Control Chart     Used to objectively define a process and variation Process containing only common causes of variation is considered stable, implying that the variation is predictable within the established control limits Processes containing special as well as common causes of variation are considered unstable. In such cases the special causes fall outside the established control limits Control charts can be plotted for tracking Production failures, defects by schedule/effort/cost and variances Control Chart No. of Defects Upper Control Limit Lower Control Limit Days Stable Process PMP Prep Course 12
  • 13. Project Quality Mangement 4/3/2011 Control Chart No. of Defects Upper Control Limit Lower Control Limit Days Unstable Process Benchmarking Is comparison among two projects, processes or performance of organizations The goal is to evaluate the differences between two projects and to make corrective actions to the current project Is also used as a measurement against industry standards, competitors‟ level of performance PMP Prep Course 13
  • 14. Project Quality Mangement 4/3/2011 Design of Experiments  The approach relies on statistical what-if scenarios to determine what variables within a project will result in the best outcome. Most often used on the product of project rather than the project Is also used as a method to identify which variables within a project or product , are causing failures Flowcharting   PMP Prep Course The flowchart shows the logical steps required to accomplish an objective. The flowchart steps through a logical sequence and checks for “YES” or „NO” branching 14
  • 15. Project Quality Mangement 4/3/2011 Flowcharting Measure attributes of Deliverable Deliverable Ready for Quality check Conformance To Requirements YES Deliverable is Ready for Dispatch NO Return to owner Quality Check Additional Quality Tools  1. Brainstorming  2. Nominal Group Techniques PMP Prep Course 15
  • 16. Project Quality Mangement 4/3/2011 Perform Quality Assurance Quality assurance (QA) is the sum of the planning and the implementations of the plan that ensures the project meets the quality demand  Involved in continuous process improvement, for improving the quality of all processes  Perform Quality Assurance INPUTS 1. Project Management Plan 2. Quality Metrics 3. Work Performance Information 4. Quality Control Measurements PMP Prep Course TOOLS & TECHNIQUES 1. Plan Quality & Perform Quality Control Tools & Techniques 2. Quality Audits 3. Process Analysis OUTPUTS 1. Organizational Process Assets Updates 2. Change Requests 3. Project Management Plan Updates 4. Project Document Updates 16
  • 17. Project Quality Mangement 4/3/2011 Perform Quality Assurance  Inputs  1. Project Management Plan  Quality Management Plan  Process Improvement Plan  2. Quality Metrics  3. Work Performance Information  4. Quality Control Measurements Perform Quality Assurance  Tools and Techniques  1. Plan Quality and Perform Quality Control Tools & Techniques  2. Quality Audits  3. Process Analysis PMP Prep Course 17
  • 18. Project Quality Mangement 4/3/2011 Perform Quality Assurance  Outputs     1. Organizational Process Assets Updates 2. Change Requests 3. Project Management Plan Updates 4. Project Document Updates Perform Quality Control    PMP Prep Course Quality Control is to monitor and measure project results to determine that the results are as per quality standards QC measures performance, scheduling and cost variances QC occurs throughout the life of project 18
  • 19. Project Quality Mangement 4/3/2011 Perform Quality Control  Project team should do the following QC activities  Conduct statistical quality control  Inspect the product to minimize errors  Study special causes to determine anomalies to quality  Check the tolerance range to determine if the results are within acceptable level of quality Perform Quality Control  Project team should know the differences between the following terms Prevention Keeping errors out of the process Attribute Sampling The result either conforms or does not conform Variable Sampling The result is rated on a continuous scale that measures the degree conformity Tolerances Control Limits Specified range of accepted results PMP Prep Course Inspection Keeping errors out of the hands of the customer Thresholds, which can indicate whether the process is out of control 19
  • 20. Project Quality Mangement 4/3/2011 Perform Quality Control INPUTS 1. Project Management Plan 2. Quality Metrics 3. Quality Checklists 4. Work Performance Measurements 5. Approved change Requests 6. Deliverables 7. Organizational Process Assets TOOLS & TECHNIQUES 1. Cause and Effect Diagrams 2. Control Charts 3. Flowcharting 4. Histogram 5. Pareto Chart 6. Run Chart 7. Scatter Diagram 8. Statistical sampling 9. Inspection 10. Approved Change Requests Review OUTPUTS 1. Quality Control Measurements 2. Validated changes 3. Validated Deliverables 4. Organizational Process Assets Updates 5. Change Requests 6. Project Management Plan Updates 7. Project Document Updates Perform Quality Control         PMP Prep Course Inputs 1. Project Management Plan 2. Quality Metrics 3. Quality Checklists 4.Work Performance Measurements 5. Approved Change Requests 6. Deliverables 7. Organizational Process Assets 20
  • 21. Project Quality Mangement 4/3/2011 Perform Quality Control       Tools and Techniques 1. Cause and Effect Diagrams 2. Control Chart 3. Flowcharting 4. Histogram 5. Pareto Chart Perform Quality Control       PMP Prep Course Tools and Techniques 6. Run Chart 7. Scatter Diagram 8. Statistical sampling 9. Inspection 10. Approved Change Requests Review 21
  • 22. Project Quality Mangement 4/3/2011 Perform Quality Control  Outputs        1. Quality Control Measurements 2.Validated Changes 3.Validated Deliverables 4. Organizational Process Assets Updates 5. Change Requests 6. Project Management Plan Updates 7. Project Document Updates Tools & Techniques  Quality Tools        PMP Prep Course 1. Cause and Effect Diagram 2. Control Charts 3. Flowcharting 4. Histogram 5. Pareto Chart 6. Run Chart 7. Scatter Diagram 22
  • 23. Project Quality Mangement 4/3/2011 Cause and Effect Diagram To visualize     clarify link identify and classify possible causes of problems in processes, products and services. Also known as Fishbone diagrams or Ishikawa diagrams Examples  Identifying sources of defect causes  Cause and Effect Diagram Product Process Cause7 Cause1 Cause3 Cause9 Cause2 Cause8 Customer Satisfaction Cause4 Cause6 Cause5 Resources PMP Prep Course 23
  • 24. Project Quality Mangement 4/3/2011 Cause and Effect Diagram     Identify a problem (effect) with a list of potential causes Write the Effect at the rightmost side of the paper Identify Major Causes of the problem, which become “Big Branches” Cause Categories are Measurement, Methods, Materials, Machines, People and Environment Cause and Effect Diagram      PMP Prep Course Fill in the “Small branches” with sub-clauses till the lowermost level Review the diagram with the work process Work on the Most important causes Collect the data related to identified Root Causes and study relationship Continue for all Root Causes 24
  • 25. Project Quality Mangement 4/3/2011    Also known as Frequency Distribution Chart A bar graph that groups the data by predetermined intervals to show the frequency of the data set Used to measure and analyze the data and identify Defect Classification, Delivery Times, Survey Findings Y-Axis Histogram X-Axis Pareto Chart      PMP Prep Course Is also known as 80 – 20 rule Provides the ability to Categorize Items, usually by content (type of defect, position, process, time, etc.) or cause (materials, operating methods, manpower, measurement, etc.) factors Identify the causes or characteristics that contribute most to a problem Decide which basic causes of a problem to work on first Understand the effectiveness of the improvement by doing pre- and post improvement charts 25
  • 26. Project Quality Mangement 4/3/2011 Pareto Chart    Define the problem clearly Collect sufficient Sample Size Sort the data in descending order by occurrence/frequency of cause/characteristics Run Chart        PMP Prep Course A graph of data in a chronological order, which displays changes and trends in the central tendency Used to monitor and quantify process outputs prior to control charts Decide which output of a process to measure Label the chart vertically and horizontally Plot the individual measurements over time Connect Data points Monitor the data points for Trends 26
  • 27. Project Quality Mangement 4/3/2011 No. of Defects Run Chart Average Days Scatter Diagram  It is used for problem solving and understanding cause-and-effect relationships  It shows if a relation exists between Two variables  Also known as Correlation Diagrams PMP Prep Course 27
  • 28. Project Quality Mangement 4/3/2011 Scatter Diagram Scatter Diagram Car Age & Price Price 3000 2000 1000 1 3 2 Age Years 4 5 Project Quality Management To Sum Up…. 1. We identified the project quality management knowledge area‟s processes 2. We know how to plan quality for the project 3. We know how to implement quality assurance 4. We know how to monitor and control quality PMP Prep Course 28