City of Novi
               Road Asset Management & Funding
                           Analysis




         March 12, 2012


Page 1 of 19              Road Asset Management and Funding Analysis Presentation   March 2012
Pavement Asset Management,
     RoadSoft-GIS, and the PASER System
         In 2002, Public Act 499 was signed into law defining
         asset management as “an ongoing process of
         maintaining, upgrading, and operating physical assets
         cost-effectively, based on a continuous physical
         inventory and condition assessment”
         RoadSoft software was introduced in 1993, and since
         that time, yearly funding from MDOT has enabled
         LTAP at Michigan Tech to continue to refine
         development and provide technical support.
         The Pavement Surface Evaluation and Rating (PASER)
         methodology is used to collect road surface condition
         data. PASER is a visual assessment system that rates
         the road surface on a scale of 1-10. Where 10 is new
         construction and 1 is totally failed.




Page 2 of 19             Road Asset Management and Funding Analysis Presentation   March 2012
Maintaining An Asset
               The PASER rating, and subsequent classification to ‘Good’, ‘Fair’, & ‘Poor’,
               corresponds to an associated Remaining Service Life (RSL).
               It is much more cost effective to perform preventative maintenance while
               the condition is still good.

                                                      Pavement Deterioration Curve


                                  10
                                   9
                                   8
                   PASER Rating




                                   7
                                   6
                                   5                                                                       Critical Distress
                                   4                                                                       Point - PASER 4
                                   3       Remaining
                                   2       Service Life
                                   1
                                       0    5          10             15            20             25     30       35
                                                             Years Since Construction



Page 3 of 19                                    Road Asset Management and Funding Analysis Presentation                        March 2012
Pavement Life Cycle – Mix of Fixes
         $2.70/syd/year over life of pavement – 36 years
         Average condition rating = 7

                                             Life Cycle Curve - Mix of Fixes

                              10
                               9
                               8
               PASER Rating




                               7
                               6
                               5
                               4
                               3
                               2
                               1
                                   0   5          10            15             20            25      30   35
                                                                       Year


Page 4 of 19                               Road Asset Management and Funding Analysis Presentation             March 2012
Pavement Life Cycle – No Maintenance
         $3.30/syd/year over life of pavement – 36 years
         Average condition rating = 6
                                           Life Cycle Curve - No Maintenance

                              10
                              9
                              8
               PASER Rating




                              7
                              6
                              5
                              4
                              3
                              2
                              1
                                   0   5           10            15             20             25     30   35
                                                                        Year



Page 5 of 19                                Road Asset Management and Funding Analysis Presentation             March 2012
Road Network Condition Evaluation
 Process Steps
         Field Survey – Collect Data
         Database Creation / Data Quality Assurance
         Maintenance Alternative Selection and Cost
         Assignment
         Preliminary Network Analysis
         Identify Funding Level
         Refined Network Analysis – Selecting
         Segments/Neighborhoods
         Track Maintenance and Reconstruction
         Projects
         Update Database / Adjust Analysis
Page 6 of 19          Road Asset Management and Funding Analysis Presentation   March 2012
City Road Network Status
         Approximately 172 miles of City-owned roads
               100 Miles Asphalt
               70 Miles Concrete
               2 Miles Gravel
         Condition
               19 Miles Poor (PASER 1-3)
                 Reconstruction Candidates
               98 Miles Fair-Good (PASER 4-5)
                 Major Rehabilitation Candidates
               55 Miles Good-Very Good (Paser 6-10)
                 Light Preventative Maintenance Candidates




Page 7 of 19                 Road Asset Management and Funding Analysis Presentation   March 2012
Strategy Evaluation and Optimization
         Roadsoft uses the following parameters to select
         the appropriate maintenance and capital
         procedures
               Specific Preventative Maintenance, Rehabilitation, and
               Reconstruction alternatives
               Costs for these alternatives
               Expected deterioration curves (rates)
               Budget
               Duration (5-year plan, 10-year plan, etc)
         Roadsoft does not
               Pick specific segments
               Consider other capital projects (utility, etc)


Page 8 of 19                  Road Asset Management and Funding Analysis Presentation   March 2012
Roadsoft Map Interface




Page 9 of 19   Road Asset Management and Funding Analysis Presentation   March 2012
Roadsoft Optimization Engine




Page 10 of 19   Road Asset Management and Funding Analysis Presentation   March 2012
Results

         Analysis was performed at several funding levels
         Funding levels were evaluated for programs with
         consistent budgets, as well as ‘front loaded’
         The following graphs summarize the findings




Page 11 of 19          Road Asset Management and Funding Analysis Presentation   March 2012
Side-by-side Projected Condition
 Comparison

                                                        Projected Condition Distribution 2022
                     100%
                     90%
                                  32%               26%
                     80%
                     70%                                                     56%
      % of Network




                                                                                                      69%
                     60%                            23%                                                     79%   Good
                     50%                                                                                          Fair
                     40%          57%                                                                             Poor
                                                                             16%
                     30%
                                                    50%                                               12%
                     20%
                                                                             28%                            12%
                     10%                                                                              19%
                                  11%                                                                       9%
                      0%
                            Current Condition   $5M - Recon-          $3.2M - Current                 $4M   $5M
                                                struction Only         Funding Level
                                                                 Funding Level / Year




Page 12 of 19                                     Road Asset Management and Funding Analysis Presentation         March 2012
Side-by-side Projected PASER Comparison
                    8.5


                     8


                                                                                                      $5M/Yr - Mix of Fixes
                    7.5


                                                                                                      $4M/Yr - Mix of Fixes
                     7
            PASER




                    6.5
                                                                                                      $3.2M/Yr - (Current Funding)

                     6

                                                                                                      $5M/Yr - RC Only
                    5.5


                     5
                     2011   2013         2015                2017                2019          2021         2023

                                                           Years

          Figure 1: Projected Paser Rating At Various Funding Levels




Page 13 of 19                        Road Asset Management and Funding Analysis Presentation                                  March 2012
Side-by-side Projected RSL Comparison
                                        8



                                        7
                                                                                                                       $5M/Yr - Mix of Fixes
                Years Until PASER = 4




                                        6



                                        5
                                                                                                                       $4M/Yr - Mix of Fixes


                                        4



                                        3

                                                                                                                       $3.2M/Yr - (Current Funding)
                                        2                                                                              $5M/Yr - RC Only


                                        1
                                        2011   2013      2015                2017                 2019          2021         2023

                                                                            Years

          Figure 2: Projected Average years until PASER = 4




Page 14 of 19                                         Road Asset Management and Funding Analysis Presentation                                  March 2012
Centerline Miles Receiving Treatment

                                         Total Miles
                                       Reconstructed
                                        (RC), 20, 5%
                                Total Miles
                             Rehabilitated (RH),
                                 50, 13%




                                                                             Total Miles
                                                                             Preventative
                                                                          Maintenance (PM),
                                                                              330, 82%
      Figure 3: $5 Million / Year - 10 Year Program: Centerline Miles Receiving Treatment




Page 15 of 19                         Road Asset Management and Funding Analysis Presentation   March 2012
Funding Allocation

                                                                         Preventative
                                                                      Maintenance (PM),
                                                                       $5,000,000, 10%

                          Reconstruction
                        (RC), $20,000,000,
                               40%




                                                                                 Rehabilitation (RH),
                                                                                 $25,000,000, 50%




      Figure 4: $5 Million / Year - 10 Year Program: Total $ Spent Over 10 Year Program




Page 16 of 19                        Road Asset Management and Funding Analysis Presentation            March 2012
Conclusions
        Current Funding Level - $3,200,000 is not sufficient to
        maintain the average PASER condition over ten years.
        Funding the road program at $4,000,000 per year improves
        the average condition of the system, however more streets
        would be in poor condition
        An investment of $5,000,000 per year
                Provides ample funding to maintain roads currently in
                good/fair condition (protect previous investments)
                Provides ample funding for road program to incorporate a
                reconstruction component
                Roads in ‘Poor’ category are slightly reduced over 10 year
                period
                Provides improved overall average PASER rating of system
                (From 6.5 to 7.5) after 10 years




Page 17 of 19                   Road Asset Management and Funding Analysis Presentation   March 2012
Road Network Condition Evaluation
 Process Steps
        Field Survey – Collect Data
        Database Creation / Data Quality Assurance
        Maintenance Alternative Selection and Cost
        Assignment
        Preliminary Network Analysis
        Identify Funding Level
        Refined Network Analysis – Selecting
        Segments/Neighborhoods
        Track Maintenance and Reconstruction
        Projects
        Update Database / Adjust Analysis
Page 18 of 19        Road Asset Management and Funding Analysis Presentation   March 2012
City of Novi
                Road Asset Management & Funding
                            Analysis



                    Questions / Discussion




Page 19 of 19           Road Asset Management and Funding Analysis Presentation   March 2012

Weitere ähnliche Inhalte

Ähnlich wie Road Asset Management Funding Analysis

Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
BCV
 
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
BCV
 
Credit rating assignment
Credit rating assignmentCredit rating assignment
Credit rating assignment
Sheetal Yadav
 
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
BCV
 
Embraer Conference Call 3Q11 Results
Embraer Conference Call 3Q11 ResultsEmbraer Conference Call 3Q11 Results
Embraer Conference Call 3Q11 Results
Embraer RI
 
Pavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellonPavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellon
mecocca5
 

Ähnlich wie Road Asset Management Funding Analysis (20)

Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
Financial Analysis - CSR Corp ltd. provides a wide range of rolling stock p…
 
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
Financial Analysis - Zhejiang Expressway Co., ltd., through its subsidiari…
 
Reichert rpo2012
Reichert rpo2012Reichert rpo2012
Reichert rpo2012
 
Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...Financial Analysis - China Communications Construction Company Ltd. is a tran...
Financial Analysis - China Communications Construction Company Ltd. is a tran...
 
Richard THOMAS"Analysis of decision making for sustainable land management"
Richard THOMAS"Analysis of decision making for sustainable land management"Richard THOMAS"Analysis of decision making for sustainable land management"
Richard THOMAS"Analysis of decision making for sustainable land management"
 
Campus Crest Communities Investor Presentation
Campus Crest Communities Investor PresentationCampus Crest Communities Investor Presentation
Campus Crest Communities Investor Presentation
 
Presentation 3Q12
Presentation 3Q12Presentation 3Q12
Presentation 3Q12
 
Credit rating assignment
Credit rating assignmentCredit rating assignment
Credit rating assignment
 
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
Investigation and Improvement of Road Pavement Section for Rankuva Crossing t...
 
Presentation 2Q12
Presentation 2Q12Presentation 2Q12
Presentation 2Q12
 
Presentation 1Q12
Presentation 1Q12Presentation 1Q12
Presentation 1Q12
 
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
Financial Analysis - Shanghai Construction Co., ltd. undertakes a variety …
 
Embraer Conference Call 3Q11 Results
Embraer Conference Call 3Q11 ResultsEmbraer Conference Call 3Q11 Results
Embraer Conference Call 3Q11 Results
 
Fundamental Analysis & Financial Analyst Recommandations - Google Inc - US382...
Fundamental Analysis & Financial Analyst Recommandations - Google Inc - US382...Fundamental Analysis & Financial Analyst Recommandations - Google Inc - US382...
Fundamental Analysis & Financial Analyst Recommandations - Google Inc - US382...
 
Financial Analysis - LinkedIn Corporation operates a social networking websit...
Financial Analysis - LinkedIn Corporation operates a social networking websit...Financial Analysis - LinkedIn Corporation operates a social networking websit...
Financial Analysis - LinkedIn Corporation operates a social networking websit...
 
Pavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellonPavement preservation john curley and dane mellon
Pavement preservation john curley and dane mellon
 
Financial Analysis - PetroChina Company Limited explores, develops, and produ...
Financial Analysis - PetroChina Company Limited explores, develops, and produ...Financial Analysis - PetroChina Company Limited explores, develops, and produ...
Financial Analysis - PetroChina Company Limited explores, develops, and produ...
 
Apimec – 3 q07 results
Apimec – 3 q07 resultsApimec – 3 q07 results
Apimec – 3 q07 results
 
Korea Supplement
Korea SupplementKorea Supplement
Korea Supplement
 
Namma Railu - The Proposal for Commuter Rail Service in Bangalore
Namma Railu - The Proposal for Commuter Rail Service in BangaloreNamma Railu - The Proposal for Commuter Rail Service in Bangalore
Namma Railu - The Proposal for Commuter Rail Service in Bangalore
 

Kürzlich hochgeladen

Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
WSO2
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 

Kürzlich hochgeladen (20)

"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ..."I see eyes in my soup": How Delivery Hero implemented the safety system for ...
"I see eyes in my soup": How Delivery Hero implemented the safety system for ...
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
A Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source MilvusA Beginners Guide to Building a RAG App Using Open Source Milvus
A Beginners Guide to Building a RAG App Using Open Source Milvus
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Automating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps ScriptAutomating Google Workspace (GWS) & more with Apps Script
Automating Google Workspace (GWS) & more with Apps Script
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 

Road Asset Management Funding Analysis

  • 1. City of Novi Road Asset Management & Funding Analysis March 12, 2012 Page 1 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 2. Pavement Asset Management, RoadSoft-GIS, and the PASER System In 2002, Public Act 499 was signed into law defining asset management as “an ongoing process of maintaining, upgrading, and operating physical assets cost-effectively, based on a continuous physical inventory and condition assessment” RoadSoft software was introduced in 1993, and since that time, yearly funding from MDOT has enabled LTAP at Michigan Tech to continue to refine development and provide technical support. The Pavement Surface Evaluation and Rating (PASER) methodology is used to collect road surface condition data. PASER is a visual assessment system that rates the road surface on a scale of 1-10. Where 10 is new construction and 1 is totally failed. Page 2 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 3. Maintaining An Asset The PASER rating, and subsequent classification to ‘Good’, ‘Fair’, & ‘Poor’, corresponds to an associated Remaining Service Life (RSL). It is much more cost effective to perform preventative maintenance while the condition is still good. Pavement Deterioration Curve 10 9 8 PASER Rating 7 6 5 Critical Distress 4 Point - PASER 4 3 Remaining 2 Service Life 1 0 5 10 15 20 25 30 35 Years Since Construction Page 3 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 4. Pavement Life Cycle – Mix of Fixes $2.70/syd/year over life of pavement – 36 years Average condition rating = 7 Life Cycle Curve - Mix of Fixes 10 9 8 PASER Rating 7 6 5 4 3 2 1 0 5 10 15 20 25 30 35 Year Page 4 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 5. Pavement Life Cycle – No Maintenance $3.30/syd/year over life of pavement – 36 years Average condition rating = 6 Life Cycle Curve - No Maintenance 10 9 8 PASER Rating 7 6 5 4 3 2 1 0 5 10 15 20 25 30 35 Year Page 5 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 6. Road Network Condition Evaluation Process Steps Field Survey – Collect Data Database Creation / Data Quality Assurance Maintenance Alternative Selection and Cost Assignment Preliminary Network Analysis Identify Funding Level Refined Network Analysis – Selecting Segments/Neighborhoods Track Maintenance and Reconstruction Projects Update Database / Adjust Analysis Page 6 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 7. City Road Network Status Approximately 172 miles of City-owned roads 100 Miles Asphalt 70 Miles Concrete 2 Miles Gravel Condition 19 Miles Poor (PASER 1-3) Reconstruction Candidates 98 Miles Fair-Good (PASER 4-5) Major Rehabilitation Candidates 55 Miles Good-Very Good (Paser 6-10) Light Preventative Maintenance Candidates Page 7 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 8. Strategy Evaluation and Optimization Roadsoft uses the following parameters to select the appropriate maintenance and capital procedures Specific Preventative Maintenance, Rehabilitation, and Reconstruction alternatives Costs for these alternatives Expected deterioration curves (rates) Budget Duration (5-year plan, 10-year plan, etc) Roadsoft does not Pick specific segments Consider other capital projects (utility, etc) Page 8 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 9. Roadsoft Map Interface Page 9 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 10. Roadsoft Optimization Engine Page 10 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 11. Results Analysis was performed at several funding levels Funding levels were evaluated for programs with consistent budgets, as well as ‘front loaded’ The following graphs summarize the findings Page 11 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 12. Side-by-side Projected Condition Comparison Projected Condition Distribution 2022 100% 90% 32% 26% 80% 70% 56% % of Network 69% 60% 23% 79% Good 50% Fair 40% 57% Poor 16% 30% 50% 12% 20% 28% 12% 10% 19% 11% 9% 0% Current Condition $5M - Recon- $3.2M - Current $4M $5M struction Only Funding Level Funding Level / Year Page 12 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 13. Side-by-side Projected PASER Comparison 8.5 8 $5M/Yr - Mix of Fixes 7.5 $4M/Yr - Mix of Fixes 7 PASER 6.5 $3.2M/Yr - (Current Funding) 6 $5M/Yr - RC Only 5.5 5 2011 2013 2015 2017 2019 2021 2023 Years Figure 1: Projected Paser Rating At Various Funding Levels Page 13 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 14. Side-by-side Projected RSL Comparison 8 7 $5M/Yr - Mix of Fixes Years Until PASER = 4 6 5 $4M/Yr - Mix of Fixes 4 3 $3.2M/Yr - (Current Funding) 2 $5M/Yr - RC Only 1 2011 2013 2015 2017 2019 2021 2023 Years Figure 2: Projected Average years until PASER = 4 Page 14 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 15. Centerline Miles Receiving Treatment Total Miles Reconstructed (RC), 20, 5% Total Miles Rehabilitated (RH), 50, 13% Total Miles Preventative Maintenance (PM), 330, 82% Figure 3: $5 Million / Year - 10 Year Program: Centerline Miles Receiving Treatment Page 15 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 16. Funding Allocation Preventative Maintenance (PM), $5,000,000, 10% Reconstruction (RC), $20,000,000, 40% Rehabilitation (RH), $25,000,000, 50% Figure 4: $5 Million / Year - 10 Year Program: Total $ Spent Over 10 Year Program Page 16 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 17. Conclusions Current Funding Level - $3,200,000 is not sufficient to maintain the average PASER condition over ten years. Funding the road program at $4,000,000 per year improves the average condition of the system, however more streets would be in poor condition An investment of $5,000,000 per year Provides ample funding to maintain roads currently in good/fair condition (protect previous investments) Provides ample funding for road program to incorporate a reconstruction component Roads in ‘Poor’ category are slightly reduced over 10 year period Provides improved overall average PASER rating of system (From 6.5 to 7.5) after 10 years Page 17 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 18. Road Network Condition Evaluation Process Steps Field Survey – Collect Data Database Creation / Data Quality Assurance Maintenance Alternative Selection and Cost Assignment Preliminary Network Analysis Identify Funding Level Refined Network Analysis – Selecting Segments/Neighborhoods Track Maintenance and Reconstruction Projects Update Database / Adjust Analysis Page 18 of 19 Road Asset Management and Funding Analysis Presentation March 2012
  • 19. City of Novi Road Asset Management & Funding Analysis Questions / Discussion Page 19 of 19 Road Asset Management and Funding Analysis Presentation March 2012