Cost of Delay, Rescheduling and
Cancellation In Airlines




Introduction

Usually Airlines are suffering from flights delay issues, but
most of them control these problems and their causes, so the
issue of flight delay may create a bad impression on the airline
image and its brand name in the market, and consequently it is
directly related to the concerned airline operation divisions and
departments, from maintenance, flight operation, commercial
and customer service, as they are interacted and integrated
divisions that serve for one mission, so every division has its
own rules and impacts on dispatch the flight on time, and any
negligence may reflects on airline final performance, and cause         Mohammed S. Awad
the delay of the flight. In aviation industry the cost of delay is       Research Scholar

considerably high due the high gained revenue of the flights and high direct fixed
operating cost for a certain type of aircraft hence we measure the activities of an
airline by its performance which usually addressed by the performance report of
Operation Control Committee OCC. Where the maintenance and material divisions
are the main airline departments that support the operation, as they are responsible for
aircraft technical readiness and fulfill the provision of spare parts of the aircraft, and
tracking/ monitoring the technical operating performance by papering reliability
report, which is similar as performance report, but its results are technical oriented, i.e
defining technical problems and failure diagnostic before its happen and cause a delay
or cancelation, which play a major rule in preventive maintenance program for the
aircraft. Finally by referring to Boeing Company reports, the engineering and
maintenance issues and problems for aircraft are represents 30-40% of total delay
cost for the flight in airline industry.


1
OCC Operation Control Committee:

The weekly report of this committee is one
of the main sources of airline activity
evaluation and it is an effective tool to
explore and define deviations so a proper
action may take on time and most of
operating and serving departments represents
in the committee, so this report rise the
initial signals to predicate defect or trouble a
certain failure in the airline activity for one
week period.

Delay Cost:
It is too complicated to evaluate and
calculate the delay cost in the airline
industry and its impacts on the image and the
brand of the airline. So we can refer to
Boeing terms and definitions for delay cost
that addressed in AGIFORS - Denver which are

    1-   Passenger direct cost
    2-   Direct Operating Cost
    3-   Cost of unavailability of scheduling Aircraft
    4-   Cost of losing the image and the loyalty for the airline.

In our case we will use only two factors in the analysis only:
    1- Passenger direct cost
    2- Direct Operating Cost

the calculation of delay or cancellation cost
will as the following:

Direct Operating Cost + expected income
revenue of the delay or cancelled flight.

And according to the study of American
Airlines – domestic routes, the results are :

Delay from :
0 – 15 minute.......... No Calculation of Cost
16 - 60 minute….......0.25 % ticket/min/pax
1 – 2 Hours ……0.5 % ticket /min/pax Approximately 1 out 8 passengers will
probably not buy their next ticket on this airline.
2 – 5 Hours …….... All passengers will probably not buy tickets on this airline again
for at least a year. And in this stage the growth of delay cost increase exponentially
until reach to 5 hours delay period ( out of business).




2
While the next figure explain the relationship between these costs and its average
values, indicating the direct cost of passenger may happen after 20 min of delay time,
and its impact on the passenger loyalty, image and the brand value of the airline.


Impacts of Engineering and
Maintenance:

Referring to the Boeing Study, the
share impact of maintenance and
engineering causes may reach 30-40
of total delay causes. And the
technical causes are the main
reasons for cancellation of the           Figure ( 2 ) Delay Cost Elements - American Airlines Study.
flights and as its shows in the
previous figures, the maximum delay period for maintenance cause is 45-120 if there
is no cancellation. And the consequential effects of late aircraft arrival play a major
rule in rescheduling the flights again.


Delay Cost - Yemenia Case Study:

The period of 02/01/2010 to
12/03/2010 characterize by repeated
many delays in flights –Yemenia.
Among of that , the technical delays
and engine failures of B737-800
fleet which create a total mess in the
flight scheduling program. So the
delay cases can be address in two
directions
First : counting the repeated delays
issues
                                                       Figure ( 1 ) Measuring the time period costs
Second : the delay time                                         American Airlines Study.

So delays can be caused by one of the following reasons:

    1- Delay of the flight of the same aircraft type.
    2- Delay of the flight may cause the need to change the type of the aircraft from
       bigger to smaller capacity which lead to extra cost of spill passengers.
    3- Delay of the flight may cause the need to change the type of the aircraft from
       smaller to bigger capacity which lead to extra cost of losing the opportunity of
       un utilize seats for sale in last minutes.
    4- Aircraft Grounded cost, by sending another aircraft for taking the passengers
       and supported spare parts.
    5- Some time suddenly two aircrafts ground in the same time, and rise a hard
       time for planners and consequently may lead to cancel the flight.
    6- Un readiness of the aircraft for unexpected time.
    7- Longer maintenance programs may lead to delay the flights.



3
Figure ( 3 ). Delay Factors of Yemen Airways
Analysis:

In spite of defining Boeing Company the main factors that may cause the delays,
pointing out the maintenance /engineering and bad weather but yemenia analysis
results indicates another factors that impact high influence of those mentioned in
Boeing Study. However technical and engine failures remains the main factor in the
period of 02/01/2010 to 12/03/2010

    1-   Transit Passengers                        2-   Technical Problem
    3-   Airport Security                          4-   ATC
    5-   Late Arrival of Aircraft                  6-   Bad Weather
    7-   Maintenance Problems                      8-   Other factors

As indicated in graph, the other factors take the large share in the delay reasons,
yemenia should review all the delay items category so that the other reasons well
defined in the analysis and re casted in the right way. Also similar category should be
merge to be one category as maintenance and technical.
  This lead us to the result of the analysis, so
Number of Delays
with less than 20 min =121 delays
with cumulative time = 1355 min

Number of Delays
with greater than 20 min =87 delays
with cumulative time = 4185 min

but for technical delays, it take larger time to fix and rectify in spite of hidden
function issues




4
Summary:

    1- The analysis show the un
       availability of support fleet ,
       as the scheduling designed
       with one supported aircraft.
       But in some cases of two
       aircraft grounded in the same
       time led to a total mess in
       scheduling that need to
       rescheduling and delay the
       other flights.
    2- The technical delay have the
       majority causes of delays, and
       when its happen , its take a long time.
    3- In spite of the impact of transit passengers on delay, the maximum allowable
       time period for transit passengers is 45-60 min, but the delay period may reach
       to 5 hours or more and effects on the airline image in the market.
    4- Advanced and prior corporation between commercial and technical
       departments so that they adapted and implemented a the right scheduling
       without interruption based on the sound of the market.
    5- Brand name of the airline in the market may get lose, if the airline repeat these
       delays, and changing the capacities of aircrafts in the last minutes.




                       Figure ( 4 ) Frequency Distribution of Delay Periods

                                 




5

More Related Content

What's hot

Aircraft Maintenance practices introduction
Aircraft Maintenance practices introduction Aircraft Maintenance practices introduction
Aircraft Maintenance practices introduction Gaurav Garv
 
Deferred Maintenance Article
Deferred Maintenance ArticleDeferred Maintenance Article
Deferred Maintenance ArticleDouglas Evans
 
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce Magazine
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce MagazineLufthansa Systems Turnaround Management Solution in Aircraft Commerce Magazine
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce MagazineMichael Muzik
 
Aircraft Maintenance Records and Airworthiness Directives for General Aviation
Aircraft Maintenance Records and Airworthiness Directives for General AviationAircraft Maintenance Records and Airworthiness Directives for General Aviation
Aircraft Maintenance Records and Airworthiness Directives for General AviationFAA Safety Team Central Florida
 
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...iosrjce
 
Airport planning
Airport planning Airport planning
Airport planning Sonali99999
 
Aircraft maintenance and manuals week 2
Aircraft maintenance and manuals week 2Aircraft maintenance and manuals week 2
Aircraft maintenance and manuals week 2Jairo Gutierrez
 
Capacity Management in Airline Industry- A Case Study
Capacity Management in Airline Industry- A Case StudyCapacity Management in Airline Industry- A Case Study
Capacity Management in Airline Industry- A Case StudyAyat A. Saleh
 
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...CSCJournals
 
Airport planning part 1 -erau webinar
Airport planning part 1 -erau webinarAirport planning part 1 -erau webinar
Airport planning part 1 -erau webinarERAUWebinars
 
Work Project 1-latest
Work Project 1-latestWork Project 1-latest
Work Project 1-latestRanjit David
 
Check interval escalation
Check interval escalation Check interval escalation
Check interval escalation Mohammed Awad
 

What's hot (19)

Topic of the Month (14-03): Transition Training
Topic of the Month (14-03): Transition TrainingTopic of the Month (14-03): Transition Training
Topic of the Month (14-03): Transition Training
 
Aircraft Maintenance practices introduction
Aircraft Maintenance practices introduction Aircraft Maintenance practices introduction
Aircraft Maintenance practices introduction
 
Deferred Maintenance Article
Deferred Maintenance ArticleDeferred Maintenance Article
Deferred Maintenance Article
 
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce Magazine
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce MagazineLufthansa Systems Turnaround Management Solution in Aircraft Commerce Magazine
Lufthansa Systems Turnaround Management Solution in Aircraft Commerce Magazine
 
Aircraft Maintenance Documentation
Aircraft Maintenance DocumentationAircraft Maintenance Documentation
Aircraft Maintenance Documentation
 
Aircraft Maintenance Records and Airworthiness Directives for General Aviation
Aircraft Maintenance Records and Airworthiness Directives for General AviationAircraft Maintenance Records and Airworthiness Directives for General Aviation
Aircraft Maintenance Records and Airworthiness Directives for General Aviation
 
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...
An Aviation Case Study: Sorting Out Key Factor Leading An Airline Operator Ab...
 
Airport planning
Airport planning Airport planning
Airport planning
 
Operation and Maintenance of Light Sport Aircraft
Operation and Maintenance of Light Sport AircraftOperation and Maintenance of Light Sport Aircraft
Operation and Maintenance of Light Sport Aircraft
 
Capacity Management
Capacity ManagementCapacity Management
Capacity Management
 
Aircraft maintenance and manuals week 2
Aircraft maintenance and manuals week 2Aircraft maintenance and manuals week 2
Aircraft maintenance and manuals week 2
 
What to Expect From your Mechanic
What to Expect From your MechanicWhat to Expect From your Mechanic
What to Expect From your Mechanic
 
Capacity Management in Airline Industry- A Case Study
Capacity Management in Airline Industry- A Case StudyCapacity Management in Airline Industry- A Case Study
Capacity Management in Airline Industry- A Case Study
 
Aircraft inspections
Aircraft inspectionsAircraft inspections
Aircraft inspections
 
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...
A Novel Approach To The Weight and Balance Calculation for The De Haviland Ca...
 
Airport planning part 1 -erau webinar
Airport planning part 1 -erau webinarAirport planning part 1 -erau webinar
Airport planning part 1 -erau webinar
 
Stall and Spins - Awareness and Avoidance
Stall and Spins - Awareness and AvoidanceStall and Spins - Awareness and Avoidance
Stall and Spins - Awareness and Avoidance
 
Work Project 1-latest
Work Project 1-latestWork Project 1-latest
Work Project 1-latest
 
Check interval escalation
Check interval escalation Check interval escalation
Check interval escalation
 

Viewers also liked

Airline flights delay prediction- 2014 Spring Data Mining Project
Airline flights delay prediction- 2014 Spring Data Mining ProjectAirline flights delay prediction- 2014 Spring Data Mining Project
Airline flights delay prediction- 2014 Spring Data Mining ProjectHaozhe Wang
 
Flight Delay Prediction Model (2)
Flight Delay Prediction Model (2)Flight Delay Prediction Model (2)
Flight Delay Prediction Model (2)Shubham Gupta
 
Capital One Card Lab Connect Saving Shelter Pets Case Study
Capital One Card Lab Connect Saving Shelter Pets Case StudyCapital One Card Lab Connect Saving Shelter Pets Case Study
Capital One Card Lab Connect Saving Shelter Pets Case StudyRebecca Higman
 
Content wants to be free (from projects) - J.boye Aarhus 2015
Content wants to be free (from projects) - J.boye Aarhus 2015Content wants to be free (from projects) - J.boye Aarhus 2015
Content wants to be free (from projects) - J.boye Aarhus 2015Rasmus Skjoldan
 
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis County
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis CountyWebinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis County
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis CountyKimbia, Inc
 
Case study brookfield airport
Case study brookfield airportCase study brookfield airport
Case study brookfield airportColo_cr
 
Flink Case Study: Capital One
Flink Case Study: Capital OneFlink Case Study: Capital One
Flink Case Study: Capital OneFlink Forward
 
Data Mining & Analytics for U.S. Airlines On-Time Performance
Data Mining & Analytics for U.S. Airlines On-Time Performance Data Mining & Analytics for U.S. Airlines On-Time Performance
Data Mining & Analytics for U.S. Airlines On-Time Performance Mingxuan Li
 

Viewers also liked (9)

Airline flights delay prediction- 2014 Spring Data Mining Project
Airline flights delay prediction- 2014 Spring Data Mining ProjectAirline flights delay prediction- 2014 Spring Data Mining Project
Airline flights delay prediction- 2014 Spring Data Mining Project
 
Flight Delay Prediction Model (2)
Flight Delay Prediction Model (2)Flight Delay Prediction Model (2)
Flight Delay Prediction Model (2)
 
Capital One Card Lab Connect Saving Shelter Pets Case Study
Capital One Card Lab Connect Saving Shelter Pets Case StudyCapital One Card Lab Connect Saving Shelter Pets Case Study
Capital One Card Lab Connect Saving Shelter Pets Case Study
 
Content wants to be free (from projects) - J.boye Aarhus 2015
Content wants to be free (from projects) - J.boye Aarhus 2015Content wants to be free (from projects) - J.boye Aarhus 2015
Content wants to be free (from projects) - J.boye Aarhus 2015
 
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis County
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis CountyWebinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis County
Webinar: Social Media + P2P Fundraising: A Case Study w/ CASA of Travis County
 
Case study brookfield airport
Case study brookfield airportCase study brookfield airport
Case study brookfield airport
 
BIG DATA TO AVOID WEATHER RELATED FLIGHT DELAYS PPT
BIG DATA TO AVOID WEATHER RELATED FLIGHT DELAYS PPTBIG DATA TO AVOID WEATHER RELATED FLIGHT DELAYS PPT
BIG DATA TO AVOID WEATHER RELATED FLIGHT DELAYS PPT
 
Flink Case Study: Capital One
Flink Case Study: Capital OneFlink Case Study: Capital One
Flink Case Study: Capital One
 
Data Mining & Analytics for U.S. Airlines On-Time Performance
Data Mining & Analytics for U.S. Airlines On-Time Performance Data Mining & Analytics for U.S. Airlines On-Time Performance
Data Mining & Analytics for U.S. Airlines On-Time Performance
 

Similar to Cost of Delay

Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214
Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214
Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214deepak kumar
 
Air Traffic Control Database Management System for Seamless Transit
Air Traffic Control Database Management System for Seamless TransitAir Traffic Control Database Management System for Seamless Transit
Air Traffic Control Database Management System for Seamless TransitIRJET Journal
 
50.- DIAPOSITIVAS ME.pdf
50.- DIAPOSITIVAS ME.pdf50.- DIAPOSITIVAS ME.pdf
50.- DIAPOSITIVAS ME.pdfmarcocando9
 
Simulation_Final_Project_Grp6.pptx
Simulation_Final_Project_Grp6.pptxSimulation_Final_Project_Grp6.pptx
Simulation_Final_Project_Grp6.pptxShivamPandey521834
 
Shared aircraft spares holdings or pooling: To increase air carrier operation...
Shared aircraft spares holdings or pooling: To increase air carrier operation...Shared aircraft spares holdings or pooling: To increase air carrier operation...
Shared aircraft spares holdings or pooling: To increase air carrier operation...Mersie Amha Melke
 
digital avionics systems
digital avionics systemsdigital avionics systems
digital avionics systemsrammohan ijjada
 
Human factors - Maintenance and inspection
Human factors - Maintenance and inspectionHuman factors - Maintenance and inspection
Human factors - Maintenance and inspectionLahiru Dilshan
 
Consequences of Errors in Aviation
Consequences of Errors in AviationConsequences of Errors in Aviation
Consequences of Errors in AviationOmar Hayat Khan, MSc
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonellakingstonmj
 
Aircraft Routine Checks neethu1.0
Aircraft Routine Checks neethu1.0Aircraft Routine Checks neethu1.0
Aircraft Routine Checks neethu1.0Neethu Nair
 
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...SITA
 
Aircraft Inspection and Maintenance Records
Aircraft Inspection and Maintenance RecordsAircraft Inspection and Maintenance Records
Aircraft Inspection and Maintenance RecordsFernando Araujo
 
Karen Lee and Jonathan Pelosi prepared this case under the s.docx
Karen Lee and Jonathan Pelosi prepared this case under the s.docxKaren Lee and Jonathan Pelosi prepared this case under the s.docx
Karen Lee and Jonathan Pelosi prepared this case under the s.docxDIPESH30
 
AMTE233 Part 3 (1).pdf
AMTE233 Part 3 (1).pdfAMTE233 Part 3 (1).pdf
AMTE233 Part 3 (1).pdfParkJihyo12
 
Tugas iii etops approval
Tugas iii etops approvalTugas iii etops approval
Tugas iii etops approvalLalu Giat Putra
 

Similar to Cost of Delay (20)

Producción inspeccionada de aeronaves
Producción inspeccionada de aeronavesProducción inspeccionada de aeronaves
Producción inspeccionada de aeronaves
 
Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214
Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214
Additive manufacturing-for-the-aircraft-industry-a-review-2329-6542-1000214
 
CDM Aviation Point of View
CDM Aviation Point of View CDM Aviation Point of View
CDM Aviation Point of View
 
Air Traffic Control Database Management System for Seamless Transit
Air Traffic Control Database Management System for Seamless TransitAir Traffic Control Database Management System for Seamless Transit
Air Traffic Control Database Management System for Seamless Transit
 
50.- DIAPOSITIVAS ME.pdf
50.- DIAPOSITIVAS ME.pdf50.- DIAPOSITIVAS ME.pdf
50.- DIAPOSITIVAS ME.pdf
 
Simulation_Final_Project_Grp6.pptx
Simulation_Final_Project_Grp6.pptxSimulation_Final_Project_Grp6.pptx
Simulation_Final_Project_Grp6.pptx
 
Shared aircraft spares holdings or pooling: To increase air carrier operation...
Shared aircraft spares holdings or pooling: To increase air carrier operation...Shared aircraft spares holdings or pooling: To increase air carrier operation...
Shared aircraft spares holdings or pooling: To increase air carrier operation...
 
digital avionics systems
digital avionics systemsdigital avionics systems
digital avionics systems
 
Human factors - Maintenance and inspection
Human factors - Maintenance and inspectionHuman factors - Maintenance and inspection
Human factors - Maintenance and inspection
 
Consequences of Errors in Aviation
Consequences of Errors in AviationConsequences of Errors in Aviation
Consequences of Errors in Aviation
 
Executive Transport Detatchment Sigonella
Executive Transport Detatchment SigonellaExecutive Transport Detatchment Sigonella
Executive Transport Detatchment Sigonella
 
Series B note
Series B noteSeries B note
Series B note
 
Aircraft Routine Checks neethu1.0
Aircraft Routine Checks neethu1.0Aircraft Routine Checks neethu1.0
Aircraft Routine Checks neethu1.0
 
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...
India Aviation ICT Forum 2013 - Manish Sinha, Deputy COO, Hyderabad Internati...
 
Aircraft Inspection and Maintenance Records
Aircraft Inspection and Maintenance RecordsAircraft Inspection and Maintenance Records
Aircraft Inspection and Maintenance Records
 
Karen Lee and Jonathan Pelosi prepared this case under the s.docx
Karen Lee and Jonathan Pelosi prepared this case under the s.docxKaren Lee and Jonathan Pelosi prepared this case under the s.docx
Karen Lee and Jonathan Pelosi prepared this case under the s.docx
 
Aero
Aero Aero
Aero
 
AMTE233 Part 3 (1).pdf
AMTE233 Part 3 (1).pdfAMTE233 Part 3 (1).pdf
AMTE233 Part 3 (1).pdf
 
Tugas iii etops approval
Tugas iii etops approvalTugas iii etops approval
Tugas iii etops approval
 
Is your aircraft talking to you? Listen!
Is your aircraft talking to you?  Listen!Is your aircraft talking to you?  Listen!
Is your aircraft talking to you? Listen!
 

More from Mohammed Awad

Air Cargo Forecast 2023 for Aviation Industry
Air Cargo Forecast 2023 for Aviation IndustryAir Cargo Forecast 2023 for Aviation Industry
Air Cargo Forecast 2023 for Aviation IndustryMohammed Awad
 
BCG Matrix Analysis for Airlines for period Dec 2019
BCG Matrix Analysis for Airlines for period Dec 2019BCG Matrix Analysis for Airlines for period Dec 2019
BCG Matrix Analysis for Airlines for period Dec 2019Mohammed Awad
 
Air Cargo Forecast.pdf
Air Cargo Forecast.pdfAir Cargo Forecast.pdf
Air Cargo Forecast.pdfMohammed Awad
 
Aviation Business Leader - Global Ceo Excellence
Aviation Business Leader - Global Ceo ExcellenceAviation Business Leader - Global Ceo Excellence
Aviation Business Leader - Global Ceo ExcellenceMohammed Awad
 
New destination 4.pdf
New destination 4.pdfNew destination 4.pdf
New destination 4.pdfMohammed Awad
 
Rush Hour Analysis final 12.pdf
Rush Hour Analysis final 12.pdfRush Hour Analysis final 12.pdf
Rush Hour Analysis final 12.pdfMohammed Awad
 
Has Airline Forecasting changed forever?
Has Airline Forecasting changed forever?Has Airline Forecasting changed forever?
Has Airline Forecasting changed forever?Mohammed Awad
 
Back To Norms DXB 2022
Back To Norms DXB 2022 Back To Norms DXB 2022
Back To Norms DXB 2022 Mohammed Awad
 
Solar Presentation 1.pdf
Solar Presentation 1.pdfSolar Presentation 1.pdf
Solar Presentation 1.pdfMohammed Awad
 
JFK AIRPORT 2021-3.pdf
JFK  AIRPORT    2021-3.pdfJFK  AIRPORT    2021-3.pdf
JFK AIRPORT 2021-3.pdfMohammed Awad
 
Fare Mapping Analysis.pdf
Fare Mapping Analysis.pdfFare Mapping Analysis.pdf
Fare Mapping Analysis.pdfMohammed Awad
 
Back To Norms 123 y.pdf
Back To Norms 123 y.pdfBack To Norms 123 y.pdf
Back To Norms 123 y.pdfMohammed Awad
 
Ceo article arabic11
Ceo article arabic11Ceo article arabic11
Ceo article arabic11Mohammed Awad
 
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2Is Low Cost Carrier Profitable -Ryan article - Issue No. 2
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2Mohammed Awad
 
Is Low Cost Carrier Profitable - Norwegian article - Issue No. 1
Is Low Cost Carrier Profitable  - Norwegian article - Issue No. 1Is Low Cost Carrier Profitable  - Norwegian article - Issue No. 1
Is Low Cost Carrier Profitable - Norwegian article - Issue No. 1Mohammed Awad
 
Standout From The Crowds
Standout From The CrowdsStandout From The Crowds
Standout From The CrowdsMohammed Awad
 
All roads lead to rome final
All roads lead to rome finalAll roads lead to rome final
All roads lead to rome finalMohammed Awad
 
Airport forecasting issue 45 tls 2020 - Toulouse Airport
Airport forecasting issue 45 tls 2020 - Toulouse AirportAirport forecasting issue 45 tls 2020 - Toulouse Airport
Airport forecasting issue 45 tls 2020 - Toulouse AirportMohammed Awad
 
Aeroporti de roma fco
Aeroporti de roma fcoAeroporti de roma fco
Aeroporti de roma fcoMohammed Awad
 

More from Mohammed Awad (20)

Air Cargo Forecast 2023 for Aviation Industry
Air Cargo Forecast 2023 for Aviation IndustryAir Cargo Forecast 2023 for Aviation Industry
Air Cargo Forecast 2023 for Aviation Industry
 
BCG Matrix Analysis for Airlines for period Dec 2019
BCG Matrix Analysis for Airlines for period Dec 2019BCG Matrix Analysis for Airlines for period Dec 2019
BCG Matrix Analysis for Airlines for period Dec 2019
 
Air Cargo Forecast.pdf
Air Cargo Forecast.pdfAir Cargo Forecast.pdf
Air Cargo Forecast.pdf
 
Aviation Business Leader - Global Ceo Excellence
Aviation Business Leader - Global Ceo ExcellenceAviation Business Leader - Global Ceo Excellence
Aviation Business Leader - Global Ceo Excellence
 
New destination 4.pdf
New destination 4.pdfNew destination 4.pdf
New destination 4.pdf
 
Rush Hour Analysis final 12.pdf
Rush Hour Analysis final 12.pdfRush Hour Analysis final 12.pdf
Rush Hour Analysis final 12.pdf
 
Has Airline Forecasting changed forever?
Has Airline Forecasting changed forever?Has Airline Forecasting changed forever?
Has Airline Forecasting changed forever?
 
Back To Norms DXB 2022
Back To Norms DXB 2022 Back To Norms DXB 2022
Back To Norms DXB 2022
 
Solar Presentation 1.pdf
Solar Presentation 1.pdfSolar Presentation 1.pdf
Solar Presentation 1.pdf
 
JFK AIRPORT 2021-3.pdf
JFK  AIRPORT    2021-3.pdfJFK  AIRPORT    2021-3.pdf
JFK AIRPORT 2021-3.pdf
 
black swan.pdf
black swan.pdfblack swan.pdf
black swan.pdf
 
Fare Mapping Analysis.pdf
Fare Mapping Analysis.pdfFare Mapping Analysis.pdf
Fare Mapping Analysis.pdf
 
Back To Norms 123 y.pdf
Back To Norms 123 y.pdfBack To Norms 123 y.pdf
Back To Norms 123 y.pdf
 
Ceo article arabic11
Ceo article arabic11Ceo article arabic11
Ceo article arabic11
 
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2Is Low Cost Carrier Profitable -Ryan article - Issue No. 2
Is Low Cost Carrier Profitable -Ryan article - Issue No. 2
 
Is Low Cost Carrier Profitable - Norwegian article - Issue No. 1
Is Low Cost Carrier Profitable  - Norwegian article - Issue No. 1Is Low Cost Carrier Profitable  - Norwegian article - Issue No. 1
Is Low Cost Carrier Profitable - Norwegian article - Issue No. 1
 
Standout From The Crowds
Standout From The CrowdsStandout From The Crowds
Standout From The Crowds
 
All roads lead to rome final
All roads lead to rome finalAll roads lead to rome final
All roads lead to rome final
 
Airport forecasting issue 45 tls 2020 - Toulouse Airport
Airport forecasting issue 45 tls 2020 - Toulouse AirportAirport forecasting issue 45 tls 2020 - Toulouse Airport
Airport forecasting issue 45 tls 2020 - Toulouse Airport
 
Aeroporti de roma fco
Aeroporti de roma fcoAeroporti de roma fco
Aeroporti de roma fco
 

Recently uploaded

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 

Recently uploaded (20)

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 

Cost of Delay

  • 1. Cost of Delay, Rescheduling and Cancellation In Airlines Introduction Usually Airlines are suffering from flights delay issues, but most of them control these problems and their causes, so the issue of flight delay may create a bad impression on the airline image and its brand name in the market, and consequently it is directly related to the concerned airline operation divisions and departments, from maintenance, flight operation, commercial and customer service, as they are interacted and integrated divisions that serve for one mission, so every division has its own rules and impacts on dispatch the flight on time, and any negligence may reflects on airline final performance, and cause Mohammed S. Awad the delay of the flight. In aviation industry the cost of delay is Research Scholar considerably high due the high gained revenue of the flights and high direct fixed operating cost for a certain type of aircraft hence we measure the activities of an airline by its performance which usually addressed by the performance report of Operation Control Committee OCC. Where the maintenance and material divisions are the main airline departments that support the operation, as they are responsible for aircraft technical readiness and fulfill the provision of spare parts of the aircraft, and tracking/ monitoring the technical operating performance by papering reliability report, which is similar as performance report, but its results are technical oriented, i.e defining technical problems and failure diagnostic before its happen and cause a delay or cancelation, which play a major rule in preventive maintenance program for the aircraft. Finally by referring to Boeing Company reports, the engineering and maintenance issues and problems for aircraft are represents 30-40% of total delay cost for the flight in airline industry. 1
  • 2. OCC Operation Control Committee: The weekly report of this committee is one of the main sources of airline activity evaluation and it is an effective tool to explore and define deviations so a proper action may take on time and most of operating and serving departments represents in the committee, so this report rise the initial signals to predicate defect or trouble a certain failure in the airline activity for one week period. Delay Cost: It is too complicated to evaluate and calculate the delay cost in the airline industry and its impacts on the image and the brand of the airline. So we can refer to Boeing terms and definitions for delay cost that addressed in AGIFORS - Denver which are 1- Passenger direct cost 2- Direct Operating Cost 3- Cost of unavailability of scheduling Aircraft 4- Cost of losing the image and the loyalty for the airline. In our case we will use only two factors in the analysis only: 1- Passenger direct cost 2- Direct Operating Cost the calculation of delay or cancellation cost will as the following: Direct Operating Cost + expected income revenue of the delay or cancelled flight. And according to the study of American Airlines – domestic routes, the results are : Delay from : 0 – 15 minute.......... No Calculation of Cost 16 - 60 minute….......0.25 % ticket/min/pax 1 – 2 Hours ……0.5 % ticket /min/pax Approximately 1 out 8 passengers will probably not buy their next ticket on this airline. 2 – 5 Hours …….... All passengers will probably not buy tickets on this airline again for at least a year. And in this stage the growth of delay cost increase exponentially until reach to 5 hours delay period ( out of business). 2
  • 3. While the next figure explain the relationship between these costs and its average values, indicating the direct cost of passenger may happen after 20 min of delay time, and its impact on the passenger loyalty, image and the brand value of the airline. Impacts of Engineering and Maintenance: Referring to the Boeing Study, the share impact of maintenance and engineering causes may reach 30-40 of total delay causes. And the technical causes are the main reasons for cancellation of the Figure ( 2 ) Delay Cost Elements - American Airlines Study. flights and as its shows in the previous figures, the maximum delay period for maintenance cause is 45-120 if there is no cancellation. And the consequential effects of late aircraft arrival play a major rule in rescheduling the flights again. Delay Cost - Yemenia Case Study: The period of 02/01/2010 to 12/03/2010 characterize by repeated many delays in flights –Yemenia. Among of that , the technical delays and engine failures of B737-800 fleet which create a total mess in the flight scheduling program. So the delay cases can be address in two directions First : counting the repeated delays issues Figure ( 1 ) Measuring the time period costs Second : the delay time American Airlines Study. So delays can be caused by one of the following reasons: 1- Delay of the flight of the same aircraft type. 2- Delay of the flight may cause the need to change the type of the aircraft from bigger to smaller capacity which lead to extra cost of spill passengers. 3- Delay of the flight may cause the need to change the type of the aircraft from smaller to bigger capacity which lead to extra cost of losing the opportunity of un utilize seats for sale in last minutes. 4- Aircraft Grounded cost, by sending another aircraft for taking the passengers and supported spare parts. 5- Some time suddenly two aircrafts ground in the same time, and rise a hard time for planners and consequently may lead to cancel the flight. 6- Un readiness of the aircraft for unexpected time. 7- Longer maintenance programs may lead to delay the flights. 3
  • 4. Figure ( 3 ). Delay Factors of Yemen Airways Analysis: In spite of defining Boeing Company the main factors that may cause the delays, pointing out the maintenance /engineering and bad weather but yemenia analysis results indicates another factors that impact high influence of those mentioned in Boeing Study. However technical and engine failures remains the main factor in the period of 02/01/2010 to 12/03/2010 1- Transit Passengers 2- Technical Problem 3- Airport Security 4- ATC 5- Late Arrival of Aircraft 6- Bad Weather 7- Maintenance Problems 8- Other factors As indicated in graph, the other factors take the large share in the delay reasons, yemenia should review all the delay items category so that the other reasons well defined in the analysis and re casted in the right way. Also similar category should be merge to be one category as maintenance and technical. This lead us to the result of the analysis, so Number of Delays with less than 20 min =121 delays with cumulative time = 1355 min Number of Delays with greater than 20 min =87 delays with cumulative time = 4185 min but for technical delays, it take larger time to fix and rectify in spite of hidden function issues 4
  • 5. Summary: 1- The analysis show the un availability of support fleet , as the scheduling designed with one supported aircraft. But in some cases of two aircraft grounded in the same time led to a total mess in scheduling that need to rescheduling and delay the other flights. 2- The technical delay have the majority causes of delays, and when its happen , its take a long time. 3- In spite of the impact of transit passengers on delay, the maximum allowable time period for transit passengers is 45-60 min, but the delay period may reach to 5 hours or more and effects on the airline image in the market. 4- Advanced and prior corporation between commercial and technical departments so that they adapted and implemented a the right scheduling without interruption based on the sound of the market. 5- Brand name of the airline in the market may get lose, if the airline repeat these delays, and changing the capacities of aircrafts in the last minutes. Figure ( 4 ) Frequency Distribution of Delay Periods  5