SlideShare ist ein Scribd-Unternehmen logo
1 von 123
Petro‐Chemical and Refinery 
Master Electrical Plans and What a 
Good Electrical System Looks Like
Speaker:
Vincent W. Wedelich, *PE, MBA, 
Project Manager Power Distribution & Controls, Burns 
& McDonnell Engineering Co, Inc.
*Registered PE in Texas.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
1
Your company should have a 
Zero Policy.
• “zero” safety incidents
• “zero” power failures; with “fastest” power 
recovery
• “zero” flares and process leaks
• “zero” process downtime
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
2
Get everybody on board 
to save bottom line 
• Petro‐Chemical facility owners and refiners are advised to set a goal 
of “zero” power failure and “fastest” power recovery and share the 
goal with all the employees, including people working outside the 
plant. 
• When a refinery/petro‐chemical facility shuts down, business profit 
is gone, thereby affecting everybody in the company, from the CEO 
to the maintenance worker.
• Any employees that offer key contribution in terms of ideas and 
innovations to increased reliability and availability of a power 
system should be offered financial incentive for avoiding power 
failures. 
• The Power of Habit!  By: Charles Duhigg Read it….
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
3
Reference Data
• Long term optimization of asset replacement in energy 
infrastructures; Ype C. Wijnia, Martijn S. Kom, Saskia Y. de Jager, 
Paulien M. Herder 2006
• Refinery power failures: causes, costs and solutions;  Patrick J 
Christensen, William H Graf and Thomas W Yeung Hydrocarbon 
Publishing Company 2013
• Integrating Advanced Relays On Medium Voltage Switchgear Safety 
Instrumented Systems (P66 and BMcD) IEEE PCIC 2013.
• OSHA 1910.119 Process safety management of highly hazardous 
chemicals
• Arc Flash Mitigation in a Chemical and Refining Facility Using IEC 
61850 (CPChem/BMcD IEEE PCIC 2012)
• Many, many papers and studies published by IEEE.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
4
Abstract:
• The material used in this presentation was readily available 
from the internet and IEEE presentations.  This 
presentation is for educational, safety, and process 
improvement purposes only.
• Applicable to Refineries and Petrochemical facilities 
• Review of what an Electrical System Master Plan Study is: 
– to identify system improvements related to reliability,
– safety and maintainability for projected load expansion at the 
refinery/petro‐chemical facility within the next 5 to 20 years. 
– This master plan and the ideas presented were geared towards 
creating a good foundation for the future of the electrical 
system primarily through upgrade and replacement projects. 
– Illustrate what a good electrical system looks like.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
5
Bio
• Presenter: IEEE Houston Past Chair 
• Mr. Wedelich is an Associate level project 
manager and electrical engineer in 
the Houston T&D Power Distribution and 
Controls Department at Burns & McDonnell. 
• His responsibilities include Power System 
Design and Project Management for the 
Industrial and refinery/petro‐chemical facility 
Markets. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
6
Read the OSHA report on:
THE 100 LARGEST LOSSES
• 1972–2011
• Large 
Property 
Damage 
Losses In The 
Hydrocarbon 
Industry
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
7
What do (Refinery, Petrochemical, Gas 
Processing, & Terminals and 
Distribution) have in common?
• EarthQuakes
• Fires
• Explosions
• Hurricanes (flooding)
• Vapor Cloud Explosions
• Corrosion (pipe racks!!!) failing.
• Mechanical Damage
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
8
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
9
Explosion
• Five people were killed and two seriously injured 
following an explosion at a plastics plant producing 200 
million barrels per year of specialty grade PVC. The 
highway was shut and local residents evacuated. The 
explosion occurred in a reactor where vinyl chloride 
and vinyl acetate were being mixed. Up to 75% of the 
plant was destroyed in the explosion. The explosion 
was felt 4 miles away.
• Solution: Implement Safety Integrity Systems 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
10
Explosion
• A release of hexane created a vapor cloud which 
ignited on an electric motor causing an 
explosion. This resulted in damage to the unit 
and some 20 injuries. The plant was eventually 
replaced.
• Solutions: Implement Safety Integrity Systems 
and address Area Classification Issues
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
11
Explosion/Fire
• An accident occurred at one of the methylcellulose 
manufacturing facilities located at this site. At 16:26 an 
explosion occurred and was followed by a fire, which was 
extinguished at 23:11 the same day.
• Seventeen people who were working at the site were 
injured in this accident; three critically, five seriously and 
nine with minor injuries. There was one minor injury off 
site. Static electricity induced the ignition of 
methylcellulose powders, resulting in a powder dust 
explosion. All methylcellulose operations were suspended 
for two months before sequentially restarting.
• Solutions: Resolve the Area Classification Issues
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
12
Hurricane
(Flooding)
• This petrochemical facility sustained damage 
during Hurricane Ike. Storm surge, flooding and 
high winds caused significant damage at the 
site. Force majeure was declared and the most 
heavily damaged portion of the plant remained 
off line for 152 days.
• Solutions: Coastal sites: The flood maps need to 
be updated and electrical equipment needs to 
be raised into elevated Power Control Room’s.  
Have an alternate power source.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
13
Explosion
• A massive explosion occurred in an ammonium nitrate 
storage warehouse of a fertilizer plant just outside the 
southern French city of Toulouse. The warehouse 
contained approximately 300 tons of off‐specification 
ammonium nitrate crystals. The explosion had the 
strength of a 3.2 magnitude (Richter Scale) earthquake, 
left most of the plant in ruins and caused damage to 
surrounding areas. Thirty people were killed in the 
blast and approximately 3,000 people were injured. 
• Solutions: Address the (Area Classification Issues)
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
14
Explosion
• An explosion and fire occurred in an olefins unit at this 
petrochemical plant. The incident originated at the cracked gas 
compressor in the olefins unit and was caused by a failed air 
assisted check valve on a five inch diameter, 500 psi discharge line 
from the compressor. 
• Upon closure of the check valve, one of the pins holding the two‐
piece check valve stem broke and allowed it to open in the 
opposite direction. This led to a gas leak, ignition, explosion and 
ensuing fire at the partially enclosed compressor building. The 
explosion damaged a line to the quench tower, which fed the fire. 
The fire was allowed to burn itself out.
• About 30 workers were treated for minor injuries. 
• Solutions: Address the (Safety Integrity Systems,  and the Area 
Classification Issues)
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
15
Fire/Explosion
• A vent connection failed on a compressor suction 
line, releasing gas which led to a violent explosion 
with widespread damage. This was believed to be 
a fatigue failure due to vibration. 
• Fatigue failures due to vibration!!  Vibrations 
and corrosion is setting the industry up for 
major issues.
• In electricity networks almost all parts are 
vibrating at 100 Hz, resulting in metal fatigue.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
16
Aging Infrastructure
• The oldest assets in operation are about 60 years old, the 
average age of the asset base is about 30 years. 
• However, assets do not have perpetual lives, as normal 
wear and tear takes it toll.
• In the energy distribution systems, the assets are relatively 
old. 
• Distribution companies expect a large number of assets to 
fail because they reach their end of life in 1 to 21 years 
from now (current year 2015).
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
17
Aging Infrastructure
• Vibration and corrosion influences build up over time, and 
nobody knows for certain how fast deterioration will take 
place. 
• The best estimate for the lifespan is between 40 and 80 
years, depending on the type of asset. 
• This means we can expect at least part of the asset base to 
reach end‐of‐life within 1 to 11 years.
• End‐of‐life is defined as a non‐repairable failure of the 
asset.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
18
Aging Infrastructure
• The failing assets will have to be replaced, 
which would potentially double the total 
workload in this 20 year period.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
19
Aging Personnel
In parallel, to aging equipment , engineering staff 
retires after about 40 years in service. 
As most of them were employed during the
seventies, we can expect a large part of them to 
retire in the year 2016.  About half of the work 
force will retire by year 2013). IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
20
One in Five
• One in five young people will need to become an 
engineer if we have any chance of addressing 
severe skills shortages and rebalancing the 
economy towards advanced manufacturing, new 
research has warned.
• There is no getting away from the fact that 
women are substantially under‐represented in 
manufacturing at a time when industry needs to 
be tapping into every potential talent pool to 
access the skills it needs.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
21
Demand is high and is getting higher 
for qualified engineers
• With the number of baby boomers retiring in 2017 and in 2022 . . . the big 
fear is that . . . there are not enough individuals coming into the workforce 
to replace everybody, especially in the engineering fields. 
• The dilemma of a shortage of skilled engineers has become a prime topic 
of discussion across the country. 
• The present‐day labor market for most United States‐born engineering 
graduates remains relatively competitive in a time of high unemployment 
after large manufacturers and firms have consolidated operations during 
the recession. 
• Many engineers also have to compete with highly qualified candidates in 
China and India. 
• But recruiters indicate that demand for engineers and a more technically 
inclined workforce in the U.S. is only expected to grow. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
22
Refinery/petro‐chemical facility 
Shutdowns 
from 2009 to 2012
From 2009 to 2012, there were over 1700 refinery shutdowns, or 1.2 shutdowns per day. 
IEEE/AiChE Joint Presentation April 9, 2015 Rev. 0 For 
Educational, Safety, and Process Improvement Purposes Only
23
Causes of power 
disruptions from 
2009 to 2012
Other causes, mostly fires that occurred at the refinery/petro‐chemical facility.  
Unfortunately, over 60% of the causes of electrical disruptions are not specified. Most of 
the unspecified power failures were listed as “a power failure occurred at the refinery 
and caused flaring” or similar statements. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
24
Flooding during Hurricanes
• Although high wind and debris are the most 
commonly cited causes of hurricane damage, for 
Gulf Coast refineries in the US, where hurricanes 
hit most often and hardest, the greatest 
hurricane damage is the result of flooding. 
• It is not uncommon for a water line to be seen in 
refineries, the electrical equipment needs to be 
raised out of the water flood line.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
25
Structural Integrity
• It is important to understand that there is a difference between reliably 
supporting piping & process equipment versus being able to “stand in 
place” with piping and process equipment.
• In many existing facilities, 
– previous expansions, 
– modifications, 
– the age of the structures 
– as well as unknown conditions such as materials, 
– have drastically reduced the overall reliability of the support structures.
• While these structures remain upright, that does not mean they have the 
same reliability they once did in the original state.
• In many instances, the “in‐place” condition of many of the support 
structures are 
– already well below current minimum standards of reliability, 
– not to mention “good practice” standards.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
26
New steel is added to aging pipe racks, 
this can occur 3 and 4 times, the 
engineers designing these pipe racks 
could not have anticipated this.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
27
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
28
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
29
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
30
Key Issues LPG Fire
• Lack of Freeze Protection Of Dead‐legs: failure likely 
resulted from water trapped in the propane mix control 
station dead‐leg freezing due to low ambient temperatures. 
• Lack of an Emergency Isolation Of Equipment 
• Lack of Fireproofing Of Support Steel 
• Lack of Fire Protection For High Pressure LPG Service 
• Chlorine Release: change it to sodium hypochlorite system.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
31
Multiple unit shutdowns 
• Since most refinery/petro‐chemical facility units are 
integrated and sometimes share the same power supply, 
power failures could lead to the shutdown of these 
integrated units and the production loss of many refined 
products, thereby magnifying potential damages. 
• A facility in Alaska, experienced a power outage. The 
hydrocracker and another unit were shutdown. 
• In a Texas, plant experienced an external power failure that 
knocked its plant and other refineries in the area offline. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
32
Safety and Reliability Approval
• Most companies care about three values: financials, 
reliability and safety.
• For manageable optimization purposes, a single‐objective is 
pursued. 
• The common way forward is to express safety and reliability 
in monetary values.
• What is the cost to the bottom line if it is not corrected?
• There is no acceptable monetary value that can be place on 
safety and saving lives.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
33
Production loss and profit penalties
• When a power failure occurs, a refinery/petro‐chemical 
facility unit or units, or an entire facility must be shut 
down and production is lost. 
• A refiner could post a loss instead of profit in a quarter, 
and adverse financial impacts are further magnified 
when refining margins are poor. 
• For a rough estimate, a US Gulf Coast refinery/petro‐
chemical facility with an average‐ sized FCC unit of 80K 
b/d will lose $68K/hour for a downed unit.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
34
Case study
• A facility (refinery/petro‐chemical facility up north), was down from 28 October to 
20 November 2012 due to SuperStorm Sandy. 
• According to the company, the expenses related to the storm were $56 million 
before tax. 
• This loss did not include missed production for over three weeks.
• Based on the refinery’s nameplate gasoline production capacity of 145 000 b/d 
and distillate production capacity of 115,000 b/d, 
• a utilization rate of 85% and average spot market prices of gasoline of $2.812/gal 
and $3.084/gal for distillates in New York Harbor during the shutdown period, 
estimated revenue loss was over $650 million. 
• Net profit loss ranged from $5.3 million for cash margins of $1/bbl to $26.5 million 
for cash margins of $5/bbl. 
• US refineries outside the East Coast should expect a bigger financial impact, since 
East Coast refiners are known to have much lower refining margins than their 
peers in other parts of the country. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
35
Potential legal liabilities 
• Aside from missed production, outages prompt unnecessary flaring of 
hydrocarbons to avoid unsafe conditions. 
• Over the past 10 years, the US EPA has entered into settlements with 28 
different refineries that are aimed at restricting emissions by the oil 
industry. 
• The EPA has acquired consent decrees from 105 US refineries in 32 states 
and territories since December 2000. 
• All of the settlements have involved at least one of four primary pollution 
types: NOx, SOx, benzene and volatile organic compounds (VOCs). 
• Furthermore, all of the violations involved one or more four key 
refinery/petro‐chemical facility components: the FCC unit, SRU, flares and 
heaters/ boilers. 
• Excessive flaring can lead to environmental concerns and incur fines 
imposed by environmental agencies. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
36
Potential legal liabilities
• A facility in Texas paid over $87 million in fines 
issued by OSHA along with undisclosed 
amounts in civil suits related to an explosion 
and subsequent fire at its Texas City, Texas, 
refinery/petro‐chemical facility that resulted 
in 15 worker deaths and over 170 injuries. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
37
A Reliable Electrical Supply
• Electricity is the lifeblood of the 
refinery/petro‐chemical facility operation. 
• Optimal design and excellent construction 
mean nothing if the plant cannot receive a 
consistent and reliable power supply. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
38
Managing Electrical Outages
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
39
In handling risk management
• A refinery/petro‐chemical facility must install the most 
reliable equipment available in the market that can 
withstand disruptions caused by 
– weather, 
– power surges, 
– blackouts, 
– and any other outside elements. 
• Since no equipment is perfect, reliability engineers and 
operators still need to prepare for worst‐case scenarios 
as well as the most frequently occurring possibilities. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
40
Crisis Management
• When a problem does arise, the second part 
of the strategy — crisis management — comes 
into play. 
• This involves the recovery technologies that 
allow for safe shutdown and continued 
operation, and the restart methods that will 
not lead to the same problem that caused the 
previous failure. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
41
Prevention and protection
• One of the most important preventative 
measures a refinery/petro‐chemical facility 
can take is to have an efficient maintenance 
program. 
• Studies show that the failure rate of electrical 
equipment is three times higher for 
components that are not part of a scheduled 
preventative maintenance program. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
42
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
43
Reliability of systems
Everyone in this room, is smart, and can without a doubt, show that the reliability is not as bad as 
it looks, (using monte‐carlo type tools).  In affect they can kill key improvements by using 
statistics and math.  This is short term thinking.  
A safer more reliable, facility will return higher profits.  
Reward your employees who bring you safety ideas, and optimization ideas.  
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
44
Radial Feed System
• A Radial Feed System supplies electrical power via a single lineup of 
components from a supply bus, such as the utility supply, to the final 
utilization equipment. 
• In simplified terms, one feeder supplies one or more distribution 
transformers which in turn supplies one or more motor control centers or 
distribution panels. 
• These motor control centers and distribution panels then supply individual 
motor or other branch circuit loads. There is no duplication of equipment.
• Failure of any single component will cause an outage to all loads
downstream of the failure point and loss of production. 
• In addition the electrical equipment must be shut down to perform 
routine maintenance. 
• System investment is the lowest of the circuit arrangements, operation is 
simple, and reliability is as good as the quality and maintenance of the 
components. IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
45
Dual Feed System
• Various Dual Feed Systems are available and provide multiple paths to supply all or 
parts of the distribution system. 
• A primary selective system provides dual feeds on the primary or upstream side of 
a transformer. 
• A secondary selective system provides dual feeds on the lower voltage side of a 
pair of transformers but not all the utilization equipment is redundant. 
• Some power systems incorporate both primary and secondary selective options. 
• Dual Feed Systems provide multiple ways to supply most components except for 
the final utilization equipment – individual starters to motors for instance. 
• On properly designed Dual Feed systems, most maintenance can be performed 
following proper switching of loads without affecting refinery/petro‐chemical 
facility operations.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
46
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
47
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
48
Dual Feed System
• However, pumps and compressors that are not redundant (un‐
spared) will require operations interruptions for maintenance. 
• On Dual Feed systems with normally‐closed ties or automatic 
transfer schemes, a power outage or significant loss of production 
should be minimized for a single feeder or transformer failure. 
• Operation of the system is more complicated and initial installation 
cost is higher than for a Radial Feed System. 
• The main advantage of a Dual Feed system is that because of the 
multiple paths to provide electrical power, the electrical system has 
a high degree of reliability and availability which results in an overall 
lower LPO exposure than for a Radial System. 
• This is important for critical process or utility operations.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
49
Loop‐Feed or Ring‐Bus System
• A Loop‐Feed arrangement is sometimes used on 
primary distribution systems to feed multiple loads 
from different sources. 
• Generally, it is a system that can be manually‐
configured to isolate portions of the loop for 
maintenance or repair. 
• A ring‐bus system includes multiple sources and loads 
in a normally‐closed loop system with protective 
relaying designed to automatically isolate faulted 
sections.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
50
Combinations of Radial, Dual Feed, 
and Looped Systems
• Combinations of the above systems are present in most facilities. 
• The incoming Utility power and perhaps the primary distribution system in 
the plant are usually some form of Dual Feed, Looped, or Ring‐Bus system 
for reliability and maintainability. 
• Critical utility or common facilities that can never be shutdown, such as 
boiler plants, effluent systems, sulfur removal plants, plant air compressor 
systems, or the like, almost always require 2 or more sources of power 
(usually Dual Feed system) with careful consideration of load arrangement 
for maintainability. 
• The electrical availability, operational reliability and maintenance 
requirements are balanced against installed capital costs. 
• It should be noted that installation of a radial fed system connected to a 
secondary selective system does cause problems trying to schedule 
maintenance for the secondary selective bus.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
51
Formulating strategies 
to mitigate power  failures 
• Every processing unit within an oil refinery/petro‐
chemical facility was meticulously designed and 
planned on the assumption that it would receive a 
constant power supply. 
• With that in mind, it is necessary to consider the steps 
that could be taken to ensure 24/7 production from 
every process. 
• Risk management and crisis management must be 
practiced to maximize productivity of the plant. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
52
Impacts of refinery/petro‐chemical 
facility power failures
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
53
Power independence 
• Onsite power generation via combined heat and 
power (CHP) units and microgrids are worth 
consideration. 
• The latest CHP and microgrid technologies can be 
incorporated into the design of a new 
refinery/petro‐chemical facility power grid that 
can be combined with other renewable energy 
generation units as a way to improve power 
supply security and reduce plant carbon 
footprint. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
54
Get everybody on board 
to save bottom line 
• Petro‐Chemical facility owners and refiners are advised to set a goal 
of “zero” power failure and “fastest” power recovery and share the 
goal with all the employees, including people working outside the 
plant. 
• When a refinery/petro‐chemical facility shuts down, business profit 
is gone, thereby affecting everybody in the company, from the CEO 
to the maintenance worker.
• Any employees that offer key contribution in terms of ideas and 
innovations to increased reliability and availability of a power 
system should be offered financial incentive for avoiding power 
failures. 
• The Power of Habit!  By: Charles Duhigg Read it….
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
55
Major Equipment In Electrical Systems
• Generators
• Motors 
• Power & control cables 
• Transformers 
• UPS
• Battery chargers 
• Battery banks 
• Switch gear & control gear 
• Panels 
• Lighting 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
56
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
57
Transformers
• Almost every malfunction is a result of the failure of 
the device’s insulation system. 
• The insulation is what keeps the transformer in 
electrical balance and, when the insulation ceases to 
function, the entire transformer is susceptible to 
immediate failure. 
• Faults, heat and mechanical damage will lead to 
insulation failure, but the electrical engineer can avoid 
these issues by selecting a unit capable of withstanding 
expected operating and fault conditions. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
58
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
59
Cables 
• A refinery/petro‐chemical facility will use miles of cable for power 
distribution, motor operation and process control. 
• Its ability to transport signals and current will impact the entire 
refinery/petro‐chemical facility’s ability to operate. 
• Protection of all the cables is vital for any part of a process. 
• Cables will suffer from degradation to their insulation through heat 
and contamination. 
• Parts of a cable that heat up from excessive current or external 
factors will be vulnerable to water trees and short circuits. 
• Cables surrounded by polymer insulation are especially vulnerable 
to the damage caused by water trees. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
60
Major Equipment In Electrical Systems
Cables: An electrical cable comprises two or more 
wires running side by side and bonded, twisted, or 
braided together to form a single assembly, the 
ends of which can be connected to two devices, 
enabling the transfer of electrical signals from one 
device to the other.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
61
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
62
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
63
Switchgear
• Switchgear is a combination of electrical 
enclosures, buses, protective relays, circuit 
breakers, fuses, controls and indicating devices 
that are used to distribute power to and protect 
other electric equipment. 
• Receiving power from generators or transmission 
cables, they will distribute their power to other 
switchgear (or switchboards) and motor control 
centers. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
64
Switchgear
• Arcing is a major threat to switchgear safety and 
reliability. 
• Major arc flashes and blasts will ruin the switchgear 
and nearby equipment, and endanger nearby workers.
• An arcing event can cost a refinery/petro‐chemical 
facility as much as $15 million per incident.
• Plant engineers should select arc‐resistant models that 
utilize quick sensing and switching to de‐energize arcs. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
65
Motor control center 
• A motor control center (MCC) is used to group a 
number of combinations of motor controllers together 
with a common power bus. 
• A MCC gives operators easy and safe control over a 
number of different motors throughout the facility. 
• Motor controllers serve several key functions: starting 
or stopping the motor it controls, interrupting the 
current of the motor, and providing overcurrent 
protection. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
66
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
67
Major Equipment In Electrical Systems
Panels: is a component of an electricity supply 
system which divides an electrical power feed 
into subsidiary circuits, while providing a 
protective fuse or circuit breaker for each circuit 
in a common enclosure.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
68
MAJOR EQUIPMENT IN ELECTRICAL SYSTEMS
Switchgear & control gear : switchgear is the 
combination of electrical disconnect switches, fuses 
or circuit breakers used to control, protect and 
isolate electrical equipment. Switchgear is used 
both to de‐energize equipment to allow work to be 
done and to clear faults downstream
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
69
Motors 
• As far as consumption of electric energy goes, 
nothing in a refinery/petro‐chemical facility 
comes close to the amount of power provided 
to motor‐driven devices. 
• Motor‐driven equipment will typically account 
for 70% of energy consumption in refineries, 
so special attention must be paid to their 
proper selection and operation. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
70
Major Equipment In Electrical Systems
Motor: a motor, is a machine designed to 
convert one form of energy into mechanical 
energy
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
71
Protective relays
• Relays are essential to any electrical system.
• Pick one kind of relay, so that you can develop a reliable, intelligent 
data collection system.   
• Do not allow any capital project team to implement multiple relay 
manufactures.  It complicates the entire system.
• They are used in all parts of the system, from the generators and 
substation to the transmission lines and load. 
• Protective relays detect abnormal system conditions and direct the 
circuit breakers to operate in the proper manner, to correct any 
abnormality. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
72
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
73
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
74
Grounding
• A properly grounded (earthed) system will 
protect equipment and personnel from exposure 
to fault currents. 
• Well‐placed and ‐designed grounding will divert 
any faults to earth or a grounded bus. 
• It is utilized throughout an electric system for 
equipment such as transformers and motors, and 
on conductive structures like storage tanks and 
pipes. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
75
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
76
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
77
Inadequate Lightning Protection
• In Port Arthur, Texas, facility experienced lightning that led to a power 
outage and also stated a fire. The lightning caused a crude unit, two 
hydrotreaters and a delayed coker to shut down. 
• Unlike the above experience, in July 2009, a refinery/petro‐chemical 
facility in Pasadena, Texas, experienced a lightning strike that disabled all 
power to the Tank farm, which resulted in loss of feed to the refinery’s 
crude unit. The feed was restored with a backup generator, and the 
refinery was able to run using backup power and keep operations online 
despite the loss of power to the tank farm. 
• A facility in Los Angeles CA experienced a power surge caused by lightning, 
which caused the hydrocracking unit to trip. Emissions of sulphur dioxide 
and hydrogen sulphide were released during the flaring caused by the 
shutdown. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
78
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
79
Lightning Protection
• Fixed Angle Method
• Rolling Sphere Method
• Proper grounding
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
80
Introduction to Lightning Protection
i. Notes continued:  
» Aluminum materials shall not be used where they come 
in to direct contact with earth.  A bimetallic connector 
shall be installed not less than 10” above earth level.
» Aluminum conductors shall not be attached to a surface 
coated with alkaline base paint, embedded in concrete 
or masonry, or installed in a location subject to 
excessive moisture.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
81
Introduction to Lightning Protection
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
82
Introduction to Lightning Protection
– Air Terminal height 
• The tip of an air terminal shall not be less then 10 
inches above the object or area it is to protect.
– Zone of protection
• To determine the zone of protection, the geometry of 
the structure shall be considered.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
83
Introduction to Lightning Protection
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
84
Introduction to Lightning Protection
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
85
Introduction to Lightning Protection
– Location of devices
• There are set distances that an air terminal can be 
installed apart from each other on a roof peak or at 
the edge of the roof that is pitched or flat.
– Within 2’ of the edge of the roof
– 20‐25 ft. maximum spacing along the ridge.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
86
Recovery and restart
• Preventative and protective measures will make 
great strides towards decreasing downtime 
arising from power failures. 
• But if a failure does occur, it is necessary to 
minimize loss in production and resume normal 
operation as quickly as possible. 
• Even if the units are running at reduced rates, 
flaring can be reduced and production will not 
completely halt. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
87
Backup generators 
• When the power goes down, all the units have 
to stop. 
• On‐site generators give operators the ability to 
continue running units when the primary 
power goes down.
• These units are not usually used as the 
primary power due to fuel costs. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
88
Major Equipment In Electrical Systems
Generator: a generator is a device that converts mechanical 
energy to electrical energy for use in an external circuit. 
The source of mechanical energy may vary widely from a hand 
crank to an internal combustion engine. Generators provide 
nearly all of the power for electric power grids.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
89
Uninterruptible power supply 
• UPS is a device that acts as a backup power source. 
• It is designed to detect power dips and power failures, and initiate a 
battery backup power once a problem is detected.
• A UPS should only be used in an environment that it is rated for. 
• UPS system loads consist of 
– digital control systems, 
– programmable logic controllers, 
– critical process instruments, 
– fire and gas alarm panels, 
– safety shutdown systems, 
– process equipment control panels (boiler controls, compressor 
controls, and so on) 
– and other critical electrical loads.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
90
Major Equipment In Electrical Systems
UPS: An uninterruptible power supply, also 
uninterruptible power source, UPS, is an 
electrical apparatus that provides emergency 
power to a load when the input power source, 
typically mains power, fails
UPS
INPUT OUTPUT
Spikes
Interruption
Harmonics
Under Voltage
Continuous
Clean
Filtered
Critical
Loads
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
91
3‐ UPS COMPONENTS
1. Normal Electric Source
2. Rectifier (Charger)
3. Battery.
4. Inverter.
5. Static Transfer Switch (STS).
6. Maintenance Bypass Switch (MBS).
7. Bypass Electric Source.
STS
Critical Load
Bypass
Source
Normal
Source
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
92
4‐ How UPS Works?
STS
Critical Load
Bypass
Source
Normal
Source
Normal Mode
Auto Bypass
ManualBypass
Power Outage
(Battery Mode)
FAILURE
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
93
Major Equipment In Electrical Systems
Battery banks: a container consisting of one or 
more cells, in which chemical energy is 
converted into electricity and used as a source 
of power
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
94
Major Equipment In Electrical Systems
Battery charger : A battery charger or recharger 
is a device used to put energy into a secondary 
cell or rechargeable battery by converting 
current from AC to DC.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
95
What we have found during site visits
• Pipe racks are severely overloaded.  When performing laser scans it can be 
seen that the pipe racks are in fatigue, bending beyond the calculated 
values.
• Corrosion is causing pipes and pipe racks to fail.
• Area classification issues, there are to many to count.
– Hydrogen pipe/Control Valve in close proximity to a new PCR.
– Conduit Seals not installed or installed incorrectly.
– Arcing and sparking devices in areas that need explosion proof devices.
• New equipment added that now creates an area classification issue.
• SIS and SIF systems are not in place.
• Aging personnel, leaving behind young untrained personnel. 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
96
What we have found during site visits
• Mis‐coordination of circuit breakers and fuses.
• Undersized equipment (voltage or current).
– Cannot withstand the short circuit current
– Cannot withstand the continuous current.
– I have heard CEO’s say: we don’t have this problem in our 
facility do we?  (radial feeds to critical process units?  Can’t 
be).  It is our jobs to inform our supervisors, they trust the 
line managers, the maintenance crews, etc.. To inform 
them of safety and reliability issues.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
97
An electrical master plan addresses
• The reliability and safety of the existing electrical 
system.
• A report should be created to mitigate 
(short/long term) plan to improve the reliability 
and the safety of the electrical system supported 
by justification.
• Electrical cable and equipment needs to be 
reviewed to see if the support structures are in 
good shape.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
98
A Master Plan should include:
• Recommendations of applying best practices and 
equipment assessment.
• Develop an accurate system model (ETAP, SKM, Easy 
Power etc..) data collecting from the site visit to figure 
out some of the reliability or safety issues such as:
– Substation configuration (radial or redundant) 
– Under rated equipment
– Overload equipment
– Voltage Dip 
– Single Point of Failure
– Short Circuit capability
– Replacing of oil switches and protection relays
– Future substation or equipment capabilityIEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
99
Long Range Plan Theories
• Long Range Plan Theories 
– Equipment Consolidation
– Equipment Modernization
– Equipment Maintainability
• Long term goal, add substations as new load 
dictates
– Existing study must show that limited existing capacity 
exists
– New load must be required
– Envision one substation per area
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
100
Goal of the Master Plan is to:
• Determine the strengths and weaknesses of 
existing system.
• Determine the load growth potential.
• Perform a reliability analysis.
• List recently completed projects.
• List identified problems from survey.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
101
Master plan should clearly 
• List code related issues.
• List grounding issues.
• List lighting issues.
• List area classification issues.
• List maintenance department and operator complaints, 
confirm these complaints.
• List bad actors.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
102
System Studies
• Can transmission system increases (larger transmission 
transformers) 
– bring more capacity to a distribution substation?
– Limitation is the switchgear bus
• Can the system utilization be improved through power 
factor correction?
• Can how the feeders are fed from the distribution 
substations be optimized to isolate outages?
• Can how the unit substations are fed from feeders be 
optimized to isolate outages?
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
103
Safety
• Entire system analyzed for shock and arc flash 
hazards.
• Problem areas are identified and corrected
– Equipment Replacement
– Settings Adjustments
– Other arc flash mitigation techniques
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
104
Spare Equipment
• Identify long lead items that have sufficient 
risk of failing that extended downtime could 
be avoided by having spare equipment onsite
– Transformers
– Breakers
– Etc.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
105
Improve Maintainability
Redundancy study of unit substations
• Insure A & B pumps are fed from different substation sources 
(Switchracks, and or MCC’s) at a minimum but ultimately different 
substations.
• Evaluate turn around schedule versus unit loads to ensure 
substations can be shut down for maintenance.
• Improve equipment maintenance through equipment design.
• i.e. Draw out breakers are easier to maintain than bolt‐in breakers.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
106
Equipment Consolidation
• Evaluate equipment and proposed projects 
keeping in mind the goal of equipment 
consolidation
• I.e. instead of multiple smaller switchracks or 
MCC ‘s or buildings, consolidate like 
equipment into larger buildings (Power 
Control Rooms).
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
107
Modernize Old Equipment
• Equipment Replacement
– Old equipment that can not meet existing 
standards or be modernized should be replaced.
– Cable Busses
– Old Switchracks
– Obsolete equipment should be replaced
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
108
Modernize equipment
• Add new relays, breakers, etc. to equipment 
that the core is still functional but better 
technology exists for components.
– Relay replacement projects
– Breaker replacement projects
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
109
Not everything is the same.
• One facilities bad actor may not be an issue at another 
refinery/petro‐chemical facility.
• Oil switches might fail for a variety of reasons, 
• PILC cable with pot heads connect to the oil switch, might 
have issues.
• SF6 might work better in colder climates.
• Some maintenance crews love PILC, others hate it and want 
it all out of the ground.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
110
Refinery/petro‐chemical engineers and 
managers need to know the following:
• What are the lessons learned for refinery/petro‐chemical engineers and 
managers when dealing with SIS systems or a lack of a good SIS system in 
place? 
– Complexity of operations and the pressure to control the number of operators 
makes it more and more important to have a reliable SIS.
• What are the lessons learned for refinery/petro‐chemical engineers and 
managers when dealing with electrical distribution systems or a lack of a 
good redundant electrical distribution system in place? 
– Relief scenarios involving electrical distribution faults are complex and can be 
worst case.
• In your opinion what do refinery/petro‐chemical engineers and managers 
need to know about master planning and making a petrochemical system 
safe and reliable? 
– PHA/LOPA should be extended to involve electrical distribution faults.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
111
Understand the Power Requirements
• Total Connected Load 
• Running Load
– Rule of thumb in industrial facilities 90% of load 
rotating and 10% of load static.
• Utility Required Power Factor
• Utility Required Harmonic Distortion 
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
112
Understand the Utility Connection
• Voltage Level Available from the Utility
• Utility Requirements for Connection
– Most utilities have documents with their 
requirements for connection
– The utility will normally want to approve the one 
line and layout.
– Utility may require some space and equipment 
inside the substation for metering.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
113
Understand the Internal Electrical 
Distribution
• Routing Power Cables in the Facility
– Cable Tray
– Duct Bank
– Air Insulated Conductors
• Unit Substation Size
– 25‐MVA max for 15‐kV
– 15‐MVA max for 5‐kV
– 2.5‐MVA max for 480‐V
• Unit Substation Voltage Levels
– 15‐kV
• 7.5‐kV
– 5‐kV
• 2400‐V
– 480‐V
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
114
Understand your Unit Substation 
Equipment
• Power Center
• Transformers
• Switchgear
• Motor Controllers
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
115
Understand the Power Centers
• Locating
– Classified Area
– Blast Zone
• Prefab
– Elevation
– Shipping Issues
• Site Built
– Building Penetrations
– Equipment Access
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
116
Understand the Transformers
• Transformer Sizing
– Connected Load
– Running Load
• Transformer Impedance
– Short Circuit
– Arc Flash
• Transformer Grounding
– High Resistance Grounding
• 5‐kV
• 2400‐V
• 480‐V
– Low Resistance Grounding
• 15‐kV
• 27‐kV
• 38‐kV
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
117
Understand Your Switchgear
• Medium Voltage (38‐kV, 27‐kV, 15‐kV, 5‐kV)
– Metal Clad
– Arc‐Resistant
– Nema 3R
– Shelter Form
• Low Voltage (600‐V)
– Metal Enclosed
– Arc‐Resistant
– Nema 3R
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
118
Understand Your Motor Control 
Centers (MCC)
• Medium Voltage (5‐kV only)
– Metal Enclosed
– Arc Resistant
– Nema 3R (Outdoor)
• Low Voltage
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
119
Understand the Electrical Loads
• Motors
– Pump
– Compressors
– Fans
• Variable Frequency Drives
• Other Loads
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
120
Understand Your Motors
• Motors
– Medium Voltage Motors
• Induction 
• Synchronous
– Low Voltage Motors
• <250‐hp
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
121
Understand Your Substation 
Configuration
• Radial
• Primary Selective
• Double Ended
– Tie Open
– Tie Closed
• Other Variations
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
122
Questions?
• Vincent W. Wedelich *P.E. MBA
• vwedelich@burnsmcd.com
• 832‐214‐2804 main
• 832‐932‐9236 cell
• *licensed professional engineer in Texas.
IEEE/AiChE Joint Presentation April 9, 2015 
Rev. 0 For Educational, Safety, and Process 
Improvement Purposes Only
123

Weitere ähnliche Inhalte

Andere mochten auch

Tracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmTracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmVincent Wedelich, PE MBA
 
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAPERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAVincent Wedelich, PE MBA
 
Catastrophic Engineering Failure
Catastrophic Engineering FailureCatastrophic Engineering Failure
Catastrophic Engineering FailureLiving Online
 
Ieee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsIeee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsVincent Wedelich, PE MBA
 
Electrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersElectrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersVincent Wedelich, PE MBA
 
Affordable automobile for low income families
Affordable automobile for low income families Affordable automobile for low income families
Affordable automobile for low income families Vincent Wedelich, PE MBA
 

Andere mochten auch (20)

Tracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmTracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmm
 
Understanding power concepts rev 0
Understanding power concepts rev 0Understanding power concepts rev 0
Understanding power concepts rev 0
 
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAPERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
 
MANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPTMANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPT
 
American barrick vww
American barrick vwwAmerican barrick vww
American barrick vww
 
Catastrophic Engineering Failure
Catastrophic Engineering FailureCatastrophic Engineering Failure
Catastrophic Engineering Failure
 
Area classification
Area classification Area classification
Area classification
 
2012 ieee pes lunch ethics 020112
2012 ieee pes lunch ethics 0201122012 ieee pes lunch ethics 020112
2012 ieee pes lunch ethics 020112
 
Ieee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systemsIeee transfer schemes for M-T-M distribution systems
Ieee transfer schemes for M-T-M distribution systems
 
Ieee power quality distribution systems
Ieee power quality distribution systemsIeee power quality distribution systems
Ieee power quality distribution systems
 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
 
Good to great ppt (vww)
Good to great ppt (vww)Good to great ppt (vww)
Good to great ppt (vww)
 
Area classification
Area classification Area classification
Area classification
 
MANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPTMANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPT
 
Electrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersElectrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managers
 
Solar skin
Solar skinSolar skin
Solar skin
 
Affordable automobile for low income families
Affordable automobile for low income families Affordable automobile for low income families
Affordable automobile for low income families
 
IEEE Motor Presentation
IEEE Motor PresentationIEEE Motor Presentation
IEEE Motor Presentation
 
THE PROFIT CHAIN
THE PROFIT CHAINTHE PROFIT CHAIN
THE PROFIT CHAIN
 
Executive compensation main ppt
Executive compensation main pptExecutive compensation main ppt
Executive compensation main ppt
 

Ähnlich wie Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilities) will maximize profits if they develop a zero policy.

Performance Attributes of Secondary Window Systems
Performance Attributes of Secondary Window SystemsPerformance Attributes of Secondary Window Systems
Performance Attributes of Secondary Window SystemsThermolite Window Systems
 
Resume for Management position 14-05-15
Resume for Management position 14-05-15Resume for Management position 14-05-15
Resume for Management position 14-05-15John Barnett
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
 
Cameron Jefferies CV Aug_2015
Cameron Jefferies CV Aug_2015Cameron Jefferies CV Aug_2015
Cameron Jefferies CV Aug_2015Cameron Jefferies
 
Josh Resume 11_18_2016
Josh Resume 11_18_2016Josh Resume 11_18_2016
Josh Resume 11_18_2016Smith Joshua
 
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011Pulse webinar: Energy Managers, Carve out Your Niche, June 2011
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011Pulse Energy
 
CV - David Kime - January 16_1
CV - David Kime - January 16_1CV - David Kime - January 16_1
CV - David Kime - January 16_1David Kime
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsScottMadden, Inc.
 
AEC - Extended Profile
AEC - Extended ProfileAEC - Extended Profile
AEC - Extended ProfileRicky Huyser
 
Steve Allan Sept2016
Steve Allan Sept2016  Steve Allan Sept2016
Steve Allan Sept2016 Steve Allan
 
CV - SEISMIC BISWAS -new - Copy
CV - SEISMIC BISWAS -new - CopyCV - SEISMIC BISWAS -new - Copy
CV - SEISMIC BISWAS -new - CopySeismic Biswas
 
Curriculum Vitae 2015
Curriculum Vitae 2015Curriculum Vitae 2015
Curriculum Vitae 2015James Ellams
 
Haison Company
Haison CompanyHaison Company
Haison Companyhaison
 
John Hopwood Resume
John Hopwood ResumeJohn Hopwood Resume
John Hopwood ResumeJohn Hopwood
 
August 2010 - Michigan Energy Forum - Jay Murdoch
August 2010 - Michigan Energy Forum - Jay MurdochAugust 2010 - Michigan Energy Forum - Jay Murdoch
August 2010 - Michigan Energy Forum - Jay MurdochAnnArborSPARK
 

Ähnlich wie Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilities) will maximize profits if they develop a zero policy. (20)

Jai Townsend - CV
Jai Townsend - CVJai Townsend - CV
Jai Townsend - CV
 
Performance Attributes of Secondary Window Systems
Performance Attributes of Secondary Window SystemsPerformance Attributes of Secondary Window Systems
Performance Attributes of Secondary Window Systems
 
Resume for Management position 14-05-15
Resume for Management position 14-05-15Resume for Management position 14-05-15
Resume for Management position 14-05-15
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
Cameron Jefferies CV Aug_2015
Cameron Jefferies CV Aug_2015Cameron Jefferies CV Aug_2015
Cameron Jefferies CV Aug_2015
 
C.V
C.VC.V
C.V
 
Josh Resume 11_18_2016
Josh Resume 11_18_2016Josh Resume 11_18_2016
Josh Resume 11_18_2016
 
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011Pulse webinar: Energy Managers, Carve out Your Niche, June 2011
Pulse webinar: Energy Managers, Carve out Your Niche, June 2011
 
Project Vietnam
Project VietnamProject Vietnam
Project Vietnam
 
CV - David Kime - January 16_1
CV - David Kime - January 16_1CV - David Kime - January 16_1
CV - David Kime - January 16_1
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
RSRynkiewicz2015r
RSRynkiewicz2015rRSRynkiewicz2015r
RSRynkiewicz2015r
 
AEC - Extended Profile
AEC - Extended ProfileAEC - Extended Profile
AEC - Extended Profile
 
Steve Allan Sept2016
Steve Allan Sept2016  Steve Allan Sept2016
Steve Allan Sept2016
 
CV - SEISMIC BISWAS -new - Copy
CV - SEISMIC BISWAS -new - CopyCV - SEISMIC BISWAS -new - Copy
CV - SEISMIC BISWAS -new - Copy
 
Curriculum Vitae 2015
Curriculum Vitae 2015Curriculum Vitae 2015
Curriculum Vitae 2015
 
Haison Company
Haison CompanyHaison Company
Haison Company
 
David Walker CV+
David Walker CV+David Walker CV+
David Walker CV+
 
John Hopwood Resume
John Hopwood ResumeJohn Hopwood Resume
John Hopwood Resume
 
August 2010 - Michigan Energy Forum - Jay Murdoch
August 2010 - Michigan Energy Forum - Jay MurdochAugust 2010 - Michigan Energy Forum - Jay Murdoch
August 2010 - Michigan Energy Forum - Jay Murdoch
 

Mehr von Vincent Wedelich, PE MBA (14)

Part 3 motor application considerations understanding power concepts rev 5 vi...
Part 3 motor application considerations understanding power concepts rev 5 vi...Part 3 motor application considerations understanding power concepts rev 5 vi...
Part 3 motor application considerations understanding power concepts rev 5 vi...
 
Amerada hess final presentation
Amerada hess final presentationAmerada hess final presentation
Amerada hess final presentation
 
Balanced scorecard presentation rev 0
Balanced scorecard presentation rev 0Balanced scorecard presentation rev 0
Balanced scorecard presentation rev 0
 
Frontier corporation
Frontier corporationFrontier corporation
Frontier corporation
 
Financial Derivatives and Options
Financial Derivatives and OptionsFinancial Derivatives and Options
Financial Derivatives and Options
 
Iceland krona vincent wedelich
Iceland krona vincent wedelichIceland krona vincent wedelich
Iceland krona vincent wedelich
 
Tracking firm presentation (vincent wedelich) mmm 3M
Tracking firm presentation (vincent wedelich) mmm 3MTracking firm presentation (vincent wedelich) mmm 3M
Tracking firm presentation (vincent wedelich) mmm 3M
 
capacitors
capacitorscapacitors
capacitors
 
Electrical condition monitoring part 2
Electrical condition monitoring part 2Electrical condition monitoring part 2
Electrical condition monitoring part 2
 
IEEE substation design
IEEE substation designIEEE substation design
IEEE substation design
 
Overcurrent coordination
Overcurrent coordinationOvercurrent coordination
Overcurrent coordination
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
Improving substation reliability & availability
Improving substation reliability & availability Improving substation reliability & availability
Improving substation reliability & availability
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
 

Kürzlich hochgeladen

RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...lizamodels9
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876dlhescort
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Sheetaleventcompany
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000dlhescort
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 

Kürzlich hochgeladen (20)

RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 

Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilities) will maximize profits if they develop a zero policy.