GDAS PM Professions:
PMP Study Group
                                          Session #4: Scope Management




Monique Howard
September 25, 2008

© 2005 Hewlett-Packard Development Company, L.P.
The information contained herein is subject to change without notice
Agenda
•   Scope Management
•   Open Forum: Participant Questions
•   Study Group Questions
•   Wrap Up
Scope Management
•   Means constantly checking to make sure you are
    completing all the work
•   Means not letting people randomly add to the
    scope of the project without a structured change
    control system
•   Means making sure all changes fit within the
    project charter
•   Means defining and controlling what is and is not
    included in the project
•   Means preventing extra work or gold plating
Scope Management
•   Know the difference between product and project scope
     − Product Scope: requirements that relate to the product of the project
     − Project Scope: the work you need to do to deliver the product of the project
•   Scope Planning
     − Scope Management Plan: how scope will be planned, executed and controlled
•   Scope Definition: primary concerned with what is and not included in the project
     − Output: Project Scope Statement (living document throughout the life of the project)
•   Create WBS
     − The WBS is deliverable oriented and breaks the project into smaller more manageable pieces
     − Decomposition: The work is decomposed into smaller pieces called work packages. Work
       packages are divided further into schedule activities. Work packages are assigned to
       individuals or parts of the performing organization.
     − The level higher than a work package is called the control account. This is the level where cost
       can be estimated
     − Output: WBS, WBS Dictionary, Scope Baseline
•   Scope Verification
     − the act of checking the work against the project management plan, WBS and WBS dictionary,
       and meeting with the customers to gain formal acceptance of deliverables
     − Can be done at the end of each project phase and during monitoring and controlling
     − Scope Verification and Quality Control can overlap
     − Both are similar in that both involve checking for the correctness of work
     − However, the primary focus of scope verification is customer acceptance of the deliverables
       while quality control involves meeting the quality requirements specified for the deliverables
       Performed whenever a project is terminated to verify the level of completion
•   Scope Control
Open Forum: Participant Questions



  If you have a question, raise your hand
1.    When you started creating a Work Breakdown Structure for your project, you soon
     realized that it was too complicated to be done on a single piece of paper. You then
     started using a Work Breakdown Structure numbering system to

      A.   Determine the complexity of the project
      B.   Determine the level at which individual WBS elements are found
      C.   Help in automating the WBS using appropriate software
      D.   Present justification for the project
1.    When you started creating a Work Breakdown Structure for your project, you soon
     realized that it was too complicated to be done on a single piece of paper. You then
     started using a Work Breakdown Structure numbering system to

      A.   Determine the complexity of the project
      B.   Determine the level at which individual WBS elements are found
      C.   Help in automating the WBS using appropriate software
      D.   Present justification for the project



Correct Choice: B
Justification:     Each WBS component, including work packages and control accounts within a
WBS, is generally assigned a unique identifier from a code of accounts. These identifiers provide a
structure for hierarchical summation of costs, schedule and resource information.

Reference: PMBOK Third Edition, Page Number: 117

pmstudy.com comments: The items at the lowest level of the WBS may be referred to as work
packages, especially in organizations that follow earned value management practices. These work
packages may, in turn, be further decomposed in a subproject work breakdown structure. WBS
numbering system determines the level at which individual WBS elements are found
2. Your project involves manufacturing high-precision engine subassemblies for the
    shipping industry. You have to perform several activities such as measuring,
    examining, and verifying to determine whether work and deliverables meet
    requirements and product acceptance criteria. You would have to do several
    reviews, product reviews, audits and walkthroughs. These activities are carried out
    in which process?

    A.   Scope Verification
    B.   Quality Inspection
    C.   Scope Planning
    D.   Change Control Process
2. Your project involves manufacturing high-precision engine subassemblies for the
    shipping industry. You have to perform several activities such as measuring,
    examining, and verifying to determine whether work and deliverables meet
    requirements and product acceptance criteria. You would have to do several
    reviews, product reviews, audits and walkthroughs. These activities are carried out
    in which process?

     A.   Scope Verification
     B.   Quality Inspection
     C.   Scope Planning
     D.   Change Control Process


Correct Choice: A
Justification:     Inspection(which is a Tool for Scope Verification) includes activities such as
measuring, examining and testing undertaken to determine whether results conform to
requirements. Inspections are variously called reviews, product reviews, audits and walk-throughs.

Reference: PMBOK Third Edition, Page Number: 119
3. Your project involves manufacturing high-precision engine subassemblies for the
    shipping industry. You have to perform several activities such as measuring,
    examining, and verifying to determine whether work and deliverables meet
    requirements and product acceptance criteria. You would have to do several reviews,
    product reviews, audits and walkthroughs. These activities are carried out in which
    process?

    A.   Scope Verification
    B.   Quality Inspection
    C.   Scope Planning
    D.   Change Control Process
3. Your project involves manufacturing high-precision engine subassemblies for the
    shipping industry. You have to perform several activities such as measuring,
    examining, and verifying to determine whether work and deliverables meet
    requirements and product acceptance criteria. You would have to do several reviews,
    product reviews, audits and walkthroughs. These activities are carried out in which
    process?

     A.   Scope Verification
     B.   Quality Inspection
     C.   Scope Planning
     D.   Change Control Process

Correct Choice:     A  
Justification:     Inspection(which is a Tool for Scope Verification) includes activities such as
measuring, examining and testing undertaken to determine whether results conform to requirements.
Inspections are variously called reviews, product reviews, audits and walk-throughs.

Reference: PMBOK Third Edition, Page Number: 119
4. As a project manager, you are responsible for managing changes to the project scope. If
    during the end of the project, a customer wants to make a major change to the scope of
    work, you should:

    A.   Reject the change
    B.   Make the required change
    C.   Escalate to senior management
    D.   Let the customer know about the impact of the change
4. As a project manager, you are responsible for managing changes to the project scope. If
    during the end of the project, a customer wants to make a major change to the scope of
    work, you should:

    A.   Reject the change
    B.   Make the required change
    C.   Escalate to senior management
    D.   Let the customer know about the impact of the change



 Correct Choice:     D  
 Justification:      If there is a major change to the project, the Project Manager should try to
 influence the change to minimize the impact on the project. Usually the project manager is advised
 to do the following:

 1. Evaluate the impact of the change within the team
 2. Let the customer(or person requesting the change) know about the impact of the change
 3. If changes are required, then open a change control and get it approved - definitely inform the
 management and the change control board about the impact of the changes
 4. If changes are approved by the change control board, then make the appropriate changes in the
 project plan

 Reference: pmstudy.com notes as mentioned above
5. In your project, you use product analysis to translate project objectives into tangible
    deliverables and requirements. All the following tools are used for product analysis
    EXCEPT:

     A.   Value Engineering
     B.   Value Analysis
     C.   Product Breakdown
     D.   Benefit/Cost Analysis
5. In your project, you use product analysis to translate project objectives into tangible
    deliverables and requirements. All the following tools are used for product analysis
    EXCEPT:

     A.   Value Engineering
     B.   Value Analysis
     C.   Product Breakdown
     D.   Benefit/Cost Analysis


Correct Choice:    D  
Justification:     Product analysis includes techniques such as product breakdown, systems analysis,
systems engineering, value engineering, value analysis and functional analysis.

Reference: PMBOK Third Edition , Page Number: 110
6. You recently joined as the project manager of ABC Company. The outgoing project manager
    mentioned that of late, she had been facing several issues with new change requests. The
    customers were located in the same office and they interacted directly with the project team and, at
    times, informally asked for some changes in the project`s product. If the changes were small, the
    project team members usually agreed to do the changes. The project manager found it difficult to
    prioritize activities and ensure that tasks are done as per schedule. The project had 50 team
    members and there was some discontent amongst them about the work they were supposed to do.

    What should be your first priority in this project? 

     A.   Create a detailed project scope statement
     B.   Align the project objectives with the organizational goals
     C.   Ensure proper project scope control
     D.   Call a meeting of all the project stakeholders to determine and resolve any outstanding issues
6. You recently joined as the project manager of ABC Company. The outgoing project manager
     mentioned that of late, she had been facing several issues with new change requests. The
     customers were located in the same office and they interacted directly with the project team and, at
     times, informally asked for some changes in the project`s product. If the changes were small, the
     project team members usually agreed to do the changes. The project manager found it difficult to
     prioritize activities and ensure that tasks are done as per schedule. The project had 50 team
     members and there was some discontent amongst them about the work they were supposed to do.

     What should be your first priority in this project? 

       A.   Create a detailed project scope statement
       B.   Align the project objectives with the organizational goals
       C.   Ensure proper project scope control
       D.   Call a meeting of all the project stakeholders to determine and resolve any outstanding issues


Correct Choice:   C  
Justification:     Project scope control is concerned with influencing the factors that create project scope changes and
controlling the impact of those changes. Scope control assures that all requested changes and recommended
corrective actions are processed through the project integrated change control process. Project scope control is also
used to manage the actual changes when they occur and is integrated with the other control processes. Uncontrolled
changes are often referred to as project scope creep.

Reference: PMBOK Third Edition Page 119

pmstudy notes: Option 1: The project scope statement should already be prepared since the project is in execution
stage. Option 2: Aligning the project objectives with the organizational goals happens in initial stages of the project
i.e. when the project charter is being created. Option 3: This is the correct answer. Usually, if there is no proper
project scope control, there might be scope creep, reprioritization of activities and discontent among team members
who do not know what each person is supposed to do. Option 4: Calling a meeting will not resolve the outstanding
issues related to scope creep and not having proper project scope control
7. A project was terminated early because of funding related issues. The project
    manager met the customer to establish and document the level and extent of project
    completion. What tool should be used for the purpose?

    A.   Performance Measurement
    B.   Scope Change Control System
    C.   Inspection
    D.   Earned Value
7. A project was terminated early because of funding related issues. The project
    manager met the customer to establish and document the level and extent of project
    completion. What tool should be used for the purpose?

     A.   Performance Measurement
     B.   Scope Change Control System
     C.   Inspection
     D.   Earned Value


Correct Choice:     C  
Justification:     Scope Verification:... If the project is terminated early, the project scope verification
process should establish and document the level and extent of completion. A tool used for project
scope verification is "Inspection". Also, please refer to Figure 5-9

Reference: PMBOK Third Edition, Page Number: 118
8. As a project manager, you are creating a document that describes the conditions or
    capabilities that must be possessed by the deliverables of the project to satisfy a
    contract, standard, specification, or other formally imposed documents. This
    document will also be referred to as:

     A.   Product scope description
     B.   Project requirements
     C.   Product acceptance criteria
     D.   Project objectives
8. As a project manager, you are creating a document that describes the conditions or
    capabilities that must be possessed by the deliverables of the project to satisfy a
    contract, standard, specification, or other formally imposed documents. This
    document will also be referred to as:

     A.   Product scope description
     B.   Project requirements
     C.   Product acceptance criteria
     D.   Project objectives


Correct Choice:     B  
Justification:     Project Requirements: Describes the conditions or capabilities that must be met
or possessed by the deliverables of the project to satisfy a contract, standard, specification, or
other formally imposed documents.

Reference: PMBOK Third Edition, Page Number: 111
9. Your management is evaluating a project which requires an investment of $ 500,000.
    The expected inflow is $ 100,000 for the first year, and $ 300,000 for every year after
    that. What is the payback period?

     A.   2 years
     B.   2 years, 4 months
     C.   3 years
     D.   Cannot be determined because discount rate is not specified
9. Your management is evaluating a project which requires an investment of $ 500,000.
    The expected inflow is $ 100,000 for the first year, and $ 300,000 for every year after
    that. What is the payback period?

     A.   2 years
     B.   2 years, 4 months
     C.   3 years
     D.   Cannot be determined because discount rate is not specified


Correct Choice:     B  
Justification:     Payback Period = Number of years required for an organization to recapture an initial investment

=$ 100,000 (1 year) + $ 300,000(2nd year) + $ 100,000(4 months, 3rd year)
=$500,000
So, payback period = 2 years, 4 months

Reference: pmstudy.com notes as mentioned above
10. You are the project manager for an initiative aimed at releasing a new product in
    the market. But because of government regulations, you will have to make some
    changes to the project scope and the WBS. Any approved modifications to the
    contents of the scope statement should be done through:

     A.   Scope Management Plan Updates
     B.   Work Breakdown Structure
     C.   Project Plan
     D.   Project Charter
10. You are the project manager for an initiative aimed at releasing a new product in
    the market. But because of government regulations, you will have to make some
    changes to the project scope and the WBS. Any approved modifications to the
    contents of the scope statement should be done through:

     A.   Scope Management Plan Updates
     B.   Work Breakdown Structure
     C.   Project Plan
     D.   Project Charter


Correct Choice:     A 
Justification:     Project Scope Management Plan (updates) : If approved change requests result from
the Create WBS process, then the project scope management plan may need to be updated to include
approved changes.

Reference: PMBOK Third Edition, Page Number: 118
11. Your project is very critical for the company and must be completed within six
    months. The project charter has been signed, but the scope statement is not yet
    prepared. The management asks you to go ahead with the project without the scope
    statement being approved. What should you do? (SELECT THE BEST ANSWER)

    A. Refuse to work on the project because the management is not following standard
       project management practices
    B. Since time is of essence, you should start the project with inputs from the project
       charter
    C. Meet the management and mention the problems you will face without a scope
       statement
    D. Escalate the issue to the project sponsor and issue a risk memo
11. Your project is very critical for the company and must be completed within six
    months. The project charter has been signed, but the scope statement is not yet
    prepared. The management asks you to go ahead with the project without the scope
    statement being approved. What should you do? (SELECT THE BEST ANSWER)

      A. Refuse to work on the project because the management is not following standard
         project management practices
      B. Since time is of essence, you should start the project with inputs from the project
         charter
      C. Meet the management and mention the problems you will face without a scope
         statement
      D. Escalate the issue to the project sponsor and issue a risk memo

Correct Choice:     C  
Justification:     Without the scope statement, you do not have a good understanding of the
project justification, product, project deliverables and project objectives. Without completing the
scope statement, you do not have all the inputs for the scope definition and for the creation of
Work Breakdown Structure. So, the best option is to talk to the management about the problems
faced if there is no scope statement. So, Choice 3 is the "BEST AVAILABLE ALTERNATIVE"

* Choice 1 is an extreme step and is not recommended
* Choice 2 will cause problems e.g. you will not be able to create a WBS without a list of
deliverables which is available in the scope statement.
* Choice 4 is an extreme measure and is not recommended

Reference: pmstudy.com notes as mentioned above
12. In your project, you are now interested in determining the cause of variance
    relative to the scope baseline and deciding whether corrective action is required.
    You should use:

     A.   Configuration Management System
     B.   Variance Analysis
     C.   Replanning
     D.   Earned Value Spreadsheets
12. In your project, you are now interested in determining the cause of variance
     relative to the scope baseline and deciding whether corrective action is required.
     You should use:

      A.   Configuration Management System
      B.   Variance Analysis
      C.   Replanning
      D.   Earned Value Spreadsheets



Correct Choice:     B  
Justification:     Variance Analysis: Project performance measurements are used to assess the
magnitude of variation. Important aspects of project scope control include determining the cause of
variance relative to the scope baseline and deciding whether corrective action is required.

Reference: PMBOK Third Edition, Page Number: 121
13. Your company is going through a financial crisis and has set a pre-defined budget to
    work with. For your project, a pre-defined budget will become a:

    A.   Risk
    B.   Assumption
    C.   Constraint
    D.   Stage point
13. Your company is going through a financial crisis and has set a pre-defined budget to
    work with. For your project, a pre-defined budget will become a:

    A.   Risk
    B.   Assumption
    C.   Constraint
    D.   Stage point



 Correct Choice:     C  
 Justification:     Project Constraints: ... a predefined budget or any imposed dates (schedule
 milestones) that are issued by the customer or performing organization

 Reference: PMBOK Third Edition, Page Number: 111
14. You are explaining the importance of Work Breakdown Structure (WBS) to your project
    team members. In this context, all the following statements about Work Breakdown
    Structure(WBS) are correct EXCEPT:

    A. It is a hierarchical decomposition of work
    B. Planned work contained in the lowest level WBS components are also called WBS
       dictionaries
    C. WBS subdivides the project work into smaller, more manageable pieces of work
    D. WBS organizes and defines the total scope of work of the project
14. You are explaining the importance of Work Breakdown Structure (WBS) to your project
    team members. In this context, all the following statements about Work Breakdown
    Structure(WBS) are correct EXCEPT:

    A. It is a hierarchical decomposition of work
    B. Planned work contained in the lowest level WBS components are also called WBS
       dictionaries
    C. WBS subdivides the project work into smaller, more manageable pieces of work
    D. WBS organizes and defines the total scope of work of the project



  Correct Choice:     B  
  Justification:     The planned work contained within the lowest-level WBS components, which
  are also called work packages, can be scheduled, cost-estimated, monitored and controlled.

  Reference: PMBOK Third Edition, Page Number: 112
15. Scope Verification is the process of obtaining stakeholder`s formal acceptance of
    the completed project scope and associated deliverables. In this context, which
    statement related to Scope Verification is correct?

    A. Scope Verification is similar to Quality Control.
    B. Quality Control is generally performed before Scope Verification, but these two
       processes may also be done in parallel.
    C. Scope Verification indicates the end of a project.
    D. Scope Verification is the final sign-off from the sponsor and customer.
15. Scope Verification is the process of obtaining stakeholder`s formal acceptance of
    the completed project scope and associated deliverables. In this context, which
    statement related to Scope Verification is correct?

    A. Scope Verification is similar to Quality Control.
    B. Quality Control is generally performed before Scope Verification, but these two
       processes may also be done in parallel.
    C. Scope Verification indicates the end of a project.
    D. Scope Verification is the final sign-off from the sponsor and customer.


Correct Choice:     B  
Justification:     Quality Control is generally performed before Scope Verification, but these
two processes can be performed in parallel

Reference: PMBOK Third Edition, Page Number: 118
16. One of your tasks as a project manager is to prepare a Scope Statement for your
    project. The scope statement provides:

    A. Authorization to the project manager for using organizational resources for
       project activities.
    B. Documentation of how the project scope will be managed and how scope
       changes will be integrated into the project.
    C. Definition for Work Breakdown structure
    D. A documented basis for making future project decisions and for confirming
       or developing a common understanding of the project scope among the
       stakeholders.
16. One of your tasks as a project manager is to prepare a Scope Statement for your
    project. The scope statement provides:

     A. Authorization to the project manager for using organizational resources for
        project activities.
     B. Documentation of how the project scope will be managed and how scope
        changes will be integrated into the project.
     C. Definition for Work Breakdown structure
     D. A documented basis for making future project decisions and for confirming
        or developing a common understanding of the project scope among the
        stakeholders.


Correct Choice:     D  
Justification:     Project Scope Statement: ... provides a documented basis for making future
decisions or developing a common understanding of the project scope among the stakeholders.

Reference: PMBOK Third Edition, Page Number: 370
17. Your company is constructing a dam and your project (which is being performed
    under a contract) mandates that you should be paying compensation to any
    person displaced because of the project. What kind of constraint is this?

    A.   Social
    B.   Legal
    C.   Environmental
    D.   Humanitarian
17. Your company is constructing a dam and your project (which is being performed
    under a contract) mandates that you should be paying compensation to any
    person displaced because of the project. What kind of constraint is this?

    A.   Social
    B.   Legal
    C.   Environmental
    D.   Humanitarian


Correct Choice:     B  
Justification:     When a project is performed under a contract, contractual provisions
will generally be constraints.

Reference: PMBOK Third Edition, Page Number: 111

pmstudy.com comments: Anything done under a contract becomes a legal constraint
18. Generally accepted methods for translating project objectives into tangible
    deliverables and requirements are also referred to as:

     A.   Product Analysis
     B.   Risk Measurement
     C.   Alternatives Identification
     D.   Benefit/Cost Analysis
18. Generally accepted methods for translating project objectives into tangible
    deliverables and requirements are also referred to as:

     A.   Product Analysis
     B.   Risk Measurement
     C.   Alternatives Identification
     D.   Benefit/Cost Analysis


Correct Choice:     A  
Justification:     Product Analysis: Each application area has one or more generally accepted
methods for translating project objectives into tangible deliverables and requirements.

Reference: PMBOK Third Edition, Page Number: 110
19. You have created a WBS Dictionary which you can use to: 

    A. Verify that the deliverables being produced and accepted are included in the
       approved project scope
    B. Determine whether work and deliverables meet requirements and product
       acceptance criteria
    C. Influence the factors that create project scope changes and control the impact of
       those changes
    D. Get acceptance of the project scope from the customer
19. You have created a WBS Dictionary which you can use to: 

     A. Verify that the deliverables being produced and accepted are included in the
        approved project scope
     B. Determine whether work and deliverables meet requirements and product
        acceptance criteria
     C. Influence the factors that create project scope changes and control the impact of
        those changes
     D. Get acceptance of the project scope from the customer


Correct Choice:     A  
Justification:     The WBS Dictionary is a component of the detailed project scope definition, and is
used to verify that the deliverables being produced and accepted are included in the approved
project scope.

Reference: PMBOK Third Edition, Page Number: 118
20. Decomposition is the subdivision of project deliverables into smaller, more
    manageable components until the work and deliverables are defined at the work
    package level. This is a valuable tool for Scope Definition. However,
    decomposition may not be possible for a deliverable or subproject if:

    A. The deliverable or subproject is very complicated
    B. The deliverable or subproject is already being produced
    C. The deliverable or subproject will be accomplished after a very long time (i.e.
       far into the future)
    D. None of the above : Decomposition of deliverables is always possible
20. Decomposition is the subdivision of project deliverables into smaller, more
    manageable components until the work and deliverables are defined at the work
    package level. This is a valuable tool for Scope Definition. However,
    decomposition may not be possible for a deliverable or subproject if:

    A. The deliverable or subproject is very complicated
    B. The deliverable or subproject is already being produced
    C. The deliverable or subproject will be accomplished after a very long time (i.e.
       far into the future)
    D. None of the above : Decomposition of deliverables is always possible


 Correct Choice:     C  
 Justification:     Decomposition may not be possible for a deliverable or subproject that will
 be accomplished far into the future.

 Reference: PMBOK Third Edition, Page Number: 114
21. As a project manager, you must formalize acceptance of the project scope and keep
    the project focused on the business need that it was undertaken to address. This
    should be done:

    A.   At the beginning of the project
    B.   At the end of the project
    C.   When required by the business sponsor
    D.   After each phase of the project
21. As a project manager, you must formalize acceptance of the project scope and keep
    the project focused on the business need that it was undertaken to address. This
    should be done:

    A.   At the beginning of the project
    B.   At the end of the project
    C.   When required by the business sponsor
    D.   After each phase of the project


Correct Choice:     D  
Justification:     Scope verification deals with formalizing acceptance of the project scope. This
should be done at the end of each phase

Reference: pmstudy.com notes as mentioned above
22. You are the project manager for a software project responsible for creating a software
    tool for your finance department. Once the project is completed, maintenance of the
    product:

     A. Will not be part of the project life cycle
     B. Will be included in project life cycle because the same resources will be used for
        maintaining the product as those who developed the product.
     C. May be included in the project life cycle if determined by the management
     D. Will become another project
22. You are the project manager for a software project responsible for creating a software
    tool for your finance department. Once the project is completed, maintenance of the
    product:

     A. Will not be part of the project life cycle
     B. Will be included in project life cycle because the same resources will be used for
        maintaining the product as those who developed the product.
     C. May be included in the project life cycle if determined by the management
     D. Will become another project


Correct Choice:     A  
Justification:     Projects and operations differ primarily in that operations are ongoing and
repetitive, while projects are temporary and unique

Reference: PMBOK Third Edition, Page Number: 6

pmstudy.com comments: Maintenance is an ongoing activity and should never be part of any
project
Wrap Up
    Conference Number: 547-941-6414 or 866-547-8978
    Passcode: Leader – 844306338, Participant – 370670831

5     Time Management           October 9   2:00pm EST   Presenter:       https://
      (PMBOK Chapters 6)
                                                            www.rooms.hp.com/attend/default.aspx?key
                                                            =EHHS4NQJHR
                                                         Participant:     https://
                                                            www.rooms.hp.com/attend/default.aspx?key
                                                            =EP44BUX8KS

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Pmstudy exam 2
Pmstudy exam 2Pmstudy exam 2
Pmstudy exam 2
 
Risk 9-pm study project risk management-test
Risk 9-pm study project risk management-testRisk 9-pm study project risk management-test
Risk 9-pm study project risk management-test
 
Pmstudy exam_1
Pmstudy exam_1Pmstudy exam_1
Pmstudy exam_1
 
Pm study project risk management test
Pm study project  risk management testPm study project  risk management test
Pm study project risk management test
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quiz
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
Risk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbazRisk 0-risk-guide book for pmi-rmp by amer elbaz
Risk 0-risk-guide book for pmi-rmp by amer elbaz
 
Pmstudy exam 3
Pmstudy exam 3Pmstudy exam 3
Pmstudy exam 3
 
Pmp full mock test – 200 questions
Pmp full mock test – 200 questionsPmp full mock test – 200 questions
Pmp full mock test – 200 questions
 
Pmp test 04
Pmp test 04Pmp test 04
Pmp test 04
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
Risk 8- pm study question risk management
Risk 8- pm study question risk managementRisk 8- pm study question risk management
Risk 8- pm study question risk management
 
Risk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ansRisk 5 simplelearn-exam4-ans
Risk 5 simplelearn-exam4-ans
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
Pmp5
Pmp5Pmp5
Pmp5
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 

Andere mochten auch

Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Pmbok 4th edition chapter 12 - Project Procurement Management
Pmbok 4th edition   chapter 12 - Project Procurement ManagementPmbok 4th edition   chapter 12 - Project Procurement Management
Pmbok 4th edition chapter 12 - Project Procurement ManagementAhmad Maharma, PMP,RMP
 
Engineering economics
Engineering economicsEngineering economics
Engineering economicsDeepak Kumar
 
1 introduction to engineering economics
1  introduction to engineering economics1  introduction to engineering economics
1 introduction to engineering economicsMohsin Siddique
 

Andere mochten auch (20)

P project finance
P project financeP project finance
P project finance
 
4.contracting
4.contracting4.contracting
4.contracting
 
01 project management framework
01 project management framework01 project management framework
01 project management framework
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Pmp communication chapter 10
Pmp communication chapter 10Pmp communication chapter 10
Pmp communication chapter 10
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Pmp time chapter 6
Pmp time chapter 6Pmp time chapter 6
Pmp time chapter 6
 
Pmp quality chapter 8
Pmp quality chapter 8Pmp quality chapter 8
Pmp quality chapter 8
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Pmp risk chapter 11
Pmp risk chapter 11Pmp risk chapter 11
Pmp risk chapter 11
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Pmp procurement chapter 12
Pmp procurement chapter 12Pmp procurement chapter 12
Pmp procurement chapter 12
 
Pmp hr chapter 9
Pmp hr chapter 9Pmp hr chapter 9
Pmp hr chapter 9
 
Pmbok 4th edition chapter 12 - Project Procurement Management
Pmbok 4th edition   chapter 12 - Project Procurement ManagementPmbok 4th edition   chapter 12 - Project Procurement Management
Pmbok 4th edition chapter 12 - Project Procurement Management
 
Engineering economics
Engineering economicsEngineering economics
Engineering economics
 
1 introduction to engineering economics
1  introduction to engineering economics1  introduction to engineering economics
1 introduction to engineering economics
 
Kpi for product manager
Kpi for product managerKpi for product manager
Kpi for product manager
 

Ähnlich wie Session 4 gdas pmp study group presentation

2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1reddvise
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management examJamil Faraj , PMP
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management Qussay Karam
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementHisham Ali,PMP
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250rajat898
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.pptMehediHasan636262
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge AreaJoshua Render
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measuresPavan Kumar
 
4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequence4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequenceDaw Juguilon
 
Рынок труда
Рынок трудаРынок труда
Рынок трудаEvgeniya
 
MDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfMDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfamirashraf61
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackProject Management Solutions
 

Ähnlich wie Session 4 gdas pmp study group presentation (20)

2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
 
05 pmp scope management exam
05 pmp scope management exam05 pmp scope management exam
05 pmp scope management exam
 
Pm training day 3
Pm training   day 3Pm training   day 3
Pm training day 3
 
3 scope Management
3 scope Management 3 scope Management
3 scope Management
 
Pmp chapter(5) Scope Management
Pmp chapter(5) Scope ManagementPmp chapter(5) Scope Management
Pmp chapter(5) Scope Management
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
 
Lecture 3 Project Management.ppt
Lecture 3 Project Management.pptLecture 3 Project Management.ppt
Lecture 3 Project Management.ppt
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Project Scope Management Knowledge Area
Project Scope Management Knowledge AreaProject Scope Management Knowledge Area
Project Scope Management Knowledge Area
 
Project scope management
Project scope managementProject scope management
Project scope management
 
10 me667 chap6 performance measures
10 me667 chap6 performance measures10 me667 chap6 performance measures
10 me667 chap6 performance measures
 
4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequence4 defining scope, quality, responsibility, and activity sequence
4 defining scope, quality, responsibility, and activity sequence
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Ch05
Ch05Ch05
Ch05
 
Scope Management
Scope ManagementScope Management
Scope Management
 
Рынок труда
Рынок трудаРынок труда
Рынок труда
 
MDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdfMDP2206-2217-Lec2.pdf
MDP2206-2217-Lec2.pdf
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Is your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on trackIs your project not going well this will help you get it back on track
Is your project not going well this will help you get it back on track
 

Mehr von Tu Nguyen, PMP®,PMI-RMP® (20)

3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
Time cost-control
Time cost-controlTime cost-control
Time cost-control
 
Resources
ResourcesResources
Resources
 
Pert
PertPert
Pert
 
Organization
OrganizationOrganization
Organization
 
Ch 6 construction progress control
Ch 6 construction progress controlCh 6 construction progress control
Ch 6 construction progress control
 
Ch 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisalCh 4 cash flow and investment appraisal
Ch 4 cash flow and investment appraisal
 
Ch 3 contract strategy
Ch 3 contract strategyCh 3 contract strategy
Ch 3 contract strategy
 
Ch 2 planning and scheduling
Ch 2 planning and schedulingCh 2 planning and scheduling
Ch 2 planning and scheduling
 
Ch 1 organization of construction projects
Ch 1 organization of construction projectsCh 1 organization of construction projects
Ch 1 organization of construction projects
 

Session 4 gdas pmp study group presentation

  • 1. GDAS PM Professions: PMP Study Group Session #4: Scope Management Monique Howard September 25, 2008 © 2005 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice
  • 2. Agenda • Scope Management • Open Forum: Participant Questions • Study Group Questions • Wrap Up
  • 3. Scope Management • Means constantly checking to make sure you are completing all the work • Means not letting people randomly add to the scope of the project without a structured change control system • Means making sure all changes fit within the project charter • Means defining and controlling what is and is not included in the project • Means preventing extra work or gold plating
  • 4. Scope Management • Know the difference between product and project scope − Product Scope: requirements that relate to the product of the project − Project Scope: the work you need to do to deliver the product of the project • Scope Planning − Scope Management Plan: how scope will be planned, executed and controlled • Scope Definition: primary concerned with what is and not included in the project − Output: Project Scope Statement (living document throughout the life of the project) • Create WBS − The WBS is deliverable oriented and breaks the project into smaller more manageable pieces − Decomposition: The work is decomposed into smaller pieces called work packages. Work packages are divided further into schedule activities. Work packages are assigned to individuals or parts of the performing organization. − The level higher than a work package is called the control account. This is the level where cost can be estimated − Output: WBS, WBS Dictionary, Scope Baseline • Scope Verification − the act of checking the work against the project management plan, WBS and WBS dictionary, and meeting with the customers to gain formal acceptance of deliverables − Can be done at the end of each project phase and during monitoring and controlling − Scope Verification and Quality Control can overlap − Both are similar in that both involve checking for the correctness of work − However, the primary focus of scope verification is customer acceptance of the deliverables while quality control involves meeting the quality requirements specified for the deliverables Performed whenever a project is terminated to verify the level of completion • Scope Control
  • 5. Open Forum: Participant Questions If you have a question, raise your hand
  • 6. 1. When you started creating a Work Breakdown Structure for your project, you soon realized that it was too complicated to be done on a single piece of paper. You then started using a Work Breakdown Structure numbering system to A. Determine the complexity of the project B. Determine the level at which individual WBS elements are found C. Help in automating the WBS using appropriate software D. Present justification for the project
  • 7. 1. When you started creating a Work Breakdown Structure for your project, you soon realized that it was too complicated to be done on a single piece of paper. You then started using a Work Breakdown Structure numbering system to A. Determine the complexity of the project B. Determine the level at which individual WBS elements are found C. Help in automating the WBS using appropriate software D. Present justification for the project Correct Choice: B Justification:     Each WBS component, including work packages and control accounts within a WBS, is generally assigned a unique identifier from a code of accounts. These identifiers provide a structure for hierarchical summation of costs, schedule and resource information. Reference: PMBOK Third Edition, Page Number: 117 pmstudy.com comments: The items at the lowest level of the WBS may be referred to as work packages, especially in organizations that follow earned value management practices. These work packages may, in turn, be further decomposed in a subproject work breakdown structure. WBS numbering system determines the level at which individual WBS elements are found
  • 8. 2. Your project involves manufacturing high-precision engine subassemblies for the shipping industry. You have to perform several activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. You would have to do several reviews, product reviews, audits and walkthroughs. These activities are carried out in which process? A. Scope Verification B. Quality Inspection C. Scope Planning D. Change Control Process
  • 9. 2. Your project involves manufacturing high-precision engine subassemblies for the shipping industry. You have to perform several activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. You would have to do several reviews, product reviews, audits and walkthroughs. These activities are carried out in which process? A. Scope Verification B. Quality Inspection C. Scope Planning D. Change Control Process Correct Choice: A Justification:     Inspection(which is a Tool for Scope Verification) includes activities such as measuring, examining and testing undertaken to determine whether results conform to requirements. Inspections are variously called reviews, product reviews, audits and walk-throughs. Reference: PMBOK Third Edition, Page Number: 119
  • 10. 3. Your project involves manufacturing high-precision engine subassemblies for the shipping industry. You have to perform several activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. You would have to do several reviews, product reviews, audits and walkthroughs. These activities are carried out in which process? A. Scope Verification B. Quality Inspection C. Scope Planning D. Change Control Process
  • 11. 3. Your project involves manufacturing high-precision engine subassemblies for the shipping industry. You have to perform several activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. You would have to do several reviews, product reviews, audits and walkthroughs. These activities are carried out in which process? A. Scope Verification B. Quality Inspection C. Scope Planning D. Change Control Process Correct Choice:     A   Justification:     Inspection(which is a Tool for Scope Verification) includes activities such as measuring, examining and testing undertaken to determine whether results conform to requirements. Inspections are variously called reviews, product reviews, audits and walk-throughs. Reference: PMBOK Third Edition, Page Number: 119
  • 12. 4. As a project manager, you are responsible for managing changes to the project scope. If during the end of the project, a customer wants to make a major change to the scope of work, you should: A. Reject the change B. Make the required change C. Escalate to senior management D. Let the customer know about the impact of the change
  • 13. 4. As a project manager, you are responsible for managing changes to the project scope. If during the end of the project, a customer wants to make a major change to the scope of work, you should: A. Reject the change B. Make the required change C. Escalate to senior management D. Let the customer know about the impact of the change Correct Choice:     D   Justification:      If there is a major change to the project, the Project Manager should try to influence the change to minimize the impact on the project. Usually the project manager is advised to do the following: 1. Evaluate the impact of the change within the team 2. Let the customer(or person requesting the change) know about the impact of the change 3. If changes are required, then open a change control and get it approved - definitely inform the management and the change control board about the impact of the changes 4. If changes are approved by the change control board, then make the appropriate changes in the project plan Reference: pmstudy.com notes as mentioned above
  • 14. 5. In your project, you use product analysis to translate project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT: A. Value Engineering B. Value Analysis C. Product Breakdown D. Benefit/Cost Analysis
  • 15. 5. In your project, you use product analysis to translate project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT: A. Value Engineering B. Value Analysis C. Product Breakdown D. Benefit/Cost Analysis Correct Choice:    D   Justification:     Product analysis includes techniques such as product breakdown, systems analysis, systems engineering, value engineering, value analysis and functional analysis. Reference: PMBOK Third Edition , Page Number: 110
  • 16. 6. You recently joined as the project manager of ABC Company. The outgoing project manager mentioned that of late, she had been facing several issues with new change requests. The customers were located in the same office and they interacted directly with the project team and, at times, informally asked for some changes in the project`s product. If the changes were small, the project team members usually agreed to do the changes. The project manager found it difficult to prioritize activities and ensure that tasks are done as per schedule. The project had 50 team members and there was some discontent amongst them about the work they were supposed to do. What should be your first priority in this project?  A. Create a detailed project scope statement B. Align the project objectives with the organizational goals C. Ensure proper project scope control D. Call a meeting of all the project stakeholders to determine and resolve any outstanding issues
  • 17. 6. You recently joined as the project manager of ABC Company. The outgoing project manager mentioned that of late, she had been facing several issues with new change requests. The customers were located in the same office and they interacted directly with the project team and, at times, informally asked for some changes in the project`s product. If the changes were small, the project team members usually agreed to do the changes. The project manager found it difficult to prioritize activities and ensure that tasks are done as per schedule. The project had 50 team members and there was some discontent amongst them about the work they were supposed to do. What should be your first priority in this project?  A. Create a detailed project scope statement B. Align the project objectives with the organizational goals C. Ensure proper project scope control D. Call a meeting of all the project stakeholders to determine and resolve any outstanding issues Correct Choice:   C   Justification:     Project scope control is concerned with influencing the factors that create project scope changes and controlling the impact of those changes. Scope control assures that all requested changes and recommended corrective actions are processed through the project integrated change control process. Project scope control is also used to manage the actual changes when they occur and is integrated with the other control processes. Uncontrolled changes are often referred to as project scope creep. Reference: PMBOK Third Edition Page 119 pmstudy notes: Option 1: The project scope statement should already be prepared since the project is in execution stage. Option 2: Aligning the project objectives with the organizational goals happens in initial stages of the project i.e. when the project charter is being created. Option 3: This is the correct answer. Usually, if there is no proper project scope control, there might be scope creep, reprioritization of activities and discontent among team members who do not know what each person is supposed to do. Option 4: Calling a meeting will not resolve the outstanding issues related to scope creep and not having proper project scope control
  • 18. 7. A project was terminated early because of funding related issues. The project manager met the customer to establish and document the level and extent of project completion. What tool should be used for the purpose? A. Performance Measurement B. Scope Change Control System C. Inspection D. Earned Value
  • 19. 7. A project was terminated early because of funding related issues. The project manager met the customer to establish and document the level and extent of project completion. What tool should be used for the purpose? A. Performance Measurement B. Scope Change Control System C. Inspection D. Earned Value Correct Choice:     C   Justification:     Scope Verification:... If the project is terminated early, the project scope verification process should establish and document the level and extent of completion. A tool used for project scope verification is "Inspection". Also, please refer to Figure 5-9 Reference: PMBOK Third Edition, Page Number: 118
  • 20. 8. As a project manager, you are creating a document that describes the conditions or capabilities that must be possessed by the deliverables of the project to satisfy a contract, standard, specification, or other formally imposed documents. This document will also be referred to as: A. Product scope description B. Project requirements C. Product acceptance criteria D. Project objectives
  • 21. 8. As a project manager, you are creating a document that describes the conditions or capabilities that must be possessed by the deliverables of the project to satisfy a contract, standard, specification, or other formally imposed documents. This document will also be referred to as: A. Product scope description B. Project requirements C. Product acceptance criteria D. Project objectives Correct Choice:     B   Justification:     Project Requirements: Describes the conditions or capabilities that must be met or possessed by the deliverables of the project to satisfy a contract, standard, specification, or other formally imposed documents. Reference: PMBOK Third Edition, Page Number: 111
  • 22. 9. Your management is evaluating a project which requires an investment of $ 500,000. The expected inflow is $ 100,000 for the first year, and $ 300,000 for every year after that. What is the payback period? A. 2 years B. 2 years, 4 months C. 3 years D. Cannot be determined because discount rate is not specified
  • 23. 9. Your management is evaluating a project which requires an investment of $ 500,000. The expected inflow is $ 100,000 for the first year, and $ 300,000 for every year after that. What is the payback period? A. 2 years B. 2 years, 4 months C. 3 years D. Cannot be determined because discount rate is not specified Correct Choice:     B   Justification:     Payback Period = Number of years required for an organization to recapture an initial investment =$ 100,000 (1 year) + $ 300,000(2nd year) + $ 100,000(4 months, 3rd year) =$500,000 So, payback period = 2 years, 4 months Reference: pmstudy.com notes as mentioned above
  • 24. 10. You are the project manager for an initiative aimed at releasing a new product in the market. But because of government regulations, you will have to make some changes to the project scope and the WBS. Any approved modifications to the contents of the scope statement should be done through: A. Scope Management Plan Updates B. Work Breakdown Structure C. Project Plan D. Project Charter
  • 25. 10. You are the project manager for an initiative aimed at releasing a new product in the market. But because of government regulations, you will have to make some changes to the project scope and the WBS. Any approved modifications to the contents of the scope statement should be done through: A. Scope Management Plan Updates B. Work Breakdown Structure C. Project Plan D. Project Charter Correct Choice:     A  Justification:     Project Scope Management Plan (updates) : If approved change requests result from the Create WBS process, then the project scope management plan may need to be updated to include approved changes. Reference: PMBOK Third Edition, Page Number: 118
  • 26. 11. Your project is very critical for the company and must be completed within six months. The project charter has been signed, but the scope statement is not yet prepared. The management asks you to go ahead with the project without the scope statement being approved. What should you do? (SELECT THE BEST ANSWER) A. Refuse to work on the project because the management is not following standard project management practices B. Since time is of essence, you should start the project with inputs from the project charter C. Meet the management and mention the problems you will face without a scope statement D. Escalate the issue to the project sponsor and issue a risk memo
  • 27. 11. Your project is very critical for the company and must be completed within six months. The project charter has been signed, but the scope statement is not yet prepared. The management asks you to go ahead with the project without the scope statement being approved. What should you do? (SELECT THE BEST ANSWER) A. Refuse to work on the project because the management is not following standard project management practices B. Since time is of essence, you should start the project with inputs from the project charter C. Meet the management and mention the problems you will face without a scope statement D. Escalate the issue to the project sponsor and issue a risk memo Correct Choice:     C   Justification:     Without the scope statement, you do not have a good understanding of the project justification, product, project deliverables and project objectives. Without completing the scope statement, you do not have all the inputs for the scope definition and for the creation of Work Breakdown Structure. So, the best option is to talk to the management about the problems faced if there is no scope statement. So, Choice 3 is the "BEST AVAILABLE ALTERNATIVE" * Choice 1 is an extreme step and is not recommended * Choice 2 will cause problems e.g. you will not be able to create a WBS without a list of deliverables which is available in the scope statement. * Choice 4 is an extreme measure and is not recommended Reference: pmstudy.com notes as mentioned above
  • 28. 12. In your project, you are now interested in determining the cause of variance relative to the scope baseline and deciding whether corrective action is required. You should use: A. Configuration Management System B. Variance Analysis C. Replanning D. Earned Value Spreadsheets
  • 29. 12. In your project, you are now interested in determining the cause of variance relative to the scope baseline and deciding whether corrective action is required. You should use: A. Configuration Management System B. Variance Analysis C. Replanning D. Earned Value Spreadsheets Correct Choice:     B   Justification:     Variance Analysis: Project performance measurements are used to assess the magnitude of variation. Important aspects of project scope control include determining the cause of variance relative to the scope baseline and deciding whether corrective action is required. Reference: PMBOK Third Edition, Page Number: 121
  • 30. 13. Your company is going through a financial crisis and has set a pre-defined budget to work with. For your project, a pre-defined budget will become a: A. Risk B. Assumption C. Constraint D. Stage point
  • 31. 13. Your company is going through a financial crisis and has set a pre-defined budget to work with. For your project, a pre-defined budget will become a: A. Risk B. Assumption C. Constraint D. Stage point Correct Choice:     C   Justification:     Project Constraints: ... a predefined budget or any imposed dates (schedule milestones) that are issued by the customer or performing organization Reference: PMBOK Third Edition, Page Number: 111
  • 32. 14. You are explaining the importance of Work Breakdown Structure (WBS) to your project team members. In this context, all the following statements about Work Breakdown Structure(WBS) are correct EXCEPT: A. It is a hierarchical decomposition of work B. Planned work contained in the lowest level WBS components are also called WBS dictionaries C. WBS subdivides the project work into smaller, more manageable pieces of work D. WBS organizes and defines the total scope of work of the project
  • 33. 14. You are explaining the importance of Work Breakdown Structure (WBS) to your project team members. In this context, all the following statements about Work Breakdown Structure(WBS) are correct EXCEPT: A. It is a hierarchical decomposition of work B. Planned work contained in the lowest level WBS components are also called WBS dictionaries C. WBS subdivides the project work into smaller, more manageable pieces of work D. WBS organizes and defines the total scope of work of the project Correct Choice:     B   Justification:     The planned work contained within the lowest-level WBS components, which are also called work packages, can be scheduled, cost-estimated, monitored and controlled. Reference: PMBOK Third Edition, Page Number: 112
  • 34. 15. Scope Verification is the process of obtaining stakeholder`s formal acceptance of the completed project scope and associated deliverables. In this context, which statement related to Scope Verification is correct? A. Scope Verification is similar to Quality Control. B. Quality Control is generally performed before Scope Verification, but these two processes may also be done in parallel. C. Scope Verification indicates the end of a project. D. Scope Verification is the final sign-off from the sponsor and customer.
  • 35. 15. Scope Verification is the process of obtaining stakeholder`s formal acceptance of the completed project scope and associated deliverables. In this context, which statement related to Scope Verification is correct? A. Scope Verification is similar to Quality Control. B. Quality Control is generally performed before Scope Verification, but these two processes may also be done in parallel. C. Scope Verification indicates the end of a project. D. Scope Verification is the final sign-off from the sponsor and customer. Correct Choice:     B   Justification:     Quality Control is generally performed before Scope Verification, but these two processes can be performed in parallel Reference: PMBOK Third Edition, Page Number: 118
  • 36. 16. One of your tasks as a project manager is to prepare a Scope Statement for your project. The scope statement provides: A. Authorization to the project manager for using organizational resources for project activities. B. Documentation of how the project scope will be managed and how scope changes will be integrated into the project. C. Definition for Work Breakdown structure D. A documented basis for making future project decisions and for confirming or developing a common understanding of the project scope among the stakeholders.
  • 37. 16. One of your tasks as a project manager is to prepare a Scope Statement for your project. The scope statement provides: A. Authorization to the project manager for using organizational resources for project activities. B. Documentation of how the project scope will be managed and how scope changes will be integrated into the project. C. Definition for Work Breakdown structure D. A documented basis for making future project decisions and for confirming or developing a common understanding of the project scope among the stakeholders. Correct Choice:     D   Justification:     Project Scope Statement: ... provides a documented basis for making future decisions or developing a common understanding of the project scope among the stakeholders. Reference: PMBOK Third Edition, Page Number: 370
  • 38. 17. Your company is constructing a dam and your project (which is being performed under a contract) mandates that you should be paying compensation to any person displaced because of the project. What kind of constraint is this? A. Social B. Legal C. Environmental D. Humanitarian
  • 39. 17. Your company is constructing a dam and your project (which is being performed under a contract) mandates that you should be paying compensation to any person displaced because of the project. What kind of constraint is this? A. Social B. Legal C. Environmental D. Humanitarian Correct Choice:     B   Justification:     When a project is performed under a contract, contractual provisions will generally be constraints. Reference: PMBOK Third Edition, Page Number: 111 pmstudy.com comments: Anything done under a contract becomes a legal constraint
  • 40. 18. Generally accepted methods for translating project objectives into tangible deliverables and requirements are also referred to as: A. Product Analysis B. Risk Measurement C. Alternatives Identification D. Benefit/Cost Analysis
  • 41. 18. Generally accepted methods for translating project objectives into tangible deliverables and requirements are also referred to as: A. Product Analysis B. Risk Measurement C. Alternatives Identification D. Benefit/Cost Analysis Correct Choice:     A   Justification:     Product Analysis: Each application area has one or more generally accepted methods for translating project objectives into tangible deliverables and requirements. Reference: PMBOK Third Edition, Page Number: 110
  • 42. 19. You have created a WBS Dictionary which you can use to:  A. Verify that the deliverables being produced and accepted are included in the approved project scope B. Determine whether work and deliverables meet requirements and product acceptance criteria C. Influence the factors that create project scope changes and control the impact of those changes D. Get acceptance of the project scope from the customer
  • 43. 19. You have created a WBS Dictionary which you can use to:  A. Verify that the deliverables being produced and accepted are included in the approved project scope B. Determine whether work and deliverables meet requirements and product acceptance criteria C. Influence the factors that create project scope changes and control the impact of those changes D. Get acceptance of the project scope from the customer Correct Choice:     A   Justification:     The WBS Dictionary is a component of the detailed project scope definition, and is used to verify that the deliverables being produced and accepted are included in the approved project scope. Reference: PMBOK Third Edition, Page Number: 118
  • 44. 20. Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined at the work package level. This is a valuable tool for Scope Definition. However, decomposition may not be possible for a deliverable or subproject if: A. The deliverable or subproject is very complicated B. The deliverable or subproject is already being produced C. The deliverable or subproject will be accomplished after a very long time (i.e. far into the future) D. None of the above : Decomposition of deliverables is always possible
  • 45. 20. Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined at the work package level. This is a valuable tool for Scope Definition. However, decomposition may not be possible for a deliverable or subproject if: A. The deliverable or subproject is very complicated B. The deliverable or subproject is already being produced C. The deliverable or subproject will be accomplished after a very long time (i.e. far into the future) D. None of the above : Decomposition of deliverables is always possible Correct Choice:     C   Justification:     Decomposition may not be possible for a deliverable or subproject that will be accomplished far into the future. Reference: PMBOK Third Edition, Page Number: 114
  • 46. 21. As a project manager, you must formalize acceptance of the project scope and keep the project focused on the business need that it was undertaken to address. This should be done: A. At the beginning of the project B. At the end of the project C. When required by the business sponsor D. After each phase of the project
  • 47. 21. As a project manager, you must formalize acceptance of the project scope and keep the project focused on the business need that it was undertaken to address. This should be done: A. At the beginning of the project B. At the end of the project C. When required by the business sponsor D. After each phase of the project Correct Choice:     D   Justification:     Scope verification deals with formalizing acceptance of the project scope. This should be done at the end of each phase Reference: pmstudy.com notes as mentioned above
  • 48. 22. You are the project manager for a software project responsible for creating a software tool for your finance department. Once the project is completed, maintenance of the product: A. Will not be part of the project life cycle B. Will be included in project life cycle because the same resources will be used for maintaining the product as those who developed the product. C. May be included in the project life cycle if determined by the management D. Will become another project
  • 49. 22. You are the project manager for a software project responsible for creating a software tool for your finance department. Once the project is completed, maintenance of the product: A. Will not be part of the project life cycle B. Will be included in project life cycle because the same resources will be used for maintaining the product as those who developed the product. C. May be included in the project life cycle if determined by the management D. Will become another project Correct Choice:     A   Justification:     Projects and operations differ primarily in that operations are ongoing and repetitive, while projects are temporary and unique Reference: PMBOK Third Edition, Page Number: 6 pmstudy.com comments: Maintenance is an ongoing activity and should never be part of any project
  • 50. Wrap Up Conference Number: 547-941-6414 or 866-547-8978 Passcode: Leader – 844306338, Participant – 370670831 5 Time Management October 9 2:00pm EST Presenter: https:// (PMBOK Chapters 6) www.rooms.hp.com/attend/default.aspx?key =EHHS4NQJHR Participant: https:// www.rooms.hp.com/attend/default.aspx?key =EP44BUX8KS