SlideShare ist ein Scribd-Unternehmen logo
1 von 20
Relationships
                 between Activities
• A project is a sequence of activities.
   – Large projects have interrelated sequences.

• These are called Precedent activities
   – They must be defined before the project
     begins.
Step 2
           Develop a Network Model
• A Network Diagram visually displays the interrelated
  activities using nodes (circles) and arcs (arrows) that
  depict the relationships between activities.
• It is a graphical diagram.
• Two types of Graphical Network Models
   – Activity On Arc (AOA)
   – Activity On Node (AON) (We will use AON)
Two Types
              of Network Models
       Activity-on-Arc (AOA)
Time                  Time                Time


       Activity D            Activity E




       Activity-on-Node (AON)
       Activity              Activity
                                            We will use
          D                     E           this!
                    Link
What AON Nodes look like.
                                                                 Slack (S) is the difference, if any,
     The is the earliest you can start an
                                                                 between the early start (ES) and late
     activity. It is determined by the early
                                                                 start times (LS) or the early finish (EF)
     finish time of the precedent activity. If
                                                                 and late finish (EF) times.
     there are two or more precedent
     activities, this time is the same as                                S = LS - ES or S = LF - EF
     precedent activity with the latest “Early     Slack
     Finish” time.
                                                                         The earliest you can complete an
                                                                         activity--determined by adding the
                                                 Activity
                                                                         activity time (duration) to the early
                                       Early                Early        start time.
                                       Start                Finish
                                       Late                 Late
                                                                          This is the latest you can finish an
                                       Start Activity       Finish
                                                 Duration                 activity without delaying project
      This is the Late-Finish                                             completion. It is the same as the
      time minus the activity                                             Late Start time of the next activity.
      duration.                                                           If there are two or more
                                                                          subsequent activities, this time is
                                                                          the same as the earliest of those
                                                                          “Late Start” times.
© 2011 Lew Hofmann
Precedent
                                                  Relationships
          Precedent relationships determine a sequence for accomplishing activities.
          They specify that any given activity cannot start until its preceding activity or
          activities have been completed.



                                                     Activity On Node approach
  In our AON approach, the nodes (circles)
  represent activities, and the arcs                               AON
  represent the sequential relationships
  between them.


                                                        S            T           U

Nodes are simplified in the following examples.
                                                       “S” precedes “T” which precedes
                                                       “U”
Activity Relationships


S & T must be completed    T & U cannot begin until S
before U can be started.   has been completed.

           S                              T

                 U                 S

           T                              U
Activity Relationships


                                U cannot begin until S & T have been
U & V can’t begin until S & T   completed. V cannot begin until T has
have been completed.            been completed.

         S             U                S              U



         T             V                 T             V
Activity Relationships


T & U cannot begin until S has been
completed; V cannot begin until both T & U
have been completed.


            S       T       V



                    U
St. Adolf’s Hospital
                                      (A sample project)

                                                         Immediate
  Activity          Description                          Predecessor(s)   *Responsibility


   A    Select administrative and medical staff.              —               Johnson
   B    Select site and do site survey.                       —               Taylor
   C    Select equipment.                                     A               Adams
   D    Prepare final construction plans & layout.            B               Taylor
   E    Bring utilities to the site.                          B               Burton
   F    Interview applicants and fill positions in            A               Johnson
        nursing, support staff, maintenance,
        and security.
   G    Purchase and take delivery of equipment.              C               Adams
   H    Construct the hospital.                               D               Taylor
   I    Develop an information system.                        A               Simmons
   J    Install the equipment.                                E,G,H           Adams
   K    Train nurses and support staff.                       F,I,J           Johnson

*We won’t be using the “Responsibility” data, but it is important in project management.
St. Adolf’s Hospital
                               Diagramming the Network
             Activity Times
             (wks)
 Immediate                                 I
Predecessors

A     –        12                      A   F             K
B     –        9
C     A        10
D     B        10              Start       C     G           Finish
E     B        24
F     A        10
G     C        35                      B   D     H       J
H     D        40
I     A        15
J   E,G,H      4                           E
K    F,I,J     6
St. Adolf’s Hospital

                                                I
 Paths are sequences of activities
 between a project’s start and finish.

                                            A   F       K


Path           Time (wks)
                                    Start       C   G       Finish

A-I-K33
A-F-K28
                                            B   D   H   J
A-C-G-J-K          67
B-D-H-J-K          69
B-E-J-K            43
                                                E
St. Adolf’s Hospital
       The longest path is the critical path!
                                                    I


Path          Time (wks)                        A   F       K

A-I-K33
A-F-K28                             Start           C   G       Finish
A-C-G-J-K          67
B-D-H-J-K          69
B-E-J-K            43                           B   D   H   J


Project Expected
Time is 69 wks.                                     E
3. Develop the schedule

• Now we insert the time estimates.
  – This is where we distinguish between PERT & CPM.
• CPM is used when activity times are Certain.
     • It is Decision making under Certainty
     • You are certain of the time each activity will require to
       complete.

• PERT is used when activity times are not certain.
  (Decision making under risk)
Using PERT
       • PERT is used when activity times are uncertain.
             – Decision making under risk (“P” for probabilistic)
             – Three time estimates are required for each activity.
       • OPTIMISTIC TIME: Best time if everything goes perfectly
       • REALISTIC TIME: Most likely time
       • PESSIMISTIC TIME: A worst-case situation
                              B + 4M + P
           Expected Time = -------------------
                                       6

In this example, the most likely time is given a weight of 4, and the other two times (pessimistic
and optimistic) are each given weights of 1. Software allows you to change these as needed, but
the denominator must be the total of the weights given.
St. Adolf’s Hospital
                         Developing the schedule

• Earliest Start Time (ES) for an activity is the earliest finish time
   of the immediately preceding activity.
• Earliest Finish Time (EF) for an activity is its earliest start time
   plus how long it takes to do it (estimated duration).
• Latest Start Time (LS) is the latest you can finish the activity
   minus the activity’s estimated duration.
• Latest Finish Time (LF) is the latest start time of the activity that
   immediately follows it. (Latest start and finish times for each activity
   are computed starting at the project’s last activity completion time
   and working forward.)
Earliest Start and Earliest Finish Times

                                               12
                                                    I 27

              Earliest start time
                                                    15               Earliest finish time

                                        A 12                                   K 69
                                    0          12 F 22                    63
                                        12          10                         6


                                               12
                                                    C 22   22
                                                                G57
                      Start                                                            Finish
                                                    10          35



                                    0
                                        B9     9
                                                    D 19   19
                                                                H59       59
                                                                               J 63

                                        9           10          40             4



                                               9    E 33

                                                    24
© 2012 Lew Hofmann
Earliest Start and Earliest Finish Times
 Path                Time (wks)
                                               12
                                                    I 27              The Critical Path takes
 A-I-K33                                            15                69 weeks
 A-F-K28
 A-C-G-J-K              67
                                      A                                      K 69
 B-D-H-J-K              69        0       12   12 F 22                  63
 B-E-J-K                43            12            10                       6


                                               12
                                                    C 22   22
                                                                G57
                        Start                                                       Finish
                                                    10          35



                                  0
                                      B9       9
                                                    D 19   19
                                                                H59     59
                                                                             J 63
     Critical Path
                                      9             10          40           4



                                               9    E 33

                                                    24
© 2012 Lew Hofmann
Latest Start and Latest Finish Times
                        (Working from the last activity toward the first activity)


                                                  12
                                                      I27
                                                  48 1563



                                        A                                            K
                                    0       12    12 F 22      Latest          63   69      Latest
                                    2 1214        53 1063       start          63 6 69
                                                                                            finish
                                                                time                         time
                                                      C
                                                  12   22       22 G 57
                     Start                                                                  Finish
                                                  14 1024       24   59
                                                                    35



                                   0
                                        B9        9
                                                      D
                                                      19        19
                                                                     H
                                                                     59        59
                                                                                     J 63
                                    0 9 9         9 1019        19 4059        59 4 63




                                                   9 E 33
                                                  35 2459

© 2012 Lew Hofmann
Node   Duration   ES   LS   Slack
                                        Slack is the difference between LS
 A       12       0    2     2          and ES or the EF and LF.
 B        9       0    0     0
 C       10       12   14    2
                                                  12
                                                      I27
 D       10       9    9     0
 E       24       9    35    26                   48 1563
 F       10       12   53    41
 G       35       22   24    2
                                        A                                         K
 H       40       19   19    0      0       12    12 F 22                    63   69
 I       15       12   48    36     2 12 14       53 1063                    63 6 69
 J        4       59   59    0
 K        6       63   63    0
                                                      C
                                                  12   22       22 G 57
                            Start                                                        Finish
                                                  14 1024       24   59
                                                                   35



                                    0
                                        B9        9
                                                      D
                                                      19        19
                                                                    H59      59
                                                                                  J 63
     Activity Slack                 0 9 9         9 1019        19 4059      59 4 63

     Analysis
                                                   9 E 33
                                                  35 2459
© 2012 Lew Hofmann
Sample Gantt
Chart Printout

Weitere ähnliche Inhalte

Andere mochten auch

N 스크린 사례 분석보고서 4 - 애플
N 스크린 사례 분석보고서 4 - 애플N 스크린 사례 분석보고서 4 - 애플
N 스크린 사례 분석보고서 4 - 애플Youn Sang Jang
 
Mitologie universala.2.Grecia Antica
Mitologie universala.2.Grecia AnticaMitologie universala.2.Grecia Antica
Mitologie universala.2.Grecia AnticaAdela Negura
 
Tanjaouiates au Rallye Aicha des Gazelles
Tanjaouiates au Rallye Aicha des GazellesTanjaouiates au Rallye Aicha des Gazelles
Tanjaouiates au Rallye Aicha des GazellesSarah
 
Team up teacherproto_03.03.2011
Team up teacherproto_03.03.2011Team up teacherproto_03.03.2011
Team up teacherproto_03.03.2011iTEC-CNDP
 
Maha Al-Baghli - CSR as an Entrepreneurial Initiative
Maha Al-Baghli - CSR as an Entrepreneurial InitiativeMaha Al-Baghli - CSR as an Entrepreneurial Initiative
Maha Al-Baghli - CSR as an Entrepreneurial InitiativeTalal Al-Shammari
 
AIA Corp Webinar Nov 2012 #Final Draft
AIA Corp Webinar Nov 2012 #Final DraftAIA Corp Webinar Nov 2012 #Final Draft
AIA Corp Webinar Nov 2012 #Final DraftLeigh Somers
 
Les dones d’aigua
Les  dones  d’aiguaLes  dones  d’aigua
Les dones d’aiguaportermarc1
 
Mitologie universala.4.India
Mitologie universala.4.IndiaMitologie universala.4.India
Mitologie universala.4.IndiaAdela Negura
 
Desenho Parte Mecânica TID 3
Desenho Parte Mecânica TID 3Desenho Parte Mecânica TID 3
Desenho Parte Mecânica TID 3Sgtmuniz15
 
Mitologie universala.9.Indienii americani
Mitologie universala.9.Indienii americaniMitologie universala.9.Indienii americani
Mitologie universala.9.Indienii americaniAdela Negura
 

Andere mochten auch (17)

Catálogo BIC 2012
Catálogo BIC 2012Catálogo BIC 2012
Catálogo BIC 2012
 
N 스크린 사례 분석보고서 4 - 애플
N 스크린 사례 분석보고서 4 - 애플N 스크린 사례 분석보고서 4 - 애플
N 스크린 사례 분석보고서 4 - 애플
 
Mitologie universala.2.Grecia Antica
Mitologie universala.2.Grecia AnticaMitologie universala.2.Grecia Antica
Mitologie universala.2.Grecia Antica
 
Tanjaouiates au Rallye Aicha des Gazelles
Tanjaouiates au Rallye Aicha des GazellesTanjaouiates au Rallye Aicha des Gazelles
Tanjaouiates au Rallye Aicha des Gazelles
 
Poet dreams
Poet dreamsPoet dreams
Poet dreams
 
Team up teacherproto_03.03.2011
Team up teacherproto_03.03.2011Team up teacherproto_03.03.2011
Team up teacherproto_03.03.2011
 
үзүүлэн3
үзүүлэн3үзүүлэн3
үзүүлэн3
 
Maha Al-Baghli - CSR as an Entrepreneurial Initiative
Maha Al-Baghli - CSR as an Entrepreneurial InitiativeMaha Al-Baghli - CSR as an Entrepreneurial Initiative
Maha Al-Baghli - CSR as an Entrepreneurial Initiative
 
AIA Corp Webinar Nov 2012 #Final Draft
AIA Corp Webinar Nov 2012 #Final DraftAIA Corp Webinar Nov 2012 #Final Draft
AIA Corp Webinar Nov 2012 #Final Draft
 
Les dones d’aigua
Les  dones  d’aiguaLes  dones  d’aigua
Les dones d’aigua
 
Mitologie universala.4.India
Mitologie universala.4.IndiaMitologie universala.4.India
Mitologie universala.4.India
 
үзүүлэн6
үзүүлэн6үзүүлэн6
үзүүлэн6
 
Desenho Parte Mecânica TID 3
Desenho Parte Mecânica TID 3Desenho Parte Mecânica TID 3
Desenho Parte Mecânica TID 3
 
Mitologie universala.9.Indienii americani
Mitologie universala.9.Indienii americaniMitologie universala.9.Indienii americani
Mitologie universala.9.Indienii americani
 
青春
青春青春
青春
 
Undrah
UndrahUndrah
Undrah
 
Filosofia 1
Filosofia 1Filosofia 1
Filosofia 1
 

Mehr von Tim Arroyo

Individual behavior Ch 12
Individual behavior Ch 12Individual behavior Ch 12
Individual behavior Ch 12Tim Arroyo
 
Forecasting Problem Set
Forecasting Problem SetForecasting Problem Set
Forecasting Problem SetTim Arroyo
 
Es 08 pert case 1
Es 08 pert case 1Es 08 pert case 1
Es 08 pert case 1Tim Arroyo
 
Es 08 pert case 2
Es 08 pert case 2Es 08 pert case 2
Es 08 pert case 2Tim Arroyo
 
Es 08 forecasting topic final
Es 08 forecasting topic finalEs 08 forecasting topic final
Es 08 forecasting topic finalTim Arroyo
 
Lab 4 handout 043012
Lab 4 handout 043012Lab 4 handout 043012
Lab 4 handout 043012Tim Arroyo
 
Advance statistics 2
Advance statistics 2Advance statistics 2
Advance statistics 2Tim Arroyo
 
Adstat upload 1
Adstat upload 1Adstat upload 1
Adstat upload 1Tim Arroyo
 
Porters comp forces
Porters comp forcesPorters comp forces
Porters comp forcesTim Arroyo
 
Management 5 - 7
Management 5 - 7Management 5 - 7
Management 5 - 7Tim Arroyo
 
Management 1 - 4
Management 1 - 4Management 1 - 4
Management 1 - 4Tim Arroyo
 
Situation of the youth presentation (as of june 18 2010)[1]
Situation of the youth presentation (as of june 18 2010)[1]Situation of the youth presentation (as of june 18 2010)[1]
Situation of the youth presentation (as of june 18 2010)[1]Tim Arroyo
 
Peace education communication.volunteers 2011
Peace education communication.volunteers 2011Peace education communication.volunteers 2011
Peace education communication.volunteers 2011Tim Arroyo
 

Mehr von Tim Arroyo (18)

Individual behavior Ch 12
Individual behavior Ch 12Individual behavior Ch 12
Individual behavior Ch 12
 
11
1111
11
 
10
1010
10
 
5 7
5 75 7
5 7
 
13
1313
13
 
8 9
8 98 9
8 9
 
Forecasting Problem Set
Forecasting Problem SetForecasting Problem Set
Forecasting Problem Set
 
Es 08 pert case 1
Es 08 pert case 1Es 08 pert case 1
Es 08 pert case 1
 
Es 08 pert case 2
Es 08 pert case 2Es 08 pert case 2
Es 08 pert case 2
 
Es 08 forecasting topic final
Es 08 forecasting topic finalEs 08 forecasting topic final
Es 08 forecasting topic final
 
Lab 4 handout 043012
Lab 4 handout 043012Lab 4 handout 043012
Lab 4 handout 043012
 
Advance statistics 2
Advance statistics 2Advance statistics 2
Advance statistics 2
 
Adstat upload 1
Adstat upload 1Adstat upload 1
Adstat upload 1
 
Porters comp forces
Porters comp forcesPorters comp forces
Porters comp forces
 
Management 5 - 7
Management 5 - 7Management 5 - 7
Management 5 - 7
 
Management 1 - 4
Management 1 - 4Management 1 - 4
Management 1 - 4
 
Situation of the youth presentation (as of june 18 2010)[1]
Situation of the youth presentation (as of june 18 2010)[1]Situation of the youth presentation (as of june 18 2010)[1]
Situation of the youth presentation (as of june 18 2010)[1]
 
Peace education communication.volunteers 2011
Peace education communication.volunteers 2011Peace education communication.volunteers 2011
Peace education communication.volunteers 2011
 

Kürzlich hochgeladen

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking MenDelhi Call girls
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 

Kürzlich hochgeladen (20)

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 

Es 08 pert final

  • 1. Relationships between Activities • A project is a sequence of activities. – Large projects have interrelated sequences. • These are called Precedent activities – They must be defined before the project begins.
  • 2. Step 2 Develop a Network Model • A Network Diagram visually displays the interrelated activities using nodes (circles) and arcs (arrows) that depict the relationships between activities. • It is a graphical diagram. • Two types of Graphical Network Models – Activity On Arc (AOA) – Activity On Node (AON) (We will use AON)
  • 3. Two Types of Network Models Activity-on-Arc (AOA) Time Time Time Activity D Activity E Activity-on-Node (AON) Activity Activity We will use D E this! Link
  • 4. What AON Nodes look like. Slack (S) is the difference, if any, The is the earliest you can start an between the early start (ES) and late activity. It is determined by the early start times (LS) or the early finish (EF) finish time of the precedent activity. If and late finish (EF) times. there are two or more precedent activities, this time is the same as S = LS - ES or S = LF - EF precedent activity with the latest “Early Slack Finish” time. The earliest you can complete an activity--determined by adding the Activity activity time (duration) to the early Early Early start time. Start Finish Late Late This is the latest you can finish an Start Activity Finish Duration activity without delaying project This is the Late-Finish completion. It is the same as the time minus the activity Late Start time of the next activity. duration. If there are two or more subsequent activities, this time is the same as the earliest of those “Late Start” times. © 2011 Lew Hofmann
  • 5. Precedent Relationships Precedent relationships determine a sequence for accomplishing activities. They specify that any given activity cannot start until its preceding activity or activities have been completed. Activity On Node approach In our AON approach, the nodes (circles) represent activities, and the arcs AON represent the sequential relationships between them. S T U Nodes are simplified in the following examples. “S” precedes “T” which precedes “U”
  • 6. Activity Relationships S & T must be completed T & U cannot begin until S before U can be started. has been completed. S T U S T U
  • 7. Activity Relationships U cannot begin until S & T have been U & V can’t begin until S & T completed. V cannot begin until T has have been completed. been completed. S U S U T V T V
  • 8. Activity Relationships T & U cannot begin until S has been completed; V cannot begin until both T & U have been completed. S T V U
  • 9. St. Adolf’s Hospital (A sample project) Immediate Activity Description Predecessor(s) *Responsibility A Select administrative and medical staff. — Johnson B Select site and do site survey. — Taylor C Select equipment. A Adams D Prepare final construction plans & layout. B Taylor E Bring utilities to the site. B Burton F Interview applicants and fill positions in A Johnson nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C Adams H Construct the hospital. D Taylor I Develop an information system. A Simmons J Install the equipment. E,G,H Adams K Train nurses and support staff. F,I,J Johnson *We won’t be using the “Responsibility” data, but it is important in project management.
  • 10. St. Adolf’s Hospital Diagramming the Network Activity Times (wks) Immediate I Predecessors A – 12 A F K B – 9 C A 10 D B 10 Start C G Finish E B 24 F A 10 G C 35 B D H J H D 40 I A 15 J E,G,H 4 E K F,I,J 6
  • 11. St. Adolf’s Hospital I Paths are sequences of activities between a project’s start and finish. A F K Path Time (wks) Start C G Finish A-I-K33 A-F-K28 B D H J A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 E
  • 12. St. Adolf’s Hospital The longest path is the critical path! I Path Time (wks) A F K A-I-K33 A-F-K28 Start C G Finish A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 B D H J Project Expected Time is 69 wks. E
  • 13. 3. Develop the schedule • Now we insert the time estimates. – This is where we distinguish between PERT & CPM. • CPM is used when activity times are Certain. • It is Decision making under Certainty • You are certain of the time each activity will require to complete. • PERT is used when activity times are not certain. (Decision making under risk)
  • 14. Using PERT • PERT is used when activity times are uncertain. – Decision making under risk (“P” for probabilistic) – Three time estimates are required for each activity. • OPTIMISTIC TIME: Best time if everything goes perfectly • REALISTIC TIME: Most likely time • PESSIMISTIC TIME: A worst-case situation B + 4M + P Expected Time = ------------------- 6 In this example, the most likely time is given a weight of 4, and the other two times (pessimistic and optimistic) are each given weights of 1. Software allows you to change these as needed, but the denominator must be the total of the weights given.
  • 15. St. Adolf’s Hospital Developing the schedule • Earliest Start Time (ES) for an activity is the earliest finish time of the immediately preceding activity. • Earliest Finish Time (EF) for an activity is its earliest start time plus how long it takes to do it (estimated duration). • Latest Start Time (LS) is the latest you can finish the activity minus the activity’s estimated duration. • Latest Finish Time (LF) is the latest start time of the activity that immediately follows it. (Latest start and finish times for each activity are computed starting at the project’s last activity completion time and working forward.)
  • 16. Earliest Start and Earliest Finish Times 12 I 27 Earliest start time 15 Earliest finish time A 12 K 69 0 12 F 22 63 12 10 6 12 C 22 22 G57 Start Finish 10 35 0 B9 9 D 19 19 H59 59 J 63 9 10 40 4 9 E 33 24 © 2012 Lew Hofmann
  • 17. Earliest Start and Earliest Finish Times Path Time (wks) 12 I 27 The Critical Path takes A-I-K33 15 69 weeks A-F-K28 A-C-G-J-K 67 A K 69 B-D-H-J-K 69 0 12 12 F 22 63 B-E-J-K 43 12 10 6 12 C 22 22 G57 Start Finish 10 35 0 B9 9 D 19 19 H59 59 J 63 Critical Path 9 10 40 4 9 E 33 24 © 2012 Lew Hofmann
  • 18. Latest Start and Latest Finish Times (Working from the last activity toward the first activity) 12 I27 48 1563 A K 0 12 12 F 22 Latest 63 69 Latest 2 1214 53 1063 start 63 6 69 finish time time C 12 22 22 G 57 Start Finish 14 1024 24 59 35 0 B9 9 D 19 19 H 59 59 J 63 0 9 9 9 1019 19 4059 59 4 63 9 E 33 35 2459 © 2012 Lew Hofmann
  • 19. Node Duration ES LS Slack Slack is the difference between LS A 12 0 2 2 and ES or the EF and LF. B 9 0 0 0 C 10 12 14 2 12 I27 D 10 9 9 0 E 24 9 35 26 48 1563 F 10 12 53 41 G 35 22 24 2 A K H 40 19 19 0 0 12 12 F 22 63 69 I 15 12 48 36 2 12 14 53 1063 63 6 69 J 4 59 59 0 K 6 63 63 0 C 12 22 22 G 57 Start Finish 14 1024 24 59 35 0 B9 9 D 19 19 H59 59 J 63 Activity Slack 0 9 9 9 1019 19 4059 59 4 63 Analysis 9 E 33 35 2459 © 2012 Lew Hofmann