Project Proposal
Development
Training
TRAINING FOR MID-LEVEL LEADERSHIP
IN PROJECT COST ESTIMATING AND
SCHEDULING
INTRODUCTION AND
OVERVIEW
Welcome to the class. It is the first in
a series of classes that will be taught
to mid-level managers to introduce
them to project cost estimating and
the mechanics of schedule
development.
You Will Learn to:
• Estimate the cost of a pipeline
welding project with a minimum
of estimating error.
• To develop a timeline for the
project that allows a margin for
changes.
• Describe methods, uses, and
advantages/disadvantages of
top-down and bottom-up
estimating methods.
• Distinguish different kinds of
costs associated with a project.
IMAGES
COURTESY
OF
GLENN RILEY
WAUKESHA
PEARCE
OKLAHOMA
CITY
PROJECT
DEVELOPMENT
BASED ON
PROJECT LIFE
CYCLE
Larson & Gray (2021, p. 9)
AYDVAYIA (((2016)
ESTIMATING ERRORS
Steps Required
to Reduce
Estimating
Errors
PART I
Bottom-up
Top-Down
Consensus
Parametric
 Cost and time
important
 Fixed-price
contract
 Customer
wants details
 Estimate
process down
to the Work
package level
 Strategic
decision
making
 High
Uncertainty
 Internal, small
project
 Unstable
scope
 Uses pooled
experience of
upper- level
management to
estimate project
duration and
cost.
 Firms wanting
greater rigor
use the Delphi
Method to make
macro
estimates.
 Ratio method
is often used in
the “need”
phase to get
an initial
duration and
cost estimate.
 Apportion
method is an
extension to
the ratio
method used
when projects
follow past
projects.
Cost
Estimating
Methods
(pps. 140, 142, 146)
ESTIMATING PROJECT COST AND TIME
(…[objective ] “have a 95 percent probability of meeting time and cost estimates.”
(Larson & Gray, 2021, p. 136)
Cost Error Impact
$ Increased risk
$ Cost overruns
$ Extended schedules
$ Project plan is eroded
$ Profit challenges
Time Error Impact
$ Increased risk
$ Cost overruns
$ Extended schedules
$ Project plan is eroded
$ Profit challenges
 Planning – Make estimates closer to work package
definitions.
 Project scope – Ensure that scope is correctly
written.
 People- Use people that are skilled in estimating.
 Project structure – Focus on complexity of project
and making local decisions (pps. 136-137).
...
REDUCING ESTIMATING ERRORS
REDUCING ESTIMATING ERRORS (Part II)
 Guard against padding cost and time
estimates.
 Organizational culture – differing cultures
impact estimates; some tend to over-
estimate and some underestimate.
 Other factors – consider and allow for
variables (p. 137).
THE ART AND SCIENCE OF
FORECASTING
Cost vs. Forecast
 Cost = Estimate (or actual) of today’s cost to develop a work
package.
 Forecast = Estimate of cost when project is complete and
turned over to customer.
 Actual = Actual cost incurred from womb to tomb
 Cost estimate error = Difference between Cost and Actual
ESTIMATING TIME AND COST
 Supports good decisions
 Needed to schedule work
 Determines duration and cost
 Determines if the project is worth doing
 Needed to determine cash flow needs
 Helps determine how project is progressing (p. 138).
TOP-DOWN APPROACH
 Used when scope is not definitively defined
 No relevant historical data is available.
 EWAG made by upper-level management.
Steps Utilized to Apply Modern Forecasting
Methodologies
Top-Down Approach
 Rough estimate
 Usually occurs in “conceptual” stage
 Estimates often made over cocktails by upper management
 Not enough information available to finalize design
 Used until WBS tasks are clearly defined (p.142).
Top-Down
Approach
 Consensus Method
 Delphi Method
 Ratio Method
 Apportion Method
 Function Point Method for
Software and Systems
 Learning Curves (pps. 142-
145)
CONSENSUS
METHOD
DELPHI
METHOD
 Group decision process about the
likelihood that certain events will
occur .
 Uses a panel of experts familiar with
the kind of project in question.
 The notion is that insight and
experience are better equipped to
estimate project cost/times than
theoretical approaches or statistical
methods (p. 142).
 Uses pooled experience of senior
and/or middle managers to estimate
total project duration and cost.
 Involves a meeting where experts
discuss, argue, and reach a decision
as a best guesstimate (p. 142).
RATIO
METHOD
APPORTION
METHOD
 Extension to the ratio method.
 Used when projects closely follows
past projects in features and costs.
 Estimates can be made quickly with
little effort and reasonable accuracy.
 Common in relatively standard
projects with some small variation or
customization (p. 143).
 Used in the concept phase to get an
initial cost/time estimate for the
project.
 Examples: Using number of sq ft to
estimate cost/time to build a house.
Knowing sq ft and dollars per sq ft, it
should take 100 days to complete (p.
143).
Learning Curves
Function Point Methods -
Software and Systems Projects
Used when projects are repeated
several times. The time to perform a
task improves with repetition,
especially tasks that are labor
intensive. This pattern can be used to
predict reductions in time to perform
tasks. This pattern has been
quantified in the learning curve (p.
145) .
 Used in the concept phase to get an
initial cost/time estimate for the
project.
 Examples: Using number of sq ft to
estimate cost/time to build a house.
Knowing sq ft and dollars per sq ft, it
should take 100 days to complete (p.
143-144).
BOTTOM-UP APPROACH
 Cost and time are important.
 Can use a fixed-price contract..
 Customer wants details.
Bottom-up Approach
 Can take place after the project has been defined in detail .
Estimates should be made by knowledgeable people having
relevant experience with the task to improve the time and
cost projections.
 Estimates can be made at work package level using WBS components
(p. 140).
Bottom-up Approach (cont.)
 Can provide customer with alternatives regarding project completion
dates at the lower cost method vs. compressing the project delivery.
 Similar trade-offs can be compared for different levels of resources or
increases in technical performance.
 The preferred approach is to compare both top-down and bottom-up
approaches, develop schedules and budgets and reconcile the
differences between the two methods. (p. 140).
Parametric
Procedures
Template
Method
Parametric procedures are top-down
methods including ratios, or
surrogates, to estimate project times
or costs.
Parametric procedures can be applied
to specific tasks such as calculating
conversion projects, home projects
such as wallpapering the kitchen (p.
146).
 Templates can be used as a starting
point for the new project.
 Differences in the new project can be
noted and past times and costs
adjusted to reflect these differences.
 Enables the firm to develop a
potential schedule, estimate costs,
and develop a budget in a short time.
 Development of such templates in a
database can quickly reduce estimate
errors (p. 146).
Parametric
Procedures
Template
Method
Parametric procedures are top-down
methods including ratios, or
surrogates, to estimate project times
or costs.
Parametric procedures can be applied
to specific tasks such as calculating
conversion projects, home projects
such as wallpapering the kitchen (p.
146).
 Templates can be used as a starting
point for the new project.
 Differences in the new project can be
noted and past times and costs
adjusted to reflect these differences.
 Enables the firm to develop a
potential schedule, estimate costs,
and develop a budget in a short time.
 Development of such templates in a
database can quickly reduce estimate
errors (p. 146).
Phase
Estimating
Range
Estimating
 Phase estimating is a hybrid
approach using a top-down estimate
and refining the estimate for phases
as it is implemented.
 Some projects such as aerospace, IT
projects, new technology and
construction where design is
incomplete frequently use phase or
life-cycle estimating (p.147).
 Best used when “work packages have
significant uncertainty associated
with the time or cost to complete…
Work packages with significant
uncertainty should require three -
time estimates –low, average, and
high (borrowed from PERT
methodology that uses probability
distributions).
Range
Estimating
 Best used when “work packages have
significant uncertainty associated
with the time or cost to complete…
Work packages with significant
uncertainty should require three -
time estimates –low, average, and
high (borrowed from PERT
methodology that uses probability
distributions).
Range
Estimating
Phase
Estimating
 Best used when “work packages have
significant uncertainty associated
with the time or cost to complete…
Work packages with significant
uncertainty should require three -
time estimates –low, average, and
high (borrowed from PERT
methodology that uses probability
distributions).
Range
Estimating
 Phase estimating is a hybrid
approach using a top-down estimate
and refining the estimate for phases
as it is implemented.
 Some projects such as aerospace, IT
projects, new technology and
construction where design is
incomplete frequently use phase or
life-cycle estimating (p.147).
Phase
Estimating
 Best used when “work packages have
significant uncertainty associated
with the time or cost to complete…
Work packages with significant
uncertainty should require three -
time estimates –low, average, and
high (borrowed from PERT
methodology that uses probability
distributions).
Range
Estimating
References
ADVAYIA (2016). Project scheduling techniques: Probabilistic and deterministic.
Images. (n.d.) Slides 6, 9, 10, 11, 16, retrieved from https://images.search.yahoo.com/
Larson, E. W. & Gray, C. F. (2021). Project management: The managerial process (8th ed.) McGraw-Hill
Education
Riley, D.G. (2020). Waukesha Pearce, Oklahoma City, OK
Swanson, S. A. (2011). Estimating errors. PM Network, 25(10), 62–67.

Weitere ähnliche Inhalte

Ähnlich wie Project Proposal for Development Training

Project management
Project managementProject management
Project managementervinod
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdfAliaaAl4
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimationssuser9d62d6
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationMubashir Ali
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationVandalRay
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfMadhusha15
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...Egyptian Engineers Association
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resouresMayank Kothawade
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectArvinThamsir1
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptArvinThamsir1
 

Ähnlich wie Project Proposal for Development Training (20)

Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Project management
Project managementProject management
Project management
 
Project Cost Managementttttttttttt .pdf
Project Cost Managementttttttttttt   .pdfProject Cost Managementttttttttttt   .pdf
Project Cost Managementttttttttttt .pdf
 
Software Project Cost Management and estimation
Software Project Cost Management and estimationSoftware Project Cost Management and estimation
Software Project Cost Management and estimation
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Lect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost EstimationLect-5: Work Breakdown Structure and Project Cost Estimation
Lect-5: Work Breakdown Structure and Project Cost Estimation
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Project Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project EstimationProject Estimation Project Estimation Project Estimation
Project Estimation Project Estimation Project Estimation
 
Day 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdfDay 7 Project Cost Management .pdf
Day 7 Project Cost Management .pdf
 
Software
SoftwareSoftware
Software
 
Term paper spm
Term paper spmTerm paper spm
Term paper spm
 
Cost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptxCost-Estimation-Techniques unit 2.pptx
Cost-Estimation-Techniques unit 2.pptx
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
م.80-مبادرة #تواصل_تطويرم.أحمد سعيد رفاعهى-دورة حياة تقدير التكلفة بمشروعات ا...
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Estimating time and cost resoures
Estimating time and cost resouresEstimating time and cost resoures
Estimating time and cost resoures
 
Chap005
Chap005Chap005
Chap005
 
Capital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of ProjectCapital Expenditure Estimating Cost of Project
Capital Expenditure Estimating Cost of Project
 
Capital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .pptCapital Cost Expenditure Estimating .ppt
Capital Cost Expenditure Estimating .ppt
 

Kürzlich hochgeladen

Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 

Kürzlich hochgeladen (20)

9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 

Project Proposal for Development Training

  • 1. Project Proposal Development Training TRAINING FOR MID-LEVEL LEADERSHIP IN PROJECT COST ESTIMATING AND SCHEDULING
  • 2. INTRODUCTION AND OVERVIEW Welcome to the class. It is the first in a series of classes that will be taught to mid-level managers to introduce them to project cost estimating and the mechanics of schedule development.
  • 3. You Will Learn to: • Estimate the cost of a pipeline welding project with a minimum of estimating error. • To develop a timeline for the project that allows a margin for changes. • Describe methods, uses, and advantages/disadvantages of top-down and bottom-up estimating methods. • Distinguish different kinds of costs associated with a project.
  • 8. Bottom-up Top-Down Consensus Parametric  Cost and time important  Fixed-price contract  Customer wants details  Estimate process down to the Work package level  Strategic decision making  High Uncertainty  Internal, small project  Unstable scope  Uses pooled experience of upper- level management to estimate project duration and cost.  Firms wanting greater rigor use the Delphi Method to make macro estimates.  Ratio method is often used in the “need” phase to get an initial duration and cost estimate.  Apportion method is an extension to the ratio method used when projects follow past projects. Cost Estimating Methods (pps. 140, 142, 146)
  • 9. ESTIMATING PROJECT COST AND TIME (…[objective ] “have a 95 percent probability of meeting time and cost estimates.” (Larson & Gray, 2021, p. 136) Cost Error Impact $ Increased risk $ Cost overruns $ Extended schedules $ Project plan is eroded $ Profit challenges Time Error Impact $ Increased risk $ Cost overruns $ Extended schedules $ Project plan is eroded $ Profit challenges
  • 10.  Planning – Make estimates closer to work package definitions.  Project scope – Ensure that scope is correctly written.  People- Use people that are skilled in estimating.  Project structure – Focus on complexity of project and making local decisions (pps. 136-137). ... REDUCING ESTIMATING ERRORS
  • 11. REDUCING ESTIMATING ERRORS (Part II)  Guard against padding cost and time estimates.  Organizational culture – differing cultures impact estimates; some tend to over- estimate and some underestimate.  Other factors – consider and allow for variables (p. 137).
  • 12. THE ART AND SCIENCE OF FORECASTING
  • 13. Cost vs. Forecast  Cost = Estimate (or actual) of today’s cost to develop a work package.  Forecast = Estimate of cost when project is complete and turned over to customer.  Actual = Actual cost incurred from womb to tomb  Cost estimate error = Difference between Cost and Actual
  • 14. ESTIMATING TIME AND COST  Supports good decisions  Needed to schedule work  Determines duration and cost  Determines if the project is worth doing  Needed to determine cash flow needs  Helps determine how project is progressing (p. 138).
  • 15. TOP-DOWN APPROACH  Used when scope is not definitively defined  No relevant historical data is available.  EWAG made by upper-level management.
  • 16. Steps Utilized to Apply Modern Forecasting Methodologies Top-Down Approach  Rough estimate  Usually occurs in “conceptual” stage  Estimates often made over cocktails by upper management  Not enough information available to finalize design  Used until WBS tasks are clearly defined (p.142).
  • 17. Top-Down Approach  Consensus Method  Delphi Method  Ratio Method  Apportion Method  Function Point Method for Software and Systems  Learning Curves (pps. 142- 145)
  • 18. CONSENSUS METHOD DELPHI METHOD  Group decision process about the likelihood that certain events will occur .  Uses a panel of experts familiar with the kind of project in question.  The notion is that insight and experience are better equipped to estimate project cost/times than theoretical approaches or statistical methods (p. 142).  Uses pooled experience of senior and/or middle managers to estimate total project duration and cost.  Involves a meeting where experts discuss, argue, and reach a decision as a best guesstimate (p. 142).
  • 19. RATIO METHOD APPORTION METHOD  Extension to the ratio method.  Used when projects closely follows past projects in features and costs.  Estimates can be made quickly with little effort and reasonable accuracy.  Common in relatively standard projects with some small variation or customization (p. 143).  Used in the concept phase to get an initial cost/time estimate for the project.  Examples: Using number of sq ft to estimate cost/time to build a house. Knowing sq ft and dollars per sq ft, it should take 100 days to complete (p. 143).
  • 20. Learning Curves Function Point Methods - Software and Systems Projects Used when projects are repeated several times. The time to perform a task improves with repetition, especially tasks that are labor intensive. This pattern can be used to predict reductions in time to perform tasks. This pattern has been quantified in the learning curve (p. 145) .  Used in the concept phase to get an initial cost/time estimate for the project.  Examples: Using number of sq ft to estimate cost/time to build a house. Knowing sq ft and dollars per sq ft, it should take 100 days to complete (p. 143-144).
  • 21. BOTTOM-UP APPROACH  Cost and time are important.  Can use a fixed-price contract..  Customer wants details.
  • 22. Bottom-up Approach  Can take place after the project has been defined in detail . Estimates should be made by knowledgeable people having relevant experience with the task to improve the time and cost projections.  Estimates can be made at work package level using WBS components (p. 140).
  • 23. Bottom-up Approach (cont.)  Can provide customer with alternatives regarding project completion dates at the lower cost method vs. compressing the project delivery.  Similar trade-offs can be compared for different levels of resources or increases in technical performance.  The preferred approach is to compare both top-down and bottom-up approaches, develop schedules and budgets and reconcile the differences between the two methods. (p. 140).
  • 24. Parametric Procedures Template Method Parametric procedures are top-down methods including ratios, or surrogates, to estimate project times or costs. Parametric procedures can be applied to specific tasks such as calculating conversion projects, home projects such as wallpapering the kitchen (p. 146).  Templates can be used as a starting point for the new project.  Differences in the new project can be noted and past times and costs adjusted to reflect these differences.  Enables the firm to develop a potential schedule, estimate costs, and develop a budget in a short time.  Development of such templates in a database can quickly reduce estimate errors (p. 146). Parametric Procedures Template Method Parametric procedures are top-down methods including ratios, or surrogates, to estimate project times or costs. Parametric procedures can be applied to specific tasks such as calculating conversion projects, home projects such as wallpapering the kitchen (p. 146).  Templates can be used as a starting point for the new project.  Differences in the new project can be noted and past times and costs adjusted to reflect these differences.  Enables the firm to develop a potential schedule, estimate costs, and develop a budget in a short time.  Development of such templates in a database can quickly reduce estimate errors (p. 146).
  • 25. Phase Estimating Range Estimating  Phase estimating is a hybrid approach using a top-down estimate and refining the estimate for phases as it is implemented.  Some projects such as aerospace, IT projects, new technology and construction where design is incomplete frequently use phase or life-cycle estimating (p.147).  Best used when “work packages have significant uncertainty associated with the time or cost to complete… Work packages with significant uncertainty should require three - time estimates –low, average, and high (borrowed from PERT methodology that uses probability distributions). Range Estimating  Best used when “work packages have significant uncertainty associated with the time or cost to complete… Work packages with significant uncertainty should require three - time estimates –low, average, and high (borrowed from PERT methodology that uses probability distributions). Range Estimating Phase Estimating  Best used when “work packages have significant uncertainty associated with the time or cost to complete… Work packages with significant uncertainty should require three - time estimates –low, average, and high (borrowed from PERT methodology that uses probability distributions). Range Estimating  Phase estimating is a hybrid approach using a top-down estimate and refining the estimate for phases as it is implemented.  Some projects such as aerospace, IT projects, new technology and construction where design is incomplete frequently use phase or life-cycle estimating (p.147). Phase Estimating  Best used when “work packages have significant uncertainty associated with the time or cost to complete… Work packages with significant uncertainty should require three - time estimates –low, average, and high (borrowed from PERT methodology that uses probability distributions). Range Estimating
  • 26.
  • 27.
  • 28. References ADVAYIA (2016). Project scheduling techniques: Probabilistic and deterministic. Images. (n.d.) Slides 6, 9, 10, 11, 16, retrieved from https://images.search.yahoo.com/ Larson, E. W. & Gray, C. F. (2021). Project management: The managerial process (8th ed.) McGraw-Hill Education Riley, D.G. (2020). Waukesha Pearce, Oklahoma City, OK Swanson, S. A. (2011). Estimating errors. PM Network, 25(10), 62–67.