2. Replace all guttering and direct water away from building.
Repair and stabilise veranda decks and level and attach posts.
Replace missing walls at rear of building
Replace any missing boards, floorboards etc.
Slab Cottage No One. Stage One.
Repair decking and level
all posts, bearers and
joists will require
replacement. Install
missing handrails.
4. Slab Shed – Building One.
Project Outline – Stage One.
•Replace Guttering, direct water away from building.
•Stabilise four posts and level.
•Fix all loose slabs.