SlideShare ist ein Scribd-Unternehmen logo
1 von 25
Downloaden Sie, um offline zu lesen
Former NAS Moffett Field


Hangar 1 Removal Action Update

        Bryce Bartelma, PG
       Navy BRAC PMO West

        November 3, 2011
          RAB Meeting




               1
Presentation Overview



• Project Objective
• Progress Update
    Continued Monitoring            Roof, Redwood, Siding &
     and Protection                   Window Removal
     Measures                        Coating Inspections &
    Historic Mitigation/CARP         Touch-ups
    Scaffolding Installation        Moving Scaffolding
• Schedule
• Questions



                                2
Project Objective




• Control release of PCBs from Hangar 1 in accordance
  with EE/CA (July 2008) and Action Memorandum
  (December 2008)
    Demolition of interior structures
    Removal of contaminated siding
    Application of weather-resistant coating to steel frame




                             3
Continued Monitoring and
                Protection Measures

• No observed impacts to biological
  activity
• Continued storm water and ground
  surface protection
• Navy and NASA air monitoring data
  demonstrates control of air emissions




                            4
EPA and Water Board Site Inspection




                5
Hangar 1 Interactive CD



• Delay in final production. CD will contain interactive
  history and interviews but not 3-D tour.

• Navy and NASA
  looking into a web
  based version that
  will be hosted by
  NASA website and
  will contain both the
  interactive materials
  and 3-D tour!


                             6
Continued Mansard Panel Removal




              7
Continued Redwood Removal




            8
Continued Silver Siding Removal
  (Robertson Protected Metal)




              9
Window and Door Removal




           10
Zone 1 Exterior Coating & Touch-ups



                     • Use of man lifts for
                       lower level touch-ups




                11
Zone 2 East Progress – September 7




                12
Zone 2 East Progress – September 20




                13
Zone 2 East Progress – October 12




               14
Zone 2 West Progress – September 6




                15
Zone 2 West Progress – October 3




               16
Zone 2 West Progress – October 12




               17
Removing Scaffolding in Zone 1




              18
Interior View




     19
Installing Systems Scaffolding
   & Quick Deck in Zone 6




              20
Clam Shell Door Mechanisms




            21
Fiber Board Removal




• Fiber boards surround
  tracks of Clam Shell doors
• Recently sampled and
  determined to contain
  contamination
• Not structural
• Navy to remove boards
  but keep rails in-place
• NASA to consider
  replacement in re-use


                               22
Special Visitor at Moffett




            23
Schedule




• Fieldwork in zones 1 – 6
  Ongoing
• Complete fieldwork,
  confirmation sampling
  and demobilize
  Spring/Summer 2012
• Submit After Action
  Completion Report
  Summer/Fall 2012



                             24
Questions?




             Point of Contact:

               Scott Anderson
            BRAC Environmental
                  Coordinator
               (619) 532-0938
         scott.d.anderson@navy.mil



    25

Weitere ähnliche Inhalte

Was ist angesagt?

Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportHonolulu Civil Beat
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...TRC Companies, Inc.
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress reportHonolulu Civil Beat
 
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...TRC Companies, Inc.
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Niels Asjee
 
Remediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsRemediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsPeter Gringinger
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 

Was ist angesagt? (9)

Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily Report
 
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
Installation of an Impervious Cap for Control of Residual NAPL Migration, Con...
 
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
Why core the Quaternary of the North Sea? An overview/context of the GlaciSto...
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
 
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
Design of a Remedy to Control NAPL Transport and Allow for Flexible Redevelop...
 
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
Abu Dhabi - Khalifa Port Industrial Zone Project - Hydronamic - Construction ...
 
Remediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM conceptsRemediation, Clean-up and other non-NEPM concepts
Remediation, Clean-up and other non-NEPM concepts
 
The glaciation of the North Sea Basin and its implications for Carbon Capture...
The glaciation of the North Sea Basin and its implications for Carbon Capture...The glaciation of the North Sea Basin and its implications for Carbon Capture...
The glaciation of the North Sea Basin and its implications for Carbon Capture...
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 

Andere mochten auch

Navy Updates March Rab
Navy Updates March RabNavy Updates March Rab
Navy Updates March RabSteve Williams
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewSteve Williams
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldSteve Williams
 
In Search Of East Internet Company
In Search Of East Internet CompanyIn Search Of East Internet Company
In Search Of East Internet CompanyPrashant Singh
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationSteve Williams
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardSteve Williams
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanSteve Williams
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateSteve Williams
 

Andere mochten auch (8)

Navy Updates March Rab
Navy Updates March RabNavy Updates March Rab
Navy Updates March Rab
 
Moffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year Review
 
NASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett FieldNASA Update on Planetary Ventures Lease of Moffett Field
NASA Update on Planetary Ventures Lease of Moffett Field
 
In Search Of East Internet Company
In Search Of East Internet CompanyIn Search Of East Internet Company
In Search Of East Internet Company
 
EPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source InvestigationEPA MEW Study Area TCE Source Investigation
EPA MEW Study Area TCE Source Investigation
 
NASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory BoardNASA Ames Update to Restoration Advisory Board
NASA Ames Update to Restoration Advisory Board
 
Moffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management PlanMoffett RAB: EPA Update on Environmental Issues Management Plan
Moffett RAB: EPA Update on Environmental Issues Management Plan
 
Moffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area UpdateMoffett RAB: EPA MEW Superfund Study Area Update
Moffett RAB: EPA MEW Superfund Study Area Update
 

Ähnlich wie Moffett Hangar One Removal Action Update

Hangar One Update to Moffett RAB
Hangar One Update to Moffett RABHangar One Update to Moffett RAB
Hangar One Update to Moffett RABSteve Williams
 
Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Steve Williams
 
Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Steve Williams
 
Moffett RAB Hangar One Update
Moffett RAB Hangar One UpdateMoffett RAB Hangar One Update
Moffett RAB Hangar One UpdateSteve Williams
 
Hangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABHangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABSteve Williams
 
Moffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionMoffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionSteve Williams
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Jacobs Engineering
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6James AH Campbell
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E HeilandErik Heiland
 
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Fairfax County
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)DC Department of General Services
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 UpdateSteve Williams
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityFairfax County
 
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxStructural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxcpatriciarpatricia
 
01 jt twisting super tower project
01 jt   twisting super tower project01 jt   twisting super tower project
01 jt twisting super tower projectsucreargentina
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEBAURANGZEB442
 

Ähnlich wie Moffett Hangar One Removal Action Update (20)

Hangar One Update to Moffett RAB
Hangar One Update to Moffett RABHangar One Update to Moffett RAB
Hangar One Update to Moffett RAB
 
Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012Hangar One Update to Moffett RAB May 10, 2012
Hangar One Update to Moffett RAB May 10, 2012
 
Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012Hangar 1 rab update nov 29 2012
Hangar 1 rab update nov 29 2012
 
Moffett RAB Hangar One Update
Moffett RAB Hangar One UpdateMoffett RAB Hangar One Update
Moffett RAB Hangar One Update
 
Hangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RABHangar One Removal Action Update to Moffett RAB
Hangar One Removal Action Update to Moffett RAB
 
Moffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal ActionMoffett Hangar One Proposed Removal Action
Moffett Hangar One Proposed Removal Action
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
Trawsfynydd RPV Inspections - Institute of Asset Management presentation 2013
 
The discovery and evaluation of AK6
The discovery and evaluation of AK6The discovery and evaluation of AK6
The discovery and evaluation of AK6
 
101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland101025 Excellence in Exc Planning Presentation E Heiland
101025 Excellence in Exc Planning Presentation E Heiland
 
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
Public Facilities Manual Project NVBIA/NAIO Phase 2 Update - Nov. 21, 2019
 
Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)Kalorama Park & Playground ANC Presentation (December 3, 2014)
Kalorama Park & Playground ANC Presentation (December 3, 2014)
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 Update
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docxStructural estimateROOF SAILSPODIUMUNDER GROUN.docx
Structural estimateROOF SAILSPODIUMUNDER GROUN.docx
 
01 jt twisting super tower project
01 jt   twisting super tower project01 jt   twisting super tower project
01 jt twisting super tower project
 
lecture2 site investigation
lecture2   site investigationlecture2   site investigation
lecture2 site investigation
 
SOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallengesSOTC_2016_RMJ_SurveyingChallenges
SOTC_2016_RMJ_SurveyingChallenges
 
Soil investigation by AURANGZEB
Soil investigation by AURANGZEBSoil investigation by AURANGZEB
Soil investigation by AURANGZEB
 
Aoc sediment update_part2
Aoc sediment update_part2Aoc sediment update_part2
Aoc sediment update_part2
 

Mehr von Steve Williams

RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationSteve Williams
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28Steve Williams
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community PresentationSteve Williams
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Steve Williams
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentSteve Williams
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1Steve Williams
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateSteve Williams
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateSteve Williams
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesSteve Williams
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013Steve Williams
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Steve Williams
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...Steve Williams
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesSteve Williams
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Steve Williams
 
Site 28 Supplemental Investigation
Site 28 Supplemental InvestigationSite 28 Supplemental Investigation
Site 28 Supplemental InvestigationSteve Williams
 
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateMoffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateSteve Williams
 
Laser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringLaser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringSteve Williams
 
Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Steve Williams
 
Moffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateMoffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateSteve Williams
 

Mehr von Steve Williams (20)

RAB NASA Update
RAB NASA UpdateRAB NASA Update
RAB NASA Update
 
RAB Vapor Intrusion Mitigation
RAB Vapor Intrusion MitigationRAB Vapor Intrusion Mitigation
RAB Vapor Intrusion Mitigation
 
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
RAB Vapor Intrusion Update, Installation Restoration (IR) Site 28
 
RAB Community Presentation
RAB Community PresentationRAB Community Presentation
RAB Community Presentation
 
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
Endophyte Assisted Phytoremediation of TCE and Derivatives Using Hybrid Popla...
 
Orion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume AssessmentOrion Park Housing Area VOC Plume Assessment
Orion Park Housing Area VOC Plume Assessment
 
Epa vi and source investigation rab mtg update august 7 2014rv1
Epa vi  and source investigation rab mtg update    august 7 2014rv1Epa vi  and source investigation rab mtg update    august 7 2014rv1
Epa vi and source investigation rab mtg update august 7 2014rv1
 
Moffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion UpdateMoffett RAB: Navy EPA Intrusion Update
Moffett RAB: Navy EPA Intrusion Update
 
Moffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion UpdateMoffett RAB: Navy Vapor Intrusion Update
Moffett RAB: Navy Vapor Intrusion Update
 
Moffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental ActivitiesMoffett RAB: 2014 Planned Environmental Activities
Moffett RAB: 2014 Planned Environmental Activities
 
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013EPA MEW Sampling Update, Moffett RAB, November 14, 2013
EPA MEW Sampling Update, Moffett RAB, November 14, 2013
 
Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013Site 28 Update, Moffett RAB, November 14, 2013
Site 28 Update, Moffett RAB, November 14, 2013
 
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
US Army Corps of Engineers BUILDING STRONG® Air Sampling at the Former Orion ...
 
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and OpportunitiesHazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
Hazardous Substances at Moffett Field’s Hangar One: Challenges and Opportunities
 
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
Hangar One and Moffett Federal Airfield Leasing Opportunity Request for Propo...
 
Site 28 Supplemental Investigation
Site 28 Supplemental InvestigationSite 28 Supplemental Investigation
Site 28 Supplemental Investigation
 
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion UpdateMoffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
Moffett RAB: EPA Regional Groundwater and Vapor Intrusion Update
 
Laser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs MonitoringLaser based Spectrometer for VOCs Monitoring
Laser based Spectrometer for VOCs Monitoring
 
Site 25 rab nov 29 2012
Site 25 rab nov 29 2012Site 25 rab nov 29 2012
Site 25 rab nov 29 2012
 
Moffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion UpdateMoffett RAB Presentation: Vapor Intrusion Update
Moffett RAB Presentation: Vapor Intrusion Update
 

Kürzlich hochgeladen

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptxSherlyMaeNeri
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Celine George
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 

Kürzlich hochgeladen (20)

Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Judging the Relevance and worth of ideas part 2.pptx
Judging the Relevance  and worth of ideas part 2.pptxJudging the Relevance  and worth of ideas part 2.pptx
Judging the Relevance and worth of ideas part 2.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
Incoming and Outgoing Shipments in 3 STEPS Using Odoo 17
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 

Moffett Hangar One Removal Action Update

  • 1. Former NAS Moffett Field Hangar 1 Removal Action Update Bryce Bartelma, PG Navy BRAC PMO West November 3, 2011 RAB Meeting 1
  • 2. Presentation Overview • Project Objective • Progress Update  Continued Monitoring  Roof, Redwood, Siding & and Protection Window Removal Measures  Coating Inspections &  Historic Mitigation/CARP Touch-ups  Scaffolding Installation  Moving Scaffolding • Schedule • Questions 2
  • 3. Project Objective • Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 3
  • 4. Continued Monitoring and Protection Measures • No observed impacts to biological activity • Continued storm water and ground surface protection • Navy and NASA air monitoring data demonstrates control of air emissions 4
  • 5. EPA and Water Board Site Inspection 5
  • 6. Hangar 1 Interactive CD • Delay in final production. CD will contain interactive history and interviews but not 3-D tour. • Navy and NASA looking into a web based version that will be hosted by NASA website and will contain both the interactive materials and 3-D tour! 6
  • 9. Continued Silver Siding Removal (Robertson Protected Metal) 9
  • 10. Window and Door Removal 10
  • 11. Zone 1 Exterior Coating & Touch-ups • Use of man lifts for lower level touch-ups 11
  • 12. Zone 2 East Progress – September 7 12
  • 13. Zone 2 East Progress – September 20 13
  • 14. Zone 2 East Progress – October 12 14
  • 15. Zone 2 West Progress – September 6 15
  • 16. Zone 2 West Progress – October 3 16
  • 17. Zone 2 West Progress – October 12 17
  • 20. Installing Systems Scaffolding & Quick Deck in Zone 6 20
  • 21. Clam Shell Door Mechanisms 21
  • 22. Fiber Board Removal • Fiber boards surround tracks of Clam Shell doors • Recently sampled and determined to contain contamination • Not structural • Navy to remove boards but keep rails in-place • NASA to consider replacement in re-use 22
  • 23. Special Visitor at Moffett 23
  • 24. Schedule • Fieldwork in zones 1 – 6 Ongoing • Complete fieldwork, confirmation sampling and demobilize Spring/Summer 2012 • Submit After Action Completion Report Summer/Fall 2012 24
  • 25. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 25