Productivity Improvement in
WABCO Production Line
3
(1.0) TEAM
1. D.RADHAKRISHNAN LEADER OPERATION
2. V.TAMARAISELVAN MEMBER QA & TQM
3 . A.PAULRAJ MEMBER PRODUCTION
4. T.SIVARAMAPRASATH MEMBER ENGINEERING
5 D.SANTHANABHARATHI MEMBER PRODUCTION&Quality
6. ANTHONYSAMY MEMBER QUALTIY
7. V.SUSHIL RAJ MEMBER MAINTANANCE
8. A.PALANIVEL MEMBER PRODUCTION
VENUE : CONFERENCE HALL-KKLR
FREQUENCY : EVERY SATURDAY
TIME : 11.00 AM to 12.00 NOON
 (1.1 ) - Team Attendance
6 13 20 27 3 10 17 24 1 8 15 22
D.RADHAKRISHNAN P P P P P P P P P P P P
A.PALANIVEL P P A P P P P P P P P P
A.ANTHONYSAMY P P P P P P P P P A P P
T.SIVARAMPRASATH P P P P P P A P P P P P
D.SANTHANABHARATHIP P P P P P P P P P P P
V.TAMARAISELVAN P P P P P P P P P P P P
A.PAULRAJ P P P P P P P P P P P P
V.SUSHILRAJ P P P P P P P P P P P P
Attendance % 96%
OCT'12 NOV'12 DEC'12
Members
1.1 Reason for improvement, selection and Linkage :
 Improve productivity
 To reduce WIP
 Reduce material handling and fatigue
 Linked in 2012-13 PD
1.1.3. Business Linkage :
Organizational
Capability
To achieve 100%
adherence
to external customer
6
1. To Improve the current productivity ( PMPD ).
2. To meet the increased customer requirement of 550
nos/shift from the current level of 430 nos /shift with
std. manpower
3. To reduce inventory in WIP.
4. To reduce internal Rejection and rework.
Reason for Improvement:
1.1.1 Identification:
•Metal Forming is one of the key supplier for Lucas TVS .
• In the present condition customer is not giving price compensation for
increase in power cost, consumable cost and man power cost. Also customer
is asking for price reduction. To improve the over all company performance,
improve the productivity is essential
• Hence our CFT was assigned to work on this improvement in productivity
through structured approach in line with the company’s objective.
1.1.2.1.Importance
 To sustain the market share and Growth
 Continuous improvement in productivity
8
1.2. OVER ALL PLAN
6 13 20 27 3 10 17 24 1 8 15 22
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN ACTUAL
6 A
C
T7
Counter Measures
Standardisation
Future Plan
5
4
Current Situtation
Analysis
D
O
CHECK Results
1
2
3
Dec'12
Reason for
Improvement
SL.NO
P
L
A
N
DESCRIPTION
Oct'12 Nov'12
9
1.3.1 Data Collection-Current process flow
Cutting Deburr CNC-1
CNC-2
Milling
De
burr
Gimbin
g-1
Gimbin
g-2
Inspen Leak test Dispatch
CNC-3
Milling
-2
WIP is maintained in Cutting, CNC, Milling and Gimping process.
Total Man Power - 13
10
Opn.no Operation Cycle time
10 Cutting 25
20 De burring 15
30 CNC-1 75
30 CNC-2 75
30 CNC-3 75
40 Milling-1 40
40 Milling-2 40
50 De burring 15
60 Gimbing-1 30
70 Gimbing-2 15
80 Inspection 15
90 Leak test 15
100 Dispatch 15
1.3.2 Data Collection-Current Cycle Time
11
1.3.3 Interpretation of the data
Cycle Time, 25
Cycle Time, 15
Cycle Time, 75
Cycle Time, 40Cycle Time, 15
Cycle Time, 30
Cycle Time, 15
Cycle Time, 25
Cycle
Time, 15
Cycle Time
1 Tube Cutting Soco cutting
2 Deburring Manual
3 CNC Turning CNC Machine
4 Milling Milling Machine
5 Milling Deburring Manual
6 Gimping-1 SPM-1
7 Gimping-2 SPM-2
8 Final Inspection FQA Table
9 Leak Test Tester
12
1.3.4 Data collection
Series1
65%
70%
75%
80%
85%
Series1
Series1 80% 72% 72%
Employee Ef f % M/ CEf f % Line Ef f %
13
1.3.5 Data collection - WIP
0
0.5
1
1.5
2
2.5
WIP - Actual Days WIP - Plan Days
WIP - Actual Days 1 1.5 2 2 1.5 1.5
WIP - Plan Days 1 1 1 1 1 1
Apr'12 May'12 Jun'12 Jul'12 Aug'12 Sep'12
0
10
20
30
40
50
60
PMPD-Actual PMPD -Target
PMPD-Actual 40 42 40 42 42 40
PMPD -Target 52 52 52 52 52 52
Apr'12 May'12 Jun'12 Jul'12 Aug'12 Sep'12
1.3.6 Data collection - PMPD
15
1.3.7 problem definition
•Line out put is controlled by CNC Machine ( Current output is
around 430 nos / shift, so line balancing is required to match the
other line output)
• To meet the customer increased demand of 550 nos/shift, the
following machines output is to be improved with std. manpower
1. CNC turning machine
2. Milling machine
3. Gimping machine
•WIP is high due to imbalance output which creates
rejection/rework
•More material handling and unsafe practices due to poor
layout
16
1.3.8. TARGET SETTING:
• To improve the productivity from 40 to 60
PMPD by Jan’13 – by 50%
17
S.no Details Plan Actual (Avg)
1 Line output /day 600 430
2 Total manpower /day 9 13
3 No. of M/cs 9 9
4 Employee productivity 52 42
5 M/C productivity 66 48
6 Line efficiency 90% 72%
7 WIP 0 days 1.5 /2 days
8 Rework /Rejection 5000 PPM 25000 PPM
Period : Apr.2012 to Sep.2012
1.4.1 segregation of data.
Observed Employee and machine productivity is low.
Observed more rework in rusting of yoke and more scrap
in handling damage
18
1.4.2 Brainstorming: ( low productivity)
1.Cycletime high in CNC machine (waiting time)
2.Change overtime more-insert change( Waiting Time)
3. Low hardness material leads to more burr removal ( Waiting Time)
4.Absentism (waiting Time)
5.Availability of skilled manpower ( Defect)
6. Tool down time ( waiting Time)
7. Machine break down ( Waiting Time)
8.Tool life low ( Waiting Time)
9.M/c stoppage due to imbalance output ( Waiting Time)
10.Morematerial in between the stages (Un necessary movement)
11. Rejection in CNC ( Defect)
12. Rework due to improper storage (Defect)
13. Poor handling of materials ( Un necessary movement)
19
1.4.2 Brainstorming: ( low productivity)
•In correct machine / hand tools used ( Low Production)
•Process not operated properly ( Low production)
•Non optimal lay out with wasted movements ( Un necessary movement)
•Working method causes wasted movements ( Un necessary movement)
•Excessive variation /lack of standardization of product ( Low Production)
•In correct quality standards ( Defect)
•No plan for flow of work ( Un necessary movement)
•Improper supply of material /equipment ( Low Production)
•Improper maintenance of plant /equipments /tools (Low Production)
•Improper working condition resulting in interrupted work ( Low Production)
•Failing to observe safety standards ( Un safe)
•Careless workmanship causing rework /rejection ( Defect)
20
1.4.3 Identifying causes and root causes:
Method
Man/supplier
Erractic
Cycle Time
Erractic
Cycle Time
Machine & Tool
Material
More absentizam
Carless workman ship
causes rework / reject
Change over time
No plan for flow of
Work
No safety standard
follow
Cycle time High
CNC chipping issue
Machine Break down
Tool Life Low
In correct m/c or
hand tool
Process not operated
properly
Improper
Maintenance
Improper working
condition
More absentizam
Down time due to
imbalance output
More material
movement
Improper storage
Poor handling of
material
In correct quality
standard
Low hardness
material – More burr
Rejection due to Poor
RM quality
Improper supply of
material
21
1.4.2 Brainstorming: ( Validation &Grouping )
•Validation of causes was carried out in the shop floor by the
team and the causes were grouped under major categories as
per below :
•Over production (Imbalanced cycle time)
•Defects / Rework / Rejection
•Unnecessary movements
•Unnecessary material movement
•Un necessary man movement (inspection)
•Waiting time
•M/c waiting time
•Operator waiting time
•Matl.waiting time
22
1.4.3 Identifying causes and root causes:
Method
Man/supplier
Erractic
Cycle Time
Erractic
Cycle Time
Machine & Tool
Material
Man waiting time / more
movement
Cycle time(high)
More material
movement
Un necessary
Movement
Defect /
Rework/Rejection
Material Waiting time
CNC chipping issue
23
1.4.Root cause Analysis :
Cause Why1 Why2 Why3 Why4 Why5 Countermeasure
1.Over
Production in
line
Imbalanced
output
Imbalanced
cycle time
Line balance through cycle
time study through DOE
2.Waiting
Time-Material
Material stock-
rework /
rejection
No control due
to over
production
-do-
Waiting Time-
Man
Skill not
available in
Critical m/c
More
absentizam
Planning for Multi
skilling / In built
inspection- Reduce
inspector movement
3.Unnecessary
man/material
movement
More space
between
machine
Initial layout Re layout
No proper
material
handling device
Method modification in
Line
4.Rejection /
Rework
Material
damage
Damage during
movement
Design suitable material
handling system
Damage during
-storage
Minimize/Avoid storage
24
1.4.1 Why-Why Analysis:
What? When? Who? How?
1.Line Balancing through
Cycle time optimization
in critical machine.
2.Reducing cycle time by
combine operations.
Nov’12 Palanivel /
Tamaraiselvan
A. Through DOE analysis :
1)Selection of critical parameters
2)Conducting trial /analysis
3) Finalizing the optimum parameters
B. Reduce loading and unloading
time.
2.Multiskilling Dec’12 Palanivel /
Anthony
1.Identification of critical machines
2.On the job training
3.Qualification of training /skill
4. Inbuilt inspection cell in the layout
to avoid inspector movement
3.Lay out modification Dec’12 Radha/
Sivaramaprasath/
Palanivel
1.Single piece flow concept is to be
adopted .
2.Cell concept
4.Design of suitable
matl. Handling system
Nov’12 Sushilraj 1.Chute type / conveyor type to be
followed
5. Material storage Dec’12 Anthony / Jothi 1.Plan for critical item only.
2. FG stock
25
1.4.2DOE –Study for Cycle Time Reduction:
M/C selected for trial : CNC
Factors selected : Speed , Feed, Depth of cut
No.of trials planned : 8 trials
Trial combination : as per table below
Code Parameter Current (-setting) Proposed (+ setting)
A Speed 2000 RPM 2500 RPM
B Feed 0.22 mm/sec 0.35 mm /sec
C Depth of Cut 0.50 mm 0.80 mm
26
1.4.3 DOE –Study - Results:
Sl.No Combination Rej
Cycle Time
in sec Rework Insert Life
Chip
Removal Output
1 A+R-(2000,0.22,0.50) No Rej 75 Nil OK Not Ok Low
2 B-R+( 0.22,2000,0.80) N/A N/A N/A
Insert
Broken N/A N/A
3 C+R-(0.80,2000,0.22) N/A N/A N/A
Insert
Broken N/A N/A
4 B+R-(0.35,0.50,2000) No Rej 70 Nil OK Not Ok Low
5 ALL-(2000,0.22,0.50) No Rej 75 Nil OK Not Ok Low
6 ALL+(2000,0.35,0.80) No Rej 60 Nil Ok Ok High
7 A-R+(2000,0.22,0.50) No Rej 75 Nil Ok Not Ok Low
8 C-R+(0.80,2000,0.22) N/A N/A N/A
Insert
Broken N/A N/A
Combination No-6 is optimized for process parameters
27
Sl.No Combination Rej
Cycle Time
in sec Rework Insert Life
Chip
Removal Output
6 ALL+(2000,0.35,0.80) No Rej 60 Nil Ok Ok High
Process validation with new parameters:
Cycle time : Reduced from 75 sec to 65 sec
Output achieved :540 no’s / Shift
Trial results with below combination
Date
11-
Mar'13
12-
Mar'13
13-
Mar'13
14-
Mar'13
15-
Mar'13
16-
Mar'13
Avera
ge
Output 1600 1432 1527 1547 1872 1800 1630
Man Power 24 21 24 24 24 24 24
PMPD 67 68 64 64 78 75 69
Rejection 14 13 15 14 12 12 13
PPM 8750 9078 9823 9050 6410 6667 8296
28
Before After
Collet designed for single time
Loading- Cycle Time 55 sec
( Deskilling )
AFTERBEFORE
Collet designed for two times
Loading- Cycle time- 65 sec
1.4.4 Reduce cycle time in loading /unloading method:
-Collet modification in CNC
29
1.4.5 Combining Operation in cutting & Deburring:
Before After
Deburring by machine
combined with cutting operator
No separate manpower for de burring
AFTERBEFORE
Deburribg the tube by manual-
1 Man power used
30
1.4.6 Cycle Time Reduction through Hydraulic pump speed improvement:
Before After
Cycle time reduced to 20 sec
( Balanced with Gimping-2)
AFTERBEFORE
Cycle Time in Gimping-1
is 35 sec
Low Speed Pump in
Gimping SPM – 10
LBM
31
1.4.7 Cycle Time reduction in milling machine – Loading time reduction
through fixture improvement
Before After
Loading Time reduced – 5 sec
Deskilling by introducing
sensor and V block.
AFTERBEFORE Loading Time-15 sec
No V Block in Milling
Wise
32
1.4.8 Layout Modification:
Before After
Cell Type Layout – 1500 Sq. FeetAFTERBEFORE
Linear Layout- ( Cris cross material
flow, stage wise WIP,
Indirect man power used
for material movement
33
1.4.9 Layout Modification :
Before After
One operator running
two machines
AFTERBEFORE
Two operators running
two CNC machines
34
1.4.10 Layout Modification :
Before After
Length – 30 mtrs
Width – 5 mtrs
Area – 150 SQ.Mtrs
Length – 16 mtrs
Width – 5 mtrs
Area – 80 SQ.Mtrs
35
1.4.11 Modified Process flow:
Cutting Deburr
CNC-2
Millin
g
De
burr
Gimbing-
1
Gi
mb
ing
-2
Inspen
Leak
test
Dispatch
CNC-1
Cutting Deburr CNC-1
CNC-2
Milling
De
burr
Gimbin
g-1
Gimbin
g-2
Inspen Leak test Dispatch
CNC-3
Milling
-2
x x
8 Man Power used currently
13 Man Power used Earlier
36
1.4.12 .Material Handling Improvement:
Before After
Conveyor provided from CNC to
Milling Machine
AFTERBEFORE No conveyor from CNC to Milling
No Conveyor. Parts
loaded and moved
by trays
37
1.4.14. Material Handling Improvement:
Before After
Material Automatically moved
through chute.
No man power used
AFTERBEFORE
Parts batched in Bins.
In direct people moves materials
to next station
38
1.4.15.WIP Control and material storage :
Before After
No WIP .
In process material only
In chute
AFTERBEFORE WIP at every stage in Bins
39
1.4.16 Material Handling Reduction
Before After
Near to cutting machine staking
stand provided
AFTERBEFORE
No staking stand near cutting
machine
40
2.1.7. REVIEW OF WORKS AS PER PLAN:
S.no Activity Resp
Implemented
from
Vendor Status
1 Cutting deburring by M/C Sushil
Nov-12
Ravi tools Implemented
2
Conveyor provided for material
movement
Santhana Bharathi Nov-12 Hari Fabrication Implemented
3 Staking stand near cutting M/C Paulraj Nov-12
Hari Fabrication
Implemented.
4 CNC L-type location Palanivel Nov-12 Inhouse Implemented
41
2.1.7. REVIEW OF WORKS AS PER PLAN:
S.no Activity Resp
Implemented
from
Vendor Status
5 Conveyor from CNC to milling Jothilingam
Dec-12
Inhouse Implemented
6
Guage Provided near wabco
CNC
Antony Dec-12 Revathi Engg Implemented
7 Collet design for Wabco Devendran/Palanivel Dec-12
Revathi Engg
Implemented.
8 V-Block provided in milling M/c Palanivel Dec-12 Inhouse Implemented
42
2.1.7. REVIEW OF WORKS AS PER PLAN:
S.no Activity Resp
Implemented
from
Vendor Status
9
ON/OFF sensor Provided in
Milling M/c
Palanivel
Dec-12
Inhouse Implemented
10
Speed Increased in
Gimping M/c-II
Sushil/Jothi Dec-12 Inhouse Implemented
11 Linear to cell type layout Santhana bharathi Dec-12
Revathi Engg
Implemented.
4 V-Block provided in milling M/c Palanivel Dec-12 Inhouse Implemented
43
3.1.4. OVER ALL PLAN Plan Vs Actual
6 13 20 27 3 10 17 24 1 8 15 22
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN
ACTUAL
PLAN ACTUAL
6 A
C
T7
Counter Measures
Standardisation
Future Plan
5
4
Current Situtation
Analysis
D
O
CHECK Results
1
2
3
Dec'12
Reason for
Improvement
SL.NO
P
L
A
N
DESCRIPTION
Oct'12 Nov'12
44
3.1.1. RESULTS ACHIEVED
 Cycle Time reduction Achieved
 PMPD Improved
 Cost Saving Achieved
 Inventory (WIP ) Reduced
 Accident Reduced
3. RESULTS :
45
Opn.no Operation Before After Remarks
10 Cutting 25 25 One man
operating both
m/c
20 De burring 15 05
30 CNC-1 75 65 Machine
Removed
30 CNC-2 75 65 One man
operating both
m/c
30 CNC-3 75 0
40 Milling-1 40 0 M/C Removed
40 Milling-2 40 40 One man
operating both
m/c
50 De burring 15 15
60 Gimbing-1 30 15
70 Gimbing-2 15 15
80 Inspection 15 15
90 Leak test 15 15
100 Dispatch 15 15
3.1.Result : Cycle Time reduction
46
S.no Details Before After
1 Line output /day 430 540
2 Total manpower /day 13 8
3 No. of M/cs 10 8
4 Employee productivity 33 67
5 M/C productivity 43 67
6 Line efficiency 72% 90%
7 WIP 1.5 /2 days 0 days
8 Rework /Rejection 25000 PPM 8500 PPM
3.1.2 Results :
3.1.3 Results:
• Saving through man power
• Before – 13 for 430 no’s/ Shift
• After – 8 for 540 no’s / Shift
• Man power reduction / Shift - 5
• Man Power reduction/ day – 15
• Average CTC / person- Rs.6000/-(Rs.250/Day)
• Man Power cost / Part – Rs.7.50( Before)-(=250*13/430)
• Man Power Cost / Part ( After) – Rs.3.70 ( =250*8/540)
• Man Power Cost Saving/ Part – Rs.3.80
• Savings ( Jan’13-Mar’13 ) – Rs.3.99 Lakhs ( 1.05 Lakhs
Production)
• Estimated saving / Year – Rs.20 Lakhs
( estimated dispatch2013-14- 5 Lakhs number)
3.1.4 Results – Power Saving
• Power saving ( 1 CNC
and 1 Milling m/c) – Rs
2.0 Lakhs per annum
Machine KVA KW
Load
Factor Units/ Hr Unit/Mon Unit Cost
Power cost /
Annum
in L
ACE CNC 16 14 25% 3 1700 12 2
3.1.5 Results – In House Rejection
• Saving due to reduction in house rejection and
rework-Rs17000/ month (rework cost and
rejected part cost)
( When 25000 PPM the part reject is 750 no’s
(out of that 250 no’s scrap) s and now with 8500
PPM the rejection is 255 no’s( 102 no’s scraped)
Cost saving= (250XRs114.08) – ( 102XRs114.08)
= Rs.16883 / Month
3.1.6 Results – Capital equipment released:
• CNC turning machine – released for Swift Desire
yoke production and Bajaj yoke Production –
Rs.10 Lakhs approx
• Milling machine released for New Light weight
Wabco Yoke – Rs.1.0 Lakhs approx
3.1.7 Results – WIP reduction:
WIP Inventory reduced from 2 days to Zero days
0
0.2
0.4
0.6
0.8
1
1.2
WIP - Actual Days WIP - Plan Days
WIP - Actual Days 0 0 0
WIP - Plan Days 1 1 1
Jan'13 Feb'13 Mar'13
52
3.1.1. RESULTS ACHIEVED
3.1.8. RESULTS :
0
10
20
30
40
50
60
70
80
PMPD-Actual PMPD -Target
PMPD-Actual 62 65 65 67
PMPD -Target 52 52 52 52
Dec'12 Jan'13 Feb'13 Mar'13
53
4.1.1 – Documentation &
Standardization
 Work instruction changed.
 Updated in Control Plan FMEA and Process Flow
4.1.2 – Preventive measures4.1.2 – Preventive measures
 Safety Guards provided in Cutting machine to avoid accident
 5’S improvement taken care
 Visual control displayed
55
4.1.3 - Replication
 85 mm Frame Line
56
 Productivity improvement in 125 Transfer Press
Line
 Linked with PD 12-13
Resource conservation
 Cost reduction in terms of minimize in man
power and increase in productivity.
5.0 - FUTURE PLAN
TEAMS NEXT PROJECT
REASON
57
6.1.0. METHODS USED TO IMPROVE THE PRODUCTIVITY:
Category Description
CNC TURNING Combined operation
Overall Layout Cell type concept – Single piece flow
58
6.2.1 - To the Customer6.2.1 - To the Customer
 Satisfaction & requirement fulfilled
6.2.2 - To the Company6.2.2 - To the Company
 Cell concept introduced to reduce the movement
 Continuous improvement
 WIP Reduced from 2 days to 0 day
 Time saving
6.2.3 - To the Individual6.2.3 - To the Individual
 Team work
 Commitment
 Process knowledge
6.2 – Intangible Benefits
.1 –Tangible benefits (OSP) from Feb’13-Mar’13
SLNO Description Total in Lacs
1
Man Power Cost From Feb’13- Mar’13 –
2 months 1.8
   
  TOTAL 1.8
60

Weitere ähnliche Inhalte

Was ist angesagt?

LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1George Bowman
 
Herding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaHerding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaJohn Pettit
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die Nikunj Rana
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)Chris Cummins
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedureAdeeb Zaki
 
Final Presentation-2-23-12
Final Presentation-2-23-12Final Presentation-2-23-12
Final Presentation-2-23-12Keith Johnson
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
Paul brayman chronological
Paul brayman chronologicalPaul brayman chronological
Paul brayman chronologicalPaul Brayman
 
Lean Bski Essentials
Lean Bski EssentialsLean Bski Essentials
Lean Bski Essentialsbstawski
 
Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005D9 Process Improvement
 
Value stream mapping (future state)
Value stream mapping (future state)Value stream mapping (future state)
Value stream mapping (future state)nestor martinez
 
Glen &dimplex Process improvements
Glen &dimplex Process improvementsGlen &dimplex Process improvements
Glen &dimplex Process improvementsNigel Charles
 

Was ist angesagt? (20)

LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1LEAN TRANSFORMATION Final 1
LEAN TRANSFORMATION Final 1
 
SMED-Observation Training
SMED-Observation TrainingSMED-Observation Training
SMED-Observation Training
 
Herding Cats Using Lean Six Sigma
Herding Cats Using Lean Six SigmaHerding Cats Using Lean Six Sigma
Herding Cats Using Lean Six Sigma
 
CV_2016_rev_4_RW
CV_2016_rev_4_RWCV_2016_rev_4_RW
CV_2016_rev_4_RW
 
Smed smpl 1
Smed smpl 1Smed smpl 1
Smed smpl 1
 
SMED Jabil Juarez
SMED Jabil JuarezSMED Jabil Juarez
SMED Jabil Juarez
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)SBS - SMED Training (Set Up Reduction)
SBS - SMED Training (Set Up Reduction)
 
Standard operating procedure
Standard operating procedureStandard operating procedure
Standard operating procedure
 
The SMED Method by CLT Services
The SMED Method by CLT ServicesThe SMED Method by CLT Services
The SMED Method by CLT Services
 
Final Presentation-2-23-12
Final Presentation-2-23-12Final Presentation-2-23-12
Final Presentation-2-23-12
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
Paul brayman chronological
Paul brayman chronologicalPaul brayman chronological
Paul brayman chronological
 
How to reduce changeover loss
How to reduce changeover lossHow to reduce changeover loss
How to reduce changeover loss
 
jan eve resume final
jan eve resume finaljan eve resume final
jan eve resume final
 
Lean Bski Essentials
Lean Bski EssentialsLean Bski Essentials
Lean Bski Essentials
 
Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005Kaizen Blitz multicoat loading area April 2005
Kaizen Blitz multicoat loading area April 2005
 
Value stream mapping (future state)
Value stream mapping (future state)Value stream mapping (future state)
Value stream mapping (future state)
 
Glen &dimplex Process improvements
Glen &dimplex Process improvementsGlen &dimplex Process improvements
Glen &dimplex Process improvements
 

Andere mochten auch (20)

Les plus belles_photos_
Les plus belles_photos_Les plus belles_photos_
Les plus belles_photos_
 
6 opoderdojejum-130722112639-phpapp02
6 opoderdojejum-130722112639-phpapp026 opoderdojejum-130722112639-phpapp02
6 opoderdojejum-130722112639-phpapp02
 
Observaciones al proyecto de ley de educacion superior
Observaciones al proyecto de ley de educacion superiorObservaciones al proyecto de ley de educacion superior
Observaciones al proyecto de ley de educacion superior
 
Missions' Websites
Missions' WebsitesMissions' Websites
Missions' Websites
 
Endless runner game in unreal engine 4
Endless runner game in unreal engine 4Endless runner game in unreal engine 4
Endless runner game in unreal engine 4
 
Documents
DocumentsDocuments
Documents
 
Fitxa personal
Fitxa personalFitxa personal
Fitxa personal
 
Full assistència
Full assistènciaFull assistència
Full assistència
 
Plantilla exercici joc
Plantilla exercici   jocPlantilla exercici   joc
Plantilla exercici joc
 
Prueba1
Prueba1Prueba1
Prueba1
 
901
901901
901
 
Fitxa d'entrenament
Fitxa d'entrenamentFitxa d'entrenament
Fitxa d'entrenament
 
Presentación1
Presentación1Presentación1
Presentación1
 
TAREA
TAREATAREA
TAREA
 
FRS Final Agenda
FRS Final Agenda FRS Final Agenda
FRS Final Agenda
 
Carnaval en el Ecuador
Carnaval en el EcuadorCarnaval en el Ecuador
Carnaval en el Ecuador
 
Wordle!
Wordle!Wordle!
Wordle!
 
Trial
TrialTrial
Trial
 
Informações Técnicas
Informações TécnicasInformações Técnicas
Informações Técnicas
 
Fixa jugadors
Fixa jugadorsFixa jugadors
Fixa jugadors
 

Ähnlich wie SMC CFT 2012-13-IInd Half.

Overview of 3 day Lean & Kaizen Course Content
Overview of 3 day Lean & Kaizen Course ContentOverview of 3 day Lean & Kaizen Course Content
Overview of 3 day Lean & Kaizen Course ContentTimothy Wooi
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET Journal
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACJulian Kalac P.Eng
 
Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summaryguest524810
 
Production Performance Results Internet Sample
Production Performance Results   Internet SampleProduction Performance Results   Internet Sample
Production Performance Results Internet Sampleantonioharenas
 
Identifying, Mitigating and Eliminating Risk with an Asset Management Strategy
Identifying, Mitigating and Eliminating Risk with an Asset Management StrategyIdentifying, Mitigating and Eliminating Risk with an Asset Management Strategy
Identifying, Mitigating and Eliminating Risk with an Asset Management StrategyMike Poland, CMRP
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxmurugarajan001
 
Lean six sigma 3d
Lean six sigma 3dLean six sigma 3d
Lean six sigma 3dVarmahk
 
5 s and lean manufacturing
5 s and lean manufacturing5 s and lean manufacturing
5 s and lean manufacturingNouman Ali
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
Six-Sigma-Black-Belt-Project-sample
Six-Sigma-Black-Belt-Project-sampleSix-Sigma-Black-Belt-Project-sample
Six-Sigma-Black-Belt-Project-sampleDheerendra S Negi
 

Ähnlich wie SMC CFT 2012-13-IInd Half. (20)

Overview of 3 day Lean & Kaizen Course Content
Overview of 3 day Lean & Kaizen Course ContentOverview of 3 day Lean & Kaizen Course Content
Overview of 3 day Lean & Kaizen Course Content
 
5 Steps to implementing Lean
5  Steps to implementing Lean5  Steps to implementing Lean
5 Steps to implementing Lean
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
om
omom
om
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALAC
 
Baskaren Accomplishments Summary
Baskaren Accomplishments SummaryBaskaren Accomplishments Summary
Baskaren Accomplishments Summary
 
Production Performance Results Internet Sample
Production Performance Results   Internet SampleProduction Performance Results   Internet Sample
Production Performance Results Internet Sample
 
Identifying, Mitigating and Eliminating Risk with an Asset Management Strategy
Identifying, Mitigating and Eliminating Risk with an Asset Management StrategyIdentifying, Mitigating and Eliminating Risk with an Asset Management Strategy
Identifying, Mitigating and Eliminating Risk with an Asset Management Strategy
 
PROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptxPROCESS PLANNING 1.pptx
PROCESS PLANNING 1.pptx
 
Lean six sigma 3d
Lean six sigma 3dLean six sigma 3d
Lean six sigma 3d
 
5 s and lean manufacturing
5 s and lean manufacturing5 s and lean manufacturing
5 s and lean manufacturing
 
Lean - Tight Oil Design & Construction
Lean - Tight Oil Design & ConstructionLean - Tight Oil Design & Construction
Lean - Tight Oil Design & Construction
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
 
Six-Sigma-Black-Belt-Project-sample
Six-Sigma-Black-Belt-Project-sampleSix-Sigma-Black-Belt-Project-sample
Six-Sigma-Black-Belt-Project-sample
 

SMC CFT 2012-13-IInd Half.

  • 1. 1
  • 3. 3 (1.0) TEAM 1. D.RADHAKRISHNAN LEADER OPERATION 2. V.TAMARAISELVAN MEMBER QA & TQM 3 . A.PAULRAJ MEMBER PRODUCTION 4. T.SIVARAMAPRASATH MEMBER ENGINEERING 5 D.SANTHANABHARATHI MEMBER PRODUCTION&Quality 6. ANTHONYSAMY MEMBER QUALTIY 7. V.SUSHIL RAJ MEMBER MAINTANANCE 8. A.PALANIVEL MEMBER PRODUCTION VENUE : CONFERENCE HALL-KKLR FREQUENCY : EVERY SATURDAY TIME : 11.00 AM to 12.00 NOON
  • 4.  (1.1 ) - Team Attendance 6 13 20 27 3 10 17 24 1 8 15 22 D.RADHAKRISHNAN P P P P P P P P P P P P A.PALANIVEL P P A P P P P P P P P P A.ANTHONYSAMY P P P P P P P P P A P P T.SIVARAMPRASATH P P P P P P A P P P P P D.SANTHANABHARATHIP P P P P P P P P P P P V.TAMARAISELVAN P P P P P P P P P P P P A.PAULRAJ P P P P P P P P P P P P V.SUSHILRAJ P P P P P P P P P P P P Attendance % 96% OCT'12 NOV'12 DEC'12 Members
  • 5. 1.1 Reason for improvement, selection and Linkage :  Improve productivity  To reduce WIP  Reduce material handling and fatigue  Linked in 2012-13 PD 1.1.3. Business Linkage : Organizational Capability To achieve 100% adherence to external customer
  • 6. 6 1. To Improve the current productivity ( PMPD ). 2. To meet the increased customer requirement of 550 nos/shift from the current level of 430 nos /shift with std. manpower 3. To reduce inventory in WIP. 4. To reduce internal Rejection and rework. Reason for Improvement:
  • 7. 1.1.1 Identification: •Metal Forming is one of the key supplier for Lucas TVS . • In the present condition customer is not giving price compensation for increase in power cost, consumable cost and man power cost. Also customer is asking for price reduction. To improve the over all company performance, improve the productivity is essential • Hence our CFT was assigned to work on this improvement in productivity through structured approach in line with the company’s objective. 1.1.2.1.Importance  To sustain the market share and Growth  Continuous improvement in productivity
  • 8. 8 1.2. OVER ALL PLAN 6 13 20 27 3 10 17 24 1 8 15 22 PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL 6 A C T7 Counter Measures Standardisation Future Plan 5 4 Current Situtation Analysis D O CHECK Results 1 2 3 Dec'12 Reason for Improvement SL.NO P L A N DESCRIPTION Oct'12 Nov'12
  • 9. 9 1.3.1 Data Collection-Current process flow Cutting Deburr CNC-1 CNC-2 Milling De burr Gimbin g-1 Gimbin g-2 Inspen Leak test Dispatch CNC-3 Milling -2 WIP is maintained in Cutting, CNC, Milling and Gimping process. Total Man Power - 13
  • 10. 10 Opn.no Operation Cycle time 10 Cutting 25 20 De burring 15 30 CNC-1 75 30 CNC-2 75 30 CNC-3 75 40 Milling-1 40 40 Milling-2 40 50 De burring 15 60 Gimbing-1 30 70 Gimbing-2 15 80 Inspection 15 90 Leak test 15 100 Dispatch 15 1.3.2 Data Collection-Current Cycle Time
  • 11. 11 1.3.3 Interpretation of the data Cycle Time, 25 Cycle Time, 15 Cycle Time, 75 Cycle Time, 40Cycle Time, 15 Cycle Time, 30 Cycle Time, 15 Cycle Time, 25 Cycle Time, 15 Cycle Time 1 Tube Cutting Soco cutting 2 Deburring Manual 3 CNC Turning CNC Machine 4 Milling Milling Machine 5 Milling Deburring Manual 6 Gimping-1 SPM-1 7 Gimping-2 SPM-2 8 Final Inspection FQA Table 9 Leak Test Tester
  • 12. 12 1.3.4 Data collection Series1 65% 70% 75% 80% 85% Series1 Series1 80% 72% 72% Employee Ef f % M/ CEf f % Line Ef f %
  • 13. 13 1.3.5 Data collection - WIP 0 0.5 1 1.5 2 2.5 WIP - Actual Days WIP - Plan Days WIP - Actual Days 1 1.5 2 2 1.5 1.5 WIP - Plan Days 1 1 1 1 1 1 Apr'12 May'12 Jun'12 Jul'12 Aug'12 Sep'12
  • 14. 0 10 20 30 40 50 60 PMPD-Actual PMPD -Target PMPD-Actual 40 42 40 42 42 40 PMPD -Target 52 52 52 52 52 52 Apr'12 May'12 Jun'12 Jul'12 Aug'12 Sep'12 1.3.6 Data collection - PMPD
  • 15. 15 1.3.7 problem definition •Line out put is controlled by CNC Machine ( Current output is around 430 nos / shift, so line balancing is required to match the other line output) • To meet the customer increased demand of 550 nos/shift, the following machines output is to be improved with std. manpower 1. CNC turning machine 2. Milling machine 3. Gimping machine •WIP is high due to imbalance output which creates rejection/rework •More material handling and unsafe practices due to poor layout
  • 16. 16 1.3.8. TARGET SETTING: • To improve the productivity from 40 to 60 PMPD by Jan’13 – by 50%
  • 17. 17 S.no Details Plan Actual (Avg) 1 Line output /day 600 430 2 Total manpower /day 9 13 3 No. of M/cs 9 9 4 Employee productivity 52 42 5 M/C productivity 66 48 6 Line efficiency 90% 72% 7 WIP 0 days 1.5 /2 days 8 Rework /Rejection 5000 PPM 25000 PPM Period : Apr.2012 to Sep.2012 1.4.1 segregation of data. Observed Employee and machine productivity is low. Observed more rework in rusting of yoke and more scrap in handling damage
  • 18. 18 1.4.2 Brainstorming: ( low productivity) 1.Cycletime high in CNC machine (waiting time) 2.Change overtime more-insert change( Waiting Time) 3. Low hardness material leads to more burr removal ( Waiting Time) 4.Absentism (waiting Time) 5.Availability of skilled manpower ( Defect) 6. Tool down time ( waiting Time) 7. Machine break down ( Waiting Time) 8.Tool life low ( Waiting Time) 9.M/c stoppage due to imbalance output ( Waiting Time) 10.Morematerial in between the stages (Un necessary movement) 11. Rejection in CNC ( Defect) 12. Rework due to improper storage (Defect) 13. Poor handling of materials ( Un necessary movement)
  • 19. 19 1.4.2 Brainstorming: ( low productivity) •In correct machine / hand tools used ( Low Production) •Process not operated properly ( Low production) •Non optimal lay out with wasted movements ( Un necessary movement) •Working method causes wasted movements ( Un necessary movement) •Excessive variation /lack of standardization of product ( Low Production) •In correct quality standards ( Defect) •No plan for flow of work ( Un necessary movement) •Improper supply of material /equipment ( Low Production) •Improper maintenance of plant /equipments /tools (Low Production) •Improper working condition resulting in interrupted work ( Low Production) •Failing to observe safety standards ( Un safe) •Careless workmanship causing rework /rejection ( Defect)
  • 20. 20 1.4.3 Identifying causes and root causes: Method Man/supplier Erractic Cycle Time Erractic Cycle Time Machine & Tool Material More absentizam Carless workman ship causes rework / reject Change over time No plan for flow of Work No safety standard follow Cycle time High CNC chipping issue Machine Break down Tool Life Low In correct m/c or hand tool Process not operated properly Improper Maintenance Improper working condition More absentizam Down time due to imbalance output More material movement Improper storage Poor handling of material In correct quality standard Low hardness material – More burr Rejection due to Poor RM quality Improper supply of material
  • 21. 21 1.4.2 Brainstorming: ( Validation &Grouping ) •Validation of causes was carried out in the shop floor by the team and the causes were grouped under major categories as per below : •Over production (Imbalanced cycle time) •Defects / Rework / Rejection •Unnecessary movements •Unnecessary material movement •Un necessary man movement (inspection) •Waiting time •M/c waiting time •Operator waiting time •Matl.waiting time
  • 22. 22 1.4.3 Identifying causes and root causes: Method Man/supplier Erractic Cycle Time Erractic Cycle Time Machine & Tool Material Man waiting time / more movement Cycle time(high) More material movement Un necessary Movement Defect / Rework/Rejection Material Waiting time CNC chipping issue
  • 23. 23 1.4.Root cause Analysis : Cause Why1 Why2 Why3 Why4 Why5 Countermeasure 1.Over Production in line Imbalanced output Imbalanced cycle time Line balance through cycle time study through DOE 2.Waiting Time-Material Material stock- rework / rejection No control due to over production -do- Waiting Time- Man Skill not available in Critical m/c More absentizam Planning for Multi skilling / In built inspection- Reduce inspector movement 3.Unnecessary man/material movement More space between machine Initial layout Re layout No proper material handling device Method modification in Line 4.Rejection / Rework Material damage Damage during movement Design suitable material handling system Damage during -storage Minimize/Avoid storage
  • 24. 24 1.4.1 Why-Why Analysis: What? When? Who? How? 1.Line Balancing through Cycle time optimization in critical machine. 2.Reducing cycle time by combine operations. Nov’12 Palanivel / Tamaraiselvan A. Through DOE analysis : 1)Selection of critical parameters 2)Conducting trial /analysis 3) Finalizing the optimum parameters B. Reduce loading and unloading time. 2.Multiskilling Dec’12 Palanivel / Anthony 1.Identification of critical machines 2.On the job training 3.Qualification of training /skill 4. Inbuilt inspection cell in the layout to avoid inspector movement 3.Lay out modification Dec’12 Radha/ Sivaramaprasath/ Palanivel 1.Single piece flow concept is to be adopted . 2.Cell concept 4.Design of suitable matl. Handling system Nov’12 Sushilraj 1.Chute type / conveyor type to be followed 5. Material storage Dec’12 Anthony / Jothi 1.Plan for critical item only. 2. FG stock
  • 25. 25 1.4.2DOE –Study for Cycle Time Reduction: M/C selected for trial : CNC Factors selected : Speed , Feed, Depth of cut No.of trials planned : 8 trials Trial combination : as per table below Code Parameter Current (-setting) Proposed (+ setting) A Speed 2000 RPM 2500 RPM B Feed 0.22 mm/sec 0.35 mm /sec C Depth of Cut 0.50 mm 0.80 mm
  • 26. 26 1.4.3 DOE –Study - Results: Sl.No Combination Rej Cycle Time in sec Rework Insert Life Chip Removal Output 1 A+R-(2000,0.22,0.50) No Rej 75 Nil OK Not Ok Low 2 B-R+( 0.22,2000,0.80) N/A N/A N/A Insert Broken N/A N/A 3 C+R-(0.80,2000,0.22) N/A N/A N/A Insert Broken N/A N/A 4 B+R-(0.35,0.50,2000) No Rej 70 Nil OK Not Ok Low 5 ALL-(2000,0.22,0.50) No Rej 75 Nil OK Not Ok Low 6 ALL+(2000,0.35,0.80) No Rej 60 Nil Ok Ok High 7 A-R+(2000,0.22,0.50) No Rej 75 Nil Ok Not Ok Low 8 C-R+(0.80,2000,0.22) N/A N/A N/A Insert Broken N/A N/A Combination No-6 is optimized for process parameters
  • 27. 27 Sl.No Combination Rej Cycle Time in sec Rework Insert Life Chip Removal Output 6 ALL+(2000,0.35,0.80) No Rej 60 Nil Ok Ok High Process validation with new parameters: Cycle time : Reduced from 75 sec to 65 sec Output achieved :540 no’s / Shift Trial results with below combination Date 11- Mar'13 12- Mar'13 13- Mar'13 14- Mar'13 15- Mar'13 16- Mar'13 Avera ge Output 1600 1432 1527 1547 1872 1800 1630 Man Power 24 21 24 24 24 24 24 PMPD 67 68 64 64 78 75 69 Rejection 14 13 15 14 12 12 13 PPM 8750 9078 9823 9050 6410 6667 8296
  • 28. 28 Before After Collet designed for single time Loading- Cycle Time 55 sec ( Deskilling ) AFTERBEFORE Collet designed for two times Loading- Cycle time- 65 sec 1.4.4 Reduce cycle time in loading /unloading method: -Collet modification in CNC
  • 29. 29 1.4.5 Combining Operation in cutting & Deburring: Before After Deburring by machine combined with cutting operator No separate manpower for de burring AFTERBEFORE Deburribg the tube by manual- 1 Man power used
  • 30. 30 1.4.6 Cycle Time Reduction through Hydraulic pump speed improvement: Before After Cycle time reduced to 20 sec ( Balanced with Gimping-2) AFTERBEFORE Cycle Time in Gimping-1 is 35 sec Low Speed Pump in Gimping SPM – 10 LBM
  • 31. 31 1.4.7 Cycle Time reduction in milling machine – Loading time reduction through fixture improvement Before After Loading Time reduced – 5 sec Deskilling by introducing sensor and V block. AFTERBEFORE Loading Time-15 sec No V Block in Milling Wise
  • 32. 32 1.4.8 Layout Modification: Before After Cell Type Layout – 1500 Sq. FeetAFTERBEFORE Linear Layout- ( Cris cross material flow, stage wise WIP, Indirect man power used for material movement
  • 33. 33 1.4.9 Layout Modification : Before After One operator running two machines AFTERBEFORE Two operators running two CNC machines
  • 34. 34 1.4.10 Layout Modification : Before After Length – 30 mtrs Width – 5 mtrs Area – 150 SQ.Mtrs Length – 16 mtrs Width – 5 mtrs Area – 80 SQ.Mtrs
  • 35. 35 1.4.11 Modified Process flow: Cutting Deburr CNC-2 Millin g De burr Gimbing- 1 Gi mb ing -2 Inspen Leak test Dispatch CNC-1 Cutting Deburr CNC-1 CNC-2 Milling De burr Gimbin g-1 Gimbin g-2 Inspen Leak test Dispatch CNC-3 Milling -2 x x 8 Man Power used currently 13 Man Power used Earlier
  • 36. 36 1.4.12 .Material Handling Improvement: Before After Conveyor provided from CNC to Milling Machine AFTERBEFORE No conveyor from CNC to Milling No Conveyor. Parts loaded and moved by trays
  • 37. 37 1.4.14. Material Handling Improvement: Before After Material Automatically moved through chute. No man power used AFTERBEFORE Parts batched in Bins. In direct people moves materials to next station
  • 38. 38 1.4.15.WIP Control and material storage : Before After No WIP . In process material only In chute AFTERBEFORE WIP at every stage in Bins
  • 39. 39 1.4.16 Material Handling Reduction Before After Near to cutting machine staking stand provided AFTERBEFORE No staking stand near cutting machine
  • 40. 40 2.1.7. REVIEW OF WORKS AS PER PLAN: S.no Activity Resp Implemented from Vendor Status 1 Cutting deburring by M/C Sushil Nov-12 Ravi tools Implemented 2 Conveyor provided for material movement Santhana Bharathi Nov-12 Hari Fabrication Implemented 3 Staking stand near cutting M/C Paulraj Nov-12 Hari Fabrication Implemented. 4 CNC L-type location Palanivel Nov-12 Inhouse Implemented
  • 41. 41 2.1.7. REVIEW OF WORKS AS PER PLAN: S.no Activity Resp Implemented from Vendor Status 5 Conveyor from CNC to milling Jothilingam Dec-12 Inhouse Implemented 6 Guage Provided near wabco CNC Antony Dec-12 Revathi Engg Implemented 7 Collet design for Wabco Devendran/Palanivel Dec-12 Revathi Engg Implemented. 8 V-Block provided in milling M/c Palanivel Dec-12 Inhouse Implemented
  • 42. 42 2.1.7. REVIEW OF WORKS AS PER PLAN: S.no Activity Resp Implemented from Vendor Status 9 ON/OFF sensor Provided in Milling M/c Palanivel Dec-12 Inhouse Implemented 10 Speed Increased in Gimping M/c-II Sushil/Jothi Dec-12 Inhouse Implemented 11 Linear to cell type layout Santhana bharathi Dec-12 Revathi Engg Implemented. 4 V-Block provided in milling M/c Palanivel Dec-12 Inhouse Implemented
  • 43. 43 3.1.4. OVER ALL PLAN Plan Vs Actual 6 13 20 27 3 10 17 24 1 8 15 22 PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL PLAN ACTUAL 6 A C T7 Counter Measures Standardisation Future Plan 5 4 Current Situtation Analysis D O CHECK Results 1 2 3 Dec'12 Reason for Improvement SL.NO P L A N DESCRIPTION Oct'12 Nov'12
  • 44. 44 3.1.1. RESULTS ACHIEVED  Cycle Time reduction Achieved  PMPD Improved  Cost Saving Achieved  Inventory (WIP ) Reduced  Accident Reduced 3. RESULTS :
  • 45. 45 Opn.no Operation Before After Remarks 10 Cutting 25 25 One man operating both m/c 20 De burring 15 05 30 CNC-1 75 65 Machine Removed 30 CNC-2 75 65 One man operating both m/c 30 CNC-3 75 0 40 Milling-1 40 0 M/C Removed 40 Milling-2 40 40 One man operating both m/c 50 De burring 15 15 60 Gimbing-1 30 15 70 Gimbing-2 15 15 80 Inspection 15 15 90 Leak test 15 15 100 Dispatch 15 15 3.1.Result : Cycle Time reduction
  • 46. 46 S.no Details Before After 1 Line output /day 430 540 2 Total manpower /day 13 8 3 No. of M/cs 10 8 4 Employee productivity 33 67 5 M/C productivity 43 67 6 Line efficiency 72% 90% 7 WIP 1.5 /2 days 0 days 8 Rework /Rejection 25000 PPM 8500 PPM 3.1.2 Results :
  • 47. 3.1.3 Results: • Saving through man power • Before – 13 for 430 no’s/ Shift • After – 8 for 540 no’s / Shift • Man power reduction / Shift - 5 • Man Power reduction/ day – 15 • Average CTC / person- Rs.6000/-(Rs.250/Day) • Man Power cost / Part – Rs.7.50( Before)-(=250*13/430) • Man Power Cost / Part ( After) – Rs.3.70 ( =250*8/540) • Man Power Cost Saving/ Part – Rs.3.80 • Savings ( Jan’13-Mar’13 ) – Rs.3.99 Lakhs ( 1.05 Lakhs Production) • Estimated saving / Year – Rs.20 Lakhs ( estimated dispatch2013-14- 5 Lakhs number)
  • 48. 3.1.4 Results – Power Saving • Power saving ( 1 CNC and 1 Milling m/c) – Rs 2.0 Lakhs per annum Machine KVA KW Load Factor Units/ Hr Unit/Mon Unit Cost Power cost / Annum in L ACE CNC 16 14 25% 3 1700 12 2
  • 49. 3.1.5 Results – In House Rejection • Saving due to reduction in house rejection and rework-Rs17000/ month (rework cost and rejected part cost) ( When 25000 PPM the part reject is 750 no’s (out of that 250 no’s scrap) s and now with 8500 PPM the rejection is 255 no’s( 102 no’s scraped) Cost saving= (250XRs114.08) – ( 102XRs114.08) = Rs.16883 / Month
  • 50. 3.1.6 Results – Capital equipment released: • CNC turning machine – released for Swift Desire yoke production and Bajaj yoke Production – Rs.10 Lakhs approx • Milling machine released for New Light weight Wabco Yoke – Rs.1.0 Lakhs approx
  • 51. 3.1.7 Results – WIP reduction: WIP Inventory reduced from 2 days to Zero days 0 0.2 0.4 0.6 0.8 1 1.2 WIP - Actual Days WIP - Plan Days WIP - Actual Days 0 0 0 WIP - Plan Days 1 1 1 Jan'13 Feb'13 Mar'13
  • 52. 52 3.1.1. RESULTS ACHIEVED 3.1.8. RESULTS : 0 10 20 30 40 50 60 70 80 PMPD-Actual PMPD -Target PMPD-Actual 62 65 65 67 PMPD -Target 52 52 52 52 Dec'12 Jan'13 Feb'13 Mar'13
  • 53. 53 4.1.1 – Documentation & Standardization  Work instruction changed.  Updated in Control Plan FMEA and Process Flow
  • 54. 4.1.2 – Preventive measures4.1.2 – Preventive measures  Safety Guards provided in Cutting machine to avoid accident  5’S improvement taken care  Visual control displayed
  • 55. 55 4.1.3 - Replication  85 mm Frame Line
  • 56. 56  Productivity improvement in 125 Transfer Press Line  Linked with PD 12-13 Resource conservation  Cost reduction in terms of minimize in man power and increase in productivity. 5.0 - FUTURE PLAN TEAMS NEXT PROJECT REASON
  • 57. 57 6.1.0. METHODS USED TO IMPROVE THE PRODUCTIVITY: Category Description CNC TURNING Combined operation Overall Layout Cell type concept – Single piece flow
  • 58. 58 6.2.1 - To the Customer6.2.1 - To the Customer  Satisfaction & requirement fulfilled 6.2.2 - To the Company6.2.2 - To the Company  Cell concept introduced to reduce the movement  Continuous improvement  WIP Reduced from 2 days to 0 day  Time saving 6.2.3 - To the Individual6.2.3 - To the Individual  Team work  Commitment  Process knowledge 6.2 – Intangible Benefits
  • 59. .1 –Tangible benefits (OSP) from Feb’13-Mar’13 SLNO Description Total in Lacs 1 Man Power Cost From Feb’13- Mar’13 – 2 months 1.8       TOTAL 1.8
  • 60. 60