SlideShare ist ein Scribd-Unternehmen logo
1 von 24
Downloaden Sie, um offline zu lesen
© 2014 iZenBridge | CONFIDENTIAL
PMP is a registered trademark of the Project Management Institute, Inc.
Precedence Diagramming Method
(PDM)
Four Types of
Logical Relationships – PMP®
Prep Topic
Saket Bansal
© 2014 iZenBridge | CONFIDENTIAL
Dependencies
Type of logical relationship
between two activities
defines how the depended
activity is constrained by
independent activity
© 2014 iZenBridge | CONFIDENTIAL
Dependent Watching Independent
Independent
Activity start or
finish does not
get impacted
because of the
relation
Dependent
Activity Start or
Finish is
influenced by the
relation
Activity A Activity B
© 2014 iZenBridge | CONFIDENTIAL
Predecessor and Successor
A predecessor activity is an activity that logically comes
before a dependent activity in a schedule. A successor
activity is a dependent activity that logically comes after
another activity on a schedule
Independent /
Predecessor
Dependent /
Successor
Activity A Activity B
© 2014 iZenBridge | CONFIDENTIAL
Four Types of logical Relationships
• Finish-to-start (FS)
• Finish-to-finish (FF)
• Start-to-start (SS)
• Start-to-finish (SF)
© 2014 iZenBridge | CONFIDENTIAL
Two Digits / Four Types
State of Independent
(Activity A) Activity on
which activity B is
dependent on
Constraint on
Dependent
activity (Activity B)
applied on
Finish (F)
Start (S)
Finish (F)
Start (S)
© 2014 iZenBridge | CONFIDENTIAL
Four types of logical relationships
S
F/S
Someone
watching my
finish
F
F/S
S
I can not finish
until my
predecessor
condition is met
I can not start
until my
predecessor
condition is met
Someone
watching my
start
F
FS
SS
FF
SF
© 2014 iZenBridge | CONFIDENTIAL
Finish to Start (FS)
© 2014 iZenBridge | CONFIDENTIAL
Finish to start (FS)
“A logical relationship in which a successor activity
cannot start until a predecessor activity has
finished.”
Activity A Activity B
FS
Activity B is
watching my
finish date /
time I can not start
unit A
Finishes
© 2014 iZenBridge | CONFIDENTIAL
Finish to start (FS)
“A logical relationship in which a successor activity
cannot start until a predecessor activity has
finished.”
Activity A Activity B
FS
Activity B is
watching my
finish date /
time I can not start
until A
Finishes
F S
© 2014 iZenBridge | CONFIDENTIAL
Example: Finish to Start
Development Activity can not be started until design is
finished. The design activity is expected to take 4 days
and development will take 10 days
Design : 4
(Independent)
Development :10
(Dependent)
Early Finish 4Early Start 1
Early Start 5 Early Finish 14
FS
ES: Development
= Early Finish Design + 1
= 4+1
© 2014 iZenBridge | CONFIDENTIAL
Example: Finish to Start + Lag
Development Activity can not be started until one day
after design is finished. The design activity is expected to
take 4 days and development will take 10 days
Design : 4
(Independent)
Development:10
(Dependent)
Early Finish 4Early Start 1
Early Start 6 Early Finish 15
FS + 1
ES: Development
= Early Finish Design + 1 + Lag
= 4+1 + 1
© 2014 iZenBridge | CONFIDENTIAL
Example: Finish to Start - Lead
Development Activity can not be started until one day
before design is finishing. The design activity is expected
to take 4 days and development will take 10 days
Design : 4
(Independent)
Development: 10
(Dependent)
Finish 4Start 1
Start 4 Finish 13
FS - 1
ES: Development
= Early Finish Design + 1 - Lead
= 4+1 - 1
© 2014 iZenBridge | CONFIDENTIAL
Start-to-start (SS)
© 2014 iZenBridge | CONFIDENTIAL
Start-to-start (SS)
“A logical relationship in which a successor activity
cannot start until a predecessor activity has started.”
Activity A
Activity B
SS
Activity B is
watching my
Start date /
time
I can not start
until A Starts
S
S
© 2014 iZenBridge | CONFIDENTIAL
Example: Start-to-start (SS)
The activity of marketing brochure preparation can not start
until user documentation activity has started. The
marketing brochure preparation activity is expected to take
4 days and user manual preparation will take 10 days
User Docs:10
Brochure:
4
Early Start 1 Early Finish 10
Early
Start 1
Early
Finish 4
ES Brochure =
ES: User Doc +/- Lag/Lead
© 2014 iZenBridge | CONFIDENTIAL
Finish-to-finish (FF)
© 2014 iZenBridge | CONFIDENTIAL
Finish-to-finish (FF)
“A logical relationship in which a successor activity
cannot finish until a predecessor activity has
finished.”
Activity A
Activity B
FF
Activity B is
watching my
Finish date /
time
I can not
Finish until A
Finishes
F
F
© 2014 iZenBridge | CONFIDENTIAL
Example: Finish-to-finish (FF)
User Documentation activity can not finish
until development is finished. User
Documentation will take 10 days where
development will take 30 days.
Development: 30
User
Documentation
: 10
Early Start 1 Early Finish 30
Early
Finish 30
EF User Doc =
EF: Development +/- Lag/Lead
Early
Start 21
© 2014 iZenBridge | CONFIDENTIAL
Start-to-finish (SF)
© 2014 iZenBridge | CONFIDENTIAL
Start-to-finish (SF)
“A logical relationship in which a successor activity
cannot finish until a predecessor activity has
started.”
Activity A
Activity B
SF
Activity B is
watching my
Start date /
time
I can not
Finish until A
Starts
S
F
© 2014 iZenBridge | CONFIDENTIAL
Example Start-to-finish (SF)
Support activity from development team can
not finish until production support Activity is
started . Production support is expected to
start on day 15.
Production Support
Development
Support: 10
Early Start 15
Early
Finish 14
EF Development Support =
ES: Production Support -1 +/- Lag/Lead
© 2014 iZenBridge | CONFIDENTIAL
Four Types of Logical Relationships
• Finish-to-start (FS)
• Finish-to-finish (FF)
• Start-to-start (SS)
• Start-to-finish (SF)
© 2014 iZenBridge | CONFIDENTIAL
Stay Connected
YouTube
www.youtube.com/izenbridge
Saket.Bansal@iZenBridge.com
www.iZenBridge.com
forum.iZenBridge.com

Weitere ähnliche Inhalte

Was ist angesagt?

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)tomeh
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And ControllingTom Milner
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
project time management
 project time management project time management
project time managementHira Atiq
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 

Was ist angesagt? (20)

PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Project Monitoring And Controlling
Project Monitoring And ControllingProject Monitoring And Controlling
Project Monitoring And Controlling
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
project time management
 project time management project time management
project time management
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 

Andere mochten auch

PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Methodphantai24
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDMShaiful Amri Mansur
 
Precedence Diagram Method 2
Precedence Diagram Method 2Precedence Diagram Method 2
Precedence Diagram Method 2Nurul Angreliany
 
Workshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaWorkshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaSaket Bansal
 
Webinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeWebinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeSaket Bansal
 
Webinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeWebinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeSaket Bansal
 
Introduction of Project Management
Introduction of Project ManagementIntroduction of Project Management
Introduction of Project ManagementSaket Bansal
 
Webinar on Agile Metrics
Webinar on Agile Metrics Webinar on Agile Metrics
Webinar on Agile Metrics Saket Bansal
 
Lean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeLean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeSaket Bansal
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Saket Bansal
 
The Agile Way with PMI-ACP
The Agile Way with PMI-ACPThe Agile Way with PMI-ACP
The Agile Way with PMI-ACPEdureka!
 
Introduction to PMI-ACP
Introduction to PMI-ACPIntroduction to PMI-ACP
Introduction to PMI-ACPEdureka!
 
Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Saket Bansal
 
Agile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean wayAgile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean waySaket Bansal
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacksglibson rojer
 
Making a T-shirt in Second Life
Making a T-shirt in Second LifeMaking a T-shirt in Second Life
Making a T-shirt in Second LifeHeidi Trotta
 

Andere mochten auch (20)

PDM - Precedence Diagram Method
PDM - Precedence Diagram MethodPDM - Precedence Diagram Method
PDM - Precedence Diagram Method
 
Precedence Diagramming Method PDM
Precedence Diagramming Method PDMPrecedence Diagramming Method PDM
Precedence Diagramming Method PDM
 
Precedence Diagram Method 2
Precedence Diagram Method 2Precedence Diagram Method 2
Precedence Diagram Method 2
 
Network planning 1
Network planning 1Network planning 1
Network planning 1
 
Workshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) NoidaWorkshop on Test Driven Development (TDD) Noida
Workshop on Test Driven Development (TDD) Noida
 
Webinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridgeWebinar on Requirement Prioritization Process - iZenBridge
Webinar on Requirement Prioritization Process - iZenBridge
 
Webinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridgeWebinar On Collect Requirement - iZenBridge
Webinar On Collect Requirement - iZenBridge
 
Introduction of Project Management
Introduction of Project ManagementIntroduction of Project Management
Introduction of Project Management
 
Webinar on Agile Metrics
Webinar on Agile Metrics Webinar on Agile Metrics
Webinar on Agile Metrics
 
Lean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridgeLean , Pull System & Kanban |iZenBridge
Lean , Pull System & Kanban |iZenBridge
 
Net Work Planning (nwp)
Net Work Planning (nwp)Net Work Planning (nwp)
Net Work Planning (nwp)
 
Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar Procurement Contract Types | PMP | iZenBridge - Webinar
Procurement Contract Types | PMP | iZenBridge - Webinar
 
Project Management
Project ManagementProject Management
Project Management
 
Coaching Leadership
Coaching LeadershipCoaching Leadership
Coaching Leadership
 
The Agile Way with PMI-ACP
The Agile Way with PMI-ACPThe Agile Way with PMI-ACP
The Agile Way with PMI-ACP
 
Introduction to PMI-ACP
Introduction to PMI-ACPIntroduction to PMI-ACP
Introduction to PMI-ACP
 
Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability Lean India Summit : From Productivity to Profitability
Lean India Summit : From Productivity to Profitability
 
Agile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean wayAgile NCR : Starting your business in a lean way
Agile NCR : Starting your business in a lean way
 
Process of pre construction phase drawbacks
Process of pre construction phase drawbacksProcess of pre construction phase drawbacks
Process of pre construction phase drawbacks
 
Making a T-shirt in Second Life
Making a T-shirt in Second LifeMaking a T-shirt in Second Life
Making a T-shirt in Second Life
 

Ähnlich wie PMP : Precedence Diagram Method : Relationship Types | iZenBridge

Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010Abdul Ghaffar, PMP
 
Irene CV for October 2016
Irene CV for October 2016Irene CV for October 2016
Irene CV for October 2016irene O'Reilly
 
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...John Head
 
Finish Strong -- Successfully Rolling Out Your Killer QuickBase App
Finish Strong -- Successfully Rolling Out Your Killer QuickBase AppFinish Strong -- Successfully Rolling Out Your Killer QuickBase App
Finish Strong -- Successfully Rolling Out Your Killer QuickBase AppQuickBase, Inc.
 
Laimonas Lileika — Hybrid Project Management: Excellence Behind a Buzzword
Laimonas Lileika — Hybrid Project Management: Excellence Behind a BuzzwordLaimonas Lileika — Hybrid Project Management: Excellence Behind a Buzzword
Laimonas Lileika — Hybrid Project Management: Excellence Behind a BuzzwordAgileLAB
 
Integrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelIntegrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelAlan McSweeney
 
MohammedAli_Resume_2016
MohammedAli_Resume_2016MohammedAli_Resume_2016
MohammedAli_Resume_2016Mohammed Ali
 
20130312 The Zombies of Project Management
20130312 The Zombies of Project Management20130312 The Zombies of Project Management
20130312 The Zombies of Project ManagementYoussef Mourra
 
5 Traits of a Great Project Manager
5 Traits of a Great Project Manager5 Traits of a Great Project Manager
5 Traits of a Great Project ManagerBeyond20
 
Information Services Project Management Change Theme Update May 2017
Information Services Project Management Change Theme Update May 2017Information Services Project Management Change Theme Update May 2017
Information Services Project Management Change Theme Update May 2017Mark Ritchie
 
Lifecycle of a Service Project (Part 5): Evaluation and Promotion
Lifecycle of a Service Project (Part 5): Evaluation and PromotionLifecycle of a Service Project (Part 5): Evaluation and Promotion
Lifecycle of a Service Project (Part 5): Evaluation and PromotionRotary International
 

Ähnlich wie PMP : Precedence Diagram Method : Relationship Types | iZenBridge (20)

Tripod
TripodTripod
Tripod
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Irene CV for October 2016
Irene CV for October 2016Irene CV for October 2016
Irene CV for October 2016
 
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...
Intuit Quickbase Empower 2015 - Finish Strong: SUCCESSFULLLY ROLLING OUT YOUR...
 
Finish Strong -- Successfully Rolling Out Your Killer QuickBase App
Finish Strong -- Successfully Rolling Out Your Killer QuickBase AppFinish Strong -- Successfully Rolling Out Your Killer QuickBase App
Finish Strong -- Successfully Rolling Out Your Killer QuickBase App
 
Laimonas Lileika — Hybrid Project Management: Excellence Behind a Buzzword
Laimonas Lileika — Hybrid Project Management: Excellence Behind a BuzzwordLaimonas Lileika — Hybrid Project Management: Excellence Behind a Buzzword
Laimonas Lileika — Hybrid Project Management: Excellence Behind a Buzzword
 
CV
CVCV
CV
 
Webinar on Business Analysis in Project Context - PMI PBA
Webinar on Business Analysis in Project Context - PMI PBAWebinar on Business Analysis in Project Context - PMI PBA
Webinar on Business Analysis in Project Context - PMI PBA
 
MATERI SAYA.pdf
MATERI SAYA.pdfMATERI SAYA.pdf
MATERI SAYA.pdf
 
Integrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelIntegrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement Model
 
Msproject
MsprojectMsproject
Msproject
 
MohammedAli_Resume_2016
MohammedAli_Resume_2016MohammedAli_Resume_2016
MohammedAli_Resume_2016
 
20130312 The Zombies of Project Management
20130312 The Zombies of Project Management20130312 The Zombies of Project Management
20130312 The Zombies of Project Management
 
CV_Reynante Marquez
CV_Reynante MarquezCV_Reynante Marquez
CV_Reynante Marquez
 
SudhakarmosesMunnangi
SudhakarmosesMunnangiSudhakarmosesMunnangi
SudhakarmosesMunnangi
 
5 Traits of a Great Project Manager
5 Traits of a Great Project Manager5 Traits of a Great Project Manager
5 Traits of a Great Project Manager
 
Information Services Project Management Change Theme Update May 2017
Information Services Project Management Change Theme Update May 2017Information Services Project Management Change Theme Update May 2017
Information Services Project Management Change Theme Update May 2017
 
CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4CAPM Week 2 Chapter 4
CAPM Week 2 Chapter 4
 
Resume Al Cleverley 2016
Resume Al Cleverley 2016Resume Al Cleverley 2016
Resume Al Cleverley 2016
 
Lifecycle of a Service Project (Part 5): Evaluation and Promotion
Lifecycle of a Service Project (Part 5): Evaluation and PromotionLifecycle of a Service Project (Part 5): Evaluation and Promotion
Lifecycle of a Service Project (Part 5): Evaluation and Promotion
 

Mehr von Saket Bansal

Improving Collaboration by Awareness of Mind Games
Improving Collaboration by Awareness of  Mind GamesImproving Collaboration by Awareness of  Mind Games
Improving Collaboration by Awareness of Mind GamesSaket Bansal
 
Emotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeEmotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeSaket Bansal
 
Webinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionWebinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionSaket Bansal
 
Webinar on Leader As Coach
Webinar on Leader As Coach Webinar on Leader As Coach
Webinar on Leader As Coach Saket Bansal
 
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeWebinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeSaket Bansal
 
Webinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeWebinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeSaket Bansal
 
Plan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementPlan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementSaket Bansal
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementSaket Bansal
 
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...Saket Bansal
 
Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Saket Bansal
 
Agile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeAgile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeSaket Bansal
 
Technical Debt | PMI - ACP Webinar Series | iZenBridge
Technical Debt | PMI - ACP Webinar Series | iZenBridge Technical Debt | PMI - ACP Webinar Series | iZenBridge
Technical Debt | PMI - ACP Webinar Series | iZenBridge Saket Bansal
 
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...Saket Bansal
 
Webinar On Product Backlog
Webinar On Product BacklogWebinar On Product Backlog
Webinar On Product BacklogSaket Bansal
 
Scrum Webinar : Sprints - The Exploration Cycle
Scrum Webinar : Sprints - The Exploration CycleScrum Webinar : Sprints - The Exploration Cycle
Scrum Webinar : Sprints - The Exploration CycleSaket Bansal
 
PMP : Webinar on Quality Planning
PMP : Webinar  on Quality PlanningPMP : Webinar  on Quality Planning
PMP : Webinar on Quality PlanningSaket Bansal
 
Webinar : Scrum Roles
Webinar :  Scrum RolesWebinar :  Scrum Roles
Webinar : Scrum RolesSaket Bansal
 
Why Agile | Agile Values and Principles
Why Agile | Agile Values and PrinciplesWhy Agile | Agile Values and Principles
Why Agile | Agile Values and PrinciplesSaket Bansal
 
Writing User Stories : Agile Way of Capturing Requirements
Writing User Stories : Agile Way of Capturing Requirements Writing User Stories : Agile Way of Capturing Requirements
Writing User Stories : Agile Way of Capturing Requirements Saket Bansal
 
Scrum Roles : Scrum Master | Product Owner |Team
Scrum Roles : Scrum Master | Product Owner |TeamScrum Roles : Scrum Master | Product Owner |Team
Scrum Roles : Scrum Master | Product Owner |TeamSaket Bansal
 

Mehr von Saket Bansal (20)

Improving Collaboration by Awareness of Mind Games
Improving Collaboration by Awareness of  Mind GamesImproving Collaboration by Awareness of  Mind Games
Improving Collaboration by Awareness of Mind Games
 
Emotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to PracticeEmotional Intelligence: From Theory to Practice
Emotional Intelligence: From Theory to Practice
 
Webinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth EditionWebinar on Agile and PMBOK® Guide Sixth Edition
Webinar on Agile and PMBOK® Guide Sixth Edition
 
Webinar on Leader As Coach
Webinar on Leader As Coach Webinar on Leader As Coach
Webinar on Leader As Coach
 
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridgeWebinar On Scaled Agile Framework (SAFe) | iZenBridge
Webinar On Scaled Agile Framework (SAFe) | iZenBridge
 
Webinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridgeWebinar on Agile Estimation : iZenBridge
Webinar on Agile Estimation : iZenBridge
 
Plan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk ManagementPlan Risk Responses : PMP : Project Risk Management
Plan Risk Responses : PMP : Project Risk Management
 
Risk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk ManagementRisk Analysis : PMP- Project Risk Management
Risk Analysis : PMP- Project Risk Management
 
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...
iZenBridge's PMP® Math Series: Project Selection : PV , NPV, IRR, BCR and Pay...
 
Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida Agile Beyond Rituals | Presented at Agile Noida
Agile Beyond Rituals | Presented at Agile Noida
 
Agile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridgeAgile Metric | Velocity | PMI ACP | IZenBridge
Agile Metric | Velocity | PMI ACP | IZenBridge
 
Technical Debt | PMI - ACP Webinar Series | iZenBridge
Technical Debt | PMI - ACP Webinar Series | iZenBridge Technical Debt | PMI - ACP Webinar Series | iZenBridge
Technical Debt | PMI - ACP Webinar Series | iZenBridge
 
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...
PMI ACP | Agile Classroom Training Program | iZenBridge Consultancy Private L...
 
Webinar On Product Backlog
Webinar On Product BacklogWebinar On Product Backlog
Webinar On Product Backlog
 
Scrum Webinar : Sprints - The Exploration Cycle
Scrum Webinar : Sprints - The Exploration CycleScrum Webinar : Sprints - The Exploration Cycle
Scrum Webinar : Sprints - The Exploration Cycle
 
PMP : Webinar on Quality Planning
PMP : Webinar  on Quality PlanningPMP : Webinar  on Quality Planning
PMP : Webinar on Quality Planning
 
Webinar : Scrum Roles
Webinar :  Scrum RolesWebinar :  Scrum Roles
Webinar : Scrum Roles
 
Why Agile | Agile Values and Principles
Why Agile | Agile Values and PrinciplesWhy Agile | Agile Values and Principles
Why Agile | Agile Values and Principles
 
Writing User Stories : Agile Way of Capturing Requirements
Writing User Stories : Agile Way of Capturing Requirements Writing User Stories : Agile Way of Capturing Requirements
Writing User Stories : Agile Way of Capturing Requirements
 
Scrum Roles : Scrum Master | Product Owner |Team
Scrum Roles : Scrum Master | Product Owner |TeamScrum Roles : Scrum Master | Product Owner |Team
Scrum Roles : Scrum Master | Product Owner |Team
 

Kürzlich hochgeladen

DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxDIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxMichelleTuguinay1
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptxmary850239
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 
ARTERIAL BLOOD GAS ANALYSIS........pptx
ARTERIAL BLOOD  GAS ANALYSIS........pptxARTERIAL BLOOD  GAS ANALYSIS........pptx
ARTERIAL BLOOD GAS ANALYSIS........pptxAneriPatwari
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseCeline George
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
CHEST Proprioceptive neuromuscular facilitation.pptx
CHEST Proprioceptive neuromuscular facilitation.pptxCHEST Proprioceptive neuromuscular facilitation.pptx
CHEST Proprioceptive neuromuscular facilitation.pptxAneriPatwari
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research DiscourseAnita GoswamiGiri
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...DhatriParmar
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 

Kürzlich hochgeladen (20)

DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptxDIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
DIFFERENT BASKETRY IN THE PHILIPPINES PPT.pptx
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx4.9.24 School Desegregation in Boston.pptx
4.9.24 School Desegregation in Boston.pptx
 
Paradigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTAParadigm shift in nursing research by RS MEHTA
Paradigm shift in nursing research by RS MEHTA
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 
ARTERIAL BLOOD GAS ANALYSIS........pptx
ARTERIAL BLOOD  GAS ANALYSIS........pptxARTERIAL BLOOD  GAS ANALYSIS........pptx
ARTERIAL BLOOD GAS ANALYSIS........pptx
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 Database
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
CHEST Proprioceptive neuromuscular facilitation.pptx
CHEST Proprioceptive neuromuscular facilitation.pptxCHEST Proprioceptive neuromuscular facilitation.pptx
CHEST Proprioceptive neuromuscular facilitation.pptx
 
Scientific Writing :Research Discourse
Scientific  Writing :Research  DiscourseScientific  Writing :Research  Discourse
Scientific Writing :Research Discourse
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
Beauty Amidst the Bytes_ Unearthing Unexpected Advantages of the Digital Wast...
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 

PMP : Precedence Diagram Method : Relationship Types | iZenBridge

  • 1. © 2014 iZenBridge | CONFIDENTIAL PMP is a registered trademark of the Project Management Institute, Inc. Precedence Diagramming Method (PDM) Four Types of Logical Relationships – PMP® Prep Topic Saket Bansal
  • 2. © 2014 iZenBridge | CONFIDENTIAL Dependencies Type of logical relationship between two activities defines how the depended activity is constrained by independent activity
  • 3. © 2014 iZenBridge | CONFIDENTIAL Dependent Watching Independent Independent Activity start or finish does not get impacted because of the relation Dependent Activity Start or Finish is influenced by the relation Activity A Activity B
  • 4. © 2014 iZenBridge | CONFIDENTIAL Predecessor and Successor A predecessor activity is an activity that logically comes before a dependent activity in a schedule. A successor activity is a dependent activity that logically comes after another activity on a schedule Independent / Predecessor Dependent / Successor Activity A Activity B
  • 5. © 2014 iZenBridge | CONFIDENTIAL Four Types of logical Relationships • Finish-to-start (FS) • Finish-to-finish (FF) • Start-to-start (SS) • Start-to-finish (SF)
  • 6. © 2014 iZenBridge | CONFIDENTIAL Two Digits / Four Types State of Independent (Activity A) Activity on which activity B is dependent on Constraint on Dependent activity (Activity B) applied on Finish (F) Start (S) Finish (F) Start (S)
  • 7. © 2014 iZenBridge | CONFIDENTIAL Four types of logical relationships S F/S Someone watching my finish F F/S S I can not finish until my predecessor condition is met I can not start until my predecessor condition is met Someone watching my start F FS SS FF SF
  • 8. © 2014 iZenBridge | CONFIDENTIAL Finish to Start (FS)
  • 9. © 2014 iZenBridge | CONFIDENTIAL Finish to start (FS) “A logical relationship in which a successor activity cannot start until a predecessor activity has finished.” Activity A Activity B FS Activity B is watching my finish date / time I can not start unit A Finishes
  • 10. © 2014 iZenBridge | CONFIDENTIAL Finish to start (FS) “A logical relationship in which a successor activity cannot start until a predecessor activity has finished.” Activity A Activity B FS Activity B is watching my finish date / time I can not start until A Finishes F S
  • 11. © 2014 iZenBridge | CONFIDENTIAL Example: Finish to Start Development Activity can not be started until design is finished. The design activity is expected to take 4 days and development will take 10 days Design : 4 (Independent) Development :10 (Dependent) Early Finish 4Early Start 1 Early Start 5 Early Finish 14 FS ES: Development = Early Finish Design + 1 = 4+1
  • 12. © 2014 iZenBridge | CONFIDENTIAL Example: Finish to Start + Lag Development Activity can not be started until one day after design is finished. The design activity is expected to take 4 days and development will take 10 days Design : 4 (Independent) Development:10 (Dependent) Early Finish 4Early Start 1 Early Start 6 Early Finish 15 FS + 1 ES: Development = Early Finish Design + 1 + Lag = 4+1 + 1
  • 13. © 2014 iZenBridge | CONFIDENTIAL Example: Finish to Start - Lead Development Activity can not be started until one day before design is finishing. The design activity is expected to take 4 days and development will take 10 days Design : 4 (Independent) Development: 10 (Dependent) Finish 4Start 1 Start 4 Finish 13 FS - 1 ES: Development = Early Finish Design + 1 - Lead = 4+1 - 1
  • 14. © 2014 iZenBridge | CONFIDENTIAL Start-to-start (SS)
  • 15. © 2014 iZenBridge | CONFIDENTIAL Start-to-start (SS) “A logical relationship in which a successor activity cannot start until a predecessor activity has started.” Activity A Activity B SS Activity B is watching my Start date / time I can not start until A Starts S S
  • 16. © 2014 iZenBridge | CONFIDENTIAL Example: Start-to-start (SS) The activity of marketing brochure preparation can not start until user documentation activity has started. The marketing brochure preparation activity is expected to take 4 days and user manual preparation will take 10 days User Docs:10 Brochure: 4 Early Start 1 Early Finish 10 Early Start 1 Early Finish 4 ES Brochure = ES: User Doc +/- Lag/Lead
  • 17. © 2014 iZenBridge | CONFIDENTIAL Finish-to-finish (FF)
  • 18. © 2014 iZenBridge | CONFIDENTIAL Finish-to-finish (FF) “A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.” Activity A Activity B FF Activity B is watching my Finish date / time I can not Finish until A Finishes F F
  • 19. © 2014 iZenBridge | CONFIDENTIAL Example: Finish-to-finish (FF) User Documentation activity can not finish until development is finished. User Documentation will take 10 days where development will take 30 days. Development: 30 User Documentation : 10 Early Start 1 Early Finish 30 Early Finish 30 EF User Doc = EF: Development +/- Lag/Lead Early Start 21
  • 20. © 2014 iZenBridge | CONFIDENTIAL Start-to-finish (SF)
  • 21. © 2014 iZenBridge | CONFIDENTIAL Start-to-finish (SF) “A logical relationship in which a successor activity cannot finish until a predecessor activity has started.” Activity A Activity B SF Activity B is watching my Start date / time I can not Finish until A Starts S F
  • 22. © 2014 iZenBridge | CONFIDENTIAL Example Start-to-finish (SF) Support activity from development team can not finish until production support Activity is started . Production support is expected to start on day 15. Production Support Development Support: 10 Early Start 15 Early Finish 14 EF Development Support = ES: Production Support -1 +/- Lag/Lead
  • 23. © 2014 iZenBridge | CONFIDENTIAL Four Types of Logical Relationships • Finish-to-start (FS) • Finish-to-finish (FF) • Start-to-start (SS) • Start-to-finish (SF)
  • 24. © 2014 iZenBridge | CONFIDENTIAL Stay Connected YouTube www.youtube.com/izenbridge Saket.Bansal@iZenBridge.com www.iZenBridge.com forum.iZenBridge.com