SlideShare a Scribd company logo
1 of 19
Download to read offline
PM World Today – September 2011 (Vol. XIII, Issue IX)


            PM WORLD TODAY – FEATURED PAPER – SEPTEMBER 2011

      Post Disaster Engineering & Construction Program and
                      Project Management

                                  By Bob Prieto & Charles (Al) Whitaker


The post-disaster environment changes both engineering and construction
requirements as well as the framework within which it is undertaken. These changes
drive post-disaster program and project managers to address different considerations
than those encountered on a more traditional global scale program while simultaneously
dealing with the added constraints imposed by an evolving logistical situation.

Previously in, “Personal Perspective: Program Management and Events of Scale” (PM
World Today; July, 2008) the focus was on programmatic features common in the
preparation and planning to resist, respond and recover from so-called events of scale.
This paper looks more deeply at how the engineering and construction model changes
post disaster and how various logistics affecting activities are modified from those
employed on global scale programs undertaken in a non disaster environment.

Types of Disasters

Before jumping directly into the post disaster environment it is worth spending a minute
to understand the range of disasters that engineering and construction program and
project managers are likely to be called to engage in. We have tried to characterize
these simply as those with a broader scale (both natural and human caused) and those
that are more discrete in nature. The later however may have consequences as severe
as the broader scale disasters depending on the facility involved. We have specifically
included so called “Natech” disasters or naturally induced technological failures. The
most recent example of such a Natech disaster is at Fukashima.

     Broader Scale Disasters

              –    Human

                         War, civil strife, terrorism
              –    Natural

                         Regional – wind, water, earthquake, geological

     Discrete Disasters (Specific facility)

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 1
PM World Today – September 2011 (Vol. XIII, Issue IX)


              –    Human – terrorism, explosion, fire
              –    Natural – tornado, fire
              –    Natech - naturally induced, technological failure

Each of these disasters moves through three phases but in this paper we will focus only
on the later two.

     Resist (pre-disaster)

     Response

     Recover and reconstruct
              –    Enhance resiliency for each phase


Simplified Engineering & Construction Project Model

In order to understand how the engineering and construction project model changes
post-disaster it is first necessary to construct a simplified model for the non-disaster
scenario. Such a simplified model is reflected in the following figure and includes a set
of project inputs which are transformed at a project site, within a well defined
framework, to deliver the desired project outputs. Framework elements include:

         -    Business framework
         -    Project environment and setting
         -    Social and stakeholder framework
         -    Economic and political frameworks




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 2
PM World Today – September 2011 (Vol. XIII, Issue IX)




In the non-disaster scenario project inputs simplistically include:

         -    Labor
         -    Materials
         -    Equipment

Outputs from the engineering and construction process include not only the completed
project but also a significant amount of construction waste (25% of construction inputs).




Turning now to each of the framework elements in which construction typically occurs,
we can define the prime components comprising each element in a “simplified” non-
disaster construction setting. These will include business framework components such
as the contract, risk factors, the facility owner, and various labor organizations and
associated labor agreements that may exist.

Project environment and setting components of this framework element will include
project site factors, geography, climate, existing regional infrastructure, available
records and documentation and applicable codes and standards. The social and
stakeholder framework element will include components such as existing organized
stakeholders, local and regional demographics, a range of cultural or religious factors to
be considered and hopefully well established ownership rights.

Finally the economic and political framework element will include components related to
a well established rule of law, clear regulations, the required well-defined financial
institutions as well as other institutions taken for granted in everyday commercial
activities and a well defined and efficiently structured approach to project funding.



© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 3
PM World Today – September 2011 (Vol. XIII, Issue IX)




Site based factors further constrain how project inputs are transformed into the desired
project outputs within this constraining and defining framework. The transformation
process is also enabled through a set of required site services, the esprit de corps built
among the project team and the know how the contractor and his management and
technical experts bring to bear.




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 4
PM World Today – September 2011 (Vol. XIII, Issue IX)


How the Engineering and Construction Project Model Changes Post-Disaster

Disasters change each element of this model and as we will see later on activities
normally undertaken are modified by post-disaster logistics constraints as well as
modify post-disaster logistics themselves. Let’s look now at each element of the
simplified model described above and how it is modified post disaster starting with
project inputs themselves.




Each of the basic inputs from our simplified model (labor, materials, equipment) is
modified post-disaster and several new input considerations become significant. These
modified and new input factors include:

Labor
   • New management skills
    •    Skilled labor requirements changed/expanded
    •    Large unskilled labor pool mobilization
    •    Labor sourcing (Global or select nationals)
Materials
  • Material requirements and sequencing changed

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 5
PM World Today – September 2011 (Vol. XIII, Issue IX)


    •    Quantities disrupted supply chains
    •    Challenging logistics
Equipment
  • Sourcing
    •    Maintenance during construction
    •    Trained operators
Knowledge of Post-Disaster Construction

Subcontractor Finance

Non-Process Infrastructure
  • Traditional housing, provision, and utility services disrupted or inadequate
    •    Logistic facilities disrupted or inadequate
Modified Safety Practices for Post-Disaster Environment
  • Unknown conditions
    •    Specialized craft training
    •    Changed work sequences
Stronger Management Systems Role
   • Commercial transactions
    •    Labor documentation and payroll
    •    Augmented work face planning and management
Similarly the various framework elements are subject to modified or added components
which act to shape post disaster project management in ways not encountered in non-
disaster scenarios. Let’s look at each of the framework elements in turn and how the
various components are modified post-disaster.

Disaster Changes Business Framework

Disaster changes the business framework, introducing new factors into basic
construction contract considerations, significantly altering risk frameworks that the
program or project team may experience, creating new de facto owner groups different
than those the engineering and construction team and broader community may be used
to engaging with, and creating new challenges with various labor organizations.

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 6
PM World Today – September 2011 (Vol. XIII, Issue IX)


Specific modifications to the “simplified” model may include:

Contract
  • Scope includes more unknowns and potentially evolving requirements
    •    Schedule based on potential continuing risk events, degraded labor productivity,
         uncertain supply chains, and evolving approval frameworks
    •    Budgets based on uncertain labor, equipment, and material costs accounting for
         competition for constrained resources
    •    Quality standards must consider risks and intended usage and duration
Risk Framework
   • Significantly changed risk profile must be reflected in terms and conditions
Owners
  • External funding agencies may assume de facto owner’s role
Labor Organizations and Agreements
   • Existing agreements may create barriers to recovery
    •    Potential for labor strife as external workforce mobilized




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 7
PM World Today – September 2011 (Vol. XIII, Issue IX)


Disaster Changes Project and Environmental Setting Framework

Disasters, in particular broader scale disasters, fundamentally alter the project and
environmental setting. Site access will be constrained in new and potentially evolving
ways, basic site and regional geography may be fundamentally modified and the
regional infrastructure, at whatever level, that projects rely on to meet many of their
basic needs may now be non-existent. Basic assumptions under the “simplified” pre-
disaster model are no longer valid.

Changes to the various components of this framework element include:

Project Site
   • Constrained access
    •    Denied access
    •    Uncertain ownership or other property rights
Geography
  • Modified topography (floods, landslides, or mudslides; earthquake displacement;
     lava fields; aftermath of military action)

    •    Terrain limits rate of response or reconstruction
    •    Accessibility constrains available options
Climate
   • Adverse climactic conditions impact response activities (continuing hurricane
      season, seasonal extremes of temperature or precipitation)
    •    Event of scale necessitates construction in non-traditional time periods
         (monsoon, depth of winter, peak of summer)
Regional Infrastructure
  • Widespread destruction of regional infrastructures important to response and
      reconstruction (roads and rails washed away, bridges severely damaged or
      destroyed, airports rendered unusable, destroyed power generation and
      transmission capability, destroyed or degraded potable water treatment and
      distribution capability, degraded wastewater capability, constrained telecom
      services from facility damage)
    •    Regional infrastructure inadequate for level and nature of response and
         rebuilding activities

Social Infrastructures Disrupted or Destroyed
   • Housing, medical, police, fire, sanitation

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 8
PM World Today – September 2011 (Vol. XIII, Issue IX)


    •    Banking and other financial institutions
Records and Documentation
  • Lost records
    •    As-builts no longer meaningful
    •    Property rights not well documented or inconsistent with social realities (squatter
         populations)
Codes and Standards
  • Evolving as a result of event of scale
    •    Variable – affected by donor/funder requirements




Disaster Changes Social and Stakeholder Framework

Social and stakeholder frameworks undergo some of the most significant changes post-
disaster, often in ways that are not readily visible. These changes impact each of the
components that comprise this framework element. Traditional problem resolution
mechanisms may breakdown and new sources of concern or conflict emerge. Displaced
populations, transient relief and reconstruction populations and a re-emergence or
strengthening of cultural or tribal issues compound the difficulty in undertaking the
engineering and construction activities needed to respond and reconstruct post-
disaster. Often the debilitating and corrosive impacts of corruption are more sharply felt.

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 9
PM World Today – September 2011 (Vol. XIII, Issue IX)


Changes to specific framework components include:

Organized Stakeholders
   • Traditional stakeholder groups dysfunctional
    •    Stakeholder objectives evolving
    •    New stakeholder groups emerging
    •    National or international stakeholders gain roles to enable or Intervene
Demographics
  • Loss and displacement of populations
    •    Impact of relief, response, and reconstruction populations
    •    Constraints on construction labor
Cultural/Religious
   • Transitional roles often played by cultural or religious groups
    •    Cultural and religious sensitivities often elevated
    •    Tribal issues and prerogatives may resurface
Ownership Rights
  • Lack of documentation and records
    •    Conflicting claims
    •    Formal versus informal rights
    •    Confiscation in the absence of the rule of law
    •    Corruption




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 10
PM World Today – September 2011 (Vol. XIII, Issue IX)




Disaster Changes Economic and Political Framework

The destructive impact of a disaster on economic activity that existed pre-disaster is
easy to understand. Harder to come to grips with is the trajectory of economic activity
post-disaster. This trajectory is often shaped by political functionality and the extension
of politics into every aspect of life and every decision essential to post-disaster relief
and recovery. Examples of changes in the various components of this final framework
element include:

Rule of Law
   • Confiscation and security risks elevated due to lack of rule of law
    •    Emergency decrees inconsistently interpreted and applied

    •    Local laws of convenience
    •    Corruption

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 11
PM World Today – September 2011 (Vol. XIII, Issue IX)


Regulations
  • Regulations not relevant to situation on ground or act to impede progress
    •    Traditional regulations extended to situation for which they were not designed
Financial Institutions
   • Absent or disrupted

    •    Emergence of a cash economy
    •    Difficulty paying suppliers and labor
Project Funding
   • Color of money issues associated with multiple funding sources and tied
       requirements
    •    Documentation requirements evolve
    •    Lack of on-the-ground payment capability by donors
    •    Lack of timeliness of payments
Politics
   • Politics in traditionally non-political activities
    •    Every activity potentially someone’s political platform
    •    Long-range planning efforts begun anew affecting critical decisions
    •    Economic development a core consideration

    •    Capacity building may be an imperative
Sustainability and Resilience
   • Life-cycle focus may emerge




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 12
PM World Today – September 2011 (Vol. XIII, Issue IX)




Post-Disaster Project and Construction Activity

Post-disaster project and construction activity must now occur at a site where traditional
inputs and project frameworks have been modified and special challenges are present.
These special challenges include debris removal and potential reuse to mitigate ever
present logistical challenges; changed psychology both with respect to decision making
and risk taking but also with respect to a labor force that itself may be displaced or
suffering the loss of close relatives; and changed liability concerns as one of the first
things to grow post-disaster is uncertainty which is a root cause of much liability.

We have already touched upon the corrosive effects of corruption which may be
controlled or compounded by governmental leadership and enablement. These are real
issues as are those related to human and construction safety. The construction
environment is inherently dangerous and post-disaster uncertainties only exacerbate
these concerns.




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 13
PM World Today – September 2011 (Vol. XIII, Issue IX)




Finally, post-disaster construction activities face modified output requirements from
more traditional non-disaster construction.

Post-Disaster Construction Outputs

Traditional construction activities are traditionally focused on creating new facilities,
usually “permanent” in nature. Post-disaster, constructed projects may take on a wider
range of time frames including temporary, transitional and permanent dimensions.

Pressures to use disaster debris in construction may modify certain design and
construction choices and considerations related to not adding to this material problem
are only heightened post-disaster. Social dimensions of the “triple bottom line” of
sustainability take on increased importance as part of the overall disaster recovery
process.

Specific changes to post-disaster outputs include:

Completed Project
  • Temporary
    •    Transitional

    •    Permanent


© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 14
PM World Today – September 2011 (Vol. XIII, Issue IX)


Construction Waste
  • Linkage to debris considerations (disposal and reuse in construction)
    •    Recycling drivers
Sustainability
   • Capacity building

    •    Economic development
    •    New industry creation
    •    Enhanced resiliency
    •    Lessons learned and best practices




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 15
PM World Today – September 2011 (Vol. XIII, Issue IX)


Conclusion

Post-disaster engineering and construction program and project management activities
are significantly modified from non-disaster activities. Changes to the fundamental
project model employed in the management of these types of programs and projects
requires a fundamental re-think of skill sets, management processes, risks and
constraints. In addition these changes collectively significantly change the logistical
characteristics of such programs while simultaneously significantly modifying the
broader logistical space within which the disaster has occurred. Even the most basic
project activities have the potential to significantly affect project and regional logistics
and even the best intentioned relief and recovery activities have the ability to impact
response and recovery in today’s highly engineered, built environment.

The challenges of this changed environment can be met through concerted action by
the engineering, construction, government and NGO sectors. Specific recommendations
include:

     Government and NGO community must plan for assisting in post-disaster
      recovery

              –    Provide accessibility to the sites of critical infrastructure
              –    Maintain awareness of global logistics chain
              –    Ensure availability of specialized construction equipment, contracts, and
                   materials
              –    Develop well-documented system with clear interface points

              –    Preplan and rehearse response and recovery scenarios for high-
                   probability events

                         Earthquake

                         Hurricane

                         Flood

     Engagement with engineering and construction community must begin pre-
      disaster
              –    Pre-placed contracts

                         Program management

                         EPC

© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 16
PM World Today – September 2011 (Vol. XIII, Issue IX)


                         Supply chain

              –    Earliest mobilization to disaster zone
              –    Early activation of logistics chains

     Post-disaster period requires streamlined decision frameworks
              –    Decision authorities at project and disaster site

              –    Logistical-affecting processes may act as barrier in
                   post-disaster scenario

                         Examples are customs, building permits, and liability legislation

                         Consider a standard “modified” logistical template for local
                          government consideration

                                   “Go-bys”

                                   Best practices




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 17
PM World Today – September 2011 (Vol. XIII, Issue IX)


About the Authors


                               Bob Prieto

                               Co-Author




                        Bob Prieto is a Senior Vice President of Fluor Corporation, one of
                        America’s largest engineering, construction and project
management firms, where he is responsible for strategy in support of the firm’s
Industrial & Infrastructure Group and its key clients. He focuses on the development,
delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob
served as chairman of Parsons Brinckerhoff Inc. He served as a member of the
executive committee of the National Center for Asia-Pacific Economic Cooperation, a
member of the Industry Leaders’ Council of the American Society of Civil Engineers
(ASCE), and co-founder of the Disaster Resource Network. He currently serves on a
number of committees looking at issues related to infrastructure delivery and resiliency
and disaster response and rebuilding and is a member of the National Academy of
Construction. Until 2006 he served as one of three U.S. presidential appointees to the
Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and
previously served as chairman of the Engineering and Construction Governors of The
World Economic Forum and co-chair of the infrastructure task force formed after
September 11th by the New York City Chamber of Commerce. He recently completed
ten year tenure as a member of the board of trustees of Polytechnic University of New
York culminating in its merger with New York University. Bob is the author of “Strategic
Program Management” published by the Construction Management Association of
America (CMAA) and more recently a companion work entitled “Topics in Strategic
Program Management”.




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 18
PM World Today – September 2011 (Vol. XIII, Issue IX)




                                   Charles (Al) Whitaker

                                   Co-Author




                          Al Whitaker has served as program manager for DOE, DOD,
                          FEMA and other government agencies and programs and has
                          been responsible for managing large federal programs in the
area of environmental services (facilities permitting, design, and construction and site
remediation) and disaster relief. He was Fluor’s program manager for the FEMA
Individual Assistance Technical Assistance Program. This program provides temporary
housing to disaster victims. The scope for the program includes full engineering,
procurement, construction, and maintenance services. As Program Manager his
responsibilities included the execution of all task orders for disaster response anywhere
FEMA is called upon to respond. Task Orders included work in Florida, Wyoming,
Louisiana, Alabama, Mississippi, Kansas and Texas. Revenues from this program have
exceeded $1.5 billion and over 900 million safe work hours have been executed.
1976-1980. Al Whitaker has a Bachelor of Science degree in Civil Engineering (Chi
Epsilon, Civil Engineering Honorary Fraternity) from the University of Kentucky,
Lexington, Kentucky, USA (1976-1980); and a Masters of business Administration from
Texas A&M University, Mays Graduate School of Business, College Station, Texas,
USA (2002 – 2004).




© 2011 Bob Prieto and Al Whitaker
PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 19

More Related Content

Viewers also liked

Disaster management
Disaster managementDisaster management
Disaster managementVivek Bhatt
 
Himal hrm solved case
Himal hrm solved case Himal hrm solved case
Himal hrm solved case HR Bhusal
 
The landscapes of spain and europe
The landscapes of spain and europeThe landscapes of spain and europe
The landscapes of spain and europeVisi00
 
Ppt on train accident
Ppt on train accidentPpt on train accident
Ppt on train accidentneeraj verma
 
Rail accidents tam 2013-18
Rail accidents tam 2013-18Rail accidents tam 2013-18
Rail accidents tam 2013-18Vijay Kumar
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.ashrafdgrt
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Railssrinivas2036
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkVolker Hirsch
 

Viewers also liked (11)

Disaster management
Disaster managementDisaster management
Disaster management
 
Himal hrm solved case
Himal hrm solved case Himal hrm solved case
Himal hrm solved case
 
The landscapes of spain and europe
The landscapes of spain and europeThe landscapes of spain and europe
The landscapes of spain and europe
 
Rail safety ppt
Rail safety pptRail safety ppt
Rail safety ppt
 
Ppt on train accident
Ppt on train accidentPpt on train accident
Ppt on train accident
 
Rail accidents tam 2013-18
Rail accidents tam 2013-18Rail accidents tam 2013-18
Rail accidents tam 2013-18
 
Gender issues
Gender issuesGender issues
Gender issues
 
railway ppt for civil engg.
 railway ppt for civil engg. railway ppt for civil engg.
railway ppt for civil engg.
 
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of RailsRails, Types, Joints, Creep, Failure of Rails and Welding of Rails
Rails, Types, Joints, Creep, Failure of Rails and Welding of Rails
 
TEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of WorkTEDx Manchester: AI & The Future of Work
TEDx Manchester: AI & The Future of Work
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 

Similar to Post Disaster Engineering And Construction

Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Bob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
17Chapter 2Managing Projects With High Complexity.docx
17Chapter 2Managing Projects With High Complexity.docx17Chapter 2Managing Projects With High Complexity.docx
17Chapter 2Managing Projects With High Complexity.docxdrennanmicah
 
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdfahsansaeed78
 
Prieto intersection of engineering construction logistics
Prieto intersection of engineering construction logistics Prieto intersection of engineering construction logistics
Prieto intersection of engineering construction logistics Bob Prieto
 
Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsOECD Governance
 
Construction Project Essay
Construction Project EssayConstruction Project Essay
Construction Project EssayAshley Thomas
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
 
Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2ahsanrabbani
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONVijayfan2
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learningIJRES Journal
 
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...Corporate & Government Partnering (PPPs and other formats) for Societal Impa...
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...The Kingdom Summit
 
52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_projectEng. Mohamed Muhumed
 
Project risk management (1)
Project risk management (1)Project risk management (1)
Project risk management (1)Lezasmith
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.kiebut
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfDejeneTsegaye6
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxDejeneTsegaye6
 

Similar to Post Disaster Engineering And Construction (20)

Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13Prieto post disaster reconstruction model 03 27 13
Prieto post disaster reconstruction model 03 27 13
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
17Chapter 2Managing Projects With High Complexity.docx
17Chapter 2Managing Projects With High Complexity.docx17Chapter 2Managing Projects With High Complexity.docx
17Chapter 2Managing Projects With High Complexity.docx
 
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf
1661350983Unit 1 1050-V1 Introduction to Construction Management (1).pdf
 
Prieto intersection of engineering construction logistics
Prieto intersection of engineering construction logistics Prieto intersection of engineering construction logistics
Prieto intersection of engineering construction logistics
 
Evaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR ProjectsEvaluating the Impact of Community Based DRR Projects
Evaluating the Impact of Community Based DRR Projects
 
Construction Project Essay
Construction Project EssayConstruction Project Essay
Construction Project Essay
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2Economics of project evaluation for reference cpm module2
Economics of project evaluation for reference cpm module2
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learning
 
Essay Construction
Essay ConstructionEssay Construction
Essay Construction
 
Risk Management in Megaprojects
Risk Management in MegaprojectsRisk Management in Megaprojects
Risk Management in Megaprojects
 
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...Corporate & Government Partnering (PPPs and other formats) for Societal Impa...
Corporate & Government Partnering (PPPs and other formats) for Societal Impa...
 
52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project52 a risk-management_approach_to_a_successful_infrastructure_project
52 a risk-management_approach_to_a_successful_infrastructure_project
 
Project risk management (1)
Project risk management (1)Project risk management (1)
Project risk management (1)
 
1% AIMS Improving Construction productivity. November 30th 2015.
1% AIMS Improving Construction productivity.  November 30th 2015.1% AIMS Improving Construction productivity.  November 30th 2015.
1% AIMS Improving Construction productivity. November 30th 2015.
 
CSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdfCSQS ch 1, 2& 3 lec. note.pdf
CSQS ch 1, 2& 3 lec. note.pdf
 
Contract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docxContract Specification and Quantity Surveying.docx
Contract Specification and Quantity Surveying.docx
 

More from Bob Prieto

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Bob Prieto
 

More from Bob Prieto (20)

Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6
 

Post Disaster Engineering And Construction

  • 1. PM World Today – September 2011 (Vol. XIII, Issue IX) PM WORLD TODAY – FEATURED PAPER – SEPTEMBER 2011 Post Disaster Engineering & Construction Program and Project Management By Bob Prieto & Charles (Al) Whitaker The post-disaster environment changes both engineering and construction requirements as well as the framework within which it is undertaken. These changes drive post-disaster program and project managers to address different considerations than those encountered on a more traditional global scale program while simultaneously dealing with the added constraints imposed by an evolving logistical situation. Previously in, “Personal Perspective: Program Management and Events of Scale” (PM World Today; July, 2008) the focus was on programmatic features common in the preparation and planning to resist, respond and recover from so-called events of scale. This paper looks more deeply at how the engineering and construction model changes post disaster and how various logistics affecting activities are modified from those employed on global scale programs undertaken in a non disaster environment. Types of Disasters Before jumping directly into the post disaster environment it is worth spending a minute to understand the range of disasters that engineering and construction program and project managers are likely to be called to engage in. We have tried to characterize these simply as those with a broader scale (both natural and human caused) and those that are more discrete in nature. The later however may have consequences as severe as the broader scale disasters depending on the facility involved. We have specifically included so called “Natech” disasters or naturally induced technological failures. The most recent example of such a Natech disaster is at Fukashima.  Broader Scale Disasters – Human  War, civil strife, terrorism – Natural  Regional – wind, water, earthquake, geological  Discrete Disasters (Specific facility) © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 1
  • 2. PM World Today – September 2011 (Vol. XIII, Issue IX) – Human – terrorism, explosion, fire – Natural – tornado, fire – Natech - naturally induced, technological failure Each of these disasters moves through three phases but in this paper we will focus only on the later two.  Resist (pre-disaster)  Response  Recover and reconstruct – Enhance resiliency for each phase Simplified Engineering & Construction Project Model In order to understand how the engineering and construction project model changes post-disaster it is first necessary to construct a simplified model for the non-disaster scenario. Such a simplified model is reflected in the following figure and includes a set of project inputs which are transformed at a project site, within a well defined framework, to deliver the desired project outputs. Framework elements include: - Business framework - Project environment and setting - Social and stakeholder framework - Economic and political frameworks © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 2
  • 3. PM World Today – September 2011 (Vol. XIII, Issue IX) In the non-disaster scenario project inputs simplistically include: - Labor - Materials - Equipment Outputs from the engineering and construction process include not only the completed project but also a significant amount of construction waste (25% of construction inputs). Turning now to each of the framework elements in which construction typically occurs, we can define the prime components comprising each element in a “simplified” non- disaster construction setting. These will include business framework components such as the contract, risk factors, the facility owner, and various labor organizations and associated labor agreements that may exist. Project environment and setting components of this framework element will include project site factors, geography, climate, existing regional infrastructure, available records and documentation and applicable codes and standards. The social and stakeholder framework element will include components such as existing organized stakeholders, local and regional demographics, a range of cultural or religious factors to be considered and hopefully well established ownership rights. Finally the economic and political framework element will include components related to a well established rule of law, clear regulations, the required well-defined financial institutions as well as other institutions taken for granted in everyday commercial activities and a well defined and efficiently structured approach to project funding. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 3
  • 4. PM World Today – September 2011 (Vol. XIII, Issue IX) Site based factors further constrain how project inputs are transformed into the desired project outputs within this constraining and defining framework. The transformation process is also enabled through a set of required site services, the esprit de corps built among the project team and the know how the contractor and his management and technical experts bring to bear. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 4
  • 5. PM World Today – September 2011 (Vol. XIII, Issue IX) How the Engineering and Construction Project Model Changes Post-Disaster Disasters change each element of this model and as we will see later on activities normally undertaken are modified by post-disaster logistics constraints as well as modify post-disaster logistics themselves. Let’s look now at each element of the simplified model described above and how it is modified post disaster starting with project inputs themselves. Each of the basic inputs from our simplified model (labor, materials, equipment) is modified post-disaster and several new input considerations become significant. These modified and new input factors include: Labor • New management skills • Skilled labor requirements changed/expanded • Large unskilled labor pool mobilization • Labor sourcing (Global or select nationals) Materials • Material requirements and sequencing changed © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 5
  • 6. PM World Today – September 2011 (Vol. XIII, Issue IX) • Quantities disrupted supply chains • Challenging logistics Equipment • Sourcing • Maintenance during construction • Trained operators Knowledge of Post-Disaster Construction Subcontractor Finance Non-Process Infrastructure • Traditional housing, provision, and utility services disrupted or inadequate • Logistic facilities disrupted or inadequate Modified Safety Practices for Post-Disaster Environment • Unknown conditions • Specialized craft training • Changed work sequences Stronger Management Systems Role • Commercial transactions • Labor documentation and payroll • Augmented work face planning and management Similarly the various framework elements are subject to modified or added components which act to shape post disaster project management in ways not encountered in non- disaster scenarios. Let’s look at each of the framework elements in turn and how the various components are modified post-disaster. Disaster Changes Business Framework Disaster changes the business framework, introducing new factors into basic construction contract considerations, significantly altering risk frameworks that the program or project team may experience, creating new de facto owner groups different than those the engineering and construction team and broader community may be used to engaging with, and creating new challenges with various labor organizations. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 6
  • 7. PM World Today – September 2011 (Vol. XIII, Issue IX) Specific modifications to the “simplified” model may include: Contract • Scope includes more unknowns and potentially evolving requirements • Schedule based on potential continuing risk events, degraded labor productivity, uncertain supply chains, and evolving approval frameworks • Budgets based on uncertain labor, equipment, and material costs accounting for competition for constrained resources • Quality standards must consider risks and intended usage and duration Risk Framework • Significantly changed risk profile must be reflected in terms and conditions Owners • External funding agencies may assume de facto owner’s role Labor Organizations and Agreements • Existing agreements may create barriers to recovery • Potential for labor strife as external workforce mobilized © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 7
  • 8. PM World Today – September 2011 (Vol. XIII, Issue IX) Disaster Changes Project and Environmental Setting Framework Disasters, in particular broader scale disasters, fundamentally alter the project and environmental setting. Site access will be constrained in new and potentially evolving ways, basic site and regional geography may be fundamentally modified and the regional infrastructure, at whatever level, that projects rely on to meet many of their basic needs may now be non-existent. Basic assumptions under the “simplified” pre- disaster model are no longer valid. Changes to the various components of this framework element include: Project Site • Constrained access • Denied access • Uncertain ownership or other property rights Geography • Modified topography (floods, landslides, or mudslides; earthquake displacement; lava fields; aftermath of military action) • Terrain limits rate of response or reconstruction • Accessibility constrains available options Climate • Adverse climactic conditions impact response activities (continuing hurricane season, seasonal extremes of temperature or precipitation) • Event of scale necessitates construction in non-traditional time periods (monsoon, depth of winter, peak of summer) Regional Infrastructure • Widespread destruction of regional infrastructures important to response and reconstruction (roads and rails washed away, bridges severely damaged or destroyed, airports rendered unusable, destroyed power generation and transmission capability, destroyed or degraded potable water treatment and distribution capability, degraded wastewater capability, constrained telecom services from facility damage) • Regional infrastructure inadequate for level and nature of response and rebuilding activities Social Infrastructures Disrupted or Destroyed • Housing, medical, police, fire, sanitation © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 8
  • 9. PM World Today – September 2011 (Vol. XIII, Issue IX) • Banking and other financial institutions Records and Documentation • Lost records • As-builts no longer meaningful • Property rights not well documented or inconsistent with social realities (squatter populations) Codes and Standards • Evolving as a result of event of scale • Variable – affected by donor/funder requirements Disaster Changes Social and Stakeholder Framework Social and stakeholder frameworks undergo some of the most significant changes post- disaster, often in ways that are not readily visible. These changes impact each of the components that comprise this framework element. Traditional problem resolution mechanisms may breakdown and new sources of concern or conflict emerge. Displaced populations, transient relief and reconstruction populations and a re-emergence or strengthening of cultural or tribal issues compound the difficulty in undertaking the engineering and construction activities needed to respond and reconstruct post- disaster. Often the debilitating and corrosive impacts of corruption are more sharply felt. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 9
  • 10. PM World Today – September 2011 (Vol. XIII, Issue IX) Changes to specific framework components include: Organized Stakeholders • Traditional stakeholder groups dysfunctional • Stakeholder objectives evolving • New stakeholder groups emerging • National or international stakeholders gain roles to enable or Intervene Demographics • Loss and displacement of populations • Impact of relief, response, and reconstruction populations • Constraints on construction labor Cultural/Religious • Transitional roles often played by cultural or religious groups • Cultural and religious sensitivities often elevated • Tribal issues and prerogatives may resurface Ownership Rights • Lack of documentation and records • Conflicting claims • Formal versus informal rights • Confiscation in the absence of the rule of law • Corruption © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 10
  • 11. PM World Today – September 2011 (Vol. XIII, Issue IX) Disaster Changes Economic and Political Framework The destructive impact of a disaster on economic activity that existed pre-disaster is easy to understand. Harder to come to grips with is the trajectory of economic activity post-disaster. This trajectory is often shaped by political functionality and the extension of politics into every aspect of life and every decision essential to post-disaster relief and recovery. Examples of changes in the various components of this final framework element include: Rule of Law • Confiscation and security risks elevated due to lack of rule of law • Emergency decrees inconsistently interpreted and applied • Local laws of convenience • Corruption © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 11
  • 12. PM World Today – September 2011 (Vol. XIII, Issue IX) Regulations • Regulations not relevant to situation on ground or act to impede progress • Traditional regulations extended to situation for which they were not designed Financial Institutions • Absent or disrupted • Emergence of a cash economy • Difficulty paying suppliers and labor Project Funding • Color of money issues associated with multiple funding sources and tied requirements • Documentation requirements evolve • Lack of on-the-ground payment capability by donors • Lack of timeliness of payments Politics • Politics in traditionally non-political activities • Every activity potentially someone’s political platform • Long-range planning efforts begun anew affecting critical decisions • Economic development a core consideration • Capacity building may be an imperative Sustainability and Resilience • Life-cycle focus may emerge © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 12
  • 13. PM World Today – September 2011 (Vol. XIII, Issue IX) Post-Disaster Project and Construction Activity Post-disaster project and construction activity must now occur at a site where traditional inputs and project frameworks have been modified and special challenges are present. These special challenges include debris removal and potential reuse to mitigate ever present logistical challenges; changed psychology both with respect to decision making and risk taking but also with respect to a labor force that itself may be displaced or suffering the loss of close relatives; and changed liability concerns as one of the first things to grow post-disaster is uncertainty which is a root cause of much liability. We have already touched upon the corrosive effects of corruption which may be controlled or compounded by governmental leadership and enablement. These are real issues as are those related to human and construction safety. The construction environment is inherently dangerous and post-disaster uncertainties only exacerbate these concerns. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 13
  • 14. PM World Today – September 2011 (Vol. XIII, Issue IX) Finally, post-disaster construction activities face modified output requirements from more traditional non-disaster construction. Post-Disaster Construction Outputs Traditional construction activities are traditionally focused on creating new facilities, usually “permanent” in nature. Post-disaster, constructed projects may take on a wider range of time frames including temporary, transitional and permanent dimensions. Pressures to use disaster debris in construction may modify certain design and construction choices and considerations related to not adding to this material problem are only heightened post-disaster. Social dimensions of the “triple bottom line” of sustainability take on increased importance as part of the overall disaster recovery process. Specific changes to post-disaster outputs include: Completed Project • Temporary • Transitional • Permanent © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 14
  • 15. PM World Today – September 2011 (Vol. XIII, Issue IX) Construction Waste • Linkage to debris considerations (disposal and reuse in construction) • Recycling drivers Sustainability • Capacity building • Economic development • New industry creation • Enhanced resiliency • Lessons learned and best practices © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 15
  • 16. PM World Today – September 2011 (Vol. XIII, Issue IX) Conclusion Post-disaster engineering and construction program and project management activities are significantly modified from non-disaster activities. Changes to the fundamental project model employed in the management of these types of programs and projects requires a fundamental re-think of skill sets, management processes, risks and constraints. In addition these changes collectively significantly change the logistical characteristics of such programs while simultaneously significantly modifying the broader logistical space within which the disaster has occurred. Even the most basic project activities have the potential to significantly affect project and regional logistics and even the best intentioned relief and recovery activities have the ability to impact response and recovery in today’s highly engineered, built environment. The challenges of this changed environment can be met through concerted action by the engineering, construction, government and NGO sectors. Specific recommendations include:  Government and NGO community must plan for assisting in post-disaster recovery – Provide accessibility to the sites of critical infrastructure – Maintain awareness of global logistics chain – Ensure availability of specialized construction equipment, contracts, and materials – Develop well-documented system with clear interface points – Preplan and rehearse response and recovery scenarios for high- probability events  Earthquake  Hurricane  Flood  Engagement with engineering and construction community must begin pre- disaster – Pre-placed contracts  Program management  EPC © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 16
  • 17. PM World Today – September 2011 (Vol. XIII, Issue IX)  Supply chain – Earliest mobilization to disaster zone – Early activation of logistics chains  Post-disaster period requires streamlined decision frameworks – Decision authorities at project and disaster site – Logistical-affecting processes may act as barrier in post-disaster scenario  Examples are customs, building permits, and liability legislation  Consider a standard “modified” logistical template for local government consideration  “Go-bys”  Best practices © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 17
  • 18. PM World Today – September 2011 (Vol. XIII, Issue IX) About the Authors Bob Prieto Co-Author Bob Prieto is a Senior Vice President of Fluor Corporation, one of America’s largest engineering, construction and project management firms, where he is responsible for strategy in support of the firm’s Industrial & Infrastructure Group and its key clients. He focuses on the development, delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the Industry Leaders’ Council of the American Society of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He currently serves on a number of committees looking at issues related to infrastructure delivery and resiliency and disaster response and rebuilding and is a member of the National Academy of Construction. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and previously served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He recently completed ten year tenure as a member of the board of trustees of Polytechnic University of New York culminating in its merger with New York University. Bob is the author of “Strategic Program Management” published by the Construction Management Association of America (CMAA) and more recently a companion work entitled “Topics in Strategic Program Management”. © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 18
  • 19. PM World Today – September 2011 (Vol. XIII, Issue IX) Charles (Al) Whitaker Co-Author Al Whitaker has served as program manager for DOE, DOD, FEMA and other government agencies and programs and has been responsible for managing large federal programs in the area of environmental services (facilities permitting, design, and construction and site remediation) and disaster relief. He was Fluor’s program manager for the FEMA Individual Assistance Technical Assistance Program. This program provides temporary housing to disaster victims. The scope for the program includes full engineering, procurement, construction, and maintenance services. As Program Manager his responsibilities included the execution of all task orders for disaster response anywhere FEMA is called upon to respond. Task Orders included work in Florida, Wyoming, Louisiana, Alabama, Mississippi, Kansas and Texas. Revenues from this program have exceeded $1.5 billion and over 900 million safe work hours have been executed. 1976-1980. Al Whitaker has a Bachelor of Science degree in Civil Engineering (Chi Epsilon, Civil Engineering Honorary Fraternity) from the University of Kentucky, Lexington, Kentucky, USA (1976-1980); and a Masters of business Administration from Texas A&M University, Mays Graduate School of Business, College Station, Texas, USA (2002 – 2004). © 2011 Bob Prieto and Al Whitaker PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 19