SlideShare ist ein Scribd-Unternehmen logo
1 von 4
Downloaden Sie, um offline zu lesen
infrastructure:Layout 1         18/11/10        10:24      Page 1




  70    INFRASTRUCTURE
        Paulo Jorge Ribeiro Corte Real de Oliveira
        Project Manager, Neopul




        Deploying Neopul’s
        know-how in Dublin
        This report describes Neopul’s work on the Luas b1-400 extension of the Green Line from the Sandyford
        depot to Cherrywood industrial estate, which was opened to the public on 16 October 2010.

        The green line was the existing connection           embedded slab track system with the                different track types were used together with
        from Dublin city centre (St. Stephen’s Green         exception of the referred Sandyford Stop,          the necessary solutions to cater for the
        Station) and the recent developed Sandyford          which was extended with a pre-casted system        respective transitions, which were:
        area with an extension of 9km. The scope of the      put on top of the existing ballasted track             Approximately 3,500 linear metres of single
        B1-400 extension developed by Neopul,                (Bodan System). Upon casting the panels which          ballast track – built with the supply of
        included the expansion of the existing line with     formed the system, special care was taken in           10,100 tonnes of calibrated ballast, 4,000
        more 7.5km towards the south from the                consideration once there was a signalling loop         monobloc sleepers with 8,000 Vossloh
        existing Sandyford Stop to Brides Glen. This         located on the extended area. On this location,        fastening system type Skl 14, 343 tonnes of
        contract also included the expansion of the          the respective panels not only had to have a           vignole S49E1 rails, 12 turnouts with point
        Sandyford Depot (2km of single track) in order       recess to cater for the loop, but also the rebar       heating system and special track
        to cater for the new vehicles.                       had to be replaced by glass fibre cables to            equipment including twist rails, normal
            Neopul’s work scope included the design,         ensure the same strength and durability                and isolated rail joints and transition rails
        construction, testing and commissioning of           without compromising or interfering with the           to allow a perfect transition between the
        approximately 17km of single track of light rail     loop operation.                                        vignole and grooved sections.
        line system with 1,435mm gauge.                          The Stops built were Sandyford (existing);         Approximately 8,400 linear metres of single
                                                             Central Park; Glencairn; The Gallops;                  embedded track – built with the supply of
        Stops                                                Leopardstown; Racecourse; Carrickmines;                11,000 cubic metres of C40/50 concrete,
        The Luas B1-400 contract included the execution      Brennanstown; Laughanstown; Cherrywood                 1,175 tonnes of rebar, 118 tonnes of rubber
        of 11 stops and the extension of the existing        and Brides Glen.                                       encapsulated grooved Ri54 rails and 865
        Sandyford Stop from 40m to 53m as well as the                                                               tonnes of encapsulated grooved Ri59 rails,
        increase of its platforms from two to three.         Track types                                            one encapsulated Ri54 grooved rail
            All stops were executed in a concrete            On the materialisation of the track, three             diamond crossover with point heating



        EUROPEAN RAILWAY REVIEW ISSUE 6 2010
infrastructure:Layout 1          18/11/10        10:25      Page 2




                                                                                                                             INFRASTRUCTURE             71




          Detail of the extension of Sandyford Stop with the Bodan system


            system, special track equipment, complete            special track equipment including twist     Approximately 2,500 aluminothermic
            rubber encapsulation of all the system,              rails, expansion joints and normal and      weldings including ultrasonic testing of
            12 pairs of encapsulated grooved Ri54                isolated rail joints                        every single one.
            expansion joints, embedded transversal
            and longitudinal drainage and a system
            for derailment prevention on the
            structures (bridges and tunnels) – tram
            arresting devices.
            Approximately 3,200 linear metres of single
            plinth track – built with the supply of 1,200
            cubic metres of concrete, 91 tonnes of
            rebar, 314 tonnes of vignole S49E1 rails,
            12 pairs of vignole rail bridge expansion
            joints, 10,000 Vossloh fastening systems
            type 336 and special track equipment
            including twist rails, normal and isolated
            rail joints and transition rails to allow a
            perfect transition between the vignole
            and grooved sections
            Approximately 1,800 linear metres of single
            ballast track inside the Sandyford Depot to
            increase the number of stabling lines –
            built with the supply of 7,000 tonnes of
            calibrated ballast, 2,000 monobloc sleepers
            with 4,000 Vossloh fastening system type
            Skl 14, 177 tonnes of vignole S49E1 rails, 10       Preventive grinding on the plinth track
            turnouts with point heating system and



        www.europeanrailwayreview.com                                                                      EUROPEAN RAILWAY REVIEW ISSUE 6 2010
infrastructure:Layout 1         18/11/10        10:25        Page 3




  72    INFRASTRUCTURE


                                                                                        rubber encapsulation to the rails on a
                                                                                        controlled environment, before forming the
                                                                                        18m track panels put together with the
                                                                                        Rheinfeder system.
                                                                                            Besides the track, there was also the
                                                                                        following installed:
                                                                                            In the vicinity of the Sandyford Stop, one
                                                                                            trailing non-motorised switch, three set of
                                                                                            motorised facing switches and four sets of
                                                                                            non-motorised points set for spring
                                                                                            operation to facilitate normal reversing
                                                                                            operations at the stop
                                                                                            On the Sandyford Depot, one trailing non-
                                                                                            motorised switch and nine sets of
                                                                                            motorised facing switches operated by the
                                                                                            tram drivers
                                                                                            Two trailing non-motorised switches and a
                                                                                            track crossover located between the
                                                                                            running lines in the vicinity of The Gallops
                                                                                            and The Carrickmines tram stops (two in
                                                                                            each) for emergency and occasional
                                                                                            operational use




          Cherrywood viaduct. Bride Glen’s Stop, at the end



        Track work description
        The ballasted track was built essentially in areas
        separated from the urban regions, whilst the
        embedded track was built in areas shared with
        the traffic (road crossings) and in urbanised
        areas or where urbanisation is planned. The
        plinth track was installed over concrete
        structures (viaducts and bridges) constructed in
        previous contracts.
            The ballasted track was positioned and
        levelled thanks to rail road excavators equipped
        with two independent tamping heads with
        variable depth and positioning control, able to
        tamp track and turnout sleepers, together with
        mechanic rail jigs.
            The plinth track was positioned thanks to
        the use of levelling jigs and alignment push
        pull props, whilst on the embedded track a pre
        mounted sacrificial system formed from
        metallic sleepers and levelling bolts
        (Rheinfeder System) was used. This system was
        entirely assembled on a compound built for
        this purpose, were a covered marquee with an             Leopardstown viaduct
        area of 2,500m2 was created to allow gluing the



        EUROPEAN RAILWAY REVIEW ISSUE 6 2010
infrastructure:Layout 1        18/11/10        10:26      Page 4




                                                                                                                                        INFRASTRUCTURE                       73

                                                                                                                  In order to overcome the longitudinal
                                                                                                              movements imposed by the joints between the
                                                                                                              land and the structures, 24 expansion joints
                                                                                                              were supplied and applied.
                                                                                                                  All rail profiles were joined with
                                                                                                              aluminothermic weldings and every single one
                                                                                                              was tested ultrasonically.
                                                                                                                  Tension releasing was performed to all non
                                                                                                              embedded track.
                                                                                                                  At the end of the construction but before
                                                                                                              gauge run, preventive grinding was applied to
                                                                                                              the entire line.


                                                                                                              OCS
                                                                                                              Regarding the OCS system and under this
                                                                                                              contract, Neopul constructed the complete
                                                                                                              Overhead Conductor System to be operated at
                                                                                                              a nominal tension of 750 Vcc on the complete
                                                                                                              17km of single track including OCS poles (lateral
                                                                                                              & axis), bracket arms, cross span and stitches,
                                                                                                              pole tensioning equipment/mechanism, wall
                                                                                                              fixings and building anchors, overhead line
                                                                                                              equipment including conductor and feeder
                                                                                                              system including the connection to the OCS.
                                                                                                                  On the Sandyford Depot, Neopul also
                                                                                                              constructed the Overhead Conductor System
                                                                                                              sectioning, including splitting the OCS power
                                                                                                              feeding the PIT and SLAB lanes into two
                                                                                                              separate sections per lane and all necessary
                                                                                                              changes to integrate the new system to the old
                                                                                                              one including Poles, suspensions (GRP
                                                                                                              bracketarms), anchoring, section insulators and
                                                                                                              contact wire.
                                                                                                                  Besides the overhead, Neopul’s scope also
                                                                                                              included the materialisation of the feeder
                                                                                                              cables and return traction along all the track
                                                                                                              extension, including Trackside Distribution
                                                                                                              Cabinets and Track Disconnector Switches
          OCS construction on Leopardstown viaduct                                                            ensuring a perfect interface with the existing
                                                                                                              Luas system.
            A set of scissor points in advance of the           Leopardstown Viaduct – over the M50               All work was done ensuring the
            Brides Glen terminus comprising one set of          Highway                                       compatibility, interoperability of the tram
            motorised facing switches and three sets of         Carrickmines Viaduct – over the M50           services with existing Luas infrastructure and
            non-motorised points set for spring                 Highway                                       according with the maintenance requirements.
            operation to facilitate normal reversing            Glenamuck Underpass – under
            operations at the stop.                             Glenamuck Road
                                                                Spine Road Tunel – under a future                                     Paulo Jorge Ribeiro Corte
        On the Cherrywood viaduct on the track                  development area                                                      Real de Oliveira
        terminus, besides the construction and                  Cherrywood Viaduct – over the R118 Road.                                Paulo Jorge Ribeiro Corte Real de
                                                                                                                                        Oliveira has a Degree in Civil
        concrete sealing of the track, Neopul also                                                                                      Engineering which he achieved from
        applied imprinted black concrete on the             Due to the low temperatures during the Irish                                the Faculdade de Engenharia da
                                                                                                                                        Universidade do Porto. Since May
        surface, white on the walkways.                     winter, point heating systems were installed in
                                                                                                               2007 until August 2010, he was Neopul’s Project Manager of
            The track crossed the following structures:     all turnouts except on the emergency               the design and build of track and overhead conductor system
            Brewery Road Viaduct – over the Brewery         diagonals, in order to defrost the points          of the recently opened Luas Green Line extension from
                                                                                                               Sandyford to Cherrywood.
            Road roundabout                                 whenever necessary.



        www.europeanrailwayreview.com                                                                         EUROPEAN RAILWAY REVIEW ISSUE 6 2010

Weitere ähnliche Inhalte

Was ist angesagt?

Deepwater sub sea capital equipment
Deepwater sub sea capital equipmentDeepwater sub sea capital equipment
Deepwater sub sea capital equipmentamrhaggag
 
Miami Pré Sal José Formigalli
Miami Pré Sal José FormigalliMiami Pré Sal José Formigalli
Miami Pré Sal José FormigalliPetrobras
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004David Seow
 
Royal IHC corporate presentation
Royal IHC corporate presentationRoyal IHC corporate presentation
Royal IHC corporate presentationRoyal IHC
 
New osx project update_agosto_final_inglês
New osx project update_agosto_final_inglêsNew osx project update_agosto_final_inglês
New osx project update_agosto_final_inglêsosxri
 

Was ist angesagt? (6)

Deepwater sub sea capital equipment
Deepwater sub sea capital equipmentDeepwater sub sea capital equipment
Deepwater sub sea capital equipment
 
Miami Pré Sal José Formigalli
Miami Pré Sal José FormigalliMiami Pré Sal José Formigalli
Miami Pré Sal José Formigalli
 
deep_orient
deep_orientdeep_orient
deep_orient
 
C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004C9 FPSO Layout and Turret 2004
C9 FPSO Layout and Turret 2004
 
Royal IHC corporate presentation
Royal IHC corporate presentationRoyal IHC corporate presentation
Royal IHC corporate presentation
 
New osx project update_agosto_final_inglês
New osx project update_agosto_final_inglêsNew osx project update_agosto_final_inglês
New osx project update_agosto_final_inglês
 

Ähnlich wie European Railway Review Issue 6 2010

Tubular Track - Namibia
Tubular Track - NamibiaTubular Track - Namibia
Tubular Track - NamibiaTubular Track
 
Chalmer G. Galido powerpoint present pptx
Chalmer G. Galido powerpoint present pptxChalmer G. Galido powerpoint present pptx
Chalmer G. Galido powerpoint present pptxJustineSales1
 
Mining & Aggregate Conveyors Applications & Innovations
Mining & Aggregate Conveyors Applications & InnovationsMining & Aggregate Conveyors Applications & Innovations
Mining & Aggregate Conveyors Applications & InnovationsAltra Industrial Motion
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
Traction distribution
Traction distribution Traction distribution
Traction distribution Amit Kumar
 
Catalog - Products - Naval machinery and naval components - 2009 - English
Catalog - Products - Naval machinery and naval components - 2009 - EnglishCatalog - Products - Naval machinery and naval components - 2009 - English
Catalog - Products - Naval machinery and naval components - 2009 - EnglishDaniel Razvan Picioroaga
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systemsArnab Chakraborty
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling PlantAshrant Dass
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overviewminh nguyễn
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillDeanGarratt
 
Semimechanization sdls&lh ds
Semimechanization sdls&lh dsSemimechanization sdls&lh ds
Semimechanization sdls&lh dsSATYANARAYANA I
 
Nexans submarine technology-1
Nexans submarine technology-1Nexans submarine technology-1
Nexans submarine technology-1thinknice
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyKTN
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyAmanraj Singh Padan
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipelineVladimir Popovic
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingVladimir Popovic
 
Ed1 r4 product specification
Ed1 r4 product specificationEd1 r4 product specification
Ed1 r4 product specificationPrabhakar Tiwari
 
61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptxVevietpomata
 

Ähnlich wie European Railway Review Issue 6 2010 (20)

Tubular Track - Namibia
Tubular Track - NamibiaTubular Track - Namibia
Tubular Track - Namibia
 
the millau viaduct
the millau viaductthe millau viaduct
the millau viaduct
 
Chalmer G. Galido powerpoint present pptx
Chalmer G. Galido powerpoint present pptxChalmer G. Galido powerpoint present pptx
Chalmer G. Galido powerpoint present pptx
 
Mining & Aggregate Conveyors Applications & Innovations
Mining & Aggregate Conveyors Applications & InnovationsMining & Aggregate Conveyors Applications & Innovations
Mining & Aggregate Conveyors Applications & Innovations
 
Crossrail-C336-Paddington-New-Yard
Crossrail-C336-Paddington-New-YardCrossrail-C336-Paddington-New-Yard
Crossrail-C336-Paddington-New-Yard
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Traction distribution
Traction distribution Traction distribution
Traction distribution
 
Catalog - Products - Naval machinery and naval components - 2009 - English
Catalog - Products - Naval machinery and naval components - 2009 - EnglishCatalog - Products - Naval machinery and naval components - 2009 - English
Catalog - Products - Naval machinery and naval components - 2009 - English
 
Presentation on coal handling systems
Presentation on coal handling systemsPresentation on coal handling systems
Presentation on coal handling systems
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
Offshore oil and gas overview
Offshore oil and gas overviewOffshore oil and gas overview
Offshore oil and gas overview
 
Blue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drillBlue mountains cascade dam- Horizontal direction drill
Blue mountains cascade dam- Horizontal direction drill
 
Semimechanization sdls&lh ds
Semimechanization sdls&lh dsSemimechanization sdls&lh ds
Semimechanization sdls&lh ds
 
Nexans submarine technology-1
Nexans submarine technology-1Nexans submarine technology-1
Nexans submarine technology-1
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
 
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - CopyPROJECT ON  STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
PROJECT ON STUDY OF COMMUNICATION PROBLEM IN ABB DRIVE - Copy
 
Ghadames project, conveyance pipeline
Ghadames project, conveyance pipelineGhadames project, conveyance pipeline
Ghadames project, conveyance pipeline
 
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - PipelayingMan Made River Project - IV Phase / Ghadames Project - Pipelaying
Man Made River Project - IV Phase / Ghadames Project - Pipelaying
 
Ed1 r4 product specification
Ed1 r4 product specificationEd1 r4 product specification
Ed1 r4 product specification
 
61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx61904252-ONGC-ANKLESHWAR-ASSET.pptx
61904252-ONGC-ANKLESHWAR-ASSET.pptx
 

European Railway Review Issue 6 2010

  • 1. infrastructure:Layout 1 18/11/10 10:24 Page 1 70 INFRASTRUCTURE Paulo Jorge Ribeiro Corte Real de Oliveira Project Manager, Neopul Deploying Neopul’s know-how in Dublin This report describes Neopul’s work on the Luas b1-400 extension of the Green Line from the Sandyford depot to Cherrywood industrial estate, which was opened to the public on 16 October 2010. The green line was the existing connection embedded slab track system with the different track types were used together with from Dublin city centre (St. Stephen’s Green exception of the referred Sandyford Stop, the necessary solutions to cater for the Station) and the recent developed Sandyford which was extended with a pre-casted system respective transitions, which were: area with an extension of 9km. The scope of the put on top of the existing ballasted track Approximately 3,500 linear metres of single B1-400 extension developed by Neopul, (Bodan System). Upon casting the panels which ballast track – built with the supply of included the expansion of the existing line with formed the system, special care was taken in 10,100 tonnes of calibrated ballast, 4,000 more 7.5km towards the south from the consideration once there was a signalling loop monobloc sleepers with 8,000 Vossloh existing Sandyford Stop to Brides Glen. This located on the extended area. On this location, fastening system type Skl 14, 343 tonnes of contract also included the expansion of the the respective panels not only had to have a vignole S49E1 rails, 12 turnouts with point Sandyford Depot (2km of single track) in order recess to cater for the loop, but also the rebar heating system and special track to cater for the new vehicles. had to be replaced by glass fibre cables to equipment including twist rails, normal Neopul’s work scope included the design, ensure the same strength and durability and isolated rail joints and transition rails construction, testing and commissioning of without compromising or interfering with the to allow a perfect transition between the approximately 17km of single track of light rail loop operation. vignole and grooved sections. line system with 1,435mm gauge. The Stops built were Sandyford (existing); Approximately 8,400 linear metres of single Central Park; Glencairn; The Gallops; embedded track – built with the supply of Stops Leopardstown; Racecourse; Carrickmines; 11,000 cubic metres of C40/50 concrete, The Luas B1-400 contract included the execution Brennanstown; Laughanstown; Cherrywood 1,175 tonnes of rebar, 118 tonnes of rubber of 11 stops and the extension of the existing and Brides Glen. encapsulated grooved Ri54 rails and 865 Sandyford Stop from 40m to 53m as well as the tonnes of encapsulated grooved Ri59 rails, increase of its platforms from two to three. Track types one encapsulated Ri54 grooved rail All stops were executed in a concrete On the materialisation of the track, three diamond crossover with point heating EUROPEAN RAILWAY REVIEW ISSUE 6 2010
  • 2. infrastructure:Layout 1 18/11/10 10:25 Page 2 INFRASTRUCTURE 71 Detail of the extension of Sandyford Stop with the Bodan system system, special track equipment, complete special track equipment including twist Approximately 2,500 aluminothermic rubber encapsulation of all the system, rails, expansion joints and normal and weldings including ultrasonic testing of 12 pairs of encapsulated grooved Ri54 isolated rail joints every single one. expansion joints, embedded transversal and longitudinal drainage and a system for derailment prevention on the structures (bridges and tunnels) – tram arresting devices. Approximately 3,200 linear metres of single plinth track – built with the supply of 1,200 cubic metres of concrete, 91 tonnes of rebar, 314 tonnes of vignole S49E1 rails, 12 pairs of vignole rail bridge expansion joints, 10,000 Vossloh fastening systems type 336 and special track equipment including twist rails, normal and isolated rail joints and transition rails to allow a perfect transition between the vignole and grooved sections Approximately 1,800 linear metres of single ballast track inside the Sandyford Depot to increase the number of stabling lines – built with the supply of 7,000 tonnes of calibrated ballast, 2,000 monobloc sleepers with 4,000 Vossloh fastening system type Skl 14, 177 tonnes of vignole S49E1 rails, 10 Preventive grinding on the plinth track turnouts with point heating system and www.europeanrailwayreview.com EUROPEAN RAILWAY REVIEW ISSUE 6 2010
  • 3. infrastructure:Layout 1 18/11/10 10:25 Page 3 72 INFRASTRUCTURE rubber encapsulation to the rails on a controlled environment, before forming the 18m track panels put together with the Rheinfeder system. Besides the track, there was also the following installed: In the vicinity of the Sandyford Stop, one trailing non-motorised switch, three set of motorised facing switches and four sets of non-motorised points set for spring operation to facilitate normal reversing operations at the stop On the Sandyford Depot, one trailing non- motorised switch and nine sets of motorised facing switches operated by the tram drivers Two trailing non-motorised switches and a track crossover located between the running lines in the vicinity of The Gallops and The Carrickmines tram stops (two in each) for emergency and occasional operational use Cherrywood viaduct. Bride Glen’s Stop, at the end Track work description The ballasted track was built essentially in areas separated from the urban regions, whilst the embedded track was built in areas shared with the traffic (road crossings) and in urbanised areas or where urbanisation is planned. The plinth track was installed over concrete structures (viaducts and bridges) constructed in previous contracts. The ballasted track was positioned and levelled thanks to rail road excavators equipped with two independent tamping heads with variable depth and positioning control, able to tamp track and turnout sleepers, together with mechanic rail jigs. The plinth track was positioned thanks to the use of levelling jigs and alignment push pull props, whilst on the embedded track a pre mounted sacrificial system formed from metallic sleepers and levelling bolts (Rheinfeder System) was used. This system was entirely assembled on a compound built for this purpose, were a covered marquee with an Leopardstown viaduct area of 2,500m2 was created to allow gluing the EUROPEAN RAILWAY REVIEW ISSUE 6 2010
  • 4. infrastructure:Layout 1 18/11/10 10:26 Page 4 INFRASTRUCTURE 73 In order to overcome the longitudinal movements imposed by the joints between the land and the structures, 24 expansion joints were supplied and applied. All rail profiles were joined with aluminothermic weldings and every single one was tested ultrasonically. Tension releasing was performed to all non embedded track. At the end of the construction but before gauge run, preventive grinding was applied to the entire line. OCS Regarding the OCS system and under this contract, Neopul constructed the complete Overhead Conductor System to be operated at a nominal tension of 750 Vcc on the complete 17km of single track including OCS poles (lateral & axis), bracket arms, cross span and stitches, pole tensioning equipment/mechanism, wall fixings and building anchors, overhead line equipment including conductor and feeder system including the connection to the OCS. On the Sandyford Depot, Neopul also constructed the Overhead Conductor System sectioning, including splitting the OCS power feeding the PIT and SLAB lanes into two separate sections per lane and all necessary changes to integrate the new system to the old one including Poles, suspensions (GRP bracketarms), anchoring, section insulators and contact wire. Besides the overhead, Neopul’s scope also included the materialisation of the feeder cables and return traction along all the track extension, including Trackside Distribution Cabinets and Track Disconnector Switches OCS construction on Leopardstown viaduct ensuring a perfect interface with the existing Luas system. A set of scissor points in advance of the Leopardstown Viaduct – over the M50 All work was done ensuring the Brides Glen terminus comprising one set of Highway compatibility, interoperability of the tram motorised facing switches and three sets of Carrickmines Viaduct – over the M50 services with existing Luas infrastructure and non-motorised points set for spring Highway according with the maintenance requirements. operation to facilitate normal reversing Glenamuck Underpass – under operations at the stop. Glenamuck Road Spine Road Tunel – under a future Paulo Jorge Ribeiro Corte On the Cherrywood viaduct on the track development area Real de Oliveira terminus, besides the construction and Cherrywood Viaduct – over the R118 Road. Paulo Jorge Ribeiro Corte Real de Oliveira has a Degree in Civil concrete sealing of the track, Neopul also Engineering which he achieved from applied imprinted black concrete on the Due to the low temperatures during the Irish the Faculdade de Engenharia da Universidade do Porto. Since May surface, white on the walkways. winter, point heating systems were installed in 2007 until August 2010, he was Neopul’s Project Manager of The track crossed the following structures: all turnouts except on the emergency the design and build of track and overhead conductor system Brewery Road Viaduct – over the Brewery diagonals, in order to defrost the points of the recently opened Luas Green Line extension from Sandyford to Cherrywood. Road roundabout whenever necessary. www.europeanrailwayreview.com EUROPEAN RAILWAY REVIEW ISSUE 6 2010