Acumen has completed the first leg of the World Tour. This presentation is an in-depth overview of Acumen's solutions, as well as several Fuse use cases from Fuse clients
17. // Claims Analysis
Insight into project variances
◦ Advanced forensics
◦ Fuse gives meaning to the
impact of changes
◦ Pinpoints changes to critical/
driving path
◦ Every single project attribute
can be checked
◦ Calendar definition changes
May 16, 2012
18. // Reporting
Publish Analysis Results
Executive Analyst Dashboard! API &
Briefing! Report! • Interactive Custom
• Summary of • To do list! charts & Reports"
graphs"
analysis • Automation
results! of existing
reports"
May 16, 2012
19. // Integration
Schedule, Cost, Risk, Performance, EV
Asta
Cobra
Open
Prism
Plan
G2
P3/P6
PRA
MS
Excel/
Project
XML
Na>ve
tool
not
May 16, 2012
required
20. // Case Study #1
Owner/contractor Alignment
• Houston-based oil/gas owner
• Objective:
• More on-time completion for projects over $250MM
• Encourage more mature contractor schedules
• Overcome “brain drain” in scheduling
• How achieved:
• Mandated contractor Fuse Schedule Index of 75+
• Gave contractor opportunity to self-assess
22. // Case Study #1
Owner/contractor Alignment
• Outcome:
• Contractor achieved 75+ Fuse Schedule Index
• Schedule was more realistic
• Schedule was earlier!
• Owner gained confidence in the contractor
• Better collaboration & alignment between stakeholders
23. // Acumen Cloud™
Project Benchmarking
◦ Communitized benchmarking
◦ Means of determining:
◦ Schedule quality?
◦ How this ranks with other projects?
◦ How does this align our project for on-time completion?
◦ 100% anonymous, secure (SSL)
◦ Continuously getting more intelligent
◦ New libraries can be pushed to Fuse!
26. // Case Study #2
Bidding Competitiveness
• EPC bids for a utility turnaround
• Three competing bidders
• Objective:
• Owner wanting to make informed award decision
• Cheapest? Fastest? Most achievable?
• How Achieved:
• Compared schedule, cost, quality metrics
• Benchmarked using Acumen Cloud™
40. // Case Study #2
Bidding Competitiveness
• Outcome:
• Contractor B fastest, cheapest but poorest quality
• Contractor A cheapest but fundamental logic flaw
• Contractor C was most expensive but…
• Had highest quality score
• Had a true continuous driving path
• Had sound cash flow
• Ranked highly with regards to benchmarking
• Was awarded the contract!
41. Realistic Scheduling
// Case Study #3
Schedule Acceleration/Risk Reduction // S1 The Base
// S2 Critiqued
◦ GasCom // S3 Risk-Adjusted
◦ LNG Pipeline & Facility Owner
// S4 Optimized
◦ Early FEED stage
// S5 Team-Aligned
◦ Project Details
◦ Readying for sanction approval
◦ Expected First Gas Date: Dec. 2013
◦ Gas sales contract already established
◦ Using Primavera P6
42. Realistic Scheduling
// S1 > S2
Schedule Review // S1 The Base
// S2 Critiqued
◦ Sanction Board Requirements // S3 Risk-Adjusted
◦ Risk-adjusted forecast P75 // S4 Optimized
◦ Fuse Schedule Index 75+ // S5 Team-Aligned
◦ Project Status
◦ S1 showing Dec 13 first gas
◦ Risk assessment not yet conducted
43. // S1 > S2 Schedule Critique
Sound Basis of Schedule
◦ Validated multiple sub-projects
◦ Test to ensure true path to First Gas
◦ Analysis showed break in path around Early Works
◦ Fixing this, First Gas moved to the right by 2 months
◦ Schedule cleanse: further 3 months adjustment
May 16, 2012
44. // Removal of Logic Redundancy
Simplification of Schedule
8%
redundancy
Removal of redundancy led to a cleaner, more robust schedule
45. Realistic Scheduling
// S1 > S2
Summary // S1 The Base
// S2 Critiqued
◦ S2 First Gas date: May 2014 // S3 Risk-Adjusted
S1: Dec 2013 5
months
S2: May 2014 // S4 Optimized
// S5 Team-Aligned
◦ Schedule Critique Details:
◦ Missing Logic was added
◦ Lags converted to activities
◦ Float analysis
◦ Showed padding of early activities
46. // Float Analysis
GasCom
◦ S1 showed high float in early stage of project
◦ S2 resolved schedule showed the opposite
◦ Early acceleration opportunity went away
Originally perceived opportunity
for making up lost time through Resolved schedule not
60
float absorption in early stage of offering early stage schedule
40
project acceleration
20
0
Q1
Q2
Q3
Q4
2011
2011
Q1
Q2
2011
2011
Q3
2012
2012
Q4
Q1
2012
2012
Q2
Q3
2013
2013
Q4
2013
Q1
Q2
2013
2014
Q3
2014
Q4
S1
Average
Float
S2
Average
Float
2014
2014
47. Realistic Scheduling
// S2 > S3
Risk Analysis // S1 The Base
// S2 Critiqued
◦ Objective: // S3 Risk-Adjusted
◦ Determine a P75 First Gas date
// S4 Optimized
◦ Conducted Risk Workshop
// S5 Team-Aligned
Schedule
Risk
Events
Uncertainty
48. // GasCom Perception of Risk Exposure
Risk Inputs & Outputs
Uncertainty Factor Best Case (Optimistic) Worst Case (Pessimistic)
Very Conservative 50% 100%
Conservative 75% 105%
Realistic 90% 110%
Aggressive 95% 125%
Very Aggressive 100% 150%
70%
60%
Team
Percep>on
50%
Actual
Risk
Hotspots
40%
30%
20%
10%
0%
49. // Risk Insight
Risk Inputs
Aggressive
Conserva>ve
Broad
Risk
Range
• Skew
to
the
right
• Skew
to
the
lef
• Range
<>
dura>on
Ques>onable
No
Risk
Average
Risk
Range
• Missed
ranging
Range
• Accidently
includes
risk
• Degree
of
uncertainty
events
No
upside
No
Downside
Wrong
• Can
only
be
later
• Can
only
be
earlier
• Inputs
don’t
align
53. Realistic Scheduling
// S2 > S3
Summary // S1 The Base
// S2 Critiqued
◦ P75 risk-adjusted First Gas: Oct 2014 // S3 Risk-Adjusted
◦ 10 months later than board expectations
// S4 Optimized
S1: S2: S3: // S5 Team-Aligned
Dec 2013 5
May 2014 10
Oct 2014
◦ Identified key risk hot spots
◦ Long Lead procurement items
◦ Hidden path identified
◦ Driven by land acquisition delaying
pipeline early works
54. Realistic Scheduling
// S3 > S4
Getting back to Dec 2013 // S1 The Base
// S2 Critiqued
// S3 Risk-Adjusted
◦ Risk Mitigation:
// S4 Optimized
◦ Response plan identified for key risks
// S5 Team-Aligned
◦ Response plans added to schedule
◦ Assessed cost/benefit of mitigation
◦ $100MM investment to save 1 month
55. Realistic Scheduling
// S3 > S4
Getting back to Dec 2013 // S1 The Base
// S2 Critiqued
◦ Schedule Acceleration details: // S3 Risk-Adjusted
◦ LNG Pipeline ready for hookup: Feb 13 // S4 Optimized
◦ LNG Facility ready to receive gas: Nov 13 // S5 Team-Aligned
◦ Focus needed:
◦ Accelerating the LNG facility
◦ Could afford to slow down pipeline/
field work by months…
56. // LNG Facility
Acceleration Criteria Set
◦ Criteria set drives acceleration
◦ Reduce duration LNG
Facility
◦ More resources
Script
Objec/ve
◦ Changed calendars “accelerate
Facility
by
6
◦ Contractor incentive months”
Step
1
Step
2
Step
3
◦ Delay Train 2 Accelerate
Delay
Train
Introduce
6
Jeoy
2
ac>vi>es
day
working
construc>on
week/larger
camp
57. // How did this work?
Fuse 360 Acceleration
◦ CPM simulation
◦ Critical path focus
◦ Incremental push
◦ Prioritize
◦ Earliest/latest
◦ Longest durations
◦ Least resistance
58. Realistic Scheduling
// S3 > S4 > S5
Summary // S1 The Base
// S2 Critiqued
◦ LNG Facility: // S3 Risk-Adjusted
◦ Accelerated sufficiently
// S4 Optimized
◦ No longer the driving path
// S5 Team-Aligned
◦ S4 Deterministic First Gas: Aug 2013
◦ 4 months earlier than S1
◦ 12 months earlier than S3
◦ P75 risk-adjusted: Feb 2014
◦ S5 Team Buy-in
◦ Final 2 months achieved through more
aggressive mitigation
59. // GasCom Case Study
The Result
◦ Fully vetted, bought-into schedule
◦ Risk-adjusted
◦ LNG Facility accelerated to align with pipeline
◦ Mitigation plan sponsored by board
◦ Sanction awarded!
S5: Mitigated
Dec 1 2013
P75 S4: Feb 2014
S4: Accelerated S1: Target 1st Gas S2: Resolved Schedule S3: Risk-Adjusted
Aug 1 2013 Dec 1 2013 May 1 2014 Oct 1 2014
60. 6
// GasCom First Gas Dates 0
Evolution of Schedule Model
10
P75
Schedule
Delay
From
Dec
2013
1st
Gas
(months)
9
8
7
6
Resolved, risk-
10
5
adjusted,
accelerated,
4
mitigated
3
5
2
2 0
1
0
0
S1
-‐
base
S2
-‐
resolved
S3
-‐
risk-‐adjusted
S4
-‐
accelerated
S5
-‐
mi>gated
Scenario
May 16, 2012
61. // Case Study #3
Fuse Modules
ü Float analysis
ü Risk Metrics
ü Fuse 360
// Fuse 360 Demo
62. // Acceleration Efficiency™
Measure of Acceleration Effort
Example
1
Example
2
◦ 2 day project acceleration ◦ 2 day project acceleration
◦ Requires 2 days of reduction ◦ Requires 2 days of reduction
◦ Acceleration Efficiency =2/2 100% ◦ Acceleration Efficiency=2/3 67%
2 day activity
reduction 2 day activity
reduction
1 day activity
3 reduction
2 day project 2 day project
acceleration acceleration
63. // Case Study #4: Measuring Project Performance
Baseline Compliance™
◦ Traditional measures include:
◦ Earned value: heavy time investment to implement
◦ Earned schedule: similar to EV
◦ % complete: what does this really tell us?
◦ Ahead/behind baseline: too granular a scale…
◦ Baseline Compliance™
◦ Determine how close schedule is executed against baseline
◦ Measure of change during planning phase
◦ Measure of well the plan is being executed
◦ More than just date comparison
◦ Looks at period-compliance
May 16, 2012
64. // Baseline Compliance Index™
Examines
how
many
ac>vi>es
fell
within
the
expected
repor>ng
period