// A Fresh Take on Project Forensics
  Enhanced Schedule Delay Forensics through Project Metrics and Ribbon Analysis




                      Dr. Dan Patterson, PMP
                        CEO & President, Acumen

                             October 2010




                                       +1 512 291 6261 // info@projectacumen.com

                                                www.projectacumen.com
Table of Contents
   Introduction ................................................................................................................. 3
   Types of Claims ........................................................................................................... 3
   “As-planned” and “As-built” Scenarios ...................................................................... 3
   Delay Analysis .............................................................................................................. 4
       Foresight Methods:................................................................................................... 4
   Liability of Delay .......................................................................................................... 5
          Figure 1 – Ownership of Delays ............................................................................ 5
   Why are Delay Claims so Complex? .............................................................................. 6
   How Can Metric Analysis and Ribbon Visualization Help? ............................................ 6
          Figure 2 – Example of Schedule Quality Forensic Analysis ................................... 6
          Figure 3 – Example Ribbon Analysis .................................................................... 7

Using Ribbon Metric Analysis to Compare Project Scenarios ........................................... 7
          Figure 4a – Changed Durations ........................................................................... 8
          Figure 4b – Modified Logic ................................................................................... 8
          Figure 4c – Modified Lags .................................................................................... 8
          Figure 5 – Comparison between Original and Changed Scope Scenarios............. 9
          Figure 6 – Ribbon Analysis Pinpointing Delay Drivers ........................................ 10

Cause and Effect Metrics .............................................................................................. 10

Conclusions ................................................................................................................... 11




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                       2
Introduction
The business of schedule claims is both an art and a science. This paper discusses
how an analytical approach to schedule forensics using metric analysis results in a
highly effective means of determining the root cause and resultant damaging impact as
part of the project claims process. The technique can be used by owners or contractors
alike during arbitration and litigation cases.

In a perfect scenario, the need for either owner or contactor-driven claims arguably
wouldn’t arise. If the baseline or “as-planned” schedule was both highly accurate in its
execution forecast and then precisely adhered to during execution, without interference
or change, then post-execution disputes would be moot.1

However, in reality, this is rarely the case. This paper introduces a technique that helps
with determining root cause of project delays resulting in claims.

Types of Claims
Claims typically arise from several project events including:
    • Delays
    • Disruption
    • Acceleration
    • Change in scope
    • Differing site conditions
    • Termination
While these types of project claims are well defined and documented, the means by
which the root cause of the effect of such claims is resolved is often source for much
dispute and interpretation. This paper focuses on how metric analysis can assist with
the first four types of claim (delays, disruption, acceleration and change in scope). The
modeling of all four of these is heavily dependent on CPM scheduling techniques.

“As-planned” and “As-built” Scenarios
Schedules can be generally classified as either “as-planned” or “as-built”.
The “as-planned” or baseline schedule needs to comply with contract requirements;
accurately represent the agreed upon scope of work depict the contractor’s plan and
represent a plan that is constructible with a reasonable critical path2.



1
  See “Improving Project Plans using a Schedule Maturity Framework” at
www.projectacumen.com/resources/whitepapers to learn more about how to build sound project schedules during the
planning phase of a project
2
  Construction Delays 2nd Edition, Theodore Trauner, ISBN 1856176770

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                               3
The “as-built” schedule needs to accurately reflect any changes and/or status updates
made as a result of execution of work. During a project lifecycle, there may be several
as-built or statused schedules reflective of multiple points in time.

The key to successful claims analysis and the accurate determination of cause is to
have a sound basis of schedule for both the “as-planned” as well as multiple “as-built”
scenarios depicting changes over time. With such a detailed history of how the
schedule evolves during the project comes the ability to essentially walk back through
time, and determine where, when and why deviation from the “as planned” scenario
occurred. Drivers of these changes can be determined using various techniques that
focus on variances between these scenarios.

Delay Analysis
Delay analysis can be categorized as follows:

Foresight Methods:
Focus on ‘as-planned scenarios’ and compare the ‘impacted as-planned’, which
includes only owner-caused delays, with the ‘adjusted as-planned’, which includes only
contractor caused delays. Foresight methods ignore as-built history and therefore has
little basis on as-built reality.

Hindsight Methods:
Focus on ‘as-built’ scenarios and compare the as-built delayed schedule to that of the
collapsed as-built (equivalent as-built schedule with delays removed). Hindsight
methods don’t account for variations from the original baseline plan.

Contemporaneous Methods:
Focus on updated and statused snapshots of the schedule. Typically this includes the
original as-planned schedule and then a succession of updated ‘as-builts’ over time.
The key to a contemporaneous schedule is that it reflects both scope changes
(reflected in changes to activities, durations, sequence of work etc.) as well as status
updates (reflection of contractor performance). By capturing both scope change and
performance, the relative impact of both can be ascertained. The Contemporaneous
method can be executed using what is known as a Time Impact Analysis (TIA) or a
Window Analysis.

Time Impact Analysis is based on a single snapshot of a statused or updated schedule.
By updating activities to reflect actual durations and/or adding activities to reflect delay
periods, the knock-on effect to the critical path and other downstream activities in the
schedule can be determined. Delays due to either scope change or under performance
are then determined by comparing back to the “as planned or baseline”.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       4
Window Analysis on the other hand, utilizes snapshots of a schedule captured
throughout the project lifecycle through to the point of the contentious delay. By
comparing the critical path between these snapshots, the point at which the path
changes can be determined.

Additional techniques including Half Step, Impacted as Planned and Collapsed As Built
all drive towards the same objective: to pinpoint where and when variances from an
agreed upon plan occur, and from this determine why these variances came about. In
short, the various modeling techniques, through additive or subtractive updates to a
given scenario, all provide a comparison against which the cause and ownership of
delay can be better understood.

Liability of Delay
Delays and resultant claims can be identified as either owned by the contractor or the
owner of the project. Figure 1 shows the different scenarios that lead to either scenario
for the contractor or owner.



                                                    Identified Delay




                                                                  Non-Excusable
                                                                 (within contractor
                                   Excusable (beyond             control e.g., poor
                                   contractor control)
                                                                     contractor
                                                                   performance)




                     Compensable (e.g.,           Non-Compensable
                     scope changes by               (e.g., adverse
                          owner) 
                     weather)



                                Figure 1 – Ownership of Delays
Once the driving delay activity(s) within a schedule are determined, causation analysis
can be conducted to determine who is responsible for the delay. Such causation
analysis typically relies heavily on researching of project documents, review of
communication threads, expert witness testimonials etc.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                         5
Why are Delay Claims so Complex?
Delay claims tend to be complex; however it is not necessarily because of actual
determination of cause (i.e., ownership). More often delay claim complexity is due to
the complex process of determining where and when (i.e., which activities) in the
project actually caused the delay. In other words, determining what starting activity in
the overall sequence of work actually caused a knock-on delay effect through the
schedule and therefore caused an overall project delay.

How Can Metric Analysis and Ribbon Visualization Help?
The previously described techniques all strive to pinpoint variances between scenarios
(e.g., as planned and as-built). A combination of metric analysis and a visualization
technique called Project Ribbons can provide a quick, easy and yet highly accurate and
insightful means of achieving this goal.

A white paper titled “Project Simplification Through Metric Analysis” published in 2009 3
introduced the concept of applying project metrics to ‘ribbons’ or groupings of project
data. In summary, ribbons are a means of rotating long, vertical, multi-page Gantt
charts into more horizontal groupings of activities (based on a given criteria) so as to
better visualize sequence of work throughout a project.




                   Figure 2 – Example of Schedule Quality Forensic Analysis4
Figure 2 shows an example of a schedule quality assessment conducted against a
single project. Slicing the project into phases allows for viewing the likes of total float by

3
  Project Simplification Though Metric Analysis” White Paper authored by Dr Dan Patterson, October 2009,
www.projectacumen.com/resources/whitepapers
4
  Screenshot of Acumen Fuse®, a metric analysis and visualization tool. www.projectacumen.com/fuse

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                 6
phase and pinpointing specific schedule shortcomings. An overall quality score can be
achieved through the use of a quality scorecard.

Taking this a step further, and ribbonizing by, for example, “critical” and “non-critical”
activities and subsequently applying performance-based metrics such as “delayed”,
“accelerated”, “on-time”, analysts have the ability to slice and dice projects and
pinpoint bottlenecks and starting points for delay. Further, by slicing ribbons by time
periods, additional pinpointing of issues with respect to time can also be achieved. So
not only can delay-associated characteristics be determined for groupings of activities
or scenario comparisons as a whole but now delays can also be pinpointed within a
specific time period or phase of a project.

Figure 3 shows a second example project ribbonized by critical and non-critical
activities with sample delay-based metrics applied (comparison between the “as-
planned”/baseline dates and the “as-built”/statused schedule). From the analysis, it can
be seen that only two activities were completed delayed (specifically in 2009) but more
importantly, those two activities (Feasibility Study and Peer Review) were both critical
and hence had an impact on the downstream activities in the schedule (hence
impacting the completion date).




       Activities
    ribbonized by                Delay analysis
         float                     metrics by
                                                           Delay analysis
                                  time-period
                                                            metrics by
                                                              ribbon




                             Figure 3 – Example Ribbon Analysis


Using Ribbon Metric Analysis to Compare Project Scenarios
The true value of ribbon metric analysis comes with the ability to compare multiple
instances, snapshots, or scenarios of a project such as comparing “As-planned” with
“Impacted As-planned”. Consider an example whereby a contractor and owner are in
dispute over a delayed and over-budget project. The contractor is claiming that the
delays were a result of scope changes made by the owner; the owner is claiming the
scope changes had no bearing on the delays and instead the delays were caused by
poor execution of critical path work.
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                             7
Firstly, consider the contractors claim of scope change: a comparison between the
contractually agreed upon “as planned” schedule was compared to a mutually agreed
“as planned update reflecting the scope changes”. Figures 4a, b and c show lists of the
changes made to the schedule including changed durations, an added activity
(“remedial”) and modified logic.




                                                                        Increases and
                                                                        decreases to
                                                                        specific activity
                                                                        durations


                                                                        Newly added
                                                                        activity



                                Figure 4a – Changed Durations




                                                                              Changes to logic


                                  Figure 4b – Modified Logic




                                                                                     Lags added
                                                                                     to links



                                   Figure 4c – Modified Lags
Figure 5 shows the impact of these scope changes to the planned schedule reflected
using ribbons and metrics including:
    • Increase to overall duration from 270 days to 302 days
    • Forecasted project completion slipped from 18 June 2008 to 17 July 2008
    • Number of critical activities – newly added “remedial” activity actually fell on the
        critical path
    • Forecasted cost increased from $460K to $497K

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8
•    Average float for the entire project decreased – an indication of a more
         compressed and aggressive schedule
    • Delayed activities – 9 activities experienced a delay relative to the original “as-
         planned”
Focusing on the delayed activities metric, the analysis revealed that a total of nine
activities experienced a delay as a result of the scope changes. Further drilling down
into the sequence of work showed that a newly introduced regulatory design review
period driving the need for a lag to be added to the link between “FEED” and “detailed
design” was the root cause of this knock-on effect for delay. Thus, even prior to the
start of execution, the “as planned” schedule was unrealistic because it didn’t reflect
the changes to scope added by the owner.




        Time-phased effect of                        Pinpointed delayed
         scope change with                            activities as result
        regards to time, cost,                        of scope change




         Figure 5 – Comparison between Original and Changed Scope Scenarios
Next consider the owners claim of poor performance: compare the “as-built” against
both the original “as-planned” as well as the “updated plan reflecting the scope
changes”.

As seen in Figure 6, comparison ribbon analysis showed the “As-Built” project
completed on 10 July 2008 compared to the “As Planned” completion date of 18 June
compared to the scope-adjusted “as planned” completion date of 17 July 2008.

Further analysis (figure 6) showed that while 4 activities experienced completion delays,
only 2 of these were caused by poor performance (“Structural” and “mechanical”). The
key to the analysis here was then to reveal that neither of these two under-performing
activities were actually on the critical path. The first critical delaying activity was
“Commissioning - Phase I” which was driven by the newly added “Remedial” activity
(as determined by the scope variance analysis).
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       9
From this analysis, it was clear that while the “As-built” project completion did indeed
come in later than the “As planned” forecast, the root cause of this was not the under-
performing structural or mechanical activities but instead due to the change in scope
with regards to the required remedial work. This insight resulted in the contractor not
being liable for damages to the owner and instead the contractor being able to claim
damages for the impact on their additional workload for the increase in scope.




                    Figure 6 – Ribbon Analysis Pinpointing Delay Drivers


Cause and Effect Metrics
One of the benefits of a ribbon-based analysis is that the analysis can incorporate an
unlimited number of variance and quality-based critiques. These critiques can then be
used for pinpointing cause of delay as well as rolled up through the use of scorecards
to give an overall big-picture into the effect/impact of the delay. Being able to hone in
on specific individual metrics to determine root cause of variance as well as rolling up
the combined effect of multiple delays into total scores for scenarios or even specific
network paths within a project is hugely valuable.

While too numerous to list individually in this paper, metrics that help determine cause
of delay for a ribbon analysis include:
    • Quality of schedule: appropriate use of logic types, constraints and appropriate
       estimates.
    • Changes to scope: determination of additions, deletions, or changes to
       activities, resource assignments, calendars etc. Compare these changes to
       variance in forecasted performance to determine impact of the scope changes.


+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       10
•   Changes to sequence of work: through path analysis determine which paths
        within a schedule changed and, more importantly, determine the impact of these
        changes with regards to available float. This provides a means of determining
        whether a changed sequence of work was truly a driver of the delay in question.
    •   Continuous Path Durations: determination of changes to the actual length of
        work or duration within given paths (e.g. the critical path may not change in
        scope or direction but the length of the continuation of work may have
        increased as a result of a change to scope).
    •   Variance of Near-critical Paths: While the critical path is the focus in a CPM
        schedule, insight into how many other near-critical paths and how these change
        as a results of delays help correlate cause and effect as a result of a delay.
    •   Questionable Logic: in addition to suffering from insufficient logic (in the form of
        missing logic), schedules can also fall foul of having overly complex and
        redundant logic. Identifying such redundant logic helps determine, for example,
        whether an “as planned” schedule has been artificially constructed thus not truly
        representing the sequence of work to be executed.
    •   Execution Performance: Being able to pinpoint trending and patterns of poor
        performance, for example, by a specific sub-contractor, is a powerful means of
        assigning cause across multiple delaying activities across multiple critical/non
        critical paths.


Conclusions
The science behind effective schedule delay analysis is heavily based upon CPM
scheduling techniques resulting in comparisons and variances between multiple
interpretations of planned and executed schedules.

Comparing such scenarios through the use of project ribbons and subsequently
applying schedule quality, performance and delay-related metrics to these ribbons
provides a unique means of truly understanding not only the effect of delay but more
importantly, accurately pinpointing the root cause of such.




Acumen Fuse® is a metric analysis and visualization tool which assesses schedule quality, cost
forecast accuracy, risk model realism, analyzes earned value and project performance as well as
assists in the Forensic analysis process. To download a free trial of the latest version of this
revolutionary tool visit www.projectacumen.com/fuse.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       11

Weitere ähnliche Inhalte

Was ist angesagt?

How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)Amr Morsy
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)PMA Consultants
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityPMA Consultants
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk managementGlen Alleman
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1Chris Carson
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Acumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMRGlen Alleman
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
K.chaitanya pm
K.chaitanya pmK.chaitanya pm
K.chaitanya pmkongara
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_clsDennis Doherty
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Glen Alleman
 

Was ist angesagt? (20)

SanDiegoPresentation
SanDiegoPresentationSanDiegoPresentation
SanDiegoPresentation
 
Modular constructionconference feb2012_a_popescu
Modular constructionconference  feb2012_a_popescuModular constructionconference  feb2012_a_popescu
Modular constructionconference feb2012_a_popescu
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014
 
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)Risk Modeling and Analysis (Mitigating the Planning Fallacy)
Risk Modeling and Analysis (Mitigating the Planning Fallacy)
 
Top Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule ReliabilityTop Five Metrics for Measuring Schedule Reliability
Top Five Metrics for Measuring Schedule Reliability
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Modular Construction Conference 2012
Modular Construction Conference 2012Modular Construction Conference 2012
Modular Construction Conference 2012
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk management
 
Baseline Schedules 1
Baseline Schedules 1Baseline Schedules 1
Baseline Schedules 1
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
Acumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions GuideAcumen Fuse Metrics & Descriptions Guide
Acumen Fuse Metrics & Descriptions Guide
 
Essential views of the IPMR
Essential views of the IPMREssential views of the IPMR
Essential views of the IPMR
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
K.chaitanya pm
K.chaitanya pmK.chaitanya pm
K.chaitanya pm
 
targeting process part 1
targeting process part 1targeting process part 1
targeting process part 1
 
2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls2015_0220_HAI_TM1-T6-05_F_cls
2015_0220_HAI_TM1-T6-05_F_cls
 
Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
 
Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)Programmatic risk management workshop (handbook)
Programmatic risk management workshop (handbook)
 

Ähnlich wie A Fresh Take on Project Forensics

Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Robert Byrd
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guidelineZuzi Evangelista
 
AACE Recommended Practice Time Impact Analysis 52R.pdf
AACE Recommended Practice Time Impact Analysis 52R.pdfAACE Recommended Practice Time Impact Analysis 52R.pdf
AACE Recommended Practice Time Impact Analysis 52R.pdfValerie Felton
 
Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule AccelerationFaster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule AccelerationAcumen
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1reddvise
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2David Greig
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project SchedulesAcumen
 
Small projectlifecycleplantemplatev
Small projectlifecycleplantemplatevSmall projectlifecycleplantemplatev
Small projectlifecycleplantemplatevaftabsaeedi
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementChris Hattingh
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9VancityInstitute
 
Const. Productivity Management
Const. Productivity ManagementConst. Productivity Management
Const. Productivity Managementsmall_nomi
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 

Ähnlich wie A Fresh Take on Project Forensics (20)

Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
Deepwater Decommissioning Cost Estimation Whitepaper (2016-01)
 
Building a comissioning guideline
Building a comissioning guidelineBuilding a comissioning guideline
Building a comissioning guideline
 
CSC-1986.original
CSC-1986.originalCSC-1986.original
CSC-1986.original
 
AACE Recommended Practice Time Impact Analysis 52R.pdf
AACE Recommended Practice Time Impact Analysis 52R.pdfAACE Recommended Practice Time Impact Analysis 52R.pdf
AACE Recommended Practice Time Impact Analysis 52R.pdf
 
Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule AccelerationFaster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
Faster, Yet Less Risky Projects through Goal-Based Schedule Acceleration
 
2.06 time management 1
2.06 time management 12.06 time management 1
2.06 time management 1
 
As-built Programmes - Part 2
As-built Programmes - Part 2As-built Programmes - Part 2
As-built Programmes - Part 2
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
Benchmarking Project Schedules
Benchmarking Project SchedulesBenchmarking Project Schedules
Benchmarking Project Schedules
 
Small projectlifecycleplantemplatev
Small projectlifecycleplantemplatevSmall projectlifecycleplantemplatev
Small projectlifecycleplantemplatev
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Project management chapter 9
Project management chapter 9Project management chapter 9
Project management chapter 9
 
Rachhu
RachhuRachhu
Rachhu
 
Rachhu
RachhuRachhu
Rachhu
 
Const. Productivity Management
Const. Productivity ManagementConst. Productivity Management
Const. Productivity Management
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Communication 1
Communication 1Communication 1
Communication 1
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 

Mehr von Acumen

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
 

Mehr von Acumen (20)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 

Kürzlich hochgeladen

Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration TrainingCalvinarnold843
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...PRnews2
 
Simplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansSimplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansNugget Global
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfASGITConsulting
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAScathy664059
 
Implementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxImplementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxRich Reba
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHelp Desk Migration
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 

Kürzlich hochgeladen (20)

Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Customizable Contents Restoration Training
Customizable Contents Restoration TrainingCustomizable Contents Restoration Training
Customizable Contents Restoration Training
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
Introducing the AI ShillText Generator A New Era for Cryptocurrency Marketing...
 
Simplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business LoansSimplify Your Funding: Quick and Easy Business Loans
Simplify Your Funding: Quick and Easy Business Loans
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Types of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdfTypes of Cyberattacks - ASG I.T. Consulting.pdf
Types of Cyberattacks - ASG I.T. Consulting.pdf
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAS
 
Implementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptxImplementing Exponential Accelerators.pptx
Implementing Exponential Accelerators.pptx
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
How to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your BusinessHow to Conduct a Service Gap Analysis for Your Business
How to Conduct a Service Gap Analysis for Your Business
 
Authentically Social - presented by Corey Perlman
Authentically Social - presented by Corey PerlmanAuthentically Social - presented by Corey Perlman
Authentically Social - presented by Corey Perlman
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 

A Fresh Take on Project Forensics

  • 1. // A Fresh Take on Project Forensics Enhanced Schedule Delay Forensics through Project Metrics and Ribbon Analysis Dr. Dan Patterson, PMP CEO & President, Acumen October 2010 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Introduction ................................................................................................................. 3 Types of Claims ........................................................................................................... 3 “As-planned” and “As-built” Scenarios ...................................................................... 3 Delay Analysis .............................................................................................................. 4 Foresight Methods:................................................................................................... 4 Liability of Delay .......................................................................................................... 5 Figure 1 – Ownership of Delays ............................................................................ 5 Why are Delay Claims so Complex? .............................................................................. 6 How Can Metric Analysis and Ribbon Visualization Help? ............................................ 6 Figure 2 – Example of Schedule Quality Forensic Analysis ................................... 6 Figure 3 – Example Ribbon Analysis .................................................................... 7 Using Ribbon Metric Analysis to Compare Project Scenarios ........................................... 7 Figure 4a – Changed Durations ........................................................................... 8 Figure 4b – Modified Logic ................................................................................... 8 Figure 4c – Modified Lags .................................................................................... 8 Figure 5 – Comparison between Original and Changed Scope Scenarios............. 9 Figure 6 – Ribbon Analysis Pinpointing Delay Drivers ........................................ 10 Cause and Effect Metrics .............................................................................................. 10 Conclusions ................................................................................................................... 11 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Introduction The business of schedule claims is both an art and a science. This paper discusses how an analytical approach to schedule forensics using metric analysis results in a highly effective means of determining the root cause and resultant damaging impact as part of the project claims process. The technique can be used by owners or contractors alike during arbitration and litigation cases. In a perfect scenario, the need for either owner or contactor-driven claims arguably wouldn’t arise. If the baseline or “as-planned” schedule was both highly accurate in its execution forecast and then precisely adhered to during execution, without interference or change, then post-execution disputes would be moot.1 However, in reality, this is rarely the case. This paper introduces a technique that helps with determining root cause of project delays resulting in claims. Types of Claims Claims typically arise from several project events including: • Delays • Disruption • Acceleration • Change in scope • Differing site conditions • Termination While these types of project claims are well defined and documented, the means by which the root cause of the effect of such claims is resolved is often source for much dispute and interpretation. This paper focuses on how metric analysis can assist with the first four types of claim (delays, disruption, acceleration and change in scope). The modeling of all four of these is heavily dependent on CPM scheduling techniques. “As-planned” and “As-built” Scenarios Schedules can be generally classified as either “as-planned” or “as-built”. The “as-planned” or baseline schedule needs to comply with contract requirements; accurately represent the agreed upon scope of work depict the contractor’s plan and represent a plan that is constructible with a reasonable critical path2. 1 See “Improving Project Plans using a Schedule Maturity Framework” at www.projectacumen.com/resources/whitepapers to learn more about how to build sound project schedules during the planning phase of a project 2 Construction Delays 2nd Edition, Theodore Trauner, ISBN 1856176770 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. The “as-built” schedule needs to accurately reflect any changes and/or status updates made as a result of execution of work. During a project lifecycle, there may be several as-built or statused schedules reflective of multiple points in time. The key to successful claims analysis and the accurate determination of cause is to have a sound basis of schedule for both the “as-planned” as well as multiple “as-built” scenarios depicting changes over time. With such a detailed history of how the schedule evolves during the project comes the ability to essentially walk back through time, and determine where, when and why deviation from the “as planned” scenario occurred. Drivers of these changes can be determined using various techniques that focus on variances between these scenarios. Delay Analysis Delay analysis can be categorized as follows: Foresight Methods: Focus on ‘as-planned scenarios’ and compare the ‘impacted as-planned’, which includes only owner-caused delays, with the ‘adjusted as-planned’, which includes only contractor caused delays. Foresight methods ignore as-built history and therefore has little basis on as-built reality. Hindsight Methods: Focus on ‘as-built’ scenarios and compare the as-built delayed schedule to that of the collapsed as-built (equivalent as-built schedule with delays removed). Hindsight methods don’t account for variations from the original baseline plan. Contemporaneous Methods: Focus on updated and statused snapshots of the schedule. Typically this includes the original as-planned schedule and then a succession of updated ‘as-builts’ over time. The key to a contemporaneous schedule is that it reflects both scope changes (reflected in changes to activities, durations, sequence of work etc.) as well as status updates (reflection of contractor performance). By capturing both scope change and performance, the relative impact of both can be ascertained. The Contemporaneous method can be executed using what is known as a Time Impact Analysis (TIA) or a Window Analysis. Time Impact Analysis is based on a single snapshot of a statused or updated schedule. By updating activities to reflect actual durations and/or adding activities to reflect delay periods, the knock-on effect to the critical path and other downstream activities in the schedule can be determined. Delays due to either scope change or under performance are then determined by comparing back to the “as planned or baseline”. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. Window Analysis on the other hand, utilizes snapshots of a schedule captured throughout the project lifecycle through to the point of the contentious delay. By comparing the critical path between these snapshots, the point at which the path changes can be determined. Additional techniques including Half Step, Impacted as Planned and Collapsed As Built all drive towards the same objective: to pinpoint where and when variances from an agreed upon plan occur, and from this determine why these variances came about. In short, the various modeling techniques, through additive or subtractive updates to a given scenario, all provide a comparison against which the cause and ownership of delay can be better understood. Liability of Delay Delays and resultant claims can be identified as either owned by the contractor or the owner of the project. Figure 1 shows the different scenarios that lead to either scenario for the contractor or owner. Identified Delay Non-Excusable (within contractor Excusable (beyond control e.g., poor contractor control) contractor performance) Compensable (e.g., Non-Compensable scope changes by (e.g., adverse owner) weather) Figure 1 – Ownership of Delays Once the driving delay activity(s) within a schedule are determined, causation analysis can be conducted to determine who is responsible for the delay. Such causation analysis typically relies heavily on researching of project documents, review of communication threads, expert witness testimonials etc. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. Why are Delay Claims so Complex? Delay claims tend to be complex; however it is not necessarily because of actual determination of cause (i.e., ownership). More often delay claim complexity is due to the complex process of determining where and when (i.e., which activities) in the project actually caused the delay. In other words, determining what starting activity in the overall sequence of work actually caused a knock-on delay effect through the schedule and therefore caused an overall project delay. How Can Metric Analysis and Ribbon Visualization Help? The previously described techniques all strive to pinpoint variances between scenarios (e.g., as planned and as-built). A combination of metric analysis and a visualization technique called Project Ribbons can provide a quick, easy and yet highly accurate and insightful means of achieving this goal. A white paper titled “Project Simplification Through Metric Analysis” published in 2009 3 introduced the concept of applying project metrics to ‘ribbons’ or groupings of project data. In summary, ribbons are a means of rotating long, vertical, multi-page Gantt charts into more horizontal groupings of activities (based on a given criteria) so as to better visualize sequence of work throughout a project. Figure 2 – Example of Schedule Quality Forensic Analysis4 Figure 2 shows an example of a schedule quality assessment conducted against a single project. Slicing the project into phases allows for viewing the likes of total float by 3 Project Simplification Though Metric Analysis” White Paper authored by Dr Dan Patterson, October 2009, www.projectacumen.com/resources/whitepapers 4 Screenshot of Acumen Fuse®, a metric analysis and visualization tool. www.projectacumen.com/fuse +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. phase and pinpointing specific schedule shortcomings. An overall quality score can be achieved through the use of a quality scorecard. Taking this a step further, and ribbonizing by, for example, “critical” and “non-critical” activities and subsequently applying performance-based metrics such as “delayed”, “accelerated”, “on-time”, analysts have the ability to slice and dice projects and pinpoint bottlenecks and starting points for delay. Further, by slicing ribbons by time periods, additional pinpointing of issues with respect to time can also be achieved. So not only can delay-associated characteristics be determined for groupings of activities or scenario comparisons as a whole but now delays can also be pinpointed within a specific time period or phase of a project. Figure 3 shows a second example project ribbonized by critical and non-critical activities with sample delay-based metrics applied (comparison between the “as- planned”/baseline dates and the “as-built”/statused schedule). From the analysis, it can be seen that only two activities were completed delayed (specifically in 2009) but more importantly, those two activities (Feasibility Study and Peer Review) were both critical and hence had an impact on the downstream activities in the schedule (hence impacting the completion date). Activities ribbonized by Delay analysis float metrics by Delay analysis time-period metrics by ribbon Figure 3 – Example Ribbon Analysis Using Ribbon Metric Analysis to Compare Project Scenarios The true value of ribbon metric analysis comes with the ability to compare multiple instances, snapshots, or scenarios of a project such as comparing “As-planned” with “Impacted As-planned”. Consider an example whereby a contractor and owner are in dispute over a delayed and over-budget project. The contractor is claiming that the delays were a result of scope changes made by the owner; the owner is claiming the scope changes had no bearing on the delays and instead the delays were caused by poor execution of critical path work. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. Firstly, consider the contractors claim of scope change: a comparison between the contractually agreed upon “as planned” schedule was compared to a mutually agreed “as planned update reflecting the scope changes”. Figures 4a, b and c show lists of the changes made to the schedule including changed durations, an added activity (“remedial”) and modified logic. Increases and decreases to specific activity durations Newly added activity Figure 4a – Changed Durations Changes to logic Figure 4b – Modified Logic Lags added to links Figure 4c – Modified Lags Figure 5 shows the impact of these scope changes to the planned schedule reflected using ribbons and metrics including: • Increase to overall duration from 270 days to 302 days • Forecasted project completion slipped from 18 June 2008 to 17 July 2008 • Number of critical activities – newly added “remedial” activity actually fell on the critical path • Forecasted cost increased from $460K to $497K +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8
  • 9. Average float for the entire project decreased – an indication of a more compressed and aggressive schedule • Delayed activities – 9 activities experienced a delay relative to the original “as- planned” Focusing on the delayed activities metric, the analysis revealed that a total of nine activities experienced a delay as a result of the scope changes. Further drilling down into the sequence of work showed that a newly introduced regulatory design review period driving the need for a lag to be added to the link between “FEED” and “detailed design” was the root cause of this knock-on effect for delay. Thus, even prior to the start of execution, the “as planned” schedule was unrealistic because it didn’t reflect the changes to scope added by the owner. Time-phased effect of Pinpointed delayed scope change with activities as result regards to time, cost, of scope change Figure 5 – Comparison between Original and Changed Scope Scenarios Next consider the owners claim of poor performance: compare the “as-built” against both the original “as-planned” as well as the “updated plan reflecting the scope changes”. As seen in Figure 6, comparison ribbon analysis showed the “As-Built” project completed on 10 July 2008 compared to the “As Planned” completion date of 18 June compared to the scope-adjusted “as planned” completion date of 17 July 2008. Further analysis (figure 6) showed that while 4 activities experienced completion delays, only 2 of these were caused by poor performance (“Structural” and “mechanical”). The key to the analysis here was then to reveal that neither of these two under-performing activities were actually on the critical path. The first critical delaying activity was “Commissioning - Phase I” which was driven by the newly added “Remedial” activity (as determined by the scope variance analysis). +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 9
  • 10. From this analysis, it was clear that while the “As-built” project completion did indeed come in later than the “As planned” forecast, the root cause of this was not the under- performing structural or mechanical activities but instead due to the change in scope with regards to the required remedial work. This insight resulted in the contractor not being liable for damages to the owner and instead the contractor being able to claim damages for the impact on their additional workload for the increase in scope. Figure 6 – Ribbon Analysis Pinpointing Delay Drivers Cause and Effect Metrics One of the benefits of a ribbon-based analysis is that the analysis can incorporate an unlimited number of variance and quality-based critiques. These critiques can then be used for pinpointing cause of delay as well as rolled up through the use of scorecards to give an overall big-picture into the effect/impact of the delay. Being able to hone in on specific individual metrics to determine root cause of variance as well as rolling up the combined effect of multiple delays into total scores for scenarios or even specific network paths within a project is hugely valuable. While too numerous to list individually in this paper, metrics that help determine cause of delay for a ribbon analysis include: • Quality of schedule: appropriate use of logic types, constraints and appropriate estimates. • Changes to scope: determination of additions, deletions, or changes to activities, resource assignments, calendars etc. Compare these changes to variance in forecasted performance to determine impact of the scope changes. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 10
  • 11. Changes to sequence of work: through path analysis determine which paths within a schedule changed and, more importantly, determine the impact of these changes with regards to available float. This provides a means of determining whether a changed sequence of work was truly a driver of the delay in question. • Continuous Path Durations: determination of changes to the actual length of work or duration within given paths (e.g. the critical path may not change in scope or direction but the length of the continuation of work may have increased as a result of a change to scope). • Variance of Near-critical Paths: While the critical path is the focus in a CPM schedule, insight into how many other near-critical paths and how these change as a results of delays help correlate cause and effect as a result of a delay. • Questionable Logic: in addition to suffering from insufficient logic (in the form of missing logic), schedules can also fall foul of having overly complex and redundant logic. Identifying such redundant logic helps determine, for example, whether an “as planned” schedule has been artificially constructed thus not truly representing the sequence of work to be executed. • Execution Performance: Being able to pinpoint trending and patterns of poor performance, for example, by a specific sub-contractor, is a powerful means of assigning cause across multiple delaying activities across multiple critical/non critical paths. Conclusions The science behind effective schedule delay analysis is heavily based upon CPM scheduling techniques resulting in comparisons and variances between multiple interpretations of planned and executed schedules. Comparing such scenarios through the use of project ribbons and subsequently applying schedule quality, performance and delay-related metrics to these ribbons provides a unique means of truly understanding not only the effect of delay but more importantly, accurately pinpointing the root cause of such. Acumen Fuse® is a metric analysis and visualization tool which assesses schedule quality, cost forecast accuracy, risk model realism, analyzes earned value and project performance as well as assists in the Forensic analysis process. To download a free trial of the latest version of this revolutionary tool visit www.projectacumen.com/fuse. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 11