NEEDS TO KNOW ON
PUBLIC PROCUREMENT
Priyantha weerasooriya.
SSP/Director-Supplies.
PHQ
Congratulations on
Your success
Meaning of procurement
Oxford Dic; The process of obtaining
supplies, especially for Government or
an organization
Previous Tender Guidelines
in Sri Lanka
 Guidelines on Government Tender Procedure
 Separate Chapter for Foreign Funded Projects (2000)
 Guidelines on Government Tender Procedures (Revised in 1997)
 Issued a Separate book, with 60 Circulars to the tender procedure 1997 (2004)
2006 -Pro Guideline and Manuals
in Operation as at Today
 Procurement Guideline and Manual Works
and Goods 2006.
 Selection and Employment of Consultants
2007
 Procurement of Pharmaceuticals &
Medicals & Medical Devices 2006
1.4 ETHICS IN PROCUREMENT
1.4.1.Confidentiality
1.4.2.Corruption
1.4.3.Conflict of Interest
1.4.4.No gifts or inducement to be accepted
Objectives of Procurement
 Value for Money
Elements of VFM
* Economy – Minimizing Cost of Resources
* Efficiency - Maximum output against minimum input
* Effectiveness - Relationship between intended results and actual results
Public Procurement Involves
* SUPPLIES
* CONSTRUCTIONS
* SERVICES
(Over 80% Public Expenditure Goes Through Public Procurement)
Procurement in Supplies should ensure
* RIGHT QUALITY
* RIGHT QUANTITY
* RIIGHT TIME
* RIGHT PRICE
* RIGHT PLACE
 Transparency Accountability
 Fairness
 Efficiency
 Equal Opportunity
 Development of Local Business
 Achievement of National Development
Objectives
Important elements of the
Procurement Process
 Procurement Planning
 Preparation of Bidding Document
 Invitation to bid Closing
 Bid Opening
 Bid Evaluation
 Award of Contract
LAWS APPLICABLE TO PROCUREMENT
ACTIONS
1) Laws of Arbitration Act No. 11 of 1995
2) Laws of Contract
3)Bribery Act – Section 70. Any public servant who, with intent, to cause wrongful or
unlawful loss to the
Government, or to confer a wrongful or unlawful benefit, favour or advantage on
himself or any person, or with knowledge, that any wrongful or unlawful loss will be
caused to any person or to the Government, or that any wrongful or unlawful benefit,
hall upon summary trial and
conviction by a Magistrate be liable to imprisonment for a term not exceeding ten
years or to a fine not exceeding one hundred thousand rupees or to both such
imprisonment and fine.
PROCUREMENT METHOD
3.1 International Competitive Bidding (ICB)
3.2 National Competitive Bidding (NCB) - Over 2M
* Publish in a News Papers – 21 days
* Bid Security required - for 119 days
* Bid validity - for 91 days
3.3 Limited / Restricted International Competitive Bidding
(LIB) and Limited / Restricted National Competitive
Bidding (LNB)
3.4 Shopping - Below 2M
• Five (5) quotations
• Thru Registered Suppliers
• Yellow Pages and Rainbow Pages
3.5 Direct Contracting
a) Direct contracting is a means of Procurement of Goods or Services or Works from
a single supplier source.
b) It entails no competition and shall be used only under exceptional circumstances
c) This method is appropriate under the following circumstances
i) When the prices or rates are fixed pursuant to legislation by regulatory bodies
ii) Standardization of equipment, for compatibility with existing equipment, may
justify additional purchases of the same type of Goods
d) When direct contracting is used under any of the reasons above, the value of the
Procurement shall be subjected to the upper limits given under Guideline 2.14. No
government agency will qualify for automatic direct contract award unless the above
requirements are satisfied
3.6 Repeat Orders
3.7 Force Account
3.8 Emergency Account
PROCUREMENT PLANNING
“Good Start is half done:
WHAT IS STRATEGIC PROCUREMENT PLANNING?
4.1. Advance Procurement Action
4.2. Master Procurement Plan (MPP)
4.3. Total Cost Estimate
* Preparation of procurement plan 1st stage of
the procurement process
* Define what actions to be taken to focus
* List out various procurement under works,
goods, services and consultancy
* Identify by which each one of these works
goods and services are required to use
* Decide contents of individual procurement packages
* Identify the relationship between each such items
* Determine the method of procurement
* Determine the procurement lead-time for each
package and schedule, target date for each event
* Prepare a bar chart and / or table or list identifying
the above dates for each bid package to assist in
procurement monitoring
PREPARATION OF BIDDING
DOCUMENTS
STANDARD BIDDING DOCUMENT FOR
PROCUREMENT OF GOODS
FORMAT
* Invitation for Bids (IFB)
* Instructions to Bidders (ITB)
* Bid Data Sheet
* Evaluation and Qualification Criteria
* Bidding Forms
* Schedule of Requirements (SOR)
* General Condition of Contract (GCC)
* Special Conditions of Contract (SCC)
* Contract Forms
* Specifications
* Price Schedule
INSTRUCTIONS TO BIDDERS
 General - Scope of Bid
- Source of Funds
- Ethic, Fraud and Corruption
- Eligible Bidders
- Eligible Goods & related services
 Contents of Bidding Documents
- Sections of Bidding Documents
- Clarification of Bidding Documents
- Amendment of Bidding Documents
 Preparation of Bids
- Cost of Bidding
- Language of Bidding Document
- Comprising the Bid
- Bid Submission Forms and Price Schedule
- Alternative Bids
- Bid Prices and Discounts
- Currencies of Bids
- Documents Establishing the Eligibility of the bidder
- Documents Establishing the conformity of the goods
and related services
- Documents Establishing the qualifications of the
Bidder
- Period of Validity of Bids
- Bid Security
- Format and Signing of Bids
 Submission & Opening of Bids
- Submission, Sealing and Marking of Bids
- Deadline for submission of Bids
- Late Bids
- Withdrawals and modification of Bids
- Bid Opening
 Evaluation and Comparison of Bids
- Examination of Terms & conditions: Technical
Evaluation
- Conversion to Single Currency
- Domestic Preference
- Evaluation of Bids
- Comparison of Bids
- Post Qualification of the Bidder
- Purchaser’s Right Accept any Bid, and to reject any
or all Bids
 Award of Contract
- Award Criteria
- Purchaser's right to vary Quantities at time of award
- Notification of Award
- Signing of Contract
- Performance Security
ROLE IN BIDDING DOCUMENTS
 Lay down rules of the Competition
* How to price
* How to prepare and submit bids
* What will be the selection criteria
* What will be the qualification criteria
 Scope of the obligation
* Technical Specifications
* Bill of Quantities
* Delivery / Completion Time
* Warranty / Service obligations
 Conditions of Contract
* Payment Terms
* Price Adjustments
* Liability
* Insurance
* Dispute Resolution
BIDDING DATA SHEET
 General
 Contents of Bidding Documents
 Preparation of Bids
 Submission and Opening of Bids
 Evaluation and Comparison of Bids
EVALUATION AND QUALIFICATION CRITERIA
 Evaluation Criteria
 Evaluation Criteria (Methodology)
 Multiple Contracts
 Domestic Preference
 Post Qualification Requirement
BIDDING FORMS
 Bid Submission Form
 Price Schedule
 Price and completion Schedule – Related
Services
 Bid Security (Guarantee)
 Bid – Security Declaration
 Manufacturer’s Authorization
SCHEDULE OF REQUIREMENTS
 List of Goods and Delivery Schedule
 List of Related Services and completion
Schedule
 Technical Specification
 Drawings
 Inspection and Tests
GENERAL CONDITIONS OF CONTRACT
* Definitions
* Contract Documents
* Fraud and Corruption
* Interpretation
* Language
* Joint Venture, Consortium or Association
* Eligibility
* Notices
* Governing Law
* Settlement of Disputes
* Scope of Supply
* Delivery and Documents
* Supplier’s Responsibilities
* Contract Price
* Terms of Payments
* Taxes and Duties
* Performance Security
* Copyright
* Confidential Information
* Subcontracting
* Specification and Standards
* Packing and Documents
* Insurance
* Transportation
* Inspection and Tests
* Liquidated Damages
* Warranty
* Patent Indemnity
* Limitation of Liability
* Changes in Laws and Regulations
* Force Majeure
* Change Orders and Contract Amendments
* Extensions of Time
* Termination
* Assignment
CONTRACT DATA
Contract Data shall supplement and /
or amend the condition of contract
(CC). Whenever there is a conflict, the
provisions contract data shall prevail
over those in the contract condition
CONTRACT FORMS
* Contract Agreement
* Performance Security
* Bank Guarantee for
Advance Payment
NPA APPROVED STANDARD BIDDING DOCUMENTS
PUBLICATION NUMBER TITLE
ICTAD /SBD/01 Shopping Procedure
ICTAD/SBD/02 NCB
ICTAD/SBD/03 MINER CONTRACTS
ICTAD/SBD/04 DESIGN AND BUILD
Questions?
Enjoy your Tea
ISSUANCE OF BIDDING
DOCUMENTS
* Should be made available during office hours
* At least up to one day prier to deadline of submission
of bids
* Availability for inspection, free of charge
* Cost of BDs should be reasonable
* Maintain good record keeping system
* BDs shall be issued as specified in the IFB
SUBMISSION OF BIDS
* Bids shall be received only at one
location
* Bids must be submitted only under
sealed cover.
* Clearly marked as “Original” or “Copy”
putting together in one envelop
* Late bids shall not be accepted
* Bids shall be received as specified in
the IFB
BID OPENING
* BOC shall comprise of minimum two members
* Open soon after the closing of bids
* Bids shall not be rejected at the bid opening
* Only “Original” shall be opened
* Late bids shall not be opened
* Withdrawals shall not opened (if not any doubt) –
withdrawal letter open first
* Modification should with original bid
* Attendance for bidders or his representatives
* Record Keeping is very important
* Original bids and records to be handed over to the
Chairperson of TEC
* Bids shall be opened as specified in the SBDs
NECESSITY
* IG Circular No. 2409/2012
Finance Circular No. 05/2012, dated
04.08.2011
* Delegation of financial Authorization
under FR 135
* For Goods, Works & Services
AUTHORITY FOR AWARD – SHOPPING
Authority GOSL Foreign Funded
MPC – Works inviting not less than 5 sealed quotation
form ICTAD registered contractors
Less than
Rs. 5m
Less than
Rs. 5m
MPC – Goods & Services inviting not less than 5 sealed
quotations from registered suppliers
Less than
Rs. 5m
Less than
Rs. 3m
PPC – Works inviting not less than 5 sealed quotation
from ICTACD registered contractors
Less than
Rs. 5m
Less than
Rs. 5m
PPC – Goods & Services inviting not less than 5 sealed
quotations from suppliers
Less than
Rs. 5m
Less than
Rs. 3m
MPC, DPC, PPC, - Goods & Services inviting not less than
3 quotations from registered suppliers
Less than
Rs. 5m
Less than
Rs. 1m
RPC – Works inviting not less than 5 sealed quotations
from ICTAD registered suppliers
Less than
Rs. 5m
Less than
Rs. 1m
RPC – Goods & Services inviting not less than 5 sealed
quotations from ICTAD registered suppliers
Less than
Rs. 5m
Less than
Rs. 500,000.00
CAO/HD/PD Works inviting not less than 3 sealed
quotations
Less than Rs. 500,000.00
CAO/HD/PD goods & Services inviting not less than 3
sealed quotations
Less than Rs. 250,000.00
Purpose of Bid evaluation
To determine the lowest evaluated
substantially responsive bid out of the
bid received.
Composition of TEC
1. No member should serve in both the PC & TEC.
2. Subject specialists
3. At least knowledgeable member on Procurement
procedure
4. In case of specific subject matters ,can oblation
expert advice from external members or
institutions
5. Can oblation assistance and expert advice from
consultants
Responsibilities of TEC
1. TEC members are jointly and severally responsible.
2. Within the minimum time period as agreed with PC
according to the PTS.
3. Evaluation should be made according to the approved
specifications and criteria
4. In case of CAPC & MPC, if any objection from any
bidder regarding the 10days prier to closing of bids ,
PE shall convey its decision to all the other bidders.
5. Revive and approve pre qualifications documents /
SBDs prepared by the PE.
Responsibilities of TEC Con…
6. To direct the PE to obtain clarifications from bidders in
writing if necessary.
7. T approve and issue addenda to the bidding
documents where necessary.
8. To agree upon the bid opening procedure.
9. To participate in negotiation , if directed by the PE.
10.The TEC may get assistance from external assistance .
11.Chairperson of the TEC or his nominee selected form
the TEC shall participate at the pre – bid conference.
BID EVALUATION
EVALUATION CRITERIA
• Shall be stated in Bid Documents
• All factors quantified in Monitory terms
44
Stages of bid Evaluation
Bid Examination
Detailed Bid Evaluation
Post Qualification
EVALUATION PROCESS
Preliminary Examination
• Whether the required securities are furnished.
• Whether the bid documents are properly signed.
• Whether the power of attorney for the authorized
person is submitted
• Whether joint venture agreements are submitted ( If
necessary)
• Eligibility of bidders
• Whether the bid form was purchased from the
concerned office
• Whether the person or firm submitting the bid
purchased bid form
• Whether the bid is sealed
• Whether the local agent is declared (If necessary)
46
47
Preliminary Examination
48
Substantial Responsiveness
• Failure to sign the bid form
• Eligibility requirements
• Bid security as specified
• Inability to meet the critical delivery schedule
• Conditional bids
• Unavailability of major supporting documents
• Failure to bid for the required scope of work
• Failure to quote for a major items in the package
• Failure to meet major technical requirements –
E.g. required material , plant capacity.
49
Detailed bid evaluation
Step – by – step procedure to be followed:
1. Correction of arithmetical errors
2. Un balance Bids
3. Discounts if Any;
4. Evaluation of acceptable omissions
5. Conversion to common currency
6. Completion times
7. Adjustments for various minor deviations
8. Domestic preference
9. Substantially non-responsive bids
10.Performance or service factors will be taken in to account as a
adjustment.
CORRECTION OF ARITHMETICAL ERRORS
1. Where there is discrepancy between the amount in
figures and in word , the amount in words will govern
2. Unit rate and line items
3. Average unit cost for missing items
4. Estimated unit cost for underestimated items
Exclude VAT ,Contingencies &
Provisional sum
Unbalanced Bids
Examine whether the bid is substantially
balanced
Verify that prices are not so low
Higher unit price for earlier works
Higher unit rates for underestimated work
Items
>50% the average cost and where the total
amount involved >5% of the total bid
52
Unbalanced Bids
Large contracts – say exceeding 500Mn
Discount the Loaded Item
Discount the engineer estimated value
Add the deference between two NPVs to the
bidder value for the purpose of compression
53
Unbalanced Bids
Other contract – Say not exceeding 500Mn
Ask to provide rate analysis
If the bidder fail to justify ask additional bid
security to mitigate the risk
If the bidder refuse to provide such security bid
shall be rejected.
Add the deference between two NPVs to the
bidder value for the purpose of compression
54
Alternative bids
 If the bidders are permitted to submit alternative bids , it should
be mentioned in the bidding documents
 Shall be considered as a separate bid
 If the lowest evaluated bidder has submitted the alternative bid ,
then in can be opened.
 Ask to provide rate analysis
 If the bidder fail to justify ask additional bid security to mitigate
the risk
 If the bidder refuse to provide such security bid shall be rejected.
 If the alternate bid price lower than the original bid , then
alternate bid value should be the lowest evaluated price
55
APPLICABLE DISCOUNT
1. Prier to closing of bids
2. Ignore Conditional Discount
3. Should be declared before closing of bids.
4. As a % or lump-sum can be declared.
5. Exclude the provisional sum and contingencies when
the discount is offered as a %
6. When the discount is offered as a lump –sum ,can
distribute uniformly to all the line items excluding
Contingencies and provisional sum.
CONVERSION TO COMMON CURRENCY
• OBJECT
– To determine lowest evaluated bid on date of specified.
• BID PRICE
– Convert in to amount payable in each currency.
• COMMON CURRENCY
– Borrower’s or any currency
• EXCHANGE RATES
– Official source such as Central Bank
• AS ON
– Any specified date
– Date to be clearly specified in bid documents.
57
DOMESTIC PREFERENCE
• Guideline 7.9.6 shall be included in the bidding
documents
• Assembly ,Fabrication & possessing etc are
commercially recognized.
• Can not modify the mix of domestic and foreign
goods after bid opening.
• No margin of preference shall be applied to any
associated services or works included in the
package.
58
Detailed evaluation of bids
Financial adjustment for Bid Price (Commercial
Aspects)
1. Adjustment for Deviation from the terms of
payment
2. Adjustment for deviation from the delivery
schedule or completion
3. Adjustment for Deviation from provision for
payment of duties and taxes
59
Detailed evaluation of bids
Financial adjustment for Bid Price (Technical
Aspects)
1. Adjustment for completeness in scope of supply –
E.g. Missing Items
2. Adjustment for Technical compliance – E.g. Alloy
wheel vs Normal wheel
3. Adjustment for Inland Transportation
4. Adjustment for spare parts
5. Maximum amount of Adjustment for deviation
60
BID EVALUATION
Other factors
• Delivery Time /Completion time
• Payment terms
• Terms of Guarantee
• Training
61
BID EVALUATION
Other Factors
• Technical Capacity
• Operating Cost
• Maintenance Cost
• Efficiency
• Resale value
62
Life cycle Cost
63
Thank You

Weitere ähnliche Inhalte

Was ist angesagt?

Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contractshiva prakash
 
Construction Claims
Construction ClaimsConstruction Claims
Construction ClaimsRajesh Sharma
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightFrancis Ho
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introductionDaniel Ross
 
Fidic contract
Fidic contract Fidic contract
Fidic contract Yash Patel
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENTSumaiya Jabin
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc ProjectsMy own
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract managementPriyesh Nair
 

Was ist angesagt? (20)

FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1ACH 231 Lecture 07 (Contract Documents) Part 1
ACH 231 Lecture 07 (Contract Documents) Part 1
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Procurement- Contract Management
Procurement- Contract ManagementProcurement- Contract Management
Procurement- Contract Management
 
Terminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it RightTerminating a Construction Contract: Getting it Right
Terminating a Construction Contract: Getting it Right
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
Tendering in construction introduction
Tendering in construction introductionTendering in construction introduction
Tendering in construction introduction
 
Fidic contract
Fidic contract Fidic contract
Fidic contract
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Tendering
TenderingTendering
Tendering
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects110801Proposed Fidic Contract Framework For Complex Epc Projects
110801Proposed Fidic Contract Framework For Complex Epc Projects
 
Overview to contract management
Overview to contract managementOverview to contract management
Overview to contract management
 

Andere mochten auch

The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & BiddingMoatasem Mabrouk
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
Purchase of inventory items
Purchase of inventory itemsPurchase of inventory items
Purchase of inventory itemsBeverly Erigan
 
Minute to say it: Team Building or Ice Breaker Activity
Minute to say it:  Team Building or Ice Breaker ActivityMinute to say it:  Team Building or Ice Breaker Activity
Minute to say it: Team Building or Ice Breaker ActivitydifferNtiated4u
 
National public procurement policy framework
National public procurement policy frameworkNational public procurement policy framework
National public procurement policy frameworkDr Lendy Spires
 
Major changes in the new Public Procurement Directives, June 2014, Universida...
Major changes in the new Public Procurement Directives, June 2014, Universida...Major changes in the new Public Procurement Directives, June 2014, Universida...
Major changes in the new Public Procurement Directives, June 2014, Universida...Carina Risvig Hamer
 
Implementing the procurement legislation
Implementing the procurement legislationImplementing the procurement legislation
Implementing the procurement legislationNigel Campbell
 
Ice Breaker Activity: Story Builder
Ice Breaker Activity: Story BuilderIce Breaker Activity: Story Builder
Ice Breaker Activity: Story Builderkatygroleau
 
Bid propsl evaluation
Bid propsl evaluation Bid propsl evaluation
Bid propsl evaluation Veluppillai Mohan
 
Which federal-policies-can-be-most-effective-slide-deck
Which federal-policies-can-be-most-effective-slide-deckWhich federal-policies-can-be-most-effective-slide-deck
Which federal-policies-can-be-most-effective-slide-deckGireesh Shrimali
 
Subsidy for SUV's and December's Increase in Demand for Large Vehicles
Subsidy for SUV's and December's Increase in Demand for Large VehiclesSubsidy for SUV's and December's Increase in Demand for Large Vehicles
Subsidy for SUV's and December's Increase in Demand for Large VehiclesGene Hayward
 
162747 633726030356563750
162747 633726030356563750162747 633726030356563750
162747 633726030356563750Rahul Sharma
 
Ice Breaker Activity
Ice Breaker ActivityIce Breaker Activity
Ice Breaker Activityclrohe
 
Income statements & cash flow
Income statements & cash flowIncome statements & cash flow
Income statements & cash flowJeronicaLogan
 
Basic macroeconomics lecture notes 1
Basic macroeconomics lecture notes 1Basic macroeconomics lecture notes 1
Basic macroeconomics lecture notes 1aneeskhattak
 

Andere mochten auch (20)

The Basics of Tendering & Bidding
The Basics of Tendering & BiddingThe Basics of Tendering & Bidding
The Basics of Tendering & Bidding
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
Bid evaluation shopping
Bid evaluation   shoppingBid evaluation   shopping
Bid evaluation shopping
 
Purchase of inventory items
Purchase of inventory itemsPurchase of inventory items
Purchase of inventory items
 
Minute to say it: Team Building or Ice Breaker Activity
Minute to say it:  Team Building or Ice Breaker ActivityMinute to say it:  Team Building or Ice Breaker Activity
Minute to say it: Team Building or Ice Breaker Activity
 
National public procurement policy framework
National public procurement policy frameworkNational public procurement policy framework
National public procurement policy framework
 
Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
Vesna Gojkovic Milin, SIGMA Public procurement review bodies conference, Ohri...
 
4th Day Basic PPT
4th Day Basic PPT4th Day Basic PPT
4th Day Basic PPT
 
Major changes in the new Public Procurement Directives, June 2014, Universida...
Major changes in the new Public Procurement Directives, June 2014, Universida...Major changes in the new Public Procurement Directives, June 2014, Universida...
Major changes in the new Public Procurement Directives, June 2014, Universida...
 
Implementing the procurement legislation
Implementing the procurement legislationImplementing the procurement legislation
Implementing the procurement legislation
 
Ice Breaker Activity: Story Builder
Ice Breaker Activity: Story BuilderIce Breaker Activity: Story Builder
Ice Breaker Activity: Story Builder
 
Bid propsl evaluation
Bid propsl evaluation Bid propsl evaluation
Bid propsl evaluation
 
Which federal-policies-can-be-most-effective-slide-deck
Which federal-policies-can-be-most-effective-slide-deckWhich federal-policies-can-be-most-effective-slide-deck
Which federal-policies-can-be-most-effective-slide-deck
 
Income statements
Income statementsIncome statements
Income statements
 
Subsidy for SUV's and December's Increase in Demand for Large Vehicles
Subsidy for SUV's and December's Increase in Demand for Large VehiclesSubsidy for SUV's and December's Increase in Demand for Large Vehicles
Subsidy for SUV's and December's Increase in Demand for Large Vehicles
 
162747 633726030356563750
162747 633726030356563750162747 633726030356563750
162747 633726030356563750
 
Ice Breaker Activity
Ice Breaker ActivityIce Breaker Activity
Ice Breaker Activity
 
Income statements & cash flow
Income statements & cash flowIncome statements & cash flow
Income statements & cash flow
 
Basic macroeconomics lecture notes 1
Basic macroeconomics lecture notes 1Basic macroeconomics lecture notes 1
Basic macroeconomics lecture notes 1
 

Ähnlich wie PUBLIC PROCUREMENT ESSENTIALS

Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdfmekuannintdemeke
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSGanesh Bhorkade
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1Shashi Kumara
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelinesRitesh Kumar Baranwal
 
Overview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxOverview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxabiytk
 
eTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & EntrepreneurshipeTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & EntrepreneurshipSyed Mohsin Raja
 
CHAPTER 5.ppt
CHAPTER 5.pptCHAPTER 5.ppt
CHAPTER 5.pptodowa1
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfPSENTHILMURUGAN2
 
Understanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesUnderstanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesLloyd Sewell
 
School nutrition procurement training Part 1
School nutrition procurement training Part 1School nutrition procurement training Part 1
School nutrition procurement training Part 1Nevada Agriculture
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahidashahida quraishi
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Managementlearnafren
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glanceTransnet Port Terminals
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering proceduresRotich Kimaru
 

Ähnlich wie PUBLIC PROCUREMENT ESSENTIALS (20)

procurement overview
procurement overviewprocurement overview
procurement overview
 
Chapter -Two (3).pdf
Chapter -Two (3).pdfChapter -Two (3).pdf
Chapter -Two (3).pdf
 
Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013Public Procurement and Contract - Theory and practice in Nepal_2013
Public Procurement and Contract - Theory and practice in Nepal_2013
 
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONSPURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
PURCHASE PROCEDURE IN AUTONOMOUS EDUCATIONAL ORGANISATIONS
 
Foundation of supply management
Foundation of supply managementFoundation of supply management
Foundation of supply management
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Overview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptxOverview Presentation - Procurement Directive, December 2021.pptx
Overview Presentation - Procurement Directive, December 2021.pptx
 
eTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & EntrepreneurshipeTendering in 2018: Tenders & Entrepreneurship
eTendering in 2018: Tenders & Entrepreneurship
 
CHAPTER 5.ppt
CHAPTER 5.pptCHAPTER 5.ppt
CHAPTER 5.ppt
 
ACH 231 Lecture 07 (Contract Documents) Part 2
ACH 231 Lecture 07 (Contract Documents) Part 2ACH 231 Lecture 07 (Contract Documents) Part 2
ACH 231 Lecture 07 (Contract Documents) Part 2
 
IFAD procurement guidelines
IFAD procurement guidelinesIFAD procurement guidelines
IFAD procurement guidelines
 
StandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdfStandardTenderDocument-14122020.pdf
StandardTenderDocument-14122020.pdf
 
Understanding Pre Qualification Questionnaires
Understanding Pre Qualification QuestionnairesUnderstanding Pre Qualification Questionnaires
Understanding Pre Qualification Questionnaires
 
School nutrition procurement training Part 1
School nutrition procurement training Part 1School nutrition procurement training Part 1
School nutrition procurement training Part 1
 
Final presentation from shahida
Final presentation from shahidaFinal presentation from shahida
Final presentation from shahida
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Management
 
IFAD's Procurement Guidelines
IFAD's Procurement GuidelinesIFAD's Procurement Guidelines
IFAD's Procurement Guidelines
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glance
 
Tendering procedures
Tendering proceduresTendering procedures
Tendering procedures
 

KĂźrzlich hochgeladen

Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfOnline Income Engine
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Trucks in Minnesota
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 

KĂźrzlich hochgeladen (20)

Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Unlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdfUnlocking the Secrets of Affiliate Marketing.pdf
Unlocking the Secrets of Affiliate Marketing.pdf
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 

PUBLIC PROCUREMENT ESSENTIALS

  • 1. NEEDS TO KNOW ON PUBLIC PROCUREMENT Priyantha weerasooriya. SSP/Director-Supplies. PHQ
  • 3. Meaning of procurement Oxford Dic; The process of obtaining supplies, especially for Government or an organization
  • 4. Previous Tender Guidelines in Sri Lanka  Guidelines on Government Tender Procedure  Separate Chapter for Foreign Funded Projects (2000)  Guidelines on Government Tender Procedures (Revised in 1997)  Issued a Separate book, with 60 Circulars to the tender procedure 1997 (2004)
  • 5. 2006 -Pro Guideline and Manuals in Operation as at Today  Procurement Guideline and Manual Works and Goods 2006.  Selection and Employment of Consultants 2007  Procurement of Pharmaceuticals & Medicals & Medical Devices 2006
  • 6. 1.4 ETHICS IN PROCUREMENT 1.4.1.Confidentiality 1.4.2.Corruption 1.4.3.Conflict of Interest 1.4.4.No gifts or inducement to be accepted
  • 7. Objectives of Procurement  Value for Money Elements of VFM * Economy – Minimizing Cost of Resources * Efficiency - Maximum output against minimum input * Effectiveness - Relationship between intended results and actual results Public Procurement Involves * SUPPLIES * CONSTRUCTIONS * SERVICES (Over 80% Public Expenditure Goes Through Public Procurement) Procurement in Supplies should ensure * RIGHT QUALITY * RIGHT QUANTITY * RIIGHT TIME * RIGHT PRICE * RIGHT PLACE
  • 8.  Transparency Accountability  Fairness  Efficiency  Equal Opportunity  Development of Local Business  Achievement of National Development Objectives
  • 9. Important elements of the Procurement Process  Procurement Planning  Preparation of Bidding Document  Invitation to bid Closing  Bid Opening  Bid Evaluation  Award of Contract
  • 10. LAWS APPLICABLE TO PROCUREMENT ACTIONS 1) Laws of Arbitration Act No. 11 of 1995 2) Laws of Contract 3)Bribery Act – Section 70. Any public servant who, with intent, to cause wrongful or unlawful loss to the Government, or to confer a wrongful or unlawful benefit, favour or advantage on himself or any person, or with knowledge, that any wrongful or unlawful loss will be caused to any person or to the Government, or that any wrongful or unlawful benefit, hall upon summary trial and conviction by a Magistrate be liable to imprisonment for a term not exceeding ten years or to a fine not exceeding one hundred thousand rupees or to both such imprisonment and fine.
  • 11. PROCUREMENT METHOD 3.1 International Competitive Bidding (ICB) 3.2 National Competitive Bidding (NCB) - Over 2M * Publish in a News Papers – 21 days * Bid Security required - for 119 days * Bid validity - for 91 days 3.3 Limited / Restricted International Competitive Bidding (LIB) and Limited / Restricted National Competitive Bidding (LNB) 3.4 Shopping - Below 2M • Five (5) quotations • Thru Registered Suppliers • Yellow Pages and Rainbow Pages
  • 12. 3.5 Direct Contracting a) Direct contracting is a means of Procurement of Goods or Services or Works from a single supplier source. b) It entails no competition and shall be used only under exceptional circumstances c) This method is appropriate under the following circumstances i) When the prices or rates are fixed pursuant to legislation by regulatory bodies ii) Standardization of equipment, for compatibility with existing equipment, may justify additional purchases of the same type of Goods d) When direct contracting is used under any of the reasons above, the value of the Procurement shall be subjected to the upper limits given under Guideline 2.14. No government agency will qualify for automatic direct contract award unless the above requirements are satisfied 3.6 Repeat Orders 3.7 Force Account 3.8 Emergency Account
  • 14. WHAT IS STRATEGIC PROCUREMENT PLANNING? 4.1. Advance Procurement Action 4.2. Master Procurement Plan (MPP) 4.3. Total Cost Estimate * Preparation of procurement plan 1st stage of the procurement process * Define what actions to be taken to focus * List out various procurement under works, goods, services and consultancy
  • 15. * Identify by which each one of these works goods and services are required to use * Decide contents of individual procurement packages * Identify the relationship between each such items * Determine the method of procurement * Determine the procurement lead-time for each package and schedule, target date for each event * Prepare a bar chart and / or table or list identifying the above dates for each bid package to assist in procurement monitoring
  • 17. STANDARD BIDDING DOCUMENT FOR PROCUREMENT OF GOODS FORMAT * Invitation for Bids (IFB) * Instructions to Bidders (ITB) * Bid Data Sheet * Evaluation and Qualification Criteria * Bidding Forms * Schedule of Requirements (SOR) * General Condition of Contract (GCC) * Special Conditions of Contract (SCC) * Contract Forms * Specifications * Price Schedule
  • 18. INSTRUCTIONS TO BIDDERS  General - Scope of Bid - Source of Funds - Ethic, Fraud and Corruption - Eligible Bidders - Eligible Goods & related services  Contents of Bidding Documents - Sections of Bidding Documents - Clarification of Bidding Documents - Amendment of Bidding Documents  Preparation of Bids - Cost of Bidding - Language of Bidding Document - Comprising the Bid - Bid Submission Forms and Price Schedule - Alternative Bids - Bid Prices and Discounts
  • 19. - Currencies of Bids - Documents Establishing the Eligibility of the bidder - Documents Establishing the conformity of the goods and related services - Documents Establishing the qualifications of the Bidder - Period of Validity of Bids - Bid Security - Format and Signing of Bids  Submission & Opening of Bids - Submission, Sealing and Marking of Bids - Deadline for submission of Bids - Late Bids - Withdrawals and modification of Bids - Bid Opening
  • 20.  Evaluation and Comparison of Bids - Examination of Terms & conditions: Technical Evaluation - Conversion to Single Currency - Domestic Preference - Evaluation of Bids - Comparison of Bids - Post Qualification of the Bidder - Purchaser’s Right Accept any Bid, and to reject any or all Bids  Award of Contract - Award Criteria - Purchaser's right to vary Quantities at time of award - Notification of Award - Signing of Contract - Performance Security
  • 21. ROLE IN BIDDING DOCUMENTS  Lay down rules of the Competition * How to price * How to prepare and submit bids * What will be the selection criteria * What will be the qualification criteria  Scope of the obligation * Technical Specifications * Bill of Quantities * Delivery / Completion Time * Warranty / Service obligations  Conditions of Contract * Payment Terms * Price Adjustments * Liability * Insurance * Dispute Resolution
  • 22. BIDDING DATA SHEET  General  Contents of Bidding Documents  Preparation of Bids  Submission and Opening of Bids  Evaluation and Comparison of Bids
  • 23. EVALUATION AND QUALIFICATION CRITERIA  Evaluation Criteria  Evaluation Criteria (Methodology)  Multiple Contracts  Domestic Preference  Post Qualification Requirement
  • 24. BIDDING FORMS  Bid Submission Form  Price Schedule  Price and completion Schedule – Related Services  Bid Security (Guarantee)  Bid – Security Declaration  Manufacturer’s Authorization
  • 25. SCHEDULE OF REQUIREMENTS  List of Goods and Delivery Schedule  List of Related Services and completion Schedule  Technical Specification  Drawings  Inspection and Tests
  • 26. GENERAL CONDITIONS OF CONTRACT * Definitions * Contract Documents * Fraud and Corruption * Interpretation * Language * Joint Venture, Consortium or Association * Eligibility * Notices * Governing Law * Settlement of Disputes * Scope of Supply * Delivery and Documents * Supplier’s Responsibilities * Contract Price * Terms of Payments * Taxes and Duties
  • 27. * Performance Security * Copyright * Confidential Information * Subcontracting * Specification and Standards * Packing and Documents * Insurance * Transportation * Inspection and Tests * Liquidated Damages * Warranty * Patent Indemnity * Limitation of Liability * Changes in Laws and Regulations * Force Majeure * Change Orders and Contract Amendments * Extensions of Time * Termination * Assignment
  • 28. CONTRACT DATA Contract Data shall supplement and / or amend the condition of contract (CC). Whenever there is a conflict, the provisions contract data shall prevail over those in the contract condition
  • 29. CONTRACT FORMS * Contract Agreement * Performance Security * Bank Guarantee for Advance Payment
  • 30. NPA APPROVED STANDARD BIDDING DOCUMENTS PUBLICATION NUMBER TITLE ICTAD /SBD/01 Shopping Procedure ICTAD/SBD/02 NCB ICTAD/SBD/03 MINER CONTRACTS ICTAD/SBD/04 DESIGN AND BUILD
  • 33. * Should be made available during office hours * At least up to one day prier to deadline of submission of bids * Availability for inspection, free of charge * Cost of BDs should be reasonable * Maintain good record keeping system * BDs shall be issued as specified in the IFB
  • 35. * Bids shall be received only at one location * Bids must be submitted only under sealed cover. * Clearly marked as “Original” or “Copy” putting together in one envelop * Late bids shall not be accepted * Bids shall be received as specified in the IFB
  • 37. * BOC shall comprise of minimum two members * Open soon after the closing of bids * Bids shall not be rejected at the bid opening * Only “Original” shall be opened * Late bids shall not be opened * Withdrawals shall not opened (if not any doubt) – withdrawal letter open first * Modification should with original bid * Attendance for bidders or his representatives * Record Keeping is very important * Original bids and records to be handed over to the Chairperson of TEC * Bids shall be opened as specified in the SBDs
  • 38. NECESSITY * IG Circular No. 2409/2012 Finance Circular No. 05/2012, dated 04.08.2011 * Delegation of financial Authorization under FR 135 * For Goods, Works & Services
  • 39. AUTHORITY FOR AWARD – SHOPPING Authority GOSL Foreign Funded MPC – Works inviting not less than 5 sealed quotation form ICTAD registered contractors Less than Rs. 5m Less than Rs. 5m MPC – Goods & Services inviting not less than 5 sealed quotations from registered suppliers Less than Rs. 5m Less than Rs. 3m PPC – Works inviting not less than 5 sealed quotation from ICTACD registered contractors Less than Rs. 5m Less than Rs. 5m PPC – Goods & Services inviting not less than 5 sealed quotations from suppliers Less than Rs. 5m Less than Rs. 3m MPC, DPC, PPC, - Goods & Services inviting not less than 3 quotations from registered suppliers Less than Rs. 5m Less than Rs. 1m RPC – Works inviting not less than 5 sealed quotations from ICTAD registered suppliers Less than Rs. 5m Less than Rs. 1m RPC – Goods & Services inviting not less than 5 sealed quotations from ICTAD registered suppliers Less than Rs. 5m Less than Rs. 500,000.00 CAO/HD/PD Works inviting not less than 3 sealed quotations Less than Rs. 500,000.00 CAO/HD/PD goods & Services inviting not less than 3 sealed quotations Less than Rs. 250,000.00
  • 40. Purpose of Bid evaluation To determine the lowest evaluated substantially responsive bid out of the bid received.
  • 41. Composition of TEC 1. No member should serve in both the PC & TEC. 2. Subject specialists 3. At least knowledgeable member on Procurement procedure 4. In case of specific subject matters ,can oblation expert advice from external members or institutions 5. Can oblation assistance and expert advice from consultants
  • 42. Responsibilities of TEC 1. TEC members are jointly and severally responsible. 2. Within the minimum time period as agreed with PC according to the PTS. 3. Evaluation should be made according to the approved specifications and criteria 4. In case of CAPC & MPC, if any objection from any bidder regarding the 10days prier to closing of bids , PE shall convey its decision to all the other bidders. 5. Revive and approve pre qualifications documents / SBDs prepared by the PE.
  • 43. Responsibilities of TEC Con… 6. To direct the PE to obtain clarifications from bidders in writing if necessary. 7. T approve and issue addenda to the bidding documents where necessary. 8. To agree upon the bid opening procedure. 9. To participate in negotiation , if directed by the PE. 10.The TEC may get assistance from external assistance . 11.Chairperson of the TEC or his nominee selected form the TEC shall participate at the pre – bid conference.
  • 44. BID EVALUATION EVALUATION CRITERIA • Shall be stated in Bid Documents • All factors quantified in Monitory terms 44
  • 45. Stages of bid Evaluation Bid Examination Detailed Bid Evaluation Post Qualification
  • 46. EVALUATION PROCESS Preliminary Examination • Whether the required securities are furnished. • Whether the bid documents are properly signed. • Whether the power of attorney for the authorized person is submitted • Whether joint venture agreements are submitted ( If necessary) • Eligibility of bidders • Whether the bid form was purchased from the concerned office • Whether the person or firm submitting the bid purchased bid form • Whether the bid is sealed • Whether the local agent is declared (If necessary) 46
  • 48. 48
  • 49. Substantial Responsiveness • Failure to sign the bid form • Eligibility requirements • Bid security as specified • Inability to meet the critical delivery schedule • Conditional bids • Unavailability of major supporting documents • Failure to bid for the required scope of work • Failure to quote for a major items in the package • Failure to meet major technical requirements – E.g. required material , plant capacity. 49
  • 50. Detailed bid evaluation Step – by – step procedure to be followed: 1. Correction of arithmetical errors 2. Un balance Bids 3. Discounts if Any; 4. Evaluation of acceptable omissions 5. Conversion to common currency 6. Completion times 7. Adjustments for various minor deviations 8. Domestic preference 9. Substantially non-responsive bids 10.Performance or service factors will be taken in to account as a adjustment.
  • 51. CORRECTION OF ARITHMETICAL ERRORS 1. Where there is discrepancy between the amount in figures and in word , the amount in words will govern 2. Unit rate and line items 3. Average unit cost for missing items 4. Estimated unit cost for underestimated items Exclude VAT ,Contingencies & Provisional sum
  • 52. Unbalanced Bids Examine whether the bid is substantially balanced Verify that prices are not so low Higher unit price for earlier works Higher unit rates for underestimated work Items >50% the average cost and where the total amount involved >5% of the total bid 52
  • 53. Unbalanced Bids Large contracts – say exceeding 500Mn Discount the Loaded Item Discount the engineer estimated value Add the deference between two NPVs to the bidder value for the purpose of compression 53
  • 54. Unbalanced Bids Other contract – Say not exceeding 500Mn Ask to provide rate analysis If the bidder fail to justify ask additional bid security to mitigate the risk If the bidder refuse to provide such security bid shall be rejected. Add the deference between two NPVs to the bidder value for the purpose of compression 54
  • 55. Alternative bids  If the bidders are permitted to submit alternative bids , it should be mentioned in the bidding documents  Shall be considered as a separate bid  If the lowest evaluated bidder has submitted the alternative bid , then in can be opened.  Ask to provide rate analysis  If the bidder fail to justify ask additional bid security to mitigate the risk  If the bidder refuse to provide such security bid shall be rejected.  If the alternate bid price lower than the original bid , then alternate bid value should be the lowest evaluated price 55
  • 56. APPLICABLE DISCOUNT 1. Prier to closing of bids 2. Ignore Conditional Discount 3. Should be declared before closing of bids. 4. As a % or lump-sum can be declared. 5. Exclude the provisional sum and contingencies when the discount is offered as a % 6. When the discount is offered as a lump –sum ,can distribute uniformly to all the line items excluding Contingencies and provisional sum.
  • 57. CONVERSION TO COMMON CURRENCY • OBJECT – To determine lowest evaluated bid on date of specified. • BID PRICE – Convert in to amount payable in each currency. • COMMON CURRENCY – Borrower’s or any currency • EXCHANGE RATES – Official source such as Central Bank • AS ON – Any specified date – Date to be clearly specified in bid documents. 57
  • 58. DOMESTIC PREFERENCE • Guideline 7.9.6 shall be included in the bidding documents • Assembly ,Fabrication & possessing etc are commercially recognized. • Can not modify the mix of domestic and foreign goods after bid opening. • No margin of preference shall be applied to any associated services or works included in the package. 58
  • 59. Detailed evaluation of bids Financial adjustment for Bid Price (Commercial Aspects) 1. Adjustment for Deviation from the terms of payment 2. Adjustment for deviation from the delivery schedule or completion 3. Adjustment for Deviation from provision for payment of duties and taxes 59
  • 60. Detailed evaluation of bids Financial adjustment for Bid Price (Technical Aspects) 1. Adjustment for completeness in scope of supply – E.g. Missing Items 2. Adjustment for Technical compliance – E.g. Alloy wheel vs Normal wheel 3. Adjustment for Inland Transportation 4. Adjustment for spare parts 5. Maximum amount of Adjustment for deviation 60
  • 61. BID EVALUATION Other factors • Delivery Time /Completion time • Payment terms • Terms of Guarantee • Training 61
  • 62. BID EVALUATION Other Factors • Technical Capacity • Operating Cost • Maintenance Cost • Efficiency • Resale value 62 Life cycle Cost
  • 63. 63