The document discusses two methods for calculating early start (ES) and late finish (LF) dates in a network diagram. The first method assumes the start activity has ES, EF, LS and LF as 1, while the second method assumes these values are 0. The document advises that either approach can be used, but in practice most scheduling tools use the second approach of starting from day 1 rather than day 0. It notes exam questions will make clear which approach to use for calculations.