SlideShare ist ein Scribd-Unternehmen logo
1 von 65
Downloaden Sie, um offline zu lesen
Based on PMBOK 5TH EditionBY: OMER ALSAYED OMER 
MBA, PMP, B.Sc.(Civil Eng.) : PMO manager EWU-DIU omeralsayed@yahoo.com +249-1234 94 587
KNOWING IS NOT ENOUGH;
WE MUST APPLY.
WILLING IS NOT ENOUGH;
WE MUST DO.
Johann Wolfgang von Goethe 
Learning Outcomes
Refresh quickly theories & fundamentals of project management
Initiate, Plan, Execute, Control, and Monitor & Close a project 
Develop and manage a project based on case studies. 
apply the all PMBOK Guide® knowledge areas to each phase of a project.
cover each phase while applying it in the context of real‐world project work.
Pursue learning through real world experiences and case studies ,in addition to technical competencies.
Using examples from participants’ and the instructor’s own projects.
Using templates form PMI R
% retain of what you learn >> when
• lecture.5%5%
• reading.10%10%
• audio‐visual.20%20%
• see a demonstration.30%30%
• engaged in a group discussion.50%50%
• practice what they learned.75%75%
• teach someone else/use90%90%
Project Management Process Group and Knowledge Area Mapping
Knowledge Area Initiating Planning Executing M& C Closing
4. Project Integration Management
Develop
Project Charter
4.2 Develop Project Management Plan
4.3 Direct & Manage Project 
Work
4.4 Monitor & Control Project Work
4.5 Perform Integrated Change Control
4.6 Close Project
or Phase
5. Project Scope Management
5.1 Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Time Management
6.1 Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
6.7 Control Schedule
7. Project Cost Management
7.1 Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality Management 8.1 Plan Quality Management 8.2 Perform Quality Assurance 8.3 Control Quality
9. Project Human Resource 
Management
9.1 Plan Human Resource
Management
9.2 Acquire Project Team
9.3 Develop Project Team
9.4 Manage Project Team
10. Project Communications 
Management
10.1 Plan Communications Management 10.2 Manage Communications 10.3 Control Communications
11. Project Risk Management
11.1 Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
11.6 Control Risks
12. Project Procurement Management 12.1 Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
12.4 Close 
Procurements
13. Project Stakeholder Management
Identify
Stakeholders
13.2 Plan Stakeholder
Management
13.3 Manage Stakeholder
Engagement
13.4 Control Stakeholder
Engagement
Project Management Process Group
Initiation, 2, 4%
Planning, 24, 51%
Executing, 8, 17%
M&C, 11, 24%
Closing, 2, 4%
process
Initiation
Planning
Executing
M&C
Closing
Project Management Process Interactions
closingclosing
0‐1‐2‐3
Initiating our project
Initiation .
• project 
selection
• Project 
statement of 
work
Project charter
• Project 
charter 
contents 
(PMBOK)
• PROJECT 
CHARTER
Stakeholders
• Identify 
Stakeholders 
• Stakeholder 
Analysis
• Stakeholder 
register
Inputs
Project Statement of 
work
Business case
Contract
EEF
OPA
T&T
Expert judgment
Output
Project Charter
AUTHORIZES
A narrative
description
of products,
services, or
results to be
delivered by
the project.
Strategic plan
Business need
Product/S/R scope description
SOW references
Statement Of Work ‐ sample
Project Title:Project Title:
• BP‐TC building 
Introduction / Background Introduction / Background 
• Brain Power Training Centre has 5 years master plan to  extend it’s training & education and consultancy 
activities 
• BPTC is targeting to  optimize their training capacity in quantity & quality  and entering new market segments, 
adding new innovated courses and material
• BPTC plans to design & construct ONE‐OF‐A‐KIND new training center building 
Objectives Objectives 
• To increase training hours per year from 1,000 to 5,000 training hours per year . 
Scope of work Scope of work 
• Project work includes 
• Design ,Construction & management of BP‐TC building
Project charter contents (PMBOK)
Project 
PURPOSE or 
justification,
Measurable project 
OBJECTIVES and 
related success 
criteria,
High‐level 
REQUIREMENTS,
ASSUMPTIONS and 
constraints,
High‐level project 
DESCRIPTION
and boundaries,
High‐level 
RISKS,
Summary 
MILESTONE
schedule,
Summary 
BUDGET,
STAKEHOLDER
list,
Project 
APPROVAL 
requirements 
Assigned PROJECT 
MANAGER, 
responsibility 
authority
Name and 
authority of the 
SPONSOR
4.1.3.1 PROJECT CHARTER SAMPLE (1/2)
Project : • BPBC Training center building
Project SPONSOR: • Prof.  A. S. Jumaa
Project MANAGER: • Engr. M. Rudwan
Project Customer: • BPBC Shareholders
Project PURPOSE or 
Justification:
• multi‐story building at Khartoum center to accommodate all  training , 
academic & other events of BPBC activities as part of BPBC strategy plan 
(2013‐2018) to enable it extend its’ existing & develop new program 
Project DESCRIPTION: • G+3 story building with training facilities
Project and Product 
Requirements:
• ..
Acceptance Criteria: • Complete all works within specified budget, time frame & industry quality
Initial Risks: • Lack of funding ‐ Governmental permeations –Growing market demand, …
Charter # :001‐08‐13  Date Prepared: December 4,2013
4.1.3.1 PROJECT CHARTER SAMPLE (2/2)
Project Objectives Success Criteria Person Approving
Scope Build‐up area sqm 800  & land scape 800 sqm + 10% QA
Time 24 months 800 sqm + 10% AK
Cost 5 USDG 5 USDG + 6 AK
Quality …. … …
Summary Milestones Due Date
Project Design start 1st August 2014
Construction start 15 October 2014
Hand over 31 July 2015
13.1 Identify Stakeholders
Input
Project charter
Procurement
documents
EEF
OPA
T&T
Stakeholder
analysis
Expert judgment
Meetings
Output
Stakeholder
register
13.1 Identify Stakeholders
Stakeholders
Organizations/Institutions
BPCT‐Board
BPCT‐ Permanent Staff
BPCT‐Part time staff
BPCT‐Admin staff
State Government
MoGW
MoHR
National Council Training
….
Beneficiaries
Professionals
Governmental bodies 
private bodies
Graduates
Construction parties
Client representative
Designer
Consultant
Contractors
Stakeholders’ Power / Interest Grid
13.1.2.1 Stakeholder Analysis
BPCT‐Board
Client representative
Designer
Consultant
Professionals (Engineers, Accountants,…)
Contractors
Sub‐contractors
suppliers
BPCT‐Part time staff
BPCT‐ Permanent Staff
Development & Labor
Ministry of General works
Graduates
Governmental & private bodies 
Ministry of Human Resources 
National Council Training
Interest
Power
13.1.3.1 Stakeholder register (PMI)
Name Position Role Contact Requirements Expectations Influence Class.*
Prof. Juma BPCT‐CEO Sponsor H 1
Eng. M. R. BPBC‐DM Designer H 2
Dr. A. R.
National 
Council 
Training
Governmental 
Authority
H 3
Eng. F.H. DIU‐ID
AB‐Consult
CC Contracting
Project Title: BPBC Training Center Building (BP-TC) Date prepared: ../…/2013
Signature:Stakeholder classification*: Internal/external, supporter/neutral/resistor, etc.
Group work Round#1
Grouping (each 4‐6)
Formats ready 
◦ blank paper – list
◦ P/I Grid
◦ S/H Register form
Exercise:
ERP Project (Statement Of Work)
Project Title:
• ERP System 
Introduction / Background 
• An organization that has no ERP will be running on many kinds of software that do not allow 
interaction. Customization also may be difficult it in some cases. This will negatively affect the 
optimized functioning of organization's business activities
Objectives 
• ERP system enables interactions of marketing, sales, quality control, products processes, 
supply lines, stocks and many other areas.
Scope of work 
• implement ERP systems in an organization, electronically syncing functions, processes, and 
departments into a system with shared data and accessibility.
ERP PROJECT CHARTER
Project : • .
Project SPONSOR: • .
Project MANAGER: • .
Project Customer: • .
Project PURPOSE or 
Justification:
• .
Project DESCRIPTION: • .
Project and Product 
Requirements:
• ..
Acceptance Criteria: • .
Initial Risks: • .
Charter # :001‐08‐13  Date Prepared: December 4,2013
STAKEHOLDER ANALYSIS MATRIX & Register form
Planning our project
Integration
• Planning processes
• Develop project 
management plan
• Project management 
plan
Scope
• Plan scope 
management
• Requirements 
management plan
• Collect req. process
• Requirements  
documentation
• Define scope process
• Project scope 
statement
• Create WBS process
• WBS 
• WBS  dictionary
cost
• Estimate Costs
Risk
• Identify Risks
process
• Risk register
Analogous vs. 
Parametric cost 
example
Planning processes
•4.2 Develop Project 
Management Plan
4. Project 
Integration 
Management
•5.1 Plan Scope Management
•5.2 Collect Requirements
•5.3 Define Scope
•5.4 Create WBS
5. Project Scope 
Management
•6.1 Plan Schedule 
Management
•6.2 Define Activities
•6.3 Sequence Activities
•6.4 Estimate Activity 
Resources
•6.5 Estimate Activity 
Durations
•6.6 Develop Schedule
6. Project Time 
Management
•7.1 Plan Cost Management
•7.2 Estimate Costs
•7.3 Determine Budget
7. Project Cost 
Management
•8.1 Plan Quality Management
8. Project Quality 
Management
•9.1 Plan Human Resource 
Management
9. Project Human 
Resource 
Management
•10.1 Plan Communications 
Management
10. Project 
Communications 
Management
•11.1 Plan Risk Management
•11.2 Identify Risks
•11.3 Perform Qualitative Risk 
Analysis
•11.4 Perform Quantitative 
Risk Analysis
•11.5 Plan Risk Responses
11. Project Risk 
Management
•12.1 Plan Procurement 
Management
12. Project 
Procurement 
Management
•13.2 Plan Stakeholder 
Management
13. Project 
Stakeholder 
Management
4.2 Develop Project Management Plan
Inputs
Project charter
Outputs from other
processes
Enterprise
environmental factors
Organizational
process assets
Tools & Techniques
Expert judgment
Facilitation Techniques
Outputs
Project management 
plan
defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive
project management plan.
Subsidiaries' Plans
Scope 
management plan
Requirements 
management plan
Schedule 
management plan
Cost management 
plan
Quality 
management plan
Process 
improvement plan
Human resource 
management plan
Communications 
management plan
Risk management 
plan
Procurement 
management plan
Stakeholder 
management plan
4.2.3.1 PROJECT MANAGEMENT PLAN 
Template (1/2)
Project Title: …..
Date Prepared: …….
Project Life Cycle:
…..
Variance and Baseline Management
Schedule Variance Threshold:
……
Schedule Baseline Management:
…..
Cost Variance Threshold:
….
Cost Baseline Management:
…..
Scope Variance Threshold:
….
Scope Baseline Management:
….
Quality Variance Threshold:
….
Performance Requirements Management:
….
Project Reviews:
……
Tailoring Decisions:
……
Project‐Specific Considerations:
…..
4.2.3.1 PROJECT MANAGEMENT PLAN 
Template (2/2)
Subsidiary Management Plans:
Area Approach
Requirements Management Plan
Scope Management Plan
Schedule Management Plan
Cost Management Plan
Quality Management Plan
Process Improvement Plan
Human Resources Management Plan
Communications Management Plan
Risk Management Plan
Procurement Management Plan
Change Management Plan
Configuration Management Plan
Baselines:
Attach all project baselines.
Samples of PROJECT MANAGEMENT PLAN
5.3 Define Scope
Inputs
Scope management plan
Project charter
Requirements
documentation
Organizational process
assets
Tools & Techniques
Expert judgment
Product analysis
Alternatives generation
Facilitation Techniques
Outputs
Project scope 
statement
Project 
documents 
updates
DETAILED description of the project and product.
boundaries -requirements collected will be INCLUDED in and excluded.
5.3.3.1 PROJECT SCOPE STATEMENT  SAMPLE
Project Title: ….. Date Prepared: ……. P 1/2
Product Scope Description:
Four story building with training facilities
Project Deliverables:
• 4 story building of 800 sqm
• Electromechanical
• Landscaping
• Furniture
• Training facilities
Project Acceptance Criteria:
• As in the project charter with addition of:
• …
Project Exclusions:
• Land acquire -Bank finance - ……
Project Constraints:
P 2/2
Project Assumptions:
Site is ready for construction by
October 2013
First design set (foundation structural
drawings are completed by mid-
September 2013)
…….
7.2.2 Estimate Costs: Tools and Techniques
7.2.2.2 Analogous Estimating
uses the values:
• Cost, budget
• or measures (size, weight), 
• complexity
• from a previous, similar project
• as the basis for estimating the same parameter
adjusted for adjusted for 
differences 
in 
complexity.
used when used when 
limited  
detailed 
information 
Uses Uses 
information 
& expert 
judgment.
lessless
costly,
time, 
lessless
accurate.
7.2.2 Estimate Costs: Tools and Techniques
7.2.2.3 Parametric Estimating
• between relevant 
historical data and 
other variables 
(building m2) .
statistical 
relationship 
• the sophistication 
• underlying data 
built into the 
model. 
produce 
higher levels 
of accuracy 
depending 
upon:
1 sqm cost $2
10 sqm cost $20 +approx.
Estimating techniques
Analogous 
L
Initiation
Parametric 
M
Planning
3‐points
H
Final plan
Bottom‐up
VH
executing
Analogous vs. Parametric 
Example
oYou are the project manager for the annual Earth 
Day 5k road race, with three primary components: 
marketing, registration, and race‐day coordination.
oFor marketing, there will be 500 flyers printed up at 
a cost $0.20 each.
It took two weeks for the flyers to be printed for last 
year event, so you estimate two weeks for the 
printing of the brochures for this event.
oLast year it took one week to design the on‐line 
registration form and the cost to host the 
registration website was $850.00 You estimate the 
same this year.
oThere will be four people used to coordinate the 
race. Each resource will be paid $25 per hour and 
they will be working an estimated seven hours, 
based on the race last year.
Marketing:
• 500 flyers 
• cost $0.20 each
• 2 weeks 
printing
Registration
• website
• $850.00
• one week 
Coordination
• 4 people
• $25 per hour 
• seven hours
Group work Round #2
Determine which TYPE
of estimate (cost & 
duration) for: 
1. marketing, 
2. registration, 
3. race‐day coordination
Analogous vs. Parametric 
Example
Coordination
Cost: $700
parametric estimating ‐ 4 x 
$25 x 7
Duration: 7 hours analogous
Registration
Cost: $850 analogous Duration: one week analogous
Marketing
Cost: $100 for brochures
parametric estimating 500 x 
$0.20
Duration: two weeks analogous
Executing
Executing processes
Direct & Manage Project Work
Work performance data
Executing processes
•4.3 Direct & Manage Project 
Work
•4.3 Direct & Manage Project 
Work
4. Project Integration 
Management
•8.2 Perform Quality Assurance•8.2 Perform Quality Assurance
8. Project Quality 
Management
•9.2 Acquire Project Team
•9.3 Develop Project Team
•9.4 Manage Project Team
•9.2 Acquire Project Team
•9.3 Develop Project Team
•9.4 Manage Project Team
9. Project Human 
Resource Management
•10.2 Manage Communications•10.2 Manage Communications
10. Project 
Communications 
Management
•12.2 Conduct Procurements•12.2 Conduct Procurements
12. Project Procurement 
Management
•13.3 Manage Stakeholder 
Engagement
•13.3 Manage Stakeholder 
Engagement
13. Project Stakeholder 
Management
INPUTS
9.4.1 Manage 
Project Team:
10.3.1 Control 
Communications:
11.2.1 Identify 
Risks: 
13.4.1 Control 
Stakeholder 
Engagement: 
OUTPUTS
4.4.3 Monitor 
and Control 
Project Work
9.4.3 Manage 
Project Team
10.2.3 Manage 
Communications
10.3.3 Control 
Communications
13.3.3 Manage 
Stakeholder 
Engagement
13.4.3 Control 
Stakeholder 
Engagement
project document used to document & monitor elements under discussion or in dispute between project 
stakeholders
Issue Log
•9.4.1.4
•10.3.1.3
•13.4.1.2
Project 
Documents
•11.2.1.10
•13.4.1.4
Project 
Documents 
Updates
• 4.4.3.4
• 9.4.3.3
• 10.2.3.3
• 10.3.3.4
• 13.4.3.4
Organizational 
Process Assets 
Updates
• 10.2.3.4
• 13.3.3.5
Issue Log • 13.3.3.1
Issue log 
template
PMI 
Issue ID Category Issue Impact on 
Objectives
Urgency
Responsible 
Party
Actions Status Due Date Comments
Issue log sample
Monitoring & Control
Monitoring 
& Control 
processes
Monitor & 
Control 
Project 
Work
Control 
Scope
SCOPE 
CREEP
Work 
performanc
e reports
Control 
Costs (EV‐
AC‐CPI)
Control risk 
process
Variance 
analysis
Monitoring & Control processes
•4.4 Monitor & Control 
Project Work
•4.5 Perform Integrated 
Change Control
4. Project 
Integration 
Management
•5.5 Validate Scope
•5.6 Control Scope
5. Project Scope 
Management
•6.7 Control Schedule
6. Project Time 
Management
•7.4 Control Costs
7. Project Cost 
Management
•8.3 Control Quality
8. Project Quality 
Management
•.
9. Project Human 
Resource 
Management
•10.3 Control 
Communications
10. Project 
Communications 
Management
•11.6 Control Risks
11. Project Risk 
Management
•12.3 Control Procurements
12. Project 
Procurement 
Management
•13.4 Control Stakeholder 
Engagement
13. Project 
Stakeholder 
Management
5.6 Control Scope
monitoring the status of the project and product scope and managing changes to the scope baseline.
Inputs
Project management plan
Requirements
documentation
Requirements traceability
matrix
Work performance data
Organizational process
assets
Tools & Techniques
Variance analysis
Outputs
Work performance 
information
Change requests
Project management plan 
updates
Project documents updates
Organizational process assets 
updates
SCOPE CREEP
Controlling
• the project scope 
ensures
• all requested changes and 
recommended corrective 
or preventive actions
are processed
• through the Perform 
Integrated Change Control 
process 
The uncontrolled 
•expansion to product 
or project scope 
without 
•adjustments to time, 
cost, and resources 
is referred 
•to as SCOPE CREEP. 
Change is inevitable; therefore some type of change control process is mandatory for every project
• elevation of 1,825 ft (556 m) above sea level, 
• 175 ft (53 m) above the stream bed. 
• capacity of 30,000 acre∙ft (37,000,000 m3)
June 1923
• capacity of the reservoir 32,000 acre‐feet (39,000,000 m3).
July 1, 1924
• capacity of 38,000 acre‐feet (47,000,000 m3)
• height would be 185 ft (56 m)
March 1925
• Water began to fill the reservoir.
March 1, 1926 
• Two and a half minutes before midnight > the St. Francis 
Dam disastrously failed. the resulting flood killed up to 600 people
March 12, 1928
47,000,000 m3  
(56 m H)
39,000,000 m3
37,000,000 m3
53 m H
St. Francis Dam (scope creep story)
7.4 Control Costs
Inputs
Cost management plan
Project funding requirements
Work performance data
Organizational process
assets
Tools & Techniques
Earned value management
Forecasting
To-complete performance
index (TCPI)
Performance reviews
Project management
software
Reserve analysis
Outputs
Work performance information
Cost forecasts
Change requests
Project management plan 
updates
Project documents updates
Organizational process assets 
updates
of monitoring the status of the project to update the project costs and managing
changes to the cost baseline.
7.4.2 Control Costs: Tools and Techniques
7.4.2.1 Earned Value Management
It integrates the scope ,cost & schedule baselines, to form the performance baseline
• authorized budget planned for the work to be accomplished for an activity or WP/CA.
• The total of the PV (performance measurement baseline PMB ,also known as budget at 
completion BAC).
Planned value. Planned value. 
• a measure of work performed expressed in terms of the budget authorized for that work. 
Earned value. Earned value. 
• realized cost incurred for the work performed on an activity during a specific time period.
Actual cost. Actual cost. 
7.4.2 Control Costs: Tools and Techniques
7.4.2.1 Earned Value Management
•SV = EV – PVSchedule 
variance
•CV= EV − ACCost variance
•SPI = EV/PV
Schedule 
performance 
index
•CPI = EV/AC
Cost 
performance 
index
PV EV AC
1‐Jan‐13 0 0 0
1‐Feb‐13 1000 800 1200
1‐Mar‐13 1500 1200 1800
1‐Apr‐13 2500
1‐May‐13 3000
1‐Jun‐13 3600
Group work Round # 3
Calculate the followings
1. BAC
2. CV & SV
3. Cumulative CPI, SPI 
4. ETC 
5. EAC
7.4.2 Control Costs: Tools and Techniques
7.4.2.1 Earned Value Management
PV, 1500
PV, 3600
EV, 1200
AC, 1800
ETC, 5400
0
1000
2000
3000
4000
5000
6000
Jan‐13 Feb‐13 Mar‐13 Apr‐13 May‐13 Jun‐13
CUM COST
Jan‐13 Feb‐13 Mar‐13 Apr‐13 May‐13 Jun‐13
PV 0 1000 1500 2500 3000 3600
EV 0 800 1200
AC 0 1200 1800
ETC 0 1200 1800 3750 4500 5400
the budgeted rate:
EAC = AC + (BAC –
EV)
= 1800 + (3600‐
1200) 
=4,200
the present CPI
EAC = BAC / CPI
=3600/.6667=5,400
considering both 
SPI and CPI factors
EAC = AC + [(BAC –
EV) / (CPI × SPI)]
=1800 + {(3600‐
1200)/(.6667*.83)}
=6,135
Closing
Closing 
processes
Close Project 
or Phase 
process
Close 
Procurements 
process
Closed 
procurements
Organizational 
process assets 
updates 
(lessons 
learned)
Project close‐
out
Closing processes
•4.6 Close Project or 
Phase
4. Project 
Integration 
Management
5. Project Scope 
Management
6. Project Time 
Management
7. Project Cost 
Management
8. Project Quality 
Management
9. Project Human 
Resource 
Management
10. Project 
Communications 
Management
11. Project Risk 
Management
•12.4 Close 
Procurements
12. Project 
Procurement 
Management
13. Project 
Stakeholder 
Management
4.6 Close Project or Phase
Inputs
Project 
management plan
Accepted 
deliverables
Organizational 
process assets
Tools & Techniques
Expert judgment
Analytical 
techniques
Meetings
Outputs
Final product, 
service, or result 
transition
Organizational 
process assets 
updates
FINALIZING all activities across all of the Project Management Process Groups to formally
complete the phase or project.
12.4 Close Procurements
Inputs
Project
management plan
Procurement
documents
Tools & Techniques
Procurement audits
Procurement
negotiations
Records
management
system
Outputs
Closed
procurements
Organizational
process assets
updates
COMPLETING each project procurement
12.4.3.1 Closed procurements
Vendor Performance Analysis
What Worked Well:
What Can Be Improved:
Record of Contract Changes
Record of Contract Disputes
Organizational process assets
updates (lessons learned)
What Worked Well:
What Can Be Improved:
Risks and Issues
ID Risk or Issue Description Response Comments
Quality Defects
Project close‐out
Useful sites
2t‐PM
preparepm.comPmi.orgOliverlehmann.com
arab‐eng.org pmstudy.com
+249‐123494587

Weitere ähnliche Inhalte

Was ist angesagt?

Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Agus Suhanto
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groupsvanessahartsfield
 
Project integration management
Project integration management Project integration management
Project integration management KU Leuven
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management FrameworkAarti Dahiya PMP
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalYudha Pratama, PMP
 
Project scope management
Project scope managementProject scope management
Project scope managementAnit Roy
 
Project integration management
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope ManagementDavidMcLachlan1
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication ManagementDavidMcLachlan1
 
Project integration management
Project  integration managementProject  integration management
Project integration managementdeep sharma
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project KnowledgeDavidMcLachlan1
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 

Was ist angesagt? (20)

05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
9.5 Manage Team
9.5 Manage Team9.5 Manage Team
9.5 Manage Team
 
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process GroupsVanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
Vanessa Hartsfield Gm591 Unit 4 Project Management Process Groups
 
Project integration management
Project integration management Project integration management
Project integration management
 
PMI Project Management Framework
PMI Project Management FrameworkPMI Project Management Framework
PMI Project Management Framework
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management final
 
Project scope management
Project scope managementProject scope management
Project scope management
 
10 project communications
10 project communications10 project communications
10 project communications
 
Scope management
Scope managementScope management
Scope management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
5.1 Plan Scope Management
5.1 Plan Scope Management5.1 Plan Scope Management
5.1 Plan Scope Management
 
10.1 Plan Communication Management
10.1 Plan Communication Management10.1 Plan Communication Management
10.1 Plan Communication Management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Project integration management
Project  integration managementProject  integration management
Project integration management
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
4.4 Manage Project Knowledge
4.4 Manage Project Knowledge4.4 Manage Project Knowledge
4.4 Manage Project Knowledge
 
Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020Portfolio mostafa saad_jan_2020
Portfolio mostafa saad_jan_2020
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 

Ähnlich wie Practical project management 12 feb 2014

Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMPEdureka!
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionJohn Khateeb
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmpDuy Tan Geek
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slidesWilber Tuttleman
 
PMP Exam Prep (Pass the Exam in a Month!) - Orientation Seminar
PMP Exam Prep (Pass the Exam in a Month!) -  Orientation SeminarPMP Exam Prep (Pass the Exam in a Month!) -  Orientation Seminar
PMP Exam Prep (Pass the Exam in a Month!) - Orientation SeminarPrudentialSolutions
 
Episode 111 Premium: There is no PMI Project Management Methodology
Episode 111 Premium: There is no PMI Project Management MethodologyEpisode 111 Premium: There is no PMI Project Management Methodology
Episode 111 Premium: There is no PMI Project Management MethodologyOSP International LLC
 
PMP Certification Brochure
PMP Certification BrochurePMP Certification Brochure
PMP Certification BrochureKnowledgehut
 
Tech Tuesday Slides - Getting Started with the Portfolio Module.
Tech Tuesday Slides - Getting Started with the Portfolio Module.Tech Tuesday Slides - Getting Started with the Portfolio Module.
Tech Tuesday Slides - Getting Started with the Portfolio Module.OnePlan Solutions
 
Operation management project-based learning
Operation management  project-based learning Operation management  project-based learning
Operation management project-based learning dsjaque
 
PMP Exam Prep Course Preview
PMP Exam Prep Course PreviewPMP Exam Prep Course Preview
PMP Exam Prep Course PreviewInvensis Learning
 
Introduction to Project Management Professional
Introduction to Project Management Professional Introduction to Project Management Professional
Introduction to Project Management Professional Pieter Glasbergen PMP®
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overviewhouserdah
 

Ähnlich wie Practical project management 12 feb 2014 (20)

Introduction to PMP
Introduction to PMPIntroduction to PMP
Introduction to PMP
 
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th EditionProject Management Professional PMI-PMP Based on PMBOK 6th Edition
Project Management Professional PMI-PMP Based on PMBOK 6th Edition
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmp
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
Section 1: introduction
Section 1: introductionSection 1: introduction
Section 1: introduction
 
e-learning_PMBOK
e-learning_PMBOKe-learning_PMBOK
e-learning_PMBOK
 
D & F Sylla.pdf
D & F Sylla.pdfD & F Sylla.pdf
D & F Sylla.pdf
 
PMP Exam Prep_sample slides
PMP Exam Prep_sample slidesPMP Exam Prep_sample slides
PMP Exam Prep_sample slides
 
PMP Exam Prep (Pass the Exam in a Month!) - Orientation Seminar
PMP Exam Prep (Pass the Exam in a Month!) -  Orientation SeminarPMP Exam Prep (Pass the Exam in a Month!) -  Orientation Seminar
PMP Exam Prep (Pass the Exam in a Month!) - Orientation Seminar
 
Bird view on projects
Bird view on projectsBird view on projects
Bird view on projects
 
Episode 111 Premium: There is no PMI Project Management Methodology
Episode 111 Premium: There is no PMI Project Management MethodologyEpisode 111 Premium: There is no PMI Project Management Methodology
Episode 111 Premium: There is no PMI Project Management Methodology
 
PMP Certification Brochure
PMP Certification BrochurePMP Certification Brochure
PMP Certification Brochure
 
Tech Tuesday Slides - Getting Started with the Portfolio Module.
Tech Tuesday Slides - Getting Started with the Portfolio Module.Tech Tuesday Slides - Getting Started with the Portfolio Module.
Tech Tuesday Slides - Getting Started with the Portfolio Module.
 
Operation management project-based learning
Operation management  project-based learning Operation management  project-based learning
Operation management project-based learning
 
PMP Prep Course(English)
PMP Prep Course(English)PMP Prep Course(English)
PMP Prep Course(English)
 
PMP Exam Prep Course Preview
PMP Exam Prep Course PreviewPMP Exam Prep Course Preview
PMP Exam Prep Course Preview
 
PM FrameWork: Module 1
PM FrameWork: Module 1PM FrameWork: Module 1
PM FrameWork: Module 1
 
PM Academy Credentials
PM Academy Credentials PM Academy Credentials
PM Academy Credentials
 
Introduction to Project Management Professional
Introduction to Project Management Professional Introduction to Project Management Professional
Introduction to Project Management Professional
 
Pmp Prep Session 1 Overview
Pmp Prep Session 1 OverviewPmp Prep Session 1 Overview
Pmp Prep Session 1 Overview
 

Mehr von Omer Alsayed PhD,MBA, PMP®

Project stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعProject stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعOmer Alsayed PhD,MBA, PMP®
 
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعيةبرنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعيةOmer Alsayed PhD,MBA, PMP®
 
09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittionOmer Alsayed PhD,MBA, PMP®
 
09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 Omer Alsayed PhD,MBA, PMP®
 
وأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلوأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلOmer Alsayed PhD,MBA, PMP®
 
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Omer Alsayed PhD,MBA, PMP®
 

Mehr von Omer Alsayed PhD,MBA, PMP® (20)

Project stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعProject stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروع
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعيةبرنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
 
04 project integration management
04 project integration management04 project integration management
04 project integration management
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
08 project quality management
08 project quality management08 project quality management
08 project quality management
 
09 project human res 2014
09 project human res 201409 project human res 2014
09 project human res 2014
 
13 project stakeholders management
13 project stakeholders management13 project stakeholders management
13 project stakeholders management
 
12 project procurement management
12 project procurement management12 project procurement management
12 project procurement management
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
09 project human res 2014
09 project human res 201409 project human res 2014
09 project human res 2014
 
Practical project management based on PMBOK5
Practical project management based on PMBOK5Practical project management based on PMBOK5
Practical project management based on PMBOK5
 
09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion
 
09 project human resources management pmbok 5th
09 project human resources management pmbok 5th09 project human resources management pmbok 5th
09 project human resources management pmbok 5th
 
09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5
 
وأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلوأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجل
 
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
 
No one can ride your back
No one can ride your backNo one can ride your back
No one can ride your back
 
المدود
المدودالمدود
المدود
 

Kürzlich hochgeladen

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 

Kürzlich hochgeladen (20)

8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 

Practical project management 12 feb 2014