SlideShare ist ein Scribd-Unternehmen logo
1 von 20
Manish Purwar, iZenBridge
   How to create Network diagram?
   How to find out Critical Path?
   Finding out float of an activity
   Schedule compression techniques
   Understanding of critical path analysis & schedule
    compression techniques
   Will help in managing projects better in real life
   Will help in solving 10 to 15 questions in PMP exam
   Activity   A does not have any dependencies on other activities.
   Activity   B, can only be started once A is complete.
   Activity   C, can be started once B is complete.
   Activity   D can be started once A is complete.
   Activity   E can be started once C & D are complete.



   Network diagram helps in visualizing the relative order and
    dependencies of these activities on each other.
   Precedence Diagramming Method (PDM) or Activity on Node
    (AON)
    • Network diagram shows dependencies
    • In PDM, boxes are used to show activities and arrows to
      show relationships.
    • Activities are put in the order they need to be performed
    • Network diagram is not concerned with when the activities
      will occur on the project timeline

                 Activity
                                    Activity 2
                    1

                                                    End
        Start



                            Activity 3
   Mandatory dependencies
    • Something MUST BE done before something else.
   Discretionary dependencies
    • There is preferred method, or order, of performing the
      work.
   External dependencies
    • Something outside the project must be done before a task
        in the project.
   Finish to Start (FS) : The successor can’t start before the
    predecessor has finished.
   Start to Start (SS) : The successor can’t start before the
    predecessor has started.
   Finish to Finish (FF) : The successor can’t finish before the
    predecessor has finished.
   Start to Finish (SF) : The successor can’t finish before the
    predecessor has started. It is rarely used.
   Finish to Start is most commonly used relationship.

    Finish to Start            Start to Start            Finish to Finish

Dig a                                                         Finish testing
              Plant tree          Start design
hole
                                                          Finish documentation

                           After 2 weeks, start coding
3 weeks                8 weeks
                      3              6       6           14
                             B                       C

                      3              6       6           14
        3 weeks                                                    5 weeks
        0         3                                           14         19
Start       A                                                        E        End
        0         3              6 weeks                      14         19

                                 3               9
                                         D
                                 8           14




                                                                               8
   Longest duration path in a Network Diagram
   It is the shortest time to complete the project
   It helps to determine the focus for project management
    efforts
   Near critical path is close in duration to critical path
   Closer the near critical and critical paths are, the more risk
    project has
3 weeks                8 weeks
                          3              6       6           14
                                 B                       C

                          3              6       6           14
        3 weeks
                                                                       5 weeks
        0         3                                               14         19
Start       A                                                            E        End
        0         3                  6 weeks                      14         19

                                     3               9
                                             D
                                     8           14




        Start, A, B, C, E, End
                or
        Start, A, D, E, End

                                                                                   10
   Total Float (slack)
    • The amount of time an activity can be delayed with out
       delaying project end date.
   Project Float (slack)
    • Amount of time project can be delayed with out delaying
       externally imposed project completion date.
   Critical path activities have zero float.
   Knowing float helps in better allocation of resources.
   If project is behind an imposed external date, then project
    will have negative float.
ES                  EF        Forward
                                                  Pass



    Backward        LS                  LF
    Pass




    ES : Early Start
    LS : Late Start               Float = LS-ES      OR     Float = LF-EF
    EF : Early Finish
    LF : Late Finish

ES and EF are calculated by Forward Pass.
LS and LF are calculated by Backward Pass.


                                                                            12
3             6    6            14
                                        B                   C
                                     3 weeks                8
                                 3             6    6     weeks 14


          0             3                                              14
                 A                                                              E 19
Start         3 weeks                                                        5 weeks      End
          0             3                                               14         19

                                           3             9
                                                  D
                                               6 weeks
                                           8             14




                                                        What is the float of Activities
        Float= LS-ES        OR   Float=LF-EF            A, B, C, D and E?



                                                                                           13
   Fast Tracking
    • Doing critical path activities in parallel
   Crashing
    • Adding more resources to complete the activities.
   Reduce scope
   Cut quality
Fast Tracking                 Crashing

   Add risk                      Add cost
   May add project               May add project
    management time                management time


 Reduce scope                 Cut Quality
       Could save cost and       Could save cost
        time                       and resources
       May negatively            May increase risk
        impact customer
        satisfaction
Drop us a note. Your
feedbacks are valuable
        to us!
   Provide PMP, Agile & Scrum training
   Provide face to face and online training of PMI-ACP (Agile
    Certified Practitioner) certification program
   Help Organizations in adapting agile
   Helps organizations in setting up project governing office.
   Get training calendar at www.iZenBridge.com
Saket Bansal
Saket.Bansal@iZenBridge.com
M: 9910802561
Web: www.iZenBridge.com
LinkedIn: www.linkedin.com/in/saketbansal
Keep in touch for
more interesting
  & interactive
 presentations
Presentation by –
      Manish Purwar
    Contact Manish at
 Mobile : +91 9910500922
purwar_manish@yahoo.com

Weitere ähnliche Inhalte

Andere mochten auch

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
Nicola2903
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagram
nelramlawy
 
Cpa & pert charts
Cpa & pert chartsCpa & pert charts
Cpa & pert charts
Golban Oana
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
popik25
 

Andere mochten auch (17)

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path AnalysisLesson in Feasibility Study- Critical Path method, Critical Path Analysis
Lesson in Feasibility Study- Critical Path method, Critical Path Analysis
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...
 
Network Diagrams
Network DiagramsNetwork Diagrams
Network Diagrams
 
The Project's Network Diagram
The Project's Network DiagramThe Project's Network Diagram
The Project's Network Diagram
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
Constructing a network diagram
Constructing a network diagramConstructing a network diagram
Constructing a network diagram
 
3.time management
3.time management3.time management
3.time management
 
Week 3 inspiration and empathy
Week 3 inspiration and empathyWeek 3 inspiration and empathy
Week 3 inspiration and empathy
 
Cpa & pert charts
Cpa & pert chartsCpa & pert charts
Cpa & pert charts
 
Critical path analysis
Critical path analysisCritical path analysis
Critical path analysis
 
Monte Carlo Statistical Methods
Monte Carlo Statistical MethodsMonte Carlo Statistical Methods
Monte Carlo Statistical Methods
 
5.communication management
5.communication management5.communication management
5.communication management
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 

Critical path analysis for pmp exam

  • 2. How to create Network diagram?  How to find out Critical Path?  Finding out float of an activity  Schedule compression techniques
  • 3. Understanding of critical path analysis & schedule compression techniques  Will help in managing projects better in real life  Will help in solving 10 to 15 questions in PMP exam
  • 4. Activity A does not have any dependencies on other activities.  Activity B, can only be started once A is complete.  Activity C, can be started once B is complete.  Activity D can be started once A is complete.  Activity E can be started once C & D are complete.  Network diagram helps in visualizing the relative order and dependencies of these activities on each other.
  • 5. Precedence Diagramming Method (PDM) or Activity on Node (AON) • Network diagram shows dependencies • In PDM, boxes are used to show activities and arrows to show relationships. • Activities are put in the order they need to be performed • Network diagram is not concerned with when the activities will occur on the project timeline Activity Activity 2 1 End Start Activity 3
  • 6. Mandatory dependencies • Something MUST BE done before something else.  Discretionary dependencies • There is preferred method, or order, of performing the work.  External dependencies • Something outside the project must be done before a task in the project.
  • 7. Finish to Start (FS) : The successor can’t start before the predecessor has finished.  Start to Start (SS) : The successor can’t start before the predecessor has started.  Finish to Finish (FF) : The successor can’t finish before the predecessor has finished.  Start to Finish (SF) : The successor can’t finish before the predecessor has started. It is rarely used.  Finish to Start is most commonly used relationship. Finish to Start Start to Start Finish to Finish Dig a Finish testing Plant tree Start design hole Finish documentation After 2 weeks, start coding
  • 8. 3 weeks 8 weeks 3 6 6 14 B C 3 6 6 14 3 weeks 5 weeks 0 3 14 19 Start A E End 0 3 6 weeks 14 19 3 9 D 8 14 8
  • 9. Longest duration path in a Network Diagram  It is the shortest time to complete the project  It helps to determine the focus for project management efforts  Near critical path is close in duration to critical path  Closer the near critical and critical paths are, the more risk project has
  • 10. 3 weeks 8 weeks 3 6 6 14 B C 3 6 6 14 3 weeks 5 weeks 0 3 14 19 Start A E End 0 3 6 weeks 14 19 3 9 D 8 14 Start, A, B, C, E, End or Start, A, D, E, End 10
  • 11. Total Float (slack) • The amount of time an activity can be delayed with out delaying project end date.  Project Float (slack) • Amount of time project can be delayed with out delaying externally imposed project completion date.  Critical path activities have zero float.  Knowing float helps in better allocation of resources.  If project is behind an imposed external date, then project will have negative float.
  • 12. ES EF Forward Pass Backward LS LF Pass ES : Early Start LS : Late Start Float = LS-ES OR Float = LF-EF EF : Early Finish LF : Late Finish ES and EF are calculated by Forward Pass. LS and LF are calculated by Backward Pass. 12
  • 13. 3 6 6 14 B C 3 weeks 8 3 6 6 weeks 14 0 3 14 A E 19 Start 3 weeks 5 weeks End 0 3 14 19 3 9 D 6 weeks 8 14 What is the float of Activities Float= LS-ES OR Float=LF-EF A, B, C, D and E? 13
  • 14. Fast Tracking • Doing critical path activities in parallel  Crashing • Adding more resources to complete the activities.  Reduce scope  Cut quality
  • 15. Fast Tracking Crashing  Add risk  Add cost  May add project  May add project management time management time Reduce scope Cut Quality  Could save cost and  Could save cost time and resources  May negatively  May increase risk impact customer satisfaction
  • 16. Drop us a note. Your feedbacks are valuable to us!
  • 17. Provide PMP, Agile & Scrum training  Provide face to face and online training of PMI-ACP (Agile Certified Practitioner) certification program  Help Organizations in adapting agile  Helps organizations in setting up project governing office.  Get training calendar at www.iZenBridge.com
  • 18. Saket Bansal Saket.Bansal@iZenBridge.com M: 9910802561 Web: www.iZenBridge.com LinkedIn: www.linkedin.com/in/saketbansal
  • 19. Keep in touch for more interesting & interactive presentations
  • 20. Presentation by – Manish Purwar Contact Manish at Mobile : +91 9910500922 purwar_manish@yahoo.com