Question bank on Stakeholder Management PMBOK-5
1. Project stakeholder management includes all of the following except
a. Identify the people, groups, or organizations that could impact or be
impacted by the project.
b. Analyze stakeholder expectations and their impact on the project.
c. Develop appropriate management strategy for effectively engaging
stakeholders in project decisions and execution.
d. Develop strategies to avoid the incorporation of changes suggested by
the stakeholders.
2. Project stakeholder management focuses on
a. Continuous communication with the stakeholders to understand their
needs and expectations.
b. Addressing issues as they occur.
c. Managing conflicting interests.
d. Fostering appropriate stakeholder engagement in project decisions
and activities.
e. All of the above.
3. What should be the key project objective?
a. Completion of project within schedule and time.
b. Avoid scope changes in the project.
c. Stakeholder satisfaction
d. Completion of project within cost.
4. The process of identifying the people ,groups, or organizations that could
impact or be impacted by a decision ,activity, or outcome of the project
and analyzing and documenting relevant information regarding their
interests,involvement,interdependencies, influence and potential impact
on the project is
a. Control Stakeholder Management
b. Manage stakeholder Engagement
c. Identify stakeholders
d. Stakeholder Analysis.
5. The process of development of appropriate management strategies to
effectively engage stakeholders throughout the project lifecycle, based on
analysis of their needs, interests and potential impact on project success.
a. Control stakeholder Management
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder engagement.
6. The process of communicating and working with stakeholders to meet
their needs and expectations, address issues as they occur, and foster
appropriate stakeholders engagement in project activities throughout
the project lifecycle is called
a. Control stakeholder engagement
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder Engagement.
7. The process of monitoring overall project stakeholder relationships and
adjusting strategies and plans for engaging stakeholders is called
a. Control stakeholder engagement
b. Manage stakeholder engagement
c. Plan stakeholder management
d. Control stakeholder engagement.
8. Which of the following is not input to the Identify stakeholders process
a. Project charter
b. Project documents
c. Procurement documents
d. Organizational process assets
e. Enterprise environmental factors.
9. Which of the following is not a tool & technique for the Identify
stakeholder’s process?
a. Stakeholders analysis
b. Expert judgment
c. Meetings
d. Analytical techniques.
10. Stakeholder register is an input to all of the following except
a. Collect requirements.
b. Plan quality management.
c. Plan communication management & Control Communications.
d. Plan risk management & identify risks.
11. Project charter provides information about
a. Internal & external parties related with the project
b. Parties affected by the result or the execution of the project
c. Groups or departments participating in the project
d. Other people or organizations affected by the project
e. All of the above.
12. All of the following are EEF except
a. Organizational Culture and structure
b. Govt. or industry standards
c. Global regional or local trends
d. Stakeholders register from other projects.
13. All of the following are OPA except
a. Stakeholders register templates
b. Lessons learnt from previous projects
c. Stakeholders register from previous projects
d. Organizational culture and structure.
14. Which of the following are not classification model for stakeholder analysis
a. Power /interest grid model.
b. Power/influence grid model.
c. Influence /Impact grid model.
d. Influence/Interest grid model.
15. Salience Model of classification of the stakeholders focuses on
a. Classifying the stakeholders based on their level of authority and level
of concern regarding the project outcomes.
b. Classifying the stakeholders based on their active involvement and
the level of authority.
c. Classifying the stakeholders on the basis of their active involvement
in the project and their ability to effect changes to the project
planning and execution.
d. Classifying the stakeholders based on their power, urgency, and
legitimacy.
16. If a stakeholder has High power and high interest in the project then
a. Monitor them
b. Keep them informed
c. Keep them satisfied
d. Manage closely
17. If a stakeholder has high interest in the project and low power then
a. Monitor them.
b. Keep them informed.
c. Keep them satisfied.
d. Manage them closely.
18.If a stakeholder has high power and low interest in the project then
a. Monitor them
b. Keep them informed
c. Manage them closely
d. Keep them satisfied.
19. The stakeholders register contains all details related to the identified
stakeholders except
a. Identification information-Name, Organization, position, location, role
in the project, contact information.
b. Assessment information-Major requirements, main expectations,
potential influence in the phase in the lifecycle with the most interest.
c. Stakeholder classification-Internal/external,
supporter/neutral/resister.
d. Stakeholder management plan.
Note-The key benefit of plan stakeholder management is that it gives clear
actionable plan to interact with project stakeholders.
20. All of the following are the inputs to the Plan stakeholders management
process except
a. Project management plan
b. Stakeholders register
c. EEF
d. OPA
e. Project documents
21. All of the following are the tools and techniques of Plan stakeholder
management except
a. Expert judgment
b. Meetings
c. Stakeholder analysis
d. Analytical techniques
22. Which of the following is the output of the plan stakeholder
management process
a. OPA updates
b. EEF updates
c. Project document updates
d. Project management plan updates.
23. As input to the plan stakeholder management project management plan
provides all of the following except
a. Life cycle selected for the project and the processes that will be
applied to each phase.
b. Description of how work will be executed to achieve project objectives
c. Description of how human resources requirements will be met how
roles and responsibilities reporting relationships and staffing
management plan will be addressed and structured in the project.
d. How stakeholder register will be updated.
e. How change management plan will be implemented.
f. Need and techniques for communications among stakeholders.
24. Expert judgment can be obtained though
a. One to one meetings
b. Interviews
c. Focus groups
d. Surveys
e. All of the above
25. The stakeholder management plan provides the following information
a. Desired and current engagement levels of the key stakeholders
b. Scope and impact of changes to stakeholders
c. Identified interrelationships and potential overlap between
stakeholders.
d. Stakeholder’s communication requirements for the current project
phase.
e. All of the above.
26. The stakeholder management plan provides the following information
a. Information’s to be distributed to stakeholders
b. Reason for the distribution of a particular information
c. Time frame and the frequency for the information to be distributed.
d. Method for updating and refining the stakeholder management plan
e. All of the above.
27. The stakeholder management plan is an input to which of the following
process
a. Collect requirements
b. Control Stakeholder engagement
c. Plan procurement management
d. Plan risk management
28.All of the following are inputs to the manage stakeholder engagement
process except
a. SH engagement plan
b. Communications management plan
c. Change request
d. Organizational process assets.
29.Which of the following is not T&T for the manage SH engagement process
a. Communication skills
b. Interpersonal skills
c. Management skills
d. Communication methods
30. Which of the following is not an output of the manage stakeholder
engagement
a. Stakeholder management plan updates
b. OPA updates
c. Project documents updates
d. Project management plan updates.
31Issue log is an input to all of the following process except
a. Control stakeholder engagement
b. Manage project team
c. Control communications
d. Develop project management plan.
32 Stakeholder management plan provides the following
a. Guidance on how the various stake holders will be involved in the
project.
b. It provides the methods and technologies used in the stakeholder
communication.
c. Used to determine the level of interactions of various stakeholders.
d. It helps define the strategy for identifying and managing stakeholders
throughout the project lifecycle.
e. All of the above.
33. The communication management plan provides
a. Stakeholder’s communication requirements.
b. Information to be communicated including the language, format, and
content and level of detail.
c. Reason for distribution of information.
d. Person and groups who will receive information
e. Escalation process
f. All the above.
34. All of the following are Organizational process assets except
a. Organizational communication requirements.
b. Issue management procedures.
c. Change control procedures.
d. Historical information about previous projects.
e. All of the above.
35. The OPA updates includes
a. Stakeholders notifications
b. Project reports
c. Project presentations
d. Project records
e. Feedback from stakeholders & Lessons learnt.
f. All of the above
36. The primary observations and measurements identified during
activities being performed to carry out the project work is called
a. Reported %of work completed.
b. Work performance data.
c. Work performance information.
d. Work performance Index.
37. Project documents which are used as input to the control stakeholder
management process are
a. Project schedule
b. Stakeholder register
c. Issues log
d. Change log
e. Project communications
f. All of the above.
38. All of the following are examples of work performance information
except
a. Status of deliverables
b. Implementation status of change requests
c. Forecasted estimates to compete
d. Number of change requests.
Note- The recommended corrective actions include changes that bring the
expected future performance in line with the project management plan.
The recommended preventive actions can reduce the probability of future
negative project performance.
39. OPA updates includes updates on stakeholder notifications, project
reports, project presentation, Feedback from stakeholders, lessons learnt
documentation.
Answers
Q.No Answers Q.No Answers Q.No Answers Q.No Answers
1 D 11 E 21 C 31 D
2 E 12 D 22 C 32 E
3 C 13 D 23 A 33 F
4 C 14 D 24 E 34 E
5 C 15 D 25 E 35 F
6 B 16 D 26 E 36 B
7 A 17 B 27 A 37 F
8 B 18 D 28 C 38 D
9 D 19 D 29 A
10 C 20 E 30 A
Stakeholder management qb
Stakeholder management qb

Weitere ähnliche Inhalte

Was ist angesagt?

Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksSudharsan Purushothaman
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 
Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Agus Suhanto
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answersMohamed Saeed
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management examJamil Faraj , PMP
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6Amit Gupta
 
Project Status Report PowerPoint Template.pptx
Project Status Report PowerPoint Template.pptxProject Status Report PowerPoint Template.pptx
Project Status Report PowerPoint Template.pptxBALASUBRAMANIAM IYER
 
Project managent communication
Project managent communicationProject managent communication
Project managent communicationAmbr Malyk
 
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfP2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfAnne Starr
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewAnand Bobade
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaJoshua Render
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality ManagementDavidMcLachlan1
 
Costing_Actual spendings & pricing
Costing_Actual spendings & pricingCosting_Actual spendings & pricing
Costing_Actual spendings & pricingAjinkya Deshpande
 
Presentation on assumption log in Project Management by MM Rahman
Presentation on assumption log in Project Management by MM RahmanPresentation on assumption log in Project Management by MM Rahman
Presentation on assumption log in Project Management by MM RahmanSTM-Skill That Matters
 

Was ist angesagt? (20)

Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folks
 
Pmp2
Pmp2Pmp2
Pmp2
 
Scheduling
SchedulingScheduling
Scheduling
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 
Project Scope Management
Project Scope ManagementProject Scope Management
Project Scope Management
 
Project Communications Management - PMBOK6
Project Communications Management - PMBOK6Project Communications Management - PMBOK6
Project Communications Management - PMBOK6
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 
How to start primavera p6
How to start primavera p6How to start primavera p6
How to start primavera p6
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
PMP as per PMBOK 6
PMP as per PMBOK 6PMP as per PMBOK 6
PMP as per PMBOK 6
 
Project Status Report PowerPoint Template.pptx
Project Status Report PowerPoint Template.pptxProject Status Report PowerPoint Template.pptx
Project Status Report PowerPoint Template.pptx
 
Project managent communication
Project managent communicationProject managent communication
Project managent communication
 
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadfP2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
P2fdumps_2021_71304130-dc2f-4f28-955d-be322d25dadf
 
PMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management OverviewPMP Chap 13 - Project stakeholder management Overview
PMP Chap 13 - Project stakeholder management Overview
 
Project Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge AreaProject Management: Integration Management Knowledge Area
Project Management: Integration Management Knowledge Area
 
8.1 Plan Quality Management
8.1 Plan Quality Management8.1 Plan Quality Management
8.1 Plan Quality Management
 
Costing_Actual spendings & pricing
Costing_Actual spendings & pricingCosting_Actual spendings & pricing
Costing_Actual spendings & pricing
 
Presentation on assumption log in Project Management by MM Rahman
Presentation on assumption log in Project Management by MM RahmanPresentation on assumption log in Project Management by MM Rahman
Presentation on assumption log in Project Management by MM Rahman
 

Ähnlich wie Stakeholder management qb

Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxwkyra78
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyHarry White
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64Skillogic Solutions
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder ManagementSanjay Rajpoot
 
is not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdfis not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdfaristogifts99
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxEJINAABEGAILJASMINEA
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questionsAnirban Chakraborty
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docxtienmixon
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.docAhsanRahman13
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxclarebernice
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxcurwenmichaela
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxjasoninnes20
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekOSP International LLC
 

Ähnlich wie Stakeholder management qb (20)

Pmp stakeholder chapter 13
Pmp stakeholder chapter 13Pmp stakeholder chapter 13
Pmp stakeholder chapter 13
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
 
Liberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers keyLiberty university busi 313 quiz 1 complete solutions correct answers key
Liberty university busi 313 quiz 1 complete solutions correct answers key
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
Free CAPM Exam Sample Question
Free CAPM Exam Sample QuestionFree CAPM Exam Sample Question
Free CAPM Exam Sample Question
 
CAPM Sample Q and A
CAPM Sample Q and ACAPM Sample Q and A
CAPM Sample Q and A
 
SERVICES DELIVERY
SERVICES DELIVERYSERVICES DELIVERY
SERVICES DELIVERY
 
10. Stakeholder Management
10. Stakeholder Management10. Stakeholder Management
10. Stakeholder Management
 
Project charter template
Project charter templateProject charter template
Project charter template
 
is not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdfis not one of the stages of a project life cycle 6. Which of the fol.pdf
is not one of the stages of a project life cycle 6. Which of the fol.pdf
 
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptxMANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
MANAGEMENT-OF-COMMUNITY-IMMERSION.pptx
 
Project evaluation and implementation notes and questions
Project evaluation and implementation   notes and questionsProject evaluation and implementation   notes and questions
Project evaluation and implementation notes and questions
 
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
(Enter your answers on the enclosed answer sheet)1. A humanis an e.docx
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.doc
 
Communications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docxCommunications Management Plan Templatewww.ProjectManagementDo.docx
Communications Management Plan Templatewww.ProjectManagementDo.docx
 
BSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docxBSBPMG522 Undertake project work1HousekeepingE.docx
BSBPMG522 Undertake project work1HousekeepingE.docx
 
BSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docxBSBPMG522 Undertake project work1Housekeeping.docx
BSBPMG522 Undertake project work1Housekeeping.docx
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 

Kürzlich hochgeladen

Dubai Call Girls Kiki O525547819 Call Girls Dubai Koko
Dubai Call Girls Kiki O525547819 Call Girls Dubai KokoDubai Call Girls Kiki O525547819 Call Girls Dubai Koko
Dubai Call Girls Kiki O525547819 Call Girls Dubai Kokokojalkojal131
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...poojakaurpk09
 
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men 🔝Bulandshahr🔝 ...
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men  🔝Bulandshahr🔝  ...➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men  🔝Bulandshahr🔝  ...
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men 🔝Bulandshahr🔝 ...amitlee9823
 
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...rightmanforbloodline
 
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...amitlee9823
 
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...amitlee9823
 
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...amitlee9823
 
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...robinsonayot
 
Presentation for the country presentation
Presentation for the country presentationPresentation for the country presentation
Presentation for the country presentationjalal879
 
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night StandCall Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...sonalitrivedi431
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...amitlee9823
 
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)amitlee9823
 
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men 🔝Mirzapur🔝 Escor...
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men  🔝Mirzapur🔝   Escor...➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men  🔝Mirzapur🔝   Escor...
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men 🔝Mirzapur🔝 Escor...amitlee9823
 
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men 🔝Tirupati🔝 Escor...
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men  🔝Tirupati🔝   Escor...➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men  🔝Tirupati🔝   Escor...
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men 🔝Tirupati🔝 Escor...amitlee9823
 
Resumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying OnlineResumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying OnlineBruce Bennett
 
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...amitlee9823
 
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night StandCall Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 

Kürzlich hochgeladen (20)

Dubai Call Girls Kiki O525547819 Call Girls Dubai Koko
Dubai Call Girls Kiki O525547819 Call Girls Dubai KokoDubai Call Girls Kiki O525547819 Call Girls Dubai Koko
Dubai Call Girls Kiki O525547819 Call Girls Dubai Koko
 
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
Virgin Call Girls Delhi Service-oriented sexy call girls ☞ 9899900591 ☜ Rita ...
 
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men 🔝Bulandshahr🔝 ...
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men  🔝Bulandshahr🔝  ...➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men  🔝Bulandshahr🔝  ...
➥🔝 7737669865 🔝▻ Bulandshahr Call-girls in Women Seeking Men 🔝Bulandshahr🔝 ...
 
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...
TEST BANK For An Introduction to Brain and Behavior, 7th Edition by Bryan Kol...
 
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Chikkabanavara Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
 
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...
Chintamani Call Girls Service: ☎ 7737669865 ☎ High Profile Model Escorts | Ba...
 
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men  🔝Nandyal🔝   Escorts...
➥🔝 7737669865 🔝▻ Nandyal Call-girls in Women Seeking Men 🔝Nandyal🔝 Escorts...
 
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
TEST BANK For Evidence-Based Practice for Nurses Appraisal and Application of...
 
Presentation for the country presentation
Presentation for the country presentationPresentation for the country presentation
Presentation for the country presentation
 
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night StandCall Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Devanahalli ☎ 7737669865 🥵 Book Your One night Stand
 
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
Hyderabad 💫✅💃 24×7 BEST GENUINE PERSON LOW PRICE CALL GIRL SERVICE FULL SATIS...
 
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
Call Girls Bommanahalli Just Call 👗 7737669865 👗 Top Class Call Girl Service ...
 
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)
Call Girls Bidadi ☎ 7737669865☎ Book Your One night Stand (Bangalore)
 
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Bidadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men 🔝Mirzapur🔝 Escor...
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men  🔝Mirzapur🔝   Escor...➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men  🔝Mirzapur🔝   Escor...
➥🔝 7737669865 🔝▻ Mirzapur Call-girls in Women Seeking Men 🔝Mirzapur🔝 Escor...
 
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men 🔝Tirupati🔝 Escor...
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men  🔝Tirupati🔝   Escor...➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men  🔝Tirupati🔝   Escor...
➥🔝 7737669865 🔝▻ Tirupati Call-girls in Women Seeking Men 🔝Tirupati🔝 Escor...
 
Resumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying OnlineResumes, Cover Letters, and Applying Online
Resumes, Cover Letters, and Applying Online
 
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
Nandini Layout Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangal...
 
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Alandi Road Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night StandCall Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Kengeri Satellite Town ☎ 7737669865 🥵 Book Your One night Stand
 

Stakeholder management qb

  • 1. Question bank on Stakeholder Management PMBOK-5 1. Project stakeholder management includes all of the following except a. Identify the people, groups, or organizations that could impact or be impacted by the project. b. Analyze stakeholder expectations and their impact on the project. c. Develop appropriate management strategy for effectively engaging stakeholders in project decisions and execution. d. Develop strategies to avoid the incorporation of changes suggested by the stakeholders. 2. Project stakeholder management focuses on a. Continuous communication with the stakeholders to understand their needs and expectations. b. Addressing issues as they occur. c. Managing conflicting interests. d. Fostering appropriate stakeholder engagement in project decisions and activities. e. All of the above. 3. What should be the key project objective? a. Completion of project within schedule and time. b. Avoid scope changes in the project. c. Stakeholder satisfaction d. Completion of project within cost. 4. The process of identifying the people ,groups, or organizations that could impact or be impacted by a decision ,activity, or outcome of the project and analyzing and documenting relevant information regarding their interests,involvement,interdependencies, influence and potential impact on the project is a. Control Stakeholder Management
  • 2. b. Manage stakeholder Engagement c. Identify stakeholders d. Stakeholder Analysis. 5. The process of development of appropriate management strategies to effectively engage stakeholders throughout the project lifecycle, based on analysis of their needs, interests and potential impact on project success. a. Control stakeholder Management b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder engagement. 6. The process of communicating and working with stakeholders to meet their needs and expectations, address issues as they occur, and foster appropriate stakeholders engagement in project activities throughout the project lifecycle is called a. Control stakeholder engagement b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder Engagement. 7. The process of monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders is called a. Control stakeholder engagement b. Manage stakeholder engagement c. Plan stakeholder management d. Control stakeholder engagement. 8. Which of the following is not input to the Identify stakeholders process a. Project charter b. Project documents c. Procurement documents d. Organizational process assets e. Enterprise environmental factors.
  • 3. 9. Which of the following is not a tool & technique for the Identify stakeholder’s process? a. Stakeholders analysis b. Expert judgment c. Meetings d. Analytical techniques. 10. Stakeholder register is an input to all of the following except a. Collect requirements. b. Plan quality management. c. Plan communication management & Control Communications. d. Plan risk management & identify risks. 11. Project charter provides information about a. Internal & external parties related with the project b. Parties affected by the result or the execution of the project c. Groups or departments participating in the project d. Other people or organizations affected by the project e. All of the above. 12. All of the following are EEF except a. Organizational Culture and structure b. Govt. or industry standards c. Global regional or local trends d. Stakeholders register from other projects. 13. All of the following are OPA except a. Stakeholders register templates b. Lessons learnt from previous projects c. Stakeholders register from previous projects d. Organizational culture and structure.
  • 4. 14. Which of the following are not classification model for stakeholder analysis a. Power /interest grid model. b. Power/influence grid model. c. Influence /Impact grid model. d. Influence/Interest grid model. 15. Salience Model of classification of the stakeholders focuses on a. Classifying the stakeholders based on their level of authority and level of concern regarding the project outcomes. b. Classifying the stakeholders based on their active involvement and the level of authority. c. Classifying the stakeholders on the basis of their active involvement in the project and their ability to effect changes to the project planning and execution. d. Classifying the stakeholders based on their power, urgency, and legitimacy. 16. If a stakeholder has High power and high interest in the project then a. Monitor them b. Keep them informed c. Keep them satisfied d. Manage closely 17. If a stakeholder has high interest in the project and low power then a. Monitor them. b. Keep them informed. c. Keep them satisfied. d. Manage them closely. 18.If a stakeholder has high power and low interest in the project then a. Monitor them b. Keep them informed c. Manage them closely d. Keep them satisfied.
  • 5. 19. The stakeholders register contains all details related to the identified stakeholders except a. Identification information-Name, Organization, position, location, role in the project, contact information. b. Assessment information-Major requirements, main expectations, potential influence in the phase in the lifecycle with the most interest. c. Stakeholder classification-Internal/external, supporter/neutral/resister. d. Stakeholder management plan. Note-The key benefit of plan stakeholder management is that it gives clear actionable plan to interact with project stakeholders. 20. All of the following are the inputs to the Plan stakeholders management process except a. Project management plan b. Stakeholders register c. EEF d. OPA e. Project documents 21. All of the following are the tools and techniques of Plan stakeholder management except a. Expert judgment b. Meetings c. Stakeholder analysis d. Analytical techniques 22. Which of the following is the output of the plan stakeholder management process a. OPA updates b. EEF updates c. Project document updates d. Project management plan updates.
  • 6. 23. As input to the plan stakeholder management project management plan provides all of the following except a. Life cycle selected for the project and the processes that will be applied to each phase. b. Description of how work will be executed to achieve project objectives c. Description of how human resources requirements will be met how roles and responsibilities reporting relationships and staffing management plan will be addressed and structured in the project. d. How stakeholder register will be updated. e. How change management plan will be implemented. f. Need and techniques for communications among stakeholders. 24. Expert judgment can be obtained though a. One to one meetings b. Interviews c. Focus groups d. Surveys e. All of the above 25. The stakeholder management plan provides the following information a. Desired and current engagement levels of the key stakeholders b. Scope and impact of changes to stakeholders c. Identified interrelationships and potential overlap between stakeholders. d. Stakeholder’s communication requirements for the current project phase. e. All of the above. 26. The stakeholder management plan provides the following information a. Information’s to be distributed to stakeholders b. Reason for the distribution of a particular information c. Time frame and the frequency for the information to be distributed. d. Method for updating and refining the stakeholder management plan e. All of the above.
  • 7. 27. The stakeholder management plan is an input to which of the following process a. Collect requirements b. Control Stakeholder engagement c. Plan procurement management d. Plan risk management 28.All of the following are inputs to the manage stakeholder engagement process except a. SH engagement plan b. Communications management plan c. Change request d. Organizational process assets. 29.Which of the following is not T&T for the manage SH engagement process a. Communication skills b. Interpersonal skills c. Management skills d. Communication methods 30. Which of the following is not an output of the manage stakeholder engagement a. Stakeholder management plan updates b. OPA updates c. Project documents updates d. Project management plan updates. 31Issue log is an input to all of the following process except a. Control stakeholder engagement b. Manage project team c. Control communications d. Develop project management plan. 32 Stakeholder management plan provides the following a. Guidance on how the various stake holders will be involved in the project.
  • 8. b. It provides the methods and technologies used in the stakeholder communication. c. Used to determine the level of interactions of various stakeholders. d. It helps define the strategy for identifying and managing stakeholders throughout the project lifecycle. e. All of the above. 33. The communication management plan provides a. Stakeholder’s communication requirements. b. Information to be communicated including the language, format, and content and level of detail. c. Reason for distribution of information. d. Person and groups who will receive information e. Escalation process f. All the above. 34. All of the following are Organizational process assets except a. Organizational communication requirements. b. Issue management procedures. c. Change control procedures. d. Historical information about previous projects. e. All of the above. 35. The OPA updates includes a. Stakeholders notifications b. Project reports c. Project presentations d. Project records e. Feedback from stakeholders & Lessons learnt.
  • 9. f. All of the above 36. The primary observations and measurements identified during activities being performed to carry out the project work is called a. Reported %of work completed. b. Work performance data. c. Work performance information. d. Work performance Index. 37. Project documents which are used as input to the control stakeholder management process are a. Project schedule b. Stakeholder register c. Issues log d. Change log e. Project communications f. All of the above. 38. All of the following are examples of work performance information except a. Status of deliverables b. Implementation status of change requests c. Forecasted estimates to compete d. Number of change requests. Note- The recommended corrective actions include changes that bring the expected future performance in line with the project management plan. The recommended preventive actions can reduce the probability of future negative project performance.
  • 10. 39. OPA updates includes updates on stakeholder notifications, project reports, project presentation, Feedback from stakeholders, lessons learnt documentation. Answers Q.No Answers Q.No Answers Q.No Answers Q.No Answers 1 D 11 E 21 C 31 D 2 E 12 D 22 C 32 E 3 C 13 D 23 A 33 F 4 C 14 D 24 E 34 E 5 C 15 D 25 E 35 F 6 B 16 D 26 E 36 B 7 A 17 B 27 A 37 F 8 B 18 D 28 C 38 D 9 D 19 D 29 A 10 C 20 E 30 A