PROGRESS REPORT OF ACCOMPLISHMENTS
                             FOR THE PERIOD OF: JANUARY – DECEMBER 2010

                                                 REGION: VII


1.0. INTRODUCTION

          The Regional Office needs to strategically respond to the requirements of the R.A. 9155 thus
paving the way to the restructuring of the Regional Offices with much clearer roles and functions. Through
its unified education development plan, it provides directions to the functional divisions’ initiatives toward
the attainment of its goals & objectives. Given this, a Regional Monitoring and Evaluation Framework is
made to serve as a roadmap towards bringing the region to a culture of quality and accountability as an
organization.

        With the present framework serving an organizational M&E for the region, its purpose for
monitoring and evaluation is to provide objective information that can inform decision-making for
continuously improving its Organizational performance for efficient and effective fulfillment of the regional
mandate, and Delivery of education services to achieve the desired outputs and sustainability of Education
Outcomes.

         The monitoring and evaluation report is aimed to establish information as basis for determining
appropriate approach / strategy to improve organizational performance in fulfillment of the regional
mandate and strengthen collective actions to service better the divisions and schools within the
accountability of the Region and present information regarding organization resource support to the region
management that will support decisions and adjustments to plans (e.g. budget, personnel, physical facilities
plan) and strategies to ensure appropriate allocation of resources to support performance efficiency and
effectiveness.


2.0. SCOPE

         With the implementation framework of the system now in place and accepted by the Regional
Management, an important part of the process is its implementation. The three - day live-out pilot RMEA
was conducted and quantitative and qualitative information per RO unit were gathered, analyzed,
interpreted and to be presented to the Regional Management. Necessary adjustments on the Work plan of
every functional division/RO unit has to be done.

         The coverage of the Monitoring and Evaluation report is from January to December 2010 as
indicated in the Work Plan of every Functional division and RO Unit. The focus of this report is on area on
Organizational Performance/Health along its Organizational Effectiveness which pertains to individual,
team and organizational effectiveness of the region. Outputs achieved per individual RO Unit and those
co-implemented by at least 2 or more RO units, Implementation Issues of each regional unit/functional
division regarding work plan implementation, Institutional issues that involves multiple functional divisions

                                                                                                             1
and Lessons Learned are tracked down while Organizational Resource Support concerns mainly with
availability and adequacy of resource requirements for the region to carry out its mandate efficiently and
effectively. This includes the analysis of how the region best optimizes its financial, human and
organizational capabilities in performing its functions by individual units and as a team.

3.0. METHODOLOGY

        The three - day live-out pilot RMEA was conducted following the STRIVE RMEA technology .
Purposely it was conducted for the participants to have established quantitative information on the
accomplishment of every RO unit, identified and clarified issues encountered and lessons learned and
adjusted the work plan of each Functional division/RO unit.

        Pre-work activity was done before the conduct of RMEA to gather initial reports on Physical
Accomplishment of every RO unit. QAAD personnel assigned in every RO unit made visit to the different
offices and did actual data collection on quantitative and qualitative information. Internal M & E was
designated in every RO unit. Tools were given for easy data collection following established standards.

        The actual conduct of RMEA took place on December 16-18, 2010 at DepED, Ecotech Center,
Cebu City. Each QAAD personnel was given assignment on what RO Unit to facilitate for easy data
gathering, analysis and interpretation using the recommended tools : CLMD by Dr. Estela B. Susvilla, T and
DD and RMSPPD by Dr. Joy Kenneth Biasong, QAAD by Ms. Rosa Cabotaje, PPRD, BFD, and Admin by
Ms. Merden Bryant. Dr. Marcial Degamo acted as the over-all Chairman.

        Different sessions were handled by the QAAD personnel. Session I on Quantitative Information
was facilitated by Dr. Estela Susvilla, Session 2 , on Issues and Proposed Resolutions by Ms. Merden
Bryant, Session 3 on Lessons Learned by Ms. Rosa Cabotaje, Session 4 on Organizational Resources by
Dr. Marcial Degamo and Session 5 on Proposed Recommendations was handled Dr. Joy Kenneth
Biasong. After every presentation of the different sessions, workshop was conducted simultaneously.
Tools were given to gather and consolidate the data.


       In plenary, the following instructions were given for the simultaneous division/unit group work:
 Each functional division/unit must have a designated official documenter
 Based on the accomplished FD/Unit Output Matrix , compute the division/unit’s physical output using
  the Table 1-A: Physical Outputs (template) Show Table 1-A in PPT.
 In plenary, there will be a consolidation of the functional division /unit physical accomplishment. For
  this, Table 1-B: Status of the functional division /unit Physical Outputs will be used.
 Compute for the balance of physical outputs and identify reasons for variance.

        A physical output can only be credited if it meets standard/s and has MOV/s.

        The quantitative and qualitative information gathered were consolidated, analyzed and interpreted
and to be presented to the top management for actions and adjustments.

                                                                                                          2
4.0. Findings

4.1. Organizational Effectiveness

4.1.1 Expected outputs

Overall percentage of accomplishment of the region
         Fiscal year 2010 was a good year for Region 7. The regional structuring took place with a great
wave of change happening in the different regional offices/units as a pilot. Every functional division was
mandated to prepare a Work Plan indicating its goals and objectives, setting its targets covering the whole
year. Based on it, results on the pilot MEA revealed that the region had 83% performance which is
satisfactorily doing well despite of the inadequacies in terms of personnel, office equipment and other
resources of the newly structured regional office.
        As shown in the Table I below, Technical Assistance Division performed the highest, followed by
the Curriculum and Learning Management Division. Almost all of the Regional Divisions/Units showed
better performance as expected.
         The functional divisions showing relatively greater performance are the Planning, Policy and
Research Division, Resource Mobilization and Special Programs and Projects Division, Administrative
Division and Budget and Finance Division.


                                                                    Table I

                                     COMPUTED ACCOMPLISHED PHYSICAL OUTPUTS
                                                                                              # of           % of
                                                                                         Accomplished   Accomplishmen
                                RO UNIT                                   # of Targets      outputs           t
 FD 1: Curriculum and Learning Management Division                            25             23             92%
 FD 2: Training and Development Division                                       5              3             60%
 FD 3: Resource Mobilization and Special Programs and Projects Division       32             23             84%
 FD 4: Quality Assurance and Accountability Division                          15             11             73%
 FD 5: Technical Assistance Division                                          29             27             93%


 FD 6: Planning, Policy and Research Division                                  9              8             89%
 AD 1: Administrative Division                                                25             22             88%
 AD 2: Budget and Finance Division                                             6              5             83%
                  Regional Performance                                        146            122            83%




                                                                                                                        3
The performance of all functional divisions/units and the over-all performance of the region is shown in the
graph below.




Percentage of unaccomplished outputs
    There are only very few targeted outputs that were not accomplished during the SY 2010. The table
below shows that only 17% left unaccomplished and noted to be done this year. It shows that every
functional division/unit did their share of accomplishing their targets despite of the limited resources in the
region.

                    Table II - COMPUTED UNACCOMPLISHED PHYSICAL OUTPUTS
                                                                          # of
                                                           # of      Unaccomplished            % of
                     RO UNIT                             Targets        outputs           Accomplishment
 FD 1: Curriculum and Learning Management
 Division                                                  25                2                   8%
 FD 2: Training and Development Division                   5                 2                  40%
 FD 3: Resource Mobilization and Special
 Programs and Projects Division                            32                11                 34%
 FD 4: Quality Assurance and Accountability
 Division                                                  15                4                  27%
 FD 5: Technical Assistance Division                       29                2                   7%
 FD 6: Planning, Policy and Research Division              9                 1                  11%
 AD 1: Administrative Division                             25                3                  12%
 AD 2: Budget and Finance Division                         6                 1                  17%

                                                           146               26                 17%



                                                                                                               4
The unaccomplished outputs can be very well understood in the graph below.




REASONS FOR BALANCE
           Common reasons for the balances of outputs of FY 2010 were overlapping of activities and time
constraint. Failure to complete the targeted outputs is one of the considerations in the making of
adjustment Work Plan for this year 2011.


    4.1.2 Unexpected /Value Added Outputs

     Shown in the Table III below are the outputs which were not targeted in the Work Plan but were done
for some reasons that there were instructions from the top management to do so.
                                           Table III: VALUE-ADDED OUTPUTS

              RO UNIT                     VALUE-ADDED OUTPUTS                      REASONS FOR ACHIEVING THEM
                               Trained ______of Preschool Administrators and       Develop of preschool instructional
                               selected teachers                                   materials
          CLMD
                               Translated Grade I competencies for First Grading   In compliance to MTB-MLE program
                               period
                               Test Item Bank construction                         For the annual Regional Achievement
                                                                                   Test
                               Translated EPP competencies from Filipino to        To align the secondary TLE
                               English                                             competencies
                               Development of Supplementary materials for          Indigenization of curriculum
                               Elementary Science
                               Trained _____ first year teachers in UbD in 19      To enhance the secondary curriculum

                                                                                                                        5
divisions in all subject areas
       Trained _______ untrained elementary teachers       To enhance the reading competencies
       in NEPP training for all in 19 divisions            of elementary pupils and teaching
                                                           strategies in teaching reading
       Regional Search for Grade I teachers with zero      To give incentives/recognize their
       non-readers conducted                               efforts and inspire them to perform
                                                           better
       _____Number of Performing Schools visited           To give recognition for the
                                                           school/district/division
QAAD   Inter agency clean and green environment            Being ordered by RD
       monitoring of schools
       Process request for subject overload


       Monitoring and Evaluation of schools recipient of
       ESC /EVS schools
PPRD   Physical accomplishment report/agency               Needed report for the DBM
       performance review submitted to DBM
       Report Cards by Congressional Districts and         Networking between RO and DOs
       Municipalities of the entire region to 15
       Congressmen, mayors of component cities
       prepared, reproduced, and distributed
       Proposed Inputs to the Central Visayas
       Regional Development Plan for SY 2010-2016
       prepared
       Result Evaluation and Monitoring Matrix             High degree of work ethics
       prepared
       Enhanced Regional BIAP prepared and                 Networking beyond and among
       submitted to CO                                     stakeholders
       Physical Accomplishment Report/Agency
       Performance Review prepared and submitted to        Needed report by DBM
       DBM
       Maintenance of laptops and computers in the         ICT skills of one staff
       region done
       Minutes, Activities, and Reports of REXECOM         Being ordered by RD
       and EXECON covered and jot down
       BAC-TWG (Bids and Awards Committee –
       Technical Working Group) results evaluation
       done




                                                                                            6
RMSPPD         Endorsements of communications in cultural and    Stakeholders from NGOs, Private
                               arts, theaters and plays                          School Sectors

                               Eco Patrol International School Competition       Positive participation from the division
                               (Science School)
                                                                                 Awareness of the environment

                               Folk Dance and Balitaw Competition


                               NAMCYA National Competition


                               Palarong Pambansa 2011 Training of the Athletes
                                                                                 With funds from the stakeholders
                               on the process
                                                                                 (ABS-CBN and Aboitiz Foundation)
                               Orientation for the Sinulog sa Kabataan sa
                                                                                 Funds from the Sinulog Foundation
                               Lalawigan sa Sugbo


                               Conference Workshop of Winning Coaches, TFSS
                               and TMs




        4.1.3   Issues

          It has been found out that issues affecting organizational effectiveness include technical,
institutional, financial, social and environmental /infrastructure issues.
          For issues within the control of the Regional Office, the issue that greatly affects organizational
effectiveness is the overlapping of organic and Project-STRIVE-related activities. Because of this issue,
personnel have less time and less focus in accomplishing their tasks.

        The proposed resolutions to address this issue are as follows:

          Functional Division Personnel to coordinate with other functional and support divisions
          Functional and Support Divisions to prioritize their activities and hold regular staff meeting
          Regional Management to provide a Regional Activity Tracking Board where the functional and
           support divisions can post their activities within a month to help prevent overlapping of
           activities because every RO Unit can best be able to schedule their activities that would not
           conflict other activities

          Another salient issue that needs attention is that the personnel of Resource Mobilization Special
Programs and Projects Division (RMSPPD) find it hard to spearhead some programs and projects related
to academics because they lack the indispensable expertise in conceptual background both in content and
skills. Although they seek the necessary expertise from the CLMD personnel by coordinating with them,
they sometimes fail to get their help because they are also busy with their organic tasks. Indeed, the
overlapping of activities affects organizational effectiveness.




                                                                                                                       7
The proposed resolution is to request the Regional Director that programs and projects related to
academics shall be turned-over to the Curriculum and Learning Management Division (CLMD) and the
RMSPPD personnel shall only give their technical support.

        Lack of personnel, both technical and support staff, and lack of office equipment/facility like
computer units, laptops, copying machine, fax machine, internet facility, network printers, and LCD
projectors are the two most critical issues that need to be elevated to higher management and to external
stakeholders like the Department of Budget and Management.

        The insufficient number of personnel of functional and support divisions has significantly curtailed
the desired efficiency and effectiveness of these divisions with respect to time. Coupled with the
overlapping of activities, some workloads are worked on at a later time.

         The unavailability of office equipment like computer units, laptops, copying machines, and network
printers also prevents the fast-tracking of the processing of documents.

        Recording, tracking, consolidating, production, and reproduction of documents require plenty of
time when done manually and when necessary equipment are lacking. If computer units were available for
use by the technical and support staff in offices, these tasks would be done in a sophisticated manner,
thus, making the work much faster and easier.

         Table IV below shows the consolidated issues and resolutions by categories cut across the
different functional divisions/units.


                                   Table IV: Consolidated Issues and Proposed Resolutions

                                                                                                   ISSUES FOR
                                                                                                  ATTENTION OF
 CATEGORIES OF        ISSUES WITHIN THE UNIT’S                                                       HIGHER                PROPOSED RESOLUTION OR
                                                             PROPOSED RESOLUTION
    ISSUES                   CONTROL                                                             MANAGEMENT /              ACTION SOUGHT FROM MGT.
                                                                                                    EXTERNAL
                                                                                                 STAKEHOLDERS
                  Less focus and limited time to           Make a request to RD to provide
                  coordinate with RO Units accomplish      a Regional Activity Tracking
                  tasks due to overlapping of activities   Board where each functional
   TECHNICAL                                               division and RO Unit can post
                                                           their activities within a month to
                                                           prevent overlapping of activities.
                  Programs and projects related to         Make a request to RD that            Lack of technical and   Make a request to RD to follow up at
                  academics are endorsed to the            programs and projects related to     support staff across    the Central Office the authority to fill
                  RMSPPD when its personnel lack the       academics should be turned-over      RO Units due to the     vacant positions.
                  indispensable conceptual                 to Curriculum and Learning           Restructuring of        .Make a request to RD to refer to the
                  background.                              Management Division (CLMD).          Offices                 CO the need for the creation of
                                                                                                                        additional PSIPOP items
  INSTITUTIONAL                                                                                 Division personnel      .Make a request to RD to follow up at
                                                                                                are detailed in the     the Central Office the authority to fill
                                                                                                Regional Office to      vacant positions.
                                                                                                complement staffing     .Make a request to RD to refer to the
                                                                                                requirement.            CO the need for the creation of
                                                                                                                        additional PSIPOP items




                                                                                                                                                     8
Inadequate funding for some                  Request RD to allocate more
                   programs and projects especially in          funds to some programs and
                   sports activities and trainings              projects such sports activities and
                                                                training and to seek external            There are still
                                                                stakeholder financial support                                      Refer to Central Office that there are
                                                                                                         divisions requesting
    FINANCIAL                                                                                                                      still divions requesting for salary for
                                                                                                         for salary of
                                                                Make a request to the RD that                                      preschool teachers.
                   Some schools offering SPED Classes                                                    preschool teachers
                                                                items purchased by schools
                   include in their purchase for assistive      offering SPED Classes be
                   devices camera, refrigerator, and            included in FTA Monitoring
                   other equipment
                    Most functional divisions and regional        Make a request to RD that the              Most functional       Refer to Central Office that the
                    units lack office furniture/supplies like   office furniture/ supplies like filing   divisions and regional    restructuring of Regional Office VII
                     filing cabinets, working tables, filing    cabinets, working tables and filing          units lack office     gives rise to the need for functional
                                boxes, and CDs.                  boxes, and CDs be provided to           equipment/facility like   divisions/regional units office
                                                                     the offices needing them.               computer units,       equipment/facilities like computer
  ENVIRONMENTAL/                                                                                            laptops, copying       units, laptops, copying machine, fax
 INFRASTRUCTURE                                                                                                machine, fax        machine, internet facility, network
                                                                                                           machine, internet       printers, and LCD projector
                                                                                                             facility, network     DepED Region VII shall generate and
                                                                                                           printers, and LCD       mobilize resources from external
                                                                                                                projector.         stakeholders to procure the needed
                                                                                                                                   ICT equipment.
                    Renovation/ expansion of RMSPPD             Make a request to RD that the
                   Office so that there is proper               renovation/expansion of
                   coordination of medical team and             RMSPPD Office shall be
                   physical facilities team                     designed such that the Physical
                                                                Facilities and Medical Teams
                                                                shall already be accommodated
                                                                in one office.
                   Divisions that are not supportive of         Make a request to the RD to
                   programs and projects despite TA             discuss during EXECON the lack
     SOCIAL        provided , specifically NAMCYA               of support of some divisions to
                                                                programs and projects like
                                                                NAMCYA.


        4.1.4      Lessons Learned

          At the course of the implementation of the targets in the Work Plan of every functional division/unit
in the region for the FY 2010, lessons were generated. The lessons learned serve as part of the essential
considerations for plan adjustments in the following quarter/year. These could either be derived either from
the facilitating factors or hindering factors encountered during its implementation of the newly restructured
Regional Office. These may provide information on how the Functional Divisions can limit strategies for the
accomplishment of Work plans and highlight factors contributory to the targets.
         Table V below shows the facilitating, hindering factors and lessons learned of the functional
divisions/units which were noted down during the conduct of pilot RMEA.


                    Table V. FACILITATING/HINDERING FACTORS and LESSONS LEARNED

         FDs/ADMIN Units                       FACILITATING FACTORS                      HINDERING FACTORS                         LESSONS LEARNED

                                                                                                                             Technical Staff performed
                                             All Technical are                       Conflicting Schedule                    well despite of their of their
                                             computer literate                                                               status of employment

                                             Render Service beyond                   Lack of support staff                   Full time Technical Staff
                                             office hours even without                                                       have greater outcome

                                                                                                                                                                9
overtime pay                                               result
 QAAD
         Do multi -tasking                                          Teamwork /support
                                                                    working relationship

                                                                    Confident /skilled Technical
                                                                    /Support Staff

                                                                    On time data reporting
         Collaborative and            Conflicting Schedule          Focus/Commitment
         supportive Regional                                        Flexibility
         Director , Assistant                                       Patience
         Regional director ,                                        Intrapersonal/Interpersonal
 TAD     STRIVE Technical                                           relationship
         Advisers , Regional Field
         Assistance Teams                                           Proper channeling of
                                                                    communications

         Time management              Time- overlapping of           Overtime work is
                                      activities                    necessary

RMSPPD
                                                                    Overtime if necessary
                                                                    during Saturday and
                                                                    Sunday

                                                                    Flexibility
                                                                    Patience
                                                                    Perseverance
                                                                    Time Management
                                                                    Focus
                                                                    Commitment
                                      Lack of staffing              Giving more focus on
         Working beyond office        requirement to handle the     assigned task resulted to
         hours facilitated the work   different areas               quality outputs.
         completion.
         Clear vision/mission of      Competitive demands of        Commitment towards work
         CLMD which inspires to       CLMD in achieving the         made work easy and
         achieve the plan             targets                       meaningful.
         Work plan serves as a        Shifting from comfort         Teamwork facilitated the
CLMD
         guide in achieving           zone to the new role as       accomplishment of targets.
         desired CLMD objectives      observed by the chief
         Weekly monitoring of         Some members lack the         Enhanced work attitude
         personnel in achieving       ability of prioritizing the   has been developed.
         targets                      activities in terms of
                                      urgency and importance
         Positive work attitude


                                                                                             10
Teamwork of all support
                                  and technical staff
                                  Equal distribution of work         Delayed submission and            Work is lighter and easy if
                                  loads                              retrieval of data                 properly and evenly
             PPRD                                                    /documents                        distributed and personnel
                                  Good working attitude                                                are cooperative and
                                                                                                       committed
              TDD                 Time Management                    Conflict of Schedule              System is very important to
                                                                                                       carry out outputs
            ADMIN                 Multi-tasking

                                  Render Service beyond
                                  office hours even without
                                  overtime pay




4.2. Organizational Resource Support
     4.2.1. Expected Outputs

    The Administrative Division, being the support division is composed of Personnel, Legal, Cashier,
Records, Supplies and General Services. Their outputs can be seen in Table VI below.
                              Table VI: Consolidated Physical Outputs of the Administrative Division




                                                                                                                               11
Actual        %
 FUNCTIONAL                     TARGETS                                          PHYSICAL ACCOMPLISHMENTS               Accomplis   ACCOMPLIS
                                                                  Target
DIVISION /UNIT       ( Planned Outputs up to Dec 2010)                             (Outputs achieved to date)             hment       HED VS.
                                                                                                                                     TARGETS
                 Support staff of the region supervised           ____?        Done. Support staff of the region        _____?
ADMINISTRATI                                                                   supervised                                           100%
VE DIVISION
                                                                               Done. SALN, Performance Rating.
                 Filing System for SALN, Performance Rating,
                                                                               Form 6, Form 48 and Service Records
                 Form 6, Form 48 and Service Records of the            1                                                     1
                                                                               of the Regional pe4rsonnel and staff                 
                 Regional Personnel and staff kept, updated
                                                                               kept                                                       100%
                 Service Record Management System)                     1       Done. Service Record Management
                 Seminar-Workshop conducted                                    System) Seminar-Workshop conducted       .
                                                                                                                             1

                 ____ Admin staff capacitated and trained on                   Done. ___capacitated and trained staff                      ___
                 Graft and Corruption conducted                                on Graft and Corruption conducted
                                                                 ___ staff                                              ___ staff

                                                                               Done Just in time. Request for
                 Timely and prompt response to request for        As need
                                                                               Personnel Records released on time
                 Personnel Records                                 arises
                                                                               Done just in time. Reclassification
                 Reclassification and Upgrading of Teachers       As need      and Upgrading of Teachers Processed                        100%
                 Processed                                         arises

                                                                               Done regularly. ___ of Applications
                 Applications for Certification Authentication
                                                                 ___           for Certification Authentication and         ___
                 and Verification (CAV) processed                                                                                         __%
                                                                               Verification (CAV) processed
                                                                               Done just in time. ___ of applications
                                                                 As need       for Travel Authority processed                             ___%
                 Applications for Travel Authority processed                                                                  __
                                                                 arises

                                                                               Done just in time. ___Applications for
                 Applications for Leave of regional/detailed     As need       Leave of regional/detailed personnel/
                                                                                                                             ___
                 personnel/ staff processed                      arises        staff processed                                            ___%

                                                                               Done. Report on Filled and Unfilled
                                                                 3 (1/
                 Report on Filled and Unfilled Positions from                  Positions from the Field Consolidated
                                                                 month x                                                     3
                 the Field Consolidated (Monthly)                              (Monthly)                                                  100%
                                                                 3)
                 Report on Personnel Movement from the                         Done. Report on Personnel Movement
                 field Consolidated                                            from the field Consolidated
                                                                       1                                                      1
                  • Transfer                                                    • Transfer                                                100%
                  • Promotion                                                   • Promotion
                 Applications for Retirement                                   Done. Applications for
                                                                           1                                                  1
                 Processed                                                     Retirement Processed                                      100%
                                                                                                                                         100%
                 Budget Estimate for Retirees                                  Done. Budget Estimate for
                                                                       1                                                     1
                 prepared                                                      Retirees prepared
Cashier                                                            On          Done on schedule. Salaries,
                 Salaries, wages benefits, and                                 wages, benefits, and vouchers
                                                                 schedul                                                                Done on
                 vouchers paid on time                                         paid on time
                                                                     e                                                                  schedule
Supplies                                                            As         Done. Needed supplies and
                 Needed supplies and materials                                 materials procured and
and General                                                       need
                 procured and delivered                                        delivered on schedule
Services                                                          arises
                 Annual Inventory of equipment
                                                                       1       Done. Annual inventory of                    1               100%
                 made
                                                                               equipment made
Records                                                             On         Done. Processed documents                                 100%
                 Prompt and timely released of
                                                                 schedul       released                                      1
                 processed documents released
                                                                     e
                 Documents and records sorted                    As            Partially done. Documents
                                                                 need          sorted according to the
                                                                 arises        following classification:
                                                                               ________ Shelved
                                                                               ________ Archived
                                                                               ________ Condemned
                                                                               ________ Disposed of
                                                                               Done just in time. Request                               Done just 12
                                                                    As
                 Timely and prompt response to                                 for Personnel Records
                                                                  need                                                                   in time
                 request for Personnel Records                                 released
                                                                  arises
The Budget and Finance Division, being the machinery in the regional office has reported their
accomplishments shown in Table VII below.

                                 Table VII: Budget and Finance Division

             TARGETS                 Target          ACCOMPLISHMENT               Actual                %
                                                                              Accomplishment     ACCOMPLISHED
                                                                                                  VS. TARGETS
     Payment of Salaries         1              Done.RO personnel             1
                                                salaries paid on time
     Salary Deductions/Taxes 1                  Done. Salary                  1
     Withheld Remitted                          Deductions/Taxes
                                                Withheld Remitted
                                                monthly
     Implementation of           1              On-going
     Agency Budget Matrix
     (ABM)
     Budget Proposal             1              Done. Budget proposal         1
                                                prepared
     Cash Program                1              Done                          1
     Financial and Budgetary     1              Done                          1
     Reports

        The support divisions of the region namely; the Administrative and the Budget and Finance
Divisions performed greatly their mandated functions as revealed in the recent conduct of pilot RMEA. It
can be noted in the Table VIII below that the over-all performance of the support divisions is 86% which
means they have been doing satisfactorily for the Fiscal Year 2010.


               Table VIII – Computed Performance of the Administrative and Budget and Finance Division

                                                                                       # of
                                                                                  Accomplished        % of
                       RO UNIT                                 # of Targets          outputs     Accomplishment
 AD 1: Administrative Division                                      25                  22            88%
 AD 2: Budget and Finance Division                                  6                  5              83%
                     Regional Performance                          31                 27              86%



The physical accomplishments of the two support divisions can be very well understood by the graph
below.




                                                                                                              13
REPORT OF NUMBER OF PERSONNEL PERCEIVED BY FD AND THE NEEDED PERSONNEL

         The Administrative Division is a support division in the region. It takes charge of personnel
deployment in the office. Table VII below shows the perceived number of personnel in the different
functional divisions and the needed personnel to complement the staffing requirement in every functional
division/unit.




             Table IX – NUMBER OF PERSONNEL PERCEIVED BY FD AND THE NEEDED PERSONNEL

                  NUMBER OF                                                                           NUMBER OF               NEEDED
                                        NUMBER OF
                  PERSONNEL                                                        CASUAL/            PERSONNEL             PERSONNEL
                                        PERSONNEL            NUMBER OF
                   PERCEIVED                                                       CONTRAC               WITH
                                           WITH              PERSONNEL
                   NEEDED BY                                                         TUAL              PLANTILLA
                                         PLANTILLA           DETAILED IN
                  FUNCTIONAL                                                       SUPPORT             POSITION
  FUNCTIONA                            POSITION FOR          THE REGION
                 AND SUPPORT                                                        STAFF               FOR THE
L/ SUPPORT                              THE REGION
DIVISION
                    DIVISIONS                                                                           REGION
                               Key                   Key                   Key                                      Key                   Key
                 Technical    Staff/   Technical    Staff/   Technical    Staff/            Contrac   Technical    Staff/   Technical    Staff/
                                                                                   Casual
                   Staff     Support     Staff     Support     Staff     Support             tual       Staff     Support     Staff     Support
                              Staff                 Staff                 Staff                                    Staff                 Staff

FD 1: PPRD          6          8          5          1         0           0        1        0           5          2         1           6
FD 2: T&D           4          2          3          2         1           0        0        0           4          2         0           0

                                                                                                                                                  14
FD 3: CLMD             18        6       11            2     2           0     0     0    13        2    5    4
FD 4: RMSPPD           12        3           7         2     0           0     0     0    7         2    5    1
FD 5: QAAD             7         4           4         2     3           0     0     0    7         2    0    2
FD 6: TAD              6         1           5         1     1           0     0     0    6         1    0    0
AD 1: Adm              1        42           1         24                0     3     2    1         29   0    13
AD 2: BFD                       41                     27                0     1     0    0         28   0    13
TOTAL                  54       107      36            61    7           0     5     2    43        68   11   39


            The authorized, existing and vacant positions in the region can be seen in the Table X below.

              Table X: Authorized Positions, Number of Filled Positions and Vacant Positions

                            AUTHORIZED POSITIONS
                                                                               NO. OF FILLED VACANT
              OFFICE             Teaching/
                                                 Non- Teaching         Total   POSITIONS     POSITIONS
                                    ES
              RD            0                    34              34            21              13
              EED           10                   4               14            9               5
              SED           11                   4               15            14              1
              ALS           4                    3               7             3               4
              PESSD         6                    3               9             6               3
              ADMIN         0                    41              41            28              13
              BFD           0                    32              32            26              6
              TOTAL         31                   121             152           107             45

4.3. Summary

        It was noted that the over-all performance of Region 7 for the past Fiscal Year 2010 was 83%,
which is Satisfactory. This means that the region as a whole had worked hard despite of inadequacies in
terms of personnel, office equipment and other resources. There is only 17% unaccomplished targeted
outputs hopefully to be carried over this year.

        On the individual performance of the different functional divisions, the Technical Assistance
Division showed the highest performance. But all of them showed greater performance in terms of
accomplishing its target as reflected in their individual Work Plans.

        On issues within control, the issue of overlapping of activities emerged as the common issue
crosscutting the five functional divisions. The seemingly lack of coordination among and between offices
could lead to conflicting of schedules, that could prevent some personnel to attend to the important
concern. This is something that needs to be improved.


                                                                                                                   15
While on issue of the lack of personnel and support, this is beyond the control among the functional
divisions. Request for additional plantilla item positions is a management matter to be considered.

         Positive work attitudes among the personnel is observed to be the best lesson learned by almost
all personnel, despite of the changes in their working environment due to restructuring. Personnel had
been moved to the other offices so new work assignment, new batch of colleagues and new office head
could be a challenge to each and every personnel undergoing the restructuring. Despite of all these factors
the loyalty and dedication to service remain evident. This contributed to the greater accomplishments of
targets in the regional office.


5.0 RECOMMENDATIONS

         The STRIVE RMEA technology which we used during the Pilot RMEA is a helpful tool for data
gathering. However, there are some parts that need to be modified. One is the tools used for data
gathering. The tools for data gathering and for generating recommendations need to be modified for easy
collection and analysis of data.
.
         In light of the issues and lessons learned presented during the conduct of the Regional Monitoring,
Evaluation and Adjustment (RMEA), the following recommendations were proposed:

On Issues within Control

    The following recommendations can be formulated out of the Issues Beyond Control.

    •    Functional and Support Divisions to prioritize their activities and hold regular staff meetings.

    •    Functional Division Personnel to coordinate with other functional and support divisions.

    •    Requests to be made in writing for purposes of recording and budgeting.

    •    Financial Reports to be disclosed and to be presented in the Regional Executive Committee
         Meeting (REXECOM) all expenditures such as electricity, water, office supplies, communication,
         gasoline, janitorial services, minor repairs and maintenance and other expenses.

    •    Provide accomplished reports to QAAD for consolidation



On Issues Beyond Control

         The following recommendations can be generated out of the Issues Beyond Control.

    •    Special request addressed to the Regional Director to provide items for those staff who are
         detailed in the Regional Office.

                                                                                                            16
•    DepEd Region VII Top Management to make a follow up to the Central Office pertaining to the
        authority to fill up support staff existing items.

    •   DepED Region VII to generate and mobilize resources from internal and external stakeholders to
        procure the needed equipment specifically ICT.

    •   Programs and projects related to academics should be turned-over to Curriculum and Learning
        Management Division (CLMD).



On Lessons Learned

    The following recommendations can be formed out of the Lessons Learned for the whole year of
implementation.

    Functional and Support Division Personnel to sustain and focus in organic functions as planned.

    DepEd Region VII Personnel to continue to develop positive work attitudes in accomplishing
     targets through having regular conferences and tracking individual assigned tasks.

    Sustain best practices which are beneficial across functional divisions




                                                                                                       17

More Related Content

What's hot

Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptx
Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptxGuidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptx
Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptxMelchorBalolong3
 
Guidelines on RPMS PPST SY 23-24.pptx
Guidelines on RPMS PPST SY 23-24.pptxGuidelines on RPMS PPST SY 23-24.pptx
Guidelines on RPMS PPST SY 23-24.pptxJsamson3
 
Performance indicators formula
Performance indicators formulaPerformance indicators formula
Performance indicators formulaAllan Tomas
 
Sample Accomplished SMEA templates
Sample Accomplished SMEA templatesSample Accomplished SMEA templates
Sample Accomplished SMEA templatesDivine Dizon
 
2 professional development_plan, pllp, action plan, 21st classroom
2 professional development_plan, pllp, action plan, 21st classroom2 professional development_plan, pllp, action plan, 21st classroom
2 professional development_plan, pllp, action plan, 21st classroomjojit apiong
 
Conducting post observation conferences
Conducting post observation conferencesConducting post observation conferences
Conducting post observation conferencesMarilu Bandolon
 
Instructional Supervisory Plan.docx
Instructional Supervisory Plan.docxInstructional Supervisory Plan.docx
Instructional Supervisory Plan.docxMARICELBALTAZAR3
 
Monitoring and Evaluation of Educational Facilities
Monitoring and Evaluation of Educational FacilitiesMonitoring and Evaluation of Educational Facilities
Monitoring and Evaluation of Educational FacilitiesTHINKER BELL
 
My individual performance-commitment-and-review-form- 3
My individual performance-commitment-and-review-form- 3My individual performance-commitment-and-review-form- 3
My individual performance-commitment-and-review-form- 3Carie Justine Estrellado
 
Supervisory plan-and-report-2022
Supervisory plan-and-report-2022Supervisory plan-and-report-2022
Supervisory plan-and-report-2022ReyMarkVidalLacaden
 
RPMS-with-movs-and-annotations-for-printing.ppt
RPMS-with-movs-and-annotations-for-printing.pptRPMS-with-movs-and-annotations-for-printing.ppt
RPMS-with-movs-and-annotations-for-printing.pptMARIADELCORTEZ
 
Deped school drrm coordinator duties and responsibilities
Deped school drrm coordinator duties and responsibilitiesDeped school drrm coordinator duties and responsibilities
Deped school drrm coordinator duties and responsibilitiesAlicel Mangulabnan
 
Module2.ppst1.4.2
Module2.ppst1.4.2Module2.ppst1.4.2
Module2.ppst1.4.2Noel Tan
 

What's hot (20)

Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptx
Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptxGuidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptx
Guidelines-and-Criteria-for-Ranking-of-Applicants-to-T-II-II-MT-I-IV.pptx
 
Guidelines on RPMS PPST SY 23-24.pptx
Guidelines on RPMS PPST SY 23-24.pptxGuidelines on RPMS PPST SY 23-24.pptx
Guidelines on RPMS PPST SY 23-24.pptx
 
Master-Teacher-RPMS.pdf
Master-Teacher-RPMS.pdfMaster-Teacher-RPMS.pdf
Master-Teacher-RPMS.pdf
 
Performance indicators formula
Performance indicators formulaPerformance indicators formula
Performance indicators formula
 
Sample Accomplished SMEA templates
Sample Accomplished SMEA templatesSample Accomplished SMEA templates
Sample Accomplished SMEA templates
 
2 professional development_plan, pllp, action plan, 21st classroom
2 professional development_plan, pllp, action plan, 21st classroom2 professional development_plan, pllp, action plan, 21st classroom
2 professional development_plan, pllp, action plan, 21st classroom
 
Sample action plan
Sample action planSample action plan
Sample action plan
 
Accomplishment Report SMM&E; June-July 2016
Accomplishment Report SMM&E; June-July 2016Accomplishment Report SMM&E; June-July 2016
Accomplishment Report SMM&E; June-July 2016
 
Conducting post observation conferences
Conducting post observation conferencesConducting post observation conferences
Conducting post observation conferences
 
Instructional Supervisory Plan.docx
Instructional Supervisory Plan.docxInstructional Supervisory Plan.docx
Instructional Supervisory Plan.docx
 
Monitoring and Evaluation of Educational Facilities
Monitoring and Evaluation of Educational FacilitiesMonitoring and Evaluation of Educational Facilities
Monitoring and Evaluation of Educational Facilities
 
My individual performance-commitment-and-review-form- 3
My individual performance-commitment-and-review-form- 3My individual performance-commitment-and-review-form- 3
My individual performance-commitment-and-review-form- 3
 
Supervisory plan-and-report-2022
Supervisory plan-and-report-2022Supervisory plan-and-report-2022
Supervisory plan-and-report-2022
 
RPMS-with-movs-and-annotations-for-printing.ppt
RPMS-with-movs-and-annotations-for-printing.pptRPMS-with-movs-and-annotations-for-printing.ppt
RPMS-with-movs-and-annotations-for-printing.ppt
 
Tip completion report
Tip completion reportTip completion report
Tip completion report
 
Deped school drrm coordinator duties and responsibilities
Deped school drrm coordinator duties and responsibilitiesDeped school drrm coordinator duties and responsibilities
Deped school drrm coordinator duties and responsibilities
 
RPMS Process
RPMS ProcessRPMS Process
RPMS Process
 
Module2.ppst1.4.2
Module2.ppst1.4.2Module2.ppst1.4.2
Module2.ppst1.4.2
 
Sample PMCF.docx
Sample PMCF.docxSample PMCF.docx
Sample PMCF.docx
 
DO No.44 series 2015
DO No.44 series 2015DO No.44 series 2015
DO No.44 series 2015
 

Viewers also liked

Centres evaluation report template new format
Centres evaluation report template new formatCentres evaluation report template new format
Centres evaluation report template new formatCentres-EU
 
Year end accomplishment report ( 2014 2015 ) by Dan Landicho
Year end accomplishment report ( 2014 2015 )  by Dan LandichoYear end accomplishment report ( 2014 2015 )  by Dan Landicho
Year end accomplishment report ( 2014 2015 ) by Dan LandichoDan Landicho Jr
 
Accomplishment reports in science
Accomplishment reports in scienceAccomplishment reports in science
Accomplishment reports in scienceReon Zedval
 
Accomplisment
AccomplismentAccomplisment
Accomplismentalona abe
 
instructional accomplishment report
instructional accomplishment reportinstructional accomplishment report
instructional accomplishment reportReon Zedval
 
Accomplishment report: Grade six
Accomplishment report:  Grade sixAccomplishment report:  Grade six
Accomplishment report: Grade sixReon Zedval
 
school accomplishment report per month
school accomplishment report per monthschool accomplishment report per month
school accomplishment report per monthReon Zedval
 

Viewers also liked (7)

Centres evaluation report template new format
Centres evaluation report template new formatCentres evaluation report template new format
Centres evaluation report template new format
 
Year end accomplishment report ( 2014 2015 ) by Dan Landicho
Year end accomplishment report ( 2014 2015 )  by Dan LandichoYear end accomplishment report ( 2014 2015 )  by Dan Landicho
Year end accomplishment report ( 2014 2015 ) by Dan Landicho
 
Accomplishment reports in science
Accomplishment reports in scienceAccomplishment reports in science
Accomplishment reports in science
 
Accomplisment
AccomplismentAccomplisment
Accomplisment
 
instructional accomplishment report
instructional accomplishment reportinstructional accomplishment report
instructional accomplishment report
 
Accomplishment report: Grade six
Accomplishment report:  Grade sixAccomplishment report:  Grade six
Accomplishment report: Grade six
 
school accomplishment report per month
school accomplishment report per monthschool accomplishment report per month
school accomplishment report per month
 

Similar to DepEd Region 7 RMEA Progress Report of Accomplishments for the Calendar Year 2010

RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...
RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...
RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...Dr. Joy Kenneth Sala Biasong
 
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...Dr. Joy Kenneth Sala Biasong
 
Second Quarter of CY 2012 RMEPA Progress Report of Accomplishments
Second Quarter of CY 2012 RMEPA Progress Report of AccomplishmentsSecond Quarter of CY 2012 RMEPA Progress Report of Accomplishments
Second Quarter of CY 2012 RMEPA Progress Report of AccomplishmentsDr. Joy Kenneth Sala Biasong
 
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...Dr. Joy Kenneth Sala Biasong
 
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকা
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকাবার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকা
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকাmeftahulhasan09
 
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...Dr. Joy Kenneth Sala Biasong
 
4th-Quarter-DMEA-PRESENTATION-Final22.pptx
4th-Quarter-DMEA-PRESENTATION-Final22.pptx4th-Quarter-DMEA-PRESENTATION-Final22.pptx
4th-Quarter-DMEA-PRESENTATION-Final22.pptxJaymarLantapeTugahan
 
HR UPDATE Anne Borde Version Final
HR UPDATE Anne Borde Version Final HR UPDATE Anne Borde Version Final
HR UPDATE Anne Borde Version Final Angelo Mangatal
 
Analysing District Plans
Analysing District PlansAnalysing District Plans
Analysing District Planssonit singh
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburDr. Md. Taibur Rahman
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
Basic understaning of m&e sang
Basic understaning of m&e sangBasic understaning of m&e sang
Basic understaning of m&e sangSang Sey
 
Monitoring and Evaluation Framework
Monitoring and Evaluation FrameworkMonitoring and Evaluation Framework
Monitoring and Evaluation FrameworkMichelle Joja
 
Performance Budgeting: Lessons and Challenges from Korea by Jangro Lee
Performance Budgeting: Lessons and Challenges from Korea by Jangro LeePerformance Budgeting: Lessons and Challenges from Korea by Jangro Lee
Performance Budgeting: Lessons and Challenges from Korea by Jangro LeeOECD Governance
 

Similar to DepEd Region 7 RMEA Progress Report of Accomplishments for the Calendar Year 2010 (20)

RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...
RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...
RMEPA Progress Report of Accomplishments for the 3rd Quarter of Calendar Year...
 
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...
First Quarter of 2013 Regional Monitoring, Evaluation and Plan Adjustment (RM...
 
Second Quarter of CY 2012 RMEPA Progress Report of Accomplishments
Second Quarter of CY 2012 RMEPA Progress Report of AccomplishmentsSecond Quarter of CY 2012 RMEPA Progress Report of Accomplishments
Second Quarter of CY 2012 RMEPA Progress Report of Accomplishments
 
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...
QAAD's Report on Regional Monitoring, Evaluation and Plan Adjustment (RMEPA) ...
 
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকা
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকাবার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকা
বার্ষিক কর্মসম্পাদন চুক্তি (এপিএ) মূলত গণপ্রজাতন্ত্রী বাংলাদেশ সরকা
 
2012 CDA Dagupan Performance Review
2012 CDA Dagupan Performance Review2012 CDA Dagupan Performance Review
2012 CDA Dagupan Performance Review
 
APR Workshop 2010 Integrating M&E in project implementation-Pakistan-A.Karim
APR Workshop 2010 Integrating M&E in project implementation-Pakistan-A.KarimAPR Workshop 2010 Integrating M&E in project implementation-Pakistan-A.Karim
APR Workshop 2010 Integrating M&E in project implementation-Pakistan-A.Karim
 
APR Workshop 2010-M&E-Integratng monitoring and evaluation in project impleme...
APR Workshop 2010-M&E-Integratng monitoring and evaluation in project impleme...APR Workshop 2010-M&E-Integratng monitoring and evaluation in project impleme...
APR Workshop 2010-M&E-Integratng monitoring and evaluation in project impleme...
 
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
DepEd Region 7 QAAD’s Report on Regional Monitoring, Evaluation and Plan Adju...
 
4th-Quarter-DMEA-PRESENTATION-Final22.pptx
4th-Quarter-DMEA-PRESENTATION-Final22.pptx4th-Quarter-DMEA-PRESENTATION-Final22.pptx
4th-Quarter-DMEA-PRESENTATION-Final22.pptx
 
HR UPDATE Anne Borde Version Final
HR UPDATE Anne Borde Version Final HR UPDATE Anne Borde Version Final
HR UPDATE Anne Borde Version Final
 
Analysing District Plans
Analysing District PlansAnalysing District Plans
Analysing District Plans
 
M&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taiburM&E of development projects and role of imed dr taibur
M&E of development projects and role of imed dr taibur
 
Healy edward
Healy edwardHealy edward
Healy edward
 
R F D Results Framework Document - Group 5
R F D  Results Framework Document - Group 5R F D  Results Framework Document - Group 5
R F D Results Framework Document - Group 5
 
AWPB
AWPBAWPB
AWPB
 
Educational Planning (QAAD Session)
Educational Planning (QAAD Session)Educational Planning (QAAD Session)
Educational Planning (QAAD Session)
 
Basic understaning of m&e sang
Basic understaning of m&e sangBasic understaning of m&e sang
Basic understaning of m&e sang
 
Monitoring and Evaluation Framework
Monitoring and Evaluation FrameworkMonitoring and Evaluation Framework
Monitoring and Evaluation Framework
 
Performance Budgeting: Lessons and Challenges from Korea by Jangro Lee
Performance Budgeting: Lessons and Challenges from Korea by Jangro LeePerformance Budgeting: Lessons and Challenges from Korea by Jangro Lee
Performance Budgeting: Lessons and Challenges from Korea by Jangro Lee
 

More from Dr. Joy Kenneth Sala Biasong

Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...
Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...
Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...Dr. Joy Kenneth Sala Biasong
 
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...Dr. Joy Kenneth Sala Biasong
 
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...Dr. Joy Kenneth Sala Biasong
 
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramFinancial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramDr. Joy Kenneth Sala Biasong
 
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramFinancial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramDr. Joy Kenneth Sala Biasong
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Dr. Joy Kenneth Sala Biasong
 
Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Dr. Joy Kenneth Sala Biasong
 
Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Dr. Joy Kenneth Sala Biasong
 
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...Dr. Joy Kenneth Sala Biasong
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Dr. Joy Kenneth Sala Biasong
 
Guidelines on the Assessment and Rating of Learning Outcomes under the K to...
Guidelines on the Assessment  and Rating of Learning Outcomes under the  K to...Guidelines on the Assessment  and Rating of Learning Outcomes under the  K to...
Guidelines on the Assessment and Rating of Learning Outcomes under the K to...Dr. Joy Kenneth Sala Biasong
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Dr. Joy Kenneth Sala Biasong
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Dr. Joy Kenneth Sala Biasong
 

More from Dr. Joy Kenneth Sala Biasong (20)

Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...
Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...
Management Advisory Services (Differential Cost Analysis) by Dr. Joy Kenneth ...
 
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Act) by Dr. J...
 
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...
Philippine TRAIN Law (Tax Reform for Acceleration and Inclusion Law) by Dr. J...
 
Project Feasibility Study
Project Feasibility StudyProject Feasibility Study
Project Feasibility Study
 
Financial Statements Analysis for Non-Accountants
Financial Statements Analysis for Non-AccountantsFinancial Statements Analysis for Non-Accountants
Financial Statements Analysis for Non-Accountants
 
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramFinancial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
 
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA ProgramFinancial Management (Short-Term Course for Non-Finance Managers) MBA Program
Financial Management (Short-Term Course for Non-Finance Managers) MBA Program
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
 
Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)
 
Financial Statements Analysis
Financial Statements AnalysisFinancial Statements Analysis
Financial Statements Analysis
 
Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)Business Planning (Business Plan for a Start-Up Venture)
Business Planning (Business Plan for a Start-Up Venture)
 
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...
Revised Guidelines on the Establishment, Merging, Conversion and Naming/Renam...
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
 
Guidelines on the Assessment and Rating of Learning Outcomes under the K to...
Guidelines on the Assessment  and Rating of Learning Outcomes under the  K to...Guidelines on the Assessment  and Rating of Learning Outcomes under the  K to...
Guidelines on the Assessment and Rating of Learning Outcomes under the K to...
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
 
Child Protection Policy
Child Protection PolicyChild Protection Policy
Child Protection Policy
 
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
Project Feasibility Study: Concepts and Procedures ( Accountancy, Management ...
 
Industrial Arts Curriculum Map
Industrial Arts Curriculum MapIndustrial Arts Curriculum Map
Industrial Arts Curriculum Map
 
Agriculture and Fishery Arts Curriculum Map
Agriculture and Fishery Arts Curriculum MapAgriculture and Fishery Arts Curriculum Map
Agriculture and Fishery Arts Curriculum Map
 
Home Economics Curriculum Map
Home Economics Curriculum MapHome Economics Curriculum Map
Home Economics Curriculum Map
 

DepEd Region 7 RMEA Progress Report of Accomplishments for the Calendar Year 2010

  • 1. PROGRESS REPORT OF ACCOMPLISHMENTS FOR THE PERIOD OF: JANUARY – DECEMBER 2010 REGION: VII 1.0. INTRODUCTION The Regional Office needs to strategically respond to the requirements of the R.A. 9155 thus paving the way to the restructuring of the Regional Offices with much clearer roles and functions. Through its unified education development plan, it provides directions to the functional divisions’ initiatives toward the attainment of its goals & objectives. Given this, a Regional Monitoring and Evaluation Framework is made to serve as a roadmap towards bringing the region to a culture of quality and accountability as an organization. With the present framework serving an organizational M&E for the region, its purpose for monitoring and evaluation is to provide objective information that can inform decision-making for continuously improving its Organizational performance for efficient and effective fulfillment of the regional mandate, and Delivery of education services to achieve the desired outputs and sustainability of Education Outcomes. The monitoring and evaluation report is aimed to establish information as basis for determining appropriate approach / strategy to improve organizational performance in fulfillment of the regional mandate and strengthen collective actions to service better the divisions and schools within the accountability of the Region and present information regarding organization resource support to the region management that will support decisions and adjustments to plans (e.g. budget, personnel, physical facilities plan) and strategies to ensure appropriate allocation of resources to support performance efficiency and effectiveness. 2.0. SCOPE With the implementation framework of the system now in place and accepted by the Regional Management, an important part of the process is its implementation. The three - day live-out pilot RMEA was conducted and quantitative and qualitative information per RO unit were gathered, analyzed, interpreted and to be presented to the Regional Management. Necessary adjustments on the Work plan of every functional division/RO unit has to be done. The coverage of the Monitoring and Evaluation report is from January to December 2010 as indicated in the Work Plan of every Functional division and RO Unit. The focus of this report is on area on Organizational Performance/Health along its Organizational Effectiveness which pertains to individual, team and organizational effectiveness of the region. Outputs achieved per individual RO Unit and those co-implemented by at least 2 or more RO units, Implementation Issues of each regional unit/functional division regarding work plan implementation, Institutional issues that involves multiple functional divisions 1
  • 2. and Lessons Learned are tracked down while Organizational Resource Support concerns mainly with availability and adequacy of resource requirements for the region to carry out its mandate efficiently and effectively. This includes the analysis of how the region best optimizes its financial, human and organizational capabilities in performing its functions by individual units and as a team. 3.0. METHODOLOGY The three - day live-out pilot RMEA was conducted following the STRIVE RMEA technology . Purposely it was conducted for the participants to have established quantitative information on the accomplishment of every RO unit, identified and clarified issues encountered and lessons learned and adjusted the work plan of each Functional division/RO unit. Pre-work activity was done before the conduct of RMEA to gather initial reports on Physical Accomplishment of every RO unit. QAAD personnel assigned in every RO unit made visit to the different offices and did actual data collection on quantitative and qualitative information. Internal M & E was designated in every RO unit. Tools were given for easy data collection following established standards. The actual conduct of RMEA took place on December 16-18, 2010 at DepED, Ecotech Center, Cebu City. Each QAAD personnel was given assignment on what RO Unit to facilitate for easy data gathering, analysis and interpretation using the recommended tools : CLMD by Dr. Estela B. Susvilla, T and DD and RMSPPD by Dr. Joy Kenneth Biasong, QAAD by Ms. Rosa Cabotaje, PPRD, BFD, and Admin by Ms. Merden Bryant. Dr. Marcial Degamo acted as the over-all Chairman. Different sessions were handled by the QAAD personnel. Session I on Quantitative Information was facilitated by Dr. Estela Susvilla, Session 2 , on Issues and Proposed Resolutions by Ms. Merden Bryant, Session 3 on Lessons Learned by Ms. Rosa Cabotaje, Session 4 on Organizational Resources by Dr. Marcial Degamo and Session 5 on Proposed Recommendations was handled Dr. Joy Kenneth Biasong. After every presentation of the different sessions, workshop was conducted simultaneously. Tools were given to gather and consolidate the data. In plenary, the following instructions were given for the simultaneous division/unit group work:  Each functional division/unit must have a designated official documenter  Based on the accomplished FD/Unit Output Matrix , compute the division/unit’s physical output using the Table 1-A: Physical Outputs (template) Show Table 1-A in PPT.  In plenary, there will be a consolidation of the functional division /unit physical accomplishment. For this, Table 1-B: Status of the functional division /unit Physical Outputs will be used.  Compute for the balance of physical outputs and identify reasons for variance. A physical output can only be credited if it meets standard/s and has MOV/s. The quantitative and qualitative information gathered were consolidated, analyzed and interpreted and to be presented to the top management for actions and adjustments. 2
  • 3. 4.0. Findings 4.1. Organizational Effectiveness 4.1.1 Expected outputs Overall percentage of accomplishment of the region Fiscal year 2010 was a good year for Region 7. The regional structuring took place with a great wave of change happening in the different regional offices/units as a pilot. Every functional division was mandated to prepare a Work Plan indicating its goals and objectives, setting its targets covering the whole year. Based on it, results on the pilot MEA revealed that the region had 83% performance which is satisfactorily doing well despite of the inadequacies in terms of personnel, office equipment and other resources of the newly structured regional office. As shown in the Table I below, Technical Assistance Division performed the highest, followed by the Curriculum and Learning Management Division. Almost all of the Regional Divisions/Units showed better performance as expected. The functional divisions showing relatively greater performance are the Planning, Policy and Research Division, Resource Mobilization and Special Programs and Projects Division, Administrative Division and Budget and Finance Division. Table I COMPUTED ACCOMPLISHED PHYSICAL OUTPUTS # of % of Accomplished Accomplishmen RO UNIT # of Targets outputs t FD 1: Curriculum and Learning Management Division 25 23 92% FD 2: Training and Development Division 5 3 60% FD 3: Resource Mobilization and Special Programs and Projects Division 32 23 84% FD 4: Quality Assurance and Accountability Division 15 11 73% FD 5: Technical Assistance Division 29 27 93% FD 6: Planning, Policy and Research Division 9 8 89% AD 1: Administrative Division 25 22 88% AD 2: Budget and Finance Division 6 5 83% Regional Performance 146 122 83% 3
  • 4. The performance of all functional divisions/units and the over-all performance of the region is shown in the graph below. Percentage of unaccomplished outputs There are only very few targeted outputs that were not accomplished during the SY 2010. The table below shows that only 17% left unaccomplished and noted to be done this year. It shows that every functional division/unit did their share of accomplishing their targets despite of the limited resources in the region. Table II - COMPUTED UNACCOMPLISHED PHYSICAL OUTPUTS # of # of Unaccomplished % of RO UNIT Targets outputs Accomplishment FD 1: Curriculum and Learning Management Division 25 2 8% FD 2: Training and Development Division 5 2 40% FD 3: Resource Mobilization and Special Programs and Projects Division 32 11 34% FD 4: Quality Assurance and Accountability Division 15 4 27% FD 5: Technical Assistance Division 29 2 7% FD 6: Planning, Policy and Research Division 9 1 11% AD 1: Administrative Division 25 3 12% AD 2: Budget and Finance Division 6 1 17% 146 26 17% 4
  • 5. The unaccomplished outputs can be very well understood in the graph below. REASONS FOR BALANCE Common reasons for the balances of outputs of FY 2010 were overlapping of activities and time constraint. Failure to complete the targeted outputs is one of the considerations in the making of adjustment Work Plan for this year 2011. 4.1.2 Unexpected /Value Added Outputs Shown in the Table III below are the outputs which were not targeted in the Work Plan but were done for some reasons that there were instructions from the top management to do so. Table III: VALUE-ADDED OUTPUTS RO UNIT VALUE-ADDED OUTPUTS REASONS FOR ACHIEVING THEM Trained ______of Preschool Administrators and Develop of preschool instructional selected teachers materials CLMD Translated Grade I competencies for First Grading In compliance to MTB-MLE program period Test Item Bank construction For the annual Regional Achievement Test Translated EPP competencies from Filipino to To align the secondary TLE English competencies Development of Supplementary materials for Indigenization of curriculum Elementary Science Trained _____ first year teachers in UbD in 19 To enhance the secondary curriculum 5
  • 6. divisions in all subject areas Trained _______ untrained elementary teachers To enhance the reading competencies in NEPP training for all in 19 divisions of elementary pupils and teaching strategies in teaching reading Regional Search for Grade I teachers with zero To give incentives/recognize their non-readers conducted efforts and inspire them to perform better _____Number of Performing Schools visited To give recognition for the school/district/division QAAD Inter agency clean and green environment Being ordered by RD monitoring of schools Process request for subject overload Monitoring and Evaluation of schools recipient of ESC /EVS schools PPRD Physical accomplishment report/agency Needed report for the DBM performance review submitted to DBM Report Cards by Congressional Districts and Networking between RO and DOs Municipalities of the entire region to 15 Congressmen, mayors of component cities prepared, reproduced, and distributed Proposed Inputs to the Central Visayas Regional Development Plan for SY 2010-2016 prepared Result Evaluation and Monitoring Matrix High degree of work ethics prepared Enhanced Regional BIAP prepared and Networking beyond and among submitted to CO stakeholders Physical Accomplishment Report/Agency Performance Review prepared and submitted to Needed report by DBM DBM Maintenance of laptops and computers in the ICT skills of one staff region done Minutes, Activities, and Reports of REXECOM Being ordered by RD and EXECON covered and jot down BAC-TWG (Bids and Awards Committee – Technical Working Group) results evaluation done 6
  • 7. RMSPPD Endorsements of communications in cultural and Stakeholders from NGOs, Private arts, theaters and plays School Sectors Eco Patrol International School Competition Positive participation from the division (Science School) Awareness of the environment Folk Dance and Balitaw Competition NAMCYA National Competition Palarong Pambansa 2011 Training of the Athletes With funds from the stakeholders on the process (ABS-CBN and Aboitiz Foundation) Orientation for the Sinulog sa Kabataan sa Funds from the Sinulog Foundation Lalawigan sa Sugbo Conference Workshop of Winning Coaches, TFSS and TMs 4.1.3 Issues It has been found out that issues affecting organizational effectiveness include technical, institutional, financial, social and environmental /infrastructure issues. For issues within the control of the Regional Office, the issue that greatly affects organizational effectiveness is the overlapping of organic and Project-STRIVE-related activities. Because of this issue, personnel have less time and less focus in accomplishing their tasks. The proposed resolutions to address this issue are as follows:  Functional Division Personnel to coordinate with other functional and support divisions  Functional and Support Divisions to prioritize their activities and hold regular staff meeting  Regional Management to provide a Regional Activity Tracking Board where the functional and support divisions can post their activities within a month to help prevent overlapping of activities because every RO Unit can best be able to schedule their activities that would not conflict other activities Another salient issue that needs attention is that the personnel of Resource Mobilization Special Programs and Projects Division (RMSPPD) find it hard to spearhead some programs and projects related to academics because they lack the indispensable expertise in conceptual background both in content and skills. Although they seek the necessary expertise from the CLMD personnel by coordinating with them, they sometimes fail to get their help because they are also busy with their organic tasks. Indeed, the overlapping of activities affects organizational effectiveness. 7
  • 8. The proposed resolution is to request the Regional Director that programs and projects related to academics shall be turned-over to the Curriculum and Learning Management Division (CLMD) and the RMSPPD personnel shall only give their technical support. Lack of personnel, both technical and support staff, and lack of office equipment/facility like computer units, laptops, copying machine, fax machine, internet facility, network printers, and LCD projectors are the two most critical issues that need to be elevated to higher management and to external stakeholders like the Department of Budget and Management. The insufficient number of personnel of functional and support divisions has significantly curtailed the desired efficiency and effectiveness of these divisions with respect to time. Coupled with the overlapping of activities, some workloads are worked on at a later time. The unavailability of office equipment like computer units, laptops, copying machines, and network printers also prevents the fast-tracking of the processing of documents. Recording, tracking, consolidating, production, and reproduction of documents require plenty of time when done manually and when necessary equipment are lacking. If computer units were available for use by the technical and support staff in offices, these tasks would be done in a sophisticated manner, thus, making the work much faster and easier. Table IV below shows the consolidated issues and resolutions by categories cut across the different functional divisions/units. Table IV: Consolidated Issues and Proposed Resolutions ISSUES FOR ATTENTION OF CATEGORIES OF ISSUES WITHIN THE UNIT’S HIGHER PROPOSED RESOLUTION OR PROPOSED RESOLUTION ISSUES CONTROL MANAGEMENT / ACTION SOUGHT FROM MGT. EXTERNAL STAKEHOLDERS Less focus and limited time to Make a request to RD to provide coordinate with RO Units accomplish a Regional Activity Tracking tasks due to overlapping of activities Board where each functional TECHNICAL division and RO Unit can post their activities within a month to prevent overlapping of activities. Programs and projects related to Make a request to RD that Lack of technical and Make a request to RD to follow up at academics are endorsed to the programs and projects related to support staff across the Central Office the authority to fill RMSPPD when its personnel lack the academics should be turned-over RO Units due to the vacant positions. indispensable conceptual to Curriculum and Learning Restructuring of .Make a request to RD to refer to the background. Management Division (CLMD). Offices CO the need for the creation of additional PSIPOP items INSTITUTIONAL Division personnel .Make a request to RD to follow up at are detailed in the the Central Office the authority to fill Regional Office to vacant positions. complement staffing .Make a request to RD to refer to the requirement. CO the need for the creation of additional PSIPOP items 8
  • 9. Inadequate funding for some Request RD to allocate more programs and projects especially in funds to some programs and sports activities and trainings projects such sports activities and training and to seek external There are still stakeholder financial support Refer to Central Office that there are divisions requesting FINANCIAL still divions requesting for salary for for salary of Make a request to the RD that preschool teachers. Some schools offering SPED Classes preschool teachers items purchased by schools include in their purchase for assistive offering SPED Classes be devices camera, refrigerator, and included in FTA Monitoring other equipment Most functional divisions and regional Make a request to RD that the Most functional Refer to Central Office that the units lack office furniture/supplies like office furniture/ supplies like filing divisions and regional restructuring of Regional Office VII filing cabinets, working tables, filing cabinets, working tables and filing units lack office gives rise to the need for functional boxes, and CDs. boxes, and CDs be provided to equipment/facility like divisions/regional units office the offices needing them. computer units, equipment/facilities like computer ENVIRONMENTAL/ laptops, copying units, laptops, copying machine, fax INFRASTRUCTURE machine, fax machine, internet facility, network machine, internet printers, and LCD projector facility, network DepED Region VII shall generate and printers, and LCD mobilize resources from external projector. stakeholders to procure the needed ICT equipment. Renovation/ expansion of RMSPPD Make a request to RD that the Office so that there is proper renovation/expansion of coordination of medical team and RMSPPD Office shall be physical facilities team designed such that the Physical Facilities and Medical Teams shall already be accommodated in one office. Divisions that are not supportive of Make a request to the RD to programs and projects despite TA discuss during EXECON the lack SOCIAL provided , specifically NAMCYA of support of some divisions to programs and projects like NAMCYA. 4.1.4 Lessons Learned At the course of the implementation of the targets in the Work Plan of every functional division/unit in the region for the FY 2010, lessons were generated. The lessons learned serve as part of the essential considerations for plan adjustments in the following quarter/year. These could either be derived either from the facilitating factors or hindering factors encountered during its implementation of the newly restructured Regional Office. These may provide information on how the Functional Divisions can limit strategies for the accomplishment of Work plans and highlight factors contributory to the targets. Table V below shows the facilitating, hindering factors and lessons learned of the functional divisions/units which were noted down during the conduct of pilot RMEA. Table V. FACILITATING/HINDERING FACTORS and LESSONS LEARNED FDs/ADMIN Units FACILITATING FACTORS HINDERING FACTORS LESSONS LEARNED Technical Staff performed All Technical are Conflicting Schedule well despite of their of their computer literate status of employment Render Service beyond Lack of support staff Full time Technical Staff office hours even without have greater outcome 9
  • 10. overtime pay result QAAD Do multi -tasking Teamwork /support working relationship Confident /skilled Technical /Support Staff On time data reporting Collaborative and Conflicting Schedule Focus/Commitment supportive Regional Flexibility Director , Assistant Patience Regional director , Intrapersonal/Interpersonal TAD STRIVE Technical relationship Advisers , Regional Field Assistance Teams Proper channeling of communications Time management Time- overlapping of Overtime work is activities necessary RMSPPD Overtime if necessary during Saturday and Sunday Flexibility Patience Perseverance Time Management Focus Commitment Lack of staffing Giving more focus on Working beyond office requirement to handle the assigned task resulted to hours facilitated the work different areas quality outputs. completion. Clear vision/mission of Competitive demands of Commitment towards work CLMD which inspires to CLMD in achieving the made work easy and achieve the plan targets meaningful. Work plan serves as a Shifting from comfort Teamwork facilitated the CLMD guide in achieving zone to the new role as accomplishment of targets. desired CLMD objectives observed by the chief Weekly monitoring of Some members lack the Enhanced work attitude personnel in achieving ability of prioritizing the has been developed. targets activities in terms of urgency and importance Positive work attitude 10
  • 11. Teamwork of all support and technical staff Equal distribution of work Delayed submission and Work is lighter and easy if loads retrieval of data properly and evenly PPRD /documents distributed and personnel Good working attitude are cooperative and committed TDD Time Management Conflict of Schedule System is very important to carry out outputs ADMIN Multi-tasking Render Service beyond office hours even without overtime pay 4.2. Organizational Resource Support 4.2.1. Expected Outputs The Administrative Division, being the support division is composed of Personnel, Legal, Cashier, Records, Supplies and General Services. Their outputs can be seen in Table VI below. Table VI: Consolidated Physical Outputs of the Administrative Division 11
  • 12. Actual % FUNCTIONAL TARGETS PHYSICAL ACCOMPLISHMENTS Accomplis ACCOMPLIS Target DIVISION /UNIT ( Planned Outputs up to Dec 2010) (Outputs achieved to date) hment HED VS. TARGETS Support staff of the region supervised ____? Done. Support staff of the region _____? ADMINISTRATI supervised 100% VE DIVISION Done. SALN, Performance Rating. Filing System for SALN, Performance Rating, Form 6, Form 48 and Service Records Form 6, Form 48 and Service Records of the 1 1 of the Regional pe4rsonnel and staff Regional Personnel and staff kept, updated kept 100% Service Record Management System) 1 Done. Service Record Management Seminar-Workshop conducted System) Seminar-Workshop conducted . 1 ____ Admin staff capacitated and trained on Done. ___capacitated and trained staff ___ Graft and Corruption conducted on Graft and Corruption conducted ___ staff ___ staff Done Just in time. Request for Timely and prompt response to request for As need Personnel Records released on time Personnel Records arises Done just in time. Reclassification Reclassification and Upgrading of Teachers As need and Upgrading of Teachers Processed 100% Processed arises Done regularly. ___ of Applications Applications for Certification Authentication ___ for Certification Authentication and ___ and Verification (CAV) processed __% Verification (CAV) processed Done just in time. ___ of applications As need for Travel Authority processed ___% Applications for Travel Authority processed __ arises Done just in time. ___Applications for Applications for Leave of regional/detailed As need Leave of regional/detailed personnel/ ___ personnel/ staff processed arises staff processed ___% Done. Report on Filled and Unfilled 3 (1/ Report on Filled and Unfilled Positions from Positions from the Field Consolidated month x 3 the Field Consolidated (Monthly) (Monthly) 100% 3) Report on Personnel Movement from the Done. Report on Personnel Movement field Consolidated from the field Consolidated 1 1 • Transfer • Transfer 100% • Promotion • Promotion Applications for Retirement Done. Applications for 1 1 Processed Retirement Processed 100% 100% Budget Estimate for Retirees Done. Budget Estimate for 1 1 prepared Retirees prepared Cashier On Done on schedule. Salaries, Salaries, wages benefits, and wages, benefits, and vouchers schedul Done on vouchers paid on time paid on time e schedule Supplies As Done. Needed supplies and Needed supplies and materials materials procured and and General need procured and delivered delivered on schedule Services arises Annual Inventory of equipment 1 Done. Annual inventory of 1 100% made equipment made Records On Done. Processed documents 100% Prompt and timely released of schedul released 1 processed documents released e Documents and records sorted As Partially done. Documents need sorted according to the arises following classification: ________ Shelved ________ Archived ________ Condemned ________ Disposed of Done just in time. Request Done just 12 As Timely and prompt response to for Personnel Records need in time request for Personnel Records released arises
  • 13. The Budget and Finance Division, being the machinery in the regional office has reported their accomplishments shown in Table VII below. Table VII: Budget and Finance Division TARGETS Target ACCOMPLISHMENT Actual % Accomplishment ACCOMPLISHED VS. TARGETS Payment of Salaries 1 Done.RO personnel 1 salaries paid on time Salary Deductions/Taxes 1 Done. Salary 1 Withheld Remitted Deductions/Taxes Withheld Remitted monthly Implementation of 1 On-going Agency Budget Matrix (ABM) Budget Proposal 1 Done. Budget proposal 1 prepared Cash Program 1 Done 1 Financial and Budgetary 1 Done 1 Reports The support divisions of the region namely; the Administrative and the Budget and Finance Divisions performed greatly their mandated functions as revealed in the recent conduct of pilot RMEA. It can be noted in the Table VIII below that the over-all performance of the support divisions is 86% which means they have been doing satisfactorily for the Fiscal Year 2010. Table VIII – Computed Performance of the Administrative and Budget and Finance Division # of Accomplished % of RO UNIT # of Targets outputs Accomplishment AD 1: Administrative Division 25 22 88% AD 2: Budget and Finance Division 6 5 83% Regional Performance 31 27 86% The physical accomplishments of the two support divisions can be very well understood by the graph below. 13
  • 14. REPORT OF NUMBER OF PERSONNEL PERCEIVED BY FD AND THE NEEDED PERSONNEL The Administrative Division is a support division in the region. It takes charge of personnel deployment in the office. Table VII below shows the perceived number of personnel in the different functional divisions and the needed personnel to complement the staffing requirement in every functional division/unit. Table IX – NUMBER OF PERSONNEL PERCEIVED BY FD AND THE NEEDED PERSONNEL NUMBER OF NUMBER OF NEEDED NUMBER OF PERSONNEL CASUAL/ PERSONNEL PERSONNEL PERSONNEL NUMBER OF PERCEIVED CONTRAC WITH WITH PERSONNEL NEEDED BY TUAL PLANTILLA PLANTILLA DETAILED IN FUNCTIONAL SUPPORT POSITION FUNCTIONA POSITION FOR THE REGION AND SUPPORT STAFF FOR THE L/ SUPPORT THE REGION DIVISION DIVISIONS REGION Key Key Key Key Key Technical Staff/ Technical Staff/ Technical Staff/ Contrac Technical Staff/ Technical Staff/ Casual Staff Support Staff Support Staff Support tual Staff Support Staff Support Staff Staff Staff Staff Staff FD 1: PPRD 6 8 5 1 0 0 1 0 5 2 1 6 FD 2: T&D 4 2 3 2 1 0 0 0 4 2 0 0 14
  • 15. FD 3: CLMD 18 6 11 2 2 0 0 0 13 2 5 4 FD 4: RMSPPD 12 3 7 2 0 0 0 0 7 2 5 1 FD 5: QAAD 7 4 4 2 3 0 0 0 7 2 0 2 FD 6: TAD 6 1 5 1 1 0 0 0 6 1 0 0 AD 1: Adm 1 42 1 24 0 3 2 1 29 0 13 AD 2: BFD 41 27 0 1 0 0 28 0 13 TOTAL 54 107 36 61 7 0 5 2 43 68 11 39 The authorized, existing and vacant positions in the region can be seen in the Table X below. Table X: Authorized Positions, Number of Filled Positions and Vacant Positions AUTHORIZED POSITIONS NO. OF FILLED VACANT OFFICE Teaching/ Non- Teaching Total POSITIONS POSITIONS ES RD 0 34 34 21 13 EED 10 4 14 9 5 SED 11 4 15 14 1 ALS 4 3 7 3 4 PESSD 6 3 9 6 3 ADMIN 0 41 41 28 13 BFD 0 32 32 26 6 TOTAL 31 121 152 107 45 4.3. Summary It was noted that the over-all performance of Region 7 for the past Fiscal Year 2010 was 83%, which is Satisfactory. This means that the region as a whole had worked hard despite of inadequacies in terms of personnel, office equipment and other resources. There is only 17% unaccomplished targeted outputs hopefully to be carried over this year. On the individual performance of the different functional divisions, the Technical Assistance Division showed the highest performance. But all of them showed greater performance in terms of accomplishing its target as reflected in their individual Work Plans. On issues within control, the issue of overlapping of activities emerged as the common issue crosscutting the five functional divisions. The seemingly lack of coordination among and between offices could lead to conflicting of schedules, that could prevent some personnel to attend to the important concern. This is something that needs to be improved. 15
  • 16. While on issue of the lack of personnel and support, this is beyond the control among the functional divisions. Request for additional plantilla item positions is a management matter to be considered. Positive work attitudes among the personnel is observed to be the best lesson learned by almost all personnel, despite of the changes in their working environment due to restructuring. Personnel had been moved to the other offices so new work assignment, new batch of colleagues and new office head could be a challenge to each and every personnel undergoing the restructuring. Despite of all these factors the loyalty and dedication to service remain evident. This contributed to the greater accomplishments of targets in the regional office. 5.0 RECOMMENDATIONS The STRIVE RMEA technology which we used during the Pilot RMEA is a helpful tool for data gathering. However, there are some parts that need to be modified. One is the tools used for data gathering. The tools for data gathering and for generating recommendations need to be modified for easy collection and analysis of data. . In light of the issues and lessons learned presented during the conduct of the Regional Monitoring, Evaluation and Adjustment (RMEA), the following recommendations were proposed: On Issues within Control The following recommendations can be formulated out of the Issues Beyond Control. • Functional and Support Divisions to prioritize their activities and hold regular staff meetings. • Functional Division Personnel to coordinate with other functional and support divisions. • Requests to be made in writing for purposes of recording and budgeting. • Financial Reports to be disclosed and to be presented in the Regional Executive Committee Meeting (REXECOM) all expenditures such as electricity, water, office supplies, communication, gasoline, janitorial services, minor repairs and maintenance and other expenses. • Provide accomplished reports to QAAD for consolidation On Issues Beyond Control The following recommendations can be generated out of the Issues Beyond Control. • Special request addressed to the Regional Director to provide items for those staff who are detailed in the Regional Office. 16
  • 17. DepEd Region VII Top Management to make a follow up to the Central Office pertaining to the authority to fill up support staff existing items. • DepED Region VII to generate and mobilize resources from internal and external stakeholders to procure the needed equipment specifically ICT. • Programs and projects related to academics should be turned-over to Curriculum and Learning Management Division (CLMD). On Lessons Learned The following recommendations can be formed out of the Lessons Learned for the whole year of implementation.  Functional and Support Division Personnel to sustain and focus in organic functions as planned.  DepEd Region VII Personnel to continue to develop positive work attitudes in accomplishing targets through having regular conferences and tracking individual assigned tasks.  Sustain best practices which are beneficial across functional divisions 17