Commissioning and Sustainability:
Ensuring Your ROI



               Presented by:
               Adam Muggleton, Cobalt Engineering


The Fourth Annual Green Building Festival
September 10, 2008
Cobalt Engineering

                                            At Cobalt, we give life to buildings.
                                            Adopting a holistic perspective, we
                                            offer fully integrated mechanical
                                            and electrical services with a
                                            sustainable focus to deliver high
                                            performance building solution for
                                            every project.

IKEA, Calgary, AB




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Adding Value
    • Advanced Energy,
      Building Comfort Modeling
                                                        Metropolis at Metrotown Mall, Burnaby, BC
    • Passive Design
    • Microclimate Analysis/Modeling
    • Daylighting Analysis
    • Façade Design
    • Sustainable Master Planning                         IGA, Various locations across Canada



    • External Airflow Analysis
    • LEED Consulting
    • Commissioning
                                                       Boston Pizza, Various locations across Canada


Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Today’s Global Issues




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Why Commission Buildings?
       A 2002 study of 60 buildings in USA found:
  •    50% had control problems
  •    40% of HVAC equipment did not function properly
  •    15% had missing equipment
  •    25% of energy management systems, economizers and variable speed
       drives did not function correctly
  •    60% of insurance claims are related to HVAC issues
  •    The number one source of complaints is HVAC
  •    The average cost of energy due to above $3 ft2
  LBNL. (2002). Lawrence Berkeley National Laboratory Survey of 60 Buildings in USA. http://buildings.lbl.gov/hpcbs/Year_01/Element_5)/
  01_E5.html




Presented by:
Adam Muggleton, MSc, LEED® AP                            Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Why Commission Buildings?




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Why Commission Buildings?




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Why Commission Buildings?




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
No Commissioning?




                                                         Image courtesy of Zurich U.S.



Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Definition
                                  The American Society of Heating,
                                  Refrigeration and Air-Conditioning
                                  Engineers (ASHRAE) Guideline 0-2005:
                                  The Commissioning Process, defines
                                  commissioning as a “Quality oriented
                                  process for achieving, verifying and
                                  documenting that the performance of
                                  facilities, systems and assemblies meets
                                  defined objectives and criteria”.

                                  Commissioning is multi discipline and can
                                  be considered a bridge between the design
                                  and delivery of a project. The more
                                  complex and interconnect the systems or
                                  building the greater the need for
                                  commissioning.


Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning and Quality
The commissioning process is based on larger global quality process
movement.
The key tenants of a quality process are:
          The end goal must be defined
          Work to be done right the first time
          Each individual worker is responsible for quality
          Verification of work, not inspection
          Focus on long term whole life of product i.e. building
          Improve quality and lower costs - lean construction



Presented by:
Adam Muggleton, MSc, LEED® AP         Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
What is Commissioning?

• A planned, collaborative and
  systematic process


• Takes place and adds value
  throughout the entire project


• Confirms that systems and the
  building function as an
  integrated whole



Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
What is Commissioning?




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Sustainable Buildings
• Commissioning, maybe counter intuitively, is very important for
  highly sustainable “green” buildings or “Net Zero” buildings

• Buildings are systems in their own right

• Commissioning commences at the component level and extends to
  the building level




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Risks to Project Completion




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Adds Value




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning KPI’s
             “You cannot manage what you do not measure”




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Process
Pre Design Phase = Quality Management




   Pre Design
                                                          Deliverables
    Owner hires design team
    Owner hires commissioning authority                  ✓ Team appointed
    Develop expectations & budgets                       ✓ Draft scope & budget
    Determine scope & budget                             ✓ Draft owners intent document
    Develop owners intent




Presented by:
Adam Muggleton, MSc, LEED® AP          Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Process
Design Phase = Quality Management

   Design
    Design for commissioning review                       Deliverables
    Develop basis of design document
    Commissioning Charrette                               ✓ Owners intent document
    Develop commissioning plan                            ✓ Basis of design document - design team
    Review LEED check list                                ✓ Issues log and Risk register
    Develop commissioning contract                        ✓ Robust design
   document clauses                                        ✓ Integrated commissioning logic network
    Develop test sheet suite                              ✓ Commissioning plan
    Develop draft functional test
   protocols(FTP’S)

                                                              Commissioning Plan includes:
                                                              ✓ Scope
                                                              ✓ Responsibility matrix
                                                              ✓ Documentation matrix
                                                              ✓ Systems logic networks
                                                              ✓ Book of systems interfaces
                                                              ✓ Pre-functional test documentation
Presented by:
Adam Muggleton, MSc, LEED® AP           Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Process
Construction Phase = Quality Control




Construction Phase
 Contractors commissioning workshop                        Deliverables
 Review submittals & O&M’s                                 ✓ Ownership of the commissioning plan
 Assistance in problem resolution                          ✓ Low levels of installation defects
 Installation inspections                                  ✓ Agreed commissioning plan
 Sample witness of static systems testing                  ✓ Right first time commissioning
 Observe equipment & systems start up                      ✓ Quality control
 Finalize functional test protocols(FTP’S)                 ✓ Deficiency reports
 Refine basis of design document                           ✓ On time systems commissioning
 Refine commissioning plan
 Finalize commissioning program




Presented by:
Adam Muggleton, MSc, LEED® AP            Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Contractors’ First Reaction to Commissioning!




Presented by:
Adam Muggleton, MSc, LEED® AP   Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Commissioning Process
 Acceptance Phase = Quality Control



Acceptance
                                                            Deliverables
 Sample witness vendor commissioning
 Sample witness systems commissioning                      ✓ Tested and validated building and systems
 Sample witness TAB                                        ✓ Documented building performance
 Witness 100% all life safety systems                      ✓ Fully operational & optimized building
 Use FTP’s to verify systems performance                   ✓ Timely completion of commissioning
 Global integration testing                                ✓ High quality environmental conditions
 Black building test                                       ✓ Low levels of deficiencies
 Assist in problem resolution                              ✓ Low levels of call backs
 Collate & document all systems test results               ✓Set trend logs to monitor building
 Produce the commissioning report                          performance
 Review and coordinate O&M team training




  Presented by:
  Adam Muggleton, MSc, LEED® AP            Commissioning & Sustainability: Ensuring your ROI
  Managing Partner Toronto
  September 10, 2008
Commissioning Process
Acceptance Phase - Post Occupancy = Quality Control & Fine tuning




 Occupancy
  Deferred FTP testing                             Deliverables
  Deferred seasonal testing
  Systems optimization                             ✓Up-dated commissioning report
  Post occupancy adjustments                       ✓Lessons learned report / workshop
  Review of outstanding defects
  Lessons learned workshop




Presented by:
Adam Muggleton, MSc, LEED® AP      Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Cost of NOT Commissioning

Commissioning exposes deficiencies in design and installation
                                             Cause of Defects in Construction
                                       Product/
                                      Equipment
                                     Failures, 10%




                                                                                                     Design
                                                                                                  Problems, 50%
                         Construction
                        Problems, 40%




M Billington. (2001). Defects in Buildings: Symptoms, Investigation, Diagnosis and Cure. www.BRE.co.uk


Presented by:
Adam Muggleton, MSc, LEED® AP                             Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Cost of NOT Commissioning

Cost of rectifying quality failures increases as the project progresses:


                                                  Cost
      Rectified at design stage                 1.00 (Zero)

      Rectified during construction             3 times design stage

      Rectified at completion                   8 times design stage

      Rectified in use                          unlimited!




Presented by:
Adam Muggleton, MSc, LEED® AP    Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Cost of NOT Commissioning
                                  Energy Costs at Differing RTU Minimum Outside Air Settings

                       $120,000

                                                                                                $99,315
                       $100,000

                                                                            $80,820
                        $80,000
     Annual Cost ($)




                                                         $61,349
                        $60,000
                                       $46,488

                        $40,000


                        $20,000


                            $0
                                     21% (Design)         30%                 40%                50%
                                                         % OA During Occupied Hours


Presented by:
Adam Muggleton, MSc, LEED® AP                            Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Costs of Commissioning
                Estimates of Construction Phase Commissioning Costs
                     (Costs from the commission authority in new construction, per square foot)




   PECI. (2002). New Construction Commissioning Costs. www.PECI.org
Presented by:
Adam Muggleton, MSc, LEED® AP                        Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Benefits of Commissioning


                                • Increased occupant thermal comfort
                                  with improved environmental control
                                • Improved indoor air quality
                                • Smoother turnover from contractor to
                                  owner
                                • Optimized Energy Performance




Presented by:
Adam Muggleton, MSc, LEED® AP        Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Benefits of Commissioning


                                • Reduced construction, operating and
                                  maintenance costs
                                • Reduced energy consumption
                                • Reduced RFI’s and change orders
                                • Reduced contractor and vender call
                                  backs



Presented by:
Adam Muggleton, MSc, LEED® AP      Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008
Presented by:
Adam Muggleton, MSc, LEED® AP
                                Thank You
                                  Commissioning & Sustainability: Ensuring your ROI
Managing Partner Toronto
September 10, 2008

More Related Content

Viewers also liked

2010 07 BSidesLV Mobilizing The PCI Resistance 1c
2010 07 BSidesLV Mobilizing The PCI Resistance 1c 2010 07 BSidesLV Mobilizing The PCI Resistance 1c
2010 07 BSidesLV Mobilizing The PCI Resistance 1c Security B-Sides
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...HIMADRI BANERJI
 
حقيبة تدريبية في تشغيل الاجهزة وصيانتها
حقيبة تدريبية في تشغيل الاجهزة وصيانتهاحقيبة تدريبية في تشغيل الاجهزة وصيانتها
حقيبة تدريبية في تشغيل الاجهزة وصيانتهاsaradosoky
 
Risk Management - Time to blow it up and start over? - Alex Hutton
Risk Management - Time to blow it up and start over? - Alex HuttonRisk Management - Time to blow it up and start over? - Alex Hutton
Risk Management - Time to blow it up and start over? - Alex HuttonSecurity B-Sides
 
Mineral processing plant design and optimisation
Mineral processing plant design and optimisation Mineral processing plant design and optimisation
Mineral processing plant design and optimisation Basdew Rooplal
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler okBunk Bonk
 

Viewers also liked (6)

2010 07 BSidesLV Mobilizing The PCI Resistance 1c
2010 07 BSidesLV Mobilizing The PCI Resistance 1c 2010 07 BSidesLV Mobilizing The PCI Resistance 1c
2010 07 BSidesLV Mobilizing The PCI Resistance 1c
 
Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...Risk management during start up and commissioning of super critical once thro...
Risk management during start up and commissioning of super critical once thro...
 
حقيبة تدريبية في تشغيل الاجهزة وصيانتها
حقيبة تدريبية في تشغيل الاجهزة وصيانتهاحقيبة تدريبية في تشغيل الاجهزة وصيانتها
حقيبة تدريبية في تشغيل الاجهزة وصيانتها
 
Risk Management - Time to blow it up and start over? - Alex Hutton
Risk Management - Time to blow it up and start over? - Alex HuttonRisk Management - Time to blow it up and start over? - Alex Hutton
Risk Management - Time to blow it up and start over? - Alex Hutton
 
Mineral processing plant design and optimisation
Mineral processing plant design and optimisation Mineral processing plant design and optimisation
Mineral processing plant design and optimisation
 
06 procedure of start up boiler ok
06 procedure of start up boiler ok06 procedure of start up boiler ok
06 procedure of start up boiler ok
 

Similar to Gbf08 muggleton commissioning

BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Engineering
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioningjeff_ranson
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioningluigiseta
 
Lex resume 2011 latest version
Lex resume 2011 latest versionLex resume 2011 latest version
Lex resume 2011 latest versionlexmaclaine
 
2.6 sustainability
2.6 sustainability2.6 sustainability
2.6 sustainabilityHumzaAlam1
 
2.6 sustainability (1)
2.6 sustainability (1)2.6 sustainability (1)
2.6 sustainability (1)HumzaAlam1
 
Total construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyTotal construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyStephen Au
 
01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas
01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas
01 Corporate Profile Green Intl_PM Services,Training and Oil & GasGREEN INTERNATIONAL
 
Agile Load Testing in the Real World
Agile Load Testing in the Real WorldAgile Load Testing in the Real World
Agile Load Testing in the Real WorldLee Barnes
 
Prem_Papabathini_Resume_2016
Prem_Papabathini_Resume_2016Prem_Papabathini_Resume_2016
Prem_Papabathini_Resume_2016Prem Papabathini
 
Building Simulations | Understanding Your Energy Profile
Building Simulations | Understanding Your Energy ProfileBuilding Simulations | Understanding Your Energy Profile
Building Simulations | Understanding Your Energy ProfileEnergy Advantage
 
Building Simulations | Understanding Your Building's Energy Profile
Building Simulations | Understanding Your Building's Energy ProfileBuilding Simulations | Understanding Your Building's Energy Profile
Building Simulations | Understanding Your Building's Energy ProfileEnergy Advantage
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...oyinleye
 
BEE Company Presentation 中英文
BEE Company Presentation 中英文BEE Company Presentation 中英文
BEE Company Presentation 中英文Lucas Wang
 

Similar to Gbf08 muggleton commissioning (20)

BDC Leed Commissioning Presentation
BDC Leed Commissioning PresentationBDC Leed Commissioning Presentation
BDC Leed Commissioning Presentation
 
BDC LEED Cx Preso
BDC LEED Cx PresoBDC LEED Cx Preso
BDC LEED Cx Preso
 
Sbai value of commissioning
Sbai value of commissioningSbai value of commissioning
Sbai value of commissioning
 
The Value of Building Commissioning
The Value of Building CommissioningThe Value of Building Commissioning
The Value of Building Commissioning
 
Leaflet Green Building
Leaflet Green BuildingLeaflet Green Building
Leaflet Green Building
 
Integrative Design Working With Your Mep
Integrative Design Working With Your MepIntegrative Design Working With Your Mep
Integrative Design Working With Your Mep
 
Phil Welker Commissioning
Phil Welker CommissioningPhil Welker Commissioning
Phil Welker Commissioning
 
Lex resume 2011 latest version
Lex resume 2011 latest versionLex resume 2011 latest version
Lex resume 2011 latest version
 
2.6 sustainability
2.6 sustainability2.6 sustainability
2.6 sustainability
 
2.6 sustainability (1)
2.6 sustainability (1)2.6 sustainability (1)
2.6 sustainability (1)
 
Total construction quality management by leading ICT technology
Total construction quality management by leading ICT technologyTotal construction quality management by leading ICT technology
Total construction quality management by leading ICT technology
 
01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas
01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas
01 Corporate Profile Green Intl_PM Services,Training and Oil & Gas
 
Agile Load Testing in the Real World
Agile Load Testing in the Real WorldAgile Load Testing in the Real World
Agile Load Testing in the Real World
 
Prem_Papabathini_Resume_2016
Prem_Papabathini_Resume_2016Prem_Papabathini_Resume_2016
Prem_Papabathini_Resume_2016
 
Obelisk Profile
Obelisk ProfileObelisk Profile
Obelisk Profile
 
Building Simulations | Understanding Your Energy Profile
Building Simulations | Understanding Your Energy ProfileBuilding Simulations | Understanding Your Energy Profile
Building Simulations | Understanding Your Energy Profile
 
Building Simulations | Understanding Your Building's Energy Profile
Building Simulations | Understanding Your Building's Energy ProfileBuilding Simulations | Understanding Your Building's Energy Profile
Building Simulations | Understanding Your Building's Energy Profile
 
Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...Opportunities and role of the quantity surveyor in green building project dev...
Opportunities and role of the quantity surveyor in green building project dev...
 
LEED EBOM Session 1
LEED EBOM Session 1LEED EBOM Session 1
LEED EBOM Session 1
 
BEE Company Presentation 中英文
BEE Company Presentation 中英文BEE Company Presentation 中英文
BEE Company Presentation 中英文
 

More from Toronto 2030 District

GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationToronto 2030 District
 
GBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesGBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesToronto 2030 District
 
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsGBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsToronto 2030 District
 
GBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignGBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignToronto 2030 District
 
GBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesGBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesToronto 2030 District
 
Closing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogClosing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogToronto 2030 District
 
Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral GroupToronto 2030 District
 
Sustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonSustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonToronto 2030 District
 
Ampersand: A Sustainable Community - Robert Smith
Ampersand:  A Sustainable Community - Robert SmithAmpersand:  A Sustainable Community - Robert Smith
Ampersand: A Sustainable Community - Robert SmithToronto 2030 District
 
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshAn Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshToronto 2030 District
 
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...Toronto 2030 District
 
Update on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramUpdate on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramToronto 2030 District
 
Toronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto 2030 District
 
The Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeThe Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeToronto 2030 District
 
Low-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveLow-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveToronto 2030 District
 
Low-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesLow-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesToronto 2030 District
 

More from Toronto 2030 District (20)

GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy GenerationGBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
GBF2014 - Rob Thornton - Flexible, Local, Resilient Energy Generation
 
GBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & CitiesGBF2014 - James Voogt - Climate Change & Cities
GBF2014 - James Voogt - Climate Change & Cities
 
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the CrosshairsGBF2014 - Glenn McGillivray - Cities in the Crosshairs
GBF2014 - Glenn McGillivray - Cities in the Crosshairs
 
GBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient DesignGBF2014 - Paul Dowsett - Resilient Design
GBF2014 - Paul Dowsett - Resilient Design
 
GBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient CitiesGBF2014 - Alec Hay - Planning Climate Resilient Cities
GBF2014 - Alec Hay - Planning Climate Resilient Cities
 
Closing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel SkogClosing The Loops in Malmö, Sweden - Daniel Skog
Closing The Loops in Malmö, Sweden - Daniel Skog
 
Re-Energizing Our Cities: From District to Specific - Integral Group
Re-Energizing Our Cities:  From District to Specific - Integral GroupRe-Energizing Our Cities:  From District to Specific - Integral Group
Re-Energizing Our Cities: From District to Specific - Integral Group
 
Sustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta PerssonSustainable Cities through an Integrated Approach - Agneta Persson
Sustainable Cities through an Integrated Approach - Agneta Persson
 
Ampersand: A Sustainable Community - Robert Smith
Ampersand:  A Sustainable Community - Robert SmithAmpersand:  A Sustainable Community - Robert Smith
Ampersand: A Sustainable Community - Robert Smith
 
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow FarabakhshAn Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
An Emerging Water Management Paradigm - Dr. Khosrow Farabakhsh
 
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...What is "Model" Sustainability?  UniverCity's Journey Toward Sustainability T...
What is "Model" Sustainability? UniverCity's Journey Toward Sustainability T...
 
B bach energy efficiency in obc2012
B bach energy efficiency in obc2012B bach energy efficiency in obc2012
B bach energy efficiency in obc2012
 
Update on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design ProgramUpdate on the Enbridge Savings By Design Program
Update on the Enbridge Savings By Design Program
 
Toronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy EfficiencyToronto Green Standard & Energy Efficiency
Toronto Green Standard & Energy Efficiency
 
The Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building CodeThe Ins & Outs of Energy Efficiency in the Building Code
The Ins & Outs of Energy Efficiency in the Building Code
 
Stormwater Compliance
Stormwater ComplianceStormwater Compliance
Stormwater Compliance
 
SB-10: The Envelope Ultimatum
SB-10: The Envelope UltimatumSB-10: The Envelope Ultimatum
SB-10: The Envelope Ultimatum
 
National Energy Code for Buildings
National Energy Code for BuildingsNational Energy Code for Buildings
National Energy Code for Buildings
 
Low-Impact Development from the Developer Perspective
Low-Impact Development from the Developer PerspectiveLow-Impact Development from the Developer Perspective
Low-Impact Development from the Developer Perspective
 
Low-Impact Development Case Study Examples
Low-Impact Development Case Study ExamplesLow-Impact Development Case Study Examples
Low-Impact Development Case Study Examples
 

Recently uploaded

MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...katerynaivanenko1
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...Rishabh Aryan
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptMaryamAfzal41
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一D SSS
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证nhjeo1gg
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024CristobalHeraud
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social MediaD SSS
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case StudySophia Viganò
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfShivakumar Viswanathan
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryrioverosanniejoy
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Servicejennyeacort
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCRdollysharma2066
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfneelspinoy
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubaikojalkojal131
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一F La
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Rndexperts
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一z xss
 
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一Fi L
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back17lcow074
 

Recently uploaded (20)

MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
MT. Marseille an Archipelago. Strategies for Integrating Residential Communit...
 
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
DAKSHIN BIHAR GRAMIN BANK: REDEFINING THE DIGITAL BANKING EXPERIENCE WITH A U...
 
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
原版1:1定制堪培拉大学毕业证(UC毕业证)#文凭成绩单#真实留信学历认证永久存档
 
cda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis pptcda.pptx critical discourse analysis ppt
cda.pptx critical discourse analysis ppt
 
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
(办理学位证)约克圣约翰大学毕业证,KCL成绩单原版一比一
 
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
在线办理ohio毕业证俄亥俄大学毕业证成绩单留信学历认证
 
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
PORTFOLIO DE ARQUITECTURA CRISTOBAL HERAUD 2024
 
306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media306MTAMount UCLA University Bachelor's Diploma in Social Media
306MTAMount UCLA University Bachelor's Diploma in Social Media
 
ARt app | UX Case Study
ARt app | UX Case StudyARt app | UX Case Study
ARt app | UX Case Study
 
FiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdfFiveHypotheses_UIDMasterclass_18April2024.pdf
FiveHypotheses_UIDMasterclass_18April2024.pdf
 
Design and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industryDesign and Managing Service in the field of tourism and hospitality industry
Design and Managing Service in the field of tourism and hospitality industry
 
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts ServiceCall Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
Call Girls in Ashok Nagar Delhi ✡️9711147426✡️ Escorts Service
 
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Nirman Vihar Delhi NCR
 
group_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdfgroup_15_empirya_p1projectIndustrial.pdf
group_15_empirya_p1projectIndustrial.pdf
 
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services DubaiDubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
Dubai Calls Girl Tapes O525547819 Real Tapes Escort Services Dubai
 
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
办理(宾州州立毕业证书)美国宾夕法尼亚州立大学毕业证成绩单原版一比一
 
Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025Top 10 Modern Web Design Trends for 2025
Top 10 Modern Web Design Trends for 2025
 
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
办理(UC毕业证书)查尔斯顿大学毕业证成绩单原版一比一
 
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
办理学位证加州州立大学洛杉矶分校毕业证成绩单原版一比一
 
shot list for my tv series two steps back
shot list for my tv series two steps backshot list for my tv series two steps back
shot list for my tv series two steps back
 

Gbf08 muggleton commissioning

  • 1. Commissioning and Sustainability: Ensuring Your ROI Presented by: Adam Muggleton, Cobalt Engineering The Fourth Annual Green Building Festival September 10, 2008
  • 2. Cobalt Engineering At Cobalt, we give life to buildings. Adopting a holistic perspective, we offer fully integrated mechanical and electrical services with a sustainable focus to deliver high performance building solution for every project. IKEA, Calgary, AB Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 3. Adding Value • Advanced Energy, Building Comfort Modeling Metropolis at Metrotown Mall, Burnaby, BC • Passive Design • Microclimate Analysis/Modeling • Daylighting Analysis • Façade Design • Sustainable Master Planning IGA, Various locations across Canada • External Airflow Analysis • LEED Consulting • Commissioning Boston Pizza, Various locations across Canada Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 4. Today’s Global Issues Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 5. Why Commission Buildings? A 2002 study of 60 buildings in USA found: • 50% had control problems • 40% of HVAC equipment did not function properly • 15% had missing equipment • 25% of energy management systems, economizers and variable speed drives did not function correctly • 60% of insurance claims are related to HVAC issues • The number one source of complaints is HVAC • The average cost of energy due to above $3 ft2 LBNL. (2002). Lawrence Berkeley National Laboratory Survey of 60 Buildings in USA. http://buildings.lbl.gov/hpcbs/Year_01/Element_5)/ 01_E5.html Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 6. Why Commission Buildings? Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 7. Why Commission Buildings? Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 8. Why Commission Buildings? Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 9. No Commissioning? Image courtesy of Zurich U.S. Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 10. Commissioning Definition The American Society of Heating, Refrigeration and Air-Conditioning Engineers (ASHRAE) Guideline 0-2005: The Commissioning Process, defines commissioning as a “Quality oriented process for achieving, verifying and documenting that the performance of facilities, systems and assemblies meets defined objectives and criteria”. Commissioning is multi discipline and can be considered a bridge between the design and delivery of a project. The more complex and interconnect the systems or building the greater the need for commissioning. Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 11. Commissioning and Quality The commissioning process is based on larger global quality process movement. The key tenants of a quality process are:  The end goal must be defined  Work to be done right the first time  Each individual worker is responsible for quality  Verification of work, not inspection  Focus on long term whole life of product i.e. building  Improve quality and lower costs - lean construction Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 12. What is Commissioning? • A planned, collaborative and systematic process • Takes place and adds value throughout the entire project • Confirms that systems and the building function as an integrated whole Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 13. What is Commissioning? Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 14. Commissioning Sustainable Buildings • Commissioning, maybe counter intuitively, is very important for highly sustainable “green” buildings or “Net Zero” buildings • Buildings are systems in their own right • Commissioning commences at the component level and extends to the building level Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 15. Risks to Project Completion Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 16. Commissioning Adds Value Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 17. Commissioning KPI’s “You cannot manage what you do not measure” Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 18. Commissioning Process Pre Design Phase = Quality Management Pre Design Deliverables  Owner hires design team  Owner hires commissioning authority ✓ Team appointed  Develop expectations & budgets ✓ Draft scope & budget  Determine scope & budget ✓ Draft owners intent document  Develop owners intent Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 19. Commissioning Process Design Phase = Quality Management Design  Design for commissioning review Deliverables  Develop basis of design document  Commissioning Charrette ✓ Owners intent document  Develop commissioning plan ✓ Basis of design document - design team  Review LEED check list ✓ Issues log and Risk register  Develop commissioning contract ✓ Robust design document clauses ✓ Integrated commissioning logic network  Develop test sheet suite ✓ Commissioning plan  Develop draft functional test protocols(FTP’S) Commissioning Plan includes: ✓ Scope ✓ Responsibility matrix ✓ Documentation matrix ✓ Systems logic networks ✓ Book of systems interfaces ✓ Pre-functional test documentation Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 20. Commissioning Process Construction Phase = Quality Control Construction Phase  Contractors commissioning workshop Deliverables  Review submittals & O&M’s ✓ Ownership of the commissioning plan  Assistance in problem resolution ✓ Low levels of installation defects  Installation inspections ✓ Agreed commissioning plan  Sample witness of static systems testing ✓ Right first time commissioning  Observe equipment & systems start up ✓ Quality control  Finalize functional test protocols(FTP’S) ✓ Deficiency reports  Refine basis of design document ✓ On time systems commissioning  Refine commissioning plan  Finalize commissioning program Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 21. Contractors’ First Reaction to Commissioning! Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 22. Commissioning Process Acceptance Phase = Quality Control Acceptance Deliverables  Sample witness vendor commissioning  Sample witness systems commissioning ✓ Tested and validated building and systems  Sample witness TAB ✓ Documented building performance  Witness 100% all life safety systems ✓ Fully operational & optimized building  Use FTP’s to verify systems performance ✓ Timely completion of commissioning  Global integration testing ✓ High quality environmental conditions  Black building test ✓ Low levels of deficiencies  Assist in problem resolution ✓ Low levels of call backs  Collate & document all systems test results ✓Set trend logs to monitor building  Produce the commissioning report performance  Review and coordinate O&M team training Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 23. Commissioning Process Acceptance Phase - Post Occupancy = Quality Control & Fine tuning Occupancy  Deferred FTP testing Deliverables  Deferred seasonal testing  Systems optimization ✓Up-dated commissioning report  Post occupancy adjustments ✓Lessons learned report / workshop  Review of outstanding defects  Lessons learned workshop Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 24. Cost of NOT Commissioning Commissioning exposes deficiencies in design and installation Cause of Defects in Construction Product/ Equipment Failures, 10% Design Problems, 50% Construction Problems, 40% M Billington. (2001). Defects in Buildings: Symptoms, Investigation, Diagnosis and Cure. www.BRE.co.uk Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 25. Cost of NOT Commissioning Cost of rectifying quality failures increases as the project progresses: Cost  Rectified at design stage 1.00 (Zero)  Rectified during construction 3 times design stage  Rectified at completion 8 times design stage  Rectified in use unlimited! Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 26. Cost of NOT Commissioning Energy Costs at Differing RTU Minimum Outside Air Settings $120,000 $99,315 $100,000 $80,820 $80,000 Annual Cost ($) $61,349 $60,000 $46,488 $40,000 $20,000 $0 21% (Design) 30% 40% 50% % OA During Occupied Hours Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 27. Costs of Commissioning Estimates of Construction Phase Commissioning Costs (Costs from the commission authority in new construction, per square foot) PECI. (2002). New Construction Commissioning Costs. www.PECI.org Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 28. Benefits of Commissioning • Increased occupant thermal comfort with improved environmental control • Improved indoor air quality • Smoother turnover from contractor to owner • Optimized Energy Performance Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 29. Benefits of Commissioning • Reduced construction, operating and maintenance costs • Reduced energy consumption • Reduced RFI’s and change orders • Reduced contractor and vender call backs Presented by: Adam Muggleton, MSc, LEED® AP Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008
  • 30. Presented by: Adam Muggleton, MSc, LEED® AP Thank You Commissioning & Sustainability: Ensuring your ROI Managing Partner Toronto September 10, 2008