1. exam questions
Exam Questions
1. Which of the following is NOT a Project Constraint?
A.
B.
C.
D.
Quality
Scale
Time
Cost
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he’s run over his budget because the staff turned out to be more expensive than
planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
A.
B.
C.
D.
Quality
Resource
Time
Cost
3. Which of the following is NOT an example of operational work?
A.
B.
C.
D.
Building a purchase order system for accounts payable
Submitting weekly purchase orders through a purchase order system
Deploying weekly anti-virus software updates
Yearly staff performance evaluations
4. You’re managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is
the BEST way to handle this situation?
A.
B.
C.
D.
Refuse to work with him because he’s being difficult
Appeal to the accountant’s manager and ask to have him required to take training
Get a special dispensation so that the accountant doesn’t have to go to the training
Work with him to understand his concerns and do what you can to help alleviate them without
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
A.
B.
C.
D.
Resource List
Stakeholder Register
Enterprise Environmental Factors
Project Plan
54 Chapter 2
Download at Boykma.Com
2. organizations, constraints, and projects
Exam Questions
6. Your manager asks you where to find a list of projects that should be managed together. What is
the BEST place to find this information?
A.
B.
C.
D.
Project Plan
Project Charter
Portfolio Charter
Program Charter
7. You want to know specifically which business goal a group of projects and programs are going to
accomplish. Which is the best place to look for this information?
A.
B.
C.
D.
Project Plan
Project Charter
Portfolio Charter
Program Charter
8. A project coordinator is having trouble securing programmers for her project. Every time she asks
her boss to give a resource to the project he says that they are too busy to help out with her project.
Which type of organization is she working in?
A.
B.
C.
D.
Functional
Weak Matrix
Strong Matrix
Projectized
9. A project manager is having trouble securing programmers for her project. Every time she asks
the programming manager for resources for her project, he says they’re all assigned to other work.
So she is constantly having to go over his head to overrule him. Which type of organization is she
working for?
A.
B.
C.
D.
Functional
Weak Matrix
Strong Matrix
Projectized
you are here 4 55
Download at Boykma.Com
3. exam answers
Answers
Exam Questions
1. Answer: B
Scale is not a project constraint. The constraints are Scope, Time, Cost, Quality, Resource, and Risk.
2. Answer: C
There is no mention of the project being late or missing its deadlines in the example. The project was over
budget, which affects the project’s cost. The project won’t meet the stakeholder’s requirements, which is a
quality problem. And the staff was more expensive than planned, which is a resource problem.
3. Answer: A
Building a purchase order system for accounts payable is a project. It’s a temporary effort that has a unique
result.
4.Answer: D
When a stakeholder is negatively impacted by your project, you need to manage his expectations and help
him to buy into your project.
5. Answer: B
The stakeholder register is where you identify all of the people who are impacted by your project.
6. Answer: D
A program is a group of projects that should be managed together because of interdependencies. A
program charter fits the description in this question.
7. Answer: C
A portfolio charter will give the business goal that a group of projects and programs will accomplish as part
of a portfolio.
56 Chapter 2
Download at Boykma.Com
4. Answers
organizations, constraints, and projects
Exam Questions
8. Answer: A
Since the project manager has to ask permission from the functional manager and can’t overrule him, she’s
working in a functional organization.
9. Answer: C
The Project Manager in this scenario can overrule the functional manager, so she’s working in a Strong Matrix
organization. If it were a projectized organization, she wouldn’t have to get permission from the functional
manager at all because she’d be the person with authority to assign resources to projects.
you are here 4 57