SlideShare ist ein Scribd-Unternehmen logo
1 von 2
Downloaden Sie, um offline zu lesen
1 May 2013                     Page 1 of 2
Construction Programming Strategy in Malaysia – Size Matters?....Or does it?
The  construction  programme  plays  a 
significant  role  in  project  monitoring  and 
control for any size of  project.  
Many  people  believe  that  a  good 
programme  should  contain  many 
thousands  of  activities    capturing  every 
minute aspect of the works.  
On  the  other  hand,  some  industry 
practitioners  consider  that  an  effective 
programme  should  be  developed  to 
incorporate only the key elements of work. 
They  reject  the  concept  of  having  large 
numbers  of  very  detailed  activities  built 
into  the  programme  simply  for  the 
perception  of  it  looking  “professional”  or 
sophisticated. The supporters of the simple 
programme  approach  argue  that  a 
programme needs to be only large enough 
to  preserve  the  primary  function  of 
predicting  accurate  forecast  dates  for  use 
during the project life and at the same time 
being capable of efficient management.    
In  this  article,  we  will  examine  the  ‘pros’ 
and  ‘cons’  of  programme  size  contrasting 
the  advocates  of  “the  more  activities  the 
better”  with  those  promoting  concise  and 
manageable programmes.   
What a programme does 
A  construction  programme  is  usually  a 
mandatory  element  in  modern 
construction  management.  A  good  and 
effective construction programme provides 
the  construction  team  with  the  tools  for 
project  monitoring  and  control  during  the 
construction stage. The major benefit of a 
good  construction  programme  is  that  it 
functions  as  a  performance  indicator  to 
monitor  performance  of  site  field  work 
against  that  originally  planned  (the 
baseline)  so  as  to  alert  at  the  earliest 
opportunity any  risk of the project being in 
delay. In addition, the programme provides 
a  guide  to  the  project  team  in  respect  to 
the  future  activities  so  that  resources  can 
be  properly  arranged  sufficiently  in 
advance.  
Moreover,  contemporaneous  programmes 
are  an  essential  part  of  the  project 
documents  used  in  delay  analysis  in  the 
event that such a study is later necessary.  
Detailed  construction  programme  –  does 
size matter?  
Because  of  some  of  its  benefits,  some 
practitioners  in  the  construction  industry 
opt  for  a  very  detailed  construction 
programme as their way of developing the 
Baseline Master Programme.  
Their  reason  is  that  more  detail  means 
better  monitoring  and  control.  It  is  often 
the case that, in a complex project such as 
the  construction  of  a  new  airport,  MRT 
project or industrial processing facility, the 
level  of  detail  in  the  Baseline  Programme 
could potentially be so large as to contain 
more  than  10,000  activities.  The  logic 
dependencies  of  the  programme  may 
exceed  two  or  three  times  the  activity 
number; in this example, 20,000 to 30,000 
activity  links  to  create  the  networked 
programme.  
It  may  be  true  that  a  comprehensive 
updated  detailed  programme  arguably 
provides  ready  information  in  respect  of 
the  status  of  the  work  at  the  time  and  it 
provides  a  guide  as  to  what  needs  to  be 
done for the coming months.  On the other 
hand,  the  manageability  of  such  a  large 
network  may  outweigh  the  benefits  in  a 
complex  project  as  there  are  too  many 
activities against which to record progress 
at the time of update.  
Due to the enormous number of activities 
in  the  programme,  the  updating  of 
activities  requires  a  considerable  staff 
resource to accomplish. A sizeable planning 
team to manage such operation is required 
given  the  time  required  for  the  team  to 
research  and  collate  as‐built  dates  and 
percentages  of  completion.  More  time  is 
required  to  review  and  scrutinise  the 
integrity of the programme at the time of 
update.  In  many  cases,  the  same  team 
would  be  tasked  to  attend  programme 
coordination  meetings,  all  other  meetings 
as  well  as  the  preparation  of  weekly  and 
monthly  comprehensive  reports,  just  to 
name a few in the Malaysian scenario.  
It  is  likely  that,  due  to  the  budget 
constraints  of  a  project,  the  planning 
department  of  an  organization  would  not 
have been allocated sufficient resources in 
the form of experienced planners such that 
the complex detailed programme could be 
properly and accurately updated. It follows 
that,  the  practicality  and  accuracy  of  the 
updated construction programme suffers in 
that it loses its main function as a ‘crystal 
ball’  or  tool  for  projecting  future  event 
dates.   
Simple  Construction  programme  –  this 
can’t be right? 
 It is a common and general perception in 
the Malaysian construction industry that a 
less  complex  and/or  less  detailed 
programme would be less “professional” or 
sophisticated and therefore less useful. For 
such  a  reason,  many  major  players  in  the 
industry  in  Malaysia  reject  a  simple 
programme as the Baseline Programme for 
a complex project. A common complaint on 
the simple programme approach is that the 
programme does not capture or reflect the 
full scope of the work.  
It  may  be  true  that  a  simple  construction 
programme  may  lack  the  luxury  of 
informing  the  project  team  in  a  precise 
detailed  manner  such  as  ‘Construct  Level 
40  –  Zone  2  –  Structural  Slab  –  Form  / 
Rebar / Concrete’.  However, a simple and 
higher  level  programme  would  be  able  to 
perform  the  same  function  as  that  of  a 
detailed  programme.  For  such  reason,  a 
simple  programme  may  not  lose  the 
functionality of being a useful programme 
as it nonetheless covers the major scope of 
the work.   
In the above example, by reference to the 
simple  construction  programme,  the 
1 May 2013                     Page 2 of 2
Construction Programming Strategy in Malaysia – Size Matters?....Or does it?
procurement  department  will  still  be  able 
to  identify  when  they  need  to  place  an 
order  and  the  required  delivery  of  the 
relevant reinforcement for Level 40 slab by 
reading  the  construction  activity  in  the 
simpler  programme,  i.e.  “Construct  Level 
40 Slab” as opposed to those of the more 
detailed programme, e.g. “Construct Level 
40 ‐ Zone 2 –Structural slab – Rebar” and 
similar in other Zones. 
The benefit of using a simpler construction 
programme for a complex project is that a 
higher  level  programme  is  easier  to 
manage.  This  is  especially  true  when  the 
programme  is  updated  and  programme 
logic might be revised to ensure a correct 
reflection  of  the  sequence  of  work  at  the 
time for projecting future event dates.  
In many cases, an updated highly detailed 
programme  of  over  10,000  activities, 
despite  its  comprehensive  and  detailed 
coverage  of  the  works,  suffers  inaccuracy 
as a result of wrong or lax input of accurate 
dates and progress percentages; the logic is 
unlikely to have been properly reviewed or, 
if  necessary,  revised  due  to  the  fact  that 
there  are  quite  simply  too many  activities 
to handle.  
This  situation  would  be  further 
complicated  with  the  incorporation  of 
other  additional  sub‐programmes  into  the 
Master  Programme.  For  example,  the 
interior  design  (ID)  work  detailed 
programme  for  a  shopping  arcade  by  a 
specialist sub‐contractor. Such a detailed ID 
works  programme  could  contribute  yet 
another  3,000  to  5,000  detailed  activities 
into the master programme.  
With  application  of  this  programming 
approach,  the  final  result  could  be  the 
creation of an unwieldy “monster”.  
Conclusion 
A  sophisticated  and  detailed  construction 
programme as the Baseline Programme is a 
viable  construction  programming  strategy 
only as long as it can be properly managed 
by experienced and a sufficient number of 
planning  staff.  In  addition,  it  is  equally 
important  that  the  planning  team  has 
sufficient  cooperation  and  support  from 
the  project  team  and  are  not  left  to 
operate  in  isolation;  the  planning  team 
must  be  constantly  made  aware  through 
feedback  from  the  project  team  as  to 
construction status and changes.  
In reality, it appears difficult in Malaysia to 
have this ‘dream team’ as identified above. 
In  many  cases,  due  to  the  financial 
constraints of a project, the planning team 
is  rarely  given  sufficient  resources  to 
manage  very  large  and  complex 
programmes.  
There  are  cases  where  the  planning  team 
lacks the full support from the construction 
teams  in  order  to  update  every  single 
activity  in  a  detailed  programme. 
Therefore,  due  to  misleading  or  incorrect 
data  sources,  a  very  detailed  programme 
becomes of little practical use in achieving 
the original intention. 
 In  such  circumstances,  a  simple 
construction  programme  would  make 
better sense; it is easier to manage (fewer 
activities) and it can still be practically used 
for  accurately  projecting  future  activity 
dates  and  completion  of  the  project  as  a 
whole.  
Any shortcomings of a simple construction 
programme  (viz.  to  address the  complaint 
it does not fully cover the scope of work) 
can  be  remedied  by  other  means  such  as 
standalone mini‐programmes.  
To  summarise,  in  the  view  of  the  author, 
size doesn’t matter; the simpler, the better.   
This article is written by Pang Yoon Sang, 
Senior Consultant, Hill International Inc 
 
 
 
  
 
 
Hill International Malaysia Sdn Bhd. Level 7 Unit 7 Block 3B Plaza Sentral Jalan Stesen Sentral 5  
KL Sentral 50470 Kuala Lumpur, Malaysia. Tel: +65 6338 2455 | Fax: +65 6339 8568 |  
E: advice.msia@hillintl.com | W: www.hillintl.com 
 
 
 
 
 
 
Hill  International  is  a  leading 
construction consultancy firm providing 
innovative  program  and  project 
management,  management  consulting, 
tender  assistance,  dispute 
mitigation/resolution  and  construction 
consultancy  services  to  public  and 
private  clients  worldwide.    We 
specialise in construction risk mitigation 
and avoidance.  
 
Additionally, we offer a full spectrum of 
services to assist clients to successfully 
manage  capital  construction  programs, 
from  initial  feasibility  through 
implementation  and  contract  closeout.  
Hill has served public and private sector 
clients  in  many  varied  projects  from 
public works, transportation, hotels and 
resorts,  leisure  and  amusement  parks 
and  sports  complexes  to  heavy 
industrial  projects  such  as,  power  & 
nuclear  plants,  pipelines,  refineries, 
offshore  and  onshore  oil  refineries, 
petrochemical  plants,  public  utilities, 
water  and  sewer  systems  and 
treatment plants.    
 
Hill  International  currently  has  over 
3,800  employees  in  100  offices 
worldwide  providing  program 
management,  project  management, 
construction  management  and 
construction  claims  services.  Hill 
International,  Inc  is  listed  in  NYSE.  For 
more  information  on  Hill,  please  visit 
our website at www.hillintl.com. 
Disclaimer:  This  article  does  not  constitute  advice,  legal  or 
otherwise,  and  is  provided  only  as  general  commentary. 
Appropriate professional advice should always be obtained before 
taking  or  refraining  from  taking  any  action  in  relation  to  such 
information and/or the application of applicable law. This article and 
the  materials  contained  in  it  are  provided  on  the  basis  that  all 
liability for any loss or damage, whether direct or indirect, arising 
out of or in connection with any use or reliance upon this article is 
excluded to the fullest extent permitted by law. 

Weitere ähnliche Inhalte

Was ist angesagt?

CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC General
Derek Regan
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
Waqar Ahmed
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical Article
Martin Gough
 
What Programme do you need, when and why
What Programme do you need, when and whyWhat Programme do you need, when and why
What Programme do you need, when and why
Declan Sherry
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Charlie Jackson
 
Project planning
Project planningProject planning
Project planning
Shaikh Zain
 

Was ist angesagt? (20)

CORTAC PPC General
CORTAC PPC GeneralCORTAC PPC General
CORTAC PPC General
 
Conveyor Belt Project Report
Conveyor Belt Project ReportConveyor Belt Project Report
Conveyor Belt Project Report
 
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
Project Schedule Planning and Development - A Guide to Develop Reliable Proje...
 
Communication
CommunicationCommunication
Communication
 
Resume 2016
Resume 2016Resume 2016
Resume 2016
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
CONVEYOR BELT PROJECT REPORT
CONVEYOR BELT PROJECT REPORTCONVEYOR BELT PROJECT REPORT
CONVEYOR BELT PROJECT REPORT
 
Project Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions ManualProject Management The Managerial Process 5th Edition Larson Solutions Manual
Project Management The Managerial Process 5th Edition Larson Solutions Manual
 
Project Management 4 Schedule Management
Project Management 4 Schedule ManagementProject Management 4 Schedule Management
Project Management 4 Schedule Management
 
Software Project Management Plan
Software Project Management PlanSoftware Project Management Plan
Software Project Management Plan
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
MCS Technical Article
MCS Technical ArticleMCS Technical Article
MCS Technical Article
 
What Programme do you need, when and why
What Programme do you need, when and whyWhat Programme do you need, when and why
What Programme do you need, when and why
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Cpmgt 305 cpmgt305
Cpmgt 305 cpmgt305Cpmgt 305 cpmgt305
Cpmgt 305 cpmgt305
 
Project planning
Project planningProject planning
Project planning
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
Niwot Ridge Capabilities
Niwot Ridge CapabilitiesNiwot Ridge Capabilities
Niwot Ridge Capabilities
 
B Nicholls resume 2016-07-17
B Nicholls resume   2016-07-17B Nicholls resume   2016-07-17
B Nicholls resume 2016-07-17
 
IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...IRJET- Scheduling and Labour Management for Residential Building Project usin...
IRJET- Scheduling and Labour Management for Residential Building Project usin...
 

Ähnlich wie Construction Programming Strategy in Malaysia – Size Matters?....Or does it?

Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
gilpinleeanna
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
Mary Stevenson
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
melchioreq
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On Primavera
Gina Buck
 
PART 2
PART 2                                                            PART 2

Ähnlich wie Construction Programming Strategy in Malaysia – Size Matters?....Or does it? (20)

Good scheduling practice
Good scheduling practiceGood scheduling practice
Good scheduling practice
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
Module Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docxModule Three Project Scope, Planning, and Time Management.docx
Module Three Project Scope, Planning, and Time Management.docx
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
Modul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatanModul 06 penentuan durasi kegiatan
Modul 06 penentuan durasi kegiatan
 
H1303024956
H1303024956H1303024956
H1303024956
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On Primavera
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Why is a Construction Programme Important - RG Group.pdf
Why is a Construction Programme Important - RG Group.pdfWhy is a Construction Programme Important - RG Group.pdf
Why is a Construction Programme Important - RG Group.pdf
 
Project cost management a simplified approach white paper - Oracle Primaver...
Project cost management   a simplified approach white paper - Oracle Primaver...Project cost management   a simplified approach white paper - Oracle Primaver...
Project cost management a simplified approach white paper - Oracle Primaver...
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
PART 2
PART 2                                                            PART 2
PART 2
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Delay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme ErrorsDelay Analysis - Correcting for Programme Errors
Delay Analysis - Correcting for Programme Errors
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 

Kürzlich hochgeladen

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
MateoGardella
 

Kürzlich hochgeladen (20)

Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
PROCESS RECORDING FORMAT.docx
PROCESS      RECORDING        FORMAT.docxPROCESS      RECORDING        FORMAT.docx
PROCESS RECORDING FORMAT.docx
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 

Construction Programming Strategy in Malaysia – Size Matters?....Or does it?

  • 1. 1 May 2013                     Page 1 of 2 Construction Programming Strategy in Malaysia – Size Matters?....Or does it? The  construction  programme  plays  a  significant  role  in  project  monitoring  and  control for any size of  project.   Many  people  believe  that  a  good  programme  should  contain  many  thousands  of  activities    capturing  every  minute aspect of the works.   On  the  other  hand,  some  industry  practitioners  consider  that  an  effective  programme  should  be  developed  to  incorporate only the key elements of work.  They  reject  the  concept  of  having  large  numbers  of  very  detailed  activities  built  into  the  programme  simply  for  the  perception  of  it  looking  “professional”  or  sophisticated. The supporters of the simple  programme  approach  argue  that  a  programme needs to be only large enough  to  preserve  the  primary  function  of  predicting  accurate  forecast  dates  for  use  during the project life and at the same time  being capable of efficient management.     In  this  article,  we  will  examine  the  ‘pros’  and  ‘cons’  of  programme  size  contrasting  the  advocates  of  “the  more  activities  the  better”  with  those  promoting  concise  and  manageable programmes.    What a programme does  A  construction  programme  is  usually  a  mandatory  element  in  modern  construction  management.  A  good  and  effective construction programme provides  the  construction  team  with  the  tools  for  project  monitoring  and  control  during  the  construction stage. The major benefit of a  good  construction  programme  is  that  it  functions  as  a  performance  indicator  to  monitor  performance  of  site  field  work  against  that  originally  planned  (the  baseline)  so  as  to  alert  at  the  earliest  opportunity any  risk of the project being in  delay. In addition, the programme provides  a  guide  to  the  project  team  in  respect  to  the  future  activities  so  that  resources  can  be  properly  arranged  sufficiently  in  advance.   Moreover,  contemporaneous  programmes  are  an  essential  part  of  the  project  documents  used  in  delay  analysis  in  the  event that such a study is later necessary.   Detailed  construction  programme  –  does  size matter?   Because  of  some  of  its  benefits,  some  practitioners  in  the  construction  industry  opt  for  a  very  detailed  construction  programme as their way of developing the  Baseline Master Programme.   Their  reason  is  that  more  detail  means  better  monitoring  and  control.  It  is  often  the case that, in a complex project such as  the  construction  of  a  new  airport,  MRT  project or industrial processing facility, the  level  of  detail  in  the  Baseline  Programme  could potentially be so large as to contain  more  than  10,000  activities.  The  logic  dependencies  of  the  programme  may  exceed  two  or  three  times  the  activity  number; in this example, 20,000 to 30,000  activity  links  to  create  the  networked  programme.   It  may  be  true  that  a  comprehensive  updated  detailed  programme  arguably  provides  ready  information  in  respect  of  the  status  of  the  work  at  the  time  and  it  provides  a  guide  as  to  what  needs  to  be  done for the coming months.  On the other  hand,  the  manageability  of  such  a  large  network  may  outweigh  the  benefits  in  a  complex  project  as  there  are  too  many  activities against which to record progress  at the time of update.   Due to the enormous number of activities  in  the  programme,  the  updating  of  activities  requires  a  considerable  staff  resource to accomplish. A sizeable planning  team to manage such operation is required  given  the  time  required  for  the  team  to  research  and  collate  as‐built  dates  and  percentages  of  completion.  More  time  is  required  to  review  and  scrutinise  the  integrity of the programme at the time of  update.  In  many  cases,  the  same  team  would  be  tasked  to  attend  programme  coordination  meetings,  all  other  meetings  as  well  as  the  preparation  of  weekly  and  monthly  comprehensive  reports,  just  to  name a few in the Malaysian scenario.   It  is  likely  that,  due  to  the  budget  constraints  of  a  project,  the  planning  department  of  an  organization  would  not  have been allocated sufficient resources in  the form of experienced planners such that  the complex detailed programme could be  properly and accurately updated. It follows  that,  the  practicality  and  accuracy  of  the  updated construction programme suffers in  that it loses its main function as a ‘crystal  ball’  or  tool  for  projecting  future  event  dates.    Simple  Construction  programme  –  this  can’t be right?   It is a common and general perception in  the Malaysian construction industry that a  less  complex  and/or  less  detailed  programme would be less “professional” or  sophisticated and therefore less useful. For  such  a  reason,  many  major  players  in  the  industry  in  Malaysia  reject  a  simple  programme as the Baseline Programme for  a complex project. A common complaint on  the simple programme approach is that the  programme does not capture or reflect the  full scope of the work.   It  may  be  true  that  a  simple  construction  programme  may  lack  the  luxury  of  informing  the  project  team  in  a  precise  detailed  manner  such  as  ‘Construct  Level  40  –  Zone  2  –  Structural  Slab  –  Form  /  Rebar / Concrete’.  However, a simple and  higher  level  programme  would  be  able  to  perform  the  same  function  as  that  of  a  detailed  programme.  For  such  reason,  a  simple  programme  may  not  lose  the  functionality of being a useful programme  as it nonetheless covers the major scope of  the work.    In the above example, by reference to the  simple  construction  programme,  the 
  • 2. 1 May 2013                     Page 2 of 2 Construction Programming Strategy in Malaysia – Size Matters?....Or does it? procurement  department  will  still  be  able  to  identify  when  they  need  to  place  an  order  and  the  required  delivery  of  the  relevant reinforcement for Level 40 slab by  reading  the  construction  activity  in  the  simpler  programme,  i.e.  “Construct  Level  40 Slab” as opposed to those of the more  detailed programme, e.g. “Construct Level  40 ‐ Zone 2 –Structural slab – Rebar” and  similar in other Zones.  The benefit of using a simpler construction  programme for a complex project is that a  higher  level  programme  is  easier  to  manage.  This  is  especially  true  when  the  programme  is  updated  and  programme  logic might be revised to ensure a correct  reflection  of  the  sequence  of  work  at  the  time for projecting future event dates.   In many cases, an updated highly detailed  programme  of  over  10,000  activities,  despite  its  comprehensive  and  detailed  coverage  of  the  works,  suffers  inaccuracy  as a result of wrong or lax input of accurate  dates and progress percentages; the logic is  unlikely to have been properly reviewed or,  if  necessary,  revised  due  to  the  fact  that  there  are  quite  simply  too many  activities  to handle.   This  situation  would  be  further  complicated  with  the  incorporation  of  other  additional  sub‐programmes  into  the  Master  Programme.  For  example,  the  interior  design  (ID)  work  detailed  programme  for  a  shopping  arcade  by  a  specialist sub‐contractor. Such a detailed ID  works  programme  could  contribute  yet  another  3,000  to  5,000  detailed  activities  into the master programme.   With  application  of  this  programming  approach,  the  final  result  could  be  the  creation of an unwieldy “monster”.   Conclusion  A  sophisticated  and  detailed  construction  programme as the Baseline Programme is a  viable  construction  programming  strategy  only as long as it can be properly managed  by experienced and a sufficient number of  planning  staff.  In  addition,  it  is  equally  important  that  the  planning  team  has  sufficient  cooperation  and  support  from  the  project  team  and  are  not  left  to  operate  in  isolation;  the  planning  team  must  be  constantly  made  aware  through  feedback  from  the  project  team  as  to  construction status and changes.   In reality, it appears difficult in Malaysia to  have this ‘dream team’ as identified above.  In  many  cases,  due  to  the  financial  constraints of a project, the planning team  is  rarely  given  sufficient  resources  to  manage  very  large  and  complex  programmes.   There  are  cases  where  the  planning  team  lacks the full support from the construction  teams  in  order  to  update  every  single  activity  in  a  detailed  programme.  Therefore,  due  to  misleading  or  incorrect  data  sources,  a  very  detailed  programme  becomes of little practical use in achieving  the original intention.   In  such  circumstances,  a  simple  construction  programme  would  make  better sense; it is easier to manage (fewer  activities) and it can still be practically used  for  accurately  projecting  future  activity  dates  and  completion  of  the  project  as  a  whole.   Any shortcomings of a simple construction  programme  (viz.  to  address the  complaint  it does not fully cover the scope of work)  can  be  remedied  by  other  means  such  as  standalone mini‐programmes.   To  summarise,  in  the  view  of  the  author,  size doesn’t matter; the simpler, the better.    This article is written by Pang Yoon Sang,  Senior Consultant, Hill International Inc               Hill International Malaysia Sdn Bhd. Level 7 Unit 7 Block 3B Plaza Sentral Jalan Stesen Sentral 5   KL Sentral 50470 Kuala Lumpur, Malaysia. Tel: +65 6338 2455 | Fax: +65 6339 8568 |   E: advice.msia@hillintl.com | W: www.hillintl.com              Hill  International  is  a  leading  construction consultancy firm providing  innovative  program  and  project  management,  management  consulting,  tender  assistance,  dispute  mitigation/resolution  and  construction  consultancy  services  to  public  and  private  clients  worldwide.    We  specialise in construction risk mitigation  and avoidance.     Additionally, we offer a full spectrum of  services to assist clients to successfully  manage  capital  construction  programs,  from  initial  feasibility  through  implementation  and  contract  closeout.   Hill has served public and private sector  clients  in  many  varied  projects  from  public works, transportation, hotels and  resorts,  leisure  and  amusement  parks  and  sports  complexes  to  heavy  industrial  projects  such  as,  power  &  nuclear  plants,  pipelines,  refineries,  offshore  and  onshore  oil  refineries,  petrochemical  plants,  public  utilities,  water  and  sewer  systems  and  treatment plants.       Hill  International  currently  has  over  3,800  employees  in  100  offices  worldwide  providing  program  management,  project  management,  construction  management  and  construction  claims  services.  Hill  International,  Inc  is  listed  in  NYSE.  For  more  information  on  Hill,  please  visit  our website at www.hillintl.com.  Disclaimer:  This  article  does  not  constitute  advice,  legal  or  otherwise,  and  is  provided  only  as  general  commentary.  Appropriate professional advice should always be obtained before  taking  or  refraining  from  taking  any  action  in  relation  to  such  information and/or the application of applicable law. This article and  the  materials  contained  in  it  are  provided  on  the  basis  that  all  liability for any loss or damage, whether direct or indirect, arising  out of or in connection with any use or reliance upon this article is  excluded to the fullest extent permitted by law.