Considerations in Selecting and
 Protecting Your IT Investment

             Helene Heller
            Senior Director

           Office of the CFO
    New York City Housing Authority


              copyrighted © 2005 NYCHA
Agenda

• Enterprise IT
• IT Governance
• IT Portfolio Selection And Management
  Methodologies
• Making the Business Case
• Project Management at NYCHA
• PMO Automation
                                          More…

1/15/06                                      2
Why is this an important topic?

• Fiscal realities dictate selective IT investment

• Technology/tools chosen need to support the business
  problem/challenge or opportunity

• Project management should guarantee that the
  selected technology works, the business problem has
  been solved, and the investment was contained

• Projects utilizing technology should support improved
  business processes and therefore be led by a business
  owner

• Business owners shouldn’t have to be professional
  project managers

1/15/06                                                   3
How To Balance IT and Business
 Drivers: Client Funded Model




   IT                                 Client
          Infrastructure   Business
              Costs         Value
Drivers                               Drivers




1/15/06                                    4
How does an Enterprise IT Structure Fit?

            Business Challenges:

  • Project requests are often “siloed” resulting in
    limited benefits to the organization
  • Requests address only a slice of an end-to-end
    business process
  • Projects aren’t supported by a strong and consistent
    business case often resulting in unclear scope
    and/or failed completion
  • Multiple technology platforms and solutions
    supporting similar business functions in different
    departments, are expensive and inefficient to support
                                                       More…

1/15/06                                                     5
Enterprise IT Structure Example

          Mapping IT Support to Business Objectives

  Effective          Vision, Objectives,
                                              Strategic Plans
  Business and IT    Business Results
  Collaboration

                  Processes, support, and
  Infrastructure tools that enable business     Application
                          functions
  Services                                      Development

                       Supporting                 Enterprise
   Project
                       Foundation                 Architecture
   Management
                      Accountability
   Discipline
                         Metrics                           More…

1/15/06                                                          6
What is IT governance?
As Defined by Gartner:

•   IT governance provides a framework in which the decisions made
    about IT issues are aligned with the overall business strategy and
    culture of the enterprise

•   Governance is concerned with setting directions, establishing
    standards and principles, and prioritizing investments.

•   The process of assigning decision rights is influenced by corporate
    culture, business orientation, stakeholders' opinions and the
    knowledge required of decision makers.


•   Effective it governance involves the assignment of decision-making
    rights and accountabilities regarding behavior in the desirable use
    of it.

1/15/06                                                                  7
IT Governance Example
  © copyright NYCHA 2003-2005

                Role of the Project Management Office (PMO)
                            NYCHA Board


                               NYCHA
                           General Manager

                                                                                     Provide
                                 Input &
                                                  GM’s Operations
      NYCHA                                                                                         NYCHA
                                                                                   Membership
                                Feedback
      CIO/CFO                                       Committee                                       DGMs

                                            Monthly Executive Project Status Reports


          PMO                                                                                       Business Unit
                              Provide
   Project Repository                                                                              Staff Reporting
                                                                                        Project
                                        Project                Project
 PM Consulting & Advice       Liaison
                                                     or                     or                        Structure
                                                                                        Steering
                                        Manager                 Team
 PM Standard Methodology
                                                                                       Committee
 & Tools
 PMO Reporting Standards
 Assistance & Coaching                       Weekly/Monthly Project Manager Status Reports


                                                           Dept. Project
                                                            Manager(s)                                     More…

1/15/06                                                                                                              8
Why is a Portfolio Approach Relevant?


• An organization must understand its goals,
  have a flexible process to determine priorities
  based on changing environments, and select
  projects that will provide meaningful
  improvement to:
     –Customer satisfaction
     –Employee productivity
     –Business process improvements
     –Cost take-out from the operating budget


1/15/06                                             9
Portfolio Management Approach –
Ongoing Process
                                             Portfolio
                                            Management

                                                                                                              GM
                         • Portfolio scope
                         • Prioritize& optimize overall IT cost, benefits, risk
                         • Actively monitor Portfolio performance
                         • Adapt to business environment changes                                  Quarterly
   Annual
                                                                                                  Portfolio
  Planning
                                                Program                                           Reviews
                                               Management
                                     •   Comprehensive program planning
                                     •   Change and risk management
                                     •   Coordination of project delivery               Monthly
                                     •   Measurement of results                         Program
             Quarterly
                                     •   Corrective actions                             Reviews
             Planning

                                                  Project
                                                Management                                                DGM
                                                           •   Deliverables
                                           •   Initiate                       Weekly
                                                           •   Scope
                                           •   Budget
                            Monthly                                           Project
                            Planning
                                                           •   Risks          Reviews
                                           •   Schedule
                                                                                             PM
                                                           •   Measure                              More…
                                           •   Resources


1/15/06                                                                                                       10
How to select the enterprise portfolio – Before

             Key Care-Abouts                      Investment Criteria
 •   Identify key stakeholders who
                                          •Identify criteria for IT investment:
     run the business
                                          improve business process, save
 •   Understand their goals and           money, break-down business
     priorities, what keeps them up at
                                          silos, etc.
     night, and what gets in the way of
                                          •Apply criteria against list of
     doing the job that supports their
     goals                                potential projects
 •   Use this knowledge to brainstorm
     potential IT solutions
                                                     Business Case
           Enterprise Solutions
                                          •Identify executive sponsor and
 •   Look for patterns among              project manager from the business
     solutions of all stakeholders
                                          •Project manager completes a
     interviewed
                                          project concept document
 •   Identify opportunities to
                                          •Project concept documents are
     implement one solution for
     multiple functions or department     presented to IT governance
                                          committee for selection

 1/15/06                                                                      11
How to select the enterprise portfolio - After
   Step One:                                         Step Three:
   •   Started with NYCHA's published “5 year             • Six categories of aggregation emerged:
       plan for fiscal years 2005 – 2009” as                   – Compliance
       submitted to HUD
                                                               – Cost takeout/employee productivity
                                                               – New partnerships
   •   Extracted business goals from these
                                                               – New revenue
       plans and hypothesized on Executive’s
                                                               – Nycha-wide initiatives
       business goal correlation and
       opportunities                                           – Resident care
                                                          • Each goal was analyzed based on the key
                                                             impact areas of people, process, & technology.
   •   In partnership with NYCHA's CFO
                                                             Goals where technology could play a role were
       conducted 1:1 sessions with DGMs to
                                                             identified and presented to the GM who
       validate business goals, key success
                                                             requested a policy planning offsite
       metrics and solutions, in the context of
       spring financial planning – 60 solutions
       resulted
                                                     Step Four:
                                                          • Building on all of the above planning and using
   Step Two:                                                 the same planning matrix as step one –
                                                             portfolio methodology was developed
   •   Results Were Aggregated & Refined After
       a Review with the General Manager                  • Impact categories were refined:
   •   Example:                                                – Customer satisfaction
Hugh Spence – DGM for Community Operations
                                                               – Resource enhancement
1.    One Voice Portal
2.    Automated DOH Licensing Information                      – Financial savings
3.    Automated Social Services Case Management
                                                          • Information sets such as: category, sponsoring
4.    Resident Employment Training & Tracking System
                                                             department, forecasted cost & benefits, & FTE
5.    Community Center Internet Connectivity                 NYCHA project resources were presented in
6.    Reduce Duplicate Function – Community Center           chart, graph & pivot table format to enable a GM
      Construction Operations                                review of 26 projects for prioritization

   1/15/06                                                                                               12
Application & Solutions Portfolio – NYCHA Today

Step Five:
• Balancing resource impact, risk, funding,
  departmental involvement & customer
  improvements, A tiered approach was
  developed by the General Manager
• Application / Solution Portfolio
   • Tier 1 Top Priority Business Initiatives
   • Tier 2 Emerging Business Initiatives (business case
     this year)
   • Tier 3 Managed by IT (limited or no business PM
     involvement)
   • Tier 4 Future Year Initiatives


1/15/06                                                13
How to Make the Business Case


• Elevator pitch: what is the business problem, challenge
  or opportunity? Why should the executive care?
• Describe in layman’s terms a credible potential solution
• Define metrics that will show the executive that the
  solution has successfully addressed the business
  problem/challenge/opportunity
• Document the cost of doing business the current way v.
  the new way that the solution will promote
• Compare to best practice examples




1/15/06                                                  14
Business Case Components
Project Team and Stakeholders         Project Approach
   • Executive Sponsor                   • Estimated Project Resource
                                           Requirements
   • Project Owner/IT Partner
                                         • Implementation Approach
   • Impacted Personnel
                                         • Estimated Duration of
Business Context
                                           Implementation
   • Business Problem
                                         • Procurement Recommendations
   • Business Goals
                                      Cost/Benefit Analysis
   • Business Functional Objectives
                                         • Methodology and Analysis
   • Metrics
                                           Results/ROI
Proposed Solution                        • Estimated Project Cost
   • Solution Description                • Funding Source(s)
   • Alternatives Considered
                                      Risk Management Plan
   • Rational for Selection
                                         • Barriers
   • Product Selection
                                         • Probability of Risk
   • Consistency with IT Strategy
                                         • Mitigation Strategy

1/15/06                                                                 15
The Goal of the IT PMO Discipline at NYCHA



          Provide the end-to-end project
          delivery and project management
          processes, standards, best
          practices, and tools to enable the
          organization to achieve far higher
          levels of performance, rapidly
          delivering big wins with positive
          financial impact.

1/15/06                                        16
PMO Roles
                                                      Project Coach
          Project Repository
                                              •   Best practice sharing across
   •   Source of information on project
                                                  organization functions and
       methodology and standards
                                                  coordinates communication
   •   Facilitates the use of a cohesive
                                              •   Raises organizational
       set of tools for project design,           performance -- mentoring
       management and reporting                   relationships may be established
                                                  across business boundaries
   •   Empowers distributed, business-
                                                  between high and low performing
       centric project ownership
                                                  project managers
   •   A first step to enfranchise the idea
                                              •   The PMO is a permanent structure
       of consolidating or sharing                and has some supervisory
       management practices but does              responsibility for all enterprise
                                                  business projects
       NOT provide direct project
                                              •   A quot;dotted linequot; reporting
       management
                                                  relationship from business-staffed
                                                  project managers and to the CIO


1/15/06                                                                          17
Functions of a Virtual IT PMO
                                                  IT PMO
    Project                                                                 Project            Communication
                            Resource                  Project
  Management                                                                 Review                  and
                            Evaluation               Planning
   Standards                                                               & Analysis           Collaboration

                                                                                               5. Providing
                                                 3. Responsible
1. Developing a                                                         4. Consistently
                         2. Ensuring the
                                                                                                  continued
                                                    for guiding
   standardized PM                                                         monitoring
                            optimization of
                                                                                                  program
                                                    each project’s
   methodology,                                                            projects to
                            organization
                                                                                                  visibility to the
                                                    planning
   process and                                                             ensure they
                            resources in
                                                                                                  Executive
                                                    efforts
   tools for                                                               are kept on
                            projects
                                                                                                  Team and
   effective project                                                       track and are
                                                                                                  facilitating
   management                                                              completed
                                                                                                  maximum
   across the                                                              successfully
                                                                                                  multi-level
   organization
                                                                                                  collaboration
                                  Resource Database          Collaboration Software           PM Methodology
   Vendor Info. Database




                               Knowledge Management           Exec. Info. System (EIS)
    Tools and Templates                                                                    Education Mgmt System




     Slide modified from two Gartner concept slides © copyright Gartner, Inc. 2002

1/15/06                                                                                                               18
NYCHA IT Project Lifecycle
   © copyright NYCHA 2003 - 2005


                                           Evaluation and
                                           Enhancement
                                  Metrics, Status, and Change Management

                                                                                          Support/
              Initiation        Planning            Execution              Close Out      Maintenance
       Concept Commit      Execution Commit   Design/Dev/Test/Deploy                      Production
                                                                        Lessons Learned




               Select
                                                                                   Refine
Prioritize     investments
                                                                                   Project
initiatives
                                                                                   Course
       Strategic Planning
                                                                       Metrics & Reviews Review
       And Analysis
                                                                                        Portfolio
            Align
            objectives                                                          Communicate
                                                                                status
  1/15/06                                                                                               19
The IT PMO Functional Blueprint at NYCHA
 © copyright NYCHA 2003-2005




Executive Sponsorship
                                               Executive Management Team




                             Business          Application Development
Concept, Justification,                                                  IT Infrastructure
                               Units
Execution, and Operations


                                                             Quality
                                          Procurement
                                                            Assurance



Collaboration,
Orchestration,
                                         IT PMO (Includes Budget Partner)
and
Coaching


                                                                             Enterprise
                                                          CIO
                            Exec. for Policy
Change Management,                                                          Technology
Standards, and Policy                                                         Architect


1/15/06                                                                                      20
Initiation Phase
Overview © copyright NYCHA 2003-2005

                                    Evaluation and Enhancement
                                      Metrics, Status, and Change Management

             Initiation            Planning             Execution              Close-Out          Support /
                                                        Execution
                                                                                                 Maintenance
        Concept Commit        Execution Commit   Design/Dev/Test/Deploy   Lessons Learned       Production


 Phase Overview
   •   The Initiation Phase sets the tone for the project

   •   The Initiation Phase is a collaborative approach of presenting a particular NYCHA business problem,
       challenge or opportunity defining a particular project to address the business issues(s) and identifying
       anticipated benefits which NYCHA expects to realize by undertaking the project.

   •   A Project Concept is required by an executive sponsor in order to get a sense if the project should be
       pursued.

   •   The Enterprise Portfolio IT selection process utilizes the materials in the project concept document to
       determine appropriate project next steps, including Pilot, Process Re-engineering or Business Case
       Development prior to commitment to move to the Planning Phase

   •   If a commitment is not provided, NYCHA may decide to revisit the project at a later date, re-define the
       project scope or terminate the project

 Entry Criteria           Business Unit Executive Sponsorship
 Exit Criteria            GM’s Operations Committee Decision to Sponsor Project to Planning Phase


  1/15/06                                                                                                      21
Initiation Phase
 Activities and Deliverables © copyright NYCHA 2003-2005




1/15/06                                                    22
Initiation Phase
 Activities and Deliverables © copyright NYCHA 2003-2005




1/15/06                                                    23
How to Scale a PM Standard Throughout the
 Enterprise: The Role of Automation



  • Project Dashboard
  • Knowledge Management &
    Collaboration Repository
  • Planning/Tracking
  • Risk Management
  • Reporting/Issue Management
  • Automated Compliance


1/15/06                                      24
PMO: Project Dashboard

•Overview: The Virtual IT PMO: a
comprehensive view, defined by user       Illustrative
role, for all the news and information
about NYCHA projects

•Users: Project team, executive
sponsors and anyone who needs to
learn more about the projects, or
need to know about status

•Elements: Workflow navigation
that guides the project manager
through the required project lifecycle.
Provides current project status,
project plan and timeline, issues and
risks logs, and link to repository
which stores past status reports and
other project-related information.

•Owner: PMO

1/15/06                                                  25
PMO: Collaboration Space

•Overview: A common repository for all
                                                Illustrative
project related document storage and
collaboration facilitation

•Users: PMO, project managers and
team members, and anyone needing
access to knowledge management

•Elements: Contains current and
historical documents and completed PMO
templates, past status reports, updated
issues and risk logs, etc. Provides version
control and authentication. Information
clearly segregated in open and protected
folders with links provided to any other
required website (e.g., NYCHA intranet).

•Owner: PMO with project managers for
their specific folders (collaboration spaces)


1/15/06                                                        26
PMO: Planning/Tracking

•Overview: The overall detailed,
activity-based plan for the project using
Microsoft Enterprise Project Server

•Users: PMO, project managers and
delegated team members, steering
committee, executive sponsor

•Elements: Planning and tracking
information in Web-based views as
detailed a view as selected by the user.
Information comes from Project Server.
Data is hierarchical and can be expanded
or collapsed to view a snapshot of the
entire project. This is what feeds the
dashboard.

•Owner: Project managers maintain the
ownership of each plan


1/15/06                                     27
PMO: Risk Management

  •Overview: Automated Compliance
  to Ensure Risk Management Plan
  Adherence and Regular Review

  •Users: Project manager leading their
  team, executive sponsor, other
  executives

  •Elements: List of all the project risks,
  their severity, impacted areas, likely
  impact (delay, budget increase) and
  mitigation strategies. Starts in Initiation
  Phase to populate the required
  documentation throughout the lifecycle,
  includes the risk management plan, risk
  log and status reports.

  •Owner: Project managers


1/15/06                                         28
PMO: Reporting
                                               Automatically Completed for
  •Overview: A set of templates to                        you!
  report the status of the project and               (can be edited)
                                                                    Illustrative
  overall portfolio throughout the lifecycle

  •Users: PMO, project managers,
  steering committee, executive sponsor,
  governance committee, CFO, Board

  •Elements: InfoPath templates, SQL
  database and web-based reporting.
  Project level template for each project.
  Three status reports depending on the
  audience - includes an overall
  red/yellow/green status assessment with
  the high level explanation followed by
  major accomplishments, key issues and
  upcoming milestones.

  •Owner: Project Manager with PMO
  review on monthly and quarterly reports

1/15/06                                                                            29
Additional Notes Slides
 Supplemental Notes Where
“More” Has Been Indicated on
the Bottom-Right Hand Side of
  the Slide: 2, 5, 6, 9 and 16


          copyrighted © 2005 NYCHA
More from Agenda Slide: NYCHA Historical Context
Let’s talk about some of the environmental factors that were in place almost three years ago, when the new CIO first
     thought about the establishing a formalized governance structure. The fiscal realities that presented themselves
     when he started, and what he saw in the technology environment in April of 2002:
At NYCHA, our primary issue was the lack of an overall information-technology governance process, and that
     manifested itself in a variety of ways. One was that projects that got supported and funded were identified through
     a specific line of business, and not considered in its enterprise sense. So if a business owner had a particular
     need for a technology-support tool, that tool was built specifically for that business owner without any
     consideration for the overall enterprise requirement. Historically, the application of that process, created a series
     of business applications that were not integrated -- they were siloed with respect to support, and with respect to
     the delivery of the solution. A specific line of business then had its own platform, its own business application, and
     its own relationship with the technology-support organization. And, even its own IT staff.
This would be repeated across the various lines of business, so the result was seven or eight different computing
     platforms, multiple technology solutions that run on those platforms, and staff that was dedicated to support those
     various platforms and solutions. The initial objective was to reorganize the technology organization into a full
     enterprise support and service organization by removing these silos, but also recognizing that over time that we
     would continue to have some of these specific platforms that would need to be supported.
We wanted to create a single technology organization that considers the primary support requirements in terms of
     technology infrastructure and business-application support.
At the same time, it became very clear that the fiscal situation at NYCHA was indeed changing. Funding that NYCHA had
     been accustomed to throughout the years, primarily from HUD, had essentially dried up. And so we had to come up
     with ways to make a decision, about how technology investments could be leveraged across multiple business
     requirements within the enterprise.
So, for example, there should not to be a separate inspection system for each line of business, but rather an enterprise-
     wide inspection system that would support each line of business. And as a means to that end, three things
     occurred: the creation of a project-management process; the reorganization of the technology organization; and
     putting into place a governance or a technology-investment consideration and support structure that would govern
     the process going forward.
To summarize, there are a lot of culture-change factors occurring at the same time. So, it actually was a challenge, but
     also a terrific opportunity. On the one hand, we were going from a system within NYCHA, that allocated funding for
     projects based on individual requests that came in, and individual analysis of these requests, to a process where
     departments had budgets, budget responsibility centers, financial planning, (encumbrance)-based budgeting, and
     the like. And all of this was happening at the same time that we were implementing a comprehensive, enterprise-
     wide financial-management system. So that was one major opportunity.
                                                                                                                     Back


 1/15/06                                                                                                               31
More from “How Does Enterprise IT …Fit” Slide:
When you don’t have a clear project-management process in place you get lots of different information -- requesting
     the same thing. So, here you might be an executive who has to make a funding decision, and you really don’t
     know what you’re getting because everyone who’s submitting a request for a project is submitting different
     information. A t the end of the day you don’t have to be a technology expert. If someone comes to you with a
     request for project and spends all that time talking about the technology and this is not an area that you’re
     familiar with, how comfortable are you going to be in making a decision to fund a project?
What’s good about having a consistent project-management discipline is that each project manager is guided by a
     consistent set of questions to, let’s say, make a business case. So the business case ends up being stronger.
     It’s more consistent. This addresses the challenge that we had historically where the scope is unclear, the
     project maybe failed in completion. One example, anecdotally, was $15 million allocated to some sort of human-
     resource management system, and all the $15 million was spent but at the end of the day we only yielded $1
     million in functionality, if you really look at the scope, because it was unclear. There was no consistent process.
     There was no consistent approach, but all the money was spent.
Finally, when you address funding of IT requests independently of each other without a clear enterprise structure,
     you end up with all these multiple technology platforms, performing perhaps similar business functions in
     different departments, and you’re not developing the benefit of having one solution where staff is trained to run
     that solution that multiple departments can use. The opportunity to accomplish all of this today is that the chief
     information officer position was created at NYCHA . If it existed before, it really existed in title, not in reality,
     and it certainly wasn’t at the deputy general manager level. Why that’s important is, ostensibly we’re a very
     large organization, a large corporation, if you will, that’s run by a general manager who reports to a board. The
     general manager is like a CEO, and underneath him he has executives, deputy general managers, there are
     seven of them, that really are responsible for the day-to-day operation of this large corporation.
In creating the chief information officer at the deputy general manager level, you’ve basically made the chief
     information officer a peer to all the executives who are responsible for running the authority. That’s significant
     because, not only does that position now have the clout to implement and champion and effectively coach this
     sort of discipline, but they have a seat at the table where all these policy decisions are being made, so they have
     more insight into the primary business goals of the enterprise.
It shows what an important role technology is playing within this organization. A t the end of the day, this all starts
     from the top. It’s embraced bottom-up, but it comes top-down, and that’s very significant. It’s very significant
     for this to be considered as important as any other initiative in the enterprise. In addition, because there wasn’t
     this process of stating what services were required, what technology was going to do, it was very fragmented, it
     was distributed across different organizational silos, people just handed things off. People didn’t know what
     other business units did, and lost the opportunity to collaborate and have a more effective solution.
A nother result is that when you have a bifurcated enterprise IT organization, there is no proper expectation on
     behalf of the customer of the type of response they’re going to get, the time that they’re going to get their
     response addressed, the hand-off that they’re going to get to three other people to address what is a very
     straightforward request or need from the IT organization. There is no good issue resolution or tracking of
     issues. Most importantly, there isn’t a good balance between what the need is from the customers for service,
     and what the capabilities are of the organization to actually address and support those services.
In that type of environment there is an inability to actually measure costs and the benefits relative to what’s being Back
     provided- to be able to make a good decision as to whether or not we could provide the services internally or we
     should go externally.


   1/15/06                                                                                                           32
More from “Enterprise IT Structure Ex. Slide
Why was this organization put in place, what are the important elements and why?
The primary driver for implementation technology has to be a sound business plan and an effective
    vision for where the organization is headed. On the basis of that type of plan, a technology
    strategy can be developed that effectively aligns with that plan. In order to carry out the
    technology strategy, the organization has to consist of infrastructure support and development in
    the growth of the infrastructure, and at the same time the development of the business solution.
    To govern that organization model, what’s needed is an effective process and discipline to
    manage technology initiatives, and have a clear blueprint of the technology architecture that
    would evolve to support the overall strategy.
What we ended up with are two operational units: an IT infrastructure group and an application-
    development group. These are the two groups that are responsible for the operations of IT,
    meaning the day-to-day programming, the day-to-day support of hardware, software, etc. Then,
    above that, as the policy-making organization, the coordination, the administrative organization,
    is the office of the CIO. Within the office of CIO is this function that we’re talking about today,
    this project and information-management function, with this virtual PMO process, the IT
    governance, the project-portfolio selection and management, the project-management discipline,
    but from a virtual sense, meaning setting the policy, the goals, the tones, facilitating, coaching,
    orchestrating.
Additionally within the Office of the CIO is an enterprise-technology architect, who is responsible for
    really understanding the business goals, but from the technology platform and solution and
    standard perspective. Within that function, the quality-assurance function, which you’ll see in our
    project-management discipline or project life cycle, we’ve institutionalized the importance of the
    role of quality assurance, why it exists in the office of CIO, reporting to the enterprise technology
    architect, is it’s important that that quality-assurance function not report to the operations group,
    the application-development group of the IT infrastructure group. With this type of organization,
    the CIO actually has a better understanding of what the objectives should be. He can
    communicate to his staff what his expectations are. There’s more accountability. There’s more
    of an understanding of what everyone’s role is within the IT organization, how that rolls up to the
    important business goals of the organization. Most importantly, he has a way of measuring all of
                                                                                                     Back
    this.


1/15/06                                                                                              33
More from “Portfolio Mgmt Approach” Slide
The methodology that we use is coming together. The point at which we select projects comes together at the same time
      as the financial-planning cycle, which is new to NYCHA . So that has been a terrific opportunity, to take advantage of
      this partnership because of the timing at which they are introducing this whole notion of semiannual financial planning.
      Then we have this opportunity to prioritize projects. So we have three types of projects at NYCHA , and to segment
      them and to come up with process-reporting requirements, depending on the nature of the project.
When we discussed the client-funded model, that we have central infrastructure projects, projects that are needed to
      make sure that we have this robust, scalable, dependable network, and those projects could range anywhere from
      introducing a new telephony technology, or upgrading the network operating system, or upgrading the e-mail system,
      or standardizing on the server platform, or developing a life cycle for PCs and laptops and servers. A ll of those
      projects are projects that our CIO and general manager like to refer to as inside (inaudible). These are things that he
      trusts the CIO to decide, that don’t really require much decision and discussion with the other executives, and these
      are projects that are going to be managed by IT.
That’s one group of projects where we are not going to bring them constantly before this governing body, which I will detail
      in a couple of slides. Then there are very small application-development projects, generally enhancements to existing
      applications where we have to make upgrades because perhaps a version of the software is no longer supportable, we
      had an audit finding perhaps, perhaps we need to upgrade based on an unsupportable platform to a different one. So
      these types of projects we have to do anyway, and really don’t need to, again, have the same sort of in-depth review
      by all of the executives.
The group of projects Called the enterprise IT business projects are what constitutes the portfolio of projects that are really
      focused on. The are the projects that we prioritize in terms of where we’re going to make the IT investment and what
      is going to be reviewed in terms of the entire portfolio. These projects consist of business solutions that are reviewed
      quarterly. We’ve now successfully gone through four quarterly reviews of the portfolio. Today’s quarterly review was
      Q1 05, which is our fifth quarterly review, and this is an opportunity -- currently we have 12 projects -- we’re probably
      going to winnow that down some in the next coming months, since some of our projects that are come on are very,
      very large projects. So we need to really bring that number down some.
It’s an opportunity for each of the project managers, again, directors, deputy directors, to come before our governance
      committee, which at the very least consists of all our executive sponsors, and give the same review, meaning answer
      the same questions of where their project is for the reporting period, which is the previous three months, and do it
      together. A ll of the project managers are going to discuss answers to the same questions, the same 90-minute
      session, so that the members of the governance committee can get a sense of the portfolio and make decisions about
      priorities if they need to. So this is part of our flexible environment.
There should be monthly program reviews with the executive sponsor, where there may be multiple projects that roll up to
      an overall program initiative. This gives the executive sponsor a way of understanding where their important program
      is going, how the different projects are working within their program, and also to give them more of an intimate
      interaction with their project managers on the projects that they’re ultimately responsible for. This is a way that they
      can really focus in on what the metrics should be, what results they should measure, and also gives them an
      opportunity to take corrective actions when there are some decisions that need to be escalated to them, that the
      project team hasn’t been able to resolve amongst themselves. A nd then of course, at the lowest level of the weekly
      reviews that are done by the project manager, and that’s the key project management, initiate, budget, schedule,
      deliverable scope, risks, resources, measures, and the like.
                                                                                                                      Back


   1/15/06                                                                                                               34
More from “IT Governance Example” Slide
The purpose of providing them with support is not to project-manage
  the process for them, not to dictate how they go about it, but to
  coach them, mentor them, and provide them with tools to help them
  move through their important projects’ life cycles. To that end,
  every time we go forward with a project where we require the
  business manager to -- the project manager to come to the
  business -- we give them an IT strategic partner. Going back to the
  example that we gave about the new IT organization, this customer-
  service approach, this organization can respond to the business
  needs of the organization and be effective -- it doesn’t matter what
  group they come from. They’re still responsible for any IT need that
  their project manager has. So, let’s say it’s the enterprise-
  technology architect. Application Development doesn’t report to
  him. The IT Infrastructure (ITI) team doesn’t report to him. But he’s
  still responsible for getting what’s needed from those groups for
  the project manager. So it’s this customer-service approach. And
  then finally, this PMO function, this virtual function, is really
  responsible for establishing standards, providing tools, developing
  the methodology, and of course, they report in to the CIO and also
  this partnership with the CFO, you could see this as a dotted line.
                                                                   Back


1/15/06                                                              35

More Related Content

What's hot

It portfolio management case study presentation
It portfolio management case study presentationIt portfolio management case study presentation
It portfolio management case study presentationMark Wilson Ramsay
 
The Chief Skeptical Officer – A New C-Level Role
The Chief Skeptical Officer – A New C-Level RoleThe Chief Skeptical Officer – A New C-Level Role
The Chief Skeptical Officer – A New C-Level RoleAlan McSweeney
 
Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Alan McSweeney
 
From Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio ManagementFrom Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio ManagementRoberto Toledo
 
On Kue Business Architecture101
On Kue Business Architecture101On Kue Business Architecture101
On Kue Business Architecture101Carolyn N. Evans
 
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...EPM Live
 
Project Portfolio Strategic Planning
Project Portfolio Strategic PlanningProject Portfolio Strategic Planning
Project Portfolio Strategic Planningvmakarov
 
It Alighnment10 V3.1
It Alighnment10 V3.1It Alighnment10 V3.1
It Alighnment10 V3.1James Sutter
 
10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processes10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processesgianarosetti
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio ManagementAnand Subramaniam
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio managementJuha-Matti Saario
 
Portfolio Management Pipeline
Portfolio Management PipelinePortfolio Management Pipeline
Portfolio Management Pipelinerichardbellatcity
 
Getting Some Respect - How to Measure and Communicate Your EA Success
Getting Some Respect - How to Measure and Communicate Your EA SuccessGetting Some Respect - How to Measure and Communicate Your EA Success
Getting Some Respect - How to Measure and Communicate Your EA SuccessDavid Baker
 
IT Project Portfolio Planning Using Excel
IT Project Portfolio Planning Using ExcelIT Project Portfolio Planning Using Excel
IT Project Portfolio Planning Using ExcelJerry Bishop
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinarAli Zeeshan
 
Project Benefit Validation - Lean Six Sigma
Project Benefit  Validation - Lean Six SigmaProject Benefit  Validation - Lean Six Sigma
Project Benefit Validation - Lean Six SigmaWillowTree Advisors
 
Why Symphini? The Symphini Change Management Approach
Why Symphini? The Symphini Change Management ApproachWhy Symphini? The Symphini Change Management Approach
Why Symphini? The Symphini Change Management ApproachSccharron
 
Impact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project SuccessImpact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project SuccessIman Baradari
 

What's hot (20)

Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012
 
It portfolio management case study presentation
It portfolio management case study presentationIt portfolio management case study presentation
It portfolio management case study presentation
 
The Chief Skeptical Officer – A New C-Level Role
The Chief Skeptical Officer – A New C-Level RoleThe Chief Skeptical Officer – A New C-Level Role
The Chief Skeptical Officer – A New C-Level Role
 
Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...Benefits Identification, Assessment, Validation and Realisation for Informati...
Benefits Identification, Assessment, Validation and Realisation for Informati...
 
From Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio ManagementFrom Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio Management
 
On Kue Business Architecture101
On Kue Business Architecture101On Kue Business Architecture101
On Kue Business Architecture101
 
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...
PPM Challenge #4: Improving PPM Maturity – 2012 PPM Challenge and Opportunity...
 
Project Portfolio Strategic Planning
Project Portfolio Strategic PlanningProject Portfolio Strategic Planning
Project Portfolio Strategic Planning
 
It Alighnment10 V3.1
It Alighnment10 V3.1It Alighnment10 V3.1
It Alighnment10 V3.1
 
10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processes10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processes
 
Project Portfolio Management
Project Portfolio ManagementProject Portfolio Management
Project Portfolio Management
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
 
Portfolio Management Pipeline
Portfolio Management PipelinePortfolio Management Pipeline
Portfolio Management Pipeline
 
Getting Some Respect - How to Measure and Communicate Your EA Success
Getting Some Respect - How to Measure and Communicate Your EA SuccessGetting Some Respect - How to Measure and Communicate Your EA Success
Getting Some Respect - How to Measure and Communicate Your EA Success
 
PROJECT PORTFOLIO MANAGEMENT at IT Services Hungary Ltd
PROJECT PORTFOLIO MANAGEMENT at IT Services Hungary LtdPROJECT PORTFOLIO MANAGEMENT at IT Services Hungary Ltd
PROJECT PORTFOLIO MANAGEMENT at IT Services Hungary Ltd
 
IT Project Portfolio Planning Using Excel
IT Project Portfolio Planning Using ExcelIT Project Portfolio Planning Using Excel
IT Project Portfolio Planning Using Excel
 
Project portfolio management - webinar
Project portfolio management - webinarProject portfolio management - webinar
Project portfolio management - webinar
 
Project Benefit Validation - Lean Six Sigma
Project Benefit  Validation - Lean Six SigmaProject Benefit  Validation - Lean Six Sigma
Project Benefit Validation - Lean Six Sigma
 
Why Symphini? The Symphini Change Management Approach
Why Symphini? The Symphini Change Management ApproachWhy Symphini? The Symphini Change Management Approach
Why Symphini? The Symphini Change Management Approach
 
Impact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project SuccessImpact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project Success
 

Viewers also liked

Dssh @ Confidence, Prague 2010
Dssh @ Confidence, Prague 2010Dssh @ Confidence, Prague 2010
Dssh @ Confidence, Prague 2010Juraj Bednar
 
Ilumtics corp profile_dec2011
Ilumtics corp profile_dec2011Ilumtics corp profile_dec2011
Ilumtics corp profile_dec2011Thanh Nguyen
 
EEC '12 - RiderState presentation - 2012
EEC '12 - RiderState presentation - 2012EEC '12 - RiderState presentation - 2012
EEC '12 - RiderState presentation - 2012Santi Casado
 
Polo 444 Design Story
Polo 444 Design StoryPolo 444 Design Story
Polo 444 Design Storybrookbanham
 
Evidence management-from-theory-to-practice-in-health-care
Evidence management-from-theory-to-practice-in-health-careEvidence management-from-theory-to-practice-in-health-care
Evidence management-from-theory-to-practice-in-health-careslwrel
 
Processing workshop intro
Processing workshop introProcessing workshop intro
Processing workshop introJuraj Bednar
 
Embedding BCE - Introduction
Embedding BCE - IntroductionEmbedding BCE - Introduction
Embedding BCE - IntroductionJISC BCE
 
Showing your business in the Best Light...Silver Moon Photography
Showing your business in the Best Light...Silver Moon PhotographyShowing your business in the Best Light...Silver Moon Photography
Showing your business in the Best Light...Silver Moon PhotographySilver Moon Photography
 
Dhwani09 Lonewolf - Theme
Dhwani09 Lonewolf - ThemeDhwani09 Lonewolf - Theme
Dhwani09 Lonewolf - ThemeJithin Jacob
 
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis Liability
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis LiabilityThe Small Company Clinical Study SponsorRoles & Duties Vis-à-vis Liability
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis LiabilityMichael Swit
 
Computer Aided Engineering Design
Computer Aided Engineering DesignComputer Aided Engineering Design
Computer Aided Engineering Designer.mitulpatel
 
Vvd Ppt Presentatie Infra Debatavond Regio Krimpenerwaard
Vvd Ppt Presentatie Infra Debatavond Regio KrimpenerwaardVvd Ppt Presentatie Infra Debatavond Regio Krimpenerwaard
Vvd Ppt Presentatie Infra Debatavond Regio KrimpenerwaardLex_Hofstra
 
Work Experience from Fugro and Svitzer
Work Experience from Fugro and SvitzerWork Experience from Fugro and Svitzer
Work Experience from Fugro and Svitzerlondal
 

Viewers also liked (20)

Dssh @ Confidence, Prague 2010
Dssh @ Confidence, Prague 2010Dssh @ Confidence, Prague 2010
Dssh @ Confidence, Prague 2010
 
Ilumtics corp profile_dec2011
Ilumtics corp profile_dec2011Ilumtics corp profile_dec2011
Ilumtics corp profile_dec2011
 
EEC '12 - RiderState presentation - 2012
EEC '12 - RiderState presentation - 2012EEC '12 - RiderState presentation - 2012
EEC '12 - RiderState presentation - 2012
 
SMS Based Push Mail
SMS Based Push MailSMS Based Push Mail
SMS Based Push Mail
 
Praveen Khanna
Praveen KhannaPraveen Khanna
Praveen Khanna
 
Polo 444 Design Story
Polo 444 Design StoryPolo 444 Design Story
Polo 444 Design Story
 
Evidence management-from-theory-to-practice-in-health-care
Evidence management-from-theory-to-practice-in-health-careEvidence management-from-theory-to-practice-in-health-care
Evidence management-from-theory-to-practice-in-health-care
 
Processing workshop intro
Processing workshop introProcessing workshop intro
Processing workshop intro
 
Embedding BCE - Introduction
Embedding BCE - IntroductionEmbedding BCE - Introduction
Embedding BCE - Introduction
 
Showing your business in the Best Light...Silver Moon Photography
Showing your business in the Best Light...Silver Moon PhotographyShowing your business in the Best Light...Silver Moon Photography
Showing your business in the Best Light...Silver Moon Photography
 
Dhwani09 Lonewolf - Theme
Dhwani09 Lonewolf - ThemeDhwani09 Lonewolf - Theme
Dhwani09 Lonewolf - Theme
 
The Poppy Appeal
The Poppy AppealThe Poppy Appeal
The Poppy Appeal
 
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis Liability
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis LiabilityThe Small Company Clinical Study SponsorRoles & Duties Vis-à-vis Liability
The Small Company Clinical Study SponsorRoles & Duties Vis-à-vis Liability
 
Computer Aided Engineering Design
Computer Aided Engineering DesignComputer Aided Engineering Design
Computer Aided Engineering Design
 
Land Of Hope
Land Of HopeLand Of Hope
Land Of Hope
 
4 types
4 types4 types
4 types
 
PhoneGap mobile development
PhoneGap mobile developmentPhoneGap mobile development
PhoneGap mobile development
 
Jupiter
JupiterJupiter
Jupiter
 
Vvd Ppt Presentatie Infra Debatavond Regio Krimpenerwaard
Vvd Ppt Presentatie Infra Debatavond Regio KrimpenerwaardVvd Ppt Presentatie Infra Debatavond Regio Krimpenerwaard
Vvd Ppt Presentatie Infra Debatavond Regio Krimpenerwaard
 
Work Experience from Fugro and Svitzer
Work Experience from Fugro and SvitzerWork Experience from Fugro and Svitzer
Work Experience from Fugro and Svitzer
 

Similar to Considerations in Selecting and Protecting Your IT Investment

Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceStefan Rank
 
Project management best practices
Project management best practicesProject management best practices
Project management best practiceswalkerswu
 
Discussion Paper PMO And Merger Projects
Discussion Paper   PMO And Merger ProjectsDiscussion Paper   PMO And Merger Projects
Discussion Paper PMO And Merger Projectstheteflonpm
 
01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write UpStefan Afendoulis
 
QFH Consulting Capabilities
QFH Consulting CapabilitiesQFH Consulting Capabilities
QFH Consulting CapabilitiesQuinn Harry
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management SkillsJessica Booth
 
Project-management-in-a-global-operation
Project-management-in-a-global-operationProject-management-in-a-global-operation
Project-management-in-a-global-operationFrank Luong PMP,MBA
 
Aufait Technologies - Introduction to BPM
Aufait Technologies - Introduction to BPMAufait Technologies - Introduction to BPM
Aufait Technologies - Introduction to BPMDinesh Kumar P
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9John Streit
 
Cost management webinar july 28 2011
Cost management webinar july 28 2011Cost management webinar july 28 2011
Cost management webinar july 28 2011richmur1
 
HP Software - The Bto Solution
HP Software - The Bto SolutionHP Software - The Bto Solution
HP Software - The Bto SolutionHPDutchWorld
 
Creating & Maturing a PMO
Creating & Maturing a PMOCreating & Maturing a PMO
Creating & Maturing a PMOSyed Raashid
 
Kt Intro Master V7
Kt Intro Master V7Kt Intro Master V7
Kt Intro Master V7TedLemmers
 
Corporater at BSC and Strategy Forum - March 2013
Corporater at BSC and Strategy Forum - March 2013Corporater at BSC and Strategy Forum - March 2013
Corporater at BSC and Strategy Forum - March 2013Pedro S. Pereira
 
PMI Global Congress 2012 Presentation
PMI Global Congress 2012 PresentationPMI Global Congress 2012 Presentation
PMI Global Congress 2012 PresentationZahidKhan007
 
SAP CVN Supply Network Planning - Supply Planning Engine Selection
SAP CVN Supply Network Planning - Supply Planning Engine SelectionSAP CVN Supply Network Planning - Supply Planning Engine Selection
SAP CVN Supply Network Planning - Supply Planning Engine SelectionPlan4Demand
 

Similar to Considerations in Selecting and Protecting Your IT Investment (20)

Business PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The DifferenceBusiness PMO & IT Pmo What Is The Difference
Business PMO & IT Pmo What Is The Difference
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
Discussion Paper PMO And Merger Projects
Discussion Paper   PMO And Merger ProjectsDiscussion Paper   PMO And Merger Projects
Discussion Paper PMO And Merger Projects
 
01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up01 Ts A Pmg Product Write Up
01 Ts A Pmg Product Write Up
 
QFH Consulting Capabilities
QFH Consulting CapabilitiesQFH Consulting Capabilities
QFH Consulting Capabilities
 
Kepner Tregoe Developing Your Hr Project Management Skills
Kepner Tregoe  Developing Your Hr Project Management SkillsKepner Tregoe  Developing Your Hr Project Management Skills
Kepner Tregoe Developing Your Hr Project Management Skills
 
Project-management-in-a-global-operation
Project-management-in-a-global-operationProject-management-in-a-global-operation
Project-management-in-a-global-operation
 
Aufait Technologies - Introduction to BPM
Aufait Technologies - Introduction to BPMAufait Technologies - Introduction to BPM
Aufait Technologies - Introduction to BPM
 
BPM in Telecoms
BPM in TelecomsBPM in Telecoms
BPM in Telecoms
 
Strivent Service Offerings Differentiators Web 2 9
Strivent Service Offerings  Differentiators Web 2 9Strivent Service Offerings  Differentiators Web 2 9
Strivent Service Offerings Differentiators Web 2 9
 
Cost management webinar july 28 2011
Cost management webinar july 28 2011Cost management webinar july 28 2011
Cost management webinar july 28 2011
 
HP Software - The Bto Solution
HP Software - The Bto SolutionHP Software - The Bto Solution
HP Software - The Bto Solution
 
SP_BTPM
SP_BTPMSP_BTPM
SP_BTPM
 
Creating & Maturing a PMO
Creating & Maturing a PMOCreating & Maturing a PMO
Creating & Maturing a PMO
 
Kt Intro Master V7
Kt Intro Master V7Kt Intro Master V7
Kt Intro Master V7
 
Corporater at BSC and Strategy Forum - March 2013
Corporater at BSC and Strategy Forum - March 2013Corporater at BSC and Strategy Forum - March 2013
Corporater at BSC and Strategy Forum - March 2013
 
Lean Information Technology Webinar
Lean Information Technology WebinarLean Information Technology Webinar
Lean Information Technology Webinar
 
MCP4
MCP4MCP4
MCP4
 
PMI Global Congress 2012 Presentation
PMI Global Congress 2012 PresentationPMI Global Congress 2012 Presentation
PMI Global Congress 2012 Presentation
 
SAP CVN Supply Network Planning - Supply Planning Engine Selection
SAP CVN Supply Network Planning - Supply Planning Engine SelectionSAP CVN Supply Network Planning - Supply Planning Engine Selection
SAP CVN Supply Network Planning - Supply Planning Engine Selection
 

Recently uploaded

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 

Recently uploaded (20)

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 

Considerations in Selecting and Protecting Your IT Investment

  • 1. Considerations in Selecting and Protecting Your IT Investment Helene Heller Senior Director Office of the CFO New York City Housing Authority copyrighted © 2005 NYCHA
  • 2. Agenda • Enterprise IT • IT Governance • IT Portfolio Selection And Management Methodologies • Making the Business Case • Project Management at NYCHA • PMO Automation More… 1/15/06 2
  • 3. Why is this an important topic? • Fiscal realities dictate selective IT investment • Technology/tools chosen need to support the business problem/challenge or opportunity • Project management should guarantee that the selected technology works, the business problem has been solved, and the investment was contained • Projects utilizing technology should support improved business processes and therefore be led by a business owner • Business owners shouldn’t have to be professional project managers 1/15/06 3
  • 4. How To Balance IT and Business Drivers: Client Funded Model IT Client Infrastructure Business Costs Value Drivers Drivers 1/15/06 4
  • 5. How does an Enterprise IT Structure Fit? Business Challenges: • Project requests are often “siloed” resulting in limited benefits to the organization • Requests address only a slice of an end-to-end business process • Projects aren’t supported by a strong and consistent business case often resulting in unclear scope and/or failed completion • Multiple technology platforms and solutions supporting similar business functions in different departments, are expensive and inefficient to support More… 1/15/06 5
  • 6. Enterprise IT Structure Example Mapping IT Support to Business Objectives Effective Vision, Objectives, Strategic Plans Business and IT Business Results Collaboration Processes, support, and Infrastructure tools that enable business Application functions Services Development Supporting Enterprise Project Foundation Architecture Management Accountability Discipline Metrics More… 1/15/06 6
  • 7. What is IT governance? As Defined by Gartner: • IT governance provides a framework in which the decisions made about IT issues are aligned with the overall business strategy and culture of the enterprise • Governance is concerned with setting directions, establishing standards and principles, and prioritizing investments. • The process of assigning decision rights is influenced by corporate culture, business orientation, stakeholders' opinions and the knowledge required of decision makers. • Effective it governance involves the assignment of decision-making rights and accountabilities regarding behavior in the desirable use of it. 1/15/06 7
  • 8. IT Governance Example © copyright NYCHA 2003-2005 Role of the Project Management Office (PMO) NYCHA Board NYCHA General Manager Provide Input & GM’s Operations NYCHA NYCHA Membership Feedback CIO/CFO Committee DGMs Monthly Executive Project Status Reports PMO Business Unit Provide Project Repository Staff Reporting Project Project Project PM Consulting & Advice Liaison or or Structure Steering Manager Team PM Standard Methodology Committee & Tools PMO Reporting Standards Assistance & Coaching Weekly/Monthly Project Manager Status Reports Dept. Project Manager(s) More… 1/15/06 8
  • 9. Why is a Portfolio Approach Relevant? • An organization must understand its goals, have a flexible process to determine priorities based on changing environments, and select projects that will provide meaningful improvement to: –Customer satisfaction –Employee productivity –Business process improvements –Cost take-out from the operating budget 1/15/06 9
  • 10. Portfolio Management Approach – Ongoing Process Portfolio Management GM • Portfolio scope • Prioritize& optimize overall IT cost, benefits, risk • Actively monitor Portfolio performance • Adapt to business environment changes Quarterly Annual Portfolio Planning Program Reviews Management • Comprehensive program planning • Change and risk management • Coordination of project delivery Monthly • Measurement of results Program Quarterly • Corrective actions Reviews Planning Project Management DGM • Deliverables • Initiate Weekly • Scope • Budget Monthly Project Planning • Risks Reviews • Schedule PM • Measure More… • Resources 1/15/06 10
  • 11. How to select the enterprise portfolio – Before Key Care-Abouts Investment Criteria • Identify key stakeholders who •Identify criteria for IT investment: run the business improve business process, save • Understand their goals and money, break-down business priorities, what keeps them up at silos, etc. night, and what gets in the way of •Apply criteria against list of doing the job that supports their goals potential projects • Use this knowledge to brainstorm potential IT solutions Business Case Enterprise Solutions •Identify executive sponsor and • Look for patterns among project manager from the business solutions of all stakeholders •Project manager completes a interviewed project concept document • Identify opportunities to •Project concept documents are implement one solution for multiple functions or department presented to IT governance committee for selection 1/15/06 11
  • 12. How to select the enterprise portfolio - After Step One: Step Three: • Started with NYCHA's published “5 year • Six categories of aggregation emerged: plan for fiscal years 2005 – 2009” as – Compliance submitted to HUD – Cost takeout/employee productivity – New partnerships • Extracted business goals from these – New revenue plans and hypothesized on Executive’s – Nycha-wide initiatives business goal correlation and opportunities – Resident care • Each goal was analyzed based on the key impact areas of people, process, & technology. • In partnership with NYCHA's CFO Goals where technology could play a role were conducted 1:1 sessions with DGMs to identified and presented to the GM who validate business goals, key success requested a policy planning offsite metrics and solutions, in the context of spring financial planning – 60 solutions resulted Step Four: • Building on all of the above planning and using Step Two: the same planning matrix as step one – portfolio methodology was developed • Results Were Aggregated & Refined After a Review with the General Manager • Impact categories were refined: • Example: – Customer satisfaction Hugh Spence – DGM for Community Operations – Resource enhancement 1. One Voice Portal 2. Automated DOH Licensing Information – Financial savings 3. Automated Social Services Case Management • Information sets such as: category, sponsoring 4. Resident Employment Training & Tracking System department, forecasted cost & benefits, & FTE 5. Community Center Internet Connectivity NYCHA project resources were presented in 6. Reduce Duplicate Function – Community Center chart, graph & pivot table format to enable a GM Construction Operations review of 26 projects for prioritization 1/15/06 12
  • 13. Application & Solutions Portfolio – NYCHA Today Step Five: • Balancing resource impact, risk, funding, departmental involvement & customer improvements, A tiered approach was developed by the General Manager • Application / Solution Portfolio • Tier 1 Top Priority Business Initiatives • Tier 2 Emerging Business Initiatives (business case this year) • Tier 3 Managed by IT (limited or no business PM involvement) • Tier 4 Future Year Initiatives 1/15/06 13
  • 14. How to Make the Business Case • Elevator pitch: what is the business problem, challenge or opportunity? Why should the executive care? • Describe in layman’s terms a credible potential solution • Define metrics that will show the executive that the solution has successfully addressed the business problem/challenge/opportunity • Document the cost of doing business the current way v. the new way that the solution will promote • Compare to best practice examples 1/15/06 14
  • 15. Business Case Components Project Team and Stakeholders Project Approach • Executive Sponsor • Estimated Project Resource Requirements • Project Owner/IT Partner • Implementation Approach • Impacted Personnel • Estimated Duration of Business Context Implementation • Business Problem • Procurement Recommendations • Business Goals Cost/Benefit Analysis • Business Functional Objectives • Methodology and Analysis • Metrics Results/ROI Proposed Solution • Estimated Project Cost • Solution Description • Funding Source(s) • Alternatives Considered Risk Management Plan • Rational for Selection • Barriers • Product Selection • Probability of Risk • Consistency with IT Strategy • Mitigation Strategy 1/15/06 15
  • 16. The Goal of the IT PMO Discipline at NYCHA Provide the end-to-end project delivery and project management processes, standards, best practices, and tools to enable the organization to achieve far higher levels of performance, rapidly delivering big wins with positive financial impact. 1/15/06 16
  • 17. PMO Roles Project Coach Project Repository • Best practice sharing across • Source of information on project organization functions and methodology and standards coordinates communication • Facilitates the use of a cohesive • Raises organizational set of tools for project design, performance -- mentoring management and reporting relationships may be established across business boundaries • Empowers distributed, business- between high and low performing centric project ownership project managers • A first step to enfranchise the idea • The PMO is a permanent structure of consolidating or sharing and has some supervisory management practices but does responsibility for all enterprise business projects NOT provide direct project • A quot;dotted linequot; reporting management relationship from business-staffed project managers and to the CIO 1/15/06 17
  • 18. Functions of a Virtual IT PMO IT PMO Project Project Communication Resource Project Management Review and Evaluation Planning Standards & Analysis Collaboration 5. Providing 3. Responsible 1. Developing a 4. Consistently 2. Ensuring the continued for guiding standardized PM monitoring optimization of program each project’s methodology, projects to organization visibility to the planning process and ensure they resources in Executive efforts tools for are kept on projects Team and effective project track and are facilitating management completed maximum across the successfully multi-level organization collaboration Resource Database Collaboration Software PM Methodology Vendor Info. Database Knowledge Management Exec. Info. System (EIS) Tools and Templates Education Mgmt System Slide modified from two Gartner concept slides © copyright Gartner, Inc. 2002 1/15/06 18
  • 19. NYCHA IT Project Lifecycle © copyright NYCHA 2003 - 2005 Evaluation and Enhancement Metrics, Status, and Change Management Support/ Initiation Planning Execution Close Out Maintenance Concept Commit Execution Commit Design/Dev/Test/Deploy Production Lessons Learned Select Refine Prioritize investments Project initiatives Course Strategic Planning Metrics & Reviews Review And Analysis Portfolio Align objectives Communicate status 1/15/06 19
  • 20. The IT PMO Functional Blueprint at NYCHA © copyright NYCHA 2003-2005 Executive Sponsorship Executive Management Team Business Application Development Concept, Justification, IT Infrastructure Units Execution, and Operations Quality Procurement Assurance Collaboration, Orchestration, IT PMO (Includes Budget Partner) and Coaching Enterprise CIO Exec. for Policy Change Management, Technology Standards, and Policy Architect 1/15/06 20
  • 21. Initiation Phase Overview © copyright NYCHA 2003-2005 Evaluation and Enhancement Metrics, Status, and Change Management Initiation Planning Execution Close-Out Support / Execution Maintenance Concept Commit Execution Commit Design/Dev/Test/Deploy Lessons Learned Production Phase Overview • The Initiation Phase sets the tone for the project • The Initiation Phase is a collaborative approach of presenting a particular NYCHA business problem, challenge or opportunity defining a particular project to address the business issues(s) and identifying anticipated benefits which NYCHA expects to realize by undertaking the project. • A Project Concept is required by an executive sponsor in order to get a sense if the project should be pursued. • The Enterprise Portfolio IT selection process utilizes the materials in the project concept document to determine appropriate project next steps, including Pilot, Process Re-engineering or Business Case Development prior to commitment to move to the Planning Phase • If a commitment is not provided, NYCHA may decide to revisit the project at a later date, re-define the project scope or terminate the project Entry Criteria Business Unit Executive Sponsorship Exit Criteria GM’s Operations Committee Decision to Sponsor Project to Planning Phase 1/15/06 21
  • 22. Initiation Phase Activities and Deliverables © copyright NYCHA 2003-2005 1/15/06 22
  • 23. Initiation Phase Activities and Deliverables © copyright NYCHA 2003-2005 1/15/06 23
  • 24. How to Scale a PM Standard Throughout the Enterprise: The Role of Automation • Project Dashboard • Knowledge Management & Collaboration Repository • Planning/Tracking • Risk Management • Reporting/Issue Management • Automated Compliance 1/15/06 24
  • 25. PMO: Project Dashboard •Overview: The Virtual IT PMO: a comprehensive view, defined by user Illustrative role, for all the news and information about NYCHA projects •Users: Project team, executive sponsors and anyone who needs to learn more about the projects, or need to know about status •Elements: Workflow navigation that guides the project manager through the required project lifecycle. Provides current project status, project plan and timeline, issues and risks logs, and link to repository which stores past status reports and other project-related information. •Owner: PMO 1/15/06 25
  • 26. PMO: Collaboration Space •Overview: A common repository for all Illustrative project related document storage and collaboration facilitation •Users: PMO, project managers and team members, and anyone needing access to knowledge management •Elements: Contains current and historical documents and completed PMO templates, past status reports, updated issues and risk logs, etc. Provides version control and authentication. Information clearly segregated in open and protected folders with links provided to any other required website (e.g., NYCHA intranet). •Owner: PMO with project managers for their specific folders (collaboration spaces) 1/15/06 26
  • 27. PMO: Planning/Tracking •Overview: The overall detailed, activity-based plan for the project using Microsoft Enterprise Project Server •Users: PMO, project managers and delegated team members, steering committee, executive sponsor •Elements: Planning and tracking information in Web-based views as detailed a view as selected by the user. Information comes from Project Server. Data is hierarchical and can be expanded or collapsed to view a snapshot of the entire project. This is what feeds the dashboard. •Owner: Project managers maintain the ownership of each plan 1/15/06 27
  • 28. PMO: Risk Management •Overview: Automated Compliance to Ensure Risk Management Plan Adherence and Regular Review •Users: Project manager leading their team, executive sponsor, other executives •Elements: List of all the project risks, their severity, impacted areas, likely impact (delay, budget increase) and mitigation strategies. Starts in Initiation Phase to populate the required documentation throughout the lifecycle, includes the risk management plan, risk log and status reports. •Owner: Project managers 1/15/06 28
  • 29. PMO: Reporting Automatically Completed for •Overview: A set of templates to you! report the status of the project and (can be edited) Illustrative overall portfolio throughout the lifecycle •Users: PMO, project managers, steering committee, executive sponsor, governance committee, CFO, Board •Elements: InfoPath templates, SQL database and web-based reporting. Project level template for each project. Three status reports depending on the audience - includes an overall red/yellow/green status assessment with the high level explanation followed by major accomplishments, key issues and upcoming milestones. •Owner: Project Manager with PMO review on monthly and quarterly reports 1/15/06 29
  • 30. Additional Notes Slides Supplemental Notes Where “More” Has Been Indicated on the Bottom-Right Hand Side of the Slide: 2, 5, 6, 9 and 16 copyrighted © 2005 NYCHA
  • 31. More from Agenda Slide: NYCHA Historical Context Let’s talk about some of the environmental factors that were in place almost three years ago, when the new CIO first thought about the establishing a formalized governance structure. The fiscal realities that presented themselves when he started, and what he saw in the technology environment in April of 2002: At NYCHA, our primary issue was the lack of an overall information-technology governance process, and that manifested itself in a variety of ways. One was that projects that got supported and funded were identified through a specific line of business, and not considered in its enterprise sense. So if a business owner had a particular need for a technology-support tool, that tool was built specifically for that business owner without any consideration for the overall enterprise requirement. Historically, the application of that process, created a series of business applications that were not integrated -- they were siloed with respect to support, and with respect to the delivery of the solution. A specific line of business then had its own platform, its own business application, and its own relationship with the technology-support organization. And, even its own IT staff. This would be repeated across the various lines of business, so the result was seven or eight different computing platforms, multiple technology solutions that run on those platforms, and staff that was dedicated to support those various platforms and solutions. The initial objective was to reorganize the technology organization into a full enterprise support and service organization by removing these silos, but also recognizing that over time that we would continue to have some of these specific platforms that would need to be supported. We wanted to create a single technology organization that considers the primary support requirements in terms of technology infrastructure and business-application support. At the same time, it became very clear that the fiscal situation at NYCHA was indeed changing. Funding that NYCHA had been accustomed to throughout the years, primarily from HUD, had essentially dried up. And so we had to come up with ways to make a decision, about how technology investments could be leveraged across multiple business requirements within the enterprise. So, for example, there should not to be a separate inspection system for each line of business, but rather an enterprise- wide inspection system that would support each line of business. And as a means to that end, three things occurred: the creation of a project-management process; the reorganization of the technology organization; and putting into place a governance or a technology-investment consideration and support structure that would govern the process going forward. To summarize, there are a lot of culture-change factors occurring at the same time. So, it actually was a challenge, but also a terrific opportunity. On the one hand, we were going from a system within NYCHA, that allocated funding for projects based on individual requests that came in, and individual analysis of these requests, to a process where departments had budgets, budget responsibility centers, financial planning, (encumbrance)-based budgeting, and the like. And all of this was happening at the same time that we were implementing a comprehensive, enterprise- wide financial-management system. So that was one major opportunity. Back 1/15/06 31
  • 32. More from “How Does Enterprise IT …Fit” Slide: When you don’t have a clear project-management process in place you get lots of different information -- requesting the same thing. So, here you might be an executive who has to make a funding decision, and you really don’t know what you’re getting because everyone who’s submitting a request for a project is submitting different information. A t the end of the day you don’t have to be a technology expert. If someone comes to you with a request for project and spends all that time talking about the technology and this is not an area that you’re familiar with, how comfortable are you going to be in making a decision to fund a project? What’s good about having a consistent project-management discipline is that each project manager is guided by a consistent set of questions to, let’s say, make a business case. So the business case ends up being stronger. It’s more consistent. This addresses the challenge that we had historically where the scope is unclear, the project maybe failed in completion. One example, anecdotally, was $15 million allocated to some sort of human- resource management system, and all the $15 million was spent but at the end of the day we only yielded $1 million in functionality, if you really look at the scope, because it was unclear. There was no consistent process. There was no consistent approach, but all the money was spent. Finally, when you address funding of IT requests independently of each other without a clear enterprise structure, you end up with all these multiple technology platforms, performing perhaps similar business functions in different departments, and you’re not developing the benefit of having one solution where staff is trained to run that solution that multiple departments can use. The opportunity to accomplish all of this today is that the chief information officer position was created at NYCHA . If it existed before, it really existed in title, not in reality, and it certainly wasn’t at the deputy general manager level. Why that’s important is, ostensibly we’re a very large organization, a large corporation, if you will, that’s run by a general manager who reports to a board. The general manager is like a CEO, and underneath him he has executives, deputy general managers, there are seven of them, that really are responsible for the day-to-day operation of this large corporation. In creating the chief information officer at the deputy general manager level, you’ve basically made the chief information officer a peer to all the executives who are responsible for running the authority. That’s significant because, not only does that position now have the clout to implement and champion and effectively coach this sort of discipline, but they have a seat at the table where all these policy decisions are being made, so they have more insight into the primary business goals of the enterprise. It shows what an important role technology is playing within this organization. A t the end of the day, this all starts from the top. It’s embraced bottom-up, but it comes top-down, and that’s very significant. It’s very significant for this to be considered as important as any other initiative in the enterprise. In addition, because there wasn’t this process of stating what services were required, what technology was going to do, it was very fragmented, it was distributed across different organizational silos, people just handed things off. People didn’t know what other business units did, and lost the opportunity to collaborate and have a more effective solution. A nother result is that when you have a bifurcated enterprise IT organization, there is no proper expectation on behalf of the customer of the type of response they’re going to get, the time that they’re going to get their response addressed, the hand-off that they’re going to get to three other people to address what is a very straightforward request or need from the IT organization. There is no good issue resolution or tracking of issues. Most importantly, there isn’t a good balance between what the need is from the customers for service, and what the capabilities are of the organization to actually address and support those services. In that type of environment there is an inability to actually measure costs and the benefits relative to what’s being Back provided- to be able to make a good decision as to whether or not we could provide the services internally or we should go externally. 1/15/06 32
  • 33. More from “Enterprise IT Structure Ex. Slide Why was this organization put in place, what are the important elements and why? The primary driver for implementation technology has to be a sound business plan and an effective vision for where the organization is headed. On the basis of that type of plan, a technology strategy can be developed that effectively aligns with that plan. In order to carry out the technology strategy, the organization has to consist of infrastructure support and development in the growth of the infrastructure, and at the same time the development of the business solution. To govern that organization model, what’s needed is an effective process and discipline to manage technology initiatives, and have a clear blueprint of the technology architecture that would evolve to support the overall strategy. What we ended up with are two operational units: an IT infrastructure group and an application- development group. These are the two groups that are responsible for the operations of IT, meaning the day-to-day programming, the day-to-day support of hardware, software, etc. Then, above that, as the policy-making organization, the coordination, the administrative organization, is the office of the CIO. Within the office of CIO is this function that we’re talking about today, this project and information-management function, with this virtual PMO process, the IT governance, the project-portfolio selection and management, the project-management discipline, but from a virtual sense, meaning setting the policy, the goals, the tones, facilitating, coaching, orchestrating. Additionally within the Office of the CIO is an enterprise-technology architect, who is responsible for really understanding the business goals, but from the technology platform and solution and standard perspective. Within that function, the quality-assurance function, which you’ll see in our project-management discipline or project life cycle, we’ve institutionalized the importance of the role of quality assurance, why it exists in the office of CIO, reporting to the enterprise technology architect, is it’s important that that quality-assurance function not report to the operations group, the application-development group of the IT infrastructure group. With this type of organization, the CIO actually has a better understanding of what the objectives should be. He can communicate to his staff what his expectations are. There’s more accountability. There’s more of an understanding of what everyone’s role is within the IT organization, how that rolls up to the important business goals of the organization. Most importantly, he has a way of measuring all of Back this. 1/15/06 33
  • 34. More from “Portfolio Mgmt Approach” Slide The methodology that we use is coming together. The point at which we select projects comes together at the same time as the financial-planning cycle, which is new to NYCHA . So that has been a terrific opportunity, to take advantage of this partnership because of the timing at which they are introducing this whole notion of semiannual financial planning. Then we have this opportunity to prioritize projects. So we have three types of projects at NYCHA , and to segment them and to come up with process-reporting requirements, depending on the nature of the project. When we discussed the client-funded model, that we have central infrastructure projects, projects that are needed to make sure that we have this robust, scalable, dependable network, and those projects could range anywhere from introducing a new telephony technology, or upgrading the network operating system, or upgrading the e-mail system, or standardizing on the server platform, or developing a life cycle for PCs and laptops and servers. A ll of those projects are projects that our CIO and general manager like to refer to as inside (inaudible). These are things that he trusts the CIO to decide, that don’t really require much decision and discussion with the other executives, and these are projects that are going to be managed by IT. That’s one group of projects where we are not going to bring them constantly before this governing body, which I will detail in a couple of slides. Then there are very small application-development projects, generally enhancements to existing applications where we have to make upgrades because perhaps a version of the software is no longer supportable, we had an audit finding perhaps, perhaps we need to upgrade based on an unsupportable platform to a different one. So these types of projects we have to do anyway, and really don’t need to, again, have the same sort of in-depth review by all of the executives. The group of projects Called the enterprise IT business projects are what constitutes the portfolio of projects that are really focused on. The are the projects that we prioritize in terms of where we’re going to make the IT investment and what is going to be reviewed in terms of the entire portfolio. These projects consist of business solutions that are reviewed quarterly. We’ve now successfully gone through four quarterly reviews of the portfolio. Today’s quarterly review was Q1 05, which is our fifth quarterly review, and this is an opportunity -- currently we have 12 projects -- we’re probably going to winnow that down some in the next coming months, since some of our projects that are come on are very, very large projects. So we need to really bring that number down some. It’s an opportunity for each of the project managers, again, directors, deputy directors, to come before our governance committee, which at the very least consists of all our executive sponsors, and give the same review, meaning answer the same questions of where their project is for the reporting period, which is the previous three months, and do it together. A ll of the project managers are going to discuss answers to the same questions, the same 90-minute session, so that the members of the governance committee can get a sense of the portfolio and make decisions about priorities if they need to. So this is part of our flexible environment. There should be monthly program reviews with the executive sponsor, where there may be multiple projects that roll up to an overall program initiative. This gives the executive sponsor a way of understanding where their important program is going, how the different projects are working within their program, and also to give them more of an intimate interaction with their project managers on the projects that they’re ultimately responsible for. This is a way that they can really focus in on what the metrics should be, what results they should measure, and also gives them an opportunity to take corrective actions when there are some decisions that need to be escalated to them, that the project team hasn’t been able to resolve amongst themselves. A nd then of course, at the lowest level of the weekly reviews that are done by the project manager, and that’s the key project management, initiate, budget, schedule, deliverable scope, risks, resources, measures, and the like. Back 1/15/06 34
  • 35. More from “IT Governance Example” Slide The purpose of providing them with support is not to project-manage the process for them, not to dictate how they go about it, but to coach them, mentor them, and provide them with tools to help them move through their important projects’ life cycles. To that end, every time we go forward with a project where we require the business manager to -- the project manager to come to the business -- we give them an IT strategic partner. Going back to the example that we gave about the new IT organization, this customer- service approach, this organization can respond to the business needs of the organization and be effective -- it doesn’t matter what group they come from. They’re still responsible for any IT need that their project manager has. So, let’s say it’s the enterprise- technology architect. Application Development doesn’t report to him. The IT Infrastructure (ITI) team doesn’t report to him. But he’s still responsible for getting what’s needed from those groups for the project manager. So it’s this customer-service approach. And then finally, this PMO function, this virtual function, is really responsible for establishing standards, providing tools, developing the methodology, and of course, they report in to the CIO and also this partnership with the CFO, you could see this as a dotted line. Back 1/15/06 35