SlideShare a Scribd company logo
1 of 30
Net work Analysis
   CPM/PERT
Project
   “A project is a series of activities directed
    to accomplishment of a desired objective.”

Work break down structure
   “Project can be splitted into small tasks
    with sequence of the their execution. This
    process is known as work break down
    structure “

    Plan your work first…..then work
    your plan
Network analysis
Network analysis is the general name given to certain specific
techniques which can be used for the planning, management and
control of projects.
Main objectives are:
1. Complete the project within stipulated period..
2. Optimize resources utilization.
3. Better coordination in interdependent activities


C.P.M & P.E.R.T are two methodologies to analyze the network
PERT -
      Project Evaluation & Review Techniques

   Definition:
   In PERT activities are shown as a network of precedence
    relationships in which successive events are joined by arrows.
     – Probabilistic activity times
     – Optimistic time, pessimistic time, most likely time.
     – Event oriented diagram



     USED IN : Project management - for non-repetitive jobs
       (research and development work), where the time and cost
       estimates tend to be quite uncertain. This technique uses
       probabilistic time estimates.
CPM - Critical Path Method

   Definition: CPM activities are shown as a network of
    precedence relationships in which successive activities are
    represented by arrows. .also called PPS
     – Single estimate of activity time
     – Deterministic activity times
     – Activity oriented diagram



     USED IN : Production management - for the jobs of
       repetitive in nature where the activity time estimates can
       be predicted with considerable certainty due to the
       existence of past experience.
Terminologies used in C.P.M

   Use of nodes and arrows


     Arrows       An arrow leads from tail to head directionally
    – Indicate ACTIVITY, a time or resource consuming effort that is
      required to perform a part of the work.
    – Direction of the progress of the project


      Nodes      A node is represented by a circle
    - Indicate EVENT, a point in time where one or more activities
      start and/or finish.
    - Some part of the project has been complete
    - Merge events, brust events.
Terminologies used in C.P.M

   Relation ship between Events:
   1. Successor Events
   2. Predecessor Events

   Activity:
   1. Successor Activity
   2. Predecessor Activity
   3. Dummy Activity
   4. Concurrent Activity
Activity on Node & Activity on Arrow

Activity on Node                Activity on Arrow

- A completion of an activity   - An arrow represents a task,
  is represented by a node         while a node is the
                                   completion of a task
                                - Arrows represent order of
                                   events
Rules to draw the network
1. Each event is presented by the nodes & activity by an
   arrow
2. The starting event should be represented by i
3. The completion of project should be assigned highest
   number in the network
4. The activities emerging from event i should have no
   predecessor activities & event having highest number in
   diagram should have no successor activity
5. The activity must have highest number for its head
   (arrow) than its tail
6. Network diagram cannot have more than one starting
   node or end node
Rules to draw the network

7.   7. There should not be a loop in diagram
8.   8. An event cannot occur or an activity cannot start unless all its
     preceding activities have been completed (not applicable on dummy
     activity )
Fulkerson’s Rule
The starting event(having no predecessor activity is
numbered as 1 ) other events are numbered in increasing
order from 1 to rightwards , if there are more then 1
initial event found in a diagram , anywhere they are to be
numbered fro top to bottom in increase order no two
events can have the same number in any case
Question 1

Activity                           Predecessor
    A                                   ---
   B                                    A
   C                                    B
   D                                    C,E
   E                                      B
   F                                      C,E
   G                                    F
   H                                    G
   I                                    H,D
   J                                    I
Draw the network diagram
Question 2

A project consist of 7 activities .Activities P,Q,R run simultaneously . The
   relationship among the various activities is as follow
Activity                                      successor
   P                                               S
   Q                                               T
   R                                               U

Activity V is the immediate successor to S, T, & U
Draw the network diagram
Question 3

Activity                                Predecessor
    A                                      ---
   B                                        ---
   C                                       A
   D                                       C
   E                                        A
   F                                        E
   G                                       B
   H                                       G
   I                                       C,E
   J                                       F
   K                                       D,G,J
Draw the network diagram
Estimation activity time
   Most optimistic completion time
   Most pessimistic completion time
   Most likely completion time
   te = a+4m+b
            6

      Where,
 a = Most optimistic completion time
 b = Most pessimistic completion time
 m = Most likely completion time



Question 4
Q: Draw the network, labeling activities



Job Activity   Immediate       Optimistic time   Most likely   Pessimistic time
                Predecessor                a              m              b
   A          -                          5              6              7
   B          -                          2              5              8
   C          A                          6               7            14
   D           B                         1               2             3
   E          C, D                      3               3             3
   F            B                       6                8            10
   G            E                        1                4            7
   H            F, G                    4                5             6
Activity Slack



-   Earliest starting time (EST) , which is a calendar time when a
    event can occur when all the predecessor events completed at the
    earliest possible times



-   Earliest finish time (EFT)
-




    * Preceding from start to finish
Activity Slack



-    Latest starting time (LST): The latest time by which an activity
     is started with out delaying the total project completion.

-    Latest finish time (LFT):




    * Start working from finish to start
Determination of critical path

Critical Path:
  Critical path is the series of connecting activities from
  starting to end for which the total time of completion of
  all activities is maximum
Critical activities /Bottle neck :
All activities come in the way of critical path are called
  critical activities
Non Critical activities : All activities do not come in the way
  of critical path are called non critical activities
Float/ Slacks

   Slack is the amount of time an event can be delayed without
    delaying the project completion

   Positive slack
   Negative slack
   Zero slack

   Slack = LST – EST
           LFT – EFT
Question 4

Activities            Predecessor activities Activity Time
     L                       ----                   3
     M                       ----                   4
     N                       L                      9
     O                       L                      3
     P                       O                      3
     Q                       N,M                    6
     R                        N,M                   4
     S                       R                      2
     T                       R                      5
     U                       P,Q,S                  6
Draw the network diagram Calculate EST,EFT,LST,LFT ,activity slack &
high light the critical path
Crash Time
Crash time = Crashed Cost – Normal Cost
              Normal Time – Crashed Time
Normal           Question 5     Crash
   Nodes       Time       Cost        Time              Cost
   1-2          3        300            2                400
   2-3          3          30           3                 30
   2-4          7        420            5                580
   2-5          9        720            7                810
   3-5          5        250            4                300
   4-5          0           0           0                   0
   5-6          6        320            4                410
   6-7          4        400            3                470
   6-8          13       780            10               900
   7-8          10       1000           9               1200

Project indirect cost is 50Rs. Per week. Draw the network diagram &
identify the critical path ? What are the normal project duration and
associated Cost ? Find total float associated with each activity
Crash the relevant activities systemically and determine the optimal
project completion and cost
Question 6
 On May 1,Arnie Watson sent a memo to his boss, the
  director of the project      (6)
   management. Stating that the MX project would
  require 13 weeks for the completion. Arnie realized
  that customer wanted the job completed in less
  time, after discussions with the functional
  managers,Arnie developed the table shown.
 According to the contract there is a penalty payment of
  $5,000 per week for every week over six. What is the
  minimum amount of additional funding that arnie
  should request.
Normal          Crash
Job Activity   Predecessor   Time   Cost ($.)     Time   Cost ($.)
                 Activity
   A              -          3      6,000        2      8,000
   B              A          5     12,000        4      13,500
   C              A          5     16,000        3      22,000
   D              A          4      8,000        2      10,000
   E             C,D         2      6,000        1       7,500
   F             B,E         3     14,000        1      20,000
Benefits of CPM/PERT

 Interdependencies of activity
 Project completion time
 Impact of late start
 Impact of early start
 “what if “ exercise
 Evaluation of performance
Questions Answered by CPM & PERT

 Completion date?
 On Schedule?
 Within Budget?
 Critical Activities?
 How can the project be finished early at the least
  cost?
Limitations to CPM/PERT

   Clearly defined, independent and stable activities
   Specified precedence relationships
   Over emphasis on critical paths
Thank you

More Related Content

What's hot

Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
Rahul Dubey
 
Way leaves and right of way
Way leaves and right of wayWay leaves and right of way
Way leaves and right of way
T Ch Hanuman Rao
 
Chap 5 project management
Chap 5 project managementChap 5 project management
Chap 5 project management
Ayesha Bhatti
 

What's hot (20)

Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
Schedule Risk Analysis (SRA) by Pedram Daneshmand 14-Jan-2011
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
Bar chart
Bar chartBar chart
Bar chart
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
Basics of Signal Designing
Basics of Signal DesigningBasics of Signal Designing
Basics of Signal Designing
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Pert & cpm project management
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project management
 
What is construction management & its Benefits?
What is construction management & its Benefits?What is construction management & its Benefits?
What is construction management & its Benefits?
 
Bar chart
Bar chart Bar chart
Bar chart
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Presentation on Revit Architecture
Presentation  on Revit ArchitecturePresentation  on Revit Architecture
Presentation on Revit Architecture
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Way leaves and right of way
Way leaves and right of wayWay leaves and right of way
Way leaves and right of way
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Construction Bidding Step-by-Step
Construction Bidding Step-by-StepConstruction Bidding Step-by-Step
Construction Bidding Step-by-Step
 
Float in Projects
Float in ProjectsFloat in Projects
Float in Projects
 
Chap 5 project management
Chap 5 project managementChap 5 project management
Chap 5 project management
 

Viewers also liked

Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
tomeh
 
Chapter3a fundamental casting processes
Chapter3a fundamental casting processesChapter3a fundamental casting processes
Chapter3a fundamental casting processes
Noor 'Izzahtul Aisyah
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
Debanjan15
 

Viewers also liked (20)

Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Program Evaluation and Review Technique
Program Evaluation and Review TechniqueProgram Evaluation and Review Technique
Program Evaluation and Review Technique
 
Program evaluation review technique (pert)
Program evaluation review technique (pert)Program evaluation review technique (pert)
Program evaluation review technique (pert)
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Project Management PERT and CPM
Project Management PERT and CPMProject Management PERT and CPM
Project Management PERT and CPM
 
U4 p1 welding metallurgy
U4 p1 welding metallurgyU4 p1 welding metallurgy
U4 p1 welding metallurgy
 
Pert
PertPert
Pert
 
Chapter3a fundamental casting processes
Chapter3a fundamental casting processesChapter3a fundamental casting processes
Chapter3a fundamental casting processes
 
Unit 5 or
Unit 5 orUnit 5 or
Unit 5 or
 
Mb0048 operations research winter 2014
Mb0048 operations research winter 2014Mb0048 operations research winter 2014
Mb0048 operations research winter 2014
 
Problem Definition in research design
Problem Definition in research designProblem Definition in research design
Problem Definition in research design
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
PERT/CPM
PERT/CPMPERT/CPM
PERT/CPM
 
Ford Fulkerson Algorithm
Ford Fulkerson AlgorithmFord Fulkerson Algorithm
Ford Fulkerson Algorithm
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Network analysis & cpm
Network analysis & cpmNetwork analysis & cpm
Network analysis & cpm
 

Similar to Pert cpm

1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
drennanmicah
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
saurabhshertukde
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
kenjordan97598
 

Similar to Pert cpm (20)

Pert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOLPert cpm SIDDANNA M BALAPGOL
Pert cpm SIDDANNA M BALAPGOL
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
 
Chapter 6 project management
Chapter 6 project managementChapter 6 project management
Chapter 6 project management
 
Ch4 scheduling
Ch4 schedulingCh4 scheduling
Ch4 scheduling
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Unit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pertUnit.6. network analysis with cpm and pert
Unit.6. network analysis with cpm and pert
 
Ch08 pm2ndhalf
Ch08 pm2ndhalfCh08 pm2ndhalf
Ch08 pm2ndhalf
 
The Network Diagram and Critical Path
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
 
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Lu3 – the planning phase lectures
Lu3 – the planning phase lecturesLu3 – the planning phase lectures
Lu3 – the planning phase lectures
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
Scheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docxScheduling Problems Complete the following problems covering pro.docx
Scheduling Problems Complete the following problems covering pro.docx
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 

Recently uploaded

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Recently uploaded (20)

Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Third Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptxThird Battle of Panipat detailed notes.pptx
Third Battle of Panipat detailed notes.pptx
 

Pert cpm

  • 1. Net work Analysis CPM/PERT
  • 2. Project  “A project is a series of activities directed to accomplishment of a desired objective.” Work break down structure  “Project can be splitted into small tasks with sequence of the their execution. This process is known as work break down structure “ Plan your work first…..then work your plan
  • 3. Network analysis Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. Main objectives are: 1. Complete the project within stipulated period.. 2. Optimize resources utilization. 3. Better coordination in interdependent activities C.P.M & P.E.R.T are two methodologies to analyze the network
  • 4. PERT - Project Evaluation & Review Techniques  Definition:  In PERT activities are shown as a network of precedence relationships in which successive events are joined by arrows. – Probabilistic activity times – Optimistic time, pessimistic time, most likely time. – Event oriented diagram USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.
  • 5. CPM - Critical Path Method  Definition: CPM activities are shown as a network of precedence relationships in which successive activities are represented by arrows. .also called PPS – Single estimate of activity time – Deterministic activity times – Activity oriented diagram USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.
  • 6. Terminologies used in C.P.M  Use of nodes and arrows Arrows  An arrow leads from tail to head directionally – Indicate ACTIVITY, a time or resource consuming effort that is required to perform a part of the work. – Direction of the progress of the project Nodes  A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. - Some part of the project has been complete - Merge events, brust events.
  • 7. Terminologies used in C.P.M  Relation ship between Events:  1. Successor Events  2. Predecessor Events  Activity:  1. Successor Activity  2. Predecessor Activity  3. Dummy Activity  4. Concurrent Activity
  • 8. Activity on Node & Activity on Arrow Activity on Node Activity on Arrow - A completion of an activity - An arrow represents a task, is represented by a node while a node is the completion of a task - Arrows represent order of events
  • 9. Rules to draw the network 1. Each event is presented by the nodes & activity by an arrow 2. The starting event should be represented by i 3. The completion of project should be assigned highest number in the network 4. The activities emerging from event i should have no predecessor activities & event having highest number in diagram should have no successor activity 5. The activity must have highest number for its head (arrow) than its tail 6. Network diagram cannot have more than one starting node or end node
  • 10. Rules to draw the network 7. 7. There should not be a loop in diagram 8. 8. An event cannot occur or an activity cannot start unless all its preceding activities have been completed (not applicable on dummy activity )
  • 11. Fulkerson’s Rule The starting event(having no predecessor activity is numbered as 1 ) other events are numbered in increasing order from 1 to rightwards , if there are more then 1 initial event found in a diagram , anywhere they are to be numbered fro top to bottom in increase order no two events can have the same number in any case
  • 12. Question 1 Activity Predecessor A --- B A C B D C,E E B F C,E G F H G I H,D J I Draw the network diagram
  • 13. Question 2 A project consist of 7 activities .Activities P,Q,R run simultaneously . The relationship among the various activities is as follow Activity successor P S Q T R U Activity V is the immediate successor to S, T, & U Draw the network diagram
  • 14. Question 3 Activity Predecessor A --- B --- C A D C E A F E G B H G I C,E J F K D,G,J Draw the network diagram
  • 15. Estimation activity time  Most optimistic completion time  Most pessimistic completion time  Most likely completion time  te = a+4m+b 6 Where,  a = Most optimistic completion time  b = Most pessimistic completion time  m = Most likely completion time 
  • 16. Question 4 Q: Draw the network, labeling activities Job Activity Immediate Optimistic time Most likely Pessimistic time Predecessor a m b  A - 5 6 7  B - 2 5 8  C A 6 7 14  D B 1 2 3  E C, D 3 3 3  F B 6 8 10  G E 1 4 7  H F, G 4 5 6
  • 17.
  • 18. Activity Slack - Earliest starting time (EST) , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times - Earliest finish time (EFT) - * Preceding from start to finish
  • 19. Activity Slack - Latest starting time (LST): The latest time by which an activity is started with out delaying the total project completion. - Latest finish time (LFT): * Start working from finish to start
  • 20. Determination of critical path Critical Path: Critical path is the series of connecting activities from starting to end for which the total time of completion of all activities is maximum Critical activities /Bottle neck : All activities come in the way of critical path are called critical activities Non Critical activities : All activities do not come in the way of critical path are called non critical activities
  • 21. Float/ Slacks  Slack is the amount of time an event can be delayed without delaying the project completion  Positive slack  Negative slack  Zero slack  Slack = LST – EST  LFT – EFT
  • 22. Question 4 Activities Predecessor activities Activity Time L ---- 3 M ---- 4 N L 9 O L 3 P O 3 Q N,M 6 R N,M 4 S R 2 T R 5 U P,Q,S 6 Draw the network diagram Calculate EST,EFT,LST,LFT ,activity slack & high light the critical path
  • 23. Crash Time Crash time = Crashed Cost – Normal Cost Normal Time – Crashed Time
  • 24. Normal Question 5 Crash Nodes Time Cost Time Cost 1-2 3 300 2 400 2-3 3 30 3 30 2-4 7 420 5 580 2-5 9 720 7 810 3-5 5 250 4 300 4-5 0 0 0 0 5-6 6 320 4 410 6-7 4 400 3 470 6-8 13 780 10 900 7-8 10 1000 9 1200 Project indirect cost is 50Rs. Per week. Draw the network diagram & identify the critical path ? What are the normal project duration and associated Cost ? Find total float associated with each activity Crash the relevant activities systemically and determine the optimal project completion and cost
  • 25. Question 6  On May 1,Arnie Watson sent a memo to his boss, the director of the project (6) management. Stating that the MX project would require 13 weeks for the completion. Arnie realized that customer wanted the job completed in less time, after discussions with the functional managers,Arnie developed the table shown.  According to the contract there is a penalty payment of $5,000 per week for every week over six. What is the minimum amount of additional funding that arnie should request.
  • 26. Normal Crash Job Activity Predecessor Time Cost ($.) Time Cost ($.) Activity  A - 3 6,000 2 8,000  B A 5 12,000 4 13,500  C A 5 16,000 3 22,000  D A 4 8,000 2 10,000  E C,D 2 6,000 1 7,500  F B,E 3 14,000 1 20,000
  • 27. Benefits of CPM/PERT  Interdependencies of activity  Project completion time  Impact of late start  Impact of early start  “what if “ exercise  Evaluation of performance
  • 28. Questions Answered by CPM & PERT  Completion date?  On Schedule?  Within Budget?  Critical Activities?  How can the project be finished early at the least cost?
  • 29. Limitations to CPM/PERT  Clearly defined, independent and stable activities  Specified precedence relationships  Over emphasis on critical paths