SlideShare ist ein Scribd-Unternehmen logo
1 von 34
Downloaden Sie, um offline zu lesen
Innovative Approach to FMEA facilitation




Govind Ramu, P.Eng,
ASQ CQMgr, CQE, CSSBB, CQA, CSQE, CRE,
ASQ Fellow,
QMS 2000 Principal Auditor IRCA (UK)
Past Section Chair Ottawa Valley- ASQ Canada
http://www.asq.org/sixsigma/about/govind.html
History of the FMEA


•• The FMEA discipline was developed in the United States
   The FMEA discipline was developed in the United States
   Military in 1949 (Military Procedure MIL-P-1629, titled
   Military in 1949 (Military Procedure MIL-P-1629, titled
   Procedures for Performing a Failure Mode, Effects and
   Procedures for Performing a Failure Mode, Effects and
   Criticality Analysis.
   Criticality Analysis.
•• The first formal application of FMEA discipline was used in
   The first formal application of FMEA discipline was used in
   aerospace in mid 60s.
    aerospace in mid 60s.
•• It was used as a reliability evaluation technique to determine
    It was used as a reliability evaluation technique to determine
   the effect of system and equipment failures. Failures were
    the effect of system and equipment failures. Failures were
   classified according to their impact on mission success and
    classified according to their impact on mission success and
   personnel/equipment safety.
    personnel/equipment safety.
•• Reference: SAE JJ1739 and AIAG.
   Reference: SAE 1739 and AIAG.
What is FMEA?


A structured approach to
A structured approach to

Identify the way in which a design // process can fail to meet
 Identify the way in which a design process can fail to meet
critical customer requirements.
 critical customer requirements.
Estimating the risk of specific causes with regard to the failures.
 Estimating the risk of specific causes with regard to the failures.
Evaluating the Current control plan for preventing the failures from
 Evaluating the Current control plan for preventing the failures from
occurring.
 occurring.
Prioritizing the actions that should be taken to improve the design/
 Prioritizing the actions that should be taken to improve the design/
process.
 process.
When to use FMEA?


FMEA is very beneficial to conduct while designing a product or
 FMEA is very beneficial to conduct while designing a product or
process.
 process.
Design FMEA should be done during initial design of the product.
 Design FMEA should be done during initial design of the product.
Process FMEA should be done during design of manufacturing
 Process FMEA should be done during design of manufacturing
process.
 process.
Process FMEA can be performed for legacy products and processes
 Process FMEA can be performed for legacy products and processes
also ififthe process carry high risks to product quality, customer, safety,
 also the process carry high risks to product quality, customer, safety,
etc.
 etc.
Different Types of FMEA




         Design FMEA                                         Process FMEA

An analytical technique used                         An analytical technique used
primarily by design responsible                      primarily by manufacturing
engineer/Team to assure                              responsible engineer/Team to
potential failure modes; causes                      assure potential failure modes;
and effects have been                                causes and effects have been
addressed for design related                         addressed for process related
characteristics.                                     characteristics.




                          System, Subsystem,
                          Component level FMEA are
                          possible scopes
Definitions
                                                                                                Criticality
                                                                                          The Criticality rating is the
                                                       Severity                           mathematical product of
                                                                                          the Severity and
                                       Severity is an assessment of how serious the       Occurrence ratings.
                                       Effect of the potential Failure Mode is on the     Criticality = (S) X (O). This
                                       Customer.                                          number is used to place
     Critical Characteristics                                                             priority on items that
                                                                                          require additional quality
Critical Characteristics are Special                                                      planning.
Characteristics defined by
organization that affect customer                      Occurrence
safety and/or could result in non-
compliance with government             Occurrence is an assessment of the likelihood
regulations and thus require special   that a particular Cause will happen and result
controls to ensure 100% compliance.    in the Failure Mode during the intended life and
                                       use of the product.




                                                                                           Risk Priority Number
                                                       Detection
                                                                                          The Risk Priority Number is a
                                       Detection is an assessment of the likelihood       mathematical product of the
                                       that the Current Controls (design and process)     numerical Severity, Occurrence,
                                       will detect the Cause of the Failure Mode or the   and Detection ratings.
                                       Failure Mode itself, thus preventing it from       RPN = (S) X (O) X (D). This
                                       reaching the Customer.                             number is used to place priority
                                                                                          on items than require additional
                                                                                          quality planning.
Definitions
                                                                                                Current Controls
                                                   FMEA Element                        Current Controls (design and process) are the
                                                                                       mechanisms that prevent the Cause of the
                                                  FMEA elements are identified or
         Function                                 analyzed in the FMEA process.
                                                                                       Failure Mode from occurring, or which detect
                                                                                       the failure before it reaches the Customer.
                                                  Common examples are Functions,
A Function could be any
                                                  Failure Modes, Causes, Effects,
intended purpose of a
                                                  Controls, and Actions. FMEA
product or process. FMEA
                                                  elements appear as column
functions are best
                                                  headings in the output form.
described in verb-noun
format with engineering
specifications.


                 Failure Mode                                     Cause                Effect

Failure Modes are sometimes described as                 A Cause is the means by       An Effect is an adverse consequence that the
categories of failure. A potential Failure Mode          which a particular element    Customer might experience. The Customer
describes the way in which a product or                  of the design or process      could be the next operation, subsequent
process could fail to perform its desired                results in a Failure Mode.    operations, or the end user.
function (design intent or performance
requirements) as described by the needs,
wants, and expectations of the internal and
external Customers.



                                                            Customer
                                                   Customers are internal and
                                                   external departments, people, and
                                                   processes that will be adversely
                                                   affected by product failure.
FMEA- A team based effort.



• Input is required from shop
    floor-supervision through to
    management.
•   Engineering/ R & D
•   Service.
•   Reliability.
•   Purchasing.
•   Quality Engineering.
•   Supplier Quality Engineering
•   Manufacturing
•   EH & S, ROHS
FMEA Traditional approach

   Review design and process using a functional block diagram, system
design, architecture and process flow chart.
   Use a brainstorming approach to gather potential failure modes.
   Use historical data from customer returns, complaints and internal
issues from comparable products or processes.
   List potential effects, both internal and external, of failure.
   Assign severity, occurrence and detection (SOD) rankings based on
the effect, probability of occurrence of the root cause and ability to
detect the root cause before the failure mode happens.
   Calculate the risk priority number (RPN) by multiplying severity,
occurrence and detection rankings. Also, calculate criticality by
multiplying severity and occurrence.
   Prioritize the failure modes (risks) based on RPN score and/or
criticality.
   Take actions to eliminate or reduce the risks.
TRADITIONAL
        APPROACH                        FMEA
                                        FMEA                           FMEA
                                                                       FMEA
                                    DEVELOPMENT
                                    DEVELOPMENT                        TEAM
                                                                       TEAM
                                      PROCESS
                                      PROCESS


    Flow               FMEA
                        FMEA
    chart              Forms
                        Forms




FMEA
 FMEA       Process
             Process                        Prepared
                                             Prepared
                                Owner
                                Owner                      Part No.
                                                            Part No.      Due Date
                                                                          Due Date
  #
  #           I.D.
               I.D.                             By
                                                By



FMEA
 FMEA       Core
             Core               Process
                                 Process    Pot Failure
                                             Pot Failure    Failure
                                                             Failure      Severity
                                                                           Severity
DATE
 DATE       Team
            Team                Function
                                 Function     Mode
                                               Mode         Effects
                                                             Effects



             Pot
              Pot                            Current
                                             Current
Class
Class                       Occurrence
                            Occurrence                     Detection
                                                           Detection
            Causes
            Causes                           Control
                                              Control
Major issues



           • Quality of the FMEA
           • Quantity of Completion
           • Fundamental issues- Bundling
             of causes!
           • Fill it, Shut it, Forget it*!


* Courtesy: Famous 80s advertisement campaign from Hero Honda Motor cycle manufacturers India. (On fuel economy)
Pitfalls


During development:
  Not understanding the fundamentals of failure mode effects analysis
(FMEA) development.
  Inadequate representation in the team from subject matter experts.
  Failing to identify the right inputs for the FMEA.
  Poor planning before assembling for brainstorming and failure ranking.


During implementation:
  Breaking the sessions into weekly meetings (thus losing continuity).
  Using severity, occurrence and detection (SOD) scales that are not
representative of the industry, product family or process group.
  Failing to learn from the risks exposed at the component and module-
level FMEA while drafting at the system level FMEA.
  Allowing the rigor of the tool to drive the intensity of initial interactions,
causing fatigue for participants.
Pitfalls (Continued)

During implementation: (Continued)
  Wasting time on risk-rating debates.
  Failing to follow through on recommended actions.
  Failing to drive actions across the board in a systemic way.
  Failing to integrate the learning from design and process FMEAs or to link to
control plans, critical to quality characteristics and critical to process
parameters.




During sustainability:
  Not incorporating the identified, mitigated risks into manufacturing
guidelines to be used for future product development.
  Failure to keep the FMEA alive by including feedback from subsequent
stages of the product life cycle.
Sources of data

Customer Returns- DPPM data
                                                                                                       % Defective, Defects per Unit
 Product Design related                        BODY OF KNOWLEDGE
 E.g. Performance, reliability, etc.                                                                   Process Control
                                           Similar sources of data from comparable                     E.g. Out of Spec, Contamination
Process Design related                       Products, processes of Organization                       Supplier caused
E.g. Opportunity for error                                                                             E.g. Out of Spec, non conformance, etc.


 Process Control
 E.g. Out of Spec, Contamination


 Customer caused                                        DFMEA / PFMEA
 E.g. damage, S/W error, etc.
                                                          (Potential)
 Supplier caused
                                                  Failure mode-Effects-Causes
 E.g. Out of Spec, non conformance, etc.

 Customer Complaints                                                                                        External Knowledge

 Customer complaints on                                                                                   Known Industry failure
 product or system performance                                                                            -Technical journals, publications,
 With No product return or RMA                                                                            -Conferences, etc.

 Internal Ongoing Reliability issues
                                                                     Supplier feedback
 Periodic Surveillance
 E.g. Out of Spec                                                    Product/Process Design Related
                                                                     E.g. tight unrealistic tolerances, Capability.
 Product or Process Changes
 E.g. failure, etc.                                                 Process control issues
                                                                    E.g. traceability, yield, etc.
Scope Process (Process FMEA)

• Formulate Cross functional Team
• Understand Customer/Process Requirements.
• Define the start and end of the Process
• All team members to walk and observe the process.
• Get the assemblers/ process operators to explain the process.
• Team makes notes and observations.
Brainstorm all potential causes for the
   failure modes




                           Inputs:
INNOVATIVE APPROACH        Process Flow charts, Manufacturing WI,
                           Historical process defect pareto, lessons learned, Etc
Brainstorming Software feature


 Microsoft VISIO®
Brainstorm all potential local & end effects
for the failure modes
Brainstorm all potential failure modes


• Utilize process flow chart-break down each step.
• Use knowledge of previous and existing parts/processes.
• Review all quality information E.g.: Scrap, rework, RMA,etc.
• Talk to internal and external customers.



                    Failure Mode                     Effect
   Failure Modes are sometimes described as          An Effect is an adverse consequence that the
   categories of failure. A potential Failure Mode   Customer might experience. The Customer
   describes the way in which a product or           could be the next operation, subsequent
   process could fail to perform its desired         operations, or the end user.
   function (design intent or performance
   requirements) as described by the needs,
   wants, and expectations of the internal and       Example:
   external Customers.                               Does not fit, Cannot load or fasten, poor
                                                     performance, intermittent failure erratic
   Example:                                          operation.
   Fiber Damage, Contamination, hairline crack,
   Dimension oversize.
Identify potential effects of failure




For each failure mode, identify the effect(s)
on the current or next process or customer
downstream in manufacturing/assembly process.



Describe the effects of failure in terms of what the customer
might notice or experience.
Cause and Effect Cascade with an example

                                                                         Cause = Corrosion
       Design       Cause                                                Effect = High Resistance
                        Effect
                        Environmental                                    Cause = High Resistance
                          Exposure                                       Effect = Insufficient Current
                        Cause
                                         Moisture Cause                  Cause = Insufficient Current
                                Effect
                                                   Effect                Effect = Dim Bulb
                                                  Corrosion
             Cause = Design
                                                Cause
             Effect = Env. Exposure                              Poor Contact
                                                                    (High       Cause
             Cause = Env. Exposure                      Effect   Resistance)
                                                                                   Effect
             Effect = Moisture
                                                                                  Insufficient
                                                                                                 Cause
                                                                                    Current
             Cause = Moisture                                                                       Effect
             Effect = Corrosion                                                                    Dim Bulb


Courtesy: Elsmar Cove
Determine severity rating




Severity is an assessment of the seriousness of
the effect of Potential failure mode to the customer.
Severity applies to effect only.




Note: Assigning severity rating should be performed as a team
Including customer representative and or Design FMEA engineer.
If the customer affected by a failure mode is a user outside the plant, team
Should consult them and assign the rating.
Identify all potential causes of failure


  How the failure could occur? Describe in terms of factors
  That can be corrected or controlled.


  There could be more than one cause for each failure!!


  Example:Improper torque, Inaccurate gauging, inadequate lubrication, etc.




Note: Experiments may have to be conducted to determine causes using technical
Problem solving.

Management should have control on the cause identified. The cause
should be at the root level.
Determine occurrence rating



    Occurrence is how frequently the specific failure cause
    Mechanism is projected to occur.
  Define Current Controls

   Systematic methods/devices in place to prevent or detect
   Failure modes or causes (before the effect happens).
   Example: Poke-Yoke, automated control for setup verification




Note: If available from a similar process, statistical data should be used to determine
Occurrence ranking.
Determine detection ranking


  Detection is an assessment of the probability that the
  current process control will detect a Potential cause.



  Also assess the ability of the process control to detect
  Low frequency failure modes or prevent from going
  Into the next process.


Note: Random quality checks are unlikely to detect the existence of an isolated
Defect and should not influence the detection ranking. Sampling done on a
Statistical basis is a valid detection control.
Current Controls

Design and Process controls are grouped according to their purpose.
Type (1)

       These controls prevent the Cause or Failure Mode from
       occurring, or reduce their rate of occurrence.
Type (2)

       These controls detect the Cause of the Failure Mode and
       lead to corrective action.
Type (3)

       These Controls detect the Failure Mode before the
       product reaches the customer. The customer could be
       the next operation, subsequent operations, or the end
       user.
    The distinction between controls that prevent failure (Type 1) and controls that detect failure (Types 2 and 3) is
    important. Type 1 controls reduce the likelihood that a Cause or Failure Mode will occur, and therefore affect
    Occurrence ratings. Type 2 and Type 3 Controls detect Causes and Failure Modes respectively, and therefore
    affect Detection ratings.
Calculate the Risk Priority Numbers

The Risk Priority Number is the product of
Severity (S) X Occurrence (O) X Detection (D) rankings.

This value should be used to rank order the concerns
In the process using Pareto. The RPN will be
between 1and 1000.


Criticality is severity multiplied by occurrence.
This is also an important metric.
RPN can be reduced by improving the detection, but the
process issue may remain intact. Criticality can be
reduced only by improving the capability or redesign.
Prioritize Corrective actions



•Concentrate on the Highest RPN
•Do not lose sight on effects with high severity.
•Think of how the occurrence can be reduced?
•How the detection can be improved?
•Where applicable use Mistake proofing techniques.
•Introduce changes in a controlled manner.
Reassess rankings when action completed


• FMEA must be a Live document.
• Review Regularly.
• Reassess rankings whenever changes made to product/process.
• Add any new defects or potential problems when found.
References


•   Potential Failure Mode & Effects Analysis, fourth edition,
    Automotive Industry Action Group, 2008.
•   Govindarajan “Govind” Ramu, “Metrics That Trigger
    Actionable Discussions: Prioritize Process Improvements
    Using Gauge R&R and SPC Capability,” ASQ Six Sigma
    Forum.
•   Traditionally, NGT is used to collect ideas:
    www.asq.org/learn-about-quality/idea-creation-
    tools/overview/nominal-group.html In FMEA development, it
    can be used to collect scores of SOD.
•   Elsmar Cove archived file references.


Bibliography
Quality Training Portal, Resource Engineering Inc., “What You Need to
Know About Failure Mode and Effects Analysis (FMEA),”
www.qualitytrainingportal.com/resources/fmea/index.htm.
May 2009 QP – Standards Outlook – Dan Reid- Major Upgrade.

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
 
Process F.M.E.A
Process F.M.E.AProcess F.M.E.A
Process F.M.E.A
 
Training ppt for control plan
Training ppt for control plan   Training ppt for control plan
Training ppt for control plan
 
Fmea
FmeaFmea
Fmea
 
PFMEA
PFMEA PFMEA
PFMEA
 
PPAP
PPAPPPAP
PPAP
 
Error proofing IATF16949:2016
Error proofing IATF16949:2016Error proofing IATF16949:2016
Error proofing IATF16949:2016
 
Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)
 
Attribute MSA presentation
Attribute MSA presentationAttribute MSA presentation
Attribute MSA presentation
 
2006 pfmea presentation
2006 pfmea presentation2006 pfmea presentation
2006 pfmea presentation
 
FMEA
FMEAFMEA
FMEA
 
Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)
 
TPM - tech talk
TPM - tech talk TPM - tech talk
TPM - tech talk
 
Poka yoke error proofing
Poka yoke error proofing Poka yoke error proofing
Poka yoke error proofing
 
5. spc control charts
5. spc   control charts5. spc   control charts
5. spc control charts
 
FMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysisFMEA - Failure mode and effects analysis
FMEA - Failure mode and effects analysis
 
Ppap training ppt
Ppap training   ppt Ppap training   ppt
Ppap training ppt
 
NG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - IntroductionNG BB 23 Measurement System Analysis - Introduction
NG BB 23 Measurement System Analysis - Introduction
 
Ppap la
Ppap laPpap la
Ppap la
 
Core tools apqp, ppap, fmea, spc and msa
Core tools   apqp, ppap, fmea, spc and msa Core tools   apqp, ppap, fmea, spc and msa
Core tools apqp, ppap, fmea, spc and msa
 

Andere mochten auch

DFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostDFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostRicardo Gonzalez Luna
 
Fmea presentation
Fmea presentationFmea presentation
Fmea presentationMurat Terzi
 
Back of the napkin FMEA
Back of the napkin FMEABack of the napkin FMEA
Back of the napkin FMEATom Curtis
 
Design flow webpage
Design flow webpageDesign flow webpage
Design flow webpageClaudia Sin
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011ExerciseLeanLLC
 
F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]ExerciseLeanLLC
 
6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]ExerciseLeanLLC
 
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]ExerciseLeanLLC
 
Std Wk Job Breakdown 522 P051 30
Std Wk Job Breakdown 522 P051 30Std Wk Job Breakdown 522 P051 30
Std Wk Job Breakdown 522 P051 30ExerciseLeanLLC
 
Services Of Exercise Lean Group
Services Of Exercise Lean GroupServices Of Exercise Lean Group
Services Of Exercise Lean GroupExerciseLeanLLC
 
Assurion%20 Value%20 Added%20 Process%20 Steps[1]
Assurion%20 Value%20 Added%20 Process%20 Steps[1]Assurion%20 Value%20 Added%20 Process%20 Steps[1]
Assurion%20 Value%20 Added%20 Process%20 Steps[1]ExerciseLeanLLC
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Abbas (Bob) Youssef MBA, PhD
 
Rapid Site Assessment June 27 2010
Rapid Site Assessment June 27 2010Rapid Site Assessment June 27 2010
Rapid Site Assessment June 27 2010ExerciseLeanLLC
 
Risk Management in Sterile Environments
Risk Management in Sterile Environments Risk Management in Sterile Environments
Risk Management in Sterile Environments Tim Sandle, Ph.D.
 
Production Efficiency July 2011
Production Efficiency July 2011Production Efficiency July 2011
Production Efficiency July 2011ExerciseLeanLLC
 
Strategic Planning Overview[1]
Strategic Planning Overview[1]Strategic Planning Overview[1]
Strategic Planning Overview[1]ExerciseLeanLLC
 

Andere mochten auch (20)

DFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostDFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and Cost
 
Fmea presentation
Fmea presentationFmea presentation
Fmea presentation
 
Back of the napkin FMEA
Back of the napkin FMEABack of the napkin FMEA
Back of the napkin FMEA
 
091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)091814 Failure Mode Effect and Analysis (FMEA)
091814 Failure Mode Effect and Analysis (FMEA)
 
Design flow webpage
Design flow webpageDesign flow webpage
Design flow webpage
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011
 
F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]
 
6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]
 
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
 
Std Wk Job Breakdown 522 P051 30
Std Wk Job Breakdown 522 P051 30Std Wk Job Breakdown 522 P051 30
Std Wk Job Breakdown 522 P051 30
 
Services Of Exercise Lean Group
Services Of Exercise Lean GroupServices Of Exercise Lean Group
Services Of Exercise Lean Group
 
Assurion%20 Value%20 Added%20 Process%20 Steps[1]
Assurion%20 Value%20 Added%20 Process%20 Steps[1]Assurion%20 Value%20 Added%20 Process%20 Steps[1]
Assurion%20 Value%20 Added%20 Process%20 Steps[1]
 
8 D Quallity Glossary
8 D Quallity Glossary8 D Quallity Glossary
8 D Quallity Glossary
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
 
Rapid Site Assessment June 27 2010
Rapid Site Assessment June 27 2010Rapid Site Assessment June 27 2010
Rapid Site Assessment June 27 2010
 
Risk Management in Sterile Environments
Risk Management in Sterile Environments Risk Management in Sterile Environments
Risk Management in Sterile Environments
 
Production Efficiency July 2011
Production Efficiency July 2011Production Efficiency July 2011
Production Efficiency July 2011
 
Mse June 24 2011
Mse June 24 2011Mse June 24 2011
Mse June 24 2011
 
8 D Training Slides
8 D Training Slides8 D Training Slides
8 D Training Slides
 
Strategic Planning Overview[1]
Strategic Planning Overview[1]Strategic Planning Overview[1]
Strategic Planning Overview[1]
 

Ähnlich wie Innovative FMEA Approach

Failure mode
Failure modeFailure mode
Failure modeGia Lara
 
Reducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsReducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsWilde Analysis Ltd.
 
FAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISFAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISANNA UNIVERSITY
 
Failure Mode Effect Analysis in Engineering Failures
Failure Mode Effect Analysis in Engineering FailuresFailure Mode Effect Analysis in Engineering Failures
Failure Mode Effect Analysis in Engineering FailuresPadmanabhan Krishnan
 
Failure mode and effects analysis
Failure mode and effects analysisFailure mode and effects analysis
Failure mode and effects analysisDeep parmar
 
IT 381_Chap_7.ppt
IT 381_Chap_7.pptIT 381_Chap_7.ppt
IT 381_Chap_7.pptRajendran C
 
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...SUNDHARAVADIVELR1
 
FMEA presentation for research and development
FMEA presentation for research and developmentFMEA presentation for research and development
FMEA presentation for research and developmentbasant11731
 
FMEA análise e odos de falhas e seus efeitos.ppt
FMEA análise e odos de falhas e seus efeitos.pptFMEA análise e odos de falhas e seus efeitos.ppt
FMEA análise e odos de falhas e seus efeitos.pptGleibsonHenrique
 
IT 381_Chap hubybybybybybybytggyguh7h7_7.ppt
IT 381_Chap hubybybybybybybytggyguh7h7_7.pptIT 381_Chap hubybybybybybybytggyguh7h7_7.ppt
IT 381_Chap hubybybybybybybytggyguh7h7_7.pptksujith0034
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
Failure modes effect analysis
Failure modes effect analysisFailure modes effect analysis
Failure modes effect analysismaheskumargkm
 

Ähnlich wie Innovative FMEA Approach (20)

Failure mode
Failure modeFailure mode
Failure mode
 
Reducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering MethodsReducing Product Development Risk with Reliability Engineering Methods
Reducing Product Development Risk with Reliability Engineering Methods
 
FAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSISFAILURE MODE EFFECT ANALYSIS
FAILURE MODE EFFECT ANALYSIS
 
Tqm fmea
Tqm fmeaTqm fmea
Tqm fmea
 
Tqm fmea
Tqm fmeaTqm fmea
Tqm fmea
 
FMEA.pptx
FMEA.pptxFMEA.pptx
FMEA.pptx
 
Failure Mode Effect Analysis in Engineering Failures
Failure Mode Effect Analysis in Engineering FailuresFailure Mode Effect Analysis in Engineering Failures
Failure Mode Effect Analysis in Engineering Failures
 
Quality & Reliability in Software Engineering
Quality & Reliability in Software EngineeringQuality & Reliability in Software Engineering
Quality & Reliability in Software Engineering
 
Failure mode and effects analysis
Failure mode and effects analysisFailure mode and effects analysis
Failure mode and effects analysis
 
FMEA
FMEAFMEA
FMEA
 
IT 381_Chap_7.ppt
IT 381_Chap_7.pptIT 381_Chap_7.ppt
IT 381_Chap_7.ppt
 
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...
Failure mode effects analysis, Computer Integrated Manufacturing, Quality fun...
 
FMEA presentation for research and development
FMEA presentation for research and developmentFMEA presentation for research and development
FMEA presentation for research and development
 
FMEA análise e odos de falhas e seus efeitos.ppt
FMEA análise e odos de falhas e seus efeitos.pptFMEA análise e odos de falhas e seus efeitos.ppt
FMEA análise e odos de falhas e seus efeitos.ppt
 
IT 381_Chap hubybybybybybybytggyguh7h7_7.ppt
IT 381_Chap hubybybybybybybytggyguh7h7_7.pptIT 381_Chap hubybybybybybybytggyguh7h7_7.ppt
IT 381_Chap hubybybybybybybytggyguh7h7_7.ppt
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
FMEA
FMEAFMEA
FMEA
 
Mahi2
Mahi2Mahi2
Mahi2
 
Mahi2
Mahi2Mahi2
Mahi2
 
Failure modes effect analysis
Failure modes effect analysisFailure modes effect analysis
Failure modes effect analysis
 

Mehr von Govind Ramu

Demystifying Cost of Quality.pdf
Demystifying Cost of Quality.pdfDemystifying Cost of Quality.pdf
Demystifying Cost of Quality.pdfGovind Ramu
 
Quality Management - Guidelines for realizing financial and economic benefits
Quality Management - Guidelines for realizing financial and economic benefitsQuality Management - Guidelines for realizing financial and economic benefits
Quality Management - Guidelines for realizing financial and economic benefitsGovind Ramu
 
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...Govind Ramu
 
ISO 9001 2015 Overview presentation
ISO 9001 2015 Overview presentation ISO 9001 2015 Overview presentation
ISO 9001 2015 Overview presentation Govind Ramu
 
ISO 9001:2015 DIS Changes, Requirements and Implementation
ISO 9001:2015 DIS Changes, Requirements and ImplementationISO 9001:2015 DIS Changes, Requirements and Implementation
ISO 9001:2015 DIS Changes, Requirements and Implementation Govind Ramu
 
Overview of the proposed Photovoltaic Solar Quality Management System standard
Overview of the proposed Photovoltaic Solar Quality Management System standardOverview of the proposed Photovoltaic Solar Quality Management System standard
Overview of the proposed Photovoltaic Solar Quality Management System standardGovind Ramu
 
Future of-quality asq 042011-govind
Future of-quality asq 042011-govindFuture of-quality asq 042011-govind
Future of-quality asq 042011-govindGovind Ramu
 
ASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit ExampleASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit ExampleGovind Ramu
 
Tips For Passing Asq Certification Exam Asq
Tips For Passing Asq Certification Exam AsqTips For Passing Asq Certification Exam Asq
Tips For Passing Asq Certification Exam AsqGovind Ramu
 
Prioritizing Process Improvements
Prioritizing Process ImprovementsPrioritizing Process Improvements
Prioritizing Process ImprovementsGovind Ramu
 
Quality In Outsourcing
Quality In OutsourcingQuality In Outsourcing
Quality In OutsourcingGovind Ramu
 
Iso9001 2008 Change Analysis Govind
Iso9001 2008 Change Analysis GovindIso9001 2008 Change Analysis Govind
Iso9001 2008 Change Analysis GovindGovind Ramu
 
Iso9001 2008 Transition Asq Govind
Iso9001 2008 Transition Asq GovindIso9001 2008 Transition Asq Govind
Iso9001 2008 Transition Asq GovindGovind Ramu
 

Mehr von Govind Ramu (13)

Demystifying Cost of Quality.pdf
Demystifying Cost of Quality.pdfDemystifying Cost of Quality.pdf
Demystifying Cost of Quality.pdf
 
Quality Management - Guidelines for realizing financial and economic benefits
Quality Management - Guidelines for realizing financial and economic benefitsQuality Management - Guidelines for realizing financial and economic benefits
Quality Management - Guidelines for realizing financial and economic benefits
 
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...
Integrated Management Systems ASQ Silicon Valley section 0613 april 2017_gr c...
 
ISO 9001 2015 Overview presentation
ISO 9001 2015 Overview presentation ISO 9001 2015 Overview presentation
ISO 9001 2015 Overview presentation
 
ISO 9001:2015 DIS Changes, Requirements and Implementation
ISO 9001:2015 DIS Changes, Requirements and ImplementationISO 9001:2015 DIS Changes, Requirements and Implementation
ISO 9001:2015 DIS Changes, Requirements and Implementation
 
Overview of the proposed Photovoltaic Solar Quality Management System standard
Overview of the proposed Photovoltaic Solar Quality Management System standardOverview of the proposed Photovoltaic Solar Quality Management System standard
Overview of the proposed Photovoltaic Solar Quality Management System standard
 
Future of-quality asq 042011-govind
Future of-quality asq 042011-govindFuture of-quality asq 042011-govind
Future of-quality asq 042011-govind
 
ASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit ExampleASQ CSSBB Affidavit Example
ASQ CSSBB Affidavit Example
 
Tips For Passing Asq Certification Exam Asq
Tips For Passing Asq Certification Exam AsqTips For Passing Asq Certification Exam Asq
Tips For Passing Asq Certification Exam Asq
 
Prioritizing Process Improvements
Prioritizing Process ImprovementsPrioritizing Process Improvements
Prioritizing Process Improvements
 
Quality In Outsourcing
Quality In OutsourcingQuality In Outsourcing
Quality In Outsourcing
 
Iso9001 2008 Change Analysis Govind
Iso9001 2008 Change Analysis GovindIso9001 2008 Change Analysis Govind
Iso9001 2008 Change Analysis Govind
 
Iso9001 2008 Transition Asq Govind
Iso9001 2008 Transition Asq GovindIso9001 2008 Transition Asq Govind
Iso9001 2008 Transition Asq Govind
 

Innovative FMEA Approach

  • 1. Innovative Approach to FMEA facilitation Govind Ramu, P.Eng, ASQ CQMgr, CQE, CSSBB, CQA, CSQE, CRE, ASQ Fellow, QMS 2000 Principal Auditor IRCA (UK) Past Section Chair Ottawa Valley- ASQ Canada http://www.asq.org/sixsigma/about/govind.html
  • 2. History of the FMEA •• The FMEA discipline was developed in the United States The FMEA discipline was developed in the United States Military in 1949 (Military Procedure MIL-P-1629, titled Military in 1949 (Military Procedure MIL-P-1629, titled Procedures for Performing a Failure Mode, Effects and Procedures for Performing a Failure Mode, Effects and Criticality Analysis. Criticality Analysis. •• The first formal application of FMEA discipline was used in The first formal application of FMEA discipline was used in aerospace in mid 60s. aerospace in mid 60s. •• It was used as a reliability evaluation technique to determine It was used as a reliability evaluation technique to determine the effect of system and equipment failures. Failures were the effect of system and equipment failures. Failures were classified according to their impact on mission success and classified according to their impact on mission success and personnel/equipment safety. personnel/equipment safety. •• Reference: SAE JJ1739 and AIAG. Reference: SAE 1739 and AIAG.
  • 3. What is FMEA? A structured approach to A structured approach to Identify the way in which a design // process can fail to meet Identify the way in which a design process can fail to meet critical customer requirements. critical customer requirements. Estimating the risk of specific causes with regard to the failures. Estimating the risk of specific causes with regard to the failures. Evaluating the Current control plan for preventing the failures from Evaluating the Current control plan for preventing the failures from occurring. occurring. Prioritizing the actions that should be taken to improve the design/ Prioritizing the actions that should be taken to improve the design/ process. process.
  • 4. When to use FMEA? FMEA is very beneficial to conduct while designing a product or FMEA is very beneficial to conduct while designing a product or process. process. Design FMEA should be done during initial design of the product. Design FMEA should be done during initial design of the product. Process FMEA should be done during design of manufacturing Process FMEA should be done during design of manufacturing process. process. Process FMEA can be performed for legacy products and processes Process FMEA can be performed for legacy products and processes also ififthe process carry high risks to product quality, customer, safety, also the process carry high risks to product quality, customer, safety, etc. etc.
  • 5. Different Types of FMEA Design FMEA Process FMEA An analytical technique used An analytical technique used primarily by design responsible primarily by manufacturing engineer/Team to assure responsible engineer/Team to potential failure modes; causes assure potential failure modes; and effects have been causes and effects have been addressed for design related addressed for process related characteristics. characteristics. System, Subsystem, Component level FMEA are possible scopes
  • 6. Definitions Criticality The Criticality rating is the Severity mathematical product of the Severity and Severity is an assessment of how serious the Occurrence ratings. Effect of the potential Failure Mode is on the Criticality = (S) X (O). This Customer. number is used to place Critical Characteristics priority on items that require additional quality Critical Characteristics are Special planning. Characteristics defined by organization that affect customer Occurrence safety and/or could result in non- compliance with government Occurrence is an assessment of the likelihood regulations and thus require special that a particular Cause will happen and result controls to ensure 100% compliance. in the Failure Mode during the intended life and use of the product. Risk Priority Number Detection The Risk Priority Number is a Detection is an assessment of the likelihood mathematical product of the that the Current Controls (design and process) numerical Severity, Occurrence, will detect the Cause of the Failure Mode or the and Detection ratings. Failure Mode itself, thus preventing it from RPN = (S) X (O) X (D). This reaching the Customer. number is used to place priority on items than require additional quality planning.
  • 7. Definitions Current Controls FMEA Element Current Controls (design and process) are the mechanisms that prevent the Cause of the FMEA elements are identified or Function analyzed in the FMEA process. Failure Mode from occurring, or which detect the failure before it reaches the Customer. Common examples are Functions, A Function could be any Failure Modes, Causes, Effects, intended purpose of a Controls, and Actions. FMEA product or process. FMEA elements appear as column functions are best headings in the output form. described in verb-noun format with engineering specifications. Failure Mode Cause Effect Failure Modes are sometimes described as A Cause is the means by An Effect is an adverse consequence that the categories of failure. A potential Failure Mode which a particular element Customer might experience. The Customer describes the way in which a product or of the design or process could be the next operation, subsequent process could fail to perform its desired results in a Failure Mode. operations, or the end user. function (design intent or performance requirements) as described by the needs, wants, and expectations of the internal and external Customers. Customer Customers are internal and external departments, people, and processes that will be adversely affected by product failure.
  • 8. FMEA- A team based effort. • Input is required from shop floor-supervision through to management. • Engineering/ R & D • Service. • Reliability. • Purchasing. • Quality Engineering. • Supplier Quality Engineering • Manufacturing • EH & S, ROHS
  • 9. FMEA Traditional approach Review design and process using a functional block diagram, system design, architecture and process flow chart. Use a brainstorming approach to gather potential failure modes. Use historical data from customer returns, complaints and internal issues from comparable products or processes. List potential effects, both internal and external, of failure. Assign severity, occurrence and detection (SOD) rankings based on the effect, probability of occurrence of the root cause and ability to detect the root cause before the failure mode happens. Calculate the risk priority number (RPN) by multiplying severity, occurrence and detection rankings. Also, calculate criticality by multiplying severity and occurrence. Prioritize the failure modes (risks) based on RPN score and/or criticality. Take actions to eliminate or reduce the risks.
  • 10. TRADITIONAL APPROACH FMEA FMEA FMEA FMEA DEVELOPMENT DEVELOPMENT TEAM TEAM PROCESS PROCESS Flow FMEA FMEA chart Forms Forms FMEA FMEA Process Process Prepared Prepared Owner Owner Part No. Part No. Due Date Due Date # # I.D. I.D. By By FMEA FMEA Core Core Process Process Pot Failure Pot Failure Failure Failure Severity Severity DATE DATE Team Team Function Function Mode Mode Effects Effects Pot Pot Current Current Class Class Occurrence Occurrence Detection Detection Causes Causes Control Control
  • 11.
  • 12. Major issues • Quality of the FMEA • Quantity of Completion • Fundamental issues- Bundling of causes! • Fill it, Shut it, Forget it*! * Courtesy: Famous 80s advertisement campaign from Hero Honda Motor cycle manufacturers India. (On fuel economy)
  • 13. Pitfalls During development: Not understanding the fundamentals of failure mode effects analysis (FMEA) development. Inadequate representation in the team from subject matter experts. Failing to identify the right inputs for the FMEA. Poor planning before assembling for brainstorming and failure ranking. During implementation: Breaking the sessions into weekly meetings (thus losing continuity). Using severity, occurrence and detection (SOD) scales that are not representative of the industry, product family or process group. Failing to learn from the risks exposed at the component and module- level FMEA while drafting at the system level FMEA. Allowing the rigor of the tool to drive the intensity of initial interactions, causing fatigue for participants.
  • 14. Pitfalls (Continued) During implementation: (Continued) Wasting time on risk-rating debates. Failing to follow through on recommended actions. Failing to drive actions across the board in a systemic way. Failing to integrate the learning from design and process FMEAs or to link to control plans, critical to quality characteristics and critical to process parameters. During sustainability: Not incorporating the identified, mitigated risks into manufacturing guidelines to be used for future product development. Failure to keep the FMEA alive by including feedback from subsequent stages of the product life cycle.
  • 15.
  • 16.
  • 17.
  • 18. Sources of data Customer Returns- DPPM data % Defective, Defects per Unit Product Design related BODY OF KNOWLEDGE E.g. Performance, reliability, etc. Process Control Similar sources of data from comparable E.g. Out of Spec, Contamination Process Design related Products, processes of Organization Supplier caused E.g. Opportunity for error E.g. Out of Spec, non conformance, etc. Process Control E.g. Out of Spec, Contamination Customer caused DFMEA / PFMEA E.g. damage, S/W error, etc. (Potential) Supplier caused Failure mode-Effects-Causes E.g. Out of Spec, non conformance, etc. Customer Complaints External Knowledge Customer complaints on Known Industry failure product or system performance -Technical journals, publications, With No product return or RMA -Conferences, etc. Internal Ongoing Reliability issues Supplier feedback Periodic Surveillance E.g. Out of Spec Product/Process Design Related E.g. tight unrealistic tolerances, Capability. Product or Process Changes E.g. failure, etc. Process control issues E.g. traceability, yield, etc.
  • 19. Scope Process (Process FMEA) • Formulate Cross functional Team • Understand Customer/Process Requirements. • Define the start and end of the Process • All team members to walk and observe the process. • Get the assemblers/ process operators to explain the process. • Team makes notes and observations.
  • 20. Brainstorm all potential causes for the failure modes Inputs: INNOVATIVE APPROACH Process Flow charts, Manufacturing WI, Historical process defect pareto, lessons learned, Etc
  • 21. Brainstorming Software feature Microsoft VISIO®
  • 22. Brainstorm all potential local & end effects for the failure modes
  • 23. Brainstorm all potential failure modes • Utilize process flow chart-break down each step. • Use knowledge of previous and existing parts/processes. • Review all quality information E.g.: Scrap, rework, RMA,etc. • Talk to internal and external customers. Failure Mode Effect Failure Modes are sometimes described as An Effect is an adverse consequence that the categories of failure. A potential Failure Mode Customer might experience. The Customer describes the way in which a product or could be the next operation, subsequent process could fail to perform its desired operations, or the end user. function (design intent or performance requirements) as described by the needs, wants, and expectations of the internal and Example: external Customers. Does not fit, Cannot load or fasten, poor performance, intermittent failure erratic Example: operation. Fiber Damage, Contamination, hairline crack, Dimension oversize.
  • 24. Identify potential effects of failure For each failure mode, identify the effect(s) on the current or next process or customer downstream in manufacturing/assembly process. Describe the effects of failure in terms of what the customer might notice or experience.
  • 25. Cause and Effect Cascade with an example Cause = Corrosion Design Cause Effect = High Resistance Effect Environmental Cause = High Resistance Exposure Effect = Insufficient Current Cause Moisture Cause Cause = Insufficient Current Effect Effect Effect = Dim Bulb Corrosion Cause = Design Cause Effect = Env. Exposure Poor Contact (High Cause Cause = Env. Exposure Effect Resistance) Effect Effect = Moisture Insufficient Cause Current Cause = Moisture Effect Effect = Corrosion Dim Bulb Courtesy: Elsmar Cove
  • 26. Determine severity rating Severity is an assessment of the seriousness of the effect of Potential failure mode to the customer. Severity applies to effect only. Note: Assigning severity rating should be performed as a team Including customer representative and or Design FMEA engineer. If the customer affected by a failure mode is a user outside the plant, team Should consult them and assign the rating.
  • 27. Identify all potential causes of failure How the failure could occur? Describe in terms of factors That can be corrected or controlled. There could be more than one cause for each failure!! Example:Improper torque, Inaccurate gauging, inadequate lubrication, etc. Note: Experiments may have to be conducted to determine causes using technical Problem solving. Management should have control on the cause identified. The cause should be at the root level.
  • 28. Determine occurrence rating Occurrence is how frequently the specific failure cause Mechanism is projected to occur. Define Current Controls Systematic methods/devices in place to prevent or detect Failure modes or causes (before the effect happens). Example: Poke-Yoke, automated control for setup verification Note: If available from a similar process, statistical data should be used to determine Occurrence ranking.
  • 29. Determine detection ranking Detection is an assessment of the probability that the current process control will detect a Potential cause. Also assess the ability of the process control to detect Low frequency failure modes or prevent from going Into the next process. Note: Random quality checks are unlikely to detect the existence of an isolated Defect and should not influence the detection ranking. Sampling done on a Statistical basis is a valid detection control.
  • 30. Current Controls Design and Process controls are grouped according to their purpose. Type (1) These controls prevent the Cause or Failure Mode from occurring, or reduce their rate of occurrence. Type (2) These controls detect the Cause of the Failure Mode and lead to corrective action. Type (3) These Controls detect the Failure Mode before the product reaches the customer. The customer could be the next operation, subsequent operations, or the end user. The distinction between controls that prevent failure (Type 1) and controls that detect failure (Types 2 and 3) is important. Type 1 controls reduce the likelihood that a Cause or Failure Mode will occur, and therefore affect Occurrence ratings. Type 2 and Type 3 Controls detect Causes and Failure Modes respectively, and therefore affect Detection ratings.
  • 31. Calculate the Risk Priority Numbers The Risk Priority Number is the product of Severity (S) X Occurrence (O) X Detection (D) rankings. This value should be used to rank order the concerns In the process using Pareto. The RPN will be between 1and 1000. Criticality is severity multiplied by occurrence. This is also an important metric. RPN can be reduced by improving the detection, but the process issue may remain intact. Criticality can be reduced only by improving the capability or redesign.
  • 32. Prioritize Corrective actions •Concentrate on the Highest RPN •Do not lose sight on effects with high severity. •Think of how the occurrence can be reduced? •How the detection can be improved? •Where applicable use Mistake proofing techniques. •Introduce changes in a controlled manner.
  • 33. Reassess rankings when action completed • FMEA must be a Live document. • Review Regularly. • Reassess rankings whenever changes made to product/process. • Add any new defects or potential problems when found.
  • 34. References • Potential Failure Mode & Effects Analysis, fourth edition, Automotive Industry Action Group, 2008. • Govindarajan “Govind” Ramu, “Metrics That Trigger Actionable Discussions: Prioritize Process Improvements Using Gauge R&R and SPC Capability,” ASQ Six Sigma Forum. • Traditionally, NGT is used to collect ideas: www.asq.org/learn-about-quality/idea-creation- tools/overview/nominal-group.html In FMEA development, it can be used to collect scores of SOD. • Elsmar Cove archived file references. Bibliography Quality Training Portal, Resource Engineering Inc., “What You Need to Know About Failure Mode and Effects Analysis (FMEA),” www.qualitytrainingportal.com/resources/fmea/index.htm. May 2009 QP – Standards Outlook – Dan Reid- Major Upgrade.