SlideShare ist ein Scribd-Unternehmen logo
1 von 12
Downloaden Sie, um offline zu lesen
WM2012 Conference, February 26 – March 1, 2012, Phoenix, Arizona, USA


   Improving DOE Project Performance Using the DOD Integrated Master Plan – 12481


Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing
Principle, Western Region, Project Time & Cost



ABSTRACT
DOE O 413 measures a project’s progress to plan by the consumption of funding, the passage
of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy,
Science, Card received a memo directing the implementation of Project Management and the
Project Management Manual, including the Integrated Master Plan and Integrated Master
Schedule. This directive states “the integrated master plan and schedule tie together all project
tasks by showing their logical relationships and any constraints controlling the start or finish of
each task. This process results in a hierarchy of related functional and layered schedules
derived from the Work Breakdown Structure that can be used for monitoring and controlling
project progress.” This paper shows how restoring the IMP/IMS paradigm to DOE program
management increases the probability of program success in ways not currently available using
DOD O 413 processes alone.

INTRODUCTION
The measures of progress to plan in units meaningful to the decision maker are needed to
answer the question – How Long Are We Willing to Wait before We Find out We Are Late?
As recently as January of 2011 updates to DOE O 413.3B were made with focus on four
philosophical goals. [3] With this 2011 directive and the 2003 memo to Robert Card (Project
Management and the Project Management Manual) [1] addressing the use of Integrated Master
Plans and Schedules in Section 6.5.1, the measures needed to answer this question are still not
specifically stated in the most recent version of the DOE O 413 series. However, the DOD
5000.02 and Integrated Master Plan (IMP) paradigm provides the mechanism to answer the
question and should be adopted by DOE. The IMP, as applied by the DOD, defines the
incremental increase of a project’s maturity, assessed through Significant Accomplishments
(SA) and Accomplishment Criteria (AC), using Measures of Effectiveness (MoE), Measures of
Performance (MoP), and Technical Performance Measures (TPM). [2]
The memo to Card reflects a nearly identical structure to the DOD Integrated Master Plan and
establishes DOE M 413.3–1 (Project Management for the Acquisition of Capital Assets) as a
primary guidance document using the IMP/IMS in 2003. But the current DOE O 413.3–1 does
not include the use on an Integrated Master Plan (IMP) [7], [11].
Applying Card’s 2003 DOD IMP paradigm to DOE O 413 series projects will improve the
probability of DOE project success through measures of increasing maturity of the deliverables
defined in the Integrated Master Plan (IMP), in addition to measures of progress through cost
and schedule performance and milestone compliance. [3]
For motivation for this IMP/IMS approach, we need only look to recent reports that provide a
sample of assessments: GAO–07–336 Major Construction Projects Need a Consistent
Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays [4], GAO–
09–406 Contract and Project Management Concerns at NNSA and Office of EM [5] and GAO–
08–1081 Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s
Major Cleanup Projects [6].



                                                1
These GAO reports found that …:
       … the cost increases and schedule delays that have occurred for most of these projects
        have been the result of inconsistent application of project management tools and
        techniques on the part of both DOE and its contractors.[5]
          … exceeded their original cost or schedule estimates, principally because of ineffective
           DOE project oversight and poor contractor management. [4]
       … had life cycle baseline cost increases, from a low of $139 million for one project to a
        high of nearly $9 billion for another, and life cycle baseline schedule delays from 2 to 15
        years. These changes occurred primarily because the baselines we reviewed included
        schedule assumptions that were not linked to technical or budget realities and the scope
        of work included other assumptions that did not prove true. [6]
Project success depends on answering 5 immutable questions, no matter the domain or the
project context in that domain, the project management method, or the agency guidance.
      1.   What does “Done” look like?
      2.   What is the path to reaching “Done” on time, on budget, and technically compliant?
      3.   What resources (time, money, staff, and facilities) are needed to reach “Done?
      4.   What impediments will prevent reaching “Done”?
      5.   How is physical progress to plan measured on the path to “Done?”
Project success starts with describing what “Done” looks like in units of measure meaningful to
the decision makers. These measures of performance (technical and programmatic) and
effectiveness (the customer’s point of view) are derived from the elements of the Integrated
Master Plan – Program Events, Significant Accomplishments, and the Accomplishment Criteria
of the baselined Work Packages.

DOE G 413.5 (Performance Measurement Baseline) describes the measurement of progress to
plan through Key Performance Parameters (KPP), Cost, and Schedule Performance. These
measures do not answer the 5 immutable questions stated above. The answers need to be in
units of Increasing Maturity of the project outcomes. [8]
DOE O 413.3b (Program and Project Management for the Acquisition of Capital Assets)
mentions the term maturity 14 times. [9] DOE O 413.3–9 (Project Review Guide for Capital
Asset Projects) mentions maturity 9 times.‡ DOE G 413.3–7A (Risk Management Guide)
provides guidance for assessing increasing project maturity. [10]
None of these Orders or Guides states HOW to measure increasing maturity or HOW to use
these measures to increase the probability of success of the project. The DOD applies the
Integrated Master Plan (IMP) paradigm, to assess the increasing maturity of the project through
Measures of Effectiveness (MoE), Measures of Performance (MoP), Key Performance
Parameters (KPP), and Technical Performance Measures (TPM) to assess the increasing
Probability of Project Success (PoPS). The DOD approach is distinctly different from the
horizontal master scheduling described in the DOE O 413 series guidance.

EVENT BASED PLANNING IS THE BASIS OF STRATEGY MAKING
From Card’s memo we have a clear and concise connection between the Integrated Master
Plan (IMP) and the supporting Integrated Master Schedule (IMS) and the management of DOE
projects guided by DOE O 413.3. The following words appear in §6.5.1 of Card’s memo and
attached manual section [1].

‡
    NASA style Technology Readiness Levels have been suggested for the DOE through GAO-07-336 [4]



                                                                                                    2
An integrated master plan is a very effective tool for project management. It is the
         contractor’s event–based plan for accomplishing the requirements contained in
         Statements of Work, Performance Work Statements, Work Authorizations, and other
         documents which communicate requirements to the contractors. The plan identifies the
         key activities, events, milestones, and reviews that make up the program or project.
         The program or project office, support contractors or the prime contractor may prepare
         the plan. The plan also identifies those events and activities that will be included in the
         integrated master schedule. The integrated master schedule is a networked
         multilayered schedule generated by the contractor that begins with all identified
         integrated master plan events, accomplishments, and criteria. It also shows the
         expected start and finish dates of these events and contains all contractually required
         events and milestones such as reviews, tests, completion dates, and deliveries
         specified in the Work Breakdown Structure.
         The integrated master plan is prepared prior to completion of the Conceptual Design
         process and is subsequently maintained by the government and the contractor through
         a collaborative effort involving all the stakeholders. The integrated master plan and
         schedule tie together all project tasks by showing their logical relationships and any
         constraints controlling the start or finish of each task.
         This process results in a hierarchy of related functional and layered schedules derived
         from the Work Breakdown Structure that can be used for monitoring and controlling
                           *
         project progress.

Strategy Making, IMP/IMS, and Systems Engineering
Building products or facilities, providing services, or remediating environments is a systems
engineering process. † Components, processes, participants, and their outcomes interact in
ways that are described as a system. Engineering of these systems is an interdisciplinary
process that deals with the work and tools that manage risk, technical activities, and the human
centered disciplines need for success. The strategy for these activities is represented in the
DOD by the Integrated Master Plan.
The IMP/IMS is a step by step process to increase the probability of project success by:
    1. Creating A Vision Of The Outcome – described in the Concept of Operations
       (ConOps) or Statement of Objectives (SOO).
    2. Analyzing The Current Situation – to determine viable alternatives for the desired
       outcomes.
    3. Determining A Strategy – for moving from the current situation to the outcome, what
       “maturity increasing” activities must be performed to move forward.
    4. Selecting The Systems Development Activities – needed to move the “increasing
       maturity” forward through Significant Accomplishments (SA).
    5. Constructs A Plan Based On These Activities – arrange the SAs in a logical
       sequence for each Program Event (PE) to provide increasing level of maturity of the
       products or service.


*
  These words taken directly from the attached Manual in the memo are nearly identical to DI–MGMT–81650, Integrated Master
  Schedule, with three levels of Master Schedules. The terms Significant Accomplishment and Accomplishment Criteria are used
  directly in Card’s memo they are connected from DID–81650 to the current – under review – is DI–MGMT–81466B, where the
  Integrated Master Plan (IMP) is mentioned. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and
  Use Guide shows how the connected the resulting IMP with the IMS mentioned in Card’s memo.
†
  “Project Management vs. Systems Engineering Management: A Practitioners’ View on Integrating the Project and Product
  Domains,” Amira Sharon,Olivier L. de Weck, and Dov Dori, Systems Engineering, Volume 14, Number 4, 2011.



                                                                                                                               3
6. Performing A Pilot Set Of Activities – to confirm they result in desirable outcomes.
   7. Evaluating These Results – “test” the logic of the SAs to assure increasing maturity will
      result.
   8. Executes The Processes – in steps 6 and 7 until the outcome is reached by developing
      the Accomplishment Criteria (AC) for each SA and the top activities for each AC.
This IMP/IMS approach is the basis of all credible development activities in the DOD. The
challenge for the DOE becomes finding how the details of each step are to be defined,
developed, and executed in the context of DOE O 413.3b.

STRUCTURE OF THE INTEGRATED MASTER PLAN IN THE DEPARTMENT OF DEFENSE
The Integrated Master Plan showing how work is performed, the criteria for the compliance of
that work with the Technical Performance Measures, and the Accomplishments needed to
deliver a capability are shown in Figure 1.
This approach provides tangible evidence of progress to plan in units of measure meaningful to
the decision makers. These units include Measures of Effectiveness (MoE) from the customer’s
point of view, Measures of Performance (MoP) from the contractor’s or owner’s point of view,
the agreed Key Performance Indicators (KPP), and the Technical Performance Measures (TPM)
for all work activities.
The trends in these measures (MoP, MoE, KPP, and TPM) reveal project progress and when
compared with standard contingency values, highlight when corrective actions should be
considered. These measures of the system technical performance have been chosen because
they are indicators of increasing maturity of the project outcomes that impact the probability of
project success. They are based on high risk or significant driving requirements or technical
parameters. These measures are analogous to the programmatic measures of expected total
cost or estimated time–to–completion (Earned Value Management measures).
Actual versus planned progress of these measures are tracked through the IMP/IMS so
engineers, constructors, and project managers can assess progress and the risk associated
with each measure. These measures are attached to each Significant Accomplishment and
Accomplishment Criteria shown in Figure 1 to provide measures of increasing maturity, as well
as other measures needed to assess the probability of project success.
These measures are distinctly different from measures of cost and schedule performance and
their related milestone compliance. Cost, schedule, and milestone compliance are necessary,
but do not sufficient to provide visibility into the effectiveness of the project for the customer.
Measures of Effectiveness (MoE) are operational measures of. Measures of Performance (MoP)
characterize physical or functional attributes relating to the system operation, measured or
estimated under specific conditions. Key Performance Parameters (KPP) represents the
capabilities and characteristics significant enough that failure to meet them can be cause for
reevaluation, reassessing, or termination of the project.
These three measures (MoE, MoP, and KPP) are the heart of the IMP/IMS Significant
Accomplishments and their Accomplishment Criteria that provide direct measure of increasing
maturity of the projects outcomes.




                                                                                                 4
Figure 1 – The work performed in the sequence Work Packages is assessed for compliance with Technical
 Performance Measures, Measures of Effectiveness (MoE), and Measures of Performance (MoP). The result is a
 description of the increasing maturity of the product or service resulting from the project.


Department of Defense Processes Integrated with DOE O 413.3b and 413.5
The U.S. Department of Defense (DOD) makes use of Event Based Plans to define the
integrated product development and integration using measures of increasing maturity. This
approach enhances project planning, scheduling, and successful execution. This plan is a
hierarchy of Project Event(s), each event supported by specific Accomplishments, and each
accomplishment associated with specific Criteria to be satisfied for its completion.
This approach is different from the traditional horizontal schedule that measures progress
through cost and schedule performance. While deliverables are defined in the Integrated Master
Schedule (IMS), measures of Effectiveness (MoE), Performance (MoP), and its related Key
Performance Parameters (KPP) and Technical Performance Measures (TPM) are not
embedded in the Performance Measurement Baseline (PMB).
By applying the IMP paradigm, a vertical Plan is created where each Accomplishment defines
the desired result(s) prior to the completion of an Event that indicates a level of the project’s
progress. Accomplishment Criteria provide tangible evidence that a specific accomplishment
has been completed according to its Measure of Effectiveness and Measure of Performance.




                                                                                                             5
DOE G 413.5 Performance Measurement Baseline defines the Scope, Design, Key
Performance Parameters, Cost, Schedule, and supporting Documentation for the project. But
this PMB does not define the Accomplishments and Criteria that must be met to successfully
deliver the outcomes of the project.
Using the IMP paradigm, units of measure of performance meaningful to the decision makers
are installed in the PMB from the Accomplishments and Criteria for the detailed work activities.
This approach makes the Integrated Master Schedule (IMS) clearer by showing what DONE
looks like in terms of deliverables and the criteria for success of those deliverables embedded in
the IMS.
The connection of the performance of work efforts to the Criteria, Accomplishments, and Project
Events is the Earned Value Management (EVM) System. The EVM System defines the
measures of progress to plan at the work performance level. These measures are used to
define progress for each Criteria and Accomplishment. This provides Project Management with
direct measures of physical percent complete for each deliverable from the project.
Figure 1 shows the programmatic structure needed to improve the probability of project
success, using the Integrated Master Schedule paradigm, with Accomplishments, and Criteria
as measures of project performance based on MoE, MoP, and TPMs. Figure 2 shows how
each of these measures is related to produce visibility to the performance of the project.

How the Department of Defense Measures Maturity of the Project’s Outcomes
DOE O 413.3b mentions maturity 14 times in the context of design, procurement, and
technology readiness assessment. The measure of maturity has two sides of a project – the
buyer side and the producer side, i.e. The Customer and the Builder.
    Measures of Effectiveness – are closely related to the achievements of the mission or
     operational objectives evaluated in the operational environment, under a specific set of
     conditions. MoE’s are stated in units meaningful to the buyer and focus on the capabilities
     independent of any technical implementation, and are connected to the mission success.
    Measures of Performance – characterize physical or functional attributes relating to the
     system operation measured or estimated under specific conditions. MoP’s are attributes
     that assure the system has the capability to perform and assure the design requirements
     can satisfy the Measures of Effectiveness.
Along with the Measures of Effectiveness and Measures of Performance, two other measures
are needed to “connect the dots.”
    Key Performance Parameters (KPP) – Represent the capabilities and characteristics so
     significant that failure to meet them can be cause for reevaluation, reassessing, or
     termination of the project. KPPs have a threshold or objective value. These characterize
     the major drivers of performance and are considered Critical to Customer (CTC).
    Technical Performance Measures (TPM) – are attributes that determine how well a
     system or system element is satisfying or expected to satisfy a technical requirement or
     goal. These measures assess the design process, define compliance to performance
     requirements, and identify technical risk, including projected performance. The TPMs are
     limited to critical thresholds.




                                                                                                6
Figure 2 – connecting the measures needed for assessing increasing project maturity assures there is visibility to
project performance in units of measure meaningful to the decision makers.




CONNECTING DOE O 413.3B WITH DOD MEASURES OF MATURITY
Table 1 is a summary of DOE O 413.3b’s Critical Design stages and the activities performed at
each stage. For each of these, we’ll demonstrate how they would be applied in the Department
of Defense Integrated Master Plan and Integrated Master Schedule paradigm and show how
these connections can add value and increase the probability of success for DOE projects.
Connections between the Critical Design stages and the elements of the Integrated Master Plan
are shown in Table 2. These connections can be applied to current DOE O 413 series projects,
guided with the Card memo [1] and the Bosco order [3].
The outcome of this approach is a programmatic architecture where performance is measured
through cost and schedule adherence as well as direct measures of increasing maturity
supported by measures of effectiveness and performance needed to assessing the probability
of project success.
Used Earned Value for activities contained in Work Packages, measures of physical percent
complete toward the Accomplishment Criteria are provided. These Accomplishment Criteria are
then direct measures of progress toward the Significant Accomplishments needed to measure
this increasing maturity of each Program Event.
This architecture is shown in Figure 1, where both vertical traceability to increasing maturity and
horizontal traceability to activity progress are integrated in a single Performance Measurement
Baseline.




                                                                                                                     7
Project Acquisition Process and Critical Decisions
      Project Planning Phase                           Project Execution Phase                            Mission
  Pre–conceptual      Conceptual         Preliminary
                                                             Final Design         Construction          Operations
      Design            Design              Design


          CD–0                   CD–1                  CD–2                      CD–3                     CD–4
                                  Actions Authorized by the Critical Design Approval
  Proceed with the         Allow              Establish              Approve expenditure        Allow start of
   conceptual design.        expenditure of      baseline budget         of funds for                operations or
                             PED funds.          for construction.       construction.               project close out.
  Request PED
   funding.                                      Continue design.
                                                 Request
                                                  construction
                                                  funding.
                                            Critical Design Pre–Requisites
  Justification of         Acquisition          Preliminary         Update project              Operational
   mission need.             plan.                 design.              execution Plan and           readiness
                                                                        Performance Baseline         review.
  Acquisition strategy     Conceptual           Review of
                             design.               contractor project  Final design and            Project transition
  Pre–conceptual                                  management           procurement                  to operations.
   planning.                Preliminary           system.              packages.
                             project                                                                Final safety
  Mission need.             execution plan       Final project       Verification of mission      report.
  Independent Project       and baseline          execution plan       need.
   Review.                   range.                and performance
                                                   baseline.           Budget and
                            Project data                               congressional
                             sheet for            Independent cost     authorization and
                             design                estimate.            appropriation
                                                                        enacted.
                            Verification of      NEPA
                             mission need.                             Approval of safety
                                                  Project data         documentation.
                            Preliminary           sheet for
                             hazard                construction.       Execution readiness
                             analysis report.                           Independent Review.
                                                  Draft preliminary
                                                   Safety Analysis
                                                   Report.
                                                 Performance
                                                  Baseline External
                                                  Independent
                                                  Review.


Table 1 – summary of CD activities from DOE O 413.3b, 29 November 2010 describe the attributes or exit criteria for
each of the Critical Decision. The documents that define the processes and content of many of these deliverables do
not directly speak to the increasing maturity of the project’s outcome. The terms “preliminary, draft, approved verified,
and final,” are used but the Significant Accomplishments and the Accomplishment Criteria needed assessment the
maturity of the project at each of these reviews is not defined.




                                                                                                                          8
Mapping the IMP/IMS Paradigm to the DOE Critical Design Reviews
The DOE O 413 series defines activities to be performed during the execution of a project. The
DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide
defines how to build the IMP and IMS that will increase the probability of success for the
project [2].


          DOE O 413.3–9 and 413.3–16 Guidance                                DOD IMP/IMS Guidance
                CD–0: Approve Mission Need                                   Understand the Project
  Identification of a mission–related need and                Define mission outcome as a Concept of Operations
   translation of this gap into functional requirements for     (ConOps)
   filling the need.                                           Partition system capabilities into classes of service
  The mission need is independent of a particular              within operational scenarios.
   solution and should not be defined by equipment,            Connect the capabilities to system requirements
   facility, technological solution, or physical end item       using some visual modeling notation.
   (413.3A).
                                                               Define Measures of Effectiveness (MoE) and
  The focus for Technology Assessment, at this stage,          Measures of Performance (MoP).
   is on clear statement of the requirements of the input
   and the desired output of the process.                      Define the delivery schedule for each measure of
                                                                performance and effectiveness.
      CD–1: Alternative Selection and Cost Range                            Develop Project Structure
  Identification of the preferred technological               Assign costs to each system element using a value
   alternative, preparation of a conceptual design, and         flow model.
   development of initial cost estimates                       Assure risk, probabilistic cost and benefit
                                                                performance attributes are defined.
                                                               Use cost, schedule and technical performance
                                                                probabilistic models to forecast potential risks to
                                                                project performance.
             CD–2: Performance Baseline                                       Create IMP / IMS
  Completion of preliminary design, development of a          Decompose scope into work packages
   performance baseline that contains a detailed scope,        Assign responsibility for deliverables
   schedule, and cost estimate.
                                                               Arrange work packages in a logical order
  The process of technology development, in
   accordance with the approved TMP should support all         Develop BCWS for work packages
   CTEs reaching TRL 6; attainment of TRL 6 is                 Assign work package measures of performance
   preferable and indicates that the technology is ready
                                                               Set Performance Measurement Baseline
   for insertion into detailed design.
               CD–3: Start of Construction                       Execute Performance Measurement Baseline
  Completion of essentially all design and engineering        Performance authorized work
   and beginning of construction, implementation,              Accumulate and report work package information
   procurement, or fabrication. A TRA is only required if
   there is significant technology modification as detailed    Analyze work package performance
   design work progresses.                                     Take corrective management action
  If substantial modification of a technology occurs, the     Maintain Performance Measurement Baseline
   TRA should be performed and a focused TMP
   developed or updated to ensure that the modified
   technology has attained TRL 6, if possible, prior to its
   insertion into the detailed design and baseline.
Table 2 – for each 413 CD, specific IMP/IMS guidance can be applied to increase the probability of project success,
by creating evidence of increasing maturity in units of measure meaningful to the decision makers.




                                                                                                                        9
CHANGING THE PROGRAM PLANNING PARADIGM FROM HORIZONTAL TO VERTICAL
Building an IMP / IMS requires a change in the normal paradigm of project management. This
change means stopping the measurement of progress as the passage of time and consumption
of funding – to measuring progress by the completion of Accomplishment Criteria and the
fulfillment of Significant Accomplishments.
It means moving from horizontal scheduling to vertical planning. These words are probably
meaningless at this point. The description of this paradigm provides an understanding of this
concept, the benefits to the project management, and the processes needed to deliver these
benefits. In many cases, the horizontal schedules are the starting point for the project. This
occurs for several reasons:
     The project started without an IMP or a real IMS. They first built a horizontal schedule in
      the manner of “shop floor” schedule. This is usually for the Period of Performance of the
      Program.
     The project was inherited from a higher or lower level process. Either as a subcontractor
      or a part of on IPT team, the schedule is focused on the functional aspects of the project.
In many cases, the conversion from horizontal to vertical planning is required or desired. The
effort to do this conversion involves several steps:
     Identify the Program Events and where in the schedule these events take place.
     Identify which work in the schedule “lands” on which event. If there is work that crosses an
      Event boundary, then it will need to be “broken” into two (2) parts. One that “lands” on the
      Event and one that restarts at the completion of the Event.

IMP / IMS FEATURES AND BENEFITS
The IMP and IMS focuses on specific areas of the project, which have been shown to be
problems with more traditional approaches. The primary focus is on project maturity Event
based planning provides a “singularly” focused process allowing each IPT to answer the
question – “what do I need to do for a specific event?” For example Preliminary Design Review
(PDR): List all the accomplishments needed for PDR? What activities need to performed for
each of these accomplishments? When all the activities are completed, the criteria satisfied, and
the accomplishments completed then a measurement of “maturity” can take place?
                 This approach is not described in the DOE O 413 series of guidance.
        Features of IMP/IMS                                         Benefits to the Program
 Provides an understanding and            Drives down cost of execution by connecting changes with the impact of
 alignment of required tasks with         changes that occur early in the project life cycle when costs are lower are
 events starting with the proposal        made visible from day one.
 Integrates relationships of
                                          Improves management visibility by connecting activities with events Permits
 products and development
                                          better understanding of risk and how it impacts cost, schedule, performance
 processes
                                          Provides a framework for using integrated tools, teams, and processes with
 A disciplined approach to planning
                                          vertical traceability Serves as foundation for systematic programmatic
 and implementation activities
                                          improvement efforts
 Iterative planning, tracking, and        Allows project flexibility – on ramps and off ramps tied to events Highlights
 reporting process                        details early – ties maturity events with activities
                                          Relates project events in terms of success – Accomplishments and Criteria
 Event–Driven Planning                    Reduces risk by ensuring that maturity of the plan is incrementally
                                          demonstrated prior to starting follow–on activities
                                          Improves measurable maturity and impact analysis Promotes project buy–in
 Increases visibility of entire project
                                          and team commitment through shared events Fosters proactive management
 to the project team
                                          at all levels through measurable outcomes



                                                                                                                        10
Features of IMP/IMS                                      Benefits to the Program
 Resource and Earned Value
                                      Provides foundation for Earned Value Reporting and EVMS
 Loadable
 Key customer events included         Encourages a win–win attitude with customers
 Clear communication of how the       Improves effectiveness through a common set of tools, measurements and
 team views the project               defined outcomes
Table 3 – IMP/IMS features and that are not directly provided by executing DOE O 413 series guided projects using
measures of cost, schedule, and milestone performance.

THE PIECES NEEDED TO INCREASE THE PROBABILITY OF PROJECT SUCCESS
Using the DOE Critical Decision (CD) review guide, the Integrated Master Plan paradigm is
applied to increase the probability of project success.
    DOE CD Outcomes                                    IMP / IMS Processes to create outcomes
                                             CD–0: Approve Mission Need
                                 Define the Significant Accomplishment needed to fulfill the mission need and
  Developing the mission         implementation strategy.
   need and acquisition          Define these in units of performance, effectiveness, and technical compliance.
   strategy                      Define the Measures of Effectiveness (MoE) and Measures of Performance (MoP)
                                  for each mission need. (see Figure 2 for relationship between these measures).
                                 Define the “increasing maturity” flow for the work needed to fulfill the mission need
                                  and acquisition strategy.
  Pre–conceptual
                                 Define the Technical Performance Measures (TPM) for each outcome at the
   planning
                                  planned level of maturity – in the DOE language the Technology Readiness Level
                                  (TRL) has similar words
                                    CD–1: Alternative Selection and Cost Range
                                 Integrated Master Plan logical “Value” flow, showing how each outcome from the
                                  work efforts satisfies the Accomplishment Criteria in units of Measures of
  Preliminary project            Effectiveness (MoE) and Measures of Performance (MoP) measured against the
   execution plan                 planned MoE and MoP.
  Verification of mission       Develop Basis of Estimate (BoE) for each Significant Accomplishment and
   need                           Accomplishment Criteria (see Figure 1 for IMP/IMS structure).
                                 Connect the BoEs with each measure of maturity and the planned cost to reach
                                  that level of maturity.
                                    CD–2: Performance (Measurement) Baseline
  Preliminary design
   review
  Review project
   management system           PDR and other reviews assess planned and actual maturity of Significant
  Final project execution      Accomplishments (SA) and the Accomplishment Criteria (AC).
   plan                        Probabilistic assessment of cost, schedule, and technical performance for each SA
  Independent cost             and AC.
   estimate
  External independent
   review
                                             CD–3: Start Construction
  Final design review
  Execution readiness
                               Starting with the Work Packages, execute each Accomplishment Criteria and
   review
                                measure actual performance against planned performance using MoE and MoP.
  Execute the
   Performance Baseline
Table 4 – for each 413 CD, specific IMP/IMS processes and their outcomes increase the probability of project
success through tangible evidence of increasing maturity in units of measure meaningful to the decision makers.




                                                                                                                      11
CONCLUSION
Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master
Schedule paradigm would provide a hierarchical set of performance measures for each
“package of work,” that provides measureable visibility to the increasing maturity of the project.
This measureable maturity provides the mechanism to forecast future performance of cost,
schedule, and technical outcomes in ways not available using just the activities in DOE O 413.
With this information project managers have another tool available to address the issues
identified in GAO–07–336 and GAO–09–406.

REFERENCES
[1]   Memorandum for Robert G, Card, Undersecretary, Energy, Science, and Environment,
      March 31, 2003 from Kyle E. McSlarrow, “Project Management and the Project
      Management Manual.” http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf
[2]   “Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide,”
      Version 0.9, August 15, 2005, Office of the Secretary of Defense (OSD),
      www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf
[3]   “Significant Changes to DOE Order 413.3B,” January 21, 2011, Paul Bosco, Director,
      Office of Engineering and Construction Management. http://1.usa.gov/v6V5z6
[4]   GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing
      Technology Readiness to Avoid Cost Increases and Delays.
[5]   GAO–09–406, Contract and Project Management Concerns at NNSA and Office of EM
[6]   GAO–08–1081, Nuclear Waste: Action Needed to Improve Accountability and
      Management of DOE’s Major Cleanup Projects.
[7]   DOE O 413.3, Program and Project Management for the Acquisition of Capital Assets,
      included in Memo to Robert Card, March 31, 2003 from Kyle E. McSlarrow. Memo
      available at http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf
[8]   DOE G 413.5, Performance Measurement Baseline.
[9]   DOE O 413.3b Program and Project Management for the Acquisition of Capital Assets.
[10] DOE G 413.3–7A Risk Management Guide.
[11] “Integrated Master Plan Analysis: The PMAG Approach,” Col. Mun H. Kwon, USAF,
     Defense AT&L, January–February, 2010, pp. 39–43.




                                                                                               12

Weitere ähnliche Inhalte

Was ist angesagt?

Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course reviewAsa Chan
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio managementGlen Alleman
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01Steven Leahy
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11tony1234
 
Design Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementDesign Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementGlen Alleman
 
Team Final_Scope Management
Team Final_Scope ManagementTeam Final_Scope Management
Team Final_Scope ManagementRKDickey
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated masterGlen Alleman
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
The Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentThe Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentGlen Alleman
 
Project implimentation
Project implimentationProject implimentation
Project implimentationMazhar Poohlah
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)love7love
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Scheduleellefsonj
 

Was ist angesagt? (20)

Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Is5540 course review
Is5540 course reviewIs5540 course review
Is5540 course review
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
06 project time management
06  project time management06  project time management
06 project time management
 
Strategic portfolio management
Strategic portfolio managementStrategic portfolio management
Strategic portfolio management
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01SLeahy - Unit 5 Assignment - IT599-01
SLeahy - Unit 5 Assignment - IT599-01
 
Brownfields agile draft v11
Brownfields agile draft v11Brownfields agile draft v11
Brownfields agile draft v11
 
Design Patterns in Electronic Data Management
Design Patterns in Electronic Data ManagementDesign Patterns in Electronic Data Management
Design Patterns in Electronic Data Management
 
Team Final_Scope Management
Team Final_Scope ManagementTeam Final_Scope Management
Team Final_Scope Management
 
Build an integrated master plan and integrated master
Build an integrated master plan and integrated masterBuild an integrated master plan and integrated master
Build an integrated master plan and integrated master
 
Chap06 project time management
Chap06 project time managementChap06 project time management
Chap06 project time management
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
The Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System DeploymentThe Role of the Architect in ERP and PDM System Deployment
The Role of the Architect in ERP and PDM System Deployment
 
Project implimentation
Project implimentationProject implimentation
Project implimentation
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)Lecture 9 (02-06-2011)
Lecture 9 (02-06-2011)
 
Integrated Master Schedule
Integrated Master ScheduleIntegrated Master Schedule
Integrated Master Schedule
 

Andere mochten auch

Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Glen Alleman
 
Architecture centered publishing systems
Architecture centered publishing systemsArchitecture centered publishing systems
Architecture centered publishing systemsGlen Alleman
 
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Glen Alleman
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management reqGlen Alleman
 
Architecture Centered Design
Architecture Centered DesignArchitecture Centered Design
Architecture Centered DesignGlen Alleman
 
Agile Project Management for ERP Projects
Agile Project Management for ERP ProjectsAgile Project Management for ERP Projects
Agile Project Management for ERP ProjectsGlen Alleman
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk managementGlen Alleman
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project ManagementGlen Alleman
 
All project variables are random variables
All project variables are random variablesAll project variables are random variables
All project variables are random variablesGlen Alleman
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connectionsGlen Alleman
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmGlen Alleman
 
Capabilities development
Capabilities developmentCapabilities development
Capabilities developmentGlen Alleman
 
About Vision, Mission And Strategy
About Vision, Mission And StrategyAbout Vision, Mission And Strategy
About Vision, Mission And StrategyGuus Vos
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One PictureGlen Alleman
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzerGlen Alleman
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned ValueGlen Alleman
 
It project management and best practices
It project management and best practicesIt project management and best practices
It project management and best practicesNaresh Pokhriyal
 

Andere mochten auch (20)

Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)Using balanced scorecard to build a project focused org (no logo)
Using balanced scorecard to build a project focused org (no logo)
 
Architecture centered publishing systems
Architecture centered publishing systemsArchitecture centered publishing systems
Architecture centered publishing systems
 
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
Inversion of control - the Impedance Mismatch of Integrated Engineering Desig...
 
Graded application of project management req
Graded application of project management reqGraded application of project management req
Graded application of project management req
 
Agile EVMS
Agile EVMSAgile EVMS
Agile EVMS
 
Architecture Centered Design
Architecture Centered DesignArchitecture Centered Design
Architecture Centered Design
 
Agile Project Management for ERP Projects
Agile Project Management for ERP ProjectsAgile Project Management for ERP Projects
Agile Project Management for ERP Projects
 
Programmatic risk management
Programmatic risk managementProgrammatic risk management
Programmatic risk management
 
Theory of Project Management
Theory of Project ManagementTheory of Project Management
Theory of Project Management
 
All project variables are random variables
All project variables are random variablesAll project variables are random variables
All project variables are random variables
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
Moe mop tpm connections
Moe mop tpm connectionsMoe mop tpm connections
Moe mop tpm connections
 
You don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pmYou don’t need agile to avoid the seven deadly sins of pm
You don’t need agile to avoid the seven deadly sins of pm
 
Capabilities development
Capabilities developmentCapabilities development
Capabilities development
 
About Vision, Mission And Strategy
About Vision, Mission And StrategyAbout Vision, Mission And Strategy
About Vision, Mission And Strategy
 
Systems Engineering in One Picture
Systems Engineering in One PictureSystems Engineering in One Picture
Systems Engineering in One Picture
 
Project breathalyzer
Project breathalyzerProject breathalyzer
Project breathalyzer
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Earning Value from Earned Value
Earning Value from Earned ValueEarning Value from Earned Value
Earning Value from Earned Value
 
It project management and best practices
It project management and best practicesIt project management and best practices
It project management and best practices
 

Ähnlich wie Improving Project Performance in the DOE

Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Project typed
Project typedProject typed
Project typedRahul
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planningCharith Sathish
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfTanzeelShahid5
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 NotesSamarthVarpe
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3POOJA UDAYAN
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
Project Management Paper
Project Management PaperProject Management Paper
Project Management PaperPam Simpson
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Jeffrey Cheah
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01Amy Roman
 
1.7 project management
1.7 project management1.7 project management
1.7 project managementexemplar2401
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET Journal
 

Ähnlich wie Improving Project Performance in the DOE (20)

Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Project typed
Project typedProject typed
Project typed
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Chapter 02 project planning
Chapter 02 project planningChapter 02 project planning
Chapter 02 project planning
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
 
Project Management Skills unit-4 Notes
Project Management Skills unit-4 NotesProject Management Skills unit-4 Notes
Project Management Skills unit-4 Notes
 
Advanced project management mod 3
Advanced project management mod 3Advanced project management mod 3
Advanced project management mod 3
 
Stopping the insanity
Stopping the insanityStopping the insanity
Stopping the insanity
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Project Management Paper
Project Management PaperProject Management Paper
Project Management Paper
 
Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)Project Management Body of Knowledge (Integration)
Project Management Body of Knowledge (Integration)
 
Assignment
Assignment Assignment
Assignment
 
1-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp011-7Projectmanagement-120312002842-Phpapp01
1-7Projectmanagement-120312002842-Phpapp01
 
1.7 project management
1.7 project management1.7 project management
1.7 project management
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
IRJET- Application of Microsoft Project for Planning and Scheduling of a Resi...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 

Mehr von Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Mehr von Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Improving Project Performance in the DOE

  • 1. WM2012 Conference, February 26 – March 1, 2012, Phoenix, Arizona, USA Improving DOE Project Performance Using the DOD Integrated Master Plan – 12481 Glen B. Alleman, DOD Programs, Project Time & Cost and Michael R. Nosbisch, Managing Principle, Western Region, Project Time & Cost ABSTRACT DOE O 413 measures a project’s progress to plan by the consumption of funding, the passage of time, and the meeting of milestones. In March of 2003, then Under Secretary, Energy, Science, Card received a memo directing the implementation of Project Management and the Project Management Manual, including the Integrated Master Plan and Integrated Master Schedule. This directive states “the integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling project progress.” This paper shows how restoring the IMP/IMS paradigm to DOE program management increases the probability of program success in ways not currently available using DOD O 413 processes alone. INTRODUCTION The measures of progress to plan in units meaningful to the decision maker are needed to answer the question – How Long Are We Willing to Wait before We Find out We Are Late? As recently as January of 2011 updates to DOE O 413.3B were made with focus on four philosophical goals. [3] With this 2011 directive and the 2003 memo to Robert Card (Project Management and the Project Management Manual) [1] addressing the use of Integrated Master Plans and Schedules in Section 6.5.1, the measures needed to answer this question are still not specifically stated in the most recent version of the DOE O 413 series. However, the DOD 5000.02 and Integrated Master Plan (IMP) paradigm provides the mechanism to answer the question and should be adopted by DOE. The IMP, as applied by the DOD, defines the incremental increase of a project’s maturity, assessed through Significant Accomplishments (SA) and Accomplishment Criteria (AC), using Measures of Effectiveness (MoE), Measures of Performance (MoP), and Technical Performance Measures (TPM). [2] The memo to Card reflects a nearly identical structure to the DOD Integrated Master Plan and establishes DOE M 413.3–1 (Project Management for the Acquisition of Capital Assets) as a primary guidance document using the IMP/IMS in 2003. But the current DOE O 413.3–1 does not include the use on an Integrated Master Plan (IMP) [7], [11]. Applying Card’s 2003 DOD IMP paradigm to DOE O 413 series projects will improve the probability of DOE project success through measures of increasing maturity of the deliverables defined in the Integrated Master Plan (IMP), in addition to measures of progress through cost and schedule performance and milestone compliance. [3] For motivation for this IMP/IMS approach, we need only look to recent reports that provide a sample of assessments: GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays [4], GAO– 09–406 Contract and Project Management Concerns at NNSA and Office of EM [5] and GAO– 08–1081 Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects [6]. 1
  • 2. These GAO reports found that …:  … the cost increases and schedule delays that have occurred for most of these projects have been the result of inconsistent application of project management tools and techniques on the part of both DOE and its contractors.[5]  … exceeded their original cost or schedule estimates, principally because of ineffective DOE project oversight and poor contractor management. [4]  … had life cycle baseline cost increases, from a low of $139 million for one project to a high of nearly $9 billion for another, and life cycle baseline schedule delays from 2 to 15 years. These changes occurred primarily because the baselines we reviewed included schedule assumptions that were not linked to technical or budget realities and the scope of work included other assumptions that did not prove true. [6] Project success depends on answering 5 immutable questions, no matter the domain or the project context in that domain, the project management method, or the agency guidance. 1. What does “Done” look like? 2. What is the path to reaching “Done” on time, on budget, and technically compliant? 3. What resources (time, money, staff, and facilities) are needed to reach “Done? 4. What impediments will prevent reaching “Done”? 5. How is physical progress to plan measured on the path to “Done?” Project success starts with describing what “Done” looks like in units of measure meaningful to the decision makers. These measures of performance (technical and programmatic) and effectiveness (the customer’s point of view) are derived from the elements of the Integrated Master Plan – Program Events, Significant Accomplishments, and the Accomplishment Criteria of the baselined Work Packages. DOE G 413.5 (Performance Measurement Baseline) describes the measurement of progress to plan through Key Performance Parameters (KPP), Cost, and Schedule Performance. These measures do not answer the 5 immutable questions stated above. The answers need to be in units of Increasing Maturity of the project outcomes. [8] DOE O 413.3b (Program and Project Management for the Acquisition of Capital Assets) mentions the term maturity 14 times. [9] DOE O 413.3–9 (Project Review Guide for Capital Asset Projects) mentions maturity 9 times.‡ DOE G 413.3–7A (Risk Management Guide) provides guidance for assessing increasing project maturity. [10] None of these Orders or Guides states HOW to measure increasing maturity or HOW to use these measures to increase the probability of success of the project. The DOD applies the Integrated Master Plan (IMP) paradigm, to assess the increasing maturity of the project through Measures of Effectiveness (MoE), Measures of Performance (MoP), Key Performance Parameters (KPP), and Technical Performance Measures (TPM) to assess the increasing Probability of Project Success (PoPS). The DOD approach is distinctly different from the horizontal master scheduling described in the DOE O 413 series guidance. EVENT BASED PLANNING IS THE BASIS OF STRATEGY MAKING From Card’s memo we have a clear and concise connection between the Integrated Master Plan (IMP) and the supporting Integrated Master Schedule (IMS) and the management of DOE projects guided by DOE O 413.3. The following words appear in §6.5.1 of Card’s memo and attached manual section [1]. ‡ NASA style Technology Readiness Levels have been suggested for the DOE through GAO-07-336 [4] 2
  • 3. An integrated master plan is a very effective tool for project management. It is the contractor’s event–based plan for accomplishing the requirements contained in Statements of Work, Performance Work Statements, Work Authorizations, and other documents which communicate requirements to the contractors. The plan identifies the key activities, events, milestones, and reviews that make up the program or project. The program or project office, support contractors or the prime contractor may prepare the plan. The plan also identifies those events and activities that will be included in the integrated master schedule. The integrated master schedule is a networked multilayered schedule generated by the contractor that begins with all identified integrated master plan events, accomplishments, and criteria. It also shows the expected start and finish dates of these events and contains all contractually required events and milestones such as reviews, tests, completion dates, and deliveries specified in the Work Breakdown Structure. The integrated master plan is prepared prior to completion of the Conceptual Design process and is subsequently maintained by the government and the contractor through a collaborative effort involving all the stakeholders. The integrated master plan and schedule tie together all project tasks by showing their logical relationships and any constraints controlling the start or finish of each task. This process results in a hierarchy of related functional and layered schedules derived from the Work Breakdown Structure that can be used for monitoring and controlling * project progress. Strategy Making, IMP/IMS, and Systems Engineering Building products or facilities, providing services, or remediating environments is a systems engineering process. † Components, processes, participants, and their outcomes interact in ways that are described as a system. Engineering of these systems is an interdisciplinary process that deals with the work and tools that manage risk, technical activities, and the human centered disciplines need for success. The strategy for these activities is represented in the DOD by the Integrated Master Plan. The IMP/IMS is a step by step process to increase the probability of project success by: 1. Creating A Vision Of The Outcome – described in the Concept of Operations (ConOps) or Statement of Objectives (SOO). 2. Analyzing The Current Situation – to determine viable alternatives for the desired outcomes. 3. Determining A Strategy – for moving from the current situation to the outcome, what “maturity increasing” activities must be performed to move forward. 4. Selecting The Systems Development Activities – needed to move the “increasing maturity” forward through Significant Accomplishments (SA). 5. Constructs A Plan Based On These Activities – arrange the SAs in a logical sequence for each Program Event (PE) to provide increasing level of maturity of the products or service. * These words taken directly from the attached Manual in the memo are nearly identical to DI–MGMT–81650, Integrated Master Schedule, with three levels of Master Schedules. The terms Significant Accomplishment and Accomplishment Criteria are used directly in Card’s memo they are connected from DID–81650 to the current – under review – is DI–MGMT–81466B, where the Integrated Master Plan (IMP) is mentioned. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide shows how the connected the resulting IMP with the IMS mentioned in Card’s memo. † “Project Management vs. Systems Engineering Management: A Practitioners’ View on Integrating the Project and Product Domains,” Amira Sharon,Olivier L. de Weck, and Dov Dori, Systems Engineering, Volume 14, Number 4, 2011. 3
  • 4. 6. Performing A Pilot Set Of Activities – to confirm they result in desirable outcomes. 7. Evaluating These Results – “test” the logic of the SAs to assure increasing maturity will result. 8. Executes The Processes – in steps 6 and 7 until the outcome is reached by developing the Accomplishment Criteria (AC) for each SA and the top activities for each AC. This IMP/IMS approach is the basis of all credible development activities in the DOD. The challenge for the DOE becomes finding how the details of each step are to be defined, developed, and executed in the context of DOE O 413.3b. STRUCTURE OF THE INTEGRATED MASTER PLAN IN THE DEPARTMENT OF DEFENSE The Integrated Master Plan showing how work is performed, the criteria for the compliance of that work with the Technical Performance Measures, and the Accomplishments needed to deliver a capability are shown in Figure 1. This approach provides tangible evidence of progress to plan in units of measure meaningful to the decision makers. These units include Measures of Effectiveness (MoE) from the customer’s point of view, Measures of Performance (MoP) from the contractor’s or owner’s point of view, the agreed Key Performance Indicators (KPP), and the Technical Performance Measures (TPM) for all work activities. The trends in these measures (MoP, MoE, KPP, and TPM) reveal project progress and when compared with standard contingency values, highlight when corrective actions should be considered. These measures of the system technical performance have been chosen because they are indicators of increasing maturity of the project outcomes that impact the probability of project success. They are based on high risk or significant driving requirements or technical parameters. These measures are analogous to the programmatic measures of expected total cost or estimated time–to–completion (Earned Value Management measures). Actual versus planned progress of these measures are tracked through the IMP/IMS so engineers, constructors, and project managers can assess progress and the risk associated with each measure. These measures are attached to each Significant Accomplishment and Accomplishment Criteria shown in Figure 1 to provide measures of increasing maturity, as well as other measures needed to assess the probability of project success. These measures are distinctly different from measures of cost and schedule performance and their related milestone compliance. Cost, schedule, and milestone compliance are necessary, but do not sufficient to provide visibility into the effectiveness of the project for the customer. Measures of Effectiveness (MoE) are operational measures of. Measures of Performance (MoP) characterize physical or functional attributes relating to the system operation, measured or estimated under specific conditions. Key Performance Parameters (KPP) represents the capabilities and characteristics significant enough that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. These three measures (MoE, MoP, and KPP) are the heart of the IMP/IMS Significant Accomplishments and their Accomplishment Criteria that provide direct measure of increasing maturity of the projects outcomes. 4
  • 5. Figure 1 – The work performed in the sequence Work Packages is assessed for compliance with Technical Performance Measures, Measures of Effectiveness (MoE), and Measures of Performance (MoP). The result is a description of the increasing maturity of the product or service resulting from the project. Department of Defense Processes Integrated with DOE O 413.3b and 413.5 The U.S. Department of Defense (DOD) makes use of Event Based Plans to define the integrated product development and integration using measures of increasing maturity. This approach enhances project planning, scheduling, and successful execution. This plan is a hierarchy of Project Event(s), each event supported by specific Accomplishments, and each accomplishment associated with specific Criteria to be satisfied for its completion. This approach is different from the traditional horizontal schedule that measures progress through cost and schedule performance. While deliverables are defined in the Integrated Master Schedule (IMS), measures of Effectiveness (MoE), Performance (MoP), and its related Key Performance Parameters (KPP) and Technical Performance Measures (TPM) are not embedded in the Performance Measurement Baseline (PMB). By applying the IMP paradigm, a vertical Plan is created where each Accomplishment defines the desired result(s) prior to the completion of an Event that indicates a level of the project’s progress. Accomplishment Criteria provide tangible evidence that a specific accomplishment has been completed according to its Measure of Effectiveness and Measure of Performance. 5
  • 6. DOE G 413.5 Performance Measurement Baseline defines the Scope, Design, Key Performance Parameters, Cost, Schedule, and supporting Documentation for the project. But this PMB does not define the Accomplishments and Criteria that must be met to successfully deliver the outcomes of the project. Using the IMP paradigm, units of measure of performance meaningful to the decision makers are installed in the PMB from the Accomplishments and Criteria for the detailed work activities. This approach makes the Integrated Master Schedule (IMS) clearer by showing what DONE looks like in terms of deliverables and the criteria for success of those deliverables embedded in the IMS. The connection of the performance of work efforts to the Criteria, Accomplishments, and Project Events is the Earned Value Management (EVM) System. The EVM System defines the measures of progress to plan at the work performance level. These measures are used to define progress for each Criteria and Accomplishment. This provides Project Management with direct measures of physical percent complete for each deliverable from the project. Figure 1 shows the programmatic structure needed to improve the probability of project success, using the Integrated Master Schedule paradigm, with Accomplishments, and Criteria as measures of project performance based on MoE, MoP, and TPMs. Figure 2 shows how each of these measures is related to produce visibility to the performance of the project. How the Department of Defense Measures Maturity of the Project’s Outcomes DOE O 413.3b mentions maturity 14 times in the context of design, procurement, and technology readiness assessment. The measure of maturity has two sides of a project – the buyer side and the producer side, i.e. The Customer and the Builder.  Measures of Effectiveness – are closely related to the achievements of the mission or operational objectives evaluated in the operational environment, under a specific set of conditions. MoE’s are stated in units meaningful to the buyer and focus on the capabilities independent of any technical implementation, and are connected to the mission success.  Measures of Performance – characterize physical or functional attributes relating to the system operation measured or estimated under specific conditions. MoP’s are attributes that assure the system has the capability to perform and assure the design requirements can satisfy the Measures of Effectiveness. Along with the Measures of Effectiveness and Measures of Performance, two other measures are needed to “connect the dots.”  Key Performance Parameters (KPP) – Represent the capabilities and characteristics so significant that failure to meet them can be cause for reevaluation, reassessing, or termination of the project. KPPs have a threshold or objective value. These characterize the major drivers of performance and are considered Critical to Customer (CTC).  Technical Performance Measures (TPM) – are attributes that determine how well a system or system element is satisfying or expected to satisfy a technical requirement or goal. These measures assess the design process, define compliance to performance requirements, and identify technical risk, including projected performance. The TPMs are limited to critical thresholds. 6
  • 7. Figure 2 – connecting the measures needed for assessing increasing project maturity assures there is visibility to project performance in units of measure meaningful to the decision makers. CONNECTING DOE O 413.3B WITH DOD MEASURES OF MATURITY Table 1 is a summary of DOE O 413.3b’s Critical Design stages and the activities performed at each stage. For each of these, we’ll demonstrate how they would be applied in the Department of Defense Integrated Master Plan and Integrated Master Schedule paradigm and show how these connections can add value and increase the probability of success for DOE projects. Connections between the Critical Design stages and the elements of the Integrated Master Plan are shown in Table 2. These connections can be applied to current DOE O 413 series projects, guided with the Card memo [1] and the Bosco order [3]. The outcome of this approach is a programmatic architecture where performance is measured through cost and schedule adherence as well as direct measures of increasing maturity supported by measures of effectiveness and performance needed to assessing the probability of project success. Used Earned Value for activities contained in Work Packages, measures of physical percent complete toward the Accomplishment Criteria are provided. These Accomplishment Criteria are then direct measures of progress toward the Significant Accomplishments needed to measure this increasing maturity of each Program Event. This architecture is shown in Figure 1, where both vertical traceability to increasing maturity and horizontal traceability to activity progress are integrated in a single Performance Measurement Baseline. 7
  • 8. Project Acquisition Process and Critical Decisions Project Planning Phase Project Execution Phase Mission Pre–conceptual Conceptual Preliminary Final Design Construction Operations Design Design Design CD–0 CD–1 CD–2 CD–3 CD–4 Actions Authorized by the Critical Design Approval  Proceed with the  Allow  Establish  Approve expenditure  Allow start of conceptual design. expenditure of baseline budget of funds for operations or PED funds. for construction. construction. project close out.  Request PED funding.  Continue design.  Request construction funding. Critical Design Pre–Requisites  Justification of  Acquisition  Preliminary  Update project  Operational mission need. plan. design. execution Plan and readiness Performance Baseline review.  Acquisition strategy  Conceptual  Review of design. contractor project  Final design and  Project transition  Pre–conceptual management procurement to operations. planning.  Preliminary system. packages. project  Final safety  Mission need. execution plan  Final project  Verification of mission report.  Independent Project and baseline execution plan need. Review. range. and performance baseline.  Budget and  Project data congressional sheet for  Independent cost authorization and design estimate. appropriation enacted.  Verification of  NEPA mission need.  Approval of safety  Project data documentation.  Preliminary sheet for hazard construction.  Execution readiness analysis report. Independent Review.  Draft preliminary Safety Analysis Report.  Performance Baseline External Independent Review. Table 1 – summary of CD activities from DOE O 413.3b, 29 November 2010 describe the attributes or exit criteria for each of the Critical Decision. The documents that define the processes and content of many of these deliverables do not directly speak to the increasing maturity of the project’s outcome. The terms “preliminary, draft, approved verified, and final,” are used but the Significant Accomplishments and the Accomplishment Criteria needed assessment the maturity of the project at each of these reviews is not defined. 8
  • 9. Mapping the IMP/IMS Paradigm to the DOE Critical Design Reviews The DOE O 413 series defines activities to be performed during the execution of a project. The DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide defines how to build the IMP and IMS that will increase the probability of success for the project [2]. DOE O 413.3–9 and 413.3–16 Guidance DOD IMP/IMS Guidance CD–0: Approve Mission Need Understand the Project  Identification of a mission–related need and  Define mission outcome as a Concept of Operations translation of this gap into functional requirements for (ConOps) filling the need.  Partition system capabilities into classes of service  The mission need is independent of a particular within operational scenarios. solution and should not be defined by equipment,  Connect the capabilities to system requirements facility, technological solution, or physical end item using some visual modeling notation. (413.3A).  Define Measures of Effectiveness (MoE) and  The focus for Technology Assessment, at this stage, Measures of Performance (MoP). is on clear statement of the requirements of the input and the desired output of the process.  Define the delivery schedule for each measure of performance and effectiveness. CD–1: Alternative Selection and Cost Range Develop Project Structure  Identification of the preferred technological  Assign costs to each system element using a value alternative, preparation of a conceptual design, and flow model. development of initial cost estimates  Assure risk, probabilistic cost and benefit performance attributes are defined.  Use cost, schedule and technical performance probabilistic models to forecast potential risks to project performance. CD–2: Performance Baseline Create IMP / IMS  Completion of preliminary design, development of a  Decompose scope into work packages performance baseline that contains a detailed scope,  Assign responsibility for deliverables schedule, and cost estimate.  Arrange work packages in a logical order  The process of technology development, in accordance with the approved TMP should support all  Develop BCWS for work packages CTEs reaching TRL 6; attainment of TRL 6 is  Assign work package measures of performance preferable and indicates that the technology is ready  Set Performance Measurement Baseline for insertion into detailed design. CD–3: Start of Construction Execute Performance Measurement Baseline  Completion of essentially all design and engineering  Performance authorized work and beginning of construction, implementation,  Accumulate and report work package information procurement, or fabrication. A TRA is only required if there is significant technology modification as detailed  Analyze work package performance design work progresses.  Take corrective management action  If substantial modification of a technology occurs, the  Maintain Performance Measurement Baseline TRA should be performed and a focused TMP developed or updated to ensure that the modified technology has attained TRL 6, if possible, prior to its insertion into the detailed design and baseline. Table 2 – for each 413 CD, specific IMP/IMS guidance can be applied to increase the probability of project success, by creating evidence of increasing maturity in units of measure meaningful to the decision makers. 9
  • 10. CHANGING THE PROGRAM PLANNING PARADIGM FROM HORIZONTAL TO VERTICAL Building an IMP / IMS requires a change in the normal paradigm of project management. This change means stopping the measurement of progress as the passage of time and consumption of funding – to measuring progress by the completion of Accomplishment Criteria and the fulfillment of Significant Accomplishments. It means moving from horizontal scheduling to vertical planning. These words are probably meaningless at this point. The description of this paradigm provides an understanding of this concept, the benefits to the project management, and the processes needed to deliver these benefits. In many cases, the horizontal schedules are the starting point for the project. This occurs for several reasons:  The project started without an IMP or a real IMS. They first built a horizontal schedule in the manner of “shop floor” schedule. This is usually for the Period of Performance of the Program.  The project was inherited from a higher or lower level process. Either as a subcontractor or a part of on IPT team, the schedule is focused on the functional aspects of the project. In many cases, the conversion from horizontal to vertical planning is required or desired. The effort to do this conversion involves several steps:  Identify the Program Events and where in the schedule these events take place.  Identify which work in the schedule “lands” on which event. If there is work that crosses an Event boundary, then it will need to be “broken” into two (2) parts. One that “lands” on the Event and one that restarts at the completion of the Event. IMP / IMS FEATURES AND BENEFITS The IMP and IMS focuses on specific areas of the project, which have been shown to be problems with more traditional approaches. The primary focus is on project maturity Event based planning provides a “singularly” focused process allowing each IPT to answer the question – “what do I need to do for a specific event?” For example Preliminary Design Review (PDR): List all the accomplishments needed for PDR? What activities need to performed for each of these accomplishments? When all the activities are completed, the criteria satisfied, and the accomplishments completed then a measurement of “maturity” can take place? This approach is not described in the DOE O 413 series of guidance. Features of IMP/IMS Benefits to the Program Provides an understanding and Drives down cost of execution by connecting changes with the impact of alignment of required tasks with changes that occur early in the project life cycle when costs are lower are events starting with the proposal made visible from day one. Integrates relationships of Improves management visibility by connecting activities with events Permits products and development better understanding of risk and how it impacts cost, schedule, performance processes Provides a framework for using integrated tools, teams, and processes with A disciplined approach to planning vertical traceability Serves as foundation for systematic programmatic and implementation activities improvement efforts Iterative planning, tracking, and Allows project flexibility – on ramps and off ramps tied to events Highlights reporting process details early – ties maturity events with activities Relates project events in terms of success – Accomplishments and Criteria Event–Driven Planning Reduces risk by ensuring that maturity of the plan is incrementally demonstrated prior to starting follow–on activities Improves measurable maturity and impact analysis Promotes project buy–in Increases visibility of entire project and team commitment through shared events Fosters proactive management to the project team at all levels through measurable outcomes 10
  • 11. Features of IMP/IMS Benefits to the Program Resource and Earned Value Provides foundation for Earned Value Reporting and EVMS Loadable Key customer events included Encourages a win–win attitude with customers Clear communication of how the Improves effectiveness through a common set of tools, measurements and team views the project defined outcomes Table 3 – IMP/IMS features and that are not directly provided by executing DOE O 413 series guided projects using measures of cost, schedule, and milestone performance. THE PIECES NEEDED TO INCREASE THE PROBABILITY OF PROJECT SUCCESS Using the DOE Critical Decision (CD) review guide, the Integrated Master Plan paradigm is applied to increase the probability of project success. DOE CD Outcomes IMP / IMS Processes to create outcomes CD–0: Approve Mission Need  Define the Significant Accomplishment needed to fulfill the mission need and  Developing the mission implementation strategy. need and acquisition  Define these in units of performance, effectiveness, and technical compliance. strategy  Define the Measures of Effectiveness (MoE) and Measures of Performance (MoP) for each mission need. (see Figure 2 for relationship between these measures).  Define the “increasing maturity” flow for the work needed to fulfill the mission need and acquisition strategy.  Pre–conceptual  Define the Technical Performance Measures (TPM) for each outcome at the planning planned level of maturity – in the DOE language the Technology Readiness Level (TRL) has similar words CD–1: Alternative Selection and Cost Range  Integrated Master Plan logical “Value” flow, showing how each outcome from the work efforts satisfies the Accomplishment Criteria in units of Measures of  Preliminary project Effectiveness (MoE) and Measures of Performance (MoP) measured against the execution plan planned MoE and MoP.  Verification of mission  Develop Basis of Estimate (BoE) for each Significant Accomplishment and need Accomplishment Criteria (see Figure 1 for IMP/IMS structure).  Connect the BoEs with each measure of maturity and the planned cost to reach that level of maturity. CD–2: Performance (Measurement) Baseline  Preliminary design review  Review project management system  PDR and other reviews assess planned and actual maturity of Significant  Final project execution Accomplishments (SA) and the Accomplishment Criteria (AC). plan  Probabilistic assessment of cost, schedule, and technical performance for each SA  Independent cost and AC. estimate  External independent review CD–3: Start Construction  Final design review  Execution readiness  Starting with the Work Packages, execute each Accomplishment Criteria and review measure actual performance against planned performance using MoE and MoP.  Execute the Performance Baseline Table 4 – for each 413 CD, specific IMP/IMS processes and their outcomes increase the probability of project success through tangible evidence of increasing maturity in units of measure meaningful to the decision makers. 11
  • 12. CONCLUSION Using DOE O 413 series guidance, adding the Integrated Master Plan and Integrated Master Schedule paradigm would provide a hierarchical set of performance measures for each “package of work,” that provides measureable visibility to the increasing maturity of the project. This measureable maturity provides the mechanism to forecast future performance of cost, schedule, and technical outcomes in ways not available using just the activities in DOE O 413. With this information project managers have another tool available to address the issues identified in GAO–07–336 and GAO–09–406. REFERENCES [1] Memorandum for Robert G, Card, Undersecretary, Energy, Science, and Environment, March 31, 2003 from Kyle E. McSlarrow, “Project Management and the Project Management Manual.” http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf [2] “Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide,” Version 0.9, August 15, 2005, Office of the Secretary of Defense (OSD), www.acq.osd.mil/se/docs/IMP_IMS_Guide_v9.pdf [3] “Significant Changes to DOE Order 413.3B,” January 21, 2011, Paul Bosco, Director, Office of Engineering and Construction Management. http://1.usa.gov/v6V5z6 [4] GAO–07–336 Major Construction Projects Need a Consistent Approach for Assessing Technology Readiness to Avoid Cost Increases and Delays. [5] GAO–09–406, Contract and Project Management Concerns at NNSA and Office of EM [6] GAO–08–1081, Nuclear Waste: Action Needed to Improve Accountability and Management of DOE’s Major Cleanup Projects. [7] DOE O 413.3, Program and Project Management for the Acquisition of Capital Assets, included in Memo to Robert Card, March 31, 2003 from Kyle E. McSlarrow. Memo available at http://www.fnal.gov/directorate/OPMO/DOE/o413/m4133-1.pdf [8] DOE G 413.5, Performance Measurement Baseline. [9] DOE O 413.3b Program and Project Management for the Acquisition of Capital Assets. [10] DOE G 413.3–7A Risk Management Guide. [11] “Integrated Master Plan Analysis: The PMAG Approach,” Col. Mun H. Kwon, USAF, Defense AT&L, January–February, 2010, pp. 39–43. 12