IV Group



  February 2009



         1
Locations

  Leksvik, Norway                                 Copenhagen, Denmark
       Industriverktøy AS                             Office
             Headquarter                                   Sales
             Development                                   Technical support
             Project Mngt.                                 Early Supplier Involvement
             Tooling                                       activities
             Molding
             Pre-assembly
       Mako AS
             Tooling         Suzhou, China
                                  IV Techmould Ltd.
                                       ”One-stop-
                                       shop”
                                       Development
                                       Project Mngt.
                                       Tooling
                                       Molding
                                       Painting
                                       Assembly

                                       2
Tooling & Engineering Capacities

Norway
     7-8 tools/month
     1 component tools, 2 component tools, Insert
     moulding
China
     25 tools/month internal
     25 tools/month external
     1 component tools, 2 component tools, Insert
     moulding



IV has a strong focus on “Early Supplier Involvement” activities, sharing knowledge and experience to
create the best possible solution for both customer and vendor. With the long experience in the group we
                 consider our self experts in the field of plastic part design and production.
                                                    3
Moulding Capacities
A total of 71 moulding machines in the range from 20 to 500 ton divided
on two facilities.
Machines throughout the organisation specially prepared to provide the
highest possible quality and accuracy.
Norway
     27 injection moulding machines.
     1 component and 2 component
     Range from 20 to 500 ton.
China
     44 injection moulding machines
     1component and 2 component
     Range from 20 to 150 ton.



                     IV a complete development partner within plastic production.

                                                       4
History / timeline


                                                                                                                                  2006
                                            1983                                                                     2005
    1961          1967        1971                        1997              2000          2001             2003

            IV start with              First order                  Thin-wall                     Production                    IV Tech
            injection                  from Ericsson                production start-             started in                    Mould, China
            moulding                   AB                           up                            Suzhou, China                 moving into
                                                                                                                                new facilities.


                                                                                                                                IV Tech
                                                                                                                                Mould
                                                                                                                                establishing
                                                                                                                  IV Tech
                                                                                                                                paint
                                                                                                                  Mould,
IV was                   First order from          Production started                                                           capacities
                                                                                   Mako Verktøy AS                China
established in           Philips                   in Sweden                                                                    Q2/06
                                                                                   becomes a subsidiary           starting
Leksvik, Norway                                                                    of Industriverktøy             toolshop
under the name                                                                     AS
                                                   2K-production
Industriverktøy                                    start-up
                                                                                                                  Termination
AS
                                                                                   Starts spray-painting          of
                                                                                   in Sweden                      production
                                                                                                                  in Sweden

                                                                        5
Industriverktøy
   Norway

        6
Location, Industriverktøy AS, Leksvik




                                        7
Facility, Industriverktøy AS, Leksvik

                                                                           Facts

                                                            Tooling since 1961
                                                            Moulding since 1967
                                                            4200 m² factory building
                                                            47 employees
                                                            Surface decoration, Tampon
                                                            printing, outsourced paint
                                                            capacity.
                                                            Assembly capacities for
                                                            preassembly and US Welding.

Industriverktøy AS in Leksvik as a engineering and knowledge centre securing the integration
                        of the long experience within the IV group.

                                             8
Injection Moulding Capacities – Industriverktøy A/S, Leksvik
Brand    Size   Type   Amount   Equip.
        (ton)
Engel    25     1K       4      1 robot

Engel    50     1K       3        No
                                robots
Engel    80     1K       10      ERC
                                robots
Engel   125t    1K       3       ERC
                                robots
Engel   150t    1K       2       ERC
                                robots
Engel   150t    2K       3       ERC
                                robots
Engel   250t    1K       1       ERC
                                robots
Engel   500t    1K       1      ERC
                                Robot
                SUM:     27


                                          9
Capacities,
Tooling Capacities, Industriverktøy AS, Leksvik
    Type            Brand         Amount
    CNC         Makino V55-5XA      1
    CNC           Makino V55        1
    CNC          Makino SNC43       1
    CNC         Fadal CNC3016       1
    CNC           Mazak 2500        1
  WEDM          Makino U53, U32     2
   EDM           Makino EDNC        3
                    30, 30S
   EDM           Makino EDNC        1
                      43S
Superdrilling       Joemars         1
CNC turning       Kern CD320        1
Flat grinding   Okamoto, Rosa       3
Laser Welding      Trumph           1
                  Powerweld
Workstation          UG             5
Workstation       Mouldflow         1

                                           10
IV Techmould
    China

      11
Location, IV Techmould AS, Suzhou

                                         Building 16
                                         8400m2 - Q1/2006




                                    12
Facility, IV Techmould AS, Suzhou

                                                                             Facts
                                                           Production start 2003
                                                           8400 m² factory building
                                                           Tool design and fabrication established
                                                           Q4/2005
                                                           Painting capability and capacity from
                                                           Q2/2006
                                                           450 employees
                                                           Surface decoration (Tampon printing)
                                                           Assembly capacities for preassembly, US
                                                           welding.

  IV Tech Mould Suzhou, as a “one stop shop” facility, offering engineering, tooling, moulding,
                 painting, testing, measurement and pre-assembly of products.
                                               13
Injection Moulding Capacities - IV Techmould AS, Suzhou
  Brand        Size   Type   Amount    Equip.
              (ton)
  Engel        25     1K       9       5 ERC
                                       robots
Battlefield    30     1K       1      No robot
  Engel        50     1K       1      No robot

Battenfeld     50     1K       1      No robot
  Engel        80     1K       25     21 ERC
                                       robots
  Engel       125     1K       2       2 ERC
                                       robots
Battelfeld    130     1K       1      No robot

 Demag        100     1K       2       With
                                       robot
  Engel       150t    2K       2       2 ERC
                                       robots
                      SUM      44


                                                 14
Tooling Capacities - IV Techmould AS, Suzhou
    Type               Brand           Amount
     CNC           Mikron HSM 400        1

     CNC           Mikron HSM 500        1

     CNC           Mikron HSM 800        1

     CNC            Fadal CNC3016        1

     CNC            Makino SNC600        1

   WEDM            Charmilles 240SL      1

   WEDM            Charmilles 240SLP     1

WEDM (drilling)     Zhongte D703F        1

    EDM             Charmilles 35P       2

    EDM             Charmilles 350P      1

    EDM             Charmilles 550S      1
    EDM            Makino EDNC 30S       1
 Laserwelding       Alpha ALV100         1

 Flat grinding       Okamoto, etc.       4
 Conventional     QJM – QB – 40VA,       4
   Milling              etc.
  Workstation      UG NX 3.0 CAD         8
  Workstation        Autocad 2006        1

                                                15
Capacities,
Painting Capacities, IV Techmould, Suzhou




 Robotic paint line
 3 spray booths equipped with ABB robots
 UV capable, capable of painting metal parts
 10K Clean room environment inside line, 100K around line.
 Capacity example: 0,8-1,0 million parts/week on 6 working days (part size range 95x47x10mm).
                                               16
IV Mako
 Norway

    17
Facility, IV Mako Verktøy AS

                                                                                 Fakta

                                                            Established 1985
                                                            14 employees
                                                            Tooling also for external customer.
                                                            1000 m² factory building
                                                            Machining in Titan, steel and Aluminium.
                                                            Tooling capacity: 4-5 tools/month.
                                                            Established in own facilities in Vanvikan.



  IV Mako Verktøy AS is a company with long experience in engineering, development and building tools for
       injection molding industry and advance machining of machanical components in titanium, etc.

                                                    18
Capacities,
Tooling Capacities, IV Mako Verktøy AS, Vanvikan
   Type              Brand         Amount

   CNC            Makino V55         1
   CNC          Okuma - MX-45VA      1

   CNC           Hermle - C600V      1

   CNC          Hermle - UWF600      1

   CNC          Hermle - UWF720      1

   CNC          Hermle - UHF851      1
   CNC-
                 Okuma - lb 300      1
  Turning
                   Charmille-
                                     1
                  Roboform 31
                 Okuma - Multus
   CNC                               1
                    b400-w
                 OSO-olomouc
                                     1
                   S.R.O.
Flat grinding         Jotes          2
    Saw          Kasto - twin a2     1
                                            19
Products IV Mako Verktøy AS, Vanvikan




 Toolmaking for injection molding and                            Production of custom made
             extrusion.                                                  prosthesis.




                                        Machining in Titanium.
                                                20
Products IV Mako Verktøy AS, Vanvikan



   Development of tools for
          big parts




                                 21
Products IV Mako Verktøy AS, Vanvikan



                                      Complicated tools with high
                                      precision




                                 22
Services IV Mako Verktøy AS, Vanvikan

• Making injection molding and extrusion tools.
• Toolmaker for external and internal customers offering following services:
     •Project Management
     •Development support
     •Engineering
     •CAD/CAM
     •Toolmanufacturing
     •Testing and qualification if needed.
• High precision machining in Titanium.




                                                   23
Quality
Quality

   ISO 9001 qualified 1994 in Leksvik and 2004 in
   Suzhou.
   ISO 9002 qualified 1996 in Leksvik and 2004 in
   Suzhou.
   ISO 14001 qualified 1999 in Leksvik and 2004 in
   Suzhou.
   Smart scope video measurement used for
   qualification measurement and in-process both in
   Leksvik and Suzhou.
   GOM ATOS II SO 4M 3D scanner available in
   our Suzhou facility.



          IV focuses on integrated SPC and in-process measurement with state of art measurement
                  equipment, enabling a continuous monitoring of the production process.
                                                      24
Products
IV Product types
   Interior and exterior parts for telecom and electronic
   industry.
   Specialized on flexible volume production with cosmetical,
   technical and high precision plastic parts.
   2K hard/hard, hard/soft solutions, cosmetic or functional.
   Thin wall technical parts in mass production.
   Insert moulding or over moulding (combination of metal
   and plastic)
   Other technical plastic products
        IV Tech Mould’s has the capacity and competence to
        manufacture parts for any market segment requiring
        parts within suitable for our machine range (25-500
        tonnage).
        Machines throughout the group are prepared and
        securing high precision moulded plastic components
        Examples of products: Toothbrush, electrical
        equipment, lightning, mobile phone plastic parts, etc        The pictures above illustrates the product spectre of current and former
                                                                     products manufactured by IV Tech Mould



                                                                25
Presentation of the
Project Management
       System




         26
Project Management – Internal Process Chain


                                                                                             T
                                  Project Managment
                                                                                             O
                                                                                             T
                                                                                             A
                                                                                             L

                                                                                             S
                                                                                             O
     Product                        Injection                                      Final
                                                                                             L
                                                                 Pre-
                                                                 Pre-assembly
                       Tooling                    Decoration
   development                      molding                                     inspection
                                                                                             U
                                                                                             T
                                                                                             I
                 Quality, Logistic, SCM, Purchasing/Sourcing, Controlling
                                                                                             O
                                                                                             N



                                                  27
Project Management - Project Driven Organisation


              Product               Injection   Decoration   Assembly
                          Tooling
            development             molding                             ........

Project 1                                                                   Product 1
Project 2                                                                   Product 2
Project 3                                                                   Product 3
Project 4                                                                   Product 4
Project 5                                                                   Product 5




                                           28
Project Management – Phases and Milestones

                                    Time

Quotation phase

             Kick-Off Milestone

            Pre-Project Phase
            Pre-
                                      Pre-Project Milestone

                                  Follow-
                                  Follow-up Phase
                                                           Commercial release Milestone

                                                   Ramp-
                                                   Ramp-up Phase
                                                                         Mass-Production
                                                                         Milestone
                                                                      Mass Production Phase


                                              29
Project Management – Milestone description
      Kick-Off Milestone:
         •Cost and budget preparations done.
         •Volume, capacity and technology analyses done.
         •Risk and product ability study done.
         •Customer awarded project
      Pre-Project Milestone:
          •Approved investment, cost and time schedules
          •Dedicated project team defined.
          •Approved Project layout and design.
          •DFMEA communicated with customer.
      Commercial release Milestone:
         •CmK approval on all components and production equipment done.
         •Limited release on all components.
         •PFMEA and approved Control plans
         •Organization and personnel trained and prepared for Ramp-up and Mass Production.
      Mass-Production Milestone:
         •CpK, PPAP approval on all components and production equipment.
         •Unlimited release on all comp.
         •Mass production orders available
                                               30
Project Management – Project Organisation and Communication

                              Customer

       Project Buyer                          Project Manager


             KAM
                                          Project Manager


                                                Operation
   Quality      Development    Tooling                        Assembly Material/Logistics

                                                       Molding

                                                       Painting

             One window to customer through project management.
                                         31
Project Management – Program Management of Multi Continent Projects.
                       Customer Development Center
          Project Buyer                        Project Manager

          Global - KAM
                                               Program Manager
           Local - KAM
                                   Project Manager             Project Manager
                                       Norway                       China

          Project Buyers                         Project Manager

                           Customer Production Sites


One window to customer through program management on bigger projects
             involving more then one continent and facility.
                                     32
Presentation of the IV Technologies




               33
Product design
Pros
   IV emphasis the importance of early involvement in projects,
   designing and developing the product together with the customer.
   Preparation of prototypes tools or SLA samples for pre-testing
   production conditions of products.
   3-D CAD/CAM
   Mould-flow analysis
   UG ( Unigraphics v. NX 3 ) in Norway and China


Why?

  Sharing knowledge and experience both ways (customer and supplier)
  – “closed loop” product design!
  Create a product optimal for both production and customer
  expectation and securing a process window throughout the complete
  production process
  Optimized process conditions secures stable delivery, more efficient
  production, lowering of cost trough out the value added chain..


  IV Tech Mould emphasizes the importance of “Early Supplier Involvement”, sharing knowledge
         and experience to create the best possible solution for both customer and supplier.
                                                                         34
Two component moulding
Description and why?

  Plastic products is being used in an increasing amount of application,
  The requirements to plastic products, both in new and existing
  market segments is constantly increasing.
  The combination of different material properties in the same
  product, for either functional or cosmetical reasons is getting
  increasingly important.

Pros
   Produce parts with properties not possible with single shot moulding.
   Produce multi-colord or multi-resin parts for functional or cosmetical
   purpose, or both.
   Eliminate assembly steps of cushion or sealing with in-moulded
   solutions; reduce price and enhance product performance.
   In-moulding of cushions and sealing achieving better bonding between
   the two materials, extending product lifetime and improving product
   quality.
   Produce parts with movable segments or components using “in-
   mould assembly” technology.


            IV Tech Mould has long traditions for delivering high quality two component plastics

                                                                            35
Over moulding, Insert moulding
Description and why?
  As for 2K products the combination of different material properties in
  the same product, for either functional or cosmetical reasons are of
  increasing importance.
  Plastic parts are taking over for metal parts; this on one side increases
  the requirement to the mechanical properties of the plastic materials, but
  on the other side also requires the possibility to combine products with
  metal and plastic moulded as one.
  Insert moulding; small metal parts moulded into the plastic product,
  over moulding; metal parts partly over moulded with plastic.

Pros                                   Difficulties
  Space savings                           Selection of suitable materials
  Cost reduction                          Suitable part design for plastic
                                          applications
  Easies the production process
                                          Handling of metal part
  Broaden the design freedom of
  products and components.                Measure tolerances for metal-
                                          and plastic part


    IV Tech Mould has spent considerable resources on the over-moulding technology and possesses
                        unique in-house competence and production capacity

                                                                               36
Thin-
Thin-wall technology
Description and why?
  Space is getting more and more important as the size of the product is                                                Flow length v.s. Wall thickness
  getting continuously reduced but the amount of product functions                                      150

  steadily increased.
                                                                                                        125
  The space for supporting components as plastic parts are getting less
  and less. The thinner plastic parts the more space for other




                                                                                     Flow length [mm]
                                                                                                        100
  components.
                                                                                                        75
                                                                                                                                                        PC/ABS Litteratur

Pros                                  Challenges                                                                                                        PC Litteratur
                                                                                                        50
                                                                                                                                                        PC/ABS Cycoloy MC2263
                                          Selection of suitable materials                                                                               Resultat IV
  Weight savings                                                                                                                                        Eksponentiel. (PC Litteratur)
                                                                                                        25

                                          Suitable part design for plastic                                                                              Eksponentiel. (PC/ABS
  Reduced cooling time                                                                                                                                  Cycoloy MC2263 Resultat IV)
                                          applications                                                   0

  Cost reduction                                                                                              0   0,2     0,4       0,6       0,8   1     1,2

                                          Mould filling simulation                                                          Wall thickness [mm]
  Miniaturization
                                          Increasing tool rigidity with additional
  Capacity increase                       support and locking mechanism
                                          Balanced gate concept
                                          Measurement tolerances


    IV Tech Mould has spent considerable resources on thin wall moulding technology and possesses
                        unique in-house competence and production capacity
                                                                             37
Thank you!




     38

Weitere ähnliche Inhalte

Andere mochten auch

Plastic Injection Molding
Plastic Injection MoldingPlastic Injection Molding
Plastic Injection MoldingSmith Drew
 
Titoma Company Introduction -Electronic Product Design & Turnkey solution China
Titoma Company Introduction -Electronic Product Design & Turnkey solution ChinaTitoma Company Introduction -Electronic Product Design & Turnkey solution China
Titoma Company Introduction -Electronic Product Design & Turnkey solution ChinaTitoma - Design for Asian Manufacturing
 
YUANGUAN Presentation 2015
YUANGUAN Presentation 2015YUANGUAN Presentation 2015
YUANGUAN Presentation 2015Alan She
 
Introduction profile- Harvest
Introduction profile- HarvestIntroduction profile- Harvest
Introduction profile- HarvestYona Jiang
 
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2Frank Li
 
Honokage Company Presentation
Honokage Company Presentation Honokage Company Presentation
Honokage Company Presentation Shirley Yu
 
Anok injection mold / dies casting -- vicky@anokmould.com
Anok injection mold / dies casting -- vicky@anokmould.comAnok injection mold / dies casting -- vicky@anokmould.com
Anok injection mold / dies casting -- vicky@anokmould.comYan VickyTeng
 
Company presentation of Derco Mould Engineering 2016
Company presentation of Derco Mould Engineering 2016Company presentation of Derco Mould Engineering 2016
Company presentation of Derco Mould Engineering 2016John Gao
 
Ningguang Mould -New
Ningguang Mould -NewNingguang Mould -New
Ningguang Mould -NewAlice Chen
 
BH Mould Presentation
BH Mould PresentationBH Mould Presentation
BH Mould PresentationAmanda Guo
 
Maxuni Presentation 2011 Updated
Maxuni Presentation 2011 UpdatedMaxuni Presentation 2011 Updated
Maxuni Presentation 2011 Updatedmaxuni
 
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015Hommer Zou
 
Kendy Mould Company Presentation-Tina Chan
Kendy Mould Company Presentation-Tina ChanKendy Mould Company Presentation-Tina Chan
Kendy Mould Company Presentation-Tina ChanTina Chan
 
IEC Russia — Automotive Industry
IEC Russia — Automotive IndustryIEC Russia — Automotive Industry
IEC Russia — Automotive IndustryRoman Fedorov
 

Andere mochten auch (15)

China Custom Mold Factory for Plastic and Rubber _
China Custom Mold Factory for Plastic and Rubber _ China Custom Mold Factory for Plastic and Rubber _
China Custom Mold Factory for Plastic and Rubber _
 
Plastic Injection Molding
Plastic Injection MoldingPlastic Injection Molding
Plastic Injection Molding
 
Titoma Company Introduction -Electronic Product Design & Turnkey solution China
Titoma Company Introduction -Electronic Product Design & Turnkey solution ChinaTitoma Company Introduction -Electronic Product Design & Turnkey solution China
Titoma Company Introduction -Electronic Product Design & Turnkey solution China
 
YUANGUAN Presentation 2015
YUANGUAN Presentation 2015YUANGUAN Presentation 2015
YUANGUAN Presentation 2015
 
Introduction profile- Harvest
Introduction profile- HarvestIntroduction profile- Harvest
Introduction profile- Harvest
 
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2
Ehlebracht Group and EIC_presentation Tools&Plastics parts Q2
 
Honokage Company Presentation
Honokage Company Presentation Honokage Company Presentation
Honokage Company Presentation
 
Anok injection mold / dies casting -- vicky@anokmould.com
Anok injection mold / dies casting -- vicky@anokmould.comAnok injection mold / dies casting -- vicky@anokmould.com
Anok injection mold / dies casting -- vicky@anokmould.com
 
Company presentation of Derco Mould Engineering 2016
Company presentation of Derco Mould Engineering 2016Company presentation of Derco Mould Engineering 2016
Company presentation of Derco Mould Engineering 2016
 
Ningguang Mould -New
Ningguang Mould -NewNingguang Mould -New
Ningguang Mould -New
 
BH Mould Presentation
BH Mould PresentationBH Mould Presentation
BH Mould Presentation
 
Maxuni Presentation 2011 Updated
Maxuni Presentation 2011 UpdatedMaxuni Presentation 2011 Updated
Maxuni Presentation 2011 Updated
 
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015
The Profile about Thinkbus Kalung (HK) manufacturing Ltd, 2015
 
Kendy Mould Company Presentation-Tina Chan
Kendy Mould Company Presentation-Tina ChanKendy Mould Company Presentation-Tina Chan
Kendy Mould Company Presentation-Tina Chan
 
IEC Russia — Automotive Industry
IEC Russia — Automotive IndustryIEC Russia — Automotive Industry
IEC Russia — Automotive Industry
 

Kürzlich hochgeladen

Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...ShrutiBose4
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncrdollysharma2066
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionMintel Group
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 

Kürzlich hochgeladen (20)

Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
Ms Motilal Padampat Sugar Mills vs. State of Uttar Pradesh & Ors. - A Milesto...
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / NcrCall Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Future Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted VersionFuture Of Sample Report 2024 | Redacted Version
Future Of Sample Report 2024 | Redacted Version
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 

IV Group Locations Tooling & Engineering Capacities

  • 1. IV Group February 2009 1
  • 2. Locations Leksvik, Norway Copenhagen, Denmark Industriverktøy AS Office Headquarter Sales Development Technical support Project Mngt. Early Supplier Involvement Tooling activities Molding Pre-assembly Mako AS Tooling Suzhou, China IV Techmould Ltd. ”One-stop- shop” Development Project Mngt. Tooling Molding Painting Assembly 2
  • 3. Tooling & Engineering Capacities Norway 7-8 tools/month 1 component tools, 2 component tools, Insert moulding China 25 tools/month internal 25 tools/month external 1 component tools, 2 component tools, Insert moulding IV has a strong focus on “Early Supplier Involvement” activities, sharing knowledge and experience to create the best possible solution for both customer and vendor. With the long experience in the group we consider our self experts in the field of plastic part design and production. 3
  • 4. Moulding Capacities A total of 71 moulding machines in the range from 20 to 500 ton divided on two facilities. Machines throughout the organisation specially prepared to provide the highest possible quality and accuracy. Norway 27 injection moulding machines. 1 component and 2 component Range from 20 to 500 ton. China 44 injection moulding machines 1component and 2 component Range from 20 to 150 ton. IV a complete development partner within plastic production. 4
  • 5. History / timeline 2006 1983 2005 1961 1967 1971 1997 2000 2001 2003 IV start with First order Thin-wall Production IV Tech injection from Ericsson production start- started in Mould, China moulding AB up Suzhou, China moving into new facilities. IV Tech Mould establishing IV Tech paint Mould, IV was First order from Production started capacities Mako Verktøy AS China established in Philips in Sweden Q2/06 becomes a subsidiary starting Leksvik, Norway of Industriverktøy toolshop under the name AS 2K-production Industriverktøy start-up Termination AS Starts spray-painting of in Sweden production in Sweden 5
  • 6. Industriverktøy Norway 6
  • 8. Facility, Industriverktøy AS, Leksvik Facts Tooling since 1961 Moulding since 1967 4200 m² factory building 47 employees Surface decoration, Tampon printing, outsourced paint capacity. Assembly capacities for preassembly and US Welding. Industriverktøy AS in Leksvik as a engineering and knowledge centre securing the integration of the long experience within the IV group. 8
  • 9. Injection Moulding Capacities – Industriverktøy A/S, Leksvik Brand Size Type Amount Equip. (ton) Engel 25 1K 4 1 robot Engel 50 1K 3 No robots Engel 80 1K 10 ERC robots Engel 125t 1K 3 ERC robots Engel 150t 1K 2 ERC robots Engel 150t 2K 3 ERC robots Engel 250t 1K 1 ERC robots Engel 500t 1K 1 ERC Robot SUM: 27 9
  • 10. Capacities, Tooling Capacities, Industriverktøy AS, Leksvik Type Brand Amount CNC Makino V55-5XA 1 CNC Makino V55 1 CNC Makino SNC43 1 CNC Fadal CNC3016 1 CNC Mazak 2500 1 WEDM Makino U53, U32 2 EDM Makino EDNC 3 30, 30S EDM Makino EDNC 1 43S Superdrilling Joemars 1 CNC turning Kern CD320 1 Flat grinding Okamoto, Rosa 3 Laser Welding Trumph 1 Powerweld Workstation UG 5 Workstation Mouldflow 1 10
  • 11. IV Techmould China 11
  • 12. Location, IV Techmould AS, Suzhou Building 16 8400m2 - Q1/2006 12
  • 13. Facility, IV Techmould AS, Suzhou Facts Production start 2003 8400 m² factory building Tool design and fabrication established Q4/2005 Painting capability and capacity from Q2/2006 450 employees Surface decoration (Tampon printing) Assembly capacities for preassembly, US welding. IV Tech Mould Suzhou, as a “one stop shop” facility, offering engineering, tooling, moulding, painting, testing, measurement and pre-assembly of products. 13
  • 14. Injection Moulding Capacities - IV Techmould AS, Suzhou Brand Size Type Amount Equip. (ton) Engel 25 1K 9 5 ERC robots Battlefield 30 1K 1 No robot Engel 50 1K 1 No robot Battenfeld 50 1K 1 No robot Engel 80 1K 25 21 ERC robots Engel 125 1K 2 2 ERC robots Battelfeld 130 1K 1 No robot Demag 100 1K 2 With robot Engel 150t 2K 2 2 ERC robots SUM 44 14
  • 15. Tooling Capacities - IV Techmould AS, Suzhou Type Brand Amount CNC Mikron HSM 400 1 CNC Mikron HSM 500 1 CNC Mikron HSM 800 1 CNC Fadal CNC3016 1 CNC Makino SNC600 1 WEDM Charmilles 240SL 1 WEDM Charmilles 240SLP 1 WEDM (drilling) Zhongte D703F 1 EDM Charmilles 35P 2 EDM Charmilles 350P 1 EDM Charmilles 550S 1 EDM Makino EDNC 30S 1 Laserwelding Alpha ALV100 1 Flat grinding Okamoto, etc. 4 Conventional QJM – QB – 40VA, 4 Milling etc. Workstation UG NX 3.0 CAD 8 Workstation Autocad 2006 1 15
  • 16. Capacities, Painting Capacities, IV Techmould, Suzhou Robotic paint line 3 spray booths equipped with ABB robots UV capable, capable of painting metal parts 10K Clean room environment inside line, 100K around line. Capacity example: 0,8-1,0 million parts/week on 6 working days (part size range 95x47x10mm). 16
  • 18. Facility, IV Mako Verktøy AS Fakta Established 1985 14 employees Tooling also for external customer. 1000 m² factory building Machining in Titan, steel and Aluminium. Tooling capacity: 4-5 tools/month. Established in own facilities in Vanvikan. IV Mako Verktøy AS is a company with long experience in engineering, development and building tools for injection molding industry and advance machining of machanical components in titanium, etc. 18
  • 19. Capacities, Tooling Capacities, IV Mako Verktøy AS, Vanvikan Type Brand Amount CNC Makino V55 1 CNC Okuma - MX-45VA 1 CNC Hermle - C600V 1 CNC Hermle - UWF600 1 CNC Hermle - UWF720 1 CNC Hermle - UHF851 1 CNC- Okuma - lb 300 1 Turning Charmille- 1 Roboform 31 Okuma - Multus CNC 1 b400-w OSO-olomouc 1 S.R.O. Flat grinding Jotes 2 Saw Kasto - twin a2 1 19
  • 20. Products IV Mako Verktøy AS, Vanvikan Toolmaking for injection molding and Production of custom made extrusion. prosthesis. Machining in Titanium. 20
  • 21. Products IV Mako Verktøy AS, Vanvikan Development of tools for big parts 21
  • 22. Products IV Mako Verktøy AS, Vanvikan Complicated tools with high precision 22
  • 23. Services IV Mako Verktøy AS, Vanvikan • Making injection molding and extrusion tools. • Toolmaker for external and internal customers offering following services: •Project Management •Development support •Engineering •CAD/CAM •Toolmanufacturing •Testing and qualification if needed. • High precision machining in Titanium. 23
  • 24. Quality Quality ISO 9001 qualified 1994 in Leksvik and 2004 in Suzhou. ISO 9002 qualified 1996 in Leksvik and 2004 in Suzhou. ISO 14001 qualified 1999 in Leksvik and 2004 in Suzhou. Smart scope video measurement used for qualification measurement and in-process both in Leksvik and Suzhou. GOM ATOS II SO 4M 3D scanner available in our Suzhou facility. IV focuses on integrated SPC and in-process measurement with state of art measurement equipment, enabling a continuous monitoring of the production process. 24
  • 25. Products IV Product types Interior and exterior parts for telecom and electronic industry. Specialized on flexible volume production with cosmetical, technical and high precision plastic parts. 2K hard/hard, hard/soft solutions, cosmetic or functional. Thin wall technical parts in mass production. Insert moulding or over moulding (combination of metal and plastic) Other technical plastic products IV Tech Mould’s has the capacity and competence to manufacture parts for any market segment requiring parts within suitable for our machine range (25-500 tonnage). Machines throughout the group are prepared and securing high precision moulded plastic components Examples of products: Toothbrush, electrical equipment, lightning, mobile phone plastic parts, etc The pictures above illustrates the product spectre of current and former products manufactured by IV Tech Mould 25
  • 26. Presentation of the Project Management System 26
  • 27. Project Management – Internal Process Chain T Project Managment O T A L S O Product Injection Final L Pre- Pre-assembly Tooling Decoration development molding inspection U T I Quality, Logistic, SCM, Purchasing/Sourcing, Controlling O N 27
  • 28. Project Management - Project Driven Organisation Product Injection Decoration Assembly Tooling development molding ........ Project 1 Product 1 Project 2 Product 2 Project 3 Product 3 Project 4 Product 4 Project 5 Product 5 28
  • 29. Project Management – Phases and Milestones Time Quotation phase Kick-Off Milestone Pre-Project Phase Pre- Pre-Project Milestone Follow- Follow-up Phase Commercial release Milestone Ramp- Ramp-up Phase Mass-Production Milestone Mass Production Phase 29
  • 30. Project Management – Milestone description Kick-Off Milestone: •Cost and budget preparations done. •Volume, capacity and technology analyses done. •Risk and product ability study done. •Customer awarded project Pre-Project Milestone: •Approved investment, cost and time schedules •Dedicated project team defined. •Approved Project layout and design. •DFMEA communicated with customer. Commercial release Milestone: •CmK approval on all components and production equipment done. •Limited release on all components. •PFMEA and approved Control plans •Organization and personnel trained and prepared for Ramp-up and Mass Production. Mass-Production Milestone: •CpK, PPAP approval on all components and production equipment. •Unlimited release on all comp. •Mass production orders available 30
  • 31. Project Management – Project Organisation and Communication Customer Project Buyer Project Manager KAM Project Manager Operation Quality Development Tooling Assembly Material/Logistics Molding Painting One window to customer through project management. 31
  • 32. Project Management – Program Management of Multi Continent Projects. Customer Development Center Project Buyer Project Manager Global - KAM Program Manager Local - KAM Project Manager Project Manager Norway China Project Buyers Project Manager Customer Production Sites One window to customer through program management on bigger projects involving more then one continent and facility. 32
  • 33. Presentation of the IV Technologies 33
  • 34. Product design Pros IV emphasis the importance of early involvement in projects, designing and developing the product together with the customer. Preparation of prototypes tools or SLA samples for pre-testing production conditions of products. 3-D CAD/CAM Mould-flow analysis UG ( Unigraphics v. NX 3 ) in Norway and China Why? Sharing knowledge and experience both ways (customer and supplier) – “closed loop” product design! Create a product optimal for both production and customer expectation and securing a process window throughout the complete production process Optimized process conditions secures stable delivery, more efficient production, lowering of cost trough out the value added chain.. IV Tech Mould emphasizes the importance of “Early Supplier Involvement”, sharing knowledge and experience to create the best possible solution for both customer and supplier. 34
  • 35. Two component moulding Description and why? Plastic products is being used in an increasing amount of application, The requirements to plastic products, both in new and existing market segments is constantly increasing. The combination of different material properties in the same product, for either functional or cosmetical reasons is getting increasingly important. Pros Produce parts with properties not possible with single shot moulding. Produce multi-colord or multi-resin parts for functional or cosmetical purpose, or both. Eliminate assembly steps of cushion or sealing with in-moulded solutions; reduce price and enhance product performance. In-moulding of cushions and sealing achieving better bonding between the two materials, extending product lifetime and improving product quality. Produce parts with movable segments or components using “in- mould assembly” technology. IV Tech Mould has long traditions for delivering high quality two component plastics 35
  • 36. Over moulding, Insert moulding Description and why? As for 2K products the combination of different material properties in the same product, for either functional or cosmetical reasons are of increasing importance. Plastic parts are taking over for metal parts; this on one side increases the requirement to the mechanical properties of the plastic materials, but on the other side also requires the possibility to combine products with metal and plastic moulded as one. Insert moulding; small metal parts moulded into the plastic product, over moulding; metal parts partly over moulded with plastic. Pros Difficulties Space savings Selection of suitable materials Cost reduction Suitable part design for plastic applications Easies the production process Handling of metal part Broaden the design freedom of products and components. Measure tolerances for metal- and plastic part IV Tech Mould has spent considerable resources on the over-moulding technology and possesses unique in-house competence and production capacity 36
  • 37. Thin- Thin-wall technology Description and why? Space is getting more and more important as the size of the product is Flow length v.s. Wall thickness getting continuously reduced but the amount of product functions 150 steadily increased. 125 The space for supporting components as plastic parts are getting less and less. The thinner plastic parts the more space for other Flow length [mm] 100 components. 75 PC/ABS Litteratur Pros Challenges PC Litteratur 50 PC/ABS Cycoloy MC2263 Selection of suitable materials Resultat IV Weight savings Eksponentiel. (PC Litteratur) 25 Suitable part design for plastic Eksponentiel. (PC/ABS Reduced cooling time Cycoloy MC2263 Resultat IV) applications 0 Cost reduction 0 0,2 0,4 0,6 0,8 1 1,2 Mould filling simulation Wall thickness [mm] Miniaturization Increasing tool rigidity with additional Capacity increase support and locking mechanism Balanced gate concept Measurement tolerances IV Tech Mould has spent considerable resources on thin wall moulding technology and possesses unique in-house competence and production capacity 37