SlideShare ist ein Scribd-Unternehmen logo
1 von 23
Downloaden Sie, um offline zu lesen
Dulles Metrorail Silver Line:
Status Report &
Transportation Infrastructure
Finance and Innovation Act
(TIFIA) Funding Update

Transportation Committee
Fairfax County Board of Supervisors
May 7, 2013
Presentation Outline

• Phase 1 Status Report
• Phase 2 Status Report
• Transportation Infrastructure Finance and
Innovation Act (TIFIA) Funding Update
• Recommendation of Preliminary TIFIA
Allocation
• Requirements from Funding Partners
• Phase 1 Plan of Finance – Closeout
• Staff Recommendations
• Timeline

2
Phase 1 – Status Report

Construction: 90% Complete
Final Design: 100% Complete
Utility Relocation: 100% Complete
Property Acquisition: All rights of entry obtained
Track Work: 100% Complete
Stations:
• McLean – 80%
• Tysons Corner – 75%
• Greensboro – 65%
• Spring Hill – 65%
• Wiehle – 84%
• First Delivery of Rail Cars – February 2014
• Wiehle Garage: 88% Complete
• Garage Substantial Completions: July 19, 2013
• Roadway Improvements (ROD): 67% complete
• August/September 2013 completion

Status
•
•
•
•
•
•

• Revised Budget Authorized: $2.905B
• Expended to Date: $2.2B
• County Phase 1 share: $467.8M
• Tax District Funds: $400M (Funding Gap =
$67.8M)
• Fairfax County share of Project expenditures through
fourth quarter 2012 = $369.1M
• $150M received from Commonwealth

Budget

(as of April 24, 2013)

• Substantial Completion: September 7, 2013
• WMATA Testing and Acceptance: August – December
2013
• West Falls Church Yard Completion: December 2013
• Sound Box and Tail Track: November 2013
• Estimated Passenger Revenue Service: December 31,
2013

Schedule

• Entire 3rd Rail energized for Metrorail train testing.
• Tunnel Clearance – No issues per WMATA
• All five stations under construction with efforts on
mechanical, electrical, plumbing, and station finishes
• Phase 1 Maintenance and Land Conveyance process
ongoing:
• Fairfax County will retain ownership of Kiss
and Ride at McLean
• Fairfax County will operate through an
easement Kiss and Ride at Spring Hill Station
• Regional planning effort underway for Phase 1 bus
service (Fairfax Connector, WMATA, Washington Flyer,
PRTC, Loudoun Transit)
• Fairfax County 2nd round of Public Meetings
ongoing
• Ask Fairfax online chat completed

Current Milestones – Past 30 Days

3
Phase 2 – Status Report

• Packet A Price Proposals Opened – April 19, 2013
• Project estimate Packet A = $1.4B - $1.6B vs. $1.177B
low bid
• Positive impact on toll rates = $300M (est.)

Status

(as of April 24, 2013)

Station included in Packet A bid.
•
County using its best efforts to mitigate
some station costs on south side. (ROW,
alternative site work funding, and
improved site layout for: garage, bus
bay, and kiss/ride design. )
Station cost will have to be funding either in
part or whole per the funding agreement
(County funding agreement share 16.1%).
County also pursuing funding from TIGER
Grants and NVTA

Innovation Center (RT 28) Station
•

•

•

• Cost Estimate: $3.093B
• Cost Estimate with value engineering and
alternative funding for garages & Innovation
Center Station: $2.7B
• Cost to build garages in Fairfax County: $105M
est.
• Fairfax County share for Phase 2 ranges from
$433M – $498M, Tax District capped at $330M

Budget
• Packet A Contract Award: May 2013
• Packet A Notice to Proceed: June 2013
• 5 Bid Packages:
• Packet A - Rail Line, Station, and Systems
(includes Innovation Center Station)
• Packet B – Yard and Shop
• Packet C (may not be issued) – Parking
Garages
• Packet D – ROW
• Packet E – Utilities
• Fairfax County working to fund & construct Herndon
and Innovation Center garages outside of project
• Financial Plan status:
• Transportation Sub Committee May 7, 2013
• BOS May 14, 2013

• Substantial Completion: Summer 2018
• Revenue Operations: Late 2018

Schedule

• FTA oversight of Phase 2 under discussion:
Ongoing
• TIFIA Letter of Interest submitted: Ongoing
• WMATA Art in Transit: Selection: Ongoing
• Reston Town Center Tunnel Design under review
by WMATA and MWAA

Current Milestones Past 30 Days

4
Request Board Approval of
Staff Recommendations

• Approve the Preliminary TIFIA Allocation of $1.9b
amongst the Funding Partners, with County to receive
$475m
• Approve the County Credit Pledge of the C & I Fund and
the Phase 2 Tax District to TIFIA; Potential use of Moral
Obligation from General Fund to meet AA Category
Rating mandated from USDOT
• Request Credit Ratings from the bond rating agencies to
comply with TIFIA Credit Review ($90,000)
• Approve the $100,000 down payment required from the
County to move forward in the TIFIA Letter of Interest
(LOI) review process
• Review short term financing options to cover the $67m
for balance of County contributions for Phase 1. This will
be paid off with receipt of TIFIA funds

5
Transportation Infrastructure
Finance and Innovation Act
(TIFIA) Status Update Recommendation of Preliminary
TIFIA Allocation

6
TIFIA Financing Overview

• Federal credit assistance in the form of direct loans
(not grants) to finance surface transportation projects
of national and regional significance
• USDOT Secretary LaHood departing & accelerated
turnaround time for documents
• Improved access to capital markets, flexible
repayment terms, and potentially more favorable
interest rates than can be found in private capital
markets for similar instruments
• Loan Repayment Deferral Option - 5 years after
project completion (2023)
• Alternatively – conduct open market bond sale & debt
service payments immediately

7
Silver Line Cost Allocation –
Funding Partners

Funding
Partner

Dulles Toll Road*

% Share TPE Baseline
75%

$ Share TPE Baseline

Funding Partner
Total
(TPE Baseline +
Garages)

Other –
Garages

$4,262,763,750

-

$4,262,763,750

Fairfax

16.1%

915,073,285

146,721,000

1,061,794,285

Loudoun
MWAA –
Aviation Funds

4.8%

272,816,880

168,413,000

441,229,880

4.1%

233,031,085

-

233,031,085

$5,683,685,000 $315,134,000

$5,998,819,000

Total

100.00%

* Includes $900m from FTA New Starts (16.1%), $275m from Commonwealth (4.9%). Net to
Dulles Toll Road is 54%. Allocation assumes the add’l $150m + $300m for Phase 2 will be used to
pay interest on Dulles Toll Road Revenue Bonds, not direct project costs.

8
Silver Line Total Project Estimate Fairfax County Costs 16.1%
Phase 1

Total Baseline

County Share @ 16.1%
Less Tax Districts
Net County due

Phase 2

Total

$2,905,685,000

$2,778,000,000

$5,683,685,000

467,815,285

447,258,000

915,073,285

(400,000,000)

(330,000,000)

(730,000,000)

$67,815,285

$117,258,000

$185,073,285

$80,959,000*

$80,959,000

65,762,000*

65,762,000

$146,721,000

$146,721,000

Garages
Herndon-Monroe
Route 28
Total Garages

TOTAL (Baseline + Garages)

$467,815,285

$593,979,000

$1,061,794,285

*Per 100% P/E and consistent with MWAA documents; County believes costs will be lower and in the process of
a feasibility study

9
TIFIA Allocation:
Funding Partner Consensus

• December 2012 – Per USDOT Project Will Remain
Eligible for 33% TIFIA Loan or $1.9b ($5.9b * 33%)
Funding Partner
Fairfax

Funding Partner
Total Project Cost

TIFIA
Allocation

$1,061,794,285

$475,000,000

Loudoun

441,229,880

200,000,000

MWAA – Aviation Funds

233,031,085

-

Dulles Toll Road
Total

4,262,763,750
$5,998,819,000

1,304,610,270
$1,979,610,270

• Meets MWAA goal of $1.2-$1.4b for the Toll Road
• Counties maintain equity of TIFIA allocation equal to
45% Total Project Cost

10
TIFIA Premium Projections
A

Funding
Partner
Fairfax

Loudoun

B
USDOT
Requested
Minimum
Credit Rating
AA Category

AA Category
Investment Grade
Dulles Toll Road (BBB Category)
Total

C

D

E (C * D)

Anticipated
TIFIA Premium

TIFIA
Allocation*

USDOT Premium
Subsidy
Allocation

2%

$475,000,000

$9,500,000

2%

200,000,000

4,000,000

12%

1,304,610,270

156,553,232

$1,979,610,270

$170,053,232

Premium allocation evaluated/ reviewed heavily by TIFIA office
when awarding project funding
* Assumes MWAA Aviation Funds receive no TIFIA Loan

11
TIFIA Status Update –
Requirements from Funding
Partners

12
TIFIA Financing

• Competitive Interest Rates that correlate to 30-Year
Treasury Note
• Flexible call options - prepay outstanding principal
• Potential future refunding opportunities
• USDOT Expected Ratings from Funding Partners
• AA Category Rating from Counties
• Investment Grade from Dulles Toll Road (MWAA)

• Pledge two County sources for Plan of Finance
• Commercial and Industrial Tax Fund
• Dulles Rail Phase 2 Tax District ($330 million)

• May be required to include Moral Obligation of the
County General Fund if AA Category Rating is not
achieved

13
USDOT Information Request –
April 2013

• Complete County Plan of Finance for TIFIA
• Commercial and Industrial Tax Fund
• Dulles Rail Phase 2 Tax District ($330 million)

• Indicative Rating Letter on the TIFIA Loan
• USDOT EXPECTS Counties to achieve rating in the AA Category
• Initial review from the Credit Rating Agencies ($90,000)

• Feasibility Study for Each Source of Credit Pledged
• MWAA Toll Road Study
• Counties expected to submit standard information: tax
assessment, economic, and demographic information

• Credit Processing Down Payment of $100,000 from each
funding partner

14
County Plan of Finance for TIFIA Commercial & Industrial Tax Fund

• Tax Rate of 12.5 cents per $100 of AV & generates
approximately $51m revenue annually
• Previously recommended to finance County project costs
outside of the two tax districts: Phase 1 ($67.8m) & Phase
2 ($117.3m)
• Planning Guideline for Long Term Forecasting:
• 50% of expenses for Tysons / Silver Line
• 50% of expenses for Remainder Countywide Projects

• Loan Repayment Deferral Option - 5 years after project
completion (2023)
• Redirect previously forecasted monies required for debt
service to fund other Countywide projects (equates to
approximately $70m total from 2014-2023)

15
County Plan of Finance for TIFIA Phase 2 Tax District $330 million

• Estimated stand alone current rating of this district likely “A”
Category, thus enhancement necessary

• Comparative Assessed Value 1/1/13: Phase 1 $11.4b vs. Phase 2 $7.5b

• Allow for growth district tax base / assessed value, similar to Phase
1 Tax District
• Phase 2 Tax Rate – 20 cents for FY 2014
• Initially began at 5 Cents in FY 2011, with 5 cent laddered increases
• Remain at this rate until rail service begins 2018, then ability to increase to
25 cents per Petition

• Accumulation of tax collections to provide for early repayment of
outstanding principal at regular intervals
• Staff recommendation that C & I Fund be used back this Tax District
for credit enhancement
• General Fund Moral Obligation may be needed to reach AA
Category if C & I Fund insufficient

16
Financing Dulles Rail - Alternate Options
Public Sector Sources

General
State/Feder Fund (Pay
al Funding
Go)

Cost of Financing /
Carrying Cost
(Lowest to High)

■

Length of Time to
Accrue Funds
(Sooner to Later)

•

General Fund Impact
(Low to High)
Impact on
Redevelopment
(Low to High)
Impact to G.O. Debt
(Low to High)
Ability to Meet Capital
Requirements
(High to Low)
Requires Third Party
Concurrence
(Degree of Difficulty)

■
♦
■

•
•

■

G.O. Bonds

C&I Funds

■
♦
♦
■
■
♦
■

■
■
■
■
♦
♦
♦

Low Impact and/or

Most Beneficial

♦
♦
■
♦
■
♦
♦
♦

Meals Tax
(Pay Go)

■
♦
■
■
■
■

•

Private Sector Sources

100% TIF

Service
Developer
Capped TIF District /CDA Contributions

•

•

♦

■

♦

♦
♦
■
■
♦
■

•

•

■
♦
■
■

■
■
♦

•

•

•
■
■
■
■

Medium Impact and/or of Concern

Other Potential Funding Options: NVTA & Federal TIGER Grants

•

•

High Impact and/or Most Difficult

17
Fairfax County Portion
Remaining Dulles Rail Financing
Phase 1

Total Project Estimate (TPE)
County Share @ 16.1%
Less Tax Districts
Net County due
Total County Remaining
Financing Needed

*paid to date to MWAA

Phase 2

Total

$2,905,685,000

$2,778,000,000

$5,683,685,000

467,815,285

447,258,000

915,073,285

(400,000,000*)

(330,000,000)

(730,000,000)

$67,815,285

$117,258,000

$185,073,285

$67,815,285

$447,258,000

$515,073,285

18
Fairfax County Cashflow
Remaining Dulles Rail Financing
Source Funds

Amount Source Debt
Service

Comment

TIFIA

$67.8m C & I Fund

TIFIA

$117.3m C & I Fund

Phase 2 costs beyond $330m from
Phase 2 Tax District (2013-2018)

TIFIA

$289.9m Phase 2
Tax District

88% of Phase 2 Tax District’s $330m
(2013-2018)

Total TIFIA

$475.0m

45% Total County Project Cost

Phase 2 Tax
District Bond Sale
or Cash
Total Remaining
Financing

$40.1m Phase 2
Tax District
$515.1m

Balance Phase 1 costs beyond
$400m from Phase 1 Tax District;
TIFIA may be used to repay short
term financing (2013)

Phase 2 Tax District Bond Sale or
Cash Contribution (2018)

19
County Phase 1 Cost - $467m

• Phase 1 Tax District fulfilled $400 million obligation
• Establish a plan of finance to cover remaining $67m
to close out the County’s Phase 1 contributions
• TIFIA Funds are not expected until end of the
Calendar Year 2013 at the earliest
• County Staff and Financial Advisor review of short
term financing options to address the $67m:
• Use portion of County’s current $100m Line of Credit
• Bond Anticipation Note (BAN)

• Staff recommendation: Utilize the Line of Credit &
then pay off from receipt of TIFIA funds.

20
Recommendations – Consistent
with May 14th Board Item

• Approve the Preliminary TIFIA Allocation of $1.9b amongst
the Funding Partners, with County to receive $475m
• Approve the County Credit Pledge of the C & I Fund and
the Phase 2 Tax District to TIFIA
• Goal to receive AA Category Rating and assumes no Moral
Obligation
• Phase 2 Tax District to utilize $290m of Preliminary TIFIA &
seeking Moral Obligation (e.g. Credit Enhancement) from C &
I Fund

• Request Credit Ratings from the bond rating agencies to
comply with TIFIA Credit Review ($90,000)
• Approve the $100,000 down payment required from the
County to move forward in the TIFIA LOI review process
• Review short term financing options to cover the $67m for
balance of County contributions for Phase 1. This will be
paid off with receipt of TIFIA funds

21
Timeline

Date

Item

October 2012

MAP-21 Revised TIFIA Loan Notification (33% to 49%)

October 2012

Funding Partners Submits LOI USDOT TIFIA (@ 49%)

December 2012

TIFIA request to Funding Partners for more information

January 2013

Funding Partners discussion on TIFIA Allocation

April / May 2013

MWAA Awards Phase 2 Design-Build Contract

May 2013

Board Discussion on TIFIA Allocation

May 2013

Discussion with Bond Rating Agencies on County Credit for TIFIA

May 2013

Submit County materials to TIFIA

Summer 2013

County Interim Financing to cover balance of Phase 1 costs

December 2013

Targeted Closing on TIFIA Loan for Funding Partners

December 2013

Begin Service for Phase 1

Spring 2014

Refinance Interim Financing for balance Phase 1 costs

December 2018

Begin Service for Phase 2

22
Questions?
23

Weitere ähnliche Inhalte

Was ist angesagt?

Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Fairfax County
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Fairfax County
 
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax County
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the BeltwayFairfax County
 
Fairfax County Parkway Corridor Study
Fairfax County Parkway Corridor StudyFairfax County Parkway Corridor Study
Fairfax County Parkway Corridor StudyFairfax County
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Fairfax County
 
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Fairfax County
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...Fairfax County
 
Reston Network Analysis: 2050 1st Tier Mitigation Results
Reston Network Analysis: 2050 1st Tier Mitigation ResultsReston Network Analysis: 2050 1st Tier Mitigation Results
Reston Network Analysis: 2050 1st Tier Mitigation ResultsFairfax County
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilityFairfax County
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Fairfax County
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisFairfax County
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictFairfax County
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationFairfax County
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Fairfax County
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayFairfax County
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Fairfax County
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationFairfax County
 

Was ist angesagt? (20)

Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016Reston Transportation Funding Plan: July 15, 2016
Reston Transportation Funding Plan: July 15, 2016
 
Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013Countywide Transit Network Study: Public Meeting July 10, 2013
Countywide Transit Network Study: Public Meeting July 10, 2013
 
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit NetworkFairfax Countywide Transit Network Study: Proposed High Quality Transit Network
Fairfax Countywide Transit Network Study: Proposed High Quality Transit Network
 
Transform 66: Inside the Beltway
Transform 66: Inside the BeltwayTransform 66: Inside the Beltway
Transform 66: Inside the Beltway
 
Reston Funding Plan
Reston Funding PlanReston Funding Plan
Reston Funding Plan
 
Fairfax County Parkway Corridor Study
Fairfax County Parkway Corridor StudyFairfax County Parkway Corridor Study
Fairfax County Parkway Corridor Study
 
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
Dulles Corridor Metrorail Project Phase 2 & Station Names: Community Meetings...
 
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2Reston Network Analysis: Community Meeting Tier 1 & Tier 2
Reston Network Analysis: Community Meeting Tier 1 & Tier 2
 
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
Continuation of CountywideDialogue on Transportation:Project SelectionA Si...Continuation of CountywideDialogue on Transportation:Project SelectionA Si...
Continuation of Countywide Dialogue on Transportation: Project Selection A Si...
 
Reston Network Analysis: 2050 1st Tier Mitigation Results
Reston Network Analysis: 2050 1st Tier Mitigation ResultsReston Network Analysis: 2050 1st Tier Mitigation Results
Reston Network Analysis: 2050 1st Tier Mitigation Results
 
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor StudyFairfax County Parkway and Franconia-Springfield Parkway Corridor Study
Fairfax County Parkway and Franconia-Springfield Parkway Corridor Study
 
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal MobilitySouthrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
Southrun Road-2016 VDOT Repaving: Complete Streets-Improving Multimodal Mobility
 
Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016Reston Network Analysis Unmitigated Results: Jan.15, 2016
Reston Network Analysis Unmitigated Results: Jan.15, 2016
 
VDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives AnalysisVDRPT Route 1 Multimodal Alternatives Analysis
VDRPT Route 1 Multimodal Alternatives Analysis
 
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield DistrictProposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
Proposed Bicycle Facilities-VDOT Summer 2015 Repaving-Springfield District
 
Continuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on TransportationContinuation of Countywide Dialogue on Transportation
Continuation of Countywide Dialogue on Transportation
 
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
Dulles Metrorail Silver Line Phase 2: Fairfax County Parking Garages Herndon ...
 
I-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the BeltwayI-66 Multimodal Improvements Inside the Beltway
I-66 Multimodal Improvements Inside the Beltway
 
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
Reston Transportation Funding Plan: Community Meeting: Nov. 7, 2016
 
Dulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study InvestigationDulles Corridor Air Rights Study Investigation
Dulles Corridor Air Rights Study Investigation
 

Andere mochten auch

Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportFairfax County
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsFairfax County
 
Bi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County RoadsBi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County RoadsFairfax County
 
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Fairfax County
 
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Fairfax County
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax County
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Fairfax County
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementFairfax County
 
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Fairfax County
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Fairfax County
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare ProgramFairfax County
 
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Fairfax County
 
Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Fairfax County
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Fairfax County
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Fairfax County
 
Transportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyTransportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyFairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Fairfax County
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Fairfax County
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesFairfax County
 
Emergency Vehicle Preemption
Emergency Vehicle PreemptionEmergency Vehicle Preemption
Emergency Vehicle PreemptionFairfax County
 

Andere mochten auch (20)

Silver Line Phase 1 Status Report
Silver Line Phase 1 Status ReportSilver Line Phase 1 Status Report
Silver Line Phase 1 Status Report
 
Operational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to TysonsOperational Analysis of Dulles Toll Road Ramps to Tysons
Operational Analysis of Dulles Toll Road Ramps to Tysons
 
Bi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County RoadsBi-County Parkway: Evaluation of Impacts on Fairfax County Roads
Bi-County Parkway: Evaluation of Impacts on Fairfax County Roads
 
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
Citizens Information Meeting: Kirby Road Sidewalks: Nov. 9, 2016
 
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
Scotts Run Trail: Magarity Road to Colshire Meadow Drive Public Hearing: Nov....
 
Fairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory CommitteeFairfax Connector Riders Advisory Committee
Fairfax Connector Riders Advisory Committee
 
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
Discussion of Converting Braddock Road from a Secondary to Primary Road-Feb. ...
 
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework AgreementI-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
I-66 Inside the Beltway Initial Traffic Analysis and Framework Agreement
 
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
Reston Network Analysis: Existing Phasing Analysis and 2050 Tier 3
 
Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)Implementation of HB2 (2014) and HB 1887 (2015)
Implementation of HB2 (2014) and HB 1887 (2015)
 
Student Free Fare Program
Student Free Fare ProgramStudent Free Fare Program
Student Free Fare Program
 
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
Reston Transportation Funding Plan: Funding Scenarios Continued: Sept. 26, 2016
 
Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016Tysons Trails: Snow Removal & Lighting July 2016
Tysons Trails: Snow Removal & Lighting July 2016
 
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016 Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
Reston Network Analysis: Transportation Advisory Commission: July 19, 2016
 
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
Hunter Mill Road and Sunset Hills Road Study, Community Meeting #6: Nov. 17, ...
 
Transportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax CountyTransportation Services Group: Employer Services in Fairfax County
Transportation Services Group: Employer Services in Fairfax County
 
Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015Silver Line Update: Dec. 1, 2015
Silver Line Update: Dec. 1, 2015
 
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015Silver Line Update-Board Transportation Committee: Oct. 13, 2015
Silver Line Update-Board Transportation Committee: Oct. 13, 2015
 
Transportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future UpdatesTransportation Priorities Plan: Future Updates
Transportation Priorities Plan: Future Updates
 
Emergency Vehicle Preemption
Emergency Vehicle PreemptionEmergency Vehicle Preemption
Emergency Vehicle Preemption
 

Ähnlich wie Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update

Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Fairfax County
 
Funding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountyFunding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountySCVTA
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateAdina Levin
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentationSCVTA
 
VTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasVTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasSCVTA
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosFairfax County
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesFairfax County
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Fairfax County
 
Reston Transportation Service District FY 2019 Tax Rate Discussion
Reston Transportation Service DistrictFY 2019 Tax Rate DiscussionReston Transportation Service DistrictFY 2019 Tax Rate Discussion
Reston Transportation Service District FY 2019 Tax Rate DiscussionFairfax County
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax County
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Fairfax County
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumFairfax County
 
NIRPC Green Fleet: Funding Process for Transportation Projects
NIRPC Green Fleet: Funding Process for Transportation ProjectsNIRPC Green Fleet: Funding Process for Transportation Projects
NIRPC Green Fleet: Funding Process for Transportation ProjectsSouth Shore Clean Cities
 

Ähnlich wie Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update (20)

Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure F...
 
Funding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara CountyFunding Transportation Improvements in Santa Clara County
Funding Transportation Improvements in Santa Clara County
 
TPO FPC SMART BERT Funding Plan Presentation
TPO FPC SMART BERT Funding Plan PresentationTPO FPC SMART BERT Funding Plan Presentation
TPO FPC SMART BERT Funding Plan Presentation
 
TPO FPC SMART Presentation on Special Assessments
TPO FPC SMART Presentation on Special AssessmentsTPO FPC SMART Presentation on Special Assessments
TPO FPC SMART Presentation on Special Assessments
 
TPO FPC SMART Special Assessments Presentation
TPO FPC SMART Special Assessments PresentationTPO FPC SMART Special Assessments Presentation
TPO FPC SMART Special Assessments Presentation
 
Transit Network Plan Update and Financial Strategy
 Transit Network Plan Update and Financial Strategy Transit Network Plan Update and Financial Strategy
Transit Network Plan Update and Financial Strategy
 
Georgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure BankGeorgia Transportation Infrastructure Bank
Georgia Transportation Infrastructure Bank
 
Nov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule UpdateNov 14 - Caltrain Modernization Cost and Schedule Update
Nov 14 - Caltrain Modernization Cost and Schedule Update
 
Final 12 01 community mtg phase ii presentation
Final 12 01 community mtg  phase ii presentationFinal 12 01 community mtg  phase ii presentation
Final 12 01 community mtg phase ii presentation
 
VTA 2016 Measure B Program Areas
VTA 2016 Measure B Program AreasVTA 2016 Measure B Program Areas
VTA 2016 Measure B Program Areas
 
Reston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding ScenariosReston Funding Plan-Funding Scenarios
Reston Funding Plan-Funding Scenarios
 
TPO FPC SMART Financial Plan Framework presentation
TPO FPC SMART Financial Plan Framework presentationTPO FPC SMART Financial Plan Framework presentation
TPO FPC SMART Financial Plan Framework presentation
 
Transportation Priorities Plan Future Updates
Transportation Priorities Plan Future UpdatesTransportation Priorities Plan Future Updates
Transportation Priorities Plan Future Updates
 
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
Reston Funding Plan: Updates and Funding Scenarios - Aug. 8 & 10, 2016
 
SMART Plan Preliminary Financial Plan Options
SMART Plan Preliminary Financial Plan OptionsSMART Plan Preliminary Financial Plan Options
SMART Plan Preliminary Financial Plan Options
 
Reston Transportation Service District FY 2019 Tax Rate Discussion
Reston Transportation Service DistrictFY 2019 Tax Rate DiscussionReston Transportation Service DistrictFY 2019 Tax Rate Discussion
Reston Transportation Service District FY 2019 Tax Rate Discussion
 
Fairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for TransportationFairfax Commercial and Industrial Property Tax for Transportation
Fairfax Commercial and Industrial Property Tax for Transportation
 
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
Reston Transportation Funding Plan: Updates and Recommendations: Jan. 19, 2017
 
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond ReferendumTransportation Priorities: Project Timelines and the 2014 Bond Referendum
Transportation Priorities: Project Timelines and the 2014 Bond Referendum
 
NIRPC Green Fleet: Funding Process for Transportation Projects
NIRPC Green Fleet: Funding Process for Transportation ProjectsNIRPC Green Fleet: Funding Process for Transportation Projects
NIRPC Green Fleet: Funding Process for Transportation Projects
 

Mehr von Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementFairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxFairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19 Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction ProgressFairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxFairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxFairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilFairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptxFairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap UpFairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual ArtsFairfax County
 

Mehr von Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022Tucker Avenue Neighborhood Community Meeting, 03-15-2022
Tucker Avenue Neighborhood Community Meeting, 03-15-2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 

Kürzlich hochgeladen

VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012ankitnayak356677
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsnaxymaxyy
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendFabwelt
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkbhavenpr
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 

Kürzlich hochgeladen (10)

VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012VIP Girls Available Call or WhatsApp 9711199012
VIP Girls Available Call or WhatsApp 9711199012
 
Quiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the roundsQuiz for Heritage Indian including all the rounds
Quiz for Heritage Indian including all the rounds
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
Manipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpkManipur-Book-Final-2-compressed.pdfsal'rpk
Manipur-Book-Final-2-compressed.pdfsal'rpk
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 

Dulles Metrorail Silver Line: Status Report and Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update

  • 1. Dulles Metrorail Silver Line: Status Report & Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update Transportation Committee Fairfax County Board of Supervisors May 7, 2013
  • 2. Presentation Outline • Phase 1 Status Report • Phase 2 Status Report • Transportation Infrastructure Finance and Innovation Act (TIFIA) Funding Update • Recommendation of Preliminary TIFIA Allocation • Requirements from Funding Partners • Phase 1 Plan of Finance – Closeout • Staff Recommendations • Timeline 2
  • 3. Phase 1 – Status Report Construction: 90% Complete Final Design: 100% Complete Utility Relocation: 100% Complete Property Acquisition: All rights of entry obtained Track Work: 100% Complete Stations: • McLean – 80% • Tysons Corner – 75% • Greensboro – 65% • Spring Hill – 65% • Wiehle – 84% • First Delivery of Rail Cars – February 2014 • Wiehle Garage: 88% Complete • Garage Substantial Completions: July 19, 2013 • Roadway Improvements (ROD): 67% complete • August/September 2013 completion Status • • • • • • • Revised Budget Authorized: $2.905B • Expended to Date: $2.2B • County Phase 1 share: $467.8M • Tax District Funds: $400M (Funding Gap = $67.8M) • Fairfax County share of Project expenditures through fourth quarter 2012 = $369.1M • $150M received from Commonwealth Budget (as of April 24, 2013) • Substantial Completion: September 7, 2013 • WMATA Testing and Acceptance: August – December 2013 • West Falls Church Yard Completion: December 2013 • Sound Box and Tail Track: November 2013 • Estimated Passenger Revenue Service: December 31, 2013 Schedule • Entire 3rd Rail energized for Metrorail train testing. • Tunnel Clearance – No issues per WMATA • All five stations under construction with efforts on mechanical, electrical, plumbing, and station finishes • Phase 1 Maintenance and Land Conveyance process ongoing: • Fairfax County will retain ownership of Kiss and Ride at McLean • Fairfax County will operate through an easement Kiss and Ride at Spring Hill Station • Regional planning effort underway for Phase 1 bus service (Fairfax Connector, WMATA, Washington Flyer, PRTC, Loudoun Transit) • Fairfax County 2nd round of Public Meetings ongoing • Ask Fairfax online chat completed Current Milestones – Past 30 Days 3
  • 4. Phase 2 – Status Report • Packet A Price Proposals Opened – April 19, 2013 • Project estimate Packet A = $1.4B - $1.6B vs. $1.177B low bid • Positive impact on toll rates = $300M (est.) Status (as of April 24, 2013) Station included in Packet A bid. • County using its best efforts to mitigate some station costs on south side. (ROW, alternative site work funding, and improved site layout for: garage, bus bay, and kiss/ride design. ) Station cost will have to be funding either in part or whole per the funding agreement (County funding agreement share 16.1%). County also pursuing funding from TIGER Grants and NVTA Innovation Center (RT 28) Station • • • • Cost Estimate: $3.093B • Cost Estimate with value engineering and alternative funding for garages & Innovation Center Station: $2.7B • Cost to build garages in Fairfax County: $105M est. • Fairfax County share for Phase 2 ranges from $433M – $498M, Tax District capped at $330M Budget • Packet A Contract Award: May 2013 • Packet A Notice to Proceed: June 2013 • 5 Bid Packages: • Packet A - Rail Line, Station, and Systems (includes Innovation Center Station) • Packet B – Yard and Shop • Packet C (may not be issued) – Parking Garages • Packet D – ROW • Packet E – Utilities • Fairfax County working to fund & construct Herndon and Innovation Center garages outside of project • Financial Plan status: • Transportation Sub Committee May 7, 2013 • BOS May 14, 2013 • Substantial Completion: Summer 2018 • Revenue Operations: Late 2018 Schedule • FTA oversight of Phase 2 under discussion: Ongoing • TIFIA Letter of Interest submitted: Ongoing • WMATA Art in Transit: Selection: Ongoing • Reston Town Center Tunnel Design under review by WMATA and MWAA Current Milestones Past 30 Days 4
  • 5. Request Board Approval of Staff Recommendations • Approve the Preliminary TIFIA Allocation of $1.9b amongst the Funding Partners, with County to receive $475m • Approve the County Credit Pledge of the C & I Fund and the Phase 2 Tax District to TIFIA; Potential use of Moral Obligation from General Fund to meet AA Category Rating mandated from USDOT • Request Credit Ratings from the bond rating agencies to comply with TIFIA Credit Review ($90,000) • Approve the $100,000 down payment required from the County to move forward in the TIFIA Letter of Interest (LOI) review process • Review short term financing options to cover the $67m for balance of County contributions for Phase 1. This will be paid off with receipt of TIFIA funds 5
  • 6. Transportation Infrastructure Finance and Innovation Act (TIFIA) Status Update Recommendation of Preliminary TIFIA Allocation 6
  • 7. TIFIA Financing Overview • Federal credit assistance in the form of direct loans (not grants) to finance surface transportation projects of national and regional significance • USDOT Secretary LaHood departing & accelerated turnaround time for documents • Improved access to capital markets, flexible repayment terms, and potentially more favorable interest rates than can be found in private capital markets for similar instruments • Loan Repayment Deferral Option - 5 years after project completion (2023) • Alternatively – conduct open market bond sale & debt service payments immediately 7
  • 8. Silver Line Cost Allocation – Funding Partners Funding Partner Dulles Toll Road* % Share TPE Baseline 75% $ Share TPE Baseline Funding Partner Total (TPE Baseline + Garages) Other – Garages $4,262,763,750 - $4,262,763,750 Fairfax 16.1% 915,073,285 146,721,000 1,061,794,285 Loudoun MWAA – Aviation Funds 4.8% 272,816,880 168,413,000 441,229,880 4.1% 233,031,085 - 233,031,085 $5,683,685,000 $315,134,000 $5,998,819,000 Total 100.00% * Includes $900m from FTA New Starts (16.1%), $275m from Commonwealth (4.9%). Net to Dulles Toll Road is 54%. Allocation assumes the add’l $150m + $300m for Phase 2 will be used to pay interest on Dulles Toll Road Revenue Bonds, not direct project costs. 8
  • 9. Silver Line Total Project Estimate Fairfax County Costs 16.1% Phase 1 Total Baseline County Share @ 16.1% Less Tax Districts Net County due Phase 2 Total $2,905,685,000 $2,778,000,000 $5,683,685,000 467,815,285 447,258,000 915,073,285 (400,000,000) (330,000,000) (730,000,000) $67,815,285 $117,258,000 $185,073,285 $80,959,000* $80,959,000 65,762,000* 65,762,000 $146,721,000 $146,721,000 Garages Herndon-Monroe Route 28 Total Garages TOTAL (Baseline + Garages) $467,815,285 $593,979,000 $1,061,794,285 *Per 100% P/E and consistent with MWAA documents; County believes costs will be lower and in the process of a feasibility study 9
  • 10. TIFIA Allocation: Funding Partner Consensus • December 2012 – Per USDOT Project Will Remain Eligible for 33% TIFIA Loan or $1.9b ($5.9b * 33%) Funding Partner Fairfax Funding Partner Total Project Cost TIFIA Allocation $1,061,794,285 $475,000,000 Loudoun 441,229,880 200,000,000 MWAA – Aviation Funds 233,031,085 - Dulles Toll Road Total 4,262,763,750 $5,998,819,000 1,304,610,270 $1,979,610,270 • Meets MWAA goal of $1.2-$1.4b for the Toll Road • Counties maintain equity of TIFIA allocation equal to 45% Total Project Cost 10
  • 11. TIFIA Premium Projections A Funding Partner Fairfax Loudoun B USDOT Requested Minimum Credit Rating AA Category AA Category Investment Grade Dulles Toll Road (BBB Category) Total C D E (C * D) Anticipated TIFIA Premium TIFIA Allocation* USDOT Premium Subsidy Allocation 2% $475,000,000 $9,500,000 2% 200,000,000 4,000,000 12% 1,304,610,270 156,553,232 $1,979,610,270 $170,053,232 Premium allocation evaluated/ reviewed heavily by TIFIA office when awarding project funding * Assumes MWAA Aviation Funds receive no TIFIA Loan 11
  • 12. TIFIA Status Update – Requirements from Funding Partners 12
  • 13. TIFIA Financing • Competitive Interest Rates that correlate to 30-Year Treasury Note • Flexible call options - prepay outstanding principal • Potential future refunding opportunities • USDOT Expected Ratings from Funding Partners • AA Category Rating from Counties • Investment Grade from Dulles Toll Road (MWAA) • Pledge two County sources for Plan of Finance • Commercial and Industrial Tax Fund • Dulles Rail Phase 2 Tax District ($330 million) • May be required to include Moral Obligation of the County General Fund if AA Category Rating is not achieved 13
  • 14. USDOT Information Request – April 2013 • Complete County Plan of Finance for TIFIA • Commercial and Industrial Tax Fund • Dulles Rail Phase 2 Tax District ($330 million) • Indicative Rating Letter on the TIFIA Loan • USDOT EXPECTS Counties to achieve rating in the AA Category • Initial review from the Credit Rating Agencies ($90,000) • Feasibility Study for Each Source of Credit Pledged • MWAA Toll Road Study • Counties expected to submit standard information: tax assessment, economic, and demographic information • Credit Processing Down Payment of $100,000 from each funding partner 14
  • 15. County Plan of Finance for TIFIA Commercial & Industrial Tax Fund • Tax Rate of 12.5 cents per $100 of AV & generates approximately $51m revenue annually • Previously recommended to finance County project costs outside of the two tax districts: Phase 1 ($67.8m) & Phase 2 ($117.3m) • Planning Guideline for Long Term Forecasting: • 50% of expenses for Tysons / Silver Line • 50% of expenses for Remainder Countywide Projects • Loan Repayment Deferral Option - 5 years after project completion (2023) • Redirect previously forecasted monies required for debt service to fund other Countywide projects (equates to approximately $70m total from 2014-2023) 15
  • 16. County Plan of Finance for TIFIA Phase 2 Tax District $330 million • Estimated stand alone current rating of this district likely “A” Category, thus enhancement necessary • Comparative Assessed Value 1/1/13: Phase 1 $11.4b vs. Phase 2 $7.5b • Allow for growth district tax base / assessed value, similar to Phase 1 Tax District • Phase 2 Tax Rate – 20 cents for FY 2014 • Initially began at 5 Cents in FY 2011, with 5 cent laddered increases • Remain at this rate until rail service begins 2018, then ability to increase to 25 cents per Petition • Accumulation of tax collections to provide for early repayment of outstanding principal at regular intervals • Staff recommendation that C & I Fund be used back this Tax District for credit enhancement • General Fund Moral Obligation may be needed to reach AA Category if C & I Fund insufficient 16
  • 17. Financing Dulles Rail - Alternate Options Public Sector Sources General State/Feder Fund (Pay al Funding Go) Cost of Financing / Carrying Cost (Lowest to High) ■ Length of Time to Accrue Funds (Sooner to Later) • General Fund Impact (Low to High) Impact on Redevelopment (Low to High) Impact to G.O. Debt (Low to High) Ability to Meet Capital Requirements (High to Low) Requires Third Party Concurrence (Degree of Difficulty) ■ ♦ ■ • • ■ G.O. Bonds C&I Funds ■ ♦ ♦ ■ ■ ♦ ■ ■ ■ ■ ■ ♦ ♦ ♦ Low Impact and/or Most Beneficial ♦ ♦ ■ ♦ ■ ♦ ♦ ♦ Meals Tax (Pay Go) ■ ♦ ■ ■ ■ ■ • Private Sector Sources 100% TIF Service Developer Capped TIF District /CDA Contributions • • ♦ ■ ♦ ♦ ♦ ■ ■ ♦ ■ • • ■ ♦ ■ ■ ■ ■ ♦ • • • ■ ■ ■ ■ Medium Impact and/or of Concern Other Potential Funding Options: NVTA & Federal TIGER Grants • • High Impact and/or Most Difficult 17
  • 18. Fairfax County Portion Remaining Dulles Rail Financing Phase 1 Total Project Estimate (TPE) County Share @ 16.1% Less Tax Districts Net County due Total County Remaining Financing Needed *paid to date to MWAA Phase 2 Total $2,905,685,000 $2,778,000,000 $5,683,685,000 467,815,285 447,258,000 915,073,285 (400,000,000*) (330,000,000) (730,000,000) $67,815,285 $117,258,000 $185,073,285 $67,815,285 $447,258,000 $515,073,285 18
  • 19. Fairfax County Cashflow Remaining Dulles Rail Financing Source Funds Amount Source Debt Service Comment TIFIA $67.8m C & I Fund TIFIA $117.3m C & I Fund Phase 2 costs beyond $330m from Phase 2 Tax District (2013-2018) TIFIA $289.9m Phase 2 Tax District 88% of Phase 2 Tax District’s $330m (2013-2018) Total TIFIA $475.0m 45% Total County Project Cost Phase 2 Tax District Bond Sale or Cash Total Remaining Financing $40.1m Phase 2 Tax District $515.1m Balance Phase 1 costs beyond $400m from Phase 1 Tax District; TIFIA may be used to repay short term financing (2013) Phase 2 Tax District Bond Sale or Cash Contribution (2018) 19
  • 20. County Phase 1 Cost - $467m • Phase 1 Tax District fulfilled $400 million obligation • Establish a plan of finance to cover remaining $67m to close out the County’s Phase 1 contributions • TIFIA Funds are not expected until end of the Calendar Year 2013 at the earliest • County Staff and Financial Advisor review of short term financing options to address the $67m: • Use portion of County’s current $100m Line of Credit • Bond Anticipation Note (BAN) • Staff recommendation: Utilize the Line of Credit & then pay off from receipt of TIFIA funds. 20
  • 21. Recommendations – Consistent with May 14th Board Item • Approve the Preliminary TIFIA Allocation of $1.9b amongst the Funding Partners, with County to receive $475m • Approve the County Credit Pledge of the C & I Fund and the Phase 2 Tax District to TIFIA • Goal to receive AA Category Rating and assumes no Moral Obligation • Phase 2 Tax District to utilize $290m of Preliminary TIFIA & seeking Moral Obligation (e.g. Credit Enhancement) from C & I Fund • Request Credit Ratings from the bond rating agencies to comply with TIFIA Credit Review ($90,000) • Approve the $100,000 down payment required from the County to move forward in the TIFIA LOI review process • Review short term financing options to cover the $67m for balance of County contributions for Phase 1. This will be paid off with receipt of TIFIA funds 21
  • 22. Timeline Date Item October 2012 MAP-21 Revised TIFIA Loan Notification (33% to 49%) October 2012 Funding Partners Submits LOI USDOT TIFIA (@ 49%) December 2012 TIFIA request to Funding Partners for more information January 2013 Funding Partners discussion on TIFIA Allocation April / May 2013 MWAA Awards Phase 2 Design-Build Contract May 2013 Board Discussion on TIFIA Allocation May 2013 Discussion with Bond Rating Agencies on County Credit for TIFIA May 2013 Submit County materials to TIFIA Summer 2013 County Interim Financing to cover balance of Phase 1 costs December 2013 Targeted Closing on TIFIA Loan for Funding Partners December 2013 Begin Service for Phase 1 Spring 2014 Refinance Interim Financing for balance Phase 1 costs December 2018 Begin Service for Phase 2 22