SlideShare ist ein Scribd-Unternehmen logo
1 von 42
Downloaden Sie, um offline zu lesen
Natural Power Consultants LTD
Eversheds, Institutional Investor workshop
2nd July 2012
TABLE OF CONTENTS



  1. Natural Power Consultants
  2. Capex comparative analysis
  3. Offshore WTG technology
  4. Foundations
  5. Cables
  6. Installation




Tuesday, July 03, 2012   2
NATURAL POWER CONSULTANTS




Renewable energy consultancy, management                   •   Energy yield analysis and technical risk reduction
services and product innovation.
                                                           •   Project design, ecology surveys, EIA and
                                                               permitting management
Onshore wind, Offshore wind, Wave & Tidal and
Biomass energy                                             •   Construction, ground surveys and contracts
                                                               management

Founded in 1996       300 Employees       14 Offices   7   •   Operational A&M and performance analysis
Countries
                                                           •   360o project due diligence

                                                           •   Owner and Lender’s Engineering & Technical
                                                               Advisors


        Tuesday, July 03, 2012        3
CAPEX COMPARATIVE ANALYSIS1

M£/MW
  4.00

  3.50
                                                         3.40              3.46              3.42         3.30
  3.00                                 3.05
                     2.76
  2.50

  2.00

  1.50

  1.00

  0.50

  0.00
               2006              2007              2008               2009             2010            2011

   Natural Power data base of 49 OWF, in 7 European countries


 • From 2006 to 2009 Capex (M£/MW) has grown, the increase has been
 driven by cables and foundations costs, in 2010 Capex started to come down

 • Key factors: distance from the shore, supply bottlenecks, raw materials,
 installation costs, cable routes

  1. Capital expenditures have been collected from our confidential data base, reinforced with trade
  journals, company websites, public data bases and academic and government reports
                  Tuesday, July 03, 2012                          4
OFFSHORE WIND TURBINE TECHNOLOGY

   After 3-4 MW before 2009, the technology is being oriented to 5-6 MW turbines

         Suppliers are now working on:
                  Reducing the weight with less components (DD or semi-integrated solutions), in order to ease foundation design,
                  installation and maintenance
                 Larger diameters (150-164 m) with same power output




         Blades :
                   Diameter is increasing from ac. 90 m (2009 ) to 164 m (2015)
                   Higher bending moment due to larger rotor affects design of the substructure
                   Blades suppliers are now mostly in-house (Siemens, Vestas, Repower, Areva)


         Generator technology :
                   Power output from 3-4 MW (2009) to 5-6 MW (2012-2014)
                   Smooth transition from DFIG to DD generators (head mass reduction/power output management)
                   Gearboxes tend to be removed to reduce maintenance and failures
                   Use of permanent magnets leads to high risks on Neodymium supply chain




          Tuesday, July 03, 2012            5
WTG SUPPLY AND INSTALLATION

Market shares – Turbines suppliers                  Number of suppliers for the 6 MW+ will
% MW installed to date – source EWEA January 2012   increase

                                                     Areva, REpower are the only leaders with 5-6 MW
                                                     WTGs but with still a low track record

                                                      Historical suppliers have delayed their entrance in
                                                     this category: Siemens 6 MW focuses on a DD
                                                     technology, diameters 120 -154m and 50% fewer parts
                                                     than comparable geared WTG; serial production
                                                     targeted for Q1 2015, Vestas V164-7.0 MW prototype
                                                     has been postponed, the first turbine is scheduled for
                                                     installation in 2013, with series production starting
                                                     from 2015

                                                     New entrants in Europe (Alstom “pure torque” DD
                                                     6MW Halliade 150, Gamesa G128-5.0 MW) will be in
                                                     competition with Asian suppliers (Golwind, Sinovel)

                                                     Before new entrants will start to produce, the
                                                     offshore WTG industry will remain a bottleneck in the
                                                     supply chain




          Tuesday, July 03, 2012              6
OFFSHORE FOUNDATION


Market shares – Foundations installed in 2011   Monopiles is the most installed typology of
% MW installed – source EWEA January 2012
                                                foundation


                                                Wind farms currently under construction show the
                                                same trend: monopiles maintaining an over 60%
                                                share


                                                Jackets and Tripods show similar shares (20% and
                                                18% respectively)


                                                Currently, no gravity based foundations have been
                                                identified in the under construction pipeline. This
                                                structure is generally used in wind farms close to
                                                shore




      Tuesday, July 03, 2012                7
MONOPILES’ ISSUES




• Monopolie made for: soft seabed, up to medium water depth, up to medium
WTG weight (e.g. the actual monopile designed to support 6.0MW WTG vary
from 6.5m to 7m in diameter)

• Grouted connection: 65% of all the monopile installed in UK is facing problems
subjected to a complex state of stress

• Installation (mechanical hammer vs drilling): insufficient wind industry
experience to guarantee required pile verticality of <0.25° (bolted flange
requirement) during driving operations.

•Few players represent a bottle neck in the supply chain
          Tuesday, July 03, 2012           8
FOUNDATIONS: NEW TRENDS

                   Jacket                                  Gravity Base




Emphasis on cost of fabrication:            Emphasis on:

• use of materials                          • noise emission to avoid limitation
• pre-assembled manufacturing process       during installation
                                            • transportation


          Tuesday, July 03, 2012        9
OFFSHORE CABLE TECHNOLOGY

                                          Ex Cable Supply                                                 Copper price 2009 -2012
                0.90
                0.80
                0.70
Cost in M£/Km




                0.60                    0.53
                0.50
                0.40                                                        Market Players
                0.30
                                                                            Market Average
                0.20
                0.10
                0.00
                       0      50       100          150    200        250
                                   Ex Cable lenght in Km


                                        Array Cable Supply
                                                                                             Main issues:
                0.35
                0.30
                                                                                             • Cable Laying: regulation, and natural condition (e.g. salt
Cost in M£/Km




                0.25
                                                                                             marsh)
                0.20                         0.20
                0.15                                                        Market Players   • Supply chain bottlenecks: reluctant cable makers to
                0.10                                                        Market Average   scale up manufacturing capacity
                0.05
                                                                                             • Scarcity of skilled personnel
                0.00
                       0        50           100          150         200
                               Array Cables Lenght in Km

                       Tuesday, July 03, 2012                    10
INSTALLATION




Latest trends:

• Players are developing vessels (e.g. Nordic Yards), which
can install every type of foundations, towers, nacelles
and turbines as a single unit

• In order to reduce installation time and costs, the
vessels are designed to deploy the whole wind turbine in
an upright position




 Tuesday, July 03, 2012           11
INSTALLATION RATE

                             Offshore Wind Farm WTG Installation Rate                                            Offshore Wind Farm Foundation Installation
                        10                                                                                                         Rate
                                                                   1 vessel                                                                             1 vessel
                                                                                                              9.00




                                                                               Inst. Rate (days/foundation)
                         8                                                                                    8.00
Inst. Rate (days/WTG)




                                                                   2 vessels
                                                                                                              7.00                                      2 vessels
                         6                                         Average 1                                  6.00
                                             5.7
                                                     4.8           vessel                                     5.00                4.44
                                                                                                                                                        Average
                         4                                         Average 2                                  4.00                                      Mopopile 1
                                                                   vessel                                     3.00                                      vessel
                                                                                                                                         2.75
                         2                                                                                    2.00                                      Average
                                                                                                              1.00                                      Mopopile 2
                         0                                                                                                                              vessels
                                                                                                              0.00
                             0               50             100                                                      0             50           100
                                         N. of WTG                                                                         N. of foundations

                  Main observations:

                  • No trend, scattered results

                  • Main drivers: weather and sea conditions, water
                  depths, integration of services, cost reduction, crane
                  capacity




                        Tuesday, July 03, 2012         12
THANK YOU FOR YOUR ATTENTION




Tuesday, July 03, 2012      13
Offshore Wind in UK –
Funding Round 3
June 27, 2012
Agenda



       Funding requirement in UK

       Conditions for investment

       Funding sources

       Utilities and other investors

       Investor models

       Conclusions




    2
Siemens is market leader in offshore turbines with
2.5 GW installed, of which nearly 1 GW in UK


Burbo Banks, UK                                      Vindeby, DK
→ 25 x SWT-3.6-107 (2007)                            → 11 x 0.45 MW (1991)

Lynn / Inner Dowsing, UK                             Middelgrunden, DK
→ 54 x SWT-3.6-107 (2008)                            → 20 x SWT-2.0-76 (2000)

Gunfleet Sands, UK                                   Samsø, DK
→ 48 x SWT-3.6-107 (2009)                            → 10 x SWT-2.3-82 (2002)

Rhyl Flats, UK                                       Rønland, DK
→ 25 x SWT-3.6-107 (2009)                            → 4 x SWT-2.3-93 (2002)

Walney, UK                                           Rødsand/Nysted, DK
→ 51 x SWT-3.6-107                                   → 72 x SWT-2.3-82 (2003)
→ 51 x SWT-3.6-120
                                                     Frederikshavn, DK
Pori, FIN                                            → 1 x SWT-2.3-82 (2003)
→ 1 x SWT-2.3-101 (2010)
                                                     Horns Rev II, DK
Baltic I, DE                                         → 91 x SWT-2.3-92 (2009)
→ 21 x SWT-2.3-93 (2010)
                                                     Rødsand II, DK
                                                     → 90 x SWT-2.3-93 (2010)

                                                     Lillgrund, SE
                                                     → 48 x SWT-2.3-93 (2007)

                                                     Hywind, NO
                                                     → 1 x SWT-2.3-82 (2009)

Source: SWP
 3
Many projects to come, some with Siemens equity



 Greater Gabbard, UK                              Anholt, DK
 → 140 x SWT-3.6-107                              → 111 x SWT-3.6-120

 Sheringham Shoal, UK                             Baltic 2, DE
 → 88 x SWT-3.6-107                               → 80 x SWT-3.6-120

 London Array, UK                                 Borkum Riffgat, DE
 → 175 SWT-3.6-120                                → 30 x SWT-3.6-107

 Lincs, UK                                        Dan-Tysk, DE
 →69 x SWT-3.6-120                                → 80 x SWT-3.6-107
 →25% Siemens Project Ventures
 (Centrica 50%, Dong 25%)                         Borkum Riffgrund 1, DE
 Gwynt Y Mor, UK                                  → 77 x SWT-3.6-120
 →160 x SWT-3.6-107
 →10% Siemens Wind Power (RWE                     Meerwind Sud Ost, DE
 60%, SWM 30%)                                    → 80 x SWT-3.6-120

 West of Duddon Sands, UK
 → 108 x SWT-3.6-120

 Teesside, UK
 → 27 x SWT-2.3-93


Note: SPV also own 50% of Smart
Wind consortium with Mainstream
Renewables, developing UK Round 3                 Rudong Intertidal, CHN
Hornsea zone (4 GW). First GW                     → 21 x SWT-2.3-101
being developed with Dong.
 Source: SWP
 4
Offshore Wind Roadmap and Funding
Requirement

                                                     18 GW by 2020 under
                                                     DECC Roadmap

                                                     £8-10bn annual funding
                                                     required

                                                     Based on £3m/MW
                                                     capex, straight line roll
                                                     out from 2015, excludes
                                                     OFTOs and capital
                                                     recycling

                                                     Depends on build out
                                                     which should generate
                                                     economies of scale to
                                                     lower construction costs
Source: DECC UK Renewable Energy Roadmap July 2011

 5
Conditions for investment



       Utilities cannot finance construction of Round 3
        on their own and need to tap new investors
        and banking market

       Conditions for entry of new capital

           Revenue certainty (FITs, ROCs)
           Regulatory certainty (EMR, OFTOs)
           Profitability & risk adjusted returns
           Visibility on long-term market growth
           De-risking projects
           Stable macroeconomic climate




    6
Funding Sources in Offshore Wind Development Cycle



                                                  Point in time – decreasing risk and required return over project life cycle
Project risk




                               Development                             Pre-construction
                                                                    (c.24+ months c.£50-                    Construction                     Operation
                        (c. 48+ months, c£10-50m)
                                                                            200m)                     (c. 24+ months, c£1Bn)               (c. 20+ years)
                                                                   • Turbine order                •    Civil construction              • O&M + Warranty
                   •   Site search                                 • Balance of plant             •    BOP                             • Zero emission cash
                   •   Feasibility study                             (BOP) Long-lead              •    Turbine
                   •   Environmental studies                          items                       •    Grid connection
                   •   Licenses (production / installation)        • Design
                   •   Permits                                     • Met mast
                   •   Land lease                                  • Geotech
                   •   Commitment to grid                          • Grid connection




               Funding source                    Development                  Pre-construction / Construction                              Operation

                                                                                                                                 Utilities, Infrastructure Funds,
                                           Utilities, Venture Capital,     Utilities, Oil & Gas Cos, Private Equity,
                       Equity                                                                                                   Direct Financial Investors, Public
                                                    Developer                               Contractors                                  Equity Markets
                                                                                Project Finance with Sponsors,                    Debt Capital Markets, Utility
                   Senior debt                   Not available
                                                                                   Multilateral & ECA support                   Bonds, Govt Sponsored Bonds

               7
Utility Investors



       UK projects have historically been developed by utilities in contrast to
        Continental Europe where independent developers are more prevalent

       UK projects have generally been financed by utilities on balance sheet
        unlike Continental Europe where limited recourse project finance is
        more common. Utilities don’t like project finance as it is expensive and
        often treated as on balance sheet by rating agencies

       Utilities have to find alternative funding sources if they want to maintain
        ratings & preserve dividends. They are forming partnerships with other
        utilities and new types of investors to share funding and risks

       We estimate of total annual capex of 10 largest European utilities
        of €40bn about €10bn could go to offshore wind with maybe half of this
        allocated to UK

    8
R3 Funding Sources

                     12.000



                     10.000
                                                                        Estimated annual construction
                                                                        costs of £8-10bn
                         8.000                                          High case – 75% total
£ million per year




                                                                        offshore wind budget
                                                                        allocated by European
                         6.000                                          utilities to UK ; £1.4bn l/r
                                                                        equity; £2.1bn l/r debt
                                                                        Base case – 50%; £1bn l/r
                         4.000                                          equity, £1.5bn l/r debt
                                                                        Low case – 30%, £0.6bn l/r
                                                                        equity; £0.9bn l/r debt
                         2.000

                                                                           Utility balance sheet
                            0                                              Ltd recourse equity
                                 High case   Base case   Low case                                       Source: Siemens
                                                                           Ltd recourse debt


                     Majority of funding from utility balance sheets unlevered
                     Balance from limited recourse equity (40%) and debt (60%)
                     More utility funding available → more other funding likely to be available
                     Additional funding from capital recycled from operational projects not shown
                     9
Other Investors



• Financial/private investors
      •Private equity / infra funds – SPV / Blackstone / Ampere / Marguerite / Ventizz
      •Private investors – Colruyt / Kirkbi Group / Oticon Foundation
      •Pension funds – Pension Danmark / PKA / PGGM
      •Japanese trading houses – Marubeni
      •Sovereign wealth funds – Masdar

• Strategic investors
      • Oil & gas companies – Statoil / Repsol
      • EPC companies – Fluor / Strabag / Hochtief

• Financial/private investors generally have limited appetite for construction
  or development risk but there are exceptions:
      • Masdar / SPV / Blackstone / Colruyt / Marguerite / Ventizz
• EPC companies often take development risk and then sell permitted project
  before construction
 10
Co-Funding Model



 Costs shared but project risks stay with utility
 Sale of minority stakes to private investors
      Operating assets
      Assets in construction with EPC wrap
 De-risking
      Opex
      PPA
      Bridge financing
 Stakes sold for premium due to risks assumed by utility
 Investments stay on balance sheet of utility
 Examples: various deals involving Dong

11
Limited Recourse Model – Project Finance



 Limited recourse financing by investors
 Banks take construction risk
      Common in Germany and Benelux, but not in UK
      Lincs is first UK PF deal with construction risk
 Banks requirements
      Higher pricing
      Significant contingency
      Debt reserve accounts
      Lower gearing and high coverage ratios
 Support from multilaterals/development banks and ECAs
 Examples: Lincs (Centrica/Dong/SPV); Meerwind (Blackstone)

12
Limited Recourse Model – Minority Stakes



 Limited recourse financing of acquisition of minority stakes by investors
 Banks do not take construction risk
 Same guarantees as under Co-Funding model
 Issues for banks
      Limited step-in rights
      No direct security over operating assets/contracts
      Change of control
      More equity required
 Support from multilaterals/development banks and ECAs
 Example: Gunfleet Sands (Marubeni)



13
Conclusions


    Utilities will play lead role in funding Round 3, but balance sheet
     pressure means they will not be able to do this alone

    Utilities are setting up JVs with other utilities & investors to share
     funding & risks. Dong leading way bringing in new investors

    New investors will require revenue and regulatory certainty, improved
     profitability, project de-risking & stable macroeconomic conditions

    Most financial investors currently have limited appetite for construction
     risk, but there are exceptions

    Limited recourse lending by commercial banks and public financing
     institutions will be critical, both at the project level and the financing of
     minority stakes in projects


    14
Thank you

Peter Weston
Global Head of Finance & Investment
Siemens Wind Power
+44 7808 824 390
peter.weston@siemens.com




Global Wind Power Finance & investment Congress
June 26-27, 2012, London
Morgan Stanley

Institutional Investors Workshop

July 2, 2012
Morgan Stanley Project Finance Transactions


Power               Approx. $300 MM         $740 MM              $45 Bn            $740 MM                 $11 Bn               $1.65 Bn             $950 MM               $950 MM


                     West Deptford                                                MACH Gen
                       Project

                    Construction/Term      Construction        Acquisition           Debt               Construction           Acquisition             Debt               Acquisition
                       Financing            Financing          Financing          Refinancing           Refinancing            Financing            Refinancing           Financing
                      November 2011          May 2008         February 2007       February 2007           June 2006             March 2006         September 2005        September 2005




Natural Resources       $750 MM              $300 MM           $240 MM              $1 Bn                 $900 MM               $240 MM              $1.55 Bn              $378 MM


                                                                                         EGPC                   EGPC                                         EGPC                   EGPC


                        Drillship              FPSO               Debt           Receivables          Pre-Export Credit        Acquisition
                       Financing             Financing         Financing         Monetization              Facility            Financing         FSA Monetization      FSA Monetization
                       March 2012          November 2011        June 2011        December 2010           October 2009                               February 2006          July 2005
                                                                                                                                June 2007




Infrastructure          $600 MM              $1.3 Bn            $100 MM            $494 MM                $213 MM               $162 MM                $1Bn                  $1Bn


                                                                                                                                                                       HANGZOU RING
                                                                                                                                                                          ROAD
                      Infrastructure       Construction         Railway       Lease Securitization
                        Financing           Financing          Financing           April 2007        Toll Road Financing   Toll Road Financing   Railroad Financing   Toll Road Financing
                      November 2010         March 2010         October 2007                              August 2006          February 2006        December 2005         December 2005




Renewables              $290 MM              $466 MM           $319 MM              10-Year               $200 MM               10-Year             $117.5 MM              $132 MM

                     Canadian Hills      Arlington Valley                                              Loraine Wind
                      Wind Project       Solar Energy II                                                  Project

                      Construction      Construction / Term                                             Wind Equity                                Construction          Construction
                                                              Construction    Commodity Offtake                            Commodity Offtake
                       Financing            Financing          Financing         Provider               Investment            Provider              Financing             Financing
                      March 2012            January 2012      December 2011      December 2011          February 2010           July 2009             July 2009           August 2008




                                                                                                                                                                                            2
Financing Sources For Greenfield Offshore Wind
                                                     Past Projects and Projections Bloomberg New Energy Finance
                                                                       Projections:


  Annual Investment                                 Annual Investment in Offshore Wind
  2012-2020                                         By Year of Commissioning and Investor Type; 2012–2015 by Existing Commitments and 2016–2020 Forecast
  Country                                € Bn       € Bn
  Germany                               39.2
                                                                     5.6            10.2                 13.8            14.2               12.3         14.4                16.1              18.6                 21.3
                                                      100%
  UK                                    38.6
                                                                      0.7            1.2
  France                                18.8                                                                                                 2.2         2.6                 2.8                3.1                 3.8
                                                                                                         3.5             3.2
  Belgium                                 6.6                         0.4            1.0

  Denmark                                 3.9          80%                    0.1
                                                                                              0.1
                                                                      0.2            0.4
  Netherlands                             3.5                                                 0.3
                                                                      0.4                                                                    2.7
                                                                                     0.3                                                                 3.9
  Rest of EU                            16.3                                                                             3.2                                                 5.2
                                                                                     0.9                 3.2                                                                                    7.1
  Total                               126.9            60%                                                                                   0.3
                                                                                                                                                                                                                    9.0
                                                                      1.0
  Sources Bloomberg New Energy Finance; Rabobank                                                                                                   0.1
                                                                                                                                             0.3
                                                                                                                         0.1                             0.3
                                                                                                                                 0.1                             0.1
                                                                                                                                                   0.4   0.4
                                                                                                         0.3
                                                                                                                   0.2                                                       0.3
                                                                                                                                                                 0.4                0.1
                                                                                                                   0.5                                                       0.5
                                                                                                         0.3                                 1.8                                                0.3
                                                                                                                                                                             0.4                          0.1

• Q: Do you believe that                               40%
                                                                                                         1.3             4.0
                                                                                                                                                         2.0
                                                                                                                                                                                                0.4
                                                                                                                                                                                                          0.7
                                                                                                                                                                                                                    0.3    0.1
                                                                      1.6                                                                                                    2.0                                           0.9
  Multilateral agencies will                                                                                                                                                                                        0.4
                                                                                                         0.7                                 1.3                                                2.1
  provide an aggregate value                                                         6.1
                                                                                                                                                         1.7                                                        2.1
  of €22Bn in capital over the                                                                                                                                               1.9
  next 8 years?                                        20%                                                               1.3                                                                    2.3
                                                                                                                                                                                                                    2.6
                                                                                                         3.9
                                                                                                                                             3.2
                                                                      1.2                                                                                3.1
                                                                                                                                                                             2.8
                                                                                                                         2.1                                                                    2.5
                                                                                                                                                                                                                    2.1

                                                        0%
                                                                     2012           2013                2014             2015               2016         2017                2018              2019                 2020


                                                         Equity-Primary Utility            Equity-Secondary Utility             Equity-Developer         Equity-IPP                 Equity-Institutional Investor

                                                         Equity-WTG                        Equity-Private Equity                Debt-Commercial          Debt-Multilateral



                                                   Sources Bloomberg New Energy Finance; Rabobank




                                                                                                                                                                                                                                 3
Banks Project Finance Participation
                                       Glass Half Empty Or Full?


• Q: Do you believe that               Banks in Project Finance Offshore Wind Transactions
  commercial banks will                Number of Transactions
  provide an aggregate value
  of €35Bn in capital over the     1                                                   12                                                   12
  next 8 years?
  – Average of ~€4.5Bn per         2                                    7                                                                   19
    year
                                   3                        4                                                                               23
• Approximately 70% of bank
  lenders into the offshore                                                                                                                 24
                                   4        1
  wind sector have only
  participated in 2 transactions
                                   5        1                                                                                               25

• Alternatively, could argue
  that banks with 2+               6        1                                                                                               26
  transactions makes ‘a
  knowledgeable market’            7        1                                                                                               27
  – 16 banks
                                   8        1                                                                                               28
• Even assuming
  ‘knowledgeable market’               0                    2               4          6               8               10              12
  doubles to 32 banks, a
  €4.5Bn average capital
  requirement would require an         “Our discussions with industry participants suggest there are around 15-20 commercial lending
  average ticket size of               banks currently active in offshore wind financing, and that there is appetite to fund €2-2.5Bn of
  approximately €140MM per             projects per year”
  bank                                 Morgan Stanley Equity Research
  – Concentration concerns?


                                                                                                                                            4
Institutional Investors as Debt Capital Providers


• Pension funds have played a       • Renewable sector: interest by institutional debt investors in European renewable sector is increasing,
  role in investing in the equity     however it is still early stages
  of offshore wind projects          – Several funds have dedicated pools of capital for infrastructure investment, which includes
                                       renewables
• Given the scale of the             – Judgment based upon limited transaction flow and unhelpful precedents (i.e. Breeze) and stability of
  anticipated build out, expect        regulatory regimes
  that the institutional debt
  capital markets will play         • Favourable markets: offshore wind predominately located in “core” Northern European markets
  some role
  – Likely only when                Investor Concerns – Not Unsurprising
    operational
                                    • Business model - Future incentive / regulatory support risk
                                    • Technology risk: evolving so why invest now?
                                    • Resource risk
                                     – Weather risk (“black swan” winter storm damaging turbines)


                                    How / When To Invest?
                                    • Unlikely that institutional investors would be willing to take construction risk of an early stage
                                      technology without sufficient guarantees or a wrap from an independent party
                                     – Renewable wind power not currently permitted under EU/EIB Project Bond Initiative
                                     – Investment grade?
                                    • Initially, expect that construction financing will be provided by banks with a potential bond takeout
                                      post-construction
                                    • In line with broader European PF bank market, which we expect will morph towards a more formal
                                      mini-perm structure
                                                                                                                                               5
Offshore Wind Financing Strategies

Current Developer / ‘IPP’ Model                        Future Utility Model?

                                              Asset
                                                         Debt

  Export Credit                                          Equity/Cash
                                     Debt                                                          Asset
  Agencies
                                                         Utility
  Commercial Banks                                                                         Equity (50% +/-)


                                                         3rd Party Equity                  Equity (50% +/-)
  Sponsor(s)                         Equity
                                                         Investors

                                                                                           Debt



 • No “On” vs. “Off” balance sheet considerations       • Depending on equity investor / structure, debt
                                                          consolidation could be relevant to Utilities
 • Rating agencies (or public ratings) not necessary
                                                        • As Utilities expand their offshore wind portfolios,
 • Continued appetite of the ECAs / commercial
                                                          additional debt burden puts pressure on balance
   banks critical for this funding approach
                                                          sheets and ratings
                                                         –While selling down an equity stake recycles
                                                          capital to allow for further development, it may
                                                          not reduce the Utility’s debt burden




                                                                                                                6
Industry Wide Financing Solution?
                         Legal / Ownership Likely to Pose Problems




                  Utility 1             Utility 2                Utility 3           Other



                        [X]%                  [X]%                    [X]%        [X]%

            FiT
Utility 1


            FiT
Utility 2                                                                    Debt Proceeds
                                                                                                 Banks / Institutional
                                                     IssuerCo                  Security              Investors
            FiT
Utility 3


            FiT
 Other




                  Utility 1                          Utility 2                       Utility 3
                   Asset                              Asset                           Asset




                                                                                                                         7
Institutional Investors Workshop
2 July 2012
Ryan Trow
Forewind

           • Forewind is a consortium comprising four leading international
               energy companies: RWE, SSE, Statoil, and Statkraft.




           • The consortium members joined forces to bid for the Dogger Bank
               Zone Development Agreement as part of The Crown Estate’s third
               licence round for UK offshore wind farms (Round 3) in 2010.
           •   Forewind combines extensive experience of international offshore
               project delivery and renewables development, construction, asset
               management and operations, with UK utility expertise spanning the
               complete electricity value chain.
           •   Together as Forewind we have the experience and expertise to
               deliver the extraordinary challenges facing Round 3 developers.
           •   Forewind is committed to securing all the necessary consents
               required for the construction and development of Dogger Bank, the
               first of which is anticipated around 2015.
           •   The Crown Estate is Forewind’s partner in the development of
               Dogger Bank.




                                                                                   2
Forewind Overall Strategy
• Forewind’s mission is to deliver development consents for safe, viable offshore wind capacity
• Priority to secure & consent early projects to build momentum & confidence in Forewind for the full zone potential
• We aim to deliver low LCOE projects that maximise value in the Dogger Bank development option

                                                                                     Dogger Bank key facts:
                                                                                     •   Capacity: Agreed target 9 GW,
                                                                                         with the potential for c.13 GW.
                                                                                     •   Area: 8660km2 ; equivalent to size
                                                                                         of North Yorkshire.
                                                                                     •   Distance: 125-290 km from shore.
                                                                                     •   Depth: 18-63 m; c.4 GW in <30m
                                                                                         water depth, c.8 GW in <35m
                                                                                         water depth; shallow compared
                                                                                         with other Round 3 zones.
                                                                                     •   Wind: High wind speeds of
                                                                                         >10 m/s average wind speed
                                                                                         across the zone.
          Middlesbrough
                                                                                     •   History: A "dogger“ was a type of
                                                                                         Dutch fishing boat that commonly
                          Hull
                                                                                         worked in the North Sea in the
                                                                                         seventeenth century.




                                                                                                                           3
Unincorporated Joint Venture

               Structure repeated for each 1GW project




                        Funding & guarantees

        SPV            SPV              SPV               SPV
         SPV            SPV              SPV               SPV




                                                         • UJV owns assets
                                    +   Bizco            • Bizco has legal
                                                           personality for
                              UJV                          licences and land
                                                           agreements etc.
                                 Operator

                                                                               4
Eight or more individual Projects
First 6 Projects have signed grid agreements
                                        Connection point               Connection date
                                        P1 – Creyke Beck   Yorkshire   Apr 2016
                                        P2 – Lackenby      Teesside    Apr 2017
                                        P3 – Lackenby      Teesside    Apr 2018
                                        P4 – Creyke Beck   Yorkshire   Apr 2019
                                        P5 – Tod Point     Teesside    Apr 2019
                                        P6 – Tod Point     Teesside    Apr 2020

                                        • Each Project will have
                                               • Around 200 turbines with a
                                                 cumulative capacity of about 1.2GW
                                               • AC collector transmission substations
                                               • HVDC transmission offshore platform
                                                 and equivalent onshore station
                                               • Approx. 200km * 2 of transmission
                                                 cables to connect to shore
                                        • Each project will cost £3bn to £4bn to
                                          construct. About £30bn needed in total
                                        • Forewind has accepted grid agreements for
                                          first 6 projects in anticipation of an
                                          appropriate regulatory environment evolving




                                                                                      5
Post Consent Risk:


• Regulatory risk – current uncertainties include EMR and transmission charging. What
  regulatory risks will there be when finance is needed?
• Political risk – how much offshore wind is wanted and when?
• Supply chain risk – For example, current global cable manufacturing capability cannot
  supply Dogger Bank’s current programme. Many other examples of supply chain
  pinch points
• Finance:
    • If pre-construction finance only comes from offshore wind farm developers it will
      take a long time to recycle funds and slow down overall deployment of offshore
      wind
    • Availability of post construction finance will impact on ability to recycle funds
    • Utilities may not want to take on £4bn construction projects on their own. Also,
      they may not have the capacity and strategic interest in being a non-operating
      investor


                                                                                          6
Institutional Investors Workshop
2 July 2012
Ryan Trow

Weitere ähnliche Inhalte

Ähnlich wie Attracting and Maintaining Institutional Investment: Offshore Wind

European wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcEuropean wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcSustainableEnergyAut
 
Session4 wind turbine services as driving force for know how transfer authore...
Session4 wind turbine services as driving force for know how transfer authore...Session4 wind turbine services as driving force for know how transfer authore...
Session4 wind turbine services as driving force for know how transfer authore...RCREEE
 
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...Yole Developpement
 
The Solar Future DE - Christoph von Bergen "What is the market and technology...
The Solar Future DE - Christoph von Bergen "What is the market and technology...The Solar Future DE - Christoph von Bergen "What is the market and technology...
The Solar Future DE - Christoph von Bergen "What is the market and technology...Paul van der Linden
 
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...EOI Escuela de Organización Industrial
 
Overcoming 25 year life reliability challenges in solar electronics
Overcoming 25 year life reliability challenges in solar electronicsOvercoming 25 year life reliability challenges in solar electronics
Overcoming 25 year life reliability challenges in solar electronicsGreg Caswell
 
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologieBnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologieMARIANO ORTULAN
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind MEC Intelligence
 
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...Pieter Jan Jordaens
 
2012 09-27 opening owi-lab-beurskens
2012 09-27 opening owi-lab-beurskens2012 09-27 opening owi-lab-beurskens
2012 09-27 opening owi-lab-beurskensSirris
 
Turbine Manufacturer M&A paper Offshore 2015
Turbine Manufacturer M&A paper Offshore 2015Turbine Manufacturer M&A paper Offshore 2015
Turbine Manufacturer M&A paper Offshore 2015Charles Yates
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketLeonardo ENERGY
 
IRJET- Maglev Wind Turbine Generator
IRJET- Maglev Wind Turbine GeneratorIRJET- Maglev Wind Turbine Generator
IRJET- Maglev Wind Turbine GeneratorIRJET Journal
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Ashish Verma
 
Bryan Crabb - GW Solar Symposium 2012
Bryan Crabb  - GW Solar Symposium 2012Bryan Crabb  - GW Solar Symposium 2012
Bryan Crabb - GW Solar Symposium 2012GW Solar Institute
 
Romax consulting: De-risking investment in the wind industry by Yann Rageul
Romax consulting: De-risking investment in the wind industry by Yann RageulRomax consulting: De-risking investment in the wind industry by Yann Rageul
Romax consulting: De-risking investment in the wind industry by Yann RageulYann Rageul
 

Ähnlich wie Attracting and Maintaining Institutional Investment: Offshore Wind (20)

European wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrcEuropean wind technology trends, Roberto Lacal Arántegui, jrc
European wind technology trends, Roberto Lacal Arántegui, jrc
 
Session4 wind turbine services as driving force for know how transfer authore...
Session4 wind turbine services as driving force for know how transfer authore...Session4 wind turbine services as driving force for know how transfer authore...
Session4 wind turbine services as driving force for know how transfer authore...
 
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...
Inverter Technology Trends & Market Expectations 2014 Report by Yole Developp...
 
The Solar Future DE - Christoph von Bergen "What is the market and technology...
The Solar Future DE - Christoph von Bergen "What is the market and technology...The Solar Future DE - Christoph von Bergen "What is the market and technology...
The Solar Future DE - Christoph von Bergen "What is the market and technology...
 
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...
Jaime de Rábago · PRECAST CONCRETE WIND TOWERS AND OFFSHORE FOUNDATIONS: A HU...
 
Overcoming 25 year life reliability challenges in solar electronics
Overcoming 25 year life reliability challenges in solar electronicsOvercoming 25 year life reliability challenges in solar electronics
Overcoming 25 year life reliability challenges in solar electronics
 
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologieBnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
Bnef university solar_wind_bioenergy_geothermal_ccs_energy_smart_technologie
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
 
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...
Guest speaker presentation at 'Seminar Offshore Wind Energy' UGent – June 201...
 
2012 09-27 opening owi-lab-beurskens
2012 09-27 opening owi-lab-beurskens2012 09-27 opening owi-lab-beurskens
2012 09-27 opening owi-lab-beurskens
 
Turbine Manufacturer M&A paper Offshore 2015
Turbine Manufacturer M&A paper Offshore 2015Turbine Manufacturer M&A paper Offshore 2015
Turbine Manufacturer M&A paper Offshore 2015
 
Webinar on grid connection of offshore wind farms
Webinar on grid connection of offshore wind farmsWebinar on grid connection of offshore wind farms
Webinar on grid connection of offshore wind farms
 
Drivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP marketDrivers and Barriers in the current CSP market
Drivers and Barriers in the current CSP market
 
Stop ripping money - Select the right generator
Stop ripping money - Select the right generatorStop ripping money - Select the right generator
Stop ripping money - Select the right generator
 
Yunasko presentation pdf
Yunasko presentation pdfYunasko presentation pdf
Yunasko presentation pdf
 
IRJET- Maglev Wind Turbine Generator
IRJET- Maglev Wind Turbine GeneratorIRJET- Maglev Wind Turbine Generator
IRJET- Maglev Wind Turbine Generator
 
Business plan
Business planBusiness plan
Business plan
 
Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...Performance paramter and suggestion to optizing the performnce of grid connec...
Performance paramter and suggestion to optizing the performnce of grid connec...
 
Bryan Crabb - GW Solar Symposium 2012
Bryan Crabb  - GW Solar Symposium 2012Bryan Crabb  - GW Solar Symposium 2012
Bryan Crabb - GW Solar Symposium 2012
 
Romax consulting: De-risking investment in the wind industry by Yann Rageul
Romax consulting: De-risking investment in the wind industry by Yann RageulRomax consulting: De-risking investment in the wind industry by Yann Rageul
Romax consulting: De-risking investment in the wind industry by Yann Rageul
 

Mehr von Eversheds Sutherland

Conduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorConduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorEversheds Sutherland
 
How technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientHow technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientEversheds Sutherland
 
Preparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsPreparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsEversheds Sutherland
 
State Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksState Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksEversheds Sutherland
 
Opportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceOpportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceEversheds Sutherland
 
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesGetting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesEversheds Sutherland
 
State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016Eversheds Sutherland
 
Is your intellectual property at risk?
Is your intellectual property at risk?Is your intellectual property at risk?
Is your intellectual property at risk?Eversheds Sutherland
 
The Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsThe Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsEversheds Sutherland
 
Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Eversheds Sutherland
 
Eversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds Sutherland
 
Data Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessData Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessEversheds Sutherland
 
LawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthLawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthEversheds Sutherland
 
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds Sutherland
 
Talent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamTalent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamEversheds Sutherland
 

Mehr von Eversheds Sutherland (20)

The fourth industrial revolution
The fourth industrial revolutionThe fourth industrial revolution
The fourth industrial revolution
 
Conduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorConduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial Sector
 
Navigating the Insurance Act
Navigating the Insurance ActNavigating the Insurance Act
Navigating the Insurance Act
 
How technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientHow technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficient
 
Preparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsPreparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contracts
 
State Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksState Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risks
 
Opportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceOpportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforce
 
Post Brexit Update
Post Brexit UpdatePost Brexit Update
Post Brexit Update
 
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesGetting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
 
Metrics for In-House Teams
Metrics for In-House TeamsMetrics for In-House Teams
Metrics for In-House Teams
 
State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016
 
Is your intellectual property at risk?
Is your intellectual property at risk?Is your intellectual property at risk?
Is your intellectual property at risk?
 
The Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsThe Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human Rights
 
Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?
 
Eversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structures
 
Data Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessData Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your business
 
LawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthLawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worth
 
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
 
Bribery and Corruption Campaign
Bribery and Corruption CampaignBribery and Corruption Campaign
Bribery and Corruption Campaign
 
Talent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamTalent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your team
 

Kürzlich hochgeladen

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 

Kürzlich hochgeladen (20)

Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 

Attracting and Maintaining Institutional Investment: Offshore Wind

  • 1. Natural Power Consultants LTD Eversheds, Institutional Investor workshop 2nd July 2012
  • 2. TABLE OF CONTENTS 1. Natural Power Consultants 2. Capex comparative analysis 3. Offshore WTG technology 4. Foundations 5. Cables 6. Installation Tuesday, July 03, 2012 2
  • 3. NATURAL POWER CONSULTANTS Renewable energy consultancy, management • Energy yield analysis and technical risk reduction services and product innovation. • Project design, ecology surveys, EIA and permitting management Onshore wind, Offshore wind, Wave & Tidal and Biomass energy • Construction, ground surveys and contracts management Founded in 1996 300 Employees 14 Offices 7 • Operational A&M and performance analysis Countries • 360o project due diligence • Owner and Lender’s Engineering & Technical Advisors Tuesday, July 03, 2012 3
  • 4. CAPEX COMPARATIVE ANALYSIS1 M£/MW 4.00 3.50 3.40 3.46 3.42 3.30 3.00 3.05 2.76 2.50 2.00 1.50 1.00 0.50 0.00 2006 2007 2008 2009 2010 2011 Natural Power data base of 49 OWF, in 7 European countries • From 2006 to 2009 Capex (M£/MW) has grown, the increase has been driven by cables and foundations costs, in 2010 Capex started to come down • Key factors: distance from the shore, supply bottlenecks, raw materials, installation costs, cable routes 1. Capital expenditures have been collected from our confidential data base, reinforced with trade journals, company websites, public data bases and academic and government reports Tuesday, July 03, 2012 4
  • 5. OFFSHORE WIND TURBINE TECHNOLOGY  After 3-4 MW before 2009, the technology is being oriented to 5-6 MW turbines  Suppliers are now working on:  Reducing the weight with less components (DD or semi-integrated solutions), in order to ease foundation design, installation and maintenance  Larger diameters (150-164 m) with same power output  Blades :  Diameter is increasing from ac. 90 m (2009 ) to 164 m (2015)  Higher bending moment due to larger rotor affects design of the substructure  Blades suppliers are now mostly in-house (Siemens, Vestas, Repower, Areva)  Generator technology :  Power output from 3-4 MW (2009) to 5-6 MW (2012-2014)  Smooth transition from DFIG to DD generators (head mass reduction/power output management)  Gearboxes tend to be removed to reduce maintenance and failures  Use of permanent magnets leads to high risks on Neodymium supply chain Tuesday, July 03, 2012 5
  • 6. WTG SUPPLY AND INSTALLATION Market shares – Turbines suppliers Number of suppliers for the 6 MW+ will % MW installed to date – source EWEA January 2012 increase Areva, REpower are the only leaders with 5-6 MW WTGs but with still a low track record  Historical suppliers have delayed their entrance in this category: Siemens 6 MW focuses on a DD technology, diameters 120 -154m and 50% fewer parts than comparable geared WTG; serial production targeted for Q1 2015, Vestas V164-7.0 MW prototype has been postponed, the first turbine is scheduled for installation in 2013, with series production starting from 2015 New entrants in Europe (Alstom “pure torque” DD 6MW Halliade 150, Gamesa G128-5.0 MW) will be in competition with Asian suppliers (Golwind, Sinovel) Before new entrants will start to produce, the offshore WTG industry will remain a bottleneck in the supply chain Tuesday, July 03, 2012 6
  • 7. OFFSHORE FOUNDATION Market shares – Foundations installed in 2011 Monopiles is the most installed typology of % MW installed – source EWEA January 2012 foundation Wind farms currently under construction show the same trend: monopiles maintaining an over 60% share Jackets and Tripods show similar shares (20% and 18% respectively) Currently, no gravity based foundations have been identified in the under construction pipeline. This structure is generally used in wind farms close to shore Tuesday, July 03, 2012 7
  • 8. MONOPILES’ ISSUES • Monopolie made for: soft seabed, up to medium water depth, up to medium WTG weight (e.g. the actual monopile designed to support 6.0MW WTG vary from 6.5m to 7m in diameter) • Grouted connection: 65% of all the monopile installed in UK is facing problems subjected to a complex state of stress • Installation (mechanical hammer vs drilling): insufficient wind industry experience to guarantee required pile verticality of <0.25° (bolted flange requirement) during driving operations. •Few players represent a bottle neck in the supply chain Tuesday, July 03, 2012 8
  • 9. FOUNDATIONS: NEW TRENDS Jacket Gravity Base Emphasis on cost of fabrication: Emphasis on: • use of materials • noise emission to avoid limitation • pre-assembled manufacturing process during installation • transportation Tuesday, July 03, 2012 9
  • 10. OFFSHORE CABLE TECHNOLOGY Ex Cable Supply Copper price 2009 -2012 0.90 0.80 0.70 Cost in M£/Km 0.60 0.53 0.50 0.40 Market Players 0.30 Market Average 0.20 0.10 0.00 0 50 100 150 200 250 Ex Cable lenght in Km Array Cable Supply Main issues: 0.35 0.30 • Cable Laying: regulation, and natural condition (e.g. salt Cost in M£/Km 0.25 marsh) 0.20 0.20 0.15 Market Players • Supply chain bottlenecks: reluctant cable makers to 0.10 Market Average scale up manufacturing capacity 0.05 • Scarcity of skilled personnel 0.00 0 50 100 150 200 Array Cables Lenght in Km Tuesday, July 03, 2012 10
  • 11. INSTALLATION Latest trends: • Players are developing vessels (e.g. Nordic Yards), which can install every type of foundations, towers, nacelles and turbines as a single unit • In order to reduce installation time and costs, the vessels are designed to deploy the whole wind turbine in an upright position Tuesday, July 03, 2012 11
  • 12. INSTALLATION RATE Offshore Wind Farm WTG Installation Rate Offshore Wind Farm Foundation Installation 10 Rate 1 vessel 1 vessel 9.00 Inst. Rate (days/foundation) 8 8.00 Inst. Rate (days/WTG) 2 vessels 7.00 2 vessels 6 Average 1 6.00 5.7 4.8 vessel 5.00 4.44 Average 4 Average 2 4.00 Mopopile 1 vessel 3.00 vessel 2.75 2 2.00 Average 1.00 Mopopile 2 0 vessels 0.00 0 50 100 0 50 100 N. of WTG N. of foundations Main observations: • No trend, scattered results • Main drivers: weather and sea conditions, water depths, integration of services, cost reduction, crane capacity Tuesday, July 03, 2012 12
  • 13. THANK YOU FOR YOUR ATTENTION Tuesday, July 03, 2012 13
  • 14. Offshore Wind in UK – Funding Round 3 June 27, 2012
  • 15. Agenda  Funding requirement in UK  Conditions for investment  Funding sources  Utilities and other investors  Investor models  Conclusions 2
  • 16. Siemens is market leader in offshore turbines with 2.5 GW installed, of which nearly 1 GW in UK Burbo Banks, UK Vindeby, DK → 25 x SWT-3.6-107 (2007) → 11 x 0.45 MW (1991) Lynn / Inner Dowsing, UK Middelgrunden, DK → 54 x SWT-3.6-107 (2008) → 20 x SWT-2.0-76 (2000) Gunfleet Sands, UK Samsø, DK → 48 x SWT-3.6-107 (2009) → 10 x SWT-2.3-82 (2002) Rhyl Flats, UK Rønland, DK → 25 x SWT-3.6-107 (2009) → 4 x SWT-2.3-93 (2002) Walney, UK Rødsand/Nysted, DK → 51 x SWT-3.6-107 → 72 x SWT-2.3-82 (2003) → 51 x SWT-3.6-120 Frederikshavn, DK Pori, FIN → 1 x SWT-2.3-82 (2003) → 1 x SWT-2.3-101 (2010) Horns Rev II, DK Baltic I, DE → 91 x SWT-2.3-92 (2009) → 21 x SWT-2.3-93 (2010) Rødsand II, DK → 90 x SWT-2.3-93 (2010) Lillgrund, SE → 48 x SWT-2.3-93 (2007) Hywind, NO → 1 x SWT-2.3-82 (2009) Source: SWP 3
  • 17. Many projects to come, some with Siemens equity Greater Gabbard, UK Anholt, DK → 140 x SWT-3.6-107 → 111 x SWT-3.6-120 Sheringham Shoal, UK Baltic 2, DE → 88 x SWT-3.6-107 → 80 x SWT-3.6-120 London Array, UK Borkum Riffgat, DE → 175 SWT-3.6-120 → 30 x SWT-3.6-107 Lincs, UK Dan-Tysk, DE →69 x SWT-3.6-120 → 80 x SWT-3.6-107 →25% Siemens Project Ventures (Centrica 50%, Dong 25%) Borkum Riffgrund 1, DE Gwynt Y Mor, UK → 77 x SWT-3.6-120 →160 x SWT-3.6-107 →10% Siemens Wind Power (RWE Meerwind Sud Ost, DE 60%, SWM 30%) → 80 x SWT-3.6-120 West of Duddon Sands, UK → 108 x SWT-3.6-120 Teesside, UK → 27 x SWT-2.3-93 Note: SPV also own 50% of Smart Wind consortium with Mainstream Renewables, developing UK Round 3 Rudong Intertidal, CHN Hornsea zone (4 GW). First GW → 21 x SWT-2.3-101 being developed with Dong. Source: SWP 4
  • 18. Offshore Wind Roadmap and Funding Requirement 18 GW by 2020 under DECC Roadmap £8-10bn annual funding required Based on £3m/MW capex, straight line roll out from 2015, excludes OFTOs and capital recycling Depends on build out which should generate economies of scale to lower construction costs Source: DECC UK Renewable Energy Roadmap July 2011 5
  • 19. Conditions for investment  Utilities cannot finance construction of Round 3 on their own and need to tap new investors and banking market  Conditions for entry of new capital  Revenue certainty (FITs, ROCs)  Regulatory certainty (EMR, OFTOs)  Profitability & risk adjusted returns  Visibility on long-term market growth  De-risking projects  Stable macroeconomic climate 6
  • 20. Funding Sources in Offshore Wind Development Cycle Point in time – decreasing risk and required return over project life cycle Project risk Development Pre-construction (c.24+ months c.£50- Construction Operation (c. 48+ months, c£10-50m) 200m) (c. 24+ months, c£1Bn) (c. 20+ years) • Turbine order • Civil construction • O&M + Warranty • Site search • Balance of plant • BOP • Zero emission cash • Feasibility study (BOP) Long-lead • Turbine • Environmental studies items • Grid connection • Licenses (production / installation) • Design • Permits • Met mast • Land lease • Geotech • Commitment to grid • Grid connection Funding source Development Pre-construction / Construction Operation Utilities, Infrastructure Funds, Utilities, Venture Capital, Utilities, Oil & Gas Cos, Private Equity, Equity Direct Financial Investors, Public Developer Contractors Equity Markets Project Finance with Sponsors, Debt Capital Markets, Utility Senior debt Not available Multilateral & ECA support Bonds, Govt Sponsored Bonds 7
  • 21. Utility Investors  UK projects have historically been developed by utilities in contrast to Continental Europe where independent developers are more prevalent  UK projects have generally been financed by utilities on balance sheet unlike Continental Europe where limited recourse project finance is more common. Utilities don’t like project finance as it is expensive and often treated as on balance sheet by rating agencies  Utilities have to find alternative funding sources if they want to maintain ratings & preserve dividends. They are forming partnerships with other utilities and new types of investors to share funding and risks  We estimate of total annual capex of 10 largest European utilities of €40bn about €10bn could go to offshore wind with maybe half of this allocated to UK 8
  • 22. R3 Funding Sources 12.000 10.000 Estimated annual construction costs of £8-10bn 8.000 High case – 75% total £ million per year offshore wind budget allocated by European 6.000 utilities to UK ; £1.4bn l/r equity; £2.1bn l/r debt Base case – 50%; £1bn l/r 4.000 equity, £1.5bn l/r debt Low case – 30%, £0.6bn l/r equity; £0.9bn l/r debt 2.000 Utility balance sheet 0 Ltd recourse equity High case Base case Low case Source: Siemens Ltd recourse debt Majority of funding from utility balance sheets unlevered Balance from limited recourse equity (40%) and debt (60%) More utility funding available → more other funding likely to be available Additional funding from capital recycled from operational projects not shown 9
  • 23. Other Investors • Financial/private investors •Private equity / infra funds – SPV / Blackstone / Ampere / Marguerite / Ventizz •Private investors – Colruyt / Kirkbi Group / Oticon Foundation •Pension funds – Pension Danmark / PKA / PGGM •Japanese trading houses – Marubeni •Sovereign wealth funds – Masdar • Strategic investors • Oil & gas companies – Statoil / Repsol • EPC companies – Fluor / Strabag / Hochtief • Financial/private investors generally have limited appetite for construction or development risk but there are exceptions: • Masdar / SPV / Blackstone / Colruyt / Marguerite / Ventizz • EPC companies often take development risk and then sell permitted project before construction 10
  • 24. Co-Funding Model  Costs shared but project risks stay with utility  Sale of minority stakes to private investors  Operating assets  Assets in construction with EPC wrap  De-risking  Opex  PPA  Bridge financing  Stakes sold for premium due to risks assumed by utility  Investments stay on balance sheet of utility  Examples: various deals involving Dong 11
  • 25. Limited Recourse Model – Project Finance  Limited recourse financing by investors  Banks take construction risk  Common in Germany and Benelux, but not in UK  Lincs is first UK PF deal with construction risk  Banks requirements  Higher pricing  Significant contingency  Debt reserve accounts  Lower gearing and high coverage ratios  Support from multilaterals/development banks and ECAs  Examples: Lincs (Centrica/Dong/SPV); Meerwind (Blackstone) 12
  • 26. Limited Recourse Model – Minority Stakes  Limited recourse financing of acquisition of minority stakes by investors  Banks do not take construction risk  Same guarantees as under Co-Funding model  Issues for banks  Limited step-in rights  No direct security over operating assets/contracts  Change of control  More equity required  Support from multilaterals/development banks and ECAs  Example: Gunfleet Sands (Marubeni) 13
  • 27. Conclusions  Utilities will play lead role in funding Round 3, but balance sheet pressure means they will not be able to do this alone  Utilities are setting up JVs with other utilities & investors to share funding & risks. Dong leading way bringing in new investors  New investors will require revenue and regulatory certainty, improved profitability, project de-risking & stable macroeconomic conditions  Most financial investors currently have limited appetite for construction risk, but there are exceptions  Limited recourse lending by commercial banks and public financing institutions will be critical, both at the project level and the financing of minority stakes in projects 14
  • 28. Thank you Peter Weston Global Head of Finance & Investment Siemens Wind Power +44 7808 824 390 peter.weston@siemens.com Global Wind Power Finance & investment Congress June 26-27, 2012, London
  • 29. Morgan Stanley Institutional Investors Workshop July 2, 2012
  • 30. Morgan Stanley Project Finance Transactions Power Approx. $300 MM $740 MM $45 Bn $740 MM $11 Bn $1.65 Bn $950 MM $950 MM West Deptford MACH Gen Project Construction/Term Construction Acquisition Debt Construction Acquisition Debt Acquisition Financing Financing Financing Refinancing Refinancing Financing Refinancing Financing November 2011 May 2008 February 2007 February 2007 June 2006 March 2006 September 2005 September 2005 Natural Resources $750 MM $300 MM $240 MM $1 Bn $900 MM $240 MM $1.55 Bn $378 MM EGPC EGPC EGPC EGPC Drillship FPSO Debt Receivables Pre-Export Credit Acquisition Financing Financing Financing Monetization Facility Financing FSA Monetization FSA Monetization March 2012 November 2011 June 2011 December 2010 October 2009 February 2006 July 2005 June 2007 Infrastructure $600 MM $1.3 Bn $100 MM $494 MM $213 MM $162 MM $1Bn $1Bn HANGZOU RING ROAD Infrastructure Construction Railway Lease Securitization Financing Financing Financing April 2007 Toll Road Financing Toll Road Financing Railroad Financing Toll Road Financing November 2010 March 2010 October 2007 August 2006 February 2006 December 2005 December 2005 Renewables $290 MM $466 MM $319 MM 10-Year $200 MM 10-Year $117.5 MM $132 MM Canadian Hills Arlington Valley Loraine Wind Wind Project Solar Energy II Project Construction Construction / Term Wind Equity Construction Construction Construction Commodity Offtake Commodity Offtake Financing Financing Financing Provider Investment Provider Financing Financing March 2012 January 2012 December 2011 December 2011 February 2010 July 2009 July 2009 August 2008 2
  • 31. Financing Sources For Greenfield Offshore Wind Past Projects and Projections Bloomberg New Energy Finance Projections: Annual Investment Annual Investment in Offshore Wind 2012-2020 By Year of Commissioning and Investor Type; 2012–2015 by Existing Commitments and 2016–2020 Forecast Country € Bn € Bn Germany 39.2 5.6 10.2 13.8 14.2 12.3 14.4 16.1 18.6 21.3 100% UK 38.6 0.7 1.2 France 18.8 2.2 2.6 2.8 3.1 3.8 3.5 3.2 Belgium 6.6 0.4 1.0 Denmark 3.9 80% 0.1 0.1 0.2 0.4 Netherlands 3.5 0.3 0.4 2.7 0.3 3.9 Rest of EU 16.3 3.2 5.2 0.9 3.2 7.1 Total 126.9 60% 0.3 9.0 1.0 Sources Bloomberg New Energy Finance; Rabobank 0.1 0.3 0.1 0.3 0.1 0.1 0.4 0.4 0.3 0.2 0.3 0.4 0.1 0.5 0.5 0.3 1.8 0.3 0.4 0.1 • Q: Do you believe that 40% 1.3 4.0 2.0 0.4 0.7 0.3 0.1 1.6 2.0 0.9 Multilateral agencies will 0.4 0.7 1.3 2.1 provide an aggregate value 6.1 1.7 2.1 of €22Bn in capital over the 1.9 next 8 years? 20% 1.3 2.3 2.6 3.9 3.2 1.2 3.1 2.8 2.1 2.5 2.1 0% 2012 2013 2014 2015 2016 2017 2018 2019 2020 Equity-Primary Utility Equity-Secondary Utility Equity-Developer Equity-IPP Equity-Institutional Investor Equity-WTG Equity-Private Equity Debt-Commercial Debt-Multilateral Sources Bloomberg New Energy Finance; Rabobank 3
  • 32. Banks Project Finance Participation Glass Half Empty Or Full? • Q: Do you believe that Banks in Project Finance Offshore Wind Transactions commercial banks will Number of Transactions provide an aggregate value of €35Bn in capital over the 1 12 12 next 8 years? – Average of ~€4.5Bn per 2 7 19 year 3 4 23 • Approximately 70% of bank lenders into the offshore 24 4 1 wind sector have only participated in 2 transactions 5 1 25 • Alternatively, could argue that banks with 2+ 6 1 26 transactions makes ‘a knowledgeable market’ 7 1 27 – 16 banks 8 1 28 • Even assuming ‘knowledgeable market’ 0 2 4 6 8 10 12 doubles to 32 banks, a €4.5Bn average capital requirement would require an “Our discussions with industry participants suggest there are around 15-20 commercial lending average ticket size of banks currently active in offshore wind financing, and that there is appetite to fund €2-2.5Bn of approximately €140MM per projects per year” bank Morgan Stanley Equity Research – Concentration concerns? 4
  • 33. Institutional Investors as Debt Capital Providers • Pension funds have played a • Renewable sector: interest by institutional debt investors in European renewable sector is increasing, role in investing in the equity however it is still early stages of offshore wind projects – Several funds have dedicated pools of capital for infrastructure investment, which includes renewables • Given the scale of the – Judgment based upon limited transaction flow and unhelpful precedents (i.e. Breeze) and stability of anticipated build out, expect regulatory regimes that the institutional debt capital markets will play • Favourable markets: offshore wind predominately located in “core” Northern European markets some role – Likely only when Investor Concerns – Not Unsurprising operational • Business model - Future incentive / regulatory support risk • Technology risk: evolving so why invest now? • Resource risk – Weather risk (“black swan” winter storm damaging turbines) How / When To Invest? • Unlikely that institutional investors would be willing to take construction risk of an early stage technology without sufficient guarantees or a wrap from an independent party – Renewable wind power not currently permitted under EU/EIB Project Bond Initiative – Investment grade? • Initially, expect that construction financing will be provided by banks with a potential bond takeout post-construction • In line with broader European PF bank market, which we expect will morph towards a more formal mini-perm structure 5
  • 34. Offshore Wind Financing Strategies Current Developer / ‘IPP’ Model Future Utility Model? Asset Debt Export Credit Equity/Cash Debt Asset Agencies Utility Commercial Banks Equity (50% +/-) 3rd Party Equity Equity (50% +/-) Sponsor(s) Equity Investors Debt • No “On” vs. “Off” balance sheet considerations • Depending on equity investor / structure, debt consolidation could be relevant to Utilities • Rating agencies (or public ratings) not necessary • As Utilities expand their offshore wind portfolios, • Continued appetite of the ECAs / commercial additional debt burden puts pressure on balance banks critical for this funding approach sheets and ratings –While selling down an equity stake recycles capital to allow for further development, it may not reduce the Utility’s debt burden 6
  • 35. Industry Wide Financing Solution? Legal / Ownership Likely to Pose Problems Utility 1 Utility 2 Utility 3 Other [X]% [X]% [X]% [X]% FiT Utility 1 FiT Utility 2 Debt Proceeds Banks / Institutional IssuerCo Security Investors FiT Utility 3 FiT Other Utility 1 Utility 2 Utility 3 Asset Asset Asset 7
  • 36. Institutional Investors Workshop 2 July 2012 Ryan Trow
  • 37. Forewind • Forewind is a consortium comprising four leading international energy companies: RWE, SSE, Statoil, and Statkraft. • The consortium members joined forces to bid for the Dogger Bank Zone Development Agreement as part of The Crown Estate’s third licence round for UK offshore wind farms (Round 3) in 2010. • Forewind combines extensive experience of international offshore project delivery and renewables development, construction, asset management and operations, with UK utility expertise spanning the complete electricity value chain. • Together as Forewind we have the experience and expertise to deliver the extraordinary challenges facing Round 3 developers. • Forewind is committed to securing all the necessary consents required for the construction and development of Dogger Bank, the first of which is anticipated around 2015. • The Crown Estate is Forewind’s partner in the development of Dogger Bank. 2
  • 38. Forewind Overall Strategy • Forewind’s mission is to deliver development consents for safe, viable offshore wind capacity • Priority to secure & consent early projects to build momentum & confidence in Forewind for the full zone potential • We aim to deliver low LCOE projects that maximise value in the Dogger Bank development option Dogger Bank key facts: • Capacity: Agreed target 9 GW, with the potential for c.13 GW. • Area: 8660km2 ; equivalent to size of North Yorkshire. • Distance: 125-290 km from shore. • Depth: 18-63 m; c.4 GW in <30m water depth, c.8 GW in <35m water depth; shallow compared with other Round 3 zones. • Wind: High wind speeds of >10 m/s average wind speed across the zone. Middlesbrough • History: A "dogger“ was a type of Dutch fishing boat that commonly Hull worked in the North Sea in the seventeenth century. 3
  • 39. Unincorporated Joint Venture Structure repeated for each 1GW project Funding & guarantees SPV SPV SPV SPV SPV SPV SPV SPV • UJV owns assets + Bizco • Bizco has legal personality for UJV licences and land agreements etc. Operator 4
  • 40. Eight or more individual Projects First 6 Projects have signed grid agreements Connection point Connection date P1 – Creyke Beck Yorkshire Apr 2016 P2 – Lackenby Teesside Apr 2017 P3 – Lackenby Teesside Apr 2018 P4 – Creyke Beck Yorkshire Apr 2019 P5 – Tod Point Teesside Apr 2019 P6 – Tod Point Teesside Apr 2020 • Each Project will have • Around 200 turbines with a cumulative capacity of about 1.2GW • AC collector transmission substations • HVDC transmission offshore platform and equivalent onshore station • Approx. 200km * 2 of transmission cables to connect to shore • Each project will cost £3bn to £4bn to construct. About £30bn needed in total • Forewind has accepted grid agreements for first 6 projects in anticipation of an appropriate regulatory environment evolving 5
  • 41. Post Consent Risk: • Regulatory risk – current uncertainties include EMR and transmission charging. What regulatory risks will there be when finance is needed? • Political risk – how much offshore wind is wanted and when? • Supply chain risk – For example, current global cable manufacturing capability cannot supply Dogger Bank’s current programme. Many other examples of supply chain pinch points • Finance: • If pre-construction finance only comes from offshore wind farm developers it will take a long time to recycle funds and slow down overall deployment of offshore wind • Availability of post construction finance will impact on ability to recycle funds • Utilities may not want to take on £4bn construction projects on their own. Also, they may not have the capacity and strategic interest in being a non-operating investor 6
  • 42. Institutional Investors Workshop 2 July 2012 Ryan Trow