SlideShare ist ein Scribd-Unternehmen logo
1 von 10
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

 Project Title:
‘Wankhede Stadium’ at Mumbai
 Project Details:Statistics:-

Approx. Area
Proposed seating
Height of the Stand
Ground radius

:
:
:
:

35,000 Sqm.
32,000
30 m from ground level
Approx. 68.50 m

Photographs:-

Photograph 1 - Wankhede stadium at Night & with Flood Lights on.

1|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

Photograph 2 - Wankhede stadium view from the stand.

Photograph 3 - Newly refurbished, Existing East Stand

2|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

 Project Status
Project Complete

 Year of Inception
The stadium construction started in June 2009 and was completed in
January 2011. The mammoth kind of structural and civil work, right from
its foundation including piling and large basement was executed in just 15
months time.

 Estimated Cost of Project
The Approximated Estimated Cost of Project was 250 Crores Plus.

 What makes the Project Eligible for an Engineering Excellence award
2013
It is like a dream project coming into a reality in view of the mammoth
quantum of work to be executed to the International Stadium standards
laid down by ICC (an International Body) in a very limited time span of just
15 months.
Getting space to live in Mumbai itself is a very difficult task. Getting space
for a Cricket stadium was a remote possibility. The only option was to
construct a new stadium at the same place, with desired enhanced seating
capacity, most modern and up to date amenities.
The working space was very limited (with Railwaly line & an existing
Stadium on two sides & residential zone on balance two sides). There no
possibility of getting any additional space, hence it was a tight site from
working and maneuvering point of view. Thus, stands on two sides (North &
South) were newly constructed whereas the East & West stands were
renovated.
At a given moment there were number of activities going on in the limited
area posing a challenge in movement of trucks, cranes, material etc.
Further, since all the activities were interdependent the work progress use
to get hampered once an agency fail to deliver in stipulated time schedule.
Refer Photograph 4 showing various site happening at the project site.
3|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

Photograph 4
Various site activity co ordination was required.
It was a real challenge during last 4 - 5 months, when the working area further
reduced to half as MCA insisted that the pitch and surrounding area should be handed
over to other agency for preparation of pitch and ground. Refer Photograph 4

showing various site happening at the project site.

Photograph 5
Various Construction activities happening at the same time.
4|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

 5 Points which makes this Project Innovative (Breakthrough / applied) …..
The structural design was complex and intricate as it involved –
i)

The 25 meter ( @ 80 ‘) cantilevered roof is the most interesting feature of the
proposed stadium. It completely opens up the stands as no columns / or an
obstruction or support come in the way of viewers. Refer Photograph 6 showing
Structural Steel work in progress for the Roof Truss members.

Photograph 6
Structural Steel work in progress for the Roof Truss members.
ii)

Heavy column sections extending beyond the top edge of the stadium and each
unit weighing in tonnes were fabricated out of 3 tubular hollow pipes in a
triangular profile fabricated out of various diameter MS pipes. Designing of the
25 m cantilever and its supporting system was a real challenge.

iii)

There was a need of creating a world class cricket stadium & an opportunity
knocked the door with the Word cup championship in year 2011. A Stiff & Steep
task of constructing Wankhede stadium was in terms of Co-ordination of various
activities, fighting against the time.

5|Page
Report on Wankhede Stadium, Mumbai

iv)

M/s. Mahimtura Consultants Pvt. Ltd.

The Stadium is located in a very much restricted, sensitive zone with lot many
constraints. During construction, the list of challenges was unending viz. adhering
traffic and other local regulations, congested area of the city, restricted entry
points to the Stadium, inadequate carriage ways for movement of heavy
vehicles, construction material, intermediate heavy monsoon pours making the
ground filthy posing more problems during work execution.

Photograph 7
Structural Steel Column Work in progress

v)

6|Page

Inspection and quality checks for the structural steel inspection, fabrication and
erection work was undertaken implementing stringent QAP (Quality Assurance
Plan) and ITP (Itemized testing plan) norms witnessed by an expert third party
inspecting agency at various locations. First, at the factory, to check quality of
material received. Then, in the second stage at the fabrication yard for testing
quality of weld and joints and lastly, on at the site. Refer Photograph 8
showing Heavy Structural Steel Column received at site from the fabrication yard.
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

Photograph 8
Heavy Structural Steel Column received at site from the fabrication yard
 5 Points on the Operational Excellence of the Project (Time, Cost & Others)
i) Out of the two parameters viz. Time & Cost, completing of the stadium in
time was more in focus in view of the international repute, though cost
aspect was monitored regularly, still was secondary.
ii) Wankhede Stadium has all the in-house facilities including the IT related
aspects at par with world standards for conducting international matches.
ii) The structural design is carried out taking into account the composite action
of the columns for earthquake resistance. Encasing of structural steel impart
fire resistance to the columns. Other exposed area is fire protected making
use of appropriate fire protection material. Thus, exposed area of steel and
fire protection to the same added to the cost.
iv) The major hurdle was to accommodate proposed, new stadium within same
old space and congested locality. It had no possibility of any horizontal
expansion. In view of these constraints, the East & West stands were
renovated, structurally strengthened to cater to enhanced spectator capacity.
Existing columns were jacketed and extended till required height.
7|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

v) Mumbai has been the birth place for players of an international repute viz.
Gavaskar, Tendulkar, Mankad, Hazare and many others. It’s the “Mecca” of
Indian Cricket and it’s a fortune that we could have such an well equipped
Stadium with every amenity that is thought of, in order to help the game of
Cricket prosper.

 5 Points on as how this Project has added to the Self Reliance of India in the
Chosen Sector.
i) India is currently a top ranked country in ICC Ranking, in all three segments of
Cricket and would strive to retain the top notch position.
ii) Availability of such a facility in Mumbai, would not only encourage the Game
of Cricket, but also give immense pleasure to Cricket lovers watching matches
in a modern environments & venues like the ‘Wankhede Stadium’, in India.
iii) Our capabilities of creating such an important & iconic structure in short
span was very much appreciated and admired by the entire Cricket playing
nations and it is a feather in the cap.
iv) Construction of Wankhede Stadium had raised the benchmark in India for
other Stadiums to be constructed in future. The various important features of
the stadium are 360 degree uninterrupted view, column free spectator
stands, covered roofing using fabric material (rather than use of cancerous
material which was being used in the past) wide enough walk ways, specious
seating arrangement, dedicated elevators for physically challenged
people and high security for players and up dated surveillance system etc.
v) The spectacular view of ‘Queen’s Necklace’ at the Marine Drive, location of
the stadium at the Sea and an appealing look of the Stadium is an USP of
Wankhede Stadium. Refer Photograph 9 below, with intended architectural
look of Wankhede Stadium.

8|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

Photograph 9
‘Wankhede Stadium’, an Architectural & Structural Marvel
 5 Key Impacts the Project has made
i) The Wankhede stadium has put India in the list of countries having an
International standard Cricket Stadium.
ii) BCCI has stood to the challenge and showed it to the worlds that it has all the
capabilities & expertise, & is elf reliant as far as construction of such World
class stadiums is concern. That how the World Cup Final was held at
Wankhede Stadium in April, 2011.
iii) At Wankhede Stadium, the entire project team was from India, is now a
Landmark structure in this category & we Indians could prove the world that
our Architects and Consultants are equally talented and have capabilities to
create such a structure.
iv) We could also prove that we have world class ground curators in India who
can prepare and maintain international standard Cricket pitches.
v) The Stadium shall be Good Revenue generation source for India once various
international matched are played at Wankhede Stadium.
9|Page
Report on Wankhede Stadium, Mumbai

M/s. Mahimtura Consultants Pvt. Ltd.

 5 Points Illumines more on the Future Readiness of the Project.
i) Creating of such a high class stadium in India shall provide an uninterrupted
Opportunity to our Cricket Hero’s and Budding Cricketers to excel their
skill in this segment of Sport in further.
ii) Column free stadium is an International concept, now followed in India in
construction of Wankhede Stadium. The 360 degree view during a match
give immense pleasure to the viewers is an USP of Wankhede Stadium.
iii) Construction of more similar kind of Stadiums in India would help in
development of the immensely loved and popular Game of Cricket,
increasing passion towards it in our Country.
iv) Aesthetically appealing roof cover out of textile fabric has given an
opening to new industries manufacturing Textile fabric thereby helping in
economical growth of India.
v) The new concept of auctioning of spectators box, modern corporate lounges
to the various businesses has begun and there is long way for further
improvisation from revenue generation point of view in India.

10 | P a g e

Weitere ähnliche Inhalte

Was ist angesagt?

Amanora Future Towers, Hadapsar, Pune - Case Study
Amanora Future Towers, Hadapsar, Pune - Case StudyAmanora Future Towers, Hadapsar, Pune - Case Study
Amanora Future Towers, Hadapsar, Pune - Case StudyAjinkya Randive
 
internship report on architecture
internship report on architectureinternship report on architecture
internship report on architecturebiruktigistu1
 
Salt Lake City Centre
Salt Lake City CentreSalt Lake City Centre
Salt Lake City CentreRashmi Gautam
 
Chandigarh Experiment with Low Cost -Housing
Chandigarh Experiment with Low Cost -HousingChandigarh Experiment with Low Cost -Housing
Chandigarh Experiment with Low Cost -HousingJIT KUMAR GUPTA
 
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal  - CII- Sohrabji Godrej Green Business Centre HyderabadArchitectural Appraisal  - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre HyderabadPrastara Architects
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameAbdul Rahman
 
Architectural Professional Practice - Fees
Architectural Professional Practice - FeesArchitectural Professional Practice - Fees
Architectural Professional Practice - FeesGalala University
 
Ancient system of town planning in india
Ancient system of town planning in indiaAncient system of town planning in india
Ancient system of town planning in indiactlachu
 
46721953 magarpatta-city
46721953 magarpatta-city46721953 magarpatta-city
46721953 magarpatta-cityBhairavi Gupta
 
Re New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaRe New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaArshadbalwa
 
Mattuthavani bus terminal case study
Mattuthavani bus terminal  case studyMattuthavani bus terminal  case study
Mattuthavani bus terminal case studyAbinaya Ramakrishnan
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationAditi Garg
 

Was ist angesagt? (20)

Amanora Future Towers, Hadapsar, Pune - Case Study
Amanora Future Towers, Hadapsar, Pune - Case StudyAmanora Future Towers, Hadapsar, Pune - Case Study
Amanora Future Towers, Hadapsar, Pune - Case Study
 
internship report on architecture
internship report on architectureinternship report on architecture
internship report on architecture
 
Salt Lake City Centre
Salt Lake City CentreSalt Lake City Centre
Salt Lake City Centre
 
APSRTC presentation
APSRTC presentationAPSRTC presentation
APSRTC presentation
 
Chandigarh Experiment with Low Cost -Housing
Chandigarh Experiment with Low Cost -HousingChandigarh Experiment with Low Cost -Housing
Chandigarh Experiment with Low Cost -Housing
 
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal  - CII- Sohrabji Godrej Green Business Centre HyderabadArchitectural Appraisal  - CII- Sohrabji Godrej Green Business Centre Hyderabad
Architectural Appraisal - CII- Sohrabji Godrej Green Business Centre Hyderabad
 
TOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-ITOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-I
 
Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
Tensile
TensileTensile
Tensile
 
Architectural Professional Practice - Fees
Architectural Professional Practice - FeesArchitectural Professional Practice - Fees
Architectural Professional Practice - Fees
 
Ancient system of town planning in india
Ancient system of town planning in indiaAncient system of town planning in india
Ancient system of town planning in india
 
46721953 magarpatta-city
46721953 magarpatta-city46721953 magarpatta-city
46721953 magarpatta-city
 
Re New Mumbai by Arshad Balwa
Re New Mumbai by Arshad BalwaRe New Mumbai by Arshad Balwa
Re New Mumbai by Arshad Balwa
 
Culinary Arts Centre
Culinary Arts CentreCulinary Arts Centre
Culinary Arts Centre
 
Urban design
Urban designUrban design
Urban design
 
L&T
L&TL&T
L&T
 
Mattuthavani bus terminal case study
Mattuthavani bus terminal  case studyMattuthavani bus terminal  case study
Mattuthavani bus terminal case study
 
Suzlon
SuzlonSuzlon
Suzlon
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
BREEAM
BREEAMBREEAM
BREEAM
 

Ähnlich wie Wankhede nomination 31-08-2013

The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013engineeringwatch
 
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...IRJET Journal
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneAwanish Shukla
 
Construction and Architecture magazine 03 jan feb 2010
Construction and Architecture magazine 03 jan feb 2010Construction and Architecture magazine 03 jan feb 2010
Construction and Architecture magazine 03 jan feb 2010Remona Divekar
 
Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)TeohPeiNi
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
Vikash_Tripathi_Resume
Vikash_Tripathi_ResumeVikash_Tripathi_Resume
Vikash_Tripathi_Resumevikash198628
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Ram1239
 
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...IRJET Journal
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...Mary Montoya
 
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...IRJET Journal
 
Project presentation.pptx
Project presentation.pptxProject presentation.pptx
Project presentation.pptxLikhithPB
 

Ähnlich wie Wankhede nomination 31-08-2013 (20)

CV - Sanjeev Aggarwal
CV - Sanjeev AggarwalCV - Sanjeev Aggarwal
CV - Sanjeev Aggarwal
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
BIM case study
BIM case studyBIM case study
BIM case study
 
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
Efficient Design for Multi-story Building Using Pre-Fabricated Steel Structur...
 
Swot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourneSwot analysis of delhi cwg project & melbourne
Swot analysis of delhi cwg project & melbourne
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
Construction and Architecture magazine 03 jan feb 2010
Construction and Architecture magazine 03 jan feb 2010Construction and Architecture magazine 03 jan feb 2010
Construction and Architecture magazine 03 jan feb 2010
 
Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)Site visit report (Soo Bee Chien & Teoh Pei Ni)
Site visit report (Soo Bee Chien & Teoh Pei Ni)
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
bala resume
bala resumebala resume
bala resume
 
Vikash_Tripathi_Resume
Vikash_Tripathi_ResumeVikash_Tripathi_Resume
Vikash_Tripathi_Resume
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering
 
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
NOVEL METHODS AND MATERIALS FOR CONCRETE FLOOR SLAB CONSTRUCTION FOR SMALL FA...
 
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...Advanced Tunnel Form Construction Technique, Case Study of  Rohan-Abhilasha, ...
Advanced Tunnel Form Construction Technique, Case Study of Rohan-Abhilasha, ...
 
Summery
SummerySummery
Summery
 
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...
IRJET-Analysis and Design of Indoor Stadium Building using ETABS Proposed at ...
 
Project presentation.pptx
Project presentation.pptxProject presentation.pptx
Project presentation.pptx
 
RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
Cv aniruddha
Cv aniruddhaCv aniruddha
Cv aniruddha
 

Mehr von engineeringwatch

Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolioengineeringwatch
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Bookletengineeringwatch
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 engineeringwatch
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation systemengineeringwatch
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limitedengineeringwatch
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)engineeringwatch
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructionsengineeringwatch
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkataengineeringwatch
 
Braithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataBraithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataengineeringwatch
 
Vedanta aluminium ltd reverse osmosis process
Vedanta aluminium ltd reverse osmosis processVedanta aluminium ltd reverse osmosis process
Vedanta aluminium ltd reverse osmosis processengineeringwatch
 

Mehr von engineeringwatch (20)

Eduindia UPTU Portfolio
Eduindia UPTU PortfolioEduindia UPTU Portfolio
Eduindia UPTU Portfolio
 
Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolio
 
Eduindia Portfolio
Eduindia PortfolioEduindia Portfolio
Eduindia Portfolio
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Booklet
 
Edu india presentation
Edu india presentationEdu india presentation
Edu india presentation
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation system
 
Globus infocom limited
Globus infocom limitedGlobus infocom limited
Globus infocom limited
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limited
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Csir cftri
Csir cftriCsir cftri
Csir cftri
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
 
Hscc (india) ltd
Hscc (india) ltdHscc (india) ltd
Hscc (india) ltd
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkata
 
Braithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkataBraithwaite & co. limited,kolkata
Braithwaite & co. limited,kolkata
 
Vedanta aluminium ltd reverse osmosis process
Vedanta aluminium ltd reverse osmosis processVedanta aluminium ltd reverse osmosis process
Vedanta aluminium ltd reverse osmosis process
 

Kürzlich hochgeladen

NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 

Kürzlich hochgeladen (20)

NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 

Wankhede nomination 31-08-2013

  • 1. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd.  Project Title: ‘Wankhede Stadium’ at Mumbai  Project Details:Statistics:- Approx. Area Proposed seating Height of the Stand Ground radius : : : : 35,000 Sqm. 32,000 30 m from ground level Approx. 68.50 m Photographs:- Photograph 1 - Wankhede stadium at Night & with Flood Lights on. 1|Page
  • 2. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd. Photograph 2 - Wankhede stadium view from the stand. Photograph 3 - Newly refurbished, Existing East Stand 2|Page
  • 3. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd.  Project Status Project Complete  Year of Inception The stadium construction started in June 2009 and was completed in January 2011. The mammoth kind of structural and civil work, right from its foundation including piling and large basement was executed in just 15 months time.  Estimated Cost of Project The Approximated Estimated Cost of Project was 250 Crores Plus.  What makes the Project Eligible for an Engineering Excellence award 2013 It is like a dream project coming into a reality in view of the mammoth quantum of work to be executed to the International Stadium standards laid down by ICC (an International Body) in a very limited time span of just 15 months. Getting space to live in Mumbai itself is a very difficult task. Getting space for a Cricket stadium was a remote possibility. The only option was to construct a new stadium at the same place, with desired enhanced seating capacity, most modern and up to date amenities. The working space was very limited (with Railwaly line & an existing Stadium on two sides & residential zone on balance two sides). There no possibility of getting any additional space, hence it was a tight site from working and maneuvering point of view. Thus, stands on two sides (North & South) were newly constructed whereas the East & West stands were renovated. At a given moment there were number of activities going on in the limited area posing a challenge in movement of trucks, cranes, material etc. Further, since all the activities were interdependent the work progress use to get hampered once an agency fail to deliver in stipulated time schedule. Refer Photograph 4 showing various site happening at the project site. 3|Page
  • 4. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd. Photograph 4 Various site activity co ordination was required. It was a real challenge during last 4 - 5 months, when the working area further reduced to half as MCA insisted that the pitch and surrounding area should be handed over to other agency for preparation of pitch and ground. Refer Photograph 4 showing various site happening at the project site. Photograph 5 Various Construction activities happening at the same time. 4|Page
  • 5. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd.  5 Points which makes this Project Innovative (Breakthrough / applied) ….. The structural design was complex and intricate as it involved – i) The 25 meter ( @ 80 ‘) cantilevered roof is the most interesting feature of the proposed stadium. It completely opens up the stands as no columns / or an obstruction or support come in the way of viewers. Refer Photograph 6 showing Structural Steel work in progress for the Roof Truss members. Photograph 6 Structural Steel work in progress for the Roof Truss members. ii) Heavy column sections extending beyond the top edge of the stadium and each unit weighing in tonnes were fabricated out of 3 tubular hollow pipes in a triangular profile fabricated out of various diameter MS pipes. Designing of the 25 m cantilever and its supporting system was a real challenge. iii) There was a need of creating a world class cricket stadium & an opportunity knocked the door with the Word cup championship in year 2011. A Stiff & Steep task of constructing Wankhede stadium was in terms of Co-ordination of various activities, fighting against the time. 5|Page
  • 6. Report on Wankhede Stadium, Mumbai iv) M/s. Mahimtura Consultants Pvt. Ltd. The Stadium is located in a very much restricted, sensitive zone with lot many constraints. During construction, the list of challenges was unending viz. adhering traffic and other local regulations, congested area of the city, restricted entry points to the Stadium, inadequate carriage ways for movement of heavy vehicles, construction material, intermediate heavy monsoon pours making the ground filthy posing more problems during work execution. Photograph 7 Structural Steel Column Work in progress v) 6|Page Inspection and quality checks for the structural steel inspection, fabrication and erection work was undertaken implementing stringent QAP (Quality Assurance Plan) and ITP (Itemized testing plan) norms witnessed by an expert third party inspecting agency at various locations. First, at the factory, to check quality of material received. Then, in the second stage at the fabrication yard for testing quality of weld and joints and lastly, on at the site. Refer Photograph 8 showing Heavy Structural Steel Column received at site from the fabrication yard.
  • 7. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd. Photograph 8 Heavy Structural Steel Column received at site from the fabrication yard  5 Points on the Operational Excellence of the Project (Time, Cost & Others) i) Out of the two parameters viz. Time & Cost, completing of the stadium in time was more in focus in view of the international repute, though cost aspect was monitored regularly, still was secondary. ii) Wankhede Stadium has all the in-house facilities including the IT related aspects at par with world standards for conducting international matches. ii) The structural design is carried out taking into account the composite action of the columns for earthquake resistance. Encasing of structural steel impart fire resistance to the columns. Other exposed area is fire protected making use of appropriate fire protection material. Thus, exposed area of steel and fire protection to the same added to the cost. iv) The major hurdle was to accommodate proposed, new stadium within same old space and congested locality. It had no possibility of any horizontal expansion. In view of these constraints, the East & West stands were renovated, structurally strengthened to cater to enhanced spectator capacity. Existing columns were jacketed and extended till required height. 7|Page
  • 8. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd. v) Mumbai has been the birth place for players of an international repute viz. Gavaskar, Tendulkar, Mankad, Hazare and many others. It’s the “Mecca” of Indian Cricket and it’s a fortune that we could have such an well equipped Stadium with every amenity that is thought of, in order to help the game of Cricket prosper.  5 Points on as how this Project has added to the Self Reliance of India in the Chosen Sector. i) India is currently a top ranked country in ICC Ranking, in all three segments of Cricket and would strive to retain the top notch position. ii) Availability of such a facility in Mumbai, would not only encourage the Game of Cricket, but also give immense pleasure to Cricket lovers watching matches in a modern environments & venues like the ‘Wankhede Stadium’, in India. iii) Our capabilities of creating such an important & iconic structure in short span was very much appreciated and admired by the entire Cricket playing nations and it is a feather in the cap. iv) Construction of Wankhede Stadium had raised the benchmark in India for other Stadiums to be constructed in future. The various important features of the stadium are 360 degree uninterrupted view, column free spectator stands, covered roofing using fabric material (rather than use of cancerous material which was being used in the past) wide enough walk ways, specious seating arrangement, dedicated elevators for physically challenged people and high security for players and up dated surveillance system etc. v) The spectacular view of ‘Queen’s Necklace’ at the Marine Drive, location of the stadium at the Sea and an appealing look of the Stadium is an USP of Wankhede Stadium. Refer Photograph 9 below, with intended architectural look of Wankhede Stadium. 8|Page
  • 9. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd. Photograph 9 ‘Wankhede Stadium’, an Architectural & Structural Marvel  5 Key Impacts the Project has made i) The Wankhede stadium has put India in the list of countries having an International standard Cricket Stadium. ii) BCCI has stood to the challenge and showed it to the worlds that it has all the capabilities & expertise, & is elf reliant as far as construction of such World class stadiums is concern. That how the World Cup Final was held at Wankhede Stadium in April, 2011. iii) At Wankhede Stadium, the entire project team was from India, is now a Landmark structure in this category & we Indians could prove the world that our Architects and Consultants are equally talented and have capabilities to create such a structure. iv) We could also prove that we have world class ground curators in India who can prepare and maintain international standard Cricket pitches. v) The Stadium shall be Good Revenue generation source for India once various international matched are played at Wankhede Stadium. 9|Page
  • 10. Report on Wankhede Stadium, Mumbai M/s. Mahimtura Consultants Pvt. Ltd.  5 Points Illumines more on the Future Readiness of the Project. i) Creating of such a high class stadium in India shall provide an uninterrupted Opportunity to our Cricket Hero’s and Budding Cricketers to excel their skill in this segment of Sport in further. ii) Column free stadium is an International concept, now followed in India in construction of Wankhede Stadium. The 360 degree view during a match give immense pleasure to the viewers is an USP of Wankhede Stadium. iii) Construction of more similar kind of Stadiums in India would help in development of the immensely loved and popular Game of Cricket, increasing passion towards it in our Country. iv) Aesthetically appealing roof cover out of textile fabric has given an opening to new industries manufacturing Textile fabric thereby helping in economical growth of India. v) The new concept of auctioning of spectators box, modern corporate lounges to the various businesses has begun and there is long way for further improvisation from revenue generation point of view in India. 10 | P a g e