1. Business of Anaerobic Digestion
Project Delivery Basics
BioCycle West – Pre-Conference Workshop
April 16th Portland Oregon
Adam Halsband – Business Development Manager
EISENMANN Corporation
2. Agenda
• Key Components of Project Development
• Key Elements of Project Delivery
• Project Delivery Approach and Drivers
– Project Development and Delivery Timeline
– Tools and Terminology
– Preliminary Engineering
– Project Delivery Organization
• Contract Structures
• Which Approach is Right for You?
3. Key Components of Project Development
Project Developer XYZ Group
Feedstock Technology- Operations
(WSA) Permitting
Offtake + Finance
4. Key Components of Project Development
Fully “Baked” Project
Feedstock Technology- Operations
Offtake Finance
(WSA) Permitting
5. Key Elements of Project Delivery
• Design
– Preliminary Design Engineering
– Detail Design Engineering
• Build
– Procurement
– Construction Management
– Construction
– Commissioning
• Operate
– Operations
– Maintenance
• Own/Transfer
9. Tools and Terminology
• “Statement of Requirements”
– Prepared by Developer and/or Owner
– Captures key project information and goals
• “Project Execution Plan”
– Prepared by Engineering Firm
– Captures project execution strategy and milestones
• “Basis of Design” (BOD) - Preliminary Engineering
– Prepared by Engineering Firm
– 30% design with +/- 25% Cost accuracy
– Crucial preliminary engineering required for;
• Permitting
• Siteing
• Project Finance
10. Preliminary Engineering
• Preliminary Engineering Typically Includes:
– Project Execution Plan
– Process Flow Diagram
– General Arrangement Drawings with Equipment Layouts
– Site Plans
– Preliminary Equipment List with Sizes
– Heat and Mass Balance/P&ID’s
– Electrical Single Line
– Motor List and Electrical Loads
– Interconnect plan
– Process controls outline
– PHA – Process Hazard Analysis
– O&M Plan with estimated costs
– Project Cost Estimate