SlideShare ist ein Scribd-Unternehmen logo
1 von 102
Taking the Blinders off MS Project  by Ed Mahler  [email_address] President, Project Administration Institute Taking the Blinders off MS Project  and The case for 3rd Party Scheduling Services Taking the Blinders off MS Project
Contents ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Purpose ,[object Object],[object Object],[object Object],To illustrate how the MS Project schedule can be made more visible for Contents
Why so much interest in the schedule? + SME’s = Sponsor Schedule ’ s vision Project Manager Project Contents Cost Time Scope Team/sponsor communication + Contract negotiation =
Why do we need a schedule/contract? ,[object Object],[object Object],[object Object],Contents ,[object Object],[object Object],[object Object],[object Object]
The Schedule Contents Must be visible so the parties understand what they are agreeing to
Task Building block of the schedule Contents
Task/Resources FS Its attributes Contents Successors Duration Predecessors
Task/Resources Predecessors FF Its relationships Contents Successors
Task/Resources Predecessors SS Its relationships Contents Successors
Task/Resources Predecessors Lag Its relationships Contents Successors
Task/Resources Predecessors Overlap Its relationships Contents Successors
Task/Resources Predecessors SF Its relationships Contents Successors
Task/Resources Its relationships Contents Successors External Dependency
Task/Resources Its relationships Contents Duration Predecessors Deliverables
Understanding the schedule ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Contents For each task in the schedule what do you need to see?
Where the schedule originates ,[object Object],[object Object],[object Object],[object Object],[object Object],Contents A schedule is constructed from any combination of the following
MSP out of the box Gantt diagram The Gantt Chart view Contents
Gantt diagram The Gantt Chart view MSP out of the box Contents The Entry Table The View menu
The entry table Gantt diagram The Gantt Chart view Contents all FS except this one is FF+ Task name Task duration Task start Task finish Predecessors Resources
The entry table Contents Indicator
Contents The entry table Indicator
Contents The entry table Indicator
Summary tasks Contents Summary tasks Overall duration Earliest start Latest finish Summary tasks
Adding a project summary Contents Tools Options
Adding a project summary Contents View tab Select Project Summary Task OK
The project summary is task 0 Contents Project Duration Project Start Project Finish
Changing summaries from days to weeks Contents Tools Options
Changing summaries from days to weeks Contents Schedule tab Change “Duration entered in” from days to weeks OK
All summary durations now in weeks Changing summaries from days to weeks Contents
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],MSP out of the box Contents For each task in the schedule what do you need to see?
Adding the Successors column Right click the column heading and Insert Column Contents
Select Successors from the pull down Adding the Successors column Contents
Added Successors column What can’t happen until this task is done? Contents To find missing successors click the filter pull down and Use a No Successors Filter to identify missing successors
What can’t happen until this task is done? Only lines with blank  Successor cells appear but without the rest of the schedule can’t see where to connect them Contents
Changing  the filter to highlight tasks By editing the view Contents and turning on the Highlight filter
Highlighted missing successors No Successors Filter Contents One can see the missing Successors in the context of the whole schedule
Add the missing Successors Adding missing successors Contents This missing successor is a project deliverable
Use the No Predecessors Filter to identify missing predecessors What about missing predecessors Contents Missing Predecessors
Inserting constraint type and date columns Contents
And running the “Tasks w constraints” filter Use the Tasks w Constraints Filter to identify date constraints Contents with date constraints confirms they are external dependencies Missing Predecessors
[object Object],[object Object],[object Object],[object Object],[object Object],MSP out of the box plus Contents For each task in the schedule what do you need to see? ,[object Object],[object Object],[object Object]
Inserting a column for notes Contents Indicator Add the Notes field
Use tools/options to reduce column width req’ts Reduce  duration and date formats Contents
Now reduce  column widths Then reduce column widths Contents
Reduced  column widths and eliminate unneeded  columns Contents and eliminate unneeded  column
The team now has what they need to understand the schedule except..... What should be under way or done by 11/18? Contents
What should be under way or complete by 11/18? Adding columns to indicate what should be under way or done by a status date Contents
Defining customized fields Right click on the column heading Select Contents
The logic behind the field Select Contents Rename the field Create a formula for the field Select the graphic to display for each value of the formula
What should be under way or complete by now? Contents As of Sunday 11/18 status date
1 task should be executing, starting 11/1, finishing 12/12 What should be under way or complete by now? This project is under way Contents Total to do count
Making the Gantt more informative Project start date line Contents Status date line Slack or float
Saving the baseline plan Gray bars are the baseline plan Contents
Customizing the toolbar – menu shortcuts Views Contents Tables Filters Project Information Baselining and un Baselining the plan Baselining and un Baselining a task Task on schedule button
Customizing the toolbar – macro buttons Contents Open, link, and unlink the common resource DB Highlight the predecessor chain to a task Prefix the external dependencies and deliverables
[object Object],[object Object],[object Object],[object Object],[object Object],Planning iterations Contents
Execution Contents Contractual parties must have visibility into what’s happening so they can agree to the changes
Execution visibility ,[object Object],[object Object],[object Object],Contents ,[object Object]
Initial Plan table Contents Status update for 12/2 1 To Do as of 11/18
Contents The Status Report table Status Report table To do & to do count columns Reschedule & reschedule count columns Baseline finish Finish variance
Contents Changing the Status date Project information button Change the Status Date from 11/18
Contents to 2 weeks later to 12/2 OK
3 to do’s are flagged Red balls indicate the tasks are on the critical path Contents 12/2 to do’s
Status reporting recommendation ,[object Object],Contents ,[object Object],[object Object],[object Object],[object Object]
the to do flag disappears Contents MS Project is told that task 2 is on schedule MSP calculates the task is 92% complete as of 12/2
Task 5 now 6 weeks, is going to 9 weeks Contents MS Project is told that task 5 needs 3 more wks
Slippage and the ripple effect ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Contents ,[object Object]
Arrows indicate which tasks moved from baseline  Contents Stretching task 5 to 9 weeks and the ripple effect Finish Variance indicates how much each task moved Task 17 moved into the future and is no longer a to do 21 tasks have changed their finish dates Vertical arrows are on the critical path Gantt bars illustrate changes from baseline
Contents MSP is told task 5 is on schedule for new date The to do ball disappears MSP calculates task 5 is 51% complete The Gantt bar shows progress to the status date Project finish date slipped from 3/6 to 3/27, 3 weeks to do’s goes to 0
Switch to the Planning table Contents Recovering from slippage – step 1 Changes to critical path (blue) tasks will affect the project end date Turn on the Critical Path filter  Objective: Deliverable finish variance back to 0  Reduce task 23 from 2 wks to 1 wk
Reduce task 23 from 2 wks to 1 wk Contents Recovering from slippage – step 2 Deliverable finish variance goes from 3 wks to 2 wks
Contents Rerun the Critical Path filter after each change  Recovering from slippage – step 3 TC production, task 6, can be reduced to 1 week duration
Reducing task 6 to 1 week took it off the critical path Contents Recovering from slippage – step 4 but didn’t change the deliverable finish variance
Another candidate for reduction is Procurement, task 21 Contents Recovering from slippage – step 5 PM reduces it from 5 weeks to 3
Procurement is now off the critical path Contents Recovering from slippage – step 6 Reduce Samples from 4 weeks to 3 but Samples, task 7, is back on the critical path and deliverable finish variance is down to 1 week
Samples is now off the critical path Contents Recovering from slippage – step 7 but project finish variance is still 1 week The PM reduces Issue beverage docs, task 15, from 5 weeks to 4
Note that almost everything is now back on the critical path. Contents Recovering from slippage – step 8 Original schedule is restored Reducing, task 15 from 5 weeks to 4 Deliverable finish variance is back to 0
Switch to the Status table Status summary – what changed? Contents Duration change filter Changes from baseline 6 duration changes (blue highlights) Project duration change
Status summary – what changed? Remaining project to do’s Contents 16 finish variences (blue arrows) Project 15% complete Status summary notes Project finish variance
Reporting via pdf ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Contents
Status summary to team – what changed? Contents Finish variance & duration change filter Status as of date
Basic report for marketing Contents Duration Who Start Finish
For marketing people that don’t like Gantt charts Contents
More detail for project team Contents Predecessors Successors Constraint
For project teams that don’t like Gantt charts Contents
Milestone Gantt Contents For those who only like pictures
Portfolio management DB Contents Project name contact date status update notes risks PM PM’s Mgr deliverable target date status code
Contents Portfolio management DB next status update % complete Wks to next update Mtg date for next update Wk of this status update
Contents Portfolio management DB Number of tasks in the schedule Number of days deliverable moved To do’s for next update Number of rescheduled tasks
Lessons Learned ,[object Object],[object Object],[object Object],[object Object],[object Object],Contents ,[object Object]
The case for 3rd Party Scheduling Services by Ed Mahler  [email_address] President, Project Administration Institute Contents
Two kinds of companies Contents ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
What is a scheduling service? ,[object Object],[object Object],[object Object],Contents
[object Object],[object Object],What is a scheduling service? Contents ,[object Object]
[object Object],Aptitudes Compulsive Doer Leader Motivator Political Communicator Good w tools Multitasking Organizer Administrator Planner Obsessive Contents Project Manager Scheduler
Contents
Wikipedia Contents In many industries, such as engineering and construction; the development and maintenance of the project schedule is the responsibility of a full time scheduler or team of schedulers, depending on the size of the project.
The project management bible
Kerzner on scheduling Contents
Benefits of a scheduling service over PM’s doing their own ,[object Object],Contents 1) 2) 3) 4) 5) 6) 7) 8) 9) Money saved on Microsoft Project tool training and product licenses New PM’s are productive sooner Planning, tracking, and reporting are consistent in format, terminology, and quality across the organization’s projects.  PM standards training and policing is eliminated Administers formal tracking process to ensure plan currency, helps the PM manage change Maintains a common resource DB ensuring consistent resource naming across projects and enables cross project resource loading analysis Provides portfolio rollup reporting for management Provides one stop reporting source for interested parties Maintains the organization’s project history Reduces the ability of the PM to hide slippage until its too late 10)
Taking the Blinders off MS Project  by Ed Mahler  [email_address] President, Project Administration Institute Taking the Blinders off MS Project  and The case for 3rd Party Scheduling Services

Weitere ähnliche Inhalte

Was ist angesagt?

How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
Product Management Training - MS Project Training
Product Management Training - MS Project TrainingProduct Management Training - MS Project Training
Product Management Training - MS Project Trainingguest2739cfb
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouCA Technologies
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003pparakh
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)Sridhar Srinivas, PMP, CSM
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialAnil Purushothaman
 
Microsoft Project Beginners Workshop
Microsoft Project Beginners WorkshopMicrosoft Project Beginners Workshop
Microsoft Project Beginners Workshopdominiquechiu
 
Master MSProject 2010
Master MSProject 2010Master MSProject 2010
Master MSProject 2010Amr Miqdadi
 

Was ist angesagt? (20)

How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Product Management Training - MS Project Training
Product Management Training - MS Project TrainingProduct Management Training - MS Project Training
Product Management Training - MS Project Training
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for You
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
Using Microsoft Project 2003
Using Microsoft Project 2003Using Microsoft Project 2003
Using Microsoft Project 2003
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
PPTs on MS Project 2010
PPTs on MS Project 2010PPTs on MS Project 2010
PPTs on MS Project 2010
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)10 key features of microsoft project plan (mpp)
10 key features of microsoft project plan (mpp)
 
Microsoft Office Project 2007 Tutorial
Microsoft Office Project 2007 TutorialMicrosoft Office Project 2007 Tutorial
Microsoft Office Project 2007 Tutorial
 
Microsoft Project Beginners Workshop
Microsoft Project Beginners WorkshopMicrosoft Project Beginners Workshop
Microsoft Project Beginners Workshop
 
MS Project 2007 Tips and Tricks
MS Project 2007 Tips and TricksMS Project 2007 Tips and Tricks
MS Project 2007 Tips and Tricks
 
Microsoft Project 2013
Microsoft Project 2013Microsoft Project 2013
Microsoft Project 2013
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Master MSProject 2010
Master MSProject 2010Master MSProject 2010
Master MSProject 2010
 

Andere mochten auch

Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010Monica Di Bratto
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMPSubodh Kumar
 
MS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamMS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamRalf C. Adam
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
Documentation Project Management
Documentation Project ManagementDocumentation Project Management
Documentation Project ManagementLarry Kunz
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completionRonie Chu
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGAnjneya Srivastava
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012Yusuf Yıldız
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical CompletionsAndy Lang
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)Isai Perez
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies Capterra
 

Andere mochten auch (20)

MS Project
MS ProjectMS Project
MS Project
 
Getting started with MS Project 2010
Getting started with MS Project 2010Getting started with MS Project 2010
Getting started with MS Project 2010
 
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
Project Management Cycle and  MS Project 2013  By Subodh Kumar PMPProject Management Cycle and  MS Project 2013  By Subodh Kumar PMP
Project Management Cycle and MS Project 2013 By Subodh Kumar PMP
 
MS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. AdamMS-Project - Unleash the Force | Ralf C. Adam
MS-Project - Unleash the Force | Ralf C. Adam
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
Typical qms-construction-docs
Typical qms-construction-docsTypical qms-construction-docs
Typical qms-construction-docs
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
duplex villa ppt
duplex villa pptduplex villa ppt
duplex villa ppt
 
Documentation Project Management
Documentation Project ManagementDocumentation Project Management
Documentation Project Management
 
Mechanical completion
Mechanical completionMechanical completion
Mechanical completion
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012FTA Construction Management Handbook - 2012
FTA Construction Management Handbook - 2012
 
Guide ms project tutorial
Guide ms project tutorialGuide ms project tutorial
Guide ms project tutorial
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Mechanical Completions
Mechanical CompletionsMechanical Completions
Mechanical Completions
 
Microsoft project 2010 (final)
Microsoft project 2010 (final)Microsoft project 2010 (final)
Microsoft project 2010 (final)
 
Villa
VillaVilla
Villa
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies The Ultimate Review of Construction Project Management Methodologies
The Ultimate Review of Construction Project Management Methodologies
 

Ähnlich wie Taking Blinders MS Project Scheduling

Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part bSiep Littooij
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectWanBK Leo
 
Module 03 Planning and SchedulingTotal Points Possible30Insu.docx
Module 03 Planning and SchedulingTotal Points Possible30Insu.docxModule 03 Planning and SchedulingTotal Points Possible30Insu.docx
Module 03 Planning and SchedulingTotal Points Possible30Insu.docxannandleola
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
TTP-3 Project Schedule with Task Dependency Links (Team projec.docx
TTP-3 Project Schedule with Task Dependency Links (Team projec.docxTTP-3 Project Schedule with Task Dependency Links (Team projec.docx
TTP-3 Project Schedule with Task Dependency Links (Team projec.docxjuliennehar
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project ManagementGoutama Bachtiar
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.TURKI , PMP
 
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxBSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxAASTHA76
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.pptMohammadReza60255
 
GANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingGANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingThangamjayarani
 
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
 Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docxMARRY7
 

Ähnlich wie Taking Blinders MS Project Scheduling (20)

Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Microsoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptxMicrosoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptx
 
Training pm jan 11 part b
Training pm jan 11 part bTraining pm jan 11 part b
Training pm jan 11 part b
 
TID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft ProjectTID Chapter 6 Introduction To Microsoft Project
TID Chapter 6 Introduction To Microsoft Project
 
Ms Project
Ms ProjectMs Project
Ms Project
 
Module 03 Planning and SchedulingTotal Points Possible30Insu.docx
Module 03 Planning and SchedulingTotal Points Possible30Insu.docxModule 03 Planning and SchedulingTotal Points Possible30Insu.docx
Module 03 Planning and SchedulingTotal Points Possible30Insu.docx
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
Session 5 4th edition PMP
Session 5 4th edition PMPSession 5 4th edition PMP
Session 5 4th edition PMP
 
Pm short course
Pm short coursePm short course
Pm short course
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Chapter 3
Chapter 3Chapter 3
Chapter 3
 
TTP-3 Project Schedule with Task Dependency Links (Team projec.docx
TTP-3 Project Schedule with Task Dependency Links (Team projec.docxTTP-3 Project Schedule with Task Dependency Links (Team projec.docx
TTP-3 Project Schedule with Task Dependency Links (Team projec.docx
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.
 
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docxBSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
BSBPMG522A Undertake project workProject Planning TemplatesBSBP.docx
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Time Management ICTI.ppt
Project Time Management ICTI.pptProject Time Management ICTI.ppt
Project Time Management ICTI.ppt
 
GANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursingGANTT CHART nursing Management for Msc nursing
GANTT CHART nursing Management for Msc nursing
 
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
 Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
Franchise Agreement Analysis Paper Guidelines and Grading Guide.docx
 

Kürzlich hochgeladen

Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 

Kürzlich hochgeladen (20)

Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 

Taking Blinders MS Project Scheduling

  • 1. Taking the Blinders off MS Project by Ed Mahler [email_address] President, Project Administration Institute Taking the Blinders off MS Project and The case for 3rd Party Scheduling Services Taking the Blinders off MS Project
  • 2.
  • 3.
  • 4. Why so much interest in the schedule? + SME’s = Sponsor Schedule ’ s vision Project Manager Project Contents Cost Time Scope Team/sponsor communication + Contract negotiation =
  • 5.
  • 6. The Schedule Contents Must be visible so the parties understand what they are agreeing to
  • 7. Task Building block of the schedule Contents
  • 8. Task/Resources FS Its attributes Contents Successors Duration Predecessors
  • 9. Task/Resources Predecessors FF Its relationships Contents Successors
  • 10. Task/Resources Predecessors SS Its relationships Contents Successors
  • 11. Task/Resources Predecessors Lag Its relationships Contents Successors
  • 12. Task/Resources Predecessors Overlap Its relationships Contents Successors
  • 13. Task/Resources Predecessors SF Its relationships Contents Successors
  • 14. Task/Resources Its relationships Contents Successors External Dependency
  • 15. Task/Resources Its relationships Contents Duration Predecessors Deliverables
  • 16.
  • 17.
  • 18. MSP out of the box Gantt diagram The Gantt Chart view Contents
  • 19. Gantt diagram The Gantt Chart view MSP out of the box Contents The Entry Table The View menu
  • 20. The entry table Gantt diagram The Gantt Chart view Contents all FS except this one is FF+ Task name Task duration Task start Task finish Predecessors Resources
  • 21. The entry table Contents Indicator
  • 22. Contents The entry table Indicator
  • 23. Contents The entry table Indicator
  • 24. Summary tasks Contents Summary tasks Overall duration Earliest start Latest finish Summary tasks
  • 25. Adding a project summary Contents Tools Options
  • 26. Adding a project summary Contents View tab Select Project Summary Task OK
  • 27. The project summary is task 0 Contents Project Duration Project Start Project Finish
  • 28. Changing summaries from days to weeks Contents Tools Options
  • 29. Changing summaries from days to weeks Contents Schedule tab Change “Duration entered in” from days to weeks OK
  • 30. All summary durations now in weeks Changing summaries from days to weeks Contents
  • 31.
  • 32. Adding the Successors column Right click the column heading and Insert Column Contents
  • 33. Select Successors from the pull down Adding the Successors column Contents
  • 34. Added Successors column What can’t happen until this task is done? Contents To find missing successors click the filter pull down and Use a No Successors Filter to identify missing successors
  • 35. What can’t happen until this task is done? Only lines with blank Successor cells appear but without the rest of the schedule can’t see where to connect them Contents
  • 36. Changing the filter to highlight tasks By editing the view Contents and turning on the Highlight filter
  • 37. Highlighted missing successors No Successors Filter Contents One can see the missing Successors in the context of the whole schedule
  • 38. Add the missing Successors Adding missing successors Contents This missing successor is a project deliverable
  • 39. Use the No Predecessors Filter to identify missing predecessors What about missing predecessors Contents Missing Predecessors
  • 40. Inserting constraint type and date columns Contents
  • 41. And running the “Tasks w constraints” filter Use the Tasks w Constraints Filter to identify date constraints Contents with date constraints confirms they are external dependencies Missing Predecessors
  • 42.
  • 43. Inserting a column for notes Contents Indicator Add the Notes field
  • 44. Use tools/options to reduce column width req’ts Reduce duration and date formats Contents
  • 45. Now reduce column widths Then reduce column widths Contents
  • 46. Reduced column widths and eliminate unneeded columns Contents and eliminate unneeded column
  • 47. The team now has what they need to understand the schedule except..... What should be under way or done by 11/18? Contents
  • 48. What should be under way or complete by 11/18? Adding columns to indicate what should be under way or done by a status date Contents
  • 49. Defining customized fields Right click on the column heading Select Contents
  • 50. The logic behind the field Select Contents Rename the field Create a formula for the field Select the graphic to display for each value of the formula
  • 51. What should be under way or complete by now? Contents As of Sunday 11/18 status date
  • 52. 1 task should be executing, starting 11/1, finishing 12/12 What should be under way or complete by now? This project is under way Contents Total to do count
  • 53. Making the Gantt more informative Project start date line Contents Status date line Slack or float
  • 54. Saving the baseline plan Gray bars are the baseline plan Contents
  • 55. Customizing the toolbar – menu shortcuts Views Contents Tables Filters Project Information Baselining and un Baselining the plan Baselining and un Baselining a task Task on schedule button
  • 56. Customizing the toolbar – macro buttons Contents Open, link, and unlink the common resource DB Highlight the predecessor chain to a task Prefix the external dependencies and deliverables
  • 57.
  • 58. Execution Contents Contractual parties must have visibility into what’s happening so they can agree to the changes
  • 59.
  • 60. Initial Plan table Contents Status update for 12/2 1 To Do as of 11/18
  • 61. Contents The Status Report table Status Report table To do & to do count columns Reschedule & reschedule count columns Baseline finish Finish variance
  • 62. Contents Changing the Status date Project information button Change the Status Date from 11/18
  • 63. Contents to 2 weeks later to 12/2 OK
  • 64. 3 to do’s are flagged Red balls indicate the tasks are on the critical path Contents 12/2 to do’s
  • 65.
  • 66. the to do flag disappears Contents MS Project is told that task 2 is on schedule MSP calculates the task is 92% complete as of 12/2
  • 67. Task 5 now 6 weeks, is going to 9 weeks Contents MS Project is told that task 5 needs 3 more wks
  • 68.
  • 69. Arrows indicate which tasks moved from baseline Contents Stretching task 5 to 9 weeks and the ripple effect Finish Variance indicates how much each task moved Task 17 moved into the future and is no longer a to do 21 tasks have changed their finish dates Vertical arrows are on the critical path Gantt bars illustrate changes from baseline
  • 70. Contents MSP is told task 5 is on schedule for new date The to do ball disappears MSP calculates task 5 is 51% complete The Gantt bar shows progress to the status date Project finish date slipped from 3/6 to 3/27, 3 weeks to do’s goes to 0
  • 71. Switch to the Planning table Contents Recovering from slippage – step 1 Changes to critical path (blue) tasks will affect the project end date Turn on the Critical Path filter Objective: Deliverable finish variance back to 0 Reduce task 23 from 2 wks to 1 wk
  • 72. Reduce task 23 from 2 wks to 1 wk Contents Recovering from slippage – step 2 Deliverable finish variance goes from 3 wks to 2 wks
  • 73. Contents Rerun the Critical Path filter after each change Recovering from slippage – step 3 TC production, task 6, can be reduced to 1 week duration
  • 74. Reducing task 6 to 1 week took it off the critical path Contents Recovering from slippage – step 4 but didn’t change the deliverable finish variance
  • 75. Another candidate for reduction is Procurement, task 21 Contents Recovering from slippage – step 5 PM reduces it from 5 weeks to 3
  • 76. Procurement is now off the critical path Contents Recovering from slippage – step 6 Reduce Samples from 4 weeks to 3 but Samples, task 7, is back on the critical path and deliverable finish variance is down to 1 week
  • 77. Samples is now off the critical path Contents Recovering from slippage – step 7 but project finish variance is still 1 week The PM reduces Issue beverage docs, task 15, from 5 weeks to 4
  • 78. Note that almost everything is now back on the critical path. Contents Recovering from slippage – step 8 Original schedule is restored Reducing, task 15 from 5 weeks to 4 Deliverable finish variance is back to 0
  • 79. Switch to the Status table Status summary – what changed? Contents Duration change filter Changes from baseline 6 duration changes (blue highlights) Project duration change
  • 80. Status summary – what changed? Remaining project to do’s Contents 16 finish variences (blue arrows) Project 15% complete Status summary notes Project finish variance
  • 81.
  • 82. Status summary to team – what changed? Contents Finish variance & duration change filter Status as of date
  • 83. Basic report for marketing Contents Duration Who Start Finish
  • 84. For marketing people that don’t like Gantt charts Contents
  • 85. More detail for project team Contents Predecessors Successors Constraint
  • 86. For project teams that don’t like Gantt charts Contents
  • 87. Milestone Gantt Contents For those who only like pictures
  • 88. Portfolio management DB Contents Project name contact date status update notes risks PM PM’s Mgr deliverable target date status code
  • 89. Contents Portfolio management DB next status update % complete Wks to next update Mtg date for next update Wk of this status update
  • 90. Contents Portfolio management DB Number of tasks in the schedule Number of days deliverable moved To do’s for next update Number of rescheduled tasks
  • 91.
  • 92. The case for 3rd Party Scheduling Services by Ed Mahler [email_address] President, Project Administration Institute Contents
  • 93.
  • 94.
  • 95.
  • 96.
  • 98. Wikipedia Contents In many industries, such as engineering and construction; the development and maintenance of the project schedule is the responsibility of a full time scheduler or team of schedulers, depending on the size of the project.
  • 101.
  • 102. Taking the Blinders off MS Project by Ed Mahler [email_address] President, Project Administration Institute Taking the Blinders off MS Project and The case for 3rd Party Scheduling Services