Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Taking Blinders MS Project Scheduling
1. Taking the Blinders off MS Project by Ed Mahler [email_address] President, Project Administration Institute Taking the Blinders off MS Project and The case for 3rd Party Scheduling Services Taking the Blinders off MS Project
2.
3.
4. Why so much interest in the schedule? + SME’s = Sponsor Schedule ’ s vision Project Manager Project Contents Cost Time Scope Team/sponsor communication + Contract negotiation =
5.
6. The Schedule Contents Must be visible so the parties understand what they are agreeing to
18. MSP out of the box Gantt diagram The Gantt Chart view Contents
19. Gantt diagram The Gantt Chart view MSP out of the box Contents The Entry Table The View menu
20. The entry table Gantt diagram The Gantt Chart view Contents all FS except this one is FF+ Task name Task duration Task start Task finish Predecessors Resources
34. Added Successors column What can’t happen until this task is done? Contents To find missing successors click the filter pull down and Use a No Successors Filter to identify missing successors
35. What can’t happen until this task is done? Only lines with blank Successor cells appear but without the rest of the schedule can’t see where to connect them Contents
36. Changing the filter to highlight tasks By editing the view Contents and turning on the Highlight filter
37. Highlighted missing successors No Successors Filter Contents One can see the missing Successors in the context of the whole schedule
38. Add the missing Successors Adding missing successors Contents This missing successor is a project deliverable
39. Use the No Predecessors Filter to identify missing predecessors What about missing predecessors Contents Missing Predecessors
41. And running the “Tasks w constraints” filter Use the Tasks w Constraints Filter to identify date constraints Contents with date constraints confirms they are external dependencies Missing Predecessors
50. The logic behind the field Select Contents Rename the field Create a formula for the field Select the graphic to display for each value of the formula
51. What should be under way or complete by now? Contents As of Sunday 11/18 status date
52. 1 task should be executing, starting 11/1, finishing 12/12 What should be under way or complete by now? This project is under way Contents Total to do count
53. Making the Gantt more informative Project start date line Contents Status date line Slack or float
55. Customizing the toolbar – menu shortcuts Views Contents Tables Filters Project Information Baselining and un Baselining the plan Baselining and un Baselining a task Task on schedule button
56. Customizing the toolbar – macro buttons Contents Open, link, and unlink the common resource DB Highlight the predecessor chain to a task Prefix the external dependencies and deliverables
61. Contents The Status Report table Status Report table To do & to do count columns Reschedule & reschedule count columns Baseline finish Finish variance
62. Contents Changing the Status date Project information button Change the Status Date from 11/18
64. 3 to do’s are flagged Red balls indicate the tasks are on the critical path Contents 12/2 to do’s
65.
66. the to do flag disappears Contents MS Project is told that task 2 is on schedule MSP calculates the task is 92% complete as of 12/2
67. Task 5 now 6 weeks, is going to 9 weeks Contents MS Project is told that task 5 needs 3 more wks
68.
69. Arrows indicate which tasks moved from baseline Contents Stretching task 5 to 9 weeks and the ripple effect Finish Variance indicates how much each task moved Task 17 moved into the future and is no longer a to do 21 tasks have changed their finish dates Vertical arrows are on the critical path Gantt bars illustrate changes from baseline
70. Contents MSP is told task 5 is on schedule for new date The to do ball disappears MSP calculates task 5 is 51% complete The Gantt bar shows progress to the status date Project finish date slipped from 3/6 to 3/27, 3 weeks to do’s goes to 0
71. Switch to the Planning table Contents Recovering from slippage – step 1 Changes to critical path (blue) tasks will affect the project end date Turn on the Critical Path filter Objective: Deliverable finish variance back to 0 Reduce task 23 from 2 wks to 1 wk
72. Reduce task 23 from 2 wks to 1 wk Contents Recovering from slippage – step 2 Deliverable finish variance goes from 3 wks to 2 wks
73. Contents Rerun the Critical Path filter after each change Recovering from slippage – step 3 TC production, task 6, can be reduced to 1 week duration
74. Reducing task 6 to 1 week took it off the critical path Contents Recovering from slippage – step 4 but didn’t change the deliverable finish variance
75. Another candidate for reduction is Procurement, task 21 Contents Recovering from slippage – step 5 PM reduces it from 5 weeks to 3
76. Procurement is now off the critical path Contents Recovering from slippage – step 6 Reduce Samples from 4 weeks to 3 but Samples, task 7, is back on the critical path and deliverable finish variance is down to 1 week
77. Samples is now off the critical path Contents Recovering from slippage – step 7 but project finish variance is still 1 week The PM reduces Issue beverage docs, task 15, from 5 weeks to 4
78. Note that almost everything is now back on the critical path. Contents Recovering from slippage – step 8 Original schedule is restored Reducing, task 15 from 5 weeks to 4 Deliverable finish variance is back to 0
79. Switch to the Status table Status summary – what changed? Contents Duration change filter Changes from baseline 6 duration changes (blue highlights) Project duration change
80. Status summary – what changed? Remaining project to do’s Contents 16 finish variences (blue arrows) Project 15% complete Status summary notes Project finish variance
81.
82. Status summary to team – what changed? Contents Finish variance & duration change filter Status as of date
88. Portfolio management DB Contents Project name contact date status update notes risks PM PM’s Mgr deliverable target date status code
89. Contents Portfolio management DB next status update % complete Wks to next update Mtg date for next update Wk of this status update
90. Contents Portfolio management DB Number of tasks in the schedule Number of days deliverable moved To do’s for next update Number of rescheduled tasks
91.
92. The case for 3rd Party Scheduling Services by Ed Mahler [email_address] President, Project Administration Institute Contents
98. Wikipedia Contents In many industries, such as engineering and construction; the development and maintenance of the project schedule is the responsibility of a full time scheduler or team of schedulers, depending on the size of the project.
102. Taking the Blinders off MS Project by Ed Mahler [email_address] President, Project Administration Institute Taking the Blinders off MS Project and The case for 3rd Party Scheduling Services