SlideShare ist ein Scribd-Unternehmen logo
1 von 52
Downloaden Sie, um offline zu lesen
Interim Assessment of the
 Future Internet
Public-Private Partnership
          May 2012




           Communications
           Networks, Content
           and Technology
More information on the European Union is available on the Internet: http://europa.eu

© European Union, 2012

The opinions expressed in this study are those of the authors and do not necessarily reflect
the views of the European Commission.

ISBN: 978-92-79-19895-3
doi: 10.2759/84215

Reproduction is authorised provided the source is acknowledged.

Printed in Belgium
EUROPEAN COMMISSION




Interim Assessment of the
      Future Internet
Public-Private Partnership
4




Assessment Panel Report

On behalf of the panel that performed the interim assessment
of the Future Internet Public-Private Partnership I am pleased to
present to the European Commission our report.




Luke Georghiou (Chair)




Anna Asimakopoulou




Piet Bel




Graham Vickery




Bob Malcolm (Rapporteur)
5
                                                                               T a b l e           o f      c o n t e n t s




Table of contents
EXECUTIVE SUMMARY
1.	INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

2.	 OBJECTIVES OF THE FI-PPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
	 2.1.	Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

3. 	    IMPLEMENTATION OF THE FI-PPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                       10
	       3.1.	Legal Framework . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .             10
	       3.2.	Programme Architecture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                        10
	       3.3. Programme Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                    11
	       3.4. Activities (July 2010 - April 2012) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                 12
	       3.5. Governance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .      14

4. FINDINGS OF THE PANEL .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                          15
	 4.1. Continuing relevance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                        15
	 4.2. Progress toward the objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                      16
	 4.3. Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .      20
	 4.4. Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .   21
	 4.5. Summary of findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                         21

5. THE PUBLIC PRIVATE PARTNERSHIP MECHANISM . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
	 5.1. The FI-PPP in comparison with other PPPs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

6. CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

7. RECOMMENDATIONS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                      29
	 7.1.  ecommendations for the Commission concerning Public-Private
       R
       Partnerships in Horizon 2020 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                    29
	 7.2. Recommendations for present partners in the programme . . . . . . . . . . . .                                                                               30
	 7.3.  ecommendations for the Commission concerning
       R
       the present programme . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                             31

ANNEX 1: PUBLIC-PRIVATE PARTNERSHIPS IN HORIZON 2020 . . . . . . . . . . . . . . . . . . .                                                                         33
ANNEX 2: COMPLEMENTARY GRANT AGREEMENT .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                                          35
ANNEX 3: OBJECTIVES OF THE INTERIM ASSESSMENT .. . . . . . . . . . . . . . . . . . . . . . . . . . .                                                               36
ANNEX 4: QUESTIONS ADDRESSED BY THE PANEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                                          37
ANNEX 5: COMPOSITION OF THE PANEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                                          39
ANNEX 6: EVIDENCE BASE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .                     41




                                                                                                                            Interim Assessment of the Future Internet Public-Private Partnership
6
                                              E x e c u t i v e   S u m m a r y




Executive Summary
                              The Panel that performed this Interim           infrastructure enabled by the future
                              Assessment of the Future Internet               internet are still valid.
                              Public-Private Partnership (FI-PPP)
                              finds that:                                    However the Panel also finds that:

                              •	he FI-PPP has been a valuable ex-
                                t                                            •	 he industrial participants in the FI-PPP
                                                                               t
                                periment in attempting to achieve              are not, in concert, fulfilling the role
                                impact similar to that of Joint Tech-          envisaged for them in a public-pri-
                                nology Initiatives (JTIs)1 but in a            vate partnership;
                                much shorter timescale than JTIs by          •	 he projects supported within the FI-PPP
                                                                               t
                                using the existing instruments of the          are, generally, making progress toward
                                7th Framework Programme;                       their own goals but not co-operating
                              •	he decision to use the instruments
                                t                                              sufficiently so as to achieve the goals
                                and processes of the 7th Framework             of the programme.
                                Programme to establish the pro-
                                gramme was valid in enabling a rapid         The table below summarises the full
                                response by the EU to technological          set of recommendations, indicating
                                and market developments;                     those which could and should be im-
                              •	he market and technological situation
                                t                                            plemented during the life of the FI-PPP
                                is such that the aims of the FI-PPP to       and recommendations for any follow-on
                                accelerate technological development         initiative.
                                and take-up by engaging early-adop-
                                ter users to identify their needs for




    No.    Summary of recommendation                                                                    Time-frame

            Recommendations for the Commission concerning PPPs in Horizon 2020

    1      Establish guidance on governance of PPPs                                                       WP2014

    2      Ensure that each PPP has an effective central governing body                                   WP2014

    3      PPPs should be able to use the widest range of innovation-oriented instruments in              WP2014
           a coordinated manner.

    4      Re-design the process of calls for and selection of proposals to focus on achieving            WP2014
           greater ‘impact’.

    5      Participants in projects within programmes must collaborate fully so as to achieve             WP2014
           programme objectives.




	See http://cordis.europa.eu/fp7/jtis
1
7
                                       E x e c u t i v e   S u m m a r y




No.   Summary of recommendation                                                                         Time-frame

            Recommendations for present and future partners in the FI-PPP

6     Industrial participants should fulfil the role expected of them in a PPP.                               Now

7     The chairman of the Steering Board should be a senior executive of a company                        June 2012
      that is not a co-ordinator of any FI-PPP project.

8     The Advisory Board should focus their advice on bringing the results of the FI-PPP                    Now and
      to market.                                                                                           continuing

9     The programme should engage more energetically - and more visibly - with the                          Now and
      wider community of both users and technology providers                                               continuing

Recommendations for the European Commission concerning the present programme

10    Calls for tender should be considered for future ‘horizontal’ actions                                   Now

11    Future calls should emphasize the importance of take-up                                                 Now

12    Future calls should explicitly seek the engagement of representatives of the                          Now and
      broad community - industrial associations, public-sector associations, consumer                      continuing
      associations, etc, and, where appropriate, regulators.

13    Engage the innovative SME community better.                                                             Now

14    Make greater effort to achieve co-ordinated, co-operative behaviour of participants                     Now
      to achieve programme objectives.




                                                                  Interim Assessment of the Future Internet Public-Private Partnership
8
                                                        I N T R O D U C T I O N




1. Introduction
                            This document comprises the report by                     The Objectives of the FI-PPP and the
                            an independent panel of experts on an                     present status of its Implementation
                            Interim Assessment of the Future Inter-                   are described in the next two sections.
                            net Public-Private Partnership (FI-PPP)2.
                                                                                      This is followed by a major section that
                            The objectives of this assessment are to                  summarises the Findings of the Panel.

                            •	 valuate the concept of the FI-PPP;
                              e                                                       There is then a special section to address
                            •	 ssess progress in the first year;
                              a                                                       the performance of the programme as
                                                                                      a Public-Private Partnership.
                            •	 ffer recommendations to the European
                              o
                              Commission and to articipants in the                    The findings of the Panel are summa-
                              FI-PPP;                                                 rised in the Conclusions section, which
                            •	
                              bring forward proposals for how                         is followed by Recommendations for
                              to further develop the FI-PPP;                          both the present programme, to en-
                                                                                      hance achievement of their objectives,
                            •	
                              contribute to the guidelines for
                                                                                      and for future programmes with similar
                              public-private partnerships in Horizon
                                                                                      ambitions that may be considered in
                              2020.
                                                                                      Horizon 2020.
                            The Panel was asked to assess the FI-PPP
                                                                                      The Panel comprised a mix of experts,
                            with respect to:
                                                                                      including some with knowledge of the
                                                                                      technology and of its use in modern
                            •	 elevance: whether the original aims
                              R
                                                                                      infrastructures, and some with general
                              of the FI-PPP are still valid and wheth-
                                                                                      expertise in RD strategy and man-
                              er the programme architecture is still
                                                                                      agement. (See Annex 5)
                              appropriate for realising those aims;
                            •	 ffectiveness: progress towards the
                              E                                                       The Panel drew upon published infor-
                              objectives;                                             mation, interviews with participants in
                            •	 Efficiency: of the management and                     the projects of which the programme is
                                operation of the programme;                           comprised, representatives of the com-
                                                                                      munity addressed by the programme
                            •	 uality: of research and innovation,
                              Q
                                                                                      but not participating, and staff of the
                              and of the actors attracted to the
                                                                                      European Commission. (See Annex 6)
                              programme.3




2
 	
  This assessment took place toward the end of the first year of operation of the programme, approximately half-way through Phase 1.
3	
  Annex 4 sets out in greater detail the questions addressed by the panel in their consideration of these issues.
9
                                           O B J E C T I V E S      O F    T H E     F I - P P P




2. Objectives of the fi-ppp
The Future Internet Public Private Part-                 The public contribution to the partner-
nership (FI-PPP) aims to significantly                   ship comes from part-funding via the
advance the implementation and uptake                    European Commission for projects, pro-
of a European-scale market for ‘smart                    gramme design, management of calls
infrastructures’.4 The intention is to                   for proposals and programme monitoring,
accelerate technological development                     and the participation of public sector
for the future internet and in parallel,                 organisations as users in the develop-
synergistically, accelerate its adoption                 ment of requirements and in trials.
in ‘smart infrastructures’ - such as
smart energy grids, smart cities, smart                  The private sector contributed during the
environmental management systems,                        formulation of the concept of the PPP5
and smart systems for mobility. Ulti-                    with significant input from an indus-
mately the ambition is to make public                    trial grouping6 that presented their vision
service infrastructures and business                     to the European Commission in January
processes significantly smarter (i.e.                    2010. During the operation of the PPP, the
more intelligent, more efficient, more                   private sector contributes in the form of
sustainable) through tighter integra-                    financial support for their participation in
tion with Internet networking and com-                   projects and from their co-operation across
puting capabilities.                                     the programme (not just within projects).




2.1. Objectives
The aims and objectives of the FI-PPP                      trial partnerships built around Future
evolved during the formation of the                        Internet value chains, involving users
programme. The Panel has taken as                          and public authorities at local, regional
the objective of the programme the                         and national levels, and providing
expected impact - over all 3 phases -                      SME players with opportunities to
as set out in the Work Programme                           offer new products, equipments, ser-
2011-2012. This is a précis:                               vices and applications;
                                                         •	 reation of new European-scale markets
                                                           C
•	 ignificant increase of the effectiveness
  S                                                        for smart infrastructures contributing
  of business processes and novel                          to European leadership in global ICT
  approaches to the operation of infra-                    applications markets;
  structures and applications of high
  economic and/or societal value.                        •	Evolution of Future Internet infra-struc-
                                                            ture compatible with the emergence of
•	 einforced industrial capability on nov-
  R                                                         open, secure and trusted service;
  el service architectures and platforms;
                                                         •	 comprehensive approach towards
                                                           A
•	 ew opportunities for novel business
  N                                                        regulatory and policy issues.
  models based on cross-sector indus-


	
4
  “White paper on the Future Internet PPP Definition”, January 2010 (http://www.future-internet.eu/uploads/media/May2009.pdf)
	 ibid.
5

	 The ‘European Future Internet Initiative Founder Members’: a group of 16 companies supporting a Call for Action
6



                                                                                   Interim Assessment of the Future Internet Public-Private Partnership
10
                                       I M P L E M E N T A T I O N          O F    T H E     F I - P P P




3. mplementation of the fi-ppp
   I
                             3.1. Legal Framework

                             In order to implement the FI-PPP rap-                         facilitate collaboration and programme
                             idly - in recognition of the very dynamic                     coordination. This clause requires fore-
                             nature of this field - it was established                     ground knowledge to be sharable across
                             within the 7th Framework Programme. In                        all projects and it requires project benefi-
                             consequence, the FI-PPP is subject to the                     ciaries to participate in joint coordination
                             Regulations of the 7th Framework Pro-                         activities. (See Annex 2.)
                             gramme and must use the same project
                             instruments, the same call and evaluation                     Also, all participants have agreed to the
                             processes, and the same project review                        terms of a Collaboration Agreement that,
                             and programme monitoring processes.                           in addition to the standard terms of the
                                                                                           Framework Programme agreement, sets
                             However, in the grant agreement for each                      out the governance arrangements for
                             project in the programme the Commission                       the FI-PPP.7
                             introduced a special clause intended to


                             3.2. Programme Architecture
                             The programme has four major ‘building blocks’ (see diagram below)




7
 	
  “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.1.2 (i))
11
                                I M P L E M E N T A T I O N   O F   T H E   F I - P P P




The four building blocks are:                   still shared within those domains) and
                                                then instantiate their own domain-spe-
•	echnology Foundation - the devel-
  T                                             cific platforms.
  opment of components for a Core
  Platform, initially in the FI-WARE project;   The Infrastructure support project is in-
•	 se cases  trials - to establish user
  U                                             tended initially, in Phase 1, to identify
  requirements in 8 sectors, especially         existing and future advanced experi-
  for common components;                        mental infrastructures across Europe.
                                                However, the scope of the Phase 1
•	nfrastructure support - making best use
  I                                             project (awarded to INFINITY) has been
  of existing European infrastructures;         expanded to encompass other studies
•	 rogramme facilitation  support.
  P                                             of value to the FI-PPP. A subsequent
                                                project, planned for Phase 2, is intend-
It is intended that the use cases and           ed to integrate, federate and upgrade
trials projects should establish their          [existing infrastructures] towards serving
various requirements for enabling               large-scale trials8.
technology components and that in
liaison with the core platform project          The Programme Facilitation and Sup-
they should agree a set of ‘Generic             port project (awarded to CONCORD)
Enablers’ common to some or all of              should facilitate the development of an
the usage areas. The core platform              overall programme view and collabora-
project(s) will develop these and make          tion across all FI-PPP projects, support
them available to the use case projects         standardisation, SME involvement, links
as the Core Platform. The Use Case              with regulatory and other relevant policy
projects will in parallel be developing         activities, dissemination and awareness
the ‘Specific Enablers’ that they believe       raising9
necessary for their domains (though



3.3. Programme Schedule
The programme is planned to be im-              •	 stablish the programme support and
                                                  E
plemented in three phases over five               coordination structures.
years (as indicated in the diagram
above). The content of each phase is:           3.3.2. Phase 2 (April 2013 – March 2015)
                                                       

3.3.1.  hase 1 (April 2011 – March 2013)
       P                                        •	 nsure availability of test infrastructure
                                                  E
                                                  for early trials,
•	
  Define usage area requirements from           •	Develop the core platform and use case
  which the architecture and common                specific functionalities, and instantiate
  enablers of the core platform will be            them on the test infrastructure.
  derived; start developing components.
                                                •	 elect and run early trials for all use
                                                  S
•	 tart evaluation of test infrastructures
  S                                               cases and prepare large scale trials.
  and identify what must be done to
  bring infrastructures to the level nec-
  essary to enable trials.


	
8
 From the FI-PPP Work Programme 2011-2012
	ibid.
9



                                                                     Interim Assessment of the Future Internet Public-Private Partnership
12
                                       I M P L E M E N T A T I O N          O F    T H E     F I - P P P




                             3.3.3.  hase 3 (May 2014 – October 2015)
                                    P                                                      •	ncrease the involvement of SMEs as
                                                                                             I
                                                                                             developers and providers of services
                             •	 rovide and enrich a stable infrastruc-
                               P                                                             and applications.
                               ture for large scale trials populated
                               with a variety of applications to
                               prove the viability of the concept.



                             3.4. Activities (July 2010 - April 2012)
                             The total notional EC budget for the                          for additional organisations to join the
                             FI-PPP is €300M. The Commission                               consortium to provide certain components
                             has earmarked €170M of funding for                            of the core platform11. The FI-WARE
                             projects in the first two phases of the                       open calls are funded to the level of
                             FI-PPP and, subject to budgetary ap-                          € 12.4 million, or 30% of FI-WARE
                             proval, €130M for phase 3.                                    funding and 14 % of Phase 1 funding,
                                                                                           and are entirely managed and run by
                             The first call for proposals was                              the FI-WARE consortium, independent
                             launched in July 2010 and closed in                           of the Commission. The open call will
                             December 2010. The first projects of                          follow the general guidelines for open
                             the FI-PPP, selected from that call, began                    calls within FP7 projects12. To ensure
                             (in principle10) in April 2011.                               fair competition, present members of
                                                                                           the FI-WARE consortium are excluded
                             3.4.1. Distribution of FI-PPP Call 1                         from participation.
                                    funds among Member States

                             The distribution of funds in the FI-PPP (see
                             figure on next page) is generally similar
                             to that of Calls 5 and 7 of Challenge 1
                             in the ICT Programme of FP7 (also see
                             figure on next page) and approximately
                             reflects their GDP. The exceptions are a
                             relatively low participation in the FI-PPP
                             of the UK and new Member States
                             compared with their participation in
                             Challenge 1 of FP7 (which addresses a
                             similar segment of the RTD community).

                             Note that the figure below excludes the
                             funding for FI-WARE open calls (which
                             would distort the figures by assigning
                             the allocation of funds to the FI-WARE
                             coordinator). As part of Phase 1, the
                             core platform project (FI-WARE) will
                             extend participation through open calls


10
   	 ee section 4.3
     S
11
   	 he first such Open Call was made on two topics: Middleware for efficient and QoS/Security-aware invocation of services and exchange of
     T
     messages; and Business Models and Business Elements Definition and Simulation.
12
   	 See http://www.fi-ware.eu/open-call/
13
                             I M P L E M E N T A T I O N   O F   T H E   F I - P P P




A call for proposals for Phase 2 is due      of additional use cases domains such as
to be launched in May 2012, closing at       Ambient Assisted Living and eHealth,
the end of October 2012. This phase will
extend participation in the programme        It is intended to make a final call for
through mergers and re-alignment of ex-      proposals for Phase 3 projects in 2013.
isting user domains and the incorporation




                                                                  Interim Assessment of the Future Internet Public-Private Partnership
14
                                             I M P L E M E N T A T I O N            O F    T H E     F I - P P P




                                  3.5. Governance
                                  The diagram below indicates the governance structure of the FI-PPP.




                                  The Steering Board is the highest FI PPP                         •	
                                                                                                     requires replies by the Steering Board
                                  Program governing body. It:                                        to its recommendations and advice;
                                  •	 represents the FI-PPP owners;                                 •	 omprises 8 people at the time of this
                                                                                                     c
                                  •	 meets monthly (real or virtual);                                assessment, meeting twice per year14.
                                  •	 ust make decisions unanimously13,
                                     m                                                             Members of the Advisory Board are also
                                     without any option of escalation.                             expected to be ‘Ambassadors’ of the PPP
                                                                                                   and represent them at high level events
                                  The Architecture Board:                                          (e.g. in the Council and Parliament).
                                  •	s a forum for meetings of technical
                                    i
                                    managers;                                                      The PPP Secretariat (provided by CON-
                                  •	 eets monthly (either physically or
                                    m                                                              CORD):
                                    by video conference);                                          •	 ndertakes day-to-day facilitation of
                                                                                                     u
                                  •	s consensus driven, with unanimous
                                    i                                                                the governance processes;
                                    decision making;                                               •	acilitates the operation of ‘Working
                                                                                                     f
                                  •	
                                    escalates to the Steering Board in the                           Groups’, which are ‘temporary groups
                                    event of decisions that cannot be re-                            established for the performance of a
                                    solved by consensus.                                             specific task and not a fixed part of
                                                                                                     the permanent FII Program govern-
                                  The Advisory Board:                                                ance structure’.15
                                  •	s independent, with no access to de-
                                    i
                                    liverables per se;


13
     	 ith one exception: when a party to the Collaboration Agreement is in breach of its obligations they are not expected to contribute to the consensus.
       W
14
     	 he members of the Advisory Board were appointed in January, and at the time of this assessment have yet to meet.
       T
15
     	 “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.4)
15
                                             F I N D I N G S      O F    T H E    P A N E L




4. Findings of the panel
4.1. Continuing relevance

The opinion of those interviewed by the                  •  uropean society to benefit from early
                                                           E
panel is that the programme is still rel-                  provision of internet-enhanced services.
evant. The assertion of the 2008 ISTAG
report16 remains valid:                                  There has been a significant internet-en-
                                                         abled development in the market-place
“A critical interdependence for the suc-                 since the original formulation of the
cess of the Web-based service industry                   Future Internet vision. This is the recent
will be the extension of the Future In-                  rapid take-up of ‘Cloud Computing’ and
ternet by offering very rich ‘horizontal                 services which make extensive use of
services’. These services will foster an                 data and functionality (applications) ‘in
interoperability and trust framework                     the cloud’.17 The FI-WARE project does
for service integration, authentication,                 include work packages that address both
privacy and security. This framework                     cloud hosting and interoperation with
will enable the Web-based service in-                    third-party cloud facilities, so the
dustry to procure, extend and repur-                     programme has recognised this phe-
pose services to new markets.”                           nomenon and has, in principle, the
                                                         means to accommodate it.
The evolution of this concept into the
vision of the Future Internet that in-                   However, the continuing relevance of
spired the FI-PPP - of the evolution                     the specific structure and architecture
of the internet from mere communi-                       of the FI-PPP, with a project dedicated
cations network to an enabling smart                     to the development of standard re-us-
infrastructure - is still valid.                         able components for a ‘core platform’
                                                         is less clear. As will be discussed in the
Furthermore, the proposition that                        following section, some Use Case pro-
development of standard re-usable                        jects have plans to develop or acquire
components for a multi-sector common                     their own ‘enablers’ - ‘specific’ and ‘ge-
(‘core’) platform will accelerate both                   neric’ - so that they are not reliant on
technological development and take-up                    the core platform project. Also, some
also, according to the evidence gained                   Use Case projects are collaborating in
by the panel, remains valid.                             order to develop common Use Case en-
                                                         ablers that are outside the scope of the
Despite difficulties and delay - and                     core platform project - such enablers
possibly further delays still to come                    being neither ‘specific’ not ‘generic’.
- the work supported by the FI-PPP is                    This raises the possibility that common
still valuable in helping:                               enablers might be better encouraged
• uropean industry to accelerate its
  E                                                      to emerge from such collaborations
  contribution to the technological                      across domains, instead of having
  development required to realise the                    a dedicated core platform project. A
  vision of the Future Internet, and                     Technology Foundation project could


 	 eport of the Information Society Technologies Advisory Group Working Group on “Web-based Service Industry”, February 2008
16
  R
17
  Notwithstanding the long ‘cloud’ gestation period since the late 1950s/1960s

                                                                                 Interim Assessment of the Future Internet Public-Private Partnership
16
                                                      F I N D I N G S   O F   T H E   P A N E L




                                   still have a role in this by providing that          enablers. But such responsibilities do
                                   encouragement and by facilitating the                not appear to be within the present re-
                                   emergence of well-supported generic                  mit of FI-WARE.


                                   4.2. Progress toward the objectives
                                   The underlying concept of the programme              engaging with the broader community
                                   is that the synergistic development of a             beyond participants in the programme.
                                   core platform and its use in early take-             And despite leading industrial compa-
                                   up trials will be achieved through the               nies being partners in the various Use
                                   projects in the programme working in                 Cases, long term sustainable exploitation
                                   concert - particularly the core-platform             plans were considered vague or even
                                   project and the set of Use Case projects             non-existent, implying that the repre-
                                   (supported by the other two projects).               sentatives of the companies might not
                                                                                        be well-coupled to their strategic plan-
                                   It is not in the Terms of Reference for              ning or marketing departments.
                                   this panel to evaluate the individual
                                   projects, for which there are already                The ‘core platform’ project (FI-WARE)
                                   standard Framework Programme review                  should be liaising satisfactorily with the
                                   processes. However, the panel has used               Use Case projects and providing techni-
                                   the reports generated in that review                 cally well-constructed Generic Enablers
                                   process to inform its understanding of               in a timely fashion. However, the quality
                                   the operation of the programme. The                  of liaison with the Use Case projects has
                                   set of reviews made at the 6-month                   been very variable and reflects closely
                                   stage of the programme shows a mixed                 the performance of those projects.
                                   picture, with some Use Cases progress-               This suggests that FI-WARE has relied
                                   ing well and achieving interim targets,              upon dealing with well-organised user-
                                   while others had start-up problems and               communities and has not been able to
                                   were lagging badly at the time of the                resolve difficulties with less well-organ-
                                   first review.18                                      ised communities. Also (at the time of
                                                                                        this report) FI-WARE is 2 months late
                                   4.2.1. Progress of projects
                                                                                       overall, at the end of its first year.
                                          towards their objectives
                                                                                        The Programme Facilitation and Sup-
                                   The ‘Use Case’ projects are concerned                port project (CONCORD) is expected
                                   with the identification of requirements              to facilitate the development of an
                                   for enablers that truly reflect the needs            overall programme view and col-
                                   of the community of the application                  laboration across all FI-PPP projects,
                                   sector of the project. The 6-month                   support standardisation, develop key
                                   review reports indicated that at the                 performance indicators, SME involve-
                                   time of the review - during October                  ment, links with regulatory and other
                                   and November 2011 - about half the                   relevant policy activities, dissemination
                                   projects were performing reasonably                  and awareness raising. However, as the
                                   well in this regard, that others needed              Description of Work for the CONCORD
                                   to try harder, and that one project was              project clearly (and correctly) states
                                   in serious trouble. However, almost all              “the FI-PPP Programme deliverables
                                   Use Case projects were criticised for not            are not those of CONCORD project, but

18
     	 ee also section 4.3.1 ‘Efficiency of operation’
      S
17
                                                F I N D I N G S      O F    T H E     P A N E L




results that all FI-PPP Projects jointly                    (so far) are organisations that have not
contribute towards”. Yet CONCORD’s                          been involved in those calls20. This sug-
very central role implies significant re-                   gests that the programme has been
sponsibility for attempting to resolve                      successful in attracting the participation
programme management problems                               of a broader community than that of
that inhibit achievement of the pro-                        the traditional Framework Programme.
gramme’s goals. There is evidence that
while CONCORD was slow to take on                           However, most of the ‘new’ partici-
this responsibility and made a slow                         pants have only single participations
start in establishing the arrangements                      in the FI-PPP whereas, by comparison,
for programme management, it is now                         organisations among the original 16
perceived to be making serious efforts to                   ‘Founder Members’ have a 43% share
improve the situation.                                      of total participations in phase 1 of the
                                                            programme and have been allocated
The Infrastructure support project                          c. 44% of FI-PPP funding of phase 1,
(INFINITY) is expected to maximise                          excluding the allocation for FI-WARE
synergy with infrastructural develop-                       Open Calls.21 The new industrial par-
ments outside the FI-PPP. The Panel is                      ticipants that have not participated in
concerned that the project participants                     Calls 5 and 7 of Challenge 1 of FP7 have
do not fully share this view. Indeed the                    been allocated c. 13% of FI-PPP funding.
6-month programme-level reviewers
commented that INFINITY was ex-                             Specific objectives
pending effort on activities that were
not fully focused on helping the PPP                        The Use Case projects vary consider-
achieve its aims, and that it was not                       ably in their effectiveness in establishing
performing its role as an external face                     common requirements for their domains
of the FI-PPP.                                              and in their relationship with the core-
                                                            platform project (FI-WARE) so that their
4.2.2.  rogress of the programme
       P                                                    needs for ‘generic enablers’ will be satis-
       toward programme-level                               fied by FI-WARE.
       objectives
                                                            Some Use Case projects have successfully
Global objectives                                           identified their needs, communicated ef-
                                                            fectively with FI-WARE and are confident
According to data provided by the Com-                      that their needs will be met by FI-WARE.
mission, industry has been extremely                        Other Use Cases projects have not yet
responsive to the FI-PPP, with the con-                     agreed which of their needs will be met
sequence that in the FI-PPP, excluding                      by FI-WARE. And some who have identi-
the FI-WARE Open Call, industry has                         fied their needs for generic enablers have
taken a much higher share of availa-                        low confidence in FI-WARE’s ability to de-
ble funds - c. 66% compared with less                       liver them in time to enable them to fulfil
than 50% in recent calls of Challenge                       their (use case) project commitments and
1 of the 7th Framework Programme19.                         the terms of their funding contracts. Con-
                                                            sequently, some of these projects have
Moreover, approximately 64% of in-                          a contingency plan to supply or acquire
dustrial participants in the programme                      their own alternative components. This

19
   	 46% in Call 5 and 34% in Call 7
20
   	 3 out of 83 industrial participants. Also, 86 unique organisations, including industrial participants, out of a total of 149 organisations
     5
     participating in FI-PPP are not participating in Challenge 1 Calls 5 and 7.
21
  	 ote that these organisations also participate intensively elsewhere in the Framework Programme, with c.30% of participations in Challenge 1.
     N

                                                                                     Interim Assessment of the Future Internet Public-Private Partnership
18
                                                  F I N D I N G S       O F    T H E     P A N E L




                               is contrary to the notion of the FI-WARE                      of FI-WARE is accessible to all current
                               results being truly generic enablers and                      and future programme participants
                               of FI-WARE being the primary supplier of                      as foreground knowledge23. But the
                               these enablers to the Use Cases.                              FI-WARE contract does not require
                                                                                             FI-WARE to ‘hand over’ its results in a
                               Several reasons have been put forward                         way that they can be used effectively
                               for this mismatch between some Use                            by others or to support them in initial
                               Case projects and FI-WARE, including the                      adoption of the results or subsequently
                               relative timing of the project start-dates                    with maintenance or training. This has
                               and the methods used by FI-WARE for                           serious implications for the ‘Core Plat-
                               requirements elicitation and software                         form’ - especially when the FI-WARE
                               development. The lack of an agreed                            project terminates, leaving no possibility
                               view on these issues and the different                        of support around the time that large-
                               relationships of the Use Case projects                        scale trials commence.
                               to FI-WARE reflect three alternative at-
                               titudes to the development process:                           There is a serious risk that unless
                                                                                             strong preventive actions are taken
                               i. ne position is that truly generic
                                  O                                                          even the user areas that are for now
                                  enablers can be developed rather                           planning to use FI-WARE outputs will
                                  independently of the application ar-                       each have to take separate responsibil-
                                  eas: in this case the general view is                      ity for maintaining and evolving those
                                  that FI-WARE should have started                           components for their area, further
                                  six months or a year before the Use                        undermining the concept of generic ena-
                                  Cases so that the Use Cases would                          blers and a common core platform.24
                                  have an earlier idea what would be
                                  provided in the core platform.                             4.2.3. Direction and management
                                                                                                    of the programme
                               ii.  nother position is that the Use Cas-
                                   A
                                   es must identify their needs first and                    While the CONCORD project is expected
                                   then ‘specify’ their requirements of                      to ‘facilitate’ the achievement of the
                                   the core platform: in this case the                       goals of the programme, responsibility
                                   core platform project should have                         for their achievement lies with the FI-PPP
                                   started later than the Use Cases to                       projects ‘jointly’. But while the original vi-
                                   give the Use Case projects time to                        sion of those who brought the FI-PPP
                                   establish their requirements.                             into existence25 may still be valid, it is not
                                                                                             clear that that vision is shared by all the
                               iii.  third position is that of ‘agile’
                                    A                                                        present participants in the programme.
                                    (highly iterative) software develop-                     As indicated in section 4.2.2 above, the
                                    ment: this requires tight interaction                    programme has attracted new partici-
                                    between developer and user. This                         pants, with more than half the budget
                                    situation does not pertain for at                        allocated to organisations other than
                                    least some Use Case projects22.                          the Founder Members. Moreover, each
                                                                                             project has its own contract, its own con-
                               However, there is, potentially, a greater                     tractual obligations, and its own staffing
                               barrier to realisation of the concept                         and management that may not share a
                               of the FI-PPP. Formally, the outcome                          co-operative vision for the programme.
22
   	 The co-ordinator of one project told the panel that, after one year, the project is “now ready for a first face-to-face meeting with FI-WARE”.
23
  	 As a consequence of the special clause 41 in all FI-PPP grant agreements (see section 3.1 and Annex 2 of this report).
24
  	 I-WARE has indicated its willingness to co-operate so as to ameliorate the difficulties posed by the project not being required to provide
     F
     supported software for User Trials.
25
  	 Particularly the European Future Internet Initiative Founder Members: see the introduction to Section 2
19
                                               F I N D I N G S      O F    T H E     P A N E L




The programme should be resilient to the                   the whole programme and to monitor
involvement of organisations and person-                   and maintain progress towards the
nel not originally involved in its formulation             objectives of the programme: “The
and it should be open to new participants                  Steering Board is the highest FI PPP
and their contribution to the evolution of                 Program governing body.”28 However,
its vision. But to preserve its focus the                  the Steering Board has not acted with
programme needs rules, processes and                       urgency to address the difficulties that
mechanisms that enable the emergence                       the programme faces, and seems not
of an evolving shared vision and the                       to be doing what it is supposed to do -
commitment of projects to help realise                     provide overall Steering of the FI-PPP.
that vision. Yet the vision of the ‘Founder
Members’ did not address at all the re-                    At the operational level the Architecture
quirements for governance appropriate                      Board has been established and appears
to a public-private partnership (see Section               to be working well to address technical
5, below). Indeed, in January 2010, the                    issues. Various Working Groups have
European Commission told the Founder                       also been established (or at the time
Members “The companies26 should set                        of this assessment are in the process
up appropriate governance/manage-                          of being established)29. However, the
ment structures with full empowerment                      Steering Board has not demonstrated
from their company executives. This is a                   ‘ownership’ of the Architecture Board
precondition for the success of the ini-                   or the Working Groups or responsibil-
tiative”.27 They did not do that.                          ity for steering them so as to maximise
                                                           progress toward the programme ob-
The programme should also be resilient                     jectives. Communication between the
to changing market and technological                       Steering Board and the Architecture
environments - especially in such a fast-                  Board and between the Steering Board
moving field as the Future Internet. This                  and the Working Groups is lacking in
requires constant monitoring of the state                  both directions. In fact it is unclear how
of development of the relevant tech-                       the Working Groups will move from
nologies and markets, and the ability to                   the current perception of some project
adapt rapidly to any developments that                     members as an extra burden to be car-
affect the viability of the programme.                     ried to being seen as a positive source
The panel specifically sought to identify                  of value added.
who in the programme felt responsibil-
ity for ‘horizon scanning’ but received                    A number of those interviewed by the
no clear answer - albeit some of those                     panel commented on the inability of
interviewed considered the Architecture                    the Steering Board to make decisions
Board to have that responsibility. (But                    binding on projects that, given the con-
see the next paragraph concerning the                      tractual arrangements, are in effect
relationship between the Steering Board                    autonomous. The Commission broke
and the Architecture Board.)                               new ground in establishing the clause
                                                           in each contract to facilitate sharing
The Steering Board is, in principle, the                   of intellectual property and project
body to maintain coherent action over                      coordination across the programme.30

26
  	 The 16 ‘Founding Members’
27
  	 “ eport of the meeting between Zoran Stancic, Deputy Director General, DG-Infso, and the Future Internet core group
     R
     of industrial stakeholders (G16)”, D(10)203076, January 2010
28
  	 “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.1.2 (i))
29
  	 Gs have so far been agreed on Dissemination, Exploitation  Business Modelling, Standardisation, Policy  Regulation.
    W
    A further WG on Security and Privacy is under consideration.
30
  	 Clause 4 1 (see Annex 3 to this report)

                                                                                    Interim Assessment of the Future Internet Public-Private Partnership
20
                                                     F I N D I N G S       O F     T H E     P A N E L




                                  But this is not sufficient to enforce co-                      However, it is not evident to the panel
                                  operation. Indeed the programme-wide                           that the lack of direction and inability to
                                  Collaboration Agreement states: “The                           resolve problems demonstrated so far
                                  Steering Board shall however not be en-                        by the Steering Board derives only from
                                  titled to act or to make legally binding                       a lack of authority: it also seems to re-
                                  declarations on behalf of any Party, but                       flect a lack of a sense of responsibility.
                                  shall make recommendations for imple-
                                  mentation in respective FII Projects”.31                       The lack of urgency has been exacer-
                                                                                                 bated by slowness in establishing Key
                                  There is ongoing discussion in the                             Performance Indicators for monitoring
                                  Steering Group about the prospects                             the programme’s progress towards its
                                  for amendment of contracts to accom-                           objectives. (The KPIs that have been
                                  modate Steering Board authority - if                           established so far are primarily meas-
                                  not now then possibly for future phas-                         ures of operational performance rather
                                  es (when decision-making will have                             than measures of impact.)
                                  more significant commercial impact).


                                  4.3. Efficiency
                                  Only the first call for proposals was                          work should continue to accelerate the
                                  made during the period evaluated by                            process still further, though not at the
                                  the present panel. Some project par-                           expense of rigour in assessing quality
                                  ticipants commented that the overall                           or viability of proposals.
                                  time from call to contract start was
                                  quicker than usual for the Framework                           However, according to programme sta-
                                  Programme. They particularly com-                              tistics provided by the Commission,
                                  mented on more rapid resolution by                             excluding special cases the ‘time to
                                  the Commission of legal and adminis-                           contract’32 was approximately 225
                                  trative matters and attributed this to                         days compared with an overall average
                                  the Commission seeking to meet the                             for the ‘Pervasive and Trusted Network
                                  tight timescale that it had set.                               and Service Infrastructures’ theme of
                                                                                                 the 7th Framework Programme of 250
                                  Indeed, with one exception (FI-WARE),                          days for years 2010-2011. So the time
                                  negotiations for the FI-PPP Call 1 projects                    to contract was also quicker than usual
                                  were all concluded by March 31st 2011,                         for the Framework Programme - if only
                                  so they could legally start on April 1st.                      by 10%. Unfortunately, though, while all
                                  That is only 120 days from call closure,                       projects except FI-WARE were legally
                                  which is extremely rapid.                                      able to start on April 1st, within only 120
                                                                                                 days, in practice several did not actually
                                  The panel is unable to judge whether                           start until contracts were finally signed in
                                  the greater speediness is a consequence                        June or July. So, given the summer break,
                                  of greater flexibility in interpretation                       many of the projects actually began wor-
                                  of the rules or more urgent execution                          king in September. This is quite contrary
                                  of the processes, or both. In any case                         to the spirit of rapid action requested ini-
                                  greater speed is to be commended                               tially by industry and achieved to a great
                                  when time-to-market is critical and                            extent by the Commission.

31
     	 “ uture Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (Article 4) article 3.1.2 (i)
        F
32
     	 ‘Time to contract’ is the time from closure of a call for proposals until both parties in a selected project have signed the project contract.
21
                                    F I N D I N G S   O F   T H E    P A N E L




4.4. Quality
The nature of ‘quality’ for the projects     proposal apart from CONCORD and
in the FI-PPP is different from that for     neither proposal scored highly.
conventional Framework Programme
projects. It has been emphasised to          For the Capacity Building Objective
proposers, evaluators, reviewers, and        there were two eligible proposals (SHIFT
the present Panel that ‘the FI-PPP is not    and INFINITY), but SHIFT was scored
about scientific excellence but about        below threshold. So INFINITY, which had
making an impact’ in a collaborative         only a modest score, was bound to be
multi-sector innovation programme.           proposed for selection according to the
                                             evaluation and selection process.
However, the panel notes that the level
of competition for Use Case projects in      There was no competition for the Techno-
the first call (a 4:1 ratio), coupled with   logy Foundation Objective and FI-WARE
evaluation scores for the higher ranked      had a very low score - only just above
proposals that are similar to those of       the threshold. Yet it was also bound to
typical FP7 evaluations, indicates that      be proposed for selection.
these projects may be considered of
high quality (with the caveat that the       The panel has also (as indicated in
subsequent implementations may not           section 4.2) examined the 6-month re-
match up to the quality of the proposals).   view reports. These give support to the
                                             indications above from the proposal
However, among the ‘horizontal’ pro-         evaluations, with at least half the Use
jects there was much less competition.       Case projects performing well, but pro-
For the Programme Facilitation and           blems with all the horizontal projects.
Support Objective there was only one


4.5. Summary of findings
The FI-PPP is a special (though not          Repeatedly the panel heard that the
unique) case of a public-private par-        projects were ‘typical FP7 projects’.
tnership, being set up within the 7th
Framework Programme. But aside from          In the next section the FI-PPP is consi-
the performance of individual projects,      dered in the context of the expectations
the panel finds that the participants are    of public-private partnerships and in
not succeeding in cooperating so as to       comparison with other public-private
achieve the programme-level objectives.      partnerships.




                                                                    Interim Assessment of the Future Internet Public-Private Partnership
22
                            T H E    P U B L I C     P R I V A T E     P A R T N E R S H I P        M E C H A N I S M




5. The Public Private Partnership Mechanism
                                Given the timing of this assessment,                       supported by the programme will be:
                                the work of the panel is expected to                       •  etter aligned with market develop-
                                                                                             b
                                contribute to the preparatory work for                       ments and industrial ambitions and
                                the detailed work programmes of Ho-                          so be
                                rizon 2020, notably the guidelines for
                                public-private partnerships.                               • exploited to a greater extent ..
                                                                                           •  ith benefits for both the industrial
                                                                                             w
                                In evaluating the FI-PPP the panel has                       suppliers and their customers, so that
                                not used for comparison the broad con-                       ..
                                cept of PPPs as vehicles which share                       • rivate investment (i.e. by industry)
                                                                                             p
                                risk between public authorities and pri-                     will increase (from the level of the
                                vate providers, most commonly for the                        Framework Programme), given the
                                delivery of infrastructure and related                       greater value that industry can real-
                                services. Our interest is confined to                        ise from a PPP.
                                those where the principal public input
                                is finance for research and innovation                     However, for public authorities to give
                                towards goals which are shared with                        to industry greater authority for the di-
                                industry. We have therefore consid-                        rection of public investment (and in the
                                ered the FI-PPP in the context of the                      case of some PPPs its disbursement)
                                structures of other PPPs engaged in                        a PPP must not be a ‘closed shop’. It
                                research and innovation and of related                     must have governance arrangements
                                mechanisms such as Joint Technology                        that ensure that:
                                Initiatives.                                               • ts leadership is representative, inclu-
                                                                                             i
                                                                                             sive and authoritative;
                                The most direct comparators for FI-PPP
                                correspond broadly to what have been                       •  articipation in the PPP’s governance
                                                                                             p
                                called ‘Market-oriented PPPs’33. These                       bodies is open;
                                include the three Recovery Plan PPPs -                     • articipation in the evolution of its
                                                                                             p
                                Factories of the Future, Energy Efficient                    strategic agenda and in the formula-
                                Buildings and Green Cars; the Article                        tion of its work-plans is open to the
                                171 Joint Technology Initiatives; and                        widest possible community;
                                the EUREKA clusters.                                       •  articipation in its programme is open;
                                                                                             p
                                                                                           •  ompetitive calls for participation are
                                                                                             c
                                In general, these PPPs are characterised                     managed fairly and transparently;
                                by:
                                                                                           •  strategic agenda is developed and
                                                                                             a
                                • ndustry taking greater responsibility
                                  i                                                          there is a process for evolving that
                                  for formulating a research and inno-                       agenda to accommodate develop-
                                  vation strategy for a domain;                              ments in technology and markets;
                                • ndustry managing the pursuit of that
                                  i                                                        • he programme is directed and man-
                                                                                             t
                                  strategy.                                                  aged fairly and effectively;
                                                                                           • he programme is administered effi-
                                                                                             t
                                The expectation is that if industry is
                                                                                             ciently and with integrity.
                                allowed to take leadership the work

33
     	 OECD (2004), Public/Private Partnerships for Innovation in OECD Science, Technology and Industry (STI) Outlook 2004,OECD- Paris
23
                        T H E    P U B L I C      P R I V A T E     P A R T N E R S H I P        M E C H A N I S M




Typically, these requirements have been                   enable resolution of the conflicting de-
satisfied by an open industrial associa-                  mands for coherent coordination and
tion (possibly more than one) undertak-                   open access.
ing the management. Where such an
association did not exist previously, new                 The following table indicates the ba-
associations have been created with the                   sic characteristics of the FI-PPP com-
specific purpose of running the PPP.                      pared with other PPPs. The other PPPs
                                                          considered are ARTEMIS (Embedded
It has typically taken a long time for                    Systems), ENIAC (Nano-Electronics),
the communities of interest behind                        CLEAN SKY (reducing environmental
PPPs to appreciate and assimilate the                     impact of aviation), FCH (Fuel Cell 
expectations of them and to establish                     Hydrogen), IMI (Innovative Medicine
governance arrangements, including                        Initiative).34
the formation of industrial associa-
tions if they did not exist before, that




 	 he table is based upon an analysis by the Commission of possible programme models for the FI-PPP during the planning phase “A Public-Private
34
  T
  Partnership for the Future Internet”, April 2009. Two PPPs of a very different nature (GALILEO and SESAR) are not included in this comparison.

                                                                                   Interim Assessment of the Future Internet Public-Private Partnership
24


Evaluation
                       ARTEMIS                  ENIAC                  FCH                CLEAN SKY                  IMI                 FI-PPP
Criteria

Level of detail    Broad technical       Broad technical       Broad technical        Specified technical   Broad scientific      Specific work-
 of Objectives     objectives (then      objectives (then      objectives             objectives            objectives            programme with
(clear, specific   detailed calls for    detailed calls for                                                                       detailed objectives;
 measurable)       proposal)             proposal)                                                                                calls for proposals
                                                                                                                                                          T H E




                                                                                                                                  within FP7

   Level of        EC + industry         EC + industry         EC + industry          EC + 98 named         EC + industry         Industrial, academic
 definition of     association and       association and       grouping (+ research   organisations         association           and public-sector
 Membership        Member states         Member states         grouping)                                                          organisations.
                                                                                                                                                          P U B L I C




                                                                                                                                  (N.b. no formally
                                                                                                                                  constituted
                                                                                                                                  association)
                                                                                                                                                          P R I V A T E




   Governing       Governing Board,      Governing Board,      Governing Board,       Governing Board,      Board, Executive      Steering Board
   structure       Executive Director,   Executive Director,   Executive Director     Executive Director,   Office, Scientific
                   Public Authorities    Public Authorities                           Technical Steering    Committee
                   Board, Industry       Board, Industry and                          Committees, General
                   and Research          Research Committee                           Forum
                   Committee

Advisory bodies    Public Authorities    Public Authorities    States                 Member States         Member States         Advisory Board (still
                                                                                                                                                          P A R T N E R S H I P




                   Board, Industry       Board, Industry and   Representatives                              Group, Stakeholder    to meet after 1 year)
                   and Research          Research Committee    Group, Scientific                            Forum
                   Committee                                   Committee

    Funding        National financial    National financial    EC 50%, Industry       EC and Members,       EC 50% (in cash       FP7 model
    - model,       contribution from     contribution from     50%                    75% pre-allocated,    for SME, Academia,
                                                                                                                                                          M E C H A N I S M




 processes and     MS , EC 55%           MS , EC 55%                                  25% open calls        Regulators and
  allocations      via JTI, private      via JTI, private      Member states and                            patients), Industry
                   participants          participants          regions can allocate                         50% (in kind for
                                                               budget to individual                         SME…) Industry
                                                               projects                                     doesn’t received EC
                                                                                                            funding
EC funding      420                  450                  470                     800                   1000                    300
                                                                         (MEuro)

                                                                       Legal status     Community Body,      Community Body,      Community Body,         Community Body,       Community Body,         FP7: articles 164 
                                                                                        art 171              art 171              art 171                 art 171               art 171                 166

                                                                       IPR provisions   Follows EC           Follows EC           High level principles   High-level general    High level principles   FP7 plus a
                                                                                        regulation and is    regulation and is    modelled after FP7      provision, modelled   modelled after FP7      contractual
                                                                                                                                                                                                                              T H E




                                                                                        provided in detail   provided in detail                           after FP7                                     clause requiring
                                                                                                                                                                                                        programme-
                                                                                                                                                                                                        wide sharing of
                                                                                                                                                                                                        foreground IP
                                                                                                                                                                                                                              P U B L I C




                                                                        Preparatory     Industrial           Industrial           “Bridging structure”    Encouraged to         “Take all necessary     16 companies
                                                                          actions       Association put in   Association put in   (an FP7 CSA) put        facilitate a quick    preparatory actions”    prepared a “White
                                                                                        place                place                in place with the       start-up              until the JU is setup   paper on the
                                                                                                                                                                                                                              P R I V A T E




                                                                                                                                  Industry Grouping                                                     Future Internet PPP
                                                                                                                                                                                                        Definition” (2010)
                                                                                                                                                                                                                              P A R T N E R S H I P
                                                                                                                                                                                                                              M E C H A N I S M
                                                                                                                                                                                                                                        25




Interim Assessment of the Future Internet Public-Private Partnership
26
                         T H E    P U B L I C      P R I V A T E     P A R T N E R S H I P         M E C H A N I S M




                              5.1. The FI-PPP in comparison with other PPPs
                              In order to establish the FI-PPP rapidly,                   sents the community of interest and
                              it was set up using the instruments and                     is actively engaged in the manage-
                              processes of FP7. In this respect the                       ment of guidance of the programme.
                              objective of a rapid response by the                        Most of the other PPPs have some
                              community to technological and mar-                         form of (open) industrial association
                              ket developments was achieved in a                          both to undertake management of the
                              way that could not have been achieved                       programme and to engage with the
                              had the Joint Technology Initiative (JTI)                   wider community, beyond the original
                              approach of establishing legal entities                     ‘thought leaders’.37
                              been adopted.
                                                                                          Another major difference is that the
                              Moreover, as noted in section 4.2.2                         FI-PPP governance arrangements to
                              above, while using the same instru-                         meet its obligation to be ‘the highest
                              ments as FP7 it is notable that the                         FI-PPP Program governing body’ are
                              FI-PPP has succeeded in attracting in-                      much less evident.
                              dustrial involvement. In FI-PPP Call 1,
                              private companies receive c. 66% of                         It might be argued that the way in
                              total funding, compared with only 34%                       which responsibilities are distributed
                              in Call 7 of FP7 Challenge 1 and 46%                        through the separate projects in the
                              in Call 535.                                                programme inhibits the establishment
                                                                                          of a coherent system of governance,
                              A similar approach using FP7 instru-                        but it is clearly the responsibility of the
                              ments was taken in the establishment                        Steering Board to govern and it is not
                              of the PPPs for Energy-efficient Build-                     doing so.
                              ings, Factories of the Future, and the
                              European Green Cars Initiative. However,                    The FI-PPP compares favourably in the
                              the interim evaluation of these PPPs                        spectrum of European PPPs in that user-
                              states that:                                                engagement is central to its approach.
                                                                                          Nonetheless, in the coming phases
                              “While this has permitted the fast                          when SME participation is intended to
                              start-up of activities and rapid im-                        become a key feature its actions will
                              plementation of programmes, the                             benefit from extending support to other
                              understanding of the structures and                         aspects of innovation, and in general to
                              mechanisms in the wider stakeholder                         an engagement with the likely demand
                              community needs to be improved”36                           environment, including involvement of
                                                                                          those responsible for regulation.
                              That comment is equally applicable to
                              the Future Internet community.                              One clear opportunity would be to link
                                                                                          this activity with the emerging instru-
                              A critical difference between the FI-PPP                    ments of pre-commercial and innovation
                              and the other PPP’s is that there is                        procurement which could secure for in-
                              no body that comprehensively repre-                         novative SMEs the crucial first customer.

35
   	 he figure of 66% excludes the results of the FI-WARE Open Call. These may boost the industrial participation further.
    T
36
   	nterim Assessment of the Research PPPs in the European Economic Recovery Plan, 2011
    I
37
   	 here are several European Technology Platforms whose scope is included within or overlaps with that of the FI-PPP, notably Net!Works, NEM
    T
    and NESSI, ISI and EPOSS. And there is also the original industrial grouping of the European Future Internet Initiative Founding Members. But
    these organisations have neither together nor individually established anything equivalent to those of the Industrial Associations of other
    PPPs - with equivalent or similar governance arrangements.
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership
Interim assessment of the future internet public private partnership

Weitere ähnliche Inhalte

Was ist angesagt?

Portugal - Shared Services Centres
Portugal - Shared Services CentresPortugal - Shared Services Centres
Portugal - Shared Services CentresFórum dos Serviços
 
D4.2. User Profile Schema and Profile Capturing
D4.2. User Profile Schema and Profile CapturingD4.2. User Profile Schema and Profile Capturing
D4.2. User Profile Schema and Profile CapturingLinkedTV
 
Terigal parking consultation report phase 1
Terigal parking consultation report phase 1Terigal parking consultation report phase 1
Terigal parking consultation report phase 1Transport Planning
 
D3.4. LinkedTV Interface and Presentation Engine Version 1
D3.4. LinkedTV Interface and Presentation Engine Version 1D3.4. LinkedTV Interface and Presentation Engine Version 1
D3.4. LinkedTV Interface and Presentation Engine Version 1LinkedTV
 
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...Dr Dev Kambhampati
 
Documentation alexandria cds_may_2008-updated_july
Documentation alexandria cds_may_2008-updated_julyDocumentation alexandria cds_may_2008-updated_july
Documentation alexandria cds_may_2008-updated_julyEiman El-Iskandarani
 
ICF Energy Efficiency in HOME Affordable Housing Manual
ICF Energy Efficiency in HOME Affordable Housing ManualICF Energy Efficiency in HOME Affordable Housing Manual
ICF Energy Efficiency in HOME Affordable Housing ManualICF_HCD
 
D3.3. LinkedTV User Interfaces Sketch
D3.3. LinkedTV User Interfaces SketchD3.3. LinkedTV User Interfaces Sketch
D3.3. LinkedTV User Interfaces SketchLinkedTV
 
D3.2. Specification of Presentation Interfaces for The Three Scenarios
D3.2. Specification of Presentation Interfaces for The Three ScenariosD3.2. Specification of Presentation Interfaces for The Three Scenarios
D3.2. Specification of Presentation Interfaces for The Three ScenariosLinkedTV
 
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated Plan
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated PlanFLOOD- serv D6.3 First Communication and Dissemination Report and Updated Plan
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated PlanPantelis Kanellopoulos
 
D3.1. Specification of Functional Requirements Satisfying User Information Needs
D3.1. Specification of Functional Requirements Satisfying User Information NeedsD3.1. Specification of Functional Requirements Satisfying User Information Needs
D3.1. Specification of Functional Requirements Satisfying User Information NeedsLinkedTV
 
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA..."Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...Palazzo Chigi - Governo Italiano
 
33134 handbook ict wp2013 fixed deadline calls v2 en
33134 handbook ict wp2013 fixed deadline calls v2 en33134 handbook ict wp2013 fixed deadline calls v2 en
33134 handbook ict wp2013 fixed deadline calls v2 enRob Blaauboer
 
API_HLR_HSS.eng_2019 (1).pdf
API_HLR_HSS.eng_2019 (1).pdfAPI_HLR_HSS.eng_2019 (1).pdf
API_HLR_HSS.eng_2019 (1).pdfmaryamrahimlu2
 
Sap co stepbystep config & user manual part 2
Sap co stepbystep config & user manual part 2Sap co stepbystep config & user manual part 2
Sap co stepbystep config & user manual part 2PallaviChawla8
 

Was ist angesagt? (20)

Portugal - Shared Services Centres
Portugal - Shared Services CentresPortugal - Shared Services Centres
Portugal - Shared Services Centres
 
D4.2. User Profile Schema and Profile Capturing
D4.2. User Profile Schema and Profile CapturingD4.2. User Profile Schema and Profile Capturing
D4.2. User Profile Schema and Profile Capturing
 
Terigal parking consultation report phase 1
Terigal parking consultation report phase 1Terigal parking consultation report phase 1
Terigal parking consultation report phase 1
 
D3.4. LinkedTV Interface and Presentation Engine Version 1
D3.4. LinkedTV Interface and Presentation Engine Version 1D3.4. LinkedTV Interface and Presentation Engine Version 1
D3.4. LinkedTV Interface and Presentation Engine Version 1
 
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...
Dr Dev Kambhampati | Export Import Bank of USA- Global Competitiveness Report...
 
World Bank Writing Sample
World Bank Writing SampleWorld Bank Writing Sample
World Bank Writing Sample
 
Documentation alexandria cds_may_2008-updated_july
Documentation alexandria cds_may_2008-updated_julyDocumentation alexandria cds_may_2008-updated_july
Documentation alexandria cds_may_2008-updated_july
 
ICF Energy Efficiency in HOME Affordable Housing Manual
ICF Energy Efficiency in HOME Affordable Housing ManualICF Energy Efficiency in HOME Affordable Housing Manual
ICF Energy Efficiency in HOME Affordable Housing Manual
 
D3.3. LinkedTV User Interfaces Sketch
D3.3. LinkedTV User Interfaces SketchD3.3. LinkedTV User Interfaces Sketch
D3.3. LinkedTV User Interfaces Sketch
 
Mbg spmp project_management
Mbg spmp project_managementMbg spmp project_management
Mbg spmp project_management
 
D3.2. Specification of Presentation Interfaces for The Three Scenarios
D3.2. Specification of Presentation Interfaces for The Three ScenariosD3.2. Specification of Presentation Interfaces for The Three Scenarios
D3.2. Specification of Presentation Interfaces for The Three Scenarios
 
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated Plan
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated PlanFLOOD- serv D6.3 First Communication and Dissemination Report and Updated Plan
FLOOD- serv D6.3 First Communication and Dissemination Report and Updated Plan
 
D3.1. Specification of Functional Requirements Satisfying User Information Needs
D3.1. Specification of Functional Requirements Satisfying User Information NeedsD3.1. Specification of Functional Requirements Satisfying User Information Needs
D3.1. Specification of Functional Requirements Satisfying User Information Needs
 
Open Source adobe lightroom like
Open Source adobe lightroom likeOpen Source adobe lightroom like
Open Source adobe lightroom like
 
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA..."Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...
"Rapporto Caio" Achieving the Objectives of the Digital Agenda for Europe (DA...
 
Full rpt
Full rptFull rpt
Full rpt
 
mpi4py Manual!
mpi4py Manual!mpi4py Manual!
mpi4py Manual!
 
33134 handbook ict wp2013 fixed deadline calls v2 en
33134 handbook ict wp2013 fixed deadline calls v2 en33134 handbook ict wp2013 fixed deadline calls v2 en
33134 handbook ict wp2013 fixed deadline calls v2 en
 
API_HLR_HSS.eng_2019 (1).pdf
API_HLR_HSS.eng_2019 (1).pdfAPI_HLR_HSS.eng_2019 (1).pdf
API_HLR_HSS.eng_2019 (1).pdf
 
Sap co stepbystep config & user manual part 2
Sap co stepbystep config & user manual part 2Sap co stepbystep config & user manual part 2
Sap co stepbystep config & user manual part 2
 

Ähnlich wie Interim assessment of the future internet public private partnership

Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementationDejened
 
Report iatc-final
Report iatc-finalReport iatc-final
Report iatc-finalagjinopulli
 
9607 guideto supplierdevelopment
9607 guideto supplierdevelopment9607 guideto supplierdevelopment
9607 guideto supplierdevelopmentSherri Dobroskay
 
Integrating developing countries’ SMEs into Global Value Chain.
Integrating developing countries’ SMEs into Global Value Chain.Integrating developing countries’ SMEs into Global Value Chain.
Integrating developing countries’ SMEs into Global Value Chain.Ira Tobing
 
Unido guide to suppler development
Unido guide to suppler developmentUnido guide to suppler development
Unido guide to suppler developmentDr Lendy Spires
 
English version dec 24 final 1
English version dec 24 final 1English version dec 24 final 1
English version dec 24 final 1wondimg
 
DOT Open Gov Plan Final
DOT Open Gov Plan FinalDOT Open Gov Plan Final
DOT Open Gov Plan FinalGovLoop
 
20090712 commodities in the if study undp exeuctive summarywith covers
20090712 commodities in the if study undp exeuctive summarywith covers20090712 commodities in the if study undp exeuctive summarywith covers
20090712 commodities in the if study undp exeuctive summarywith coversLichia Saner-Yiu
 
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Devon Cone
 
Impact assessment-study-dit
Impact assessment-study-ditImpact assessment-study-dit
Impact assessment-study-ditGirma Biresaw
 
9059_GPF Learning Series_Zambia v4 (1)
9059_GPF Learning Series_Zambia v4 (1)9059_GPF Learning Series_Zambia v4 (1)
9059_GPF Learning Series_Zambia v4 (1)Victoria Cabral
 
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...Mainstreaming Governance in Country Programs: Insights from the Governance Pa...
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...Victoria Cabral
 
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_Telecentre
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_TelecentreTelecottage_Handbook__How_to_Establish_and_Run_a_Successful_Telecentre
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_TelecentreYuri Misnikov
 
16 report project xpditte
16 report project xpditte16 report project xpditte
16 report project xpditteradha2013
 
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...LinkedTV
 

Ähnlich wie Interim assessment of the future internet public private partnership (20)

Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
 
J4769e06
J4769e06J4769e06
J4769e06
 
Comunis Project report
 Comunis Project report  Comunis Project report
Comunis Project report
 
Report iatc-final
Report iatc-finalReport iatc-final
Report iatc-final
 
9607 guideto supplierdevelopment
9607 guideto supplierdevelopment9607 guideto supplierdevelopment
9607 guideto supplierdevelopment
 
Integrating developing countries’ SMEs into Global Value Chain.
Integrating developing countries’ SMEs into Global Value Chain.Integrating developing countries’ SMEs into Global Value Chain.
Integrating developing countries’ SMEs into Global Value Chain.
 
Unido guide to suppler development
Unido guide to suppler developmentUnido guide to suppler development
Unido guide to suppler development
 
Final Report 2009
Final Report 2009Final Report 2009
Final Report 2009
 
English version dec 24 final 1
English version dec 24 final 1English version dec 24 final 1
English version dec 24 final 1
 
DOT Open Gov Plan Final
DOT Open Gov Plan FinalDOT Open Gov Plan Final
DOT Open Gov Plan Final
 
20090712 commodities in the if study undp exeuctive summarywith covers
20090712 commodities in the if study undp exeuctive summarywith covers20090712 commodities in the if study undp exeuctive summarywith covers
20090712 commodities in the if study undp exeuctive summarywith covers
 
Fulltext01
Fulltext01Fulltext01
Fulltext01
 
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)Conducting BIAs for UASC in Cairo (RefugePoint 2012)
Conducting BIAs for UASC in Cairo (RefugePoint 2012)
 
Impact assessment-study-dit
Impact assessment-study-ditImpact assessment-study-dit
Impact assessment-study-dit
 
9059_GPF Learning Series_Zambia v4 (1)
9059_GPF Learning Series_Zambia v4 (1)9059_GPF Learning Series_Zambia v4 (1)
9059_GPF Learning Series_Zambia v4 (1)
 
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...Mainstreaming Governance in Country Programs: Insights from the Governance Pa...
Mainstreaming Governance in Country Programs: Insights from the Governance Pa...
 
Report on the Implementation of the derogation to the standard rules of orig...
 Report on the Implementation of the derogation to the standard rules of orig... Report on the Implementation of the derogation to the standard rules of orig...
Report on the Implementation of the derogation to the standard rules of orig...
 
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_Telecentre
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_TelecentreTelecottage_Handbook__How_to_Establish_and_Run_a_Successful_Telecentre
Telecottage_Handbook__How_to_Establish_and_Run_a_Successful_Telecentre
 
16 report project xpditte
16 report project xpditte16 report project xpditte
16 report project xpditte
 
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...
LinkedTV Deliverable 1.6 - Intelligent hypervideo analysis evaluation, final ...
 

Mehr von Ed Dodds

Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural America
Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural AmericaUpdated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural America
Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural AmericaEd Dodds
 
ILSR 2019 12 rural coop policy brief update page 8
ILSR 2019 12 rural coop policy brief update page 8ILSR 2019 12 rural coop policy brief update page 8
ILSR 2019 12 rural coop policy brief update page 8Ed Dodds
 
Maximizing information and communications technologies for development in fai...
Maximizing information and communications technologies for development in fai...Maximizing information and communications technologies for development in fai...
Maximizing information and communications technologies for development in fai...Ed Dodds
 
Iris Ritter interconnection map
Iris Ritter interconnection mapIris Ritter interconnection map
Iris Ritter interconnection mapEd Dodds
 
Inoversity - Bob Metcalfe
Inoversity - Bob MetcalfeInoversity - Bob Metcalfe
Inoversity - Bob MetcalfeEd Dodds
 
Distributed Ledger Technology
Distributed Ledger TechnologyDistributed Ledger Technology
Distributed Ledger TechnologyEd Dodds
 
UCX: An Open Source Framework for HPC Network APIs and Beyond
UCX: An Open Source Framework for HPC Network APIs and BeyondUCX: An Open Source Framework for HPC Network APIs and Beyond
UCX: An Open Source Framework for HPC Network APIs and BeyondEd Dodds
 
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...Ed Dodds
 
Innovation Accelerators Report
Innovation Accelerators ReportInnovation Accelerators Report
Innovation Accelerators ReportEd Dodds
 
Strategy for American Innovation
Strategy for American InnovationStrategy for American Innovation
Strategy for American InnovationEd Dodds
 
Collaboration with NSFCloud
Collaboration with NSFCloudCollaboration with NSFCloud
Collaboration with NSFCloudEd Dodds
 
AppImpact: A Framework for Mobile Technology in Behavioral Healthcare
AppImpact: A Framework for Mobile Technology in Behavioral HealthcareAppImpact: A Framework for Mobile Technology in Behavioral Healthcare
AppImpact: A Framework for Mobile Technology in Behavioral HealthcareEd Dodds
 
Report to the President and Congress Ensuring Leadership in Federally Funded ...
Report to the President and Congress Ensuring Leadership in Federally Funded ...Report to the President and Congress Ensuring Leadership in Federally Funded ...
Report to the President and Congress Ensuring Leadership in Federally Funded ...Ed Dodds
 
Data Act Federal Register Notice Public Summary of Responses
Data Act Federal Register Notice Public Summary of ResponsesData Act Federal Register Notice Public Summary of Responses
Data Act Federal Register Notice Public Summary of ResponsesEd Dodds
 
Gloriad.flo con.2014.01
Gloriad.flo con.2014.01Gloriad.flo con.2014.01
Gloriad.flo con.2014.01Ed Dodds
 
2014 COMPENDIUM Edition of National Research and Education Networks in Europe
2014 COMPENDIUM Edition of National Research and  Education Networks in Europe2014 COMPENDIUM Edition of National Research and  Education Networks in Europe
2014 COMPENDIUM Edition of National Research and Education Networks in EuropeEd Dodds
 
New Westminster Keynote - Norman Jacknis
New Westminster Keynote - Norman JacknisNew Westminster Keynote - Norman Jacknis
New Westminster Keynote - Norman JacknisEd Dodds
 
HIMSS Innovation Pathways Summary
HIMSS Innovation Pathways SummaryHIMSS Innovation Pathways Summary
HIMSS Innovation Pathways SummaryEd Dodds
 

Mehr von Ed Dodds (20)

Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural America
Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural AmericaUpdated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural America
Updated Policy Brief: Cooperatives Bring Fiber Internet Access to Rural America
 
ILSR 2019 12 rural coop policy brief update page 8
ILSR 2019 12 rural coop policy brief update page 8ILSR 2019 12 rural coop policy brief update page 8
ILSR 2019 12 rural coop policy brief update page 8
 
Maximizing information and communications technologies for development in fai...
Maximizing information and communications technologies for development in fai...Maximizing information and communications technologies for development in fai...
Maximizing information and communications technologies for development in fai...
 
Iris Ritter interconnection map
Iris Ritter interconnection mapIris Ritter interconnection map
Iris Ritter interconnection map
 
Inoversity - Bob Metcalfe
Inoversity - Bob MetcalfeInoversity - Bob Metcalfe
Inoversity - Bob Metcalfe
 
Distributed Ledger Technology
Distributed Ledger TechnologyDistributed Ledger Technology
Distributed Ledger Technology
 
UCX: An Open Source Framework for HPC Network APIs and Beyond
UCX: An Open Source Framework for HPC Network APIs and BeyondUCX: An Open Source Framework for HPC Network APIs and Beyond
UCX: An Open Source Framework for HPC Network APIs and Beyond
 
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...
Digital Inclusion and Meaningful Broadband Adoption Initiatives Colin Rhinesm...
 
Jetstream
JetstreamJetstream
Jetstream
 
Innovation Accelerators Report
Innovation Accelerators ReportInnovation Accelerators Report
Innovation Accelerators Report
 
Work.
Work.Work.
Work.
 
Strategy for American Innovation
Strategy for American InnovationStrategy for American Innovation
Strategy for American Innovation
 
Collaboration with NSFCloud
Collaboration with NSFCloudCollaboration with NSFCloud
Collaboration with NSFCloud
 
AppImpact: A Framework for Mobile Technology in Behavioral Healthcare
AppImpact: A Framework for Mobile Technology in Behavioral HealthcareAppImpact: A Framework for Mobile Technology in Behavioral Healthcare
AppImpact: A Framework for Mobile Technology in Behavioral Healthcare
 
Report to the President and Congress Ensuring Leadership in Federally Funded ...
Report to the President and Congress Ensuring Leadership in Federally Funded ...Report to the President and Congress Ensuring Leadership in Federally Funded ...
Report to the President and Congress Ensuring Leadership in Federally Funded ...
 
Data Act Federal Register Notice Public Summary of Responses
Data Act Federal Register Notice Public Summary of ResponsesData Act Federal Register Notice Public Summary of Responses
Data Act Federal Register Notice Public Summary of Responses
 
Gloriad.flo con.2014.01
Gloriad.flo con.2014.01Gloriad.flo con.2014.01
Gloriad.flo con.2014.01
 
2014 COMPENDIUM Edition of National Research and Education Networks in Europe
2014 COMPENDIUM Edition of National Research and  Education Networks in Europe2014 COMPENDIUM Edition of National Research and  Education Networks in Europe
2014 COMPENDIUM Edition of National Research and Education Networks in Europe
 
New Westminster Keynote - Norman Jacknis
New Westminster Keynote - Norman JacknisNew Westminster Keynote - Norman Jacknis
New Westminster Keynote - Norman Jacknis
 
HIMSS Innovation Pathways Summary
HIMSS Innovation Pathways SummaryHIMSS Innovation Pathways Summary
HIMSS Innovation Pathways Summary
 

Kürzlich hochgeladen

New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piececharlottematthew16
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesZilliz
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 

Kürzlich hochgeladen (20)

New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Story boards and shot lists for my a level piece
Story boards and shot lists for my a level pieceStory boards and shot lists for my a level piece
Story boards and shot lists for my a level piece
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector Databases
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 

Interim assessment of the future internet public private partnership

  • 1. Interim Assessment of the Future Internet Public-Private Partnership May 2012 Communications Networks, Content and Technology
  • 2. More information on the European Union is available on the Internet: http://europa.eu © European Union, 2012 The opinions expressed in this study are those of the authors and do not necessarily reflect the views of the European Commission. ISBN: 978-92-79-19895-3 doi: 10.2759/84215 Reproduction is authorised provided the source is acknowledged. Printed in Belgium
  • 3. EUROPEAN COMMISSION Interim Assessment of the Future Internet Public-Private Partnership
  • 4. 4 Assessment Panel Report On behalf of the panel that performed the interim assessment of the Future Internet Public-Private Partnership I am pleased to present to the European Commission our report. Luke Georghiou (Chair) Anna Asimakopoulou Piet Bel Graham Vickery Bob Malcolm (Rapporteur)
  • 5. 5 T a b l e o f c o n t e n t s Table of contents EXECUTIVE SUMMARY 1. INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 2. OBJECTIVES OF THE FI-PPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 2.1. Objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 3. IMPLEMENTATION OF THE FI-PPP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 3.1. Legal Framework . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 3.2. Programme Architecture . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 3.3. Programme Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 3.4. Activities (July 2010 - April 2012) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 3.5. Governance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 4. FINDINGS OF THE PANEL .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 4.1. Continuing relevance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 4.2. Progress toward the objectives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16 4.3. Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20 4.4. Quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 4.5. Summary of findings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 5. THE PUBLIC PRIVATE PARTNERSHIP MECHANISM . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 5.1. The FI-PPP in comparison with other PPPs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 6. CONCLUSIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 7. RECOMMENDATIONS .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 7.1. ecommendations for the Commission concerning Public-Private R Partnerships in Horizon 2020 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 7.2. Recommendations for present partners in the programme . . . . . . . . . . . . 30 7.3. ecommendations for the Commission concerning R the present programme . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 ANNEX 1: PUBLIC-PRIVATE PARTNERSHIPS IN HORIZON 2020 . . . . . . . . . . . . . . . . . . . 33 ANNEX 2: COMPLEMENTARY GRANT AGREEMENT .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 ANNEX 3: OBJECTIVES OF THE INTERIM ASSESSMENT .. . . . . . . . . . . . . . . . . . . . . . . . . . . 36 ANNEX 4: QUESTIONS ADDRESSED BY THE PANEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 ANNEX 5: COMPOSITION OF THE PANEL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 ANNEX 6: EVIDENCE BASE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 Interim Assessment of the Future Internet Public-Private Partnership
  • 6. 6 E x e c u t i v e S u m m a r y Executive Summary The Panel that performed this Interim infrastructure enabled by the future Assessment of the Future Internet internet are still valid. Public-Private Partnership (FI-PPP) finds that: However the Panel also finds that: • he FI-PPP has been a valuable ex- t • he industrial participants in the FI-PPP t periment in attempting to achieve are not, in concert, fulfilling the role impact similar to that of Joint Tech- envisaged for them in a public-pri- nology Initiatives (JTIs)1 but in a vate partnership; much shorter timescale than JTIs by • he projects supported within the FI-PPP t using the existing instruments of the are, generally, making progress toward 7th Framework Programme; their own goals but not co-operating • he decision to use the instruments t sufficiently so as to achieve the goals and processes of the 7th Framework of the programme. Programme to establish the pro- gramme was valid in enabling a rapid The table below summarises the full response by the EU to technological set of recommendations, indicating and market developments; those which could and should be im- • he market and technological situation t plemented during the life of the FI-PPP is such that the aims of the FI-PPP to and recommendations for any follow-on accelerate technological development initiative. and take-up by engaging early-adop- ter users to identify their needs for No. Summary of recommendation Time-frame Recommendations for the Commission concerning PPPs in Horizon 2020 1 Establish guidance on governance of PPPs WP2014 2 Ensure that each PPP has an effective central governing body WP2014 3 PPPs should be able to use the widest range of innovation-oriented instruments in WP2014 a coordinated manner. 4 Re-design the process of calls for and selection of proposals to focus on achieving WP2014 greater ‘impact’. 5 Participants in projects within programmes must collaborate fully so as to achieve WP2014 programme objectives. See http://cordis.europa.eu/fp7/jtis 1
  • 7. 7 E x e c u t i v e S u m m a r y No. Summary of recommendation Time-frame Recommendations for present and future partners in the FI-PPP 6 Industrial participants should fulfil the role expected of them in a PPP. Now 7 The chairman of the Steering Board should be a senior executive of a company June 2012 that is not a co-ordinator of any FI-PPP project. 8 The Advisory Board should focus their advice on bringing the results of the FI-PPP Now and to market. continuing 9 The programme should engage more energetically - and more visibly - with the Now and wider community of both users and technology providers continuing Recommendations for the European Commission concerning the present programme 10 Calls for tender should be considered for future ‘horizontal’ actions Now 11 Future calls should emphasize the importance of take-up Now 12 Future calls should explicitly seek the engagement of representatives of the Now and broad community - industrial associations, public-sector associations, consumer continuing associations, etc, and, where appropriate, regulators. 13 Engage the innovative SME community better. Now 14 Make greater effort to achieve co-ordinated, co-operative behaviour of participants Now to achieve programme objectives. Interim Assessment of the Future Internet Public-Private Partnership
  • 8. 8 I N T R O D U C T I O N 1. Introduction This document comprises the report by The Objectives of the FI-PPP and the an independent panel of experts on an present status of its Implementation Interim Assessment of the Future Inter- are described in the next two sections. net Public-Private Partnership (FI-PPP)2. This is followed by a major section that The objectives of this assessment are to summarises the Findings of the Panel. • valuate the concept of the FI-PPP; e There is then a special section to address • ssess progress in the first year; a the performance of the programme as a Public-Private Partnership. • ffer recommendations to the European o Commission and to articipants in the The findings of the Panel are summa- FI-PPP; rised in the Conclusions section, which • bring forward proposals for how is followed by Recommendations for to further develop the FI-PPP; both the present programme, to en- hance achievement of their objectives, • contribute to the guidelines for and for future programmes with similar public-private partnerships in Horizon ambitions that may be considered in 2020. Horizon 2020. The Panel was asked to assess the FI-PPP The Panel comprised a mix of experts, with respect to: including some with knowledge of the technology and of its use in modern • elevance: whether the original aims R infrastructures, and some with general of the FI-PPP are still valid and wheth- expertise in RD strategy and man- er the programme architecture is still agement. (See Annex 5) appropriate for realising those aims; • ffectiveness: progress towards the E The Panel drew upon published infor- objectives; mation, interviews with participants in • Efficiency: of the management and the projects of which the programme is operation of the programme; comprised, representatives of the com- munity addressed by the programme • uality: of research and innovation, Q but not participating, and staff of the and of the actors attracted to the European Commission. (See Annex 6) programme.3 2 This assessment took place toward the end of the first year of operation of the programme, approximately half-way through Phase 1. 3 Annex 4 sets out in greater detail the questions addressed by the panel in their consideration of these issues.
  • 9. 9 O B J E C T I V E S O F T H E F I - P P P 2. Objectives of the fi-ppp The Future Internet Public Private Part- The public contribution to the partner- nership (FI-PPP) aims to significantly ship comes from part-funding via the advance the implementation and uptake European Commission for projects, pro- of a European-scale market for ‘smart gramme design, management of calls infrastructures’.4 The intention is to for proposals and programme monitoring, accelerate technological development and the participation of public sector for the future internet and in parallel, organisations as users in the develop- synergistically, accelerate its adoption ment of requirements and in trials. in ‘smart infrastructures’ - such as smart energy grids, smart cities, smart The private sector contributed during the environmental management systems, formulation of the concept of the PPP5 and smart systems for mobility. Ulti- with significant input from an indus- mately the ambition is to make public trial grouping6 that presented their vision service infrastructures and business to the European Commission in January processes significantly smarter (i.e. 2010. During the operation of the PPP, the more intelligent, more efficient, more private sector contributes in the form of sustainable) through tighter integra- financial support for their participation in tion with Internet networking and com- projects and from their co-operation across puting capabilities. the programme (not just within projects). 2.1. Objectives The aims and objectives of the FI-PPP trial partnerships built around Future evolved during the formation of the Internet value chains, involving users programme. The Panel has taken as and public authorities at local, regional the objective of the programme the and national levels, and providing expected impact - over all 3 phases - SME players with opportunities to as set out in the Work Programme offer new products, equipments, ser- 2011-2012. This is a précis: vices and applications; • reation of new European-scale markets C • ignificant increase of the effectiveness S for smart infrastructures contributing of business processes and novel to European leadership in global ICT approaches to the operation of infra- applications markets; structures and applications of high economic and/or societal value. • Evolution of Future Internet infra-struc- ture compatible with the emergence of • einforced industrial capability on nov- R open, secure and trusted service; el service architectures and platforms; • comprehensive approach towards A • ew opportunities for novel business N regulatory and policy issues. models based on cross-sector indus- 4 “White paper on the Future Internet PPP Definition”, January 2010 (http://www.future-internet.eu/uploads/media/May2009.pdf) ibid. 5 The ‘European Future Internet Initiative Founder Members’: a group of 16 companies supporting a Call for Action 6 Interim Assessment of the Future Internet Public-Private Partnership
  • 10. 10 I M P L E M E N T A T I O N O F T H E F I - P P P 3. mplementation of the fi-ppp I 3.1. Legal Framework In order to implement the FI-PPP rap- facilitate collaboration and programme idly - in recognition of the very dynamic coordination. This clause requires fore- nature of this field - it was established ground knowledge to be sharable across within the 7th Framework Programme. In all projects and it requires project benefi- consequence, the FI-PPP is subject to the ciaries to participate in joint coordination Regulations of the 7th Framework Pro- activities. (See Annex 2.) gramme and must use the same project instruments, the same call and evaluation Also, all participants have agreed to the processes, and the same project review terms of a Collaboration Agreement that, and programme monitoring processes. in addition to the standard terms of the Framework Programme agreement, sets However, in the grant agreement for each out the governance arrangements for project in the programme the Commission the FI-PPP.7 introduced a special clause intended to 3.2. Programme Architecture The programme has four major ‘building blocks’ (see diagram below) 7 “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.1.2 (i))
  • 11. 11 I M P L E M E N T A T I O N O F T H E F I - P P P The four building blocks are: still shared within those domains) and then instantiate their own domain-spe- • echnology Foundation - the devel- T cific platforms. opment of components for a Core Platform, initially in the FI-WARE project; The Infrastructure support project is in- • se cases trials - to establish user U tended initially, in Phase 1, to identify requirements in 8 sectors, especially existing and future advanced experi- for common components; mental infrastructures across Europe. However, the scope of the Phase 1 • nfrastructure support - making best use I project (awarded to INFINITY) has been of existing European infrastructures; expanded to encompass other studies • rogramme facilitation support. P of value to the FI-PPP. A subsequent project, planned for Phase 2, is intend- It is intended that the use cases and ed to integrate, federate and upgrade trials projects should establish their [existing infrastructures] towards serving various requirements for enabling large-scale trials8. technology components and that in liaison with the core platform project The Programme Facilitation and Sup- they should agree a set of ‘Generic port project (awarded to CONCORD) Enablers’ common to some or all of should facilitate the development of an the usage areas. The core platform overall programme view and collabora- project(s) will develop these and make tion across all FI-PPP projects, support them available to the use case projects standardisation, SME involvement, links as the Core Platform. The Use Case with regulatory and other relevant policy projects will in parallel be developing activities, dissemination and awareness the ‘Specific Enablers’ that they believe raising9 necessary for their domains (though 3.3. Programme Schedule The programme is planned to be im- • stablish the programme support and E plemented in three phases over five coordination structures. years (as indicated in the diagram above). The content of each phase is: 3.3.2. Phase 2 (April 2013 – March 2015) 3.3.1. hase 1 (April 2011 – March 2013) P • nsure availability of test infrastructure E for early trials, • Define usage area requirements from • Develop the core platform and use case which the architecture and common specific functionalities, and instantiate enablers of the core platform will be them on the test infrastructure. derived; start developing components. • elect and run early trials for all use S • tart evaluation of test infrastructures S cases and prepare large scale trials. and identify what must be done to bring infrastructures to the level nec- essary to enable trials. 8 From the FI-PPP Work Programme 2011-2012 ibid. 9 Interim Assessment of the Future Internet Public-Private Partnership
  • 12. 12 I M P L E M E N T A T I O N O F T H E F I - P P P 3.3.3. hase 3 (May 2014 – October 2015) P • ncrease the involvement of SMEs as I developers and providers of services • rovide and enrich a stable infrastruc- P and applications. ture for large scale trials populated with a variety of applications to prove the viability of the concept. 3.4. Activities (July 2010 - April 2012) The total notional EC budget for the for additional organisations to join the FI-PPP is €300M. The Commission consortium to provide certain components has earmarked €170M of funding for of the core platform11. The FI-WARE projects in the first two phases of the open calls are funded to the level of FI-PPP and, subject to budgetary ap- € 12.4 million, or 30% of FI-WARE proval, €130M for phase 3. funding and 14 % of Phase 1 funding, and are entirely managed and run by The first call for proposals was the FI-WARE consortium, independent launched in July 2010 and closed in of the Commission. The open call will December 2010. The first projects of follow the general guidelines for open the FI-PPP, selected from that call, began calls within FP7 projects12. To ensure (in principle10) in April 2011. fair competition, present members of the FI-WARE consortium are excluded 3.4.1. Distribution of FI-PPP Call 1 from participation. funds among Member States The distribution of funds in the FI-PPP (see figure on next page) is generally similar to that of Calls 5 and 7 of Challenge 1 in the ICT Programme of FP7 (also see figure on next page) and approximately reflects their GDP. The exceptions are a relatively low participation in the FI-PPP of the UK and new Member States compared with their participation in Challenge 1 of FP7 (which addresses a similar segment of the RTD community). Note that the figure below excludes the funding for FI-WARE open calls (which would distort the figures by assigning the allocation of funds to the FI-WARE coordinator). As part of Phase 1, the core platform project (FI-WARE) will extend participation through open calls 10 ee section 4.3 S 11 he first such Open Call was made on two topics: Middleware for efficient and QoS/Security-aware invocation of services and exchange of T messages; and Business Models and Business Elements Definition and Simulation. 12 See http://www.fi-ware.eu/open-call/
  • 13. 13 I M P L E M E N T A T I O N O F T H E F I - P P P A call for proposals for Phase 2 is due of additional use cases domains such as to be launched in May 2012, closing at Ambient Assisted Living and eHealth, the end of October 2012. This phase will extend participation in the programme It is intended to make a final call for through mergers and re-alignment of ex- proposals for Phase 3 projects in 2013. isting user domains and the incorporation Interim Assessment of the Future Internet Public-Private Partnership
  • 14. 14 I M P L E M E N T A T I O N O F T H E F I - P P P 3.5. Governance The diagram below indicates the governance structure of the FI-PPP. The Steering Board is the highest FI PPP • requires replies by the Steering Board Program governing body. It: to its recommendations and advice; • represents the FI-PPP owners; • omprises 8 people at the time of this c • meets monthly (real or virtual); assessment, meeting twice per year14. • ust make decisions unanimously13, m Members of the Advisory Board are also without any option of escalation. expected to be ‘Ambassadors’ of the PPP and represent them at high level events The Architecture Board: (e.g. in the Council and Parliament). • s a forum for meetings of technical i managers; The PPP Secretariat (provided by CON- • eets monthly (either physically or m CORD): by video conference); • ndertakes day-to-day facilitation of u • s consensus driven, with unanimous i the governance processes; decision making; • acilitates the operation of ‘Working f • escalates to the Steering Board in the Groups’, which are ‘temporary groups event of decisions that cannot be re- established for the performance of a solved by consensus. specific task and not a fixed part of the permanent FII Program govern- The Advisory Board: ance structure’.15 • s independent, with no access to de- i liverables per se; 13 ith one exception: when a party to the Collaboration Agreement is in breach of its obligations they are not expected to contribute to the consensus. W 14 he members of the Advisory Board were appointed in January, and at the time of this assessment have yet to meet. T 15 “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.4)
  • 15. 15 F I N D I N G S O F T H E P A N E L 4. Findings of the panel 4.1. Continuing relevance The opinion of those interviewed by the • uropean society to benefit from early E panel is that the programme is still rel- provision of internet-enhanced services. evant. The assertion of the 2008 ISTAG report16 remains valid: There has been a significant internet-en- abled development in the market-place “A critical interdependence for the suc- since the original formulation of the cess of the Web-based service industry Future Internet vision. This is the recent will be the extension of the Future In- rapid take-up of ‘Cloud Computing’ and ternet by offering very rich ‘horizontal services which make extensive use of services’. These services will foster an data and functionality (applications) ‘in interoperability and trust framework the cloud’.17 The FI-WARE project does for service integration, authentication, include work packages that address both privacy and security. This framework cloud hosting and interoperation with will enable the Web-based service in- third-party cloud facilities, so the dustry to procure, extend and repur- programme has recognised this phe- pose services to new markets.” nomenon and has, in principle, the means to accommodate it. The evolution of this concept into the vision of the Future Internet that in- However, the continuing relevance of spired the FI-PPP - of the evolution the specific structure and architecture of the internet from mere communi- of the FI-PPP, with a project dedicated cations network to an enabling smart to the development of standard re-us- infrastructure - is still valid. able components for a ‘core platform’ is less clear. As will be discussed in the Furthermore, the proposition that following section, some Use Case pro- development of standard re-usable jects have plans to develop or acquire components for a multi-sector common their own ‘enablers’ - ‘specific’ and ‘ge- (‘core’) platform will accelerate both neric’ - so that they are not reliant on technological development and take-up the core platform project. Also, some also, according to the evidence gained Use Case projects are collaborating in by the panel, remains valid. order to develop common Use Case en- ablers that are outside the scope of the Despite difficulties and delay - and core platform project - such enablers possibly further delays still to come being neither ‘specific’ not ‘generic’. - the work supported by the FI-PPP is This raises the possibility that common still valuable in helping: enablers might be better encouraged • uropean industry to accelerate its E to emerge from such collaborations contribution to the technological across domains, instead of having development required to realise the a dedicated core platform project. A vision of the Future Internet, and Technology Foundation project could eport of the Information Society Technologies Advisory Group Working Group on “Web-based Service Industry”, February 2008 16 R 17 Notwithstanding the long ‘cloud’ gestation period since the late 1950s/1960s Interim Assessment of the Future Internet Public-Private Partnership
  • 16. 16 F I N D I N G S O F T H E P A N E L still have a role in this by providing that enablers. But such responsibilities do encouragement and by facilitating the not appear to be within the present re- emergence of well-supported generic mit of FI-WARE. 4.2. Progress toward the objectives The underlying concept of the programme engaging with the broader community is that the synergistic development of a beyond participants in the programme. core platform and its use in early take- And despite leading industrial compa- up trials will be achieved through the nies being partners in the various Use projects in the programme working in Cases, long term sustainable exploitation concert - particularly the core-platform plans were considered vague or even project and the set of Use Case projects non-existent, implying that the repre- (supported by the other two projects). sentatives of the companies might not be well-coupled to their strategic plan- It is not in the Terms of Reference for ning or marketing departments. this panel to evaluate the individual projects, for which there are already The ‘core platform’ project (FI-WARE) standard Framework Programme review should be liaising satisfactorily with the processes. However, the panel has used Use Case projects and providing techni- the reports generated in that review cally well-constructed Generic Enablers process to inform its understanding of in a timely fashion. However, the quality the operation of the programme. The of liaison with the Use Case projects has set of reviews made at the 6-month been very variable and reflects closely stage of the programme shows a mixed the performance of those projects. picture, with some Use Cases progress- This suggests that FI-WARE has relied ing well and achieving interim targets, upon dealing with well-organised user- while others had start-up problems and communities and has not been able to were lagging badly at the time of the resolve difficulties with less well-organ- first review.18 ised communities. Also (at the time of this report) FI-WARE is 2 months late 4.2.1. Progress of projects overall, at the end of its first year. towards their objectives The Programme Facilitation and Sup- The ‘Use Case’ projects are concerned port project (CONCORD) is expected with the identification of requirements to facilitate the development of an for enablers that truly reflect the needs overall programme view and col- of the community of the application laboration across all FI-PPP projects, sector of the project. The 6-month support standardisation, develop key review reports indicated that at the performance indicators, SME involve- time of the review - during October ment, links with regulatory and other and November 2011 - about half the relevant policy activities, dissemination projects were performing reasonably and awareness raising. However, as the well in this regard, that others needed Description of Work for the CONCORD to try harder, and that one project was project clearly (and correctly) states in serious trouble. However, almost all “the FI-PPP Programme deliverables Use Case projects were criticised for not are not those of CONCORD project, but 18 ee also section 4.3.1 ‘Efficiency of operation’ S
  • 17. 17 F I N D I N G S O F T H E P A N E L results that all FI-PPP Projects jointly (so far) are organisations that have not contribute towards”. Yet CONCORD’s been involved in those calls20. This sug- very central role implies significant re- gests that the programme has been sponsibility for attempting to resolve successful in attracting the participation programme management problems of a broader community than that of that inhibit achievement of the pro- the traditional Framework Programme. gramme’s goals. There is evidence that while CONCORD was slow to take on However, most of the ‘new’ partici- this responsibility and made a slow pants have only single participations start in establishing the arrangements in the FI-PPP whereas, by comparison, for programme management, it is now organisations among the original 16 perceived to be making serious efforts to ‘Founder Members’ have a 43% share improve the situation. of total participations in phase 1 of the programme and have been allocated The Infrastructure support project c. 44% of FI-PPP funding of phase 1, (INFINITY) is expected to maximise excluding the allocation for FI-WARE synergy with infrastructural develop- Open Calls.21 The new industrial par- ments outside the FI-PPP. The Panel is ticipants that have not participated in concerned that the project participants Calls 5 and 7 of Challenge 1 of FP7 have do not fully share this view. Indeed the been allocated c. 13% of FI-PPP funding. 6-month programme-level reviewers commented that INFINITY was ex- Specific objectives pending effort on activities that were not fully focused on helping the PPP The Use Case projects vary consider- achieve its aims, and that it was not ably in their effectiveness in establishing performing its role as an external face common requirements for their domains of the FI-PPP. and in their relationship with the core- platform project (FI-WARE) so that their 4.2.2. rogress of the programme P needs for ‘generic enablers’ will be satis- toward programme-level fied by FI-WARE. objectives Some Use Case projects have successfully Global objectives identified their needs, communicated ef- fectively with FI-WARE and are confident According to data provided by the Com- that their needs will be met by FI-WARE. mission, industry has been extremely Other Use Cases projects have not yet responsive to the FI-PPP, with the con- agreed which of their needs will be met sequence that in the FI-PPP, excluding by FI-WARE. And some who have identi- the FI-WARE Open Call, industry has fied their needs for generic enablers have taken a much higher share of availa- low confidence in FI-WARE’s ability to de- ble funds - c. 66% compared with less liver them in time to enable them to fulfil than 50% in recent calls of Challenge their (use case) project commitments and 1 of the 7th Framework Programme19. the terms of their funding contracts. Con- sequently, some of these projects have Moreover, approximately 64% of in- a contingency plan to supply or acquire dustrial participants in the programme their own alternative components. This 19 46% in Call 5 and 34% in Call 7 20 3 out of 83 industrial participants. Also, 86 unique organisations, including industrial participants, out of a total of 149 organisations 5 participating in FI-PPP are not participating in Challenge 1 Calls 5 and 7. 21 ote that these organisations also participate intensively elsewhere in the Framework Programme, with c.30% of participations in Challenge 1. N Interim Assessment of the Future Internet Public-Private Partnership
  • 18. 18 F I N D I N G S O F T H E P A N E L is contrary to the notion of the FI-WARE of FI-WARE is accessible to all current results being truly generic enablers and and future programme participants of FI-WARE being the primary supplier of as foreground knowledge23. But the these enablers to the Use Cases. FI-WARE contract does not require FI-WARE to ‘hand over’ its results in a Several reasons have been put forward way that they can be used effectively for this mismatch between some Use by others or to support them in initial Case projects and FI-WARE, including the adoption of the results or subsequently relative timing of the project start-dates with maintenance or training. This has and the methods used by FI-WARE for serious implications for the ‘Core Plat- requirements elicitation and software form’ - especially when the FI-WARE development. The lack of an agreed project terminates, leaving no possibility view on these issues and the different of support around the time that large- relationships of the Use Case projects scale trials commence. to FI-WARE reflect three alternative at- titudes to the development process: There is a serious risk that unless strong preventive actions are taken i. ne position is that truly generic O even the user areas that are for now enablers can be developed rather planning to use FI-WARE outputs will independently of the application ar- each have to take separate responsibil- eas: in this case the general view is ity for maintaining and evolving those that FI-WARE should have started components for their area, further six months or a year before the Use undermining the concept of generic ena- Cases so that the Use Cases would blers and a common core platform.24 have an earlier idea what would be provided in the core platform. 4.2.3. Direction and management of the programme ii. nother position is that the Use Cas- A es must identify their needs first and While the CONCORD project is expected then ‘specify’ their requirements of to ‘facilitate’ the achievement of the the core platform: in this case the goals of the programme, responsibility core platform project should have for their achievement lies with the FI-PPP started later than the Use Cases to projects ‘jointly’. But while the original vi- give the Use Case projects time to sion of those who brought the FI-PPP establish their requirements. into existence25 may still be valid, it is not clear that that vision is shared by all the iii. third position is that of ‘agile’ A present participants in the programme. (highly iterative) software develop- As indicated in section 4.2.2 above, the ment: this requires tight interaction programme has attracted new partici- between developer and user. This pants, with more than half the budget situation does not pertain for at allocated to organisations other than least some Use Case projects22. the Founder Members. Moreover, each project has its own contract, its own con- However, there is, potentially, a greater tractual obligations, and its own staffing barrier to realisation of the concept and management that may not share a of the FI-PPP. Formally, the outcome co-operative vision for the programme. 22 The co-ordinator of one project told the panel that, after one year, the project is “now ready for a first face-to-face meeting with FI-WARE”. 23 As a consequence of the special clause 41 in all FI-PPP grant agreements (see section 3.1 and Annex 2 of this report). 24 I-WARE has indicated its willingness to co-operate so as to ameliorate the difficulties posed by the project not being required to provide F supported software for User Trials. 25 Particularly the European Future Internet Initiative Founder Members: see the introduction to Section 2
  • 19. 19 F I N D I N G S O F T H E P A N E L The programme should be resilient to the the whole programme and to monitor involvement of organisations and person- and maintain progress towards the nel not originally involved in its formulation objectives of the programme: “The and it should be open to new participants Steering Board is the highest FI PPP and their contribution to the evolution of Program governing body.”28 However, its vision. But to preserve its focus the the Steering Board has not acted with programme needs rules, processes and urgency to address the difficulties that mechanisms that enable the emergence the programme faces, and seems not of an evolving shared vision and the to be doing what it is supposed to do - commitment of projects to help realise provide overall Steering of the FI-PPP. that vision. Yet the vision of the ‘Founder Members’ did not address at all the re- At the operational level the Architecture quirements for governance appropriate Board has been established and appears to a public-private partnership (see Section to be working well to address technical 5, below). Indeed, in January 2010, the issues. Various Working Groups have European Commission told the Founder also been established (or at the time Members “The companies26 should set of this assessment are in the process up appropriate governance/manage- of being established)29. However, the ment structures with full empowerment Steering Board has not demonstrated from their company executives. This is a ‘ownership’ of the Architecture Board precondition for the success of the ini- or the Working Groups or responsibil- tiative”.27 They did not do that. ity for steering them so as to maximise progress toward the programme ob- The programme should also be resilient jectives. Communication between the to changing market and technological Steering Board and the Architecture environments - especially in such a fast- Board and between the Steering Board moving field as the Future Internet. This and the Working Groups is lacking in requires constant monitoring of the state both directions. In fact it is unclear how of development of the relevant tech- the Working Groups will move from nologies and markets, and the ability to the current perception of some project adapt rapidly to any developments that members as an extra burden to be car- affect the viability of the programme. ried to being seen as a positive source The panel specifically sought to identify of value added. who in the programme felt responsibil- ity for ‘horizon scanning’ but received A number of those interviewed by the no clear answer - albeit some of those panel commented on the inability of interviewed considered the Architecture the Steering Board to make decisions Board to have that responsibility. (But binding on projects that, given the con- see the next paragraph concerning the tractual arrangements, are in effect relationship between the Steering Board autonomous. The Commission broke and the Architecture Board.) new ground in establishing the clause in each contract to facilitate sharing The Steering Board is, in principle, the of intellectual property and project body to maintain coherent action over coordination across the programme.30 26 The 16 ‘Founding Members’ 27 “ eport of the meeting between Zoran Stancic, Deputy Director General, DG-Infso, and the Future Internet core group R of industrial stakeholders (G16)”, D(10)203076, January 2010 28 “Future Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (article 3.1.2 (i)) 29 Gs have so far been agreed on Dissemination, Exploitation Business Modelling, Standardisation, Policy Regulation. W A further WG on Security and Privacy is under consideration. 30 Clause 4 1 (see Annex 3 to this report) Interim Assessment of the Future Internet Public-Private Partnership
  • 20. 20 F I N D I N G S O F T H E P A N E L But this is not sufficient to enforce co- However, it is not evident to the panel operation. Indeed the programme-wide that the lack of direction and inability to Collaboration Agreement states: “The resolve problems demonstrated so far Steering Board shall however not be en- by the Steering Board derives only from titled to act or to make legally binding a lack of authority: it also seems to re- declarations on behalf of any Party, but flect a lack of a sense of responsibility. shall make recommendations for imple- mentation in respective FII Projects”.31 The lack of urgency has been exacer- bated by slowness in establishing Key There is ongoing discussion in the Performance Indicators for monitoring Steering Group about the prospects the programme’s progress towards its for amendment of contracts to accom- objectives. (The KPIs that have been modate Steering Board authority - if established so far are primarily meas- not now then possibly for future phas- ures of operational performance rather es (when decision-making will have than measures of impact.) more significant commercial impact). 4.3. Efficiency Only the first call for proposals was work should continue to accelerate the made during the period evaluated by process still further, though not at the the present panel. Some project par- expense of rigour in assessing quality ticipants commented that the overall or viability of proposals. time from call to contract start was quicker than usual for the Framework However, according to programme sta- Programme. They particularly com- tistics provided by the Commission, mented on more rapid resolution by excluding special cases the ‘time to the Commission of legal and adminis- contract’32 was approximately 225 trative matters and attributed this to days compared with an overall average the Commission seeking to meet the for the ‘Pervasive and Trusted Network tight timescale that it had set. and Service Infrastructures’ theme of the 7th Framework Programme of 250 Indeed, with one exception (FI-WARE), days for years 2010-2011. So the time negotiations for the FI-PPP Call 1 projects to contract was also quicker than usual were all concluded by March 31st 2011, for the Framework Programme - if only so they could legally start on April 1st. by 10%. Unfortunately, though, while all That is only 120 days from call closure, projects except FI-WARE were legally which is extremely rapid. able to start on April 1st, within only 120 days, in practice several did not actually The panel is unable to judge whether start until contracts were finally signed in the greater speediness is a consequence June or July. So, given the summer break, of greater flexibility in interpretation many of the projects actually began wor- of the rules or more urgent execution king in September. This is quite contrary of the processes, or both. In any case to the spirit of rapid action requested ini- greater speed is to be commended tially by industry and achieved to a great when time-to-market is critical and extent by the Commission. 31 “ uture Internet Public Private Partner-ship Programme - Collaboration Agreement” June 2010 (Article 4) article 3.1.2 (i) F 32 ‘Time to contract’ is the time from closure of a call for proposals until both parties in a selected project have signed the project contract.
  • 21. 21 F I N D I N G S O F T H E P A N E L 4.4. Quality The nature of ‘quality’ for the projects proposal apart from CONCORD and in the FI-PPP is different from that for neither proposal scored highly. conventional Framework Programme projects. It has been emphasised to For the Capacity Building Objective proposers, evaluators, reviewers, and there were two eligible proposals (SHIFT the present Panel that ‘the FI-PPP is not and INFINITY), but SHIFT was scored about scientific excellence but about below threshold. So INFINITY, which had making an impact’ in a collaborative only a modest score, was bound to be multi-sector innovation programme. proposed for selection according to the evaluation and selection process. However, the panel notes that the level of competition for Use Case projects in There was no competition for the Techno- the first call (a 4:1 ratio), coupled with logy Foundation Objective and FI-WARE evaluation scores for the higher ranked had a very low score - only just above proposals that are similar to those of the threshold. Yet it was also bound to typical FP7 evaluations, indicates that be proposed for selection. these projects may be considered of high quality (with the caveat that the The panel has also (as indicated in subsequent implementations may not section 4.2) examined the 6-month re- match up to the quality of the proposals). view reports. These give support to the indications above from the proposal However, among the ‘horizontal’ pro- evaluations, with at least half the Use jects there was much less competition. Case projects performing well, but pro- For the Programme Facilitation and blems with all the horizontal projects. Support Objective there was only one 4.5. Summary of findings The FI-PPP is a special (though not Repeatedly the panel heard that the unique) case of a public-private par- projects were ‘typical FP7 projects’. tnership, being set up within the 7th Framework Programme. But aside from In the next section the FI-PPP is consi- the performance of individual projects, dered in the context of the expectations the panel finds that the participants are of public-private partnerships and in not succeeding in cooperating so as to comparison with other public-private achieve the programme-level objectives. partnerships. Interim Assessment of the Future Internet Public-Private Partnership
  • 22. 22 T H E P U B L I C P R I V A T E P A R T N E R S H I P M E C H A N I S M 5. The Public Private Partnership Mechanism Given the timing of this assessment, supported by the programme will be: the work of the panel is expected to • etter aligned with market develop- b contribute to the preparatory work for ments and industrial ambitions and the detailed work programmes of Ho- so be rizon 2020, notably the guidelines for public-private partnerships. • exploited to a greater extent .. • ith benefits for both the industrial w In evaluating the FI-PPP the panel has suppliers and their customers, so that not used for comparison the broad con- .. cept of PPPs as vehicles which share • rivate investment (i.e. by industry) p risk between public authorities and pri- will increase (from the level of the vate providers, most commonly for the Framework Programme), given the delivery of infrastructure and related greater value that industry can real- services. Our interest is confined to ise from a PPP. those where the principal public input is finance for research and innovation However, for public authorities to give towards goals which are shared with to industry greater authority for the di- industry. We have therefore consid- rection of public investment (and in the ered the FI-PPP in the context of the case of some PPPs its disbursement) structures of other PPPs engaged in a PPP must not be a ‘closed shop’. It research and innovation and of related must have governance arrangements mechanisms such as Joint Technology that ensure that: Initiatives. • ts leadership is representative, inclu- i sive and authoritative; The most direct comparators for FI-PPP correspond broadly to what have been • articipation in the PPP’s governance p called ‘Market-oriented PPPs’33. These bodies is open; include the three Recovery Plan PPPs - • articipation in the evolution of its p Factories of the Future, Energy Efficient strategic agenda and in the formula- Buildings and Green Cars; the Article tion of its work-plans is open to the 171 Joint Technology Initiatives; and widest possible community; the EUREKA clusters. • articipation in its programme is open; p • ompetitive calls for participation are c In general, these PPPs are characterised managed fairly and transparently; by: • strategic agenda is developed and a • ndustry taking greater responsibility i there is a process for evolving that for formulating a research and inno- agenda to accommodate develop- vation strategy for a domain; ments in technology and markets; • ndustry managing the pursuit of that i • he programme is directed and man- t strategy. aged fairly and effectively; • he programme is administered effi- t The expectation is that if industry is ciently and with integrity. allowed to take leadership the work 33 OECD (2004), Public/Private Partnerships for Innovation in OECD Science, Technology and Industry (STI) Outlook 2004,OECD- Paris
  • 23. 23 T H E P U B L I C P R I V A T E P A R T N E R S H I P M E C H A N I S M Typically, these requirements have been enable resolution of the conflicting de- satisfied by an open industrial associa- mands for coherent coordination and tion (possibly more than one) undertak- open access. ing the management. Where such an association did not exist previously, new The following table indicates the ba- associations have been created with the sic characteristics of the FI-PPP com- specific purpose of running the PPP. pared with other PPPs. The other PPPs considered are ARTEMIS (Embedded It has typically taken a long time for Systems), ENIAC (Nano-Electronics), the communities of interest behind CLEAN SKY (reducing environmental PPPs to appreciate and assimilate the impact of aviation), FCH (Fuel Cell expectations of them and to establish Hydrogen), IMI (Innovative Medicine governance arrangements, including Initiative).34 the formation of industrial associa- tions if they did not exist before, that he table is based upon an analysis by the Commission of possible programme models for the FI-PPP during the planning phase “A Public-Private 34 T Partnership for the Future Internet”, April 2009. Two PPPs of a very different nature (GALILEO and SESAR) are not included in this comparison. Interim Assessment of the Future Internet Public-Private Partnership
  • 24. 24 Evaluation ARTEMIS ENIAC FCH CLEAN SKY IMI FI-PPP Criteria Level of detail Broad technical Broad technical Broad technical Specified technical Broad scientific Specific work- of Objectives objectives (then objectives (then objectives objectives objectives programme with (clear, specific detailed calls for detailed calls for detailed objectives; measurable) proposal) proposal) calls for proposals T H E within FP7 Level of EC + industry EC + industry EC + industry EC + 98 named EC + industry Industrial, academic definition of association and association and grouping (+ research organisations association and public-sector Membership Member states Member states grouping) organisations. P U B L I C (N.b. no formally constituted association) P R I V A T E Governing Governing Board, Governing Board, Governing Board, Governing Board, Board, Executive Steering Board structure Executive Director, Executive Director, Executive Director Executive Director, Office, Scientific Public Authorities Public Authorities Technical Steering Committee Board, Industry Board, Industry and Committees, General and Research Research Committee Forum Committee Advisory bodies Public Authorities Public Authorities States Member States Member States Advisory Board (still P A R T N E R S H I P Board, Industry Board, Industry and Representatives Group, Stakeholder to meet after 1 year) and Research Research Committee Group, Scientific Forum Committee Committee Funding National financial National financial EC 50%, Industry EC and Members, EC 50% (in cash FP7 model - model, contribution from contribution from 50% 75% pre-allocated, for SME, Academia, M E C H A N I S M processes and MS , EC 55% MS , EC 55% 25% open calls Regulators and allocations via JTI, private via JTI, private Member states and patients), Industry participants participants regions can allocate 50% (in kind for budget to individual SME…) Industry projects doesn’t received EC funding
  • 25. EC funding 420 450 470 800 1000 300 (MEuro) Legal status Community Body, Community Body, Community Body, Community Body, Community Body, FP7: articles 164 art 171 art 171 art 171 art 171 art 171 166 IPR provisions Follows EC Follows EC High level principles High-level general High level principles FP7 plus a regulation and is regulation and is modelled after FP7 provision, modelled modelled after FP7 contractual T H E provided in detail provided in detail after FP7 clause requiring programme- wide sharing of foreground IP P U B L I C Preparatory Industrial Industrial “Bridging structure” Encouraged to “Take all necessary 16 companies actions Association put in Association put in (an FP7 CSA) put facilitate a quick preparatory actions” prepared a “White place place in place with the start-up until the JU is setup paper on the P R I V A T E Industry Grouping Future Internet PPP Definition” (2010) P A R T N E R S H I P M E C H A N I S M 25 Interim Assessment of the Future Internet Public-Private Partnership
  • 26. 26 T H E P U B L I C P R I V A T E P A R T N E R S H I P M E C H A N I S M 5.1. The FI-PPP in comparison with other PPPs In order to establish the FI-PPP rapidly, sents the community of interest and it was set up using the instruments and is actively engaged in the manage- processes of FP7. In this respect the ment of guidance of the programme. objective of a rapid response by the Most of the other PPPs have some community to technological and mar- form of (open) industrial association ket developments was achieved in a both to undertake management of the way that could not have been achieved programme and to engage with the had the Joint Technology Initiative (JTI) wider community, beyond the original approach of establishing legal entities ‘thought leaders’.37 been adopted. Another major difference is that the Moreover, as noted in section 4.2.2 FI-PPP governance arrangements to above, while using the same instru- meet its obligation to be ‘the highest ments as FP7 it is notable that the FI-PPP Program governing body’ are FI-PPP has succeeded in attracting in- much less evident. dustrial involvement. In FI-PPP Call 1, private companies receive c. 66% of It might be argued that the way in total funding, compared with only 34% which responsibilities are distributed in Call 7 of FP7 Challenge 1 and 46% through the separate projects in the in Call 535. programme inhibits the establishment of a coherent system of governance, A similar approach using FP7 instru- but it is clearly the responsibility of the ments was taken in the establishment Steering Board to govern and it is not of the PPPs for Energy-efficient Build- doing so. ings, Factories of the Future, and the European Green Cars Initiative. However, The FI-PPP compares favourably in the the interim evaluation of these PPPs spectrum of European PPPs in that user- states that: engagement is central to its approach. Nonetheless, in the coming phases “While this has permitted the fast when SME participation is intended to start-up of activities and rapid im- become a key feature its actions will plementation of programmes, the benefit from extending support to other understanding of the structures and aspects of innovation, and in general to mechanisms in the wider stakeholder an engagement with the likely demand community needs to be improved”36 environment, including involvement of those responsible for regulation. That comment is equally applicable to the Future Internet community. One clear opportunity would be to link this activity with the emerging instru- A critical difference between the FI-PPP ments of pre-commercial and innovation and the other PPP’s is that there is procurement which could secure for in- no body that comprehensively repre- novative SMEs the crucial first customer. 35 he figure of 66% excludes the results of the FI-WARE Open Call. These may boost the industrial participation further. T 36 nterim Assessment of the Research PPPs in the European Economic Recovery Plan, 2011 I 37 here are several European Technology Platforms whose scope is included within or overlaps with that of the FI-PPP, notably Net!Works, NEM T and NESSI, ISI and EPOSS. And there is also the original industrial grouping of the European Future Internet Initiative Founding Members. But these organisations have neither together nor individually established anything equivalent to those of the Industrial Associations of other PPPs - with equivalent or similar governance arrangements.