37. Network Diagram with Expected Activity Times and Variances Chapter 11: Project Management 1 2 3 4 5 6 [5.5, 0.694] [7.0, 0.444] [4.83, 0.250] [10, 0.0] [4.0, 0.111] [4.33, 1.0] [11.5, 0.913] A B C D E F G
41. Probability of Project Being Completed on or Before Time 25 Chapter 11: Project Management Only path A-D-F has reasonable chance of taking 25 or more: From standard normal table in Appendix A, there is a 5.82% chance of completing project on or before time 25.
42. Probability of Path A-D-F being Completed on or Before Time 25 Chapter 11: Project Management 5.82%
43. Plan E Project Operations Network Chapter 11: Project Management
44. Proper Use of Dummy Activities Chapter 11: Project Management