Planning for NASA Procurements
MS Project Schedule Template
Small & Large Actions
$25-125K & $10-50M

Disclaimer: This briefing is not a
government document.

1
Objectives
• To identify repeatable process steps in small
and large procurements that can be called out
in MS Project schedule templates.
– The two templates are available for schedulers
working on Space Flight Systems projects.

• To support load balancing for procurement
actions throughout the year.
– It will help prevent a log jam of actions in the
fourth quarter.
Disclaimer: This briefing is not a government document.

2
Scope of the Problem
Based on a one-year sample of 3,500 procurement
actions for Spaceflight Systems
• Fewer than 600 (17%) exceeded $25,000.
• 6 procurements exceed $1 million
• 65 procurements range from $200K to $1 million
• 517 procurements range in value from $25K to
$200K
• Conclusion – Complex scheduling issues are linked to
a small number of high-value actions.
Disclaimer: This briefing is not a
government document.

3
Solutions
•
•
•
•
•

Simplified WBS for $25-125K procurements
“Plug-in” Schedule template for $25-125K
“Plug-in” Schedule template for $10-50M
Roles & Responsibility Matrix for $10-50M
Each project task in the template is set to start as early as
possible. All durations are “business days.”
Procurement Roles & Responsibilities / Process Steps Guide can be found at:
http://prod.nais.nasa.gov/portals/pl/documents/Source_Selection_Guide_March_2012.pdf

Disclaimer: This briefing is not a
government document.

4
Template Contents
• Using the templates will help project managers avoid
surprises in procurement schedules.
• Each template shows all procurement process steps
and nominal duration of tasks from start of
requirements definition to finish with award to a
vendor.
• Templates have no “date constrained” tasks and can
be directly inserted in new or existing schedules.
• They will cascade forward from the start date of the
procurement action.
Disclaimer: This briefing is not a
government document.

5
Simplified Actions $25-150K
Best & Worst Case Scenarios

Disclaimer: This briefing is not a
government document.

6
$10-50M Procurements
Best & Worst Case Scenarios
• The “typical case” depends on completing process
steps with experienced staff and managers.

Value
$1-10M

Space Flight Systems Expectations
of Business Days to Complete $10-50M
Procurement Actions at NASA GRC
Based on Federal Acquisition Regulations
Best
Typical
Case
Case
100
250

Worst
Case
300+

$10-50M

150

300

450+

>$50M

200

400

550+

Disclaimer: This briefing is not a
government document.

7
$10-50M Procurements
Estimated Duration
• Matches NASA Task and Time Estimates
Estimated Duration of NASA Procurements for $10 -50 Million
Procurement
Phase

Estimated
Duration

Business Days
Min-Max

PPIO Schedule
Using Parallel
Execution of Tasks

Phase 1

2-3 months

60-90

60

Phase 2

2-3 months

60-90

97

Phase 3

4-6 months

120-180

111

Totals

8-12 months

240-360

268

Disclaimer: This briefing is not a
government document.

8
$10-50M Procurements
Major Milestones

Disclaimer: This briefing is not a
government document.

9
Roles & Responsibilities - 1
SEC/SEB tasks displayed by who does what when
Source: GRC procurement office. See citations below.
Contracing
Officer

PHASE 1 - Estimate: 2 - 3 Months
Create SEC Schedule (incorporate planned leave)
IDIQ Task Structure (Planning for Set-up in Procurement Systems/Administration of Tasks)
Develop Work Breakdown/Funding Structure
Identify SEC Team
Source Selection Authority (Selection Official) Appointment Letter
Source Evaluation Committee Appointment Letter
OGE-450/SF-278 Financial Disclosure Forms by SEC Members
Procurement Briefing to SEC Team
Facility/Information Technology Security Plan
SEB/Security/Legal Briefing
Post Sources Sought Notice for Market Research/Small-Business Set-aside Possibilities
Draft SOW
Select/Edit Contract Clauses
Obtain E-Room or other Electronic Evaluation Tool (Protected Server)
E-Room/Electronic Tool Briefing (i.e. how to use system, enter findings)
Obtain Secure Room for Committee; Distribute Keys
Furnish Room with Materials, Supplies, Equipment
Personal Services Determination
Sources Sought Notice Responses Due
Final SOW
Develop Past Performance Questionnaire/Instructions
Develop Cost Templates/Instructions
Budget Verification (Out-year Forecasts)

Disclaimer: This briefing is not a
government document.

SEB
Chair

Project
Team

Finance

Support
& Other

Legal

Admin
Admin
Admin
Admin

10
Roles & Responsibilities - 2
SEC/SEB tasks displayed by who does what when
Source: NASA

Contracing

SEB

Project

Officer

Chair

Team

Support
Finance

& Other

PHASE 2 - Estimate: 2 - 3 Months
Industry Day/ Site Tour
DRFP/Industry Day Questions Due
Respond to DRFP/Industry Day Questions
Briefing to Source Selection Authority for Final RFP Approval
Final RFP Issue (including Cover Letter summarizing Major Changes)
Black-Out Notice
Final RFP Questions Due
Respond to Final RFP Questions
Past Performance Proposals Due
Additional Planning for Evaluation (Methodology) using RFP Sections L & M
Proposals Due
Briefing on the proper creation of a Finding
Acceptance of Proposals/ SEC Members Conflict of Interest Verification
EEO/VETS-100/CCR/Reps and Certs Compliance
Distribute Proposals for review

Disclaimer: This briefing is not a
government document.

Legal

11
Roles & Responsibilities - 3
SEC/SEB tasks displayed by who does what when
Source: NASA

Contracing

SEB

Project

Officer

Chair

Team

Support
Finance

& Other

PHASE 3 - Estimate: 4 - 6 Months (number of proposals is huge factor)
Individual Mission Suitability Evaluations
Consensus Mission Suitability Evaluations
Past Performance Evaluations
Cost Evaluations
Create Source Selection Authority Presentation
Dry-Run of Selection/Competitive Range SSA Presentation
SSA Presentation for Selection or Competitive Range Determination
Notification to Offerors; Open Discussions
Competitive Range Discussions
Interim Proposals Due
Evaluate Interim Proposals/Advise Offerors of Further Issues
Interim Questions to Offerors
Final Proposals Due
Final Proposal Evaluation; Revisions to Findings
Create Final SSA Presentation
Dry-Run of SSA Presentation
Final SSA Presentation
Source Selection Statement
ANOSCA/Press Release
Debriefings
Protest Period
Award Contract; Process in Procurement's CMM System
Commence Phase-In

Disclaimer: This briefing is not a
government document.

Ex-Officio

12
Caveats
• Real experiences in terms of duration will be longer
than the ideal.
• A full team will staff up and remain available
throughout the procurement process.
• Wait time for managers to get to decision packages is
minimal though not always achievable.
• Post award engagement with the vendor for long
lead time items will reduce risks.

Disclaimer: This briefing is not a
government document.

13
Wrap Up
• A $10-50M procurement is a full time job for
the “wagon master” in charge of it.

Disclaimer: This briefing is not a
government document.

14
Backup Slides

Disclaimer: This briefing is not a
government document.

15
Large Procurements
• Detailed schedule
• Three major phases
• Work tasks conducted in parallel

Disclaimer: This briefing is not a
government document.

16
Phase 1 Milestones
Create Schedules / WBS
1.
2.
3.
4.
5.
6.

Create procurement WBS
Form source evaluation team
Set up admin support / logistics
Draft statement of work (SOW)
Draft request for proposal (RFP)
Procurement Strategy Briefing

Disclaimer: This briefing is not a
government document.

17
Phase 1 Schedule
Parts 1-3 Milestones

Disclaimer: This briefing is not a
government document.

18
Phase 1 Schedule
Parts 4-5 Milestones

Disclaimer: This briefing is not a government document.

19
Phase 1 Schedule
Part 6 Milestone

Disclaimer: This briefing is not a
government document.

20
Phase 2 Milestones
Publish RFP/ Receive Bids
1. Complete RFP
2. Vendor Response Completion

Disclaimer: This briefing is not a
government document.

21
Phase 2 Schedule
Part 1 Milestone

Disclaimer: This briefing is not a
government document.

22
Phase 2 Schedule
Part 2 Milestone

Disclaimer: This briefing is not a
government document.

23
Part 3 Milestones
Review Bids / Award Contract
1. Review RFP Responses
2. Source Selection Decision

Disclaimer: This briefing is not a
government document.

24
Phase 3 Schedule
Part 1 Milestone

Disclaimer: This briefing is not a
government document.

25
Phase 3 Schedule
Part 2 Milestone

Disclaimer: This briefing is not a
government document.

26
Conceptual Blockbusting
• Very large procurements can and will bog
down under the weight of multiple layers of
complex requirements.
• Project managers can reduce procurement
time by breaking up acquisitions into a parallel
series of lower cost buys creating a “portfolio”
of smaller, faster moving actions such as
design, fabrication, and system integration.
Disclaimer: This briefing is not a
government document.

27
Causes of Procurement Delays
• Incomplete specifications
– Vendors cannot fabricate based on poorly defined
requirements.

• Incomplete or incorrect paperwork
– NASA GRC Forms C-376 & 1707 cannot be processed with
missing or incorrect information.

• Incorrect color of money is used
– CFO funds approval and financial checks of the
procurement include that the correct WBS is being used.

• Insufficient time allowed for vendor to deliver
– Especially for the selected vendor to fabricate and deliver
the materials, goods, components, and/or services.
Disclaimer: This briefing is not a
government document.

28
Vendor Relations
Post Award
• Don’t let the vendor be a black box on long-lead
time, high-value procurements.
– If delivery time for a high-value procurement is more
than six weeks, consider including a series of check-ins
starting at the 20-day mark.
– Consider on-site visits, including design and
engineering reviews, especially if fabrication involves
a first-of-a-kind product.

• Be sure to address these issues in the initial
requirements that are sent to the vendor.
Disclaimer: This briefing is not a
government document.

29
Sole Source Actions > $150K
• Sole source procurements greater than $150K require a
“Justification of Other than Competitive” action (JOFOC).
• The approved document is published on www.fbo.gov for
15 days.
• When in doubt about a sole source approach, contact
procurement for advice.
• A response from a valid vendor stops the clock and may
start one for a competitive process.
• If your procurement is not approved to be sole-source, and
is for more than $150K, the contracting officer has
discretion in setting reasonable time frames for publishing
a pre-solicitation synopsis for large buys as well as vendor
response time for a solicitation.
Disclaimer: This briefing is not a
government document.

30
Contact
Dan Yurman
Email: djysrv@gmail.com
Linkedin
http://www.linkedin.com/in/danyurman/
Mobile: 216-218-3823
Twitter: @djysrv
Disclaimer: This briefing is not a
government document.

31

More Related Content

What's hot

Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate template
Steven Bonacorsi
 
Work study method and time study-final - copy
Work study method and time study-final - copyWork study method and time study-final - copy
Work study method and time study-final - copy
Hareesh M
 
8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training
Bryan Len
 
MRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERPMRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERP
Tom Matys
 

What's hot (20)

Improve phase lean six sigma tollgate template
Improve phase   lean six sigma tollgate templateImprove phase   lean six sigma tollgate template
Improve phase lean six sigma tollgate template
 
Work study method and time study-final - copy
Work study method and time study-final - copyWork study method and time study-final - copy
Work study method and time study-final - copy
 
8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training8D Training, Eight Disciplines Training : Tonex Training
8D Training, Eight Disciplines Training : Tonex Training
 
Kaizen Event Guide
Kaizen Event GuideKaizen Event Guide
Kaizen Event Guide
 
Six Sigma Black Belt Project
Six Sigma Black Belt ProjectSix Sigma Black Belt Project
Six Sigma Black Belt Project
 
7QC Tools
7QC Tools7QC Tools
7QC Tools
 
8D Problem Solving - Automotive Industry
8D Problem Solving - Automotive Industry8D Problem Solving - Automotive Industry
8D Problem Solving - Automotive Industry
 
Root Cause Corrective Action
Root Cause Corrective ActionRoot Cause Corrective Action
Root Cause Corrective Action
 
PDCA Cycle
PDCA CyclePDCA Cycle
PDCA Cycle
 
Just In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter PresentationJust In Time and Lean Operation Chapter Presentation
Just In Time and Lean Operation Chapter Presentation
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
MRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERPMRP (Materials Requirements Planning) in ERP
MRP (Materials Requirements Planning) in ERP
 
Affinity and relationship diagram
Affinity and relationship diagramAffinity and relationship diagram
Affinity and relationship diagram
 
Plan-for-Every-Part (PFEP) - Introduction November 2016
Plan-for-Every-Part (PFEP) - Introduction November 2016Plan-for-Every-Part (PFEP) - Introduction November 2016
Plan-for-Every-Part (PFEP) - Introduction November 2016
 
Process fmea
Process fmea Process fmea
Process fmea
 
Tpm principles and concepts
Tpm principles and conceptsTpm principles and concepts
Tpm principles and concepts
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Kanban
KanbanKanban
Kanban
 
Just in time (jit)
Just in time (jit)Just in time (jit)
Just in time (jit)
 
SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997SMRP (1997) Proactive Maintenance Slides by John Day - 1997
SMRP (1997) Proactive Maintenance Slides by John Day - 1997
 

Viewers also liked (7)

omah coffee 15.08
omah coffee 15.08omah coffee 15.08
omah coffee 15.08
 
Action Road Map Planning Tool
Action Road Map Planning ToolAction Road Map Planning Tool
Action Road Map Planning Tool
 
Project Schedule Template
Project Schedule TemplateProject Schedule Template
Project Schedule Template
 
Timeline and checklist for event planning
Timeline and checklist for event planningTimeline and checklist for event planning
Timeline and checklist for event planning
 
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDEEVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
EVENT MANAGEMENT PLAN CHECKLIST AND GUIDE
 
Event checklist
Event checklistEvent checklist
Event checklist
 
Project Planning
Project PlanningProject Planning
Project Planning
 

Similar to MS Project 2010 schedule template for large NASA procurements $10-450 million

USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
tkjohns1
 
Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1
Fred Zuercher
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptx
PhngPhmTrung
 

Similar to MS Project 2010 schedule template for large NASA procurements $10-450 million (20)

Top 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple ConstraintTop 3 Challenges in Managing Triple Constraint
Top 3 Challenges in Managing Triple Constraint
 
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%Project Storyboard: Reducing Cycle Time for Bid Tab Creationby 33%
Project Storyboard: Reducing Cycle Time for Bid Tab Creation by 33%
 
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
PROJECT STORYBOARD: Project Storyboard: Reducing Underwriting Resubmits by Ov...
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
Case Study - Deficit Analysis
Case Study - Deficit AnalysisCase Study - Deficit Analysis
Case Study - Deficit Analysis
 
IT Operations Consulting
IT Operations Consulting  IT Operations Consulting
IT Operations Consulting
 
Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014Contracting Best Practices - MESC 2014
Contracting Best Practices - MESC 2014
 
Contract administration iowa AGC
Contract administration iowa AGCContract administration iowa AGC
Contract administration iowa AGC
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Inbound MIPR Process
Inbound MIPR ProcessInbound MIPR Process
Inbound MIPR Process
 
USAF 694 Arss Drone
USAF 694 Arss DroneUSAF 694 Arss Drone
USAF 694 Arss Drone
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1Lean Six Sigma Green Belt Certification 1
Lean Six Sigma Green Belt Certification 1
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
Major Projects - Faster Better Cheaper
Major Projects - Faster Better CheaperMajor Projects - Faster Better Cheaper
Major Projects - Faster Better Cheaper
 
Lec 8.....week 12-14.ppt
Lec 8.....week 12-14.pptLec 8.....week 12-14.ppt
Lec 8.....week 12-14.ppt
 
Six_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptxSix_Sigma_Report_Template_v2 (2).pptx
Six_Sigma_Report_Template_v2 (2).pptx
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
Scope Management
Scope ManagementScope Management
Scope Management
 
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
Invest NI Lean Conference 2016 | Case Study: Elite | Developing and sustainin...
 

More from Self employed (6)

BVU Encore IT project July 2018 status report
BVU Encore IT project  July  2018 status report BVU Encore IT project  July  2018 status report
BVU Encore IT project July 2018 status report
 
Organizing a Project Management Office
Organizing a Project Management OfficeOrganizing a Project Management Office
Organizing a Project Management Office
 
Strategic planning and technology management
Strategic planning and technology managementStrategic planning and technology management
Strategic planning and technology management
 
Blogs tell stories
Blogs tell storiesBlogs tell stories
Blogs tell stories
 
Do you have klout?
Do you have klout?Do you have klout?
Do you have klout?
 
Not Even Close And No Cigar
Not Even Close And No CigarNot Even Close And No Cigar
Not Even Close And No Cigar
 

Recently uploaded

Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
dlhescort
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
lizamodels9
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
dlhescort
 

Recently uploaded (20)

Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
Call Girls Zirakpur👧 Book Now📱7837612180 📞👉Call Girl Service In Zirakpur No A...
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLWhitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
Whitefield CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂EscortCall Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
Call Girls In Nangloi Rly Metro ꧂…….95996 … 13876 Enjoy ꧂Escort
 

MS Project 2010 schedule template for large NASA procurements $10-450 million

  • 1. Planning for NASA Procurements MS Project Schedule Template Small & Large Actions $25-125K & $10-50M Disclaimer: This briefing is not a government document. 1
  • 2. Objectives • To identify repeatable process steps in small and large procurements that can be called out in MS Project schedule templates. – The two templates are available for schedulers working on Space Flight Systems projects. • To support load balancing for procurement actions throughout the year. – It will help prevent a log jam of actions in the fourth quarter. Disclaimer: This briefing is not a government document. 2
  • 3. Scope of the Problem Based on a one-year sample of 3,500 procurement actions for Spaceflight Systems • Fewer than 600 (17%) exceeded $25,000. • 6 procurements exceed $1 million • 65 procurements range from $200K to $1 million • 517 procurements range in value from $25K to $200K • Conclusion – Complex scheduling issues are linked to a small number of high-value actions. Disclaimer: This briefing is not a government document. 3
  • 4. Solutions • • • • • Simplified WBS for $25-125K procurements “Plug-in” Schedule template for $25-125K “Plug-in” Schedule template for $10-50M Roles & Responsibility Matrix for $10-50M Each project task in the template is set to start as early as possible. All durations are “business days.” Procurement Roles & Responsibilities / Process Steps Guide can be found at: http://prod.nais.nasa.gov/portals/pl/documents/Source_Selection_Guide_March_2012.pdf Disclaimer: This briefing is not a government document. 4
  • 5. Template Contents • Using the templates will help project managers avoid surprises in procurement schedules. • Each template shows all procurement process steps and nominal duration of tasks from start of requirements definition to finish with award to a vendor. • Templates have no “date constrained” tasks and can be directly inserted in new or existing schedules. • They will cascade forward from the start date of the procurement action. Disclaimer: This briefing is not a government document. 5
  • 6. Simplified Actions $25-150K Best & Worst Case Scenarios Disclaimer: This briefing is not a government document. 6
  • 7. $10-50M Procurements Best & Worst Case Scenarios • The “typical case” depends on completing process steps with experienced staff and managers. Value $1-10M Space Flight Systems Expectations of Business Days to Complete $10-50M Procurement Actions at NASA GRC Based on Federal Acquisition Regulations Best Typical Case Case 100 250 Worst Case 300+ $10-50M 150 300 450+ >$50M 200 400 550+ Disclaimer: This briefing is not a government document. 7
  • 8. $10-50M Procurements Estimated Duration • Matches NASA Task and Time Estimates Estimated Duration of NASA Procurements for $10 -50 Million Procurement Phase Estimated Duration Business Days Min-Max PPIO Schedule Using Parallel Execution of Tasks Phase 1 2-3 months 60-90 60 Phase 2 2-3 months 60-90 97 Phase 3 4-6 months 120-180 111 Totals 8-12 months 240-360 268 Disclaimer: This briefing is not a government document. 8
  • 9. $10-50M Procurements Major Milestones Disclaimer: This briefing is not a government document. 9
  • 10. Roles & Responsibilities - 1 SEC/SEB tasks displayed by who does what when Source: GRC procurement office. See citations below. Contracing Officer PHASE 1 - Estimate: 2 - 3 Months Create SEC Schedule (incorporate planned leave) IDIQ Task Structure (Planning for Set-up in Procurement Systems/Administration of Tasks) Develop Work Breakdown/Funding Structure Identify SEC Team Source Selection Authority (Selection Official) Appointment Letter Source Evaluation Committee Appointment Letter OGE-450/SF-278 Financial Disclosure Forms by SEC Members Procurement Briefing to SEC Team Facility/Information Technology Security Plan SEB/Security/Legal Briefing Post Sources Sought Notice for Market Research/Small-Business Set-aside Possibilities Draft SOW Select/Edit Contract Clauses Obtain E-Room or other Electronic Evaluation Tool (Protected Server) E-Room/Electronic Tool Briefing (i.e. how to use system, enter findings) Obtain Secure Room for Committee; Distribute Keys Furnish Room with Materials, Supplies, Equipment Personal Services Determination Sources Sought Notice Responses Due Final SOW Develop Past Performance Questionnaire/Instructions Develop Cost Templates/Instructions Budget Verification (Out-year Forecasts) Disclaimer: This briefing is not a government document. SEB Chair Project Team Finance Support & Other Legal Admin Admin Admin Admin 10
  • 11. Roles & Responsibilities - 2 SEC/SEB tasks displayed by who does what when Source: NASA Contracing SEB Project Officer Chair Team Support Finance & Other PHASE 2 - Estimate: 2 - 3 Months Industry Day/ Site Tour DRFP/Industry Day Questions Due Respond to DRFP/Industry Day Questions Briefing to Source Selection Authority for Final RFP Approval Final RFP Issue (including Cover Letter summarizing Major Changes) Black-Out Notice Final RFP Questions Due Respond to Final RFP Questions Past Performance Proposals Due Additional Planning for Evaluation (Methodology) using RFP Sections L & M Proposals Due Briefing on the proper creation of a Finding Acceptance of Proposals/ SEC Members Conflict of Interest Verification EEO/VETS-100/CCR/Reps and Certs Compliance Distribute Proposals for review Disclaimer: This briefing is not a government document. Legal 11
  • 12. Roles & Responsibilities - 3 SEC/SEB tasks displayed by who does what when Source: NASA Contracing SEB Project Officer Chair Team Support Finance & Other PHASE 3 - Estimate: 4 - 6 Months (number of proposals is huge factor) Individual Mission Suitability Evaluations Consensus Mission Suitability Evaluations Past Performance Evaluations Cost Evaluations Create Source Selection Authority Presentation Dry-Run of Selection/Competitive Range SSA Presentation SSA Presentation for Selection or Competitive Range Determination Notification to Offerors; Open Discussions Competitive Range Discussions Interim Proposals Due Evaluate Interim Proposals/Advise Offerors of Further Issues Interim Questions to Offerors Final Proposals Due Final Proposal Evaluation; Revisions to Findings Create Final SSA Presentation Dry-Run of SSA Presentation Final SSA Presentation Source Selection Statement ANOSCA/Press Release Debriefings Protest Period Award Contract; Process in Procurement's CMM System Commence Phase-In Disclaimer: This briefing is not a government document. Ex-Officio 12
  • 13. Caveats • Real experiences in terms of duration will be longer than the ideal. • A full team will staff up and remain available throughout the procurement process. • Wait time for managers to get to decision packages is minimal though not always achievable. • Post award engagement with the vendor for long lead time items will reduce risks. Disclaimer: This briefing is not a government document. 13
  • 14. Wrap Up • A $10-50M procurement is a full time job for the “wagon master” in charge of it. Disclaimer: This briefing is not a government document. 14
  • 15. Backup Slides Disclaimer: This briefing is not a government document. 15
  • 16. Large Procurements • Detailed schedule • Three major phases • Work tasks conducted in parallel Disclaimer: This briefing is not a government document. 16
  • 17. Phase 1 Milestones Create Schedules / WBS 1. 2. 3. 4. 5. 6. Create procurement WBS Form source evaluation team Set up admin support / logistics Draft statement of work (SOW) Draft request for proposal (RFP) Procurement Strategy Briefing Disclaimer: This briefing is not a government document. 17
  • 18. Phase 1 Schedule Parts 1-3 Milestones Disclaimer: This briefing is not a government document. 18
  • 19. Phase 1 Schedule Parts 4-5 Milestones Disclaimer: This briefing is not a government document. 19
  • 20. Phase 1 Schedule Part 6 Milestone Disclaimer: This briefing is not a government document. 20
  • 21. Phase 2 Milestones Publish RFP/ Receive Bids 1. Complete RFP 2. Vendor Response Completion Disclaimer: This briefing is not a government document. 21
  • 22. Phase 2 Schedule Part 1 Milestone Disclaimer: This briefing is not a government document. 22
  • 23. Phase 2 Schedule Part 2 Milestone Disclaimer: This briefing is not a government document. 23
  • 24. Part 3 Milestones Review Bids / Award Contract 1. Review RFP Responses 2. Source Selection Decision Disclaimer: This briefing is not a government document. 24
  • 25. Phase 3 Schedule Part 1 Milestone Disclaimer: This briefing is not a government document. 25
  • 26. Phase 3 Schedule Part 2 Milestone Disclaimer: This briefing is not a government document. 26
  • 27. Conceptual Blockbusting • Very large procurements can and will bog down under the weight of multiple layers of complex requirements. • Project managers can reduce procurement time by breaking up acquisitions into a parallel series of lower cost buys creating a “portfolio” of smaller, faster moving actions such as design, fabrication, and system integration. Disclaimer: This briefing is not a government document. 27
  • 28. Causes of Procurement Delays • Incomplete specifications – Vendors cannot fabricate based on poorly defined requirements. • Incomplete or incorrect paperwork – NASA GRC Forms C-376 & 1707 cannot be processed with missing or incorrect information. • Incorrect color of money is used – CFO funds approval and financial checks of the procurement include that the correct WBS is being used. • Insufficient time allowed for vendor to deliver – Especially for the selected vendor to fabricate and deliver the materials, goods, components, and/or services. Disclaimer: This briefing is not a government document. 28
  • 29. Vendor Relations Post Award • Don’t let the vendor be a black box on long-lead time, high-value procurements. – If delivery time for a high-value procurement is more than six weeks, consider including a series of check-ins starting at the 20-day mark. – Consider on-site visits, including design and engineering reviews, especially if fabrication involves a first-of-a-kind product. • Be sure to address these issues in the initial requirements that are sent to the vendor. Disclaimer: This briefing is not a government document. 29
  • 30. Sole Source Actions > $150K • Sole source procurements greater than $150K require a “Justification of Other than Competitive” action (JOFOC). • The approved document is published on www.fbo.gov for 15 days. • When in doubt about a sole source approach, contact procurement for advice. • A response from a valid vendor stops the clock and may start one for a competitive process. • If your procurement is not approved to be sole-source, and is for more than $150K, the contracting officer has discretion in setting reasonable time frames for publishing a pre-solicitation synopsis for large buys as well as vendor response time for a solicitation. Disclaimer: This briefing is not a government document. 30
  • 31. Contact Dan Yurman Email: djysrv@gmail.com Linkedin http://www.linkedin.com/in/danyurman/ Mobile: 216-218-3823 Twitter: @djysrv Disclaimer: This briefing is not a government document. 31