We enjoyed our meeting last night with the Hearst Elementary School PTA. If you happened to have missed the meeting or simply wish to share the update and modernization timeline with your neighbors, friends and family feel free to share! Thanks.
FYI: After further discussion with the Project Manager and Contractor concerning the two-story trailer construction timeline at Hearst Elementary School, there are some edits to keep you informed and up-to-date.
PTA Meeting (02/13/2013)
2. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Amendment Advisory:
After further discussion with the Project Manager and Contractor concerning
the two-story trailer construction timeline, there are amendments to help
maintain transparency and accuracy with you.
ALL AMENDMENTS ARE WRITTEN IN YELLOW.
3. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Agenda
Introductions
Meeting Recap and Updates
Modernization Timeline
Layout Overview
Q&A
Next Steps
4. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Meeting Recap and Updates
Builder Award
Turner Construction
Supplemental Demountable/Demountable Relocations
Will Erect 2nd Floor on Existing Trailer near Rec Center
Restroom Accommodations
Will Be Available in New 2nd Story
Covered Walkways
Walkways will be covered, except for connecting Hearst to Trailer
Hearst School Modernization
Site Work Begins April
Construction Done over Summer 2013
5. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Modernization Timeline
External Construction (April 2013)
Trailer Construction (June 2013)
Hearst Building Modernization (Summer 2013)
6. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Hearst Elementary School
7. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
External Construction Timing – April 2013
8. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
External Construction Timing – May 2013
9. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Construction Timing – Summer 2013
New Two
Story
Trailer
10. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Restroom Trailer Plan
11. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Sample Trailer Bathroom Photo
12. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Proposed Modified Trailer Plan
13. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Proposed Modified Trailer Plan
14. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Sample Double Level Trailer Photo
PHOTO HAS BEEN EXPANDED WITH ADDED TEXT BOX
15. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Barnard Elementary School External Trailer
16. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Sample Internal Trailer Photos
Hallway Photo
Library Photo
Bruce-Monroe at Parkview Classroom Photos
17. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Questions & Answers
18. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Next Steps
Monthly Updates via Email and Website dgs.dc.gov
Future Meetings on an As-Needed Basis
Any questions or concerns should be sent to Darrell Pressley at
darrell.pressley@dc.gov
19. Elevating the Quality of Life in the District
Elevating the Quality of Life in the District
Thank You!