Able Data – Reference Sites

Vizion Apartments, Milton Keynes
Summary      TV & Satellite System for 405 Apartments
Contact      Rob Barker, Electrical Services, BAM Construction. 01727 894 203
             Centrum Business Park, Building 4, St Albans, Herts. AL1 2RD
Location     Part of the Abbey gate Sainsbury’s development, Milton Keynes
Contract     £350K
Systems      Fracarro IRS Equipment
Timescales   March 2007 - November 2008
Contractor   BAM
Project     Able Data were contracted to build an IRS system for the new Abbey gate
Description Sainsbury’s development in Milton Keynes.
            Over the large development, it was decided to build a separate aerial rig
            and head end on each main block, subdividing the project into smaller
            independent units. Each flat was provided with its own TV and Data patch
            cabinet to allow flexible re-configuration of the services.
            One of the challenges was to build temporary TV/Sat head ends to
            accommodate new tenants moving whilst the main development continued.
Pictures




                                                                 Able Data Installations Plc
                                                                        Tel: 01442 219580
                                                                       www.abledata.co.uk
Able Data – Reference Sites

West Herts College
Summary        Cabling of new college campus
Contact        Rob Barker
               BAM Construction
               Centrium Business Park, Building 4
               St Albans, Herts. AL1 2RD
               Tel: 020 8879 1188
Location        Watford
Contract       £500K
Systems        SYSTIMAX GigaSPEED X10D, Prism Cabinets
Start & Finish Jan 2010 – April 2010
Contractor      BAM
Project         West Herts College has embarked on a long-term property strategy to
Description     modernise its facilities and transform campus life. As part of their
                plans they have built a new flagship Watford campus offering state-of-
                the-art facilities in an inspiring environment.
                Able Data were contracted to install a high performance campus wide
                structured cabling system. Over three months Able Data installed
                7,000 SYSTIMAX Cat6a UTP outlets.
Pictures




                                                               Able Data Installations Plc
                                                                      Tel: 01442 219580
                                                                    www.abledata.co.uk
Able Data – Reference Sites

Veolia Three Valleys Water
Summary          Cabling of building
Contact          Bob Davis, Senior ICT Consultant
                 Mace
                 Atelier House, 64 Pratt Street
                 London
                 NW1 0LF
                 Tel: 020 7554 8000
Location         Hatfield Business Park, Hatfield
Contract         £200K
Systems          Molex PowerCat 6 UTP Cat6
Start & Finish   Nov 2008 – Jan 2009
Consultant       Mace
Contractor       Como
Project          Veolia Water (formally Three Valleys Water) consolidated their
Description      offices into the new HUB building in Hatfield, a building to house 750
                 office staff.
                 Able Data were contracted by Como to install a 3,000 outlet Cat6 data
                 cabling system. Run over four floors, outlets were terminated in a grid
                 of 8-way consolidation points installed under the false floor. Desk
                 outlets were connected to the consolidation points through solid patch
                 lead connections.
                 The project was completed over a period of two months.
Pictures




                                                                Able Data Installations Plc
                                                                       Tel: 01442 219580
                                                                     www.abledata.co.uk
Able Data – Reference Sites

South Thames College
Summary      Cat6 Cable installation in to a refurbished part of the College
             Development.
Contact      Rob Barker
             BAM Construction
             Centrium Business Park, Building 4
             St Albans, Herts. AL1 2RD
             Tel: 020 8879 1188
Location     Wandsworth London
Contract     £85K
Systems      Brand-Rex Cat6 & OM3 Fibre Backbone
Installed
Start &      April 2010 to Oct 2010
Finish
Consultant   None
Main         BAM
Contractor
Project     Able Data installed 1200 Brand-Rex Cat6 Outlets and 288 Fibre Links.
Description This was an extremely difficult installation due to the Building
            Restraints and the age of the Building An important scheduling
            consideration was the requirement to fit around the School Terms.
Picture




                                                             Able Data Installations Plc
                                                                    Tel: 01442 219580
                                                                  www.abledata.co.uk
Able Data – Reference Sites

Misys
Summary          Cabling & moves into new headquarters building
Contact          Phil Davies, IT Manager.
                 Misys
                 One Kingdom Street, Paddington. W2 6BL
                 Tel: 020 8879 1188
Location         Paddington, London
Contract         £300K
Systems          Brand-Rex Cat6 & OM3, Cooper B-Line Cabinets
Start & Finish   Feb – Aug 2008
Consultant       April Management
Contractor       Mastercraft Design
Project          Misys were consolidating four regional offices into one new
Description      headquarters building.

                 The new offices required 3,000 Brand Rex LSOH Cat6 outlets
                 installed over three floors, each floor being cabled from two patch
                 rooms. Able Data connected the patch rooms through diversely routed
                 OM3 fibre and voice backbones. In the main computer room, Able
                 Data installed Cooper B-Line cabinets, fitted with the Unite Hawki-2
                 intelligent power monitor and control products.

                 Able Data also managed the movement of 500 users into the new
                 building. Scheduled over five weekends, this included providing an
                 asset register of all of their computer equipment and a full moves
                 service into the new offices, including connection and test of all of the
                 desktop equipment.
Pictures




                                                                  Able Data Installations Plc
                                                                         Tel: 01442 219580
                                                                        www.abledata.co.uk
Able Data – Reference Sites

HBG – Crawley Schools
Summary          Installation of Data/Voice & TV cabling in three Schools.
Contact          Mr Steve Rooke
                 HBG Construction
                 Merit House, Edgware Road, Colindale, NW9 5AF.
                 Tel: 020 8200 7070
Location         Crawley, West Sussex
Contract         £300K
Systems          Data: 6,000 Brand-Rex Cat5e Outlets plus OM3 fibre.
                 TV:   1,000 TV outlets. Fracarro K-series head end through Webro
                       CT167/CT100 cables.
Start & Finish   Feb 2004 – Aug 2005
Consultant       N/A
Contractor       HBG Construction
Project          HBG have built three new secondary schools in West Sussex, Oriel,
Description      Ifield and Thomas Bennett. As part of this project, they contracted
                 Able Data to design and install a data cabling and TV distribution
                 system.
                 The data cabling systems are based on the Brand Rex Millenium
                 Cat5e system. In each school, Able Data installed 2,000 RJ45 outlets
                 in class rooms, staff rooms and other locations. These outlets were run
                 back to a number of local patch cabinets, which were in turn
                 connected back to the main computer room via OM3 fibre.
                 The TV distribution system includes 300 class room TV outlets per
                 school. Within each school, these are fed from a single central head
                 end, which is in turn fed from a single set of TV and radio aerials. The
                 head end equipment includes a high quality Fracarro K-series
                 processing system, which as well as providing high quality TV
                 terrestrial analogue and digital channels, presents FM and DAB radio
                 to all outlets. The school can also broadcast channels from their own
                 video sources, such as DVD players, tapes or cameras.
Picture




                 Oriel School

                                                                 Able Data Installations Plc
                                                                        Tel: 01442 219580
                                                                      www.abledata.co.uk
Able Data – Reference Sites

Fidelity Oakhill Data Centre
Summary       New Data Centre at the Fidelity HQ
Contact       John Brogan, Project Manager
              Fidelity International
              Oakhill House, 130 Tonbridge Rd
              Hildenborough, Kent, TN11 9DZ
              Tel: 01732 361 144
Location      Tonbridge, Kent
Contract      £2.5M
Systems       Systimax Cat 6, LazrSPEED 300 OM3, iPatch, CPI Patch Frames
Installed     Jul – Oct 2009
Project     Fidelity International is a world-wide leading investment provider. As
Description part of their UK data centre consolidation strategy, Fidelity required a
            new Data Centre facility at its HQ facility at Tonbridge.
            Spread over two underground data halls and two office floors, the
            project required the installation of 30,000 Cat6 copper links and 11,000
            OM3 duplex fibre links to 300 Rittal cabinets and used more than
            700km of cable. All links connect to a patch field of 80 x CPI patch
            frames, each monitored with the iPatch Intelligent patch system.
            The Data Centre was cabled overhead on three levels of CPI ladder
            racking. One of the biggest challenges faced by Able Data was to
            deliver the required high quality of cabling. To work out the optimum
            cable routing schemes, Able Data built an offsite mock up of a row of
            patch frames and the associated cables. To speed up installation whilst
            minimising unsightly cable slack, Able Data single end pre-terminated
            all copper and fibre links. The entire installation was completed over a
            14 week period.
            As well as building and configuring a 40,000 port iPatch system to
            manage patching and monitor network devices, Able Data implemented
            additional bespoke functionality tailored to Fidelity’s requirements,
            including auto server provisioning.
Pictures




                                                               Able Data Installations Plc
                                                                      Tel: 01442 219580
                                                                    www.abledata.co.uk
Able Data – Reference Sites

Fidelity Investments
Summary       Cabling of Fidelity’s Date Centres
Contact       Dexter Baird
              Oakhill House, 130 Tonbridge Road
              Hildenborough, Kent
              TN11 9DZ
              Tel: 01732 777627
Location      Acton Colt Data Centre, London
              Global Switch 2 Data Centre, London
Contract      £650K (Total)
Systems       SYSTIMAX GigaSPEED XL Cat6
              SYSTIMAX LazrSPEED OM2, OM3
Start &       Jan 2003 – May 2003
Finish        Nov 2005 – Dec 2005
              Jul 2006
Project       In three separate projects, Able Data have cabled Fidelity’s London
Description   based Data centres.
              In the first project Able Data supplied and installed thirty data
              cabinets and the required cabling infrastructure. The initial installation
              of 4,000 copper links was completed within four weeks. All RJ45
              patch panels are of the Avaya Fleximax variety, where standard outlet
              modules are clipped into the panel.
              The second and third projects were similar, but on a larger scale. The
              third project at Global Switch involved 10,000 links, installed over a
              period of one month, made possible by the use of off site pre-
              termination,
              As part of the initial project, Able Installed also 1,000 10Gbit OM2
              fibre links, terminated onto SC connector outlets. The later projects
              used LC connectors.
Pictures




                                                                  Able Data Installations Plc
                                                                         Tel: 01442 219580
                                                                       www.abledata.co.uk
Able Data – Reference Sites

Debenhams
Summary       Data Cabling for new and refurbished Department Stores
Contact       Peter Craven, Project Manager.
              Bedford Road, Park Street, Taunton,
              Somerset, TA1 4DB
              Tel: 01823 364 303
Location      Various retail sites including Hemel Hempstead, Thanet, Woking,
              Portsmouth & Slough.
Contract      £150K
Systems       SYSTIMAX PowerSUM Cat5e & Excel Cabinets
Start &       November 2004 (Thanet)
Finish        March 2005 (Portsmouth, Woking, Sough)
              April 2005 (Hemel Hempstead)
Consultant    N/A
Contractor    Various
Project       Debenhams has an ongoing program of opening new stores. In each
Description   they install a structured cabling system to serve the shop floor tills and
              pay points as well as the general offices. It is Debenhams policy to use
              SYSTIMAX PowerSUM cabling throughout.
              By the nature of shop premises, most of the cabling work is in the
              ceiling void, requiring the extensive use of platforms.
              Each store floor will normally have its own cabling cabinet. These
              cabinets are joined to the master cabinet via either fibre or copper
              interlinks, depending on the distances involved.
              Part of this project involved the fast track conversion of three Alders
              stores to Debenhams in March 2005. This involved the use of three
              separate cabling teams working on the different sites.
Pictures




                                                                 Able Data Installations Plc
                                                                        Tel: 01442 219580
                                                                      www.ablecable.co.uk
Able Data – Reference Sites

Church Commissioners
Summary       Installation of Data & Voice Cabling over 6 floors
Contact       Martyn Chadaway
              CBI, ‘The Gherkin’, 30 St Mary Axe, London, EC3A 8AD.
Location      The Corporation of Church House, Church House, Great Smith Street,
              London. SW1P 3AZ.
Contract      £180K
Systems       Tyco Amp Cat6 STP & Quantum Cat5e UTP
Timescales    September 2006 – March 2007
Consultant    CBI
Project     The Corporation of The Church House was founded in 1888 as the Church
Description of England's permanent tribute to Queen Victoria's Golden Jubilee. The
            Church House, a grade II listed building, is the headquarters of the
            Archbishops' Council and all its Boards and Councils as well as of the
            Church of England Pensions Board and the National Society. It is the
            meeting-place, twice each year, of the General Synod of the Church of
            England.
            Church House also contains a Conference Centre that provides
            accommodation and facilities for a vast variety of events from AGMs,
            conferences, dinners and receptions to exhibitions.
            Able Data were contracted to install 1500 outlets over 6 floors and the
            conference centre. The key challenge of delivering this project was the
            complexity of the cable routes. The building is listed and most of the
            original features of the conference centre, meeting & conference rooms on
            the Ground and Lower Ground floors could not be changed or put in any
            risk of being damaged.
Pictures




                                                                   Able Data Installations Plc
                                                                          Tel: 01442 219580
                                                                         www.abledata.co.uk
Able Data – Reference Sites

Bucks New University (BNU)
Summary      Installation of Data & Voice Cabling over 13 Floors
Contact      Andy MacFarlane
             BAM Construction
             Centrium, Griffiths Way
             St Albans, Herts. AL1 2RD
Location     High Wycombe
Contract     £150K
Systems      Excel Cat6
Installed    Apr 2009 – Dec 2009
Contractor   BAM
Project     Buckinghamshire New University’s camp has undergone an extensive
Description £60m programme of rebuilding in 2009. A new, high-tech learning
            resources centre, known as the Gateway, forms the focal point of the
            University’s technology-led learning experience.
            Able Data were contracted by BAM to install an 1,800 Excel Cat6
            UTP cabling system, spread over the six patch rooms on the six floors
            of the new Gateway building extension. Able Data also installed an
            Blown Fibre (OM3) & a voice link backbone cabling infrastructure
            between each patch room and the main computer room on the 4th floor.
Picture




                                                              Able Data Installations Plc
                                                                     Tel: 01442 219580
                                                                   www.abledata.co.uk
Able Data – Reference Sites

Ashmolean Museum
Summary Cabling of Major New Building Extension
Contact     Dr Jonathan Moffett
            Ashmolean Museum,
            Beaumont Street, Oxford
            OX1 2PH
Contract    £200K
Systems     Molex Cat6
Installed   Dec 2008 - Oct 2009
Builder     BAM
Project     The Ashmolean Museum, dating from the 17th century, is the oldest public
            museum in the UK. Award-winning architect Rick Mather created a new
            building that has doubled the Ashmolean’s gallery space and state-of-the-art
            facilities. In November 2009, the £61M redevelopment opened to the public.
            Able Data installed a structured cabling system, consisting of nearly a thousand
            outlets, spread over 6 floors of the new building extension.
            Each of the 13 remote patch cabinet locations had a fibre & copper backbone
            linking to the Basement computer room. As well as the provision of the
            computer cabinets at each location Able Data supplied & installed an APC UPS
            & 3Comm Switch. The biggest challenge was the complexity and range of
            cable routes. Whilst some outlets are located in low floor boxes, others for high
            gallery points (overhead projectors etc) are at more than eight metres high.
            Another challenge was fitting cabling around a complex building program;
            many outlets could not be terminated or tested until after the exhibition cabinets
            had been installed.
Pictures




                                                                     Able Data Installations Plc
                                                                            Tel: 01442 219580
                                                                          www.abledata.co.uk
Able Data – Reference Sites

Ashburton Court
Summary       Hampshire County Council Office HQ & Data Centre
Contact       Bob Davis, Senior ICT Consultant
              Mace
              Atelier House, 64 Pratt Street
              London
              NW1 0LF
              Tel: 020 7554 8000

Location      Winchester City Centre
Contract      £850K
Systems       Nexans Lanmark-6 10G F/UTP, Nexans LANsense System, Excel Cat6
Installed     Sep 2007 – May 2009
Consultant    Mace
Contractor    BAM
Project     In 2009 Hamshire County Council (HCC) completed a major office
Description refurbishment of its HQ building at Ashburton Court. The conversion of
            this 1960’s council office building to a naturally ventilated, low energy
            facility included a heat recovery from the internal Data Centre as a source
            of heat to service the office areas.
            Able Data were contracted by BAM to install a data cabling system
            providing 4,000 Cat6 outlets to the new offices and meeting rooms. Able
            Data also won the contract to build the new Data Centre facility, completed
            over eight weeks in Spring 2009. With 70 Prism server cabinets, 5,000
            copper links and 2,000 fibre links, this new data centre has become HCC’s
            primary Data Centre. The facility incorporates leading edge Data Centre
            technologies to maximise space and power usage and to enable remote
            operation. Functionality installed by Able Data included a Nexans 10G
            Ca6a copper cabling system, a Nexans Intelligent Infrastructure
            Management (IIM) system, Nexans remotely control Intelligent PDU’s and
            a Data Centre wide Austin Hughes KVM system.
Pictures




                                                               Able Data Installations Plc
                                                                      Tel: 01442 219580
                                                                    www.abledata.co.uk
Able Data – Reference Sites


APAX
Summary       Molex Cat 6 – OM3
Contact       Stephen Grabiner
              020 7872 6300

Location      33 Jermyn Street
              London
              SW1Y 6DN

Contract      130k
Systems       Molex
Start &       6 Month Project
Finish
Consultant    CBI
Contractor    ISG
Project
Description   Able Data Installations installed a Molex Cat 6 & OM3 Fibre Optic
              cabling systems over 6 floors of the new London headquarters
              Building of Apax and Partners in Jermym Street.
              Apax Partners is a global private equity group that invests in five
              industry sectors. Founded more than 30 years ago, the firm uses its
              sector expertise, deep local presence and broad global platform to
              create value for its stakeholders. The history of Apax is Interwoven
              with the development of the private equity assest class on both sides
              of the Atlantic.

Pictures




                                                                 Able Data Installations Plc
                                                                        Tel: 01442 219580
                                                                      www.abledata.co.uk

Weitere ähnliche Inhalte

Andere mochten auch

презентация антигламурное шоу
презентация антигламурное шоупрезентация антигламурное шоу
презентация антигламурное шоуviktoregorov
 
The value of PR
The value of PR The value of PR
The value of PR Andre Davis
 
Persuasion and ethics
Persuasion and ethics Persuasion and ethics
Persuasion and ethics Andre Davis
 

Andere mochten auch (6)

презентация антигламурное шоу
презентация антигламурное шоупрезентация антигламурное шоу
презентация антигламурное шоу
 
Ockham
OckhamOckham
Ockham
 
Tried & True Moisture Performance
Tried & True Moisture PerformanceTried & True Moisture Performance
Tried & True Moisture Performance
 
Drawings Of Facial Expressions
Drawings Of Facial ExpressionsDrawings Of Facial Expressions
Drawings Of Facial Expressions
 
The value of PR
The value of PR The value of PR
The value of PR
 
Persuasion and ethics
Persuasion and ethics Persuasion and ethics
Persuasion and ethics
 

Ähnlich wie Consolidated

Shaun Barnes Data Cabling Reference Sites
Shaun Barnes Data Cabling Reference SitesShaun Barnes Data Cabling Reference Sites
Shaun Barnes Data Cabling Reference Sitesshaunbarnes
 
Exceltek Broadcasting Services
Exceltek Broadcasting ServicesExceltek Broadcasting Services
Exceltek Broadcasting ServicesDavid Neale
 
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQPRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQLee Stokes
 
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQPRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQGeoff Byrne
 
Cat 6a - Dublin City University
Cat 6a - Dublin City UniversityCat 6a - Dublin City University
Cat 6a - Dublin City UniversityLee Stokes
 
Robin Adcock Resume6
Robin Adcock Resume6Robin Adcock Resume6
Robin Adcock Resume6Robin Adcock
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Optus Business Centre Group
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Rentaphonesystem.com.au
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Optus Business Centre Group
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Rentaphonesystem.com.au
 

Ähnlich wie Consolidated (20)

Abbeygate
AbbeygateAbbeygate
Abbeygate
 
Shaun Barnes Data Cabling Reference Sites
Shaun Barnes Data Cabling Reference SitesShaun Barnes Data Cabling Reference Sites
Shaun Barnes Data Cabling Reference Sites
 
accv1
accv1accv1
accv1
 
Exceltek Broadcasting Services
Exceltek Broadcasting ServicesExceltek Broadcasting Services
Exceltek Broadcasting Services
 
Kemrock Case Study
Kemrock Case StudyKemrock Case Study
Kemrock Case Study
 
John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016
 
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQPRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
 
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQPRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
PRECISION CABLES PROVIDES PERFECT PRODUCTS FOR UPS HQ
 
Resume
ResumeResume
Resume
 
IP1 Project Overview
IP1 Project OverviewIP1 Project Overview
IP1 Project Overview
 
Cat 6a - Dublin City University
Cat 6a - Dublin City UniversityCat 6a - Dublin City University
Cat 6a - Dublin City University
 
BrianTechResume
BrianTechResumeBrianTechResume
BrianTechResume
 
ALABI Kola Samuel
ALABI Kola SamuelALABI Kola Samuel
ALABI Kola Samuel
 
Robin Adcock Resume6
Robin Adcock Resume6Robin Adcock Resume6
Robin Adcock Resume6
 
Isaac Williams CV
Isaac Williams CVIsaac Williams CV
Isaac Williams CV
 
Robert-Logan_CV
Robert-Logan_CVRobert-Logan_CV
Robert-Logan_CV
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
 
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
Ip and vo ip phone system benefits nec sv9100 phone system_nec univerge sv9100
 

Consolidated

  • 1. Able Data – Reference Sites Vizion Apartments, Milton Keynes Summary TV & Satellite System for 405 Apartments Contact Rob Barker, Electrical Services, BAM Construction. 01727 894 203 Centrum Business Park, Building 4, St Albans, Herts. AL1 2RD Location Part of the Abbey gate Sainsbury’s development, Milton Keynes Contract £350K Systems Fracarro IRS Equipment Timescales March 2007 - November 2008 Contractor BAM Project Able Data were contracted to build an IRS system for the new Abbey gate Description Sainsbury’s development in Milton Keynes. Over the large development, it was decided to build a separate aerial rig and head end on each main block, subdividing the project into smaller independent units. Each flat was provided with its own TV and Data patch cabinet to allow flexible re-configuration of the services. One of the challenges was to build temporary TV/Sat head ends to accommodate new tenants moving whilst the main development continued. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 2. Able Data – Reference Sites West Herts College Summary Cabling of new college campus Contact Rob Barker BAM Construction Centrium Business Park, Building 4 St Albans, Herts. AL1 2RD Tel: 020 8879 1188 Location Watford Contract £500K Systems SYSTIMAX GigaSPEED X10D, Prism Cabinets Start & Finish Jan 2010 – April 2010 Contractor BAM Project West Herts College has embarked on a long-term property strategy to Description modernise its facilities and transform campus life. As part of their plans they have built a new flagship Watford campus offering state-of- the-art facilities in an inspiring environment. Able Data were contracted to install a high performance campus wide structured cabling system. Over three months Able Data installed 7,000 SYSTIMAX Cat6a UTP outlets. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 3. Able Data – Reference Sites Veolia Three Valleys Water Summary Cabling of building Contact Bob Davis, Senior ICT Consultant Mace Atelier House, 64 Pratt Street London NW1 0LF Tel: 020 7554 8000 Location Hatfield Business Park, Hatfield Contract £200K Systems Molex PowerCat 6 UTP Cat6 Start & Finish Nov 2008 – Jan 2009 Consultant Mace Contractor Como Project Veolia Water (formally Three Valleys Water) consolidated their Description offices into the new HUB building in Hatfield, a building to house 750 office staff. Able Data were contracted by Como to install a 3,000 outlet Cat6 data cabling system. Run over four floors, outlets were terminated in a grid of 8-way consolidation points installed under the false floor. Desk outlets were connected to the consolidation points through solid patch lead connections. The project was completed over a period of two months. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 4. Able Data – Reference Sites South Thames College Summary Cat6 Cable installation in to a refurbished part of the College Development. Contact Rob Barker BAM Construction Centrium Business Park, Building 4 St Albans, Herts. AL1 2RD Tel: 020 8879 1188 Location Wandsworth London Contract £85K Systems Brand-Rex Cat6 & OM3 Fibre Backbone Installed Start & April 2010 to Oct 2010 Finish Consultant None Main BAM Contractor Project Able Data installed 1200 Brand-Rex Cat6 Outlets and 288 Fibre Links. Description This was an extremely difficult installation due to the Building Restraints and the age of the Building An important scheduling consideration was the requirement to fit around the School Terms. Picture Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 5. Able Data – Reference Sites Misys Summary Cabling & moves into new headquarters building Contact Phil Davies, IT Manager. Misys One Kingdom Street, Paddington. W2 6BL Tel: 020 8879 1188 Location Paddington, London Contract £300K Systems Brand-Rex Cat6 & OM3, Cooper B-Line Cabinets Start & Finish Feb – Aug 2008 Consultant April Management Contractor Mastercraft Design Project Misys were consolidating four regional offices into one new Description headquarters building. The new offices required 3,000 Brand Rex LSOH Cat6 outlets installed over three floors, each floor being cabled from two patch rooms. Able Data connected the patch rooms through diversely routed OM3 fibre and voice backbones. In the main computer room, Able Data installed Cooper B-Line cabinets, fitted with the Unite Hawki-2 intelligent power monitor and control products. Able Data also managed the movement of 500 users into the new building. Scheduled over five weekends, this included providing an asset register of all of their computer equipment and a full moves service into the new offices, including connection and test of all of the desktop equipment. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 6. Able Data – Reference Sites HBG – Crawley Schools Summary Installation of Data/Voice & TV cabling in three Schools. Contact Mr Steve Rooke HBG Construction Merit House, Edgware Road, Colindale, NW9 5AF. Tel: 020 8200 7070 Location Crawley, West Sussex Contract £300K Systems Data: 6,000 Brand-Rex Cat5e Outlets plus OM3 fibre. TV: 1,000 TV outlets. Fracarro K-series head end through Webro CT167/CT100 cables. Start & Finish Feb 2004 – Aug 2005 Consultant N/A Contractor HBG Construction Project HBG have built three new secondary schools in West Sussex, Oriel, Description Ifield and Thomas Bennett. As part of this project, they contracted Able Data to design and install a data cabling and TV distribution system. The data cabling systems are based on the Brand Rex Millenium Cat5e system. In each school, Able Data installed 2,000 RJ45 outlets in class rooms, staff rooms and other locations. These outlets were run back to a number of local patch cabinets, which were in turn connected back to the main computer room via OM3 fibre. The TV distribution system includes 300 class room TV outlets per school. Within each school, these are fed from a single central head end, which is in turn fed from a single set of TV and radio aerials. The head end equipment includes a high quality Fracarro K-series processing system, which as well as providing high quality TV terrestrial analogue and digital channels, presents FM and DAB radio to all outlets. The school can also broadcast channels from their own video sources, such as DVD players, tapes or cameras. Picture Oriel School Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 7. Able Data – Reference Sites Fidelity Oakhill Data Centre Summary New Data Centre at the Fidelity HQ Contact John Brogan, Project Manager Fidelity International Oakhill House, 130 Tonbridge Rd Hildenborough, Kent, TN11 9DZ Tel: 01732 361 144 Location Tonbridge, Kent Contract £2.5M Systems Systimax Cat 6, LazrSPEED 300 OM3, iPatch, CPI Patch Frames Installed Jul – Oct 2009 Project Fidelity International is a world-wide leading investment provider. As Description part of their UK data centre consolidation strategy, Fidelity required a new Data Centre facility at its HQ facility at Tonbridge. Spread over two underground data halls and two office floors, the project required the installation of 30,000 Cat6 copper links and 11,000 OM3 duplex fibre links to 300 Rittal cabinets and used more than 700km of cable. All links connect to a patch field of 80 x CPI patch frames, each monitored with the iPatch Intelligent patch system. The Data Centre was cabled overhead on three levels of CPI ladder racking. One of the biggest challenges faced by Able Data was to deliver the required high quality of cabling. To work out the optimum cable routing schemes, Able Data built an offsite mock up of a row of patch frames and the associated cables. To speed up installation whilst minimising unsightly cable slack, Able Data single end pre-terminated all copper and fibre links. The entire installation was completed over a 14 week period. As well as building and configuring a 40,000 port iPatch system to manage patching and monitor network devices, Able Data implemented additional bespoke functionality tailored to Fidelity’s requirements, including auto server provisioning. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 8. Able Data – Reference Sites Fidelity Investments Summary Cabling of Fidelity’s Date Centres Contact Dexter Baird Oakhill House, 130 Tonbridge Road Hildenborough, Kent TN11 9DZ Tel: 01732 777627 Location Acton Colt Data Centre, London Global Switch 2 Data Centre, London Contract £650K (Total) Systems SYSTIMAX GigaSPEED XL Cat6 SYSTIMAX LazrSPEED OM2, OM3 Start & Jan 2003 – May 2003 Finish Nov 2005 – Dec 2005 Jul 2006 Project In three separate projects, Able Data have cabled Fidelity’s London Description based Data centres. In the first project Able Data supplied and installed thirty data cabinets and the required cabling infrastructure. The initial installation of 4,000 copper links was completed within four weeks. All RJ45 patch panels are of the Avaya Fleximax variety, where standard outlet modules are clipped into the panel. The second and third projects were similar, but on a larger scale. The third project at Global Switch involved 10,000 links, installed over a period of one month, made possible by the use of off site pre- termination, As part of the initial project, Able Installed also 1,000 10Gbit OM2 fibre links, terminated onto SC connector outlets. The later projects used LC connectors. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 9. Able Data – Reference Sites Debenhams Summary Data Cabling for new and refurbished Department Stores Contact Peter Craven, Project Manager. Bedford Road, Park Street, Taunton, Somerset, TA1 4DB Tel: 01823 364 303 Location Various retail sites including Hemel Hempstead, Thanet, Woking, Portsmouth & Slough. Contract £150K Systems SYSTIMAX PowerSUM Cat5e & Excel Cabinets Start & November 2004 (Thanet) Finish March 2005 (Portsmouth, Woking, Sough) April 2005 (Hemel Hempstead) Consultant N/A Contractor Various Project Debenhams has an ongoing program of opening new stores. In each Description they install a structured cabling system to serve the shop floor tills and pay points as well as the general offices. It is Debenhams policy to use SYSTIMAX PowerSUM cabling throughout. By the nature of shop premises, most of the cabling work is in the ceiling void, requiring the extensive use of platforms. Each store floor will normally have its own cabling cabinet. These cabinets are joined to the master cabinet via either fibre or copper interlinks, depending on the distances involved. Part of this project involved the fast track conversion of three Alders stores to Debenhams in March 2005. This involved the use of three separate cabling teams working on the different sites. Pictures Able Data Installations Plc Tel: 01442 219580 www.ablecable.co.uk
  • 10. Able Data – Reference Sites Church Commissioners Summary Installation of Data & Voice Cabling over 6 floors Contact Martyn Chadaway CBI, ‘The Gherkin’, 30 St Mary Axe, London, EC3A 8AD. Location The Corporation of Church House, Church House, Great Smith Street, London. SW1P 3AZ. Contract £180K Systems Tyco Amp Cat6 STP & Quantum Cat5e UTP Timescales September 2006 – March 2007 Consultant CBI Project The Corporation of The Church House was founded in 1888 as the Church Description of England's permanent tribute to Queen Victoria's Golden Jubilee. The Church House, a grade II listed building, is the headquarters of the Archbishops' Council and all its Boards and Councils as well as of the Church of England Pensions Board and the National Society. It is the meeting-place, twice each year, of the General Synod of the Church of England. Church House also contains a Conference Centre that provides accommodation and facilities for a vast variety of events from AGMs, conferences, dinners and receptions to exhibitions. Able Data were contracted to install 1500 outlets over 6 floors and the conference centre. The key challenge of delivering this project was the complexity of the cable routes. The building is listed and most of the original features of the conference centre, meeting & conference rooms on the Ground and Lower Ground floors could not be changed or put in any risk of being damaged. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 11. Able Data – Reference Sites Bucks New University (BNU) Summary Installation of Data & Voice Cabling over 13 Floors Contact Andy MacFarlane BAM Construction Centrium, Griffiths Way St Albans, Herts. AL1 2RD Location High Wycombe Contract £150K Systems Excel Cat6 Installed Apr 2009 – Dec 2009 Contractor BAM Project Buckinghamshire New University’s camp has undergone an extensive Description £60m programme of rebuilding in 2009. A new, high-tech learning resources centre, known as the Gateway, forms the focal point of the University’s technology-led learning experience. Able Data were contracted by BAM to install an 1,800 Excel Cat6 UTP cabling system, spread over the six patch rooms on the six floors of the new Gateway building extension. Able Data also installed an Blown Fibre (OM3) & a voice link backbone cabling infrastructure between each patch room and the main computer room on the 4th floor. Picture Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 12. Able Data – Reference Sites Ashmolean Museum Summary Cabling of Major New Building Extension Contact Dr Jonathan Moffett Ashmolean Museum, Beaumont Street, Oxford OX1 2PH Contract £200K Systems Molex Cat6 Installed Dec 2008 - Oct 2009 Builder BAM Project The Ashmolean Museum, dating from the 17th century, is the oldest public museum in the UK. Award-winning architect Rick Mather created a new building that has doubled the Ashmolean’s gallery space and state-of-the-art facilities. In November 2009, the £61M redevelopment opened to the public. Able Data installed a structured cabling system, consisting of nearly a thousand outlets, spread over 6 floors of the new building extension. Each of the 13 remote patch cabinet locations had a fibre & copper backbone linking to the Basement computer room. As well as the provision of the computer cabinets at each location Able Data supplied & installed an APC UPS & 3Comm Switch. The biggest challenge was the complexity and range of cable routes. Whilst some outlets are located in low floor boxes, others for high gallery points (overhead projectors etc) are at more than eight metres high. Another challenge was fitting cabling around a complex building program; many outlets could not be terminated or tested until after the exhibition cabinets had been installed. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 13. Able Data – Reference Sites Ashburton Court Summary Hampshire County Council Office HQ & Data Centre Contact Bob Davis, Senior ICT Consultant Mace Atelier House, 64 Pratt Street London NW1 0LF Tel: 020 7554 8000 Location Winchester City Centre Contract £850K Systems Nexans Lanmark-6 10G F/UTP, Nexans LANsense System, Excel Cat6 Installed Sep 2007 – May 2009 Consultant Mace Contractor BAM Project In 2009 Hamshire County Council (HCC) completed a major office Description refurbishment of its HQ building at Ashburton Court. The conversion of this 1960’s council office building to a naturally ventilated, low energy facility included a heat recovery from the internal Data Centre as a source of heat to service the office areas. Able Data were contracted by BAM to install a data cabling system providing 4,000 Cat6 outlets to the new offices and meeting rooms. Able Data also won the contract to build the new Data Centre facility, completed over eight weeks in Spring 2009. With 70 Prism server cabinets, 5,000 copper links and 2,000 fibre links, this new data centre has become HCC’s primary Data Centre. The facility incorporates leading edge Data Centre technologies to maximise space and power usage and to enable remote operation. Functionality installed by Able Data included a Nexans 10G Ca6a copper cabling system, a Nexans Intelligent Infrastructure Management (IIM) system, Nexans remotely control Intelligent PDU’s and a Data Centre wide Austin Hughes KVM system. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk
  • 14. Able Data – Reference Sites APAX Summary Molex Cat 6 – OM3 Contact Stephen Grabiner 020 7872 6300 Location 33 Jermyn Street London SW1Y 6DN Contract 130k Systems Molex Start & 6 Month Project Finish Consultant CBI Contractor ISG Project Description Able Data Installations installed a Molex Cat 6 & OM3 Fibre Optic cabling systems over 6 floors of the new London headquarters Building of Apax and Partners in Jermym Street. Apax Partners is a global private equity group that invests in five industry sectors. Founded more than 30 years ago, the firm uses its sector expertise, deep local presence and broad global platform to create value for its stakeholders. The history of Apax is Interwoven with the development of the private equity assest class on both sides of the Atlantic. Pictures Able Data Installations Plc Tel: 01442 219580 www.abledata.co.uk