SlideShare a Scribd company logo
1 of 48
USACE Joplin Area Tornado
Recovery Mission

Commander’s Final Report
11 September 2011




 US Army Corps of Engineers
 BUILDING STRONG®
Scope of Devastation
• On the evening of 22 May 2011, an EF5 tornado
  devastated a heavily-populated and densely-vegetated
  area in the cities of Joplin and Duquesne, Missouri
• Trail of devastation was 6 miles long and nearly 1 mile
  wide.
• Destroyed nearly 30% of Joplin (nearly 75% damaged)
   –   More than 4000 homes.
   –   More than 1000 businesses.
   –   7 schools.
   –   1 major hospital.
• Killed 160 people.
Joplin – Before
Joplin – During
Joplin – After
Joplin – After
Joplin – After
Joplin – After
Mission Statement
      The USACE Kansas City District
established a Recovery Field Office (RFO)
 to provide rapid response and recovery
  assistance to the citizens of Joplin and
Duquesne, MO through the execution of
FEMA Mission Assignments in support of
   the National Response Framework.
Mission Summary
• Debris
   – ROW/PPDR Debris Removal
   – Technical Assistance Team
• Temporary Housing
   – 346 Units w/ Storm Shelters
   – Highway interchange
• Critical Public Facilities
   – Fire Stations
   – Schools
   – Hospital
USACE Response Timeline
•   23 May at 0844: FEMA issues WARNO to USACE
•   23 May at 1508: FEMA issues verbal mission assignments for Regional Activation & Debris
•   24 May: NWK deploys NWP Debris PRT and LRH Temp Housing Planning Team to Joplin; also
    deployed Team Leaders to RRCC and JFO
•   25-26 May: NWK CDR, Deputy, EM Chief and GIS lead visit Alabama to gain lessons learned
•   25-26 May: NWK begins working SDIC contract for Joplin area
•   26 May: FEMA issues verbal mission assignment for RFO
•   27 May: FEMA issues formal mission assignment for RFO
•   27 May: RFO location identified in Joplin, MO
•   28 May: Advanced Party occupies RFO
•   29 May-30 May: Additional Key & Essential Personnel report to RFO
•   30 May: SDIC contract awarded 01 Jun: RFO receives Critical Public Facilities Planning Mission
    from FEMA
•   01 Jun: 1st truck-load of debris hauled
•   01 Jun: Received $30 Million for Debris Mission
•   03 Jun: Received $35 Million for Debris Mission
•   07 Jun: RFO receives Mission to build Temporary Fire Stations 2 & 4
•   13 Jun: RFO receives Temporary Housing Mission
•   17 Jun: RFO receives Temporary Schools Mission
USACE Response Timeline
•   17 Jun: Received $147.5 Million for Debris Mission
•   23 Jun: Contractor places first Temp Fire Station unit
•   27 Jun: RFO issues last of 8 awards for Temporary School Contracts
•   30 Jun: Pre construction meeting with the 3 Follow-on Debris Contractors
•   01 July: Temporary Housing contract awarded
•   05 July: Temporary Housing began construction
•   05 July: Removed over 1 Million cubic yards of debris
•   09 July: Follow-on Contractors begin onsite work
•   15 July: Returned $10 Million of Debris Funding
•   17 July: SDIC contractor completed operation in the EDR
•   22 July: Returned $10 Million of Debris Funding
•   1 Aug: Contract “Substantially” completed target
•   7 Aug: Completion of the EDR 90/10 cost share
•   7 Aug: Projected vegetation reduction site completed
•   8 Aug: Start 75/25 cost share (Debris Mission)
•   21 Aug: Complete 75/25 cost share (Debris Mission)
•   26 Aug: RFO Closeout
Commander’s Final Report
Debris Mission

PRT Lead – Portland/Kansas City Districts




 US Army Corps of Engineers
 BUILDING STRONG®
Debris Mission
SCOPE:
• Provided Debris PRT support personnel and
contractor resources to coordinate and
execute all necessary actions associated with
debris clearance and removal
• Completed all 90/10 work by 7 Aug; included
more than 1.45M CY of debris and 1505
Private Property Debris Removal (PPDR)
• Completed additional 75/25 debris by 21
Aug
• Debris consisted of Construction and
Demolition (C&D), Vegetative, and Regulated
Asbestos Containing Material (RACM)
• Provided Technical Assistance thru 29 Sep
CRITICAL MILESTONES:                            PROGRAM AMOUNT: $192.5M
• Tornado Event – 22 May                        • $55M Weston (Debris Removal)
• SDIC Contract Award – 30 May                  • $30M Intelligent Investments (Debris)
• First debris loaded and hauled – 1 Jun        • $30M R&R Trucking (Debris Removal)
• First ROE received from FEMA – 16 Jun         • $30M Larry Snyder & Co. (Debris Removal)
• Small Business Contract Awards – 24 Jun       • $20M Asbell Trucking (Veg Reduction)
• End of PPDR and 90/10 Cost Share – 7 Aug      • $7.4M Rostan Solutions (ADMS)
• End of extended ROW work – 21 Aug             • $13.4M Misc
Debris Mission – Sector Map
Right of Way
Debris Removal



Before




After
PPDR Debris
Removal



Before




After
PPDR Debris
Removal



Before




After
Commander’s Final Report
Temporary Housing Mission

PRT Lead – Huntington District




 US Army Corps of Engineers
 BUILDING STRONG®
Temporary Housing Mission
SCOPE
• Provide design, site development, and
construction, including installation of utilities,
for Community Group Sites as directed by
FEMA
• Two Parks concurrently constructed: Hope
Haven (152 units) and Officer Jeff Taylor
Memorial Acres (194 units)
• Pads released in phases within each site for
housing unit placement to expedite occupancy
• Provided 170 units for families with school-
age children before the first day of school

CRITICAL MILESTONES                                  PROGRAM AMOUNT: $9.4M
• PRT DEPLOYED TO JOPLIN – 13JUN11                   • Site plan and design leveraged “Hope
• PROPOSALS RECEIVED - 28JUN11                         Haven” site for future Regional Training
• CONTRACT AWARDS – 01JUL11                            Facility for Emergency Responders (Police
• CONSTRUCTION START – 5JUL11                          Chief involved)
• TURNOVER of PADS BEGINS – 22JUL11                  • Used Huntington District MATOC contractors
• COMPLETE – 31AUG11                                   for infrastructure work
Temporary Housing
Officer Jeff Taylor Memorial Acres
Temporary Housing
                Officer Jeff Taylor Memorial Acres
•   194 Community Homes
•   11 Storm Shelters
•   School Bus/ Trolley Stop
•   31 UFAS Accessible Units
Temporary Housing
Hope Haven Community Group Site
Temporary Housing
               Hope Haven Community Group Site

•   152 Community Homes
•   9 Storm Shelters
•   School Bus/ Trolley Stop
•   21 UFAS Accessible Units
Temporary Housing
 Community Development
Commander’s Final Report
Critical Public Facilities Mission

PRT Lead – New York District




 US Army Corps of Engineers
 BUILDING STRONG®
Critical Public Facilities
                                 Fire Stations 2&4
SCOPE:
• Developed Critical Public Facilities plan for
City of Joplin’s Fire Department. Included
construction of 2 temporary fire stations that
will be utilized for approximately 1 ½ years at
the existing site of the destroyed facility
• Each station has 2 vehicle bays, sleeping
quarters, storage area, workout facility, and
kitchen




CRITICAL MILESTONES:                              PROGRAM AMOUNT:
• CONTRACT AWARD DATE - 16JUN11
• START CONSTRUCTION - 20JUN11                    • First projects to be completed by USACE
• CONSTRUCTION COMPLETION- 7JUL11
Critical Public Facilities
                                          Schools
SCOPE:
• Installed modular facilities at 8 interim
  school locations for the Joplin School
  District, to include High School, Intermediate
  School, and Elementary Schools
• Modular structures included science labs,
  gymnasiums, kitchens, and cafeterias
• Storm shelters provided at all sites




CRITICAL MILESTONES                                PROGRAM AMOUNT:
• CONTRACT AWARD DATES – 20-29 JUN 11
• BENEFICIAL OCCUPANCY DATE – 12AUG11              • All schools completed and received
• SCHOOLS REOPEN – 17AUG11                           Certificates of Occupancy before scheduled
                                                     first day of school (17 Aug )
Critical Public Facilities
                            St. Johns Mercy Hospital
SCOPE
• Infrastructure Design Development and
  Construction for 1M SF temporary hospital
• Hospital and FEMA tasked USACE with the
  site design and development of
  approximately 200,000 square feet of long
  term component medical facilities
• Timeline will be dependent on project
  phasing and fabrication of modular units
• Acquisition strategy Identified for site works,
  design/build will be used. A/E will be used to
  develop RFP




CRITICAL MILESTONES                                 PROGRAM AMOUNT: Pending
• APRIL 2012- SITE WORK AND COMPONENT
  HOSPITAL TO BE COMPLETED
PROJECT               MODULAR   STORM      TENT        COMMENTS
                      UNITS     SHELTERS   STRUCTURE

FIRESTATION #2 #4     2         2          2           2 MODULAR UNITS ,
                                                       2 GARAGES, STORM SHELTERS
IRVING@WASHINGTON     7         7          N/A         7 CLASSROOMS AND KITCHEN UNIT
                                                       WITH FREEZERS, STORM SHELTERS
EARLY CHILDHOOD@      30        N/A        N/A         CLASSROOMS
McKINLEY
JOPLIN HIGH SCHOOL@   9         37         N/A         CLASSROOMS, KITCHEN UNITS
SHOPKO                                                 WITH FREEZERS, AND STORM
                                                       SHELTERS
JOPLIN HIGH SCHOOL@   17        N/A        N/A         CLASSROOMS
MEMORIAL

EMERSON@DUQUESNE      8         3          1           CLASSROOMS, GYMNASIUM,
                                                       STORM SHELTERS
DUQUESNE@DUENWEG      7         9          N/A         CLASSROOMS, STORM SHELTERS

EAST MIDDLE SCHOOL@   19        1          1           CLASSROOMS, GYMNASIUM,
CROSSROADS                                             LOCKER ROOM, KITCHEN UNIT
                                                       WITH FREEZERS, AND STORM
                                                       SHELTERS
FRANKLIN TECH         N/A       4          N/A         STORM SHELTERS
Joplin Schools

Jun 06, 2011




August 1, 2011
Joplin Fire
Department
Jun 06, 2011




July 10, 2011
St. John’s Mercy
Hospital
100
                                                                                                                                                                                                 105




                                                                        10
                                                                                               15
                                                                                                          20
                                                                                                               25
                                                                                                                     30
                                                                                                                          35
                                                                                                                               40
                                                                                                                                    45
                                                                                                                                         50
                                                                                                                                              55
                                                                                                                                                   60
                                                                                                                                                        65
                                                                                                                                                             70
                                                                                                                                                                  75
                                                                                                                                                                       80
                                                                                                                                                                            85
                                                                                                                                                                                 90
                                                                                                                                                                                      95




                                   5
                       0
      New Orleans
       SW Division
             Buffalo
 S Pacific Division
        Rock Island
           Nashville
          Baltimore
         GL/OR Div
    Pac Ocean Div
         Huntsville
           Honolulu
             St Paul
   Miss Valley Div
             Omaha
       Jacksonville
             Detroit




                           1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2
          Louisville
    N Atlantic Div
         Pittsburgh
                 HQ
         Galveston




                                                             3 3 3 3 3
             Mobile
              ACE-IT
            Chicago
             Seattle
       Walla Walla
              Alaska                                                   4 4 4 5 5 5
          Vicksburg
     Albuquerque
      NW Division
                                                                                                                                                                                                          Total Employee Deployed = 439




         Little Rock
            Norfolk
                                                                                                                                                                                                       USACE District/Division Representation




                                                                                   6 6 6 6 7




     New England
           Logistics
      Philadelphia
       Los Angeles
                                                                                      9 10 10 10




            St Louis
     San Francisco
                                                                                               12 13




        Huntington
                                                                                                     14




        Fort Worth
                                                                                                     16




               Tulsa
                                                                                                               21




          New York
                                                                                                                23




       Sacramento
                                                                                                                                    41




           Portland
                                                                                                                                                             66




RAO (Annuitants)
                                                                                                                                                                                           98




        Kansas City
Mission Accomplished
       One Team
Highlights
• Structure
   – Responsiveness: ESF#3, District, PRTs and Supporting Districts
      mobilized rapidly and established key relationships
   – External Relationships: Strategic Communications with
      FEMA, State, and Local stakeholders aligned goals and effort
   – Internal Relationships: ESF/RFO matrix alignment (needs to occur
      earlier in mission)
• Process
   – Project Management Approach: Completed of ALL missions on
      schedule
   – Safety: Command focus resulted in only 1 reportable accident despite
      aggressive optempo and record heat
• Tools
   – Forecasting: Resource-loaded schedules allowed leaders to manage
      resources effectively and efficiently
   – PRB: Weekly boards allowed PRTs to maintain project focus and
      stakeholder satisfaction
Lessons Learned
• Structure
   – Matrix Alignment: Establish clear lines of communication and
      responsibilities; focus on ESF/RFO integration along PDT lines
   – Project Management: Provide PMP and PDT training for MM/AO; run
      RFO like a PMO
   – Advance Party: Mobilize most experienced ESF/RFO leaders and SMEs
      on ground early to establish unity of effort
• Process
   – Contracting: Develop ACI-type MATOCs that support mission (key
      milestones, incentives, Stafford Act, etc)
   – Operations: Create a PMBP-type approach to RFO operations (v. SOPs)
• Tools
   – Project Controls: Mobilize robust PC team to support PRTs
   – Information Management: Standardize PRT reporting procedures and
      tools that allow RFO leadership to forecast and analyze critical
      information
   – Dashboard: Provide common operating picture, while standardizing and
      synchronizing information analysis and reporting; serves as training tool
Structure
Matrix Alignment
Process
PMBP Approach
FEMA                Tools
                                                         RFO Dashboard
                                                      RFO Dashboard
    Home                Event          PRT            Executive   Stakeholders    Training                  ESF3                  Links


     Mission
   Assignments                                                                                      Contract Funds
                                      Schedule
     Resources                                                                                        Obligated
      Budget                                                                                                     $0   $100,000,000 $200,000,000

     Personnel                                                                                  Debris SDIC
                                                                                          Debris Follow-On
Public Affairs Office
                                                                                       Temporary Housing
   Social Media                                                                     Critical Public Facilities

     Inquiries                                                                                          Total


   Congressional

       Local              250
                                              RFO Personnel
 Lessons Learned          200                                       Reachback
                                                                    Personnel
                          150
                                                                    Personnel @
                          100                                       RFO

                           50                                       TOTAL

                            0
                                 CURRENT      REQ         REQ
                                STRENGTH     31 JUL      15 AUG
FEMA Executive            Dashboard
  Home             Event   PRT   Executive   Stakeholders   Training   ESF3   Links

Executive
Executive Briefs
   OPSUM
    SITREP
     PRB
     MUB
  Resource
Management
RFO Personnel
     SOPs
  RFO SOPs
 After Action
   Reviews
FEMA             RFO Project Review Board
                                                                    Debris



                   FEMA Approved Scope

Base:
• Debris Removal per ESF-3 Direct Federal Assistance Mission
   • ROW – Joplin, Duquesne, & Jasper
   • PPDR – EDR Zone Only
   • Estimated volume of 1.87 million cubic yards (MCY) and 1,400
   private properties


• Changes:
   • Pending New Mission: Private Property Demolition – Scope to be
   determined.
FEMA                 RFO Project Review Board
                                                                        Debris

                         FEMA Approved Cost
Base:                                    SDIC                $57M
• Programmed Amount:       ($180M)       DE-OB RFO LABOR     -$2M
     • ($180M) approved                  SDIC AWARD          -$48.06M
     • ($212.5M) funded
                                         MOD CAT3 ACM/L.F.   -$3M
     • ($211.6M) obligated               STAFF
     • ($0.9M) RFO available
                                         NWO AVAILABLE:      $3.94M
     • ($1.15M/day) burn rate
           • RFO & Contracts             FOLLOW-ON           $146.4M
                                         DEBRIS REM x3       -$90M
Changes:                                 VEG DEBRIS          -$20M
                                         ADMS                -$7.4M
• Revising Mission funding               RFO AVAILABLE:      $30M
requirements based on revised debris     OTHER               $8.2M
volumes
• De-obligated $30M from F-O Debris      ACM SEPARATION      -$1.2M
Removal Contracts                        S&R SUPPORT         -$0.5M
                                         LABOR/MISC          -$6.5M
                                         RFO AVAILABLE:      **
Debris
                   RFO Project Review Board
         Schedule Progress
         FEMA
                                      Debris


         FEMA Approved Schedule
FEMA
       Debris Project Review Board
         RFO
                             Debris
FEMA               Debris PRT
  Home              Event   PRT    Executive    Stakeholders        Training            ESF3               Links

Debris PRT                                               160                                           $10,000,000
Project Schedules                                        140                                           $9,000,000

  Real Estate                                                                                          $8,000,000
                                                         120
                                                                                                       $7,000,000
    Reports                                              100                                           $6,000,000
      PRB
                                                          80                                           $5,000,000
    Forecast                                                                                           $4,000,000
                                                          60
     ROW                                                                                               $3,000,000
                                                          40
  ROE/PPDR                                                                                             $2,000,000
                                                          20                                           $1,000,000
       EEI
       GIS                                                 0                                           $0
                                                           12-Jul     12-Aug   12-Sep    12-Oct   12-Nov
     ROW
      ROE
   Resource
 Management
   Personnel
   Contracts
      SOPs
Debris PRT SOPs
  FEMA SOPs
    Training
FEMA                       RFO SOPs
  Home                Event             PRT          Executive       Stakeholders       Training         ESF3                   Links

     SOPs
     Debris                   Program/Project           Program/Project             Program/Project        Program/Project
                                 Initiation                 Planning                   Execution              Closeout
Critical Facilities
 Temp Housing                   Debris Removal            Debris Removal
                                                                                     RFO Briefing SOP       RFO Closeout SOP
                                   Doctrine                    SOP

                               Critical Facilities       Critical Facilities                                    Debris Removal
                                                                                     Project Execution
                                   Doctrine                     SOP                                                Closeout
                                                                                        and Control
                                 Temporary                  Temporary
                                                                                         Change                 Critical Facilities
                               Housing Doctrine            Housing SOP
                                                                                       Management                   Closeout
                                                         Site Assessment
                                                                                         Quality              Temporary
                               Work Acceptance                 SOP
                                                                                       Management           Housing Closeout

                                                         Project Schedule                Records
                               Project Initiation                                                                   Lessons
                                                          Development                  Management
                                                                                                                 Learned/AARs
                                    Team                Resource Estimate
                                Establishment             Development

                                  Acquisition
                                   Strategy
FEMA               RFO SOPs
 Home           Event   PRT    Executive    Stakeholders   Training   ESF3   Links

EXECUTIVE                                  RFO Matrix
 RFO Matrix

RFO Org Chart
  RFO Duty
 Descriptions

More Related Content

What's hot

Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationFairfax County
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
 
9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration ProjectFairfax County
 
Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016Fairfax County
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Fairfax County
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionFairfax County
 
Pohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration ProjectPohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration ProjectFairfax County
 
Retrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High SchoolRetrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High SchoolFairfax County
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Fairfax County
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Fairfax County
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
 
Tchefuncte river eco-park_shorline_project_corps
Tchefuncte river eco-park_shorline_project_corpsTchefuncte river eco-park_shorline_project_corps
Tchefuncte river eco-park_shorline_project_corpsTRFoundation
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerFairfax County
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFairfax County
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern WorksCrosstown TO
 
Hunter Mill District Community Outreach Meeting
Hunter Mill District Community Outreach MeetingHunter Mill District Community Outreach Meeting
Hunter Mill District Community Outreach MeetingFairfax County
 
Original Mount Vernon HS Status Update April 2017
Original Mount Vernon HS Status Update April 2017Original Mount Vernon HS Status Update April 2017
Original Mount Vernon HS Status Update April 2017Fairfax County
 
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Fairfax County
 

What's hot (20)

Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream Restoration
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
 
9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project9499 Beach Mill Road Channel Restoration Project
9499 Beach Mill Road Channel Restoration Project
 
Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016Contractor Awareness Training Above Ground Facilities Part 1 2016
Contractor Awareness Training Above Ground Facilities Part 1 2016
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride Expansion
 
Pohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration ProjectPohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration Project
 
Short termim workplan_20100602_part1
Short termim workplan_20100602_part1Short termim workplan_20100602_part1
Short termim workplan_20100602_part1
 
Retrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High SchoolRetrofit Facility DP0625 West Potomac High School
Retrofit Facility DP0625 West Potomac High School
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
 
Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)Leigh Meadow & Towlston Basin (0584DP/0103DP)
Leigh Meadow & Towlston Basin (0584DP/0103DP)
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
 
Tchefuncte river eco-park_shorline_project_corps
Tchefuncte river eco-park_shorline_project_corpsTchefuncte river eco-park_shorline_project_corps
Tchefuncte river eco-park_shorline_project_corps
 
Old Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity SewerOld Keene Mill Emergency Gravity Sewer
Old Keene Mill Emergency Gravity Sewer
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream Restoration
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
Hunter Mill District Community Outreach Meeting
Hunter Mill District Community Outreach MeetingHunter Mill District Community Outreach Meeting
Hunter Mill District Community Outreach Meeting
 
Original Mount Vernon HS Status Update April 2017
Original Mount Vernon HS Status Update April 2017Original Mount Vernon HS Status Update April 2017
Original Mount Vernon HS Status Update April 2017
 
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
Mount Vernon Memorial Highway Trail Public Information Meeting: March 14, 2018
 

Similar to Joplin Rfo.Commanders Final Report.20 Sep 11

Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationFairfax County
 
City council presentation 05.14.12 revised
City council presentation 05.14.12 revisedCity council presentation 05.14.12 revised
City council presentation 05.14.12 revisedcityofevanston
 
Alabama Governor's Conference: Colorado Floods
Alabama Governor's Conference: Colorado FloodsAlabama Governor's Conference: Colorado Floods
Alabama Governor's Conference: Colorado FloodsTrost, Micki
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmKelseyMusich
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018Crosstown TO
 
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...GrowSmart Maine
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main ProjectFairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationFairfax County
 
1979 Mission | Mission Dolores Neighborhood Association (3-11-15)
1979 Mission | Mission Dolores Neighborhood Association (3-11-15) 1979 Mission | Mission Dolores Neighborhood Association (3-11-15)
1979 Mission | Mission Dolores Neighborhood Association (3-11-15) 1979mission
 
Bancroft Elementary School Community Meeting (January 12, 2015)
Bancroft Elementary School Community Meeting (January 12, 2015)Bancroft Elementary School Community Meeting (January 12, 2015)
Bancroft Elementary School Community Meeting (January 12, 2015)DC Department of General Services
 
Annual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDOAnnual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDOCity of College Station
 
Community Meeting – Construction Update Presentation October 21, 2015
Community Meeting – Construction Update Presentation October 21, 2015Community Meeting – Construction Update Presentation October 21, 2015
Community Meeting – Construction Update Presentation October 21, 2015DerekC1990
 
Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013Island Health
 
Community presentation-comox-valley-oct232013
Community presentation-comox-valley-oct232013Community presentation-comox-valley-oct232013
Community presentation-comox-valley-oct232013Island Health
 
Campbell River Community Information Meeting presentation Sept. 9, 2014
Campbell River Community Information Meeting presentation Sept. 9, 2014Campbell River Community Information Meeting presentation Sept. 9, 2014
Campbell River Community Information Meeting presentation Sept. 9, 2014Island Health
 
Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013StateCollegePA
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Community Presentation - January 18, 2017
Community Presentation - January 18, 2017Community Presentation - January 18, 2017
Community Presentation - January 18, 2017DerekC1990
 
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...The 2010 and 2011 canterbury earthquakes and organisational learning at the u...
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...University of Limerick
 

Similar to Joplin Rfo.Commanders Final Report.20 Sep 11 (20)

Crook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream RestorationCrook at Mantua Elementary School Stream Restoration
Crook at Mantua Elementary School Stream Restoration
 
City council presentation 05.14.12 revised
City council presentation 05.14.12 revisedCity council presentation 05.14.12 revised
City council presentation 05.14.12 revised
 
Alabama Governor's Conference: Colorado Floods
Alabama Governor's Conference: Colorado FloodsAlabama Governor's Conference: Colorado Floods
Alabama Governor's Conference: Colorado Floods
 
A Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.KmA Regulatory Update Of Stormwater Requirements.Km
A Regulatory Update Of Stormwater Requirements.Km
 
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
 
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...
Rich Roedner - Community Land Use: Towns Take on the Challenge - Vernal Pool ...
 
Powerpoint - Langley School Pump Station and Force Main Project
Powerpoint  -  Langley School Pump Station and Force Main ProjectPowerpoint  -  Langley School Pump Station and Force Main Project
Powerpoint - Langley School Pump Station and Force Main Project
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014Stream rehabilitation seminar june 11 2014
Stream rehabilitation seminar june 11 2014
 
1979 Mission | Mission Dolores Neighborhood Association (3-11-15)
1979 Mission | Mission Dolores Neighborhood Association (3-11-15) 1979 Mission | Mission Dolores Neighborhood Association (3-11-15)
1979 Mission | Mission Dolores Neighborhood Association (3-11-15)
 
Bancroft Elementary School Community Meeting (January 12, 2015)
Bancroft Elementary School Community Meeting (January 12, 2015)Bancroft Elementary School Community Meeting (January 12, 2015)
Bancroft Elementary School Community Meeting (January 12, 2015)
 
Annual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDOAnnual Review of Comprehensive Plan and UDO
Annual Review of Comprehensive Plan and UDO
 
Community Meeting – Construction Update Presentation October 21, 2015
Community Meeting – Construction Update Presentation October 21, 2015Community Meeting – Construction Update Presentation October 21, 2015
Community Meeting – Construction Update Presentation October 21, 2015
 
Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013Comox Valley Community Meeting October 23, 2013
Comox Valley Community Meeting October 23, 2013
 
Community presentation-comox-valley-oct232013
Community presentation-comox-valley-oct232013Community presentation-comox-valley-oct232013
Community presentation-comox-valley-oct232013
 
Campbell River Community Information Meeting presentation Sept. 9, 2014
Campbell River Community Information Meeting presentation Sept. 9, 2014Campbell River Community Information Meeting presentation Sept. 9, 2014
Campbell River Community Information Meeting presentation Sept. 9, 2014
 
Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013Capital Improvement Projects Update 2013
Capital Improvement Projects Update 2013
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Community Presentation - January 18, 2017
Community Presentation - January 18, 2017Community Presentation - January 18, 2017
Community Presentation - January 18, 2017
 
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...The 2010 and 2011 canterbury earthquakes and organisational learning at the u...
The 2010 and 2011 canterbury earthquakes and organisational learning at the u...
 

Joplin Rfo.Commanders Final Report.20 Sep 11

  • 1. USACE Joplin Area Tornado Recovery Mission Commander’s Final Report 11 September 2011 US Army Corps of Engineers BUILDING STRONG®
  • 2. Scope of Devastation • On the evening of 22 May 2011, an EF5 tornado devastated a heavily-populated and densely-vegetated area in the cities of Joplin and Duquesne, Missouri • Trail of devastation was 6 miles long and nearly 1 mile wide. • Destroyed nearly 30% of Joplin (nearly 75% damaged) – More than 4000 homes. – More than 1000 businesses. – 7 schools. – 1 major hospital. • Killed 160 people.
  • 9. Mission Statement The USACE Kansas City District established a Recovery Field Office (RFO) to provide rapid response and recovery assistance to the citizens of Joplin and Duquesne, MO through the execution of FEMA Mission Assignments in support of the National Response Framework.
  • 10. Mission Summary • Debris – ROW/PPDR Debris Removal – Technical Assistance Team • Temporary Housing – 346 Units w/ Storm Shelters – Highway interchange • Critical Public Facilities – Fire Stations – Schools – Hospital
  • 11. USACE Response Timeline • 23 May at 0844: FEMA issues WARNO to USACE • 23 May at 1508: FEMA issues verbal mission assignments for Regional Activation & Debris • 24 May: NWK deploys NWP Debris PRT and LRH Temp Housing Planning Team to Joplin; also deployed Team Leaders to RRCC and JFO • 25-26 May: NWK CDR, Deputy, EM Chief and GIS lead visit Alabama to gain lessons learned • 25-26 May: NWK begins working SDIC contract for Joplin area • 26 May: FEMA issues verbal mission assignment for RFO • 27 May: FEMA issues formal mission assignment for RFO • 27 May: RFO location identified in Joplin, MO • 28 May: Advanced Party occupies RFO • 29 May-30 May: Additional Key & Essential Personnel report to RFO • 30 May: SDIC contract awarded 01 Jun: RFO receives Critical Public Facilities Planning Mission from FEMA • 01 Jun: 1st truck-load of debris hauled • 01 Jun: Received $30 Million for Debris Mission • 03 Jun: Received $35 Million for Debris Mission • 07 Jun: RFO receives Mission to build Temporary Fire Stations 2 & 4 • 13 Jun: RFO receives Temporary Housing Mission • 17 Jun: RFO receives Temporary Schools Mission
  • 12. USACE Response Timeline • 17 Jun: Received $147.5 Million for Debris Mission • 23 Jun: Contractor places first Temp Fire Station unit • 27 Jun: RFO issues last of 8 awards for Temporary School Contracts • 30 Jun: Pre construction meeting with the 3 Follow-on Debris Contractors • 01 July: Temporary Housing contract awarded • 05 July: Temporary Housing began construction • 05 July: Removed over 1 Million cubic yards of debris • 09 July: Follow-on Contractors begin onsite work • 15 July: Returned $10 Million of Debris Funding • 17 July: SDIC contractor completed operation in the EDR • 22 July: Returned $10 Million of Debris Funding • 1 Aug: Contract “Substantially” completed target • 7 Aug: Completion of the EDR 90/10 cost share • 7 Aug: Projected vegetation reduction site completed • 8 Aug: Start 75/25 cost share (Debris Mission) • 21 Aug: Complete 75/25 cost share (Debris Mission) • 26 Aug: RFO Closeout
  • 13. Commander’s Final Report Debris Mission PRT Lead – Portland/Kansas City Districts US Army Corps of Engineers BUILDING STRONG®
  • 14. Debris Mission SCOPE: • Provided Debris PRT support personnel and contractor resources to coordinate and execute all necessary actions associated with debris clearance and removal • Completed all 90/10 work by 7 Aug; included more than 1.45M CY of debris and 1505 Private Property Debris Removal (PPDR) • Completed additional 75/25 debris by 21 Aug • Debris consisted of Construction and Demolition (C&D), Vegetative, and Regulated Asbestos Containing Material (RACM) • Provided Technical Assistance thru 29 Sep CRITICAL MILESTONES: PROGRAM AMOUNT: $192.5M • Tornado Event – 22 May • $55M Weston (Debris Removal) • SDIC Contract Award – 30 May • $30M Intelligent Investments (Debris) • First debris loaded and hauled – 1 Jun • $30M R&R Trucking (Debris Removal) • First ROE received from FEMA – 16 Jun • $30M Larry Snyder & Co. (Debris Removal) • Small Business Contract Awards – 24 Jun • $20M Asbell Trucking (Veg Reduction) • End of PPDR and 90/10 Cost Share – 7 Aug • $7.4M Rostan Solutions (ADMS) • End of extended ROW work – 21 Aug • $13.4M Misc
  • 15. Debris Mission – Sector Map
  • 16. Right of Way Debris Removal Before After
  • 19. Commander’s Final Report Temporary Housing Mission PRT Lead – Huntington District US Army Corps of Engineers BUILDING STRONG®
  • 20. Temporary Housing Mission SCOPE • Provide design, site development, and construction, including installation of utilities, for Community Group Sites as directed by FEMA • Two Parks concurrently constructed: Hope Haven (152 units) and Officer Jeff Taylor Memorial Acres (194 units) • Pads released in phases within each site for housing unit placement to expedite occupancy • Provided 170 units for families with school- age children before the first day of school CRITICAL MILESTONES PROGRAM AMOUNT: $9.4M • PRT DEPLOYED TO JOPLIN – 13JUN11 • Site plan and design leveraged “Hope • PROPOSALS RECEIVED - 28JUN11 Haven” site for future Regional Training • CONTRACT AWARDS – 01JUL11 Facility for Emergency Responders (Police • CONSTRUCTION START – 5JUL11 Chief involved) • TURNOVER of PADS BEGINS – 22JUL11 • Used Huntington District MATOC contractors • COMPLETE – 31AUG11 for infrastructure work
  • 21. Temporary Housing Officer Jeff Taylor Memorial Acres
  • 22. Temporary Housing Officer Jeff Taylor Memorial Acres • 194 Community Homes • 11 Storm Shelters • School Bus/ Trolley Stop • 31 UFAS Accessible Units
  • 23. Temporary Housing Hope Haven Community Group Site
  • 24. Temporary Housing Hope Haven Community Group Site • 152 Community Homes • 9 Storm Shelters • School Bus/ Trolley Stop • 21 UFAS Accessible Units
  • 26. Commander’s Final Report Critical Public Facilities Mission PRT Lead – New York District US Army Corps of Engineers BUILDING STRONG®
  • 27. Critical Public Facilities Fire Stations 2&4 SCOPE: • Developed Critical Public Facilities plan for City of Joplin’s Fire Department. Included construction of 2 temporary fire stations that will be utilized for approximately 1 ½ years at the existing site of the destroyed facility • Each station has 2 vehicle bays, sleeping quarters, storage area, workout facility, and kitchen CRITICAL MILESTONES: PROGRAM AMOUNT: • CONTRACT AWARD DATE - 16JUN11 • START CONSTRUCTION - 20JUN11 • First projects to be completed by USACE • CONSTRUCTION COMPLETION- 7JUL11
  • 28. Critical Public Facilities Schools SCOPE: • Installed modular facilities at 8 interim school locations for the Joplin School District, to include High School, Intermediate School, and Elementary Schools • Modular structures included science labs, gymnasiums, kitchens, and cafeterias • Storm shelters provided at all sites CRITICAL MILESTONES PROGRAM AMOUNT: • CONTRACT AWARD DATES – 20-29 JUN 11 • BENEFICIAL OCCUPANCY DATE – 12AUG11 • All schools completed and received • SCHOOLS REOPEN – 17AUG11 Certificates of Occupancy before scheduled first day of school (17 Aug )
  • 29. Critical Public Facilities St. Johns Mercy Hospital SCOPE • Infrastructure Design Development and Construction for 1M SF temporary hospital • Hospital and FEMA tasked USACE with the site design and development of approximately 200,000 square feet of long term component medical facilities • Timeline will be dependent on project phasing and fabrication of modular units • Acquisition strategy Identified for site works, design/build will be used. A/E will be used to develop RFP CRITICAL MILESTONES PROGRAM AMOUNT: Pending • APRIL 2012- SITE WORK AND COMPONENT HOSPITAL TO BE COMPLETED
  • 30. PROJECT MODULAR STORM TENT COMMENTS UNITS SHELTERS STRUCTURE FIRESTATION #2 #4 2 2 2 2 MODULAR UNITS , 2 GARAGES, STORM SHELTERS IRVING@WASHINGTON 7 7 N/A 7 CLASSROOMS AND KITCHEN UNIT WITH FREEZERS, STORM SHELTERS EARLY CHILDHOOD@ 30 N/A N/A CLASSROOMS McKINLEY JOPLIN HIGH SCHOOL@ 9 37 N/A CLASSROOMS, KITCHEN UNITS SHOPKO WITH FREEZERS, AND STORM SHELTERS JOPLIN HIGH SCHOOL@ 17 N/A N/A CLASSROOMS MEMORIAL EMERSON@DUQUESNE 8 3 1 CLASSROOMS, GYMNASIUM, STORM SHELTERS DUQUESNE@DUENWEG 7 9 N/A CLASSROOMS, STORM SHELTERS EAST MIDDLE SCHOOL@ 19 1 1 CLASSROOMS, GYMNASIUM, CROSSROADS LOCKER ROOM, KITCHEN UNIT WITH FREEZERS, AND STORM SHELTERS FRANKLIN TECH N/A 4 N/A STORM SHELTERS
  • 31. Joplin Schools Jun 06, 2011 August 1, 2011
  • 32. Joplin Fire Department Jun 06, 2011 July 10, 2011
  • 34. 100 105 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 5 0 New Orleans SW Division Buffalo S Pacific Division Rock Island Nashville Baltimore GL/OR Div Pac Ocean Div Huntsville Honolulu St Paul Miss Valley Div Omaha Jacksonville Detroit 1 1 1 1 1 1 1 1 1 1 1 2 2 2 2 2 2 Louisville N Atlantic Div Pittsburgh HQ Galveston 3 3 3 3 3 Mobile ACE-IT Chicago Seattle Walla Walla Alaska 4 4 4 5 5 5 Vicksburg Albuquerque NW Division Total Employee Deployed = 439 Little Rock Norfolk USACE District/Division Representation 6 6 6 6 7 New England Logistics Philadelphia Los Angeles 9 10 10 10 St Louis San Francisco 12 13 Huntington 14 Fort Worth 16 Tulsa 21 New York 23 Sacramento 41 Portland 66 RAO (Annuitants) 98 Kansas City
  • 36. Highlights • Structure – Responsiveness: ESF#3, District, PRTs and Supporting Districts mobilized rapidly and established key relationships – External Relationships: Strategic Communications with FEMA, State, and Local stakeholders aligned goals and effort – Internal Relationships: ESF/RFO matrix alignment (needs to occur earlier in mission) • Process – Project Management Approach: Completed of ALL missions on schedule – Safety: Command focus resulted in only 1 reportable accident despite aggressive optempo and record heat • Tools – Forecasting: Resource-loaded schedules allowed leaders to manage resources effectively and efficiently – PRB: Weekly boards allowed PRTs to maintain project focus and stakeholder satisfaction
  • 37. Lessons Learned • Structure – Matrix Alignment: Establish clear lines of communication and responsibilities; focus on ESF/RFO integration along PDT lines – Project Management: Provide PMP and PDT training for MM/AO; run RFO like a PMO – Advance Party: Mobilize most experienced ESF/RFO leaders and SMEs on ground early to establish unity of effort • Process – Contracting: Develop ACI-type MATOCs that support mission (key milestones, incentives, Stafford Act, etc) – Operations: Create a PMBP-type approach to RFO operations (v. SOPs) • Tools – Project Controls: Mobilize robust PC team to support PRTs – Information Management: Standardize PRT reporting procedures and tools that allow RFO leadership to forecast and analyze critical information – Dashboard: Provide common operating picture, while standardizing and synchronizing information analysis and reporting; serves as training tool
  • 40. FEMA Tools RFO Dashboard RFO Dashboard Home Event PRT Executive Stakeholders Training ESF3 Links Mission Assignments Contract Funds Schedule Resources Obligated Budget $0 $100,000,000 $200,000,000 Personnel Debris SDIC Debris Follow-On Public Affairs Office Temporary Housing Social Media Critical Public Facilities Inquiries Total Congressional Local 250 RFO Personnel Lessons Learned 200 Reachback Personnel 150 Personnel @ 100 RFO 50 TOTAL 0 CURRENT REQ REQ STRENGTH 31 JUL 15 AUG
  • 41. FEMA Executive Dashboard Home Event PRT Executive Stakeholders Training ESF3 Links Executive Executive Briefs OPSUM SITREP PRB MUB Resource Management RFO Personnel SOPs RFO SOPs After Action Reviews
  • 42. FEMA RFO Project Review Board Debris FEMA Approved Scope Base: • Debris Removal per ESF-3 Direct Federal Assistance Mission • ROW – Joplin, Duquesne, & Jasper • PPDR – EDR Zone Only • Estimated volume of 1.87 million cubic yards (MCY) and 1,400 private properties • Changes: • Pending New Mission: Private Property Demolition – Scope to be determined.
  • 43. FEMA RFO Project Review Board Debris FEMA Approved Cost Base: SDIC $57M • Programmed Amount: ($180M) DE-OB RFO LABOR -$2M • ($180M) approved SDIC AWARD -$48.06M • ($212.5M) funded MOD CAT3 ACM/L.F. -$3M • ($211.6M) obligated STAFF • ($0.9M) RFO available NWO AVAILABLE: $3.94M • ($1.15M/day) burn rate • RFO & Contracts FOLLOW-ON $146.4M DEBRIS REM x3 -$90M Changes: VEG DEBRIS -$20M ADMS -$7.4M • Revising Mission funding RFO AVAILABLE: $30M requirements based on revised debris OTHER $8.2M volumes • De-obligated $30M from F-O Debris ACM SEPARATION -$1.2M Removal Contracts S&R SUPPORT -$0.5M LABOR/MISC -$6.5M RFO AVAILABLE: **
  • 44. Debris RFO Project Review Board Schedule Progress FEMA Debris FEMA Approved Schedule
  • 45. FEMA Debris Project Review Board RFO Debris
  • 46. FEMA Debris PRT Home Event PRT Executive Stakeholders Training ESF3 Links Debris PRT 160 $10,000,000 Project Schedules 140 $9,000,000 Real Estate $8,000,000 120 $7,000,000 Reports 100 $6,000,000 PRB 80 $5,000,000 Forecast $4,000,000 60 ROW $3,000,000 40 ROE/PPDR $2,000,000 20 $1,000,000 EEI GIS 0 $0 12-Jul 12-Aug 12-Sep 12-Oct 12-Nov ROW ROE Resource Management Personnel Contracts SOPs Debris PRT SOPs FEMA SOPs Training
  • 47. FEMA RFO SOPs Home Event PRT Executive Stakeholders Training ESF3 Links SOPs Debris Program/Project Program/Project Program/Project Program/Project Initiation Planning Execution Closeout Critical Facilities Temp Housing Debris Removal Debris Removal RFO Briefing SOP RFO Closeout SOP Doctrine SOP Critical Facilities Critical Facilities Debris Removal Project Execution Doctrine SOP Closeout and Control Temporary Temporary Change Critical Facilities Housing Doctrine Housing SOP Management Closeout Site Assessment Quality Temporary Work Acceptance SOP Management Housing Closeout Project Schedule Records Project Initiation Lessons Development Management Learned/AARs Team Resource Estimate Establishment Development Acquisition Strategy
  • 48. FEMA RFO SOPs Home Event PRT Executive Stakeholders Training ESF3 Links EXECUTIVE RFO Matrix RFO Matrix RFO Org Chart RFO Duty Descriptions

Editor's Notes

  1. 1.45M CY completed in the EDR area. 1,505 Total PPDR.Right of Way (ROW) – City of Joplin, City of Duquesne, and Jasper CountyExpedited Debris Removal (EDR) zone ended 7AUG11 (90/10 cost share in EDR).Personal Property Debris Removal (PPDR). Currently only have this mission in the EDR Zone Expanded ROW debris removal mission 8/8 – 8/21 (75/25 cost share).
  2. 6 residential and 1 commercial sector established to coordinate contractor activities.
  3. Included street and 10 foot Right of Way
  4. Did not include demolition (2 or more walls remaining)