SlideShare a Scribd company logo
1 of 10
Download to read offline
lua Rd
                                                                                      Moana




                                                                                                          Ka`a
                               20 feet from wetland




                                                                                                              hum
                                  limit to edge of




                                                                                                                 anu
                                   retaining wall




                                                                                                                     St
                                                        Waiau Wetland
            New sidewalk


                                                                                     Kamehameha Hwy
                                                                 s



                                                                                4 culverts under highway
                                                               Spring




                                                                               draining into Waiau Springs
                                                             Waiau




    LEGEND
              The Project
              Wetland Limit
              Columns Near Streams                                                 PEARL
                                                                                  HARBOR
    0                   500             1000
                                           Feet




Figure 4-64 Waiau Springs and Wetland



through Pearlridge Center, discharging south into                       shore here, on which supports the growth of salt-
the East Loch of Pearl Harbor.                                          tolerant plants (mangrove and pickleweed). e
                                                                        sediment is anaerobic. Mud ats in Pearl Harbor,
`Aiea Bay State Recreation Area Wetland                                 such as this one, are relatively stable, whereas the
   e Project guideway is approximately 200 feet                         narrow riparian mud ats along streams are subject
mauka of the tidal wetland (formally a dense                            to hydraulic scouring. Recovery of the mangrove
mangal forest) fringing ‘Aiea Bay (Figure 4-66).                        removed in 2007 is well underway as juvenile
‘Aiea Stream has formed a depositional delta o the                      mangrove plants colonize the tidal at.


 4-154 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
i St
                                                                        noh
                                                                     Kao

                                       20 feet from wetland
                                          limit to edge of
   Kam                                     retaining wall
      eha
         meh
            a   Hwy


                                                         Sumida Watercress Farm                               ngs
                                                                                                     ao   Spri                                 i St
                                                                                            K   alau                                   Pali
                                                                                                                                            Mom

                                                                                   Wetland extends
                  Pearlridge                                                       beyond limit

                                                                                                  New sidewalk




                                                               ngs
                                                                                                                                                 am

                                                              Spri
                                                                                                                                      ao   Stre
                                                         uao
                                                       Kala
                                                                                                                             K   alau
                                                                                       am
                                                                                  Stre
                                                                            uao                                            Kam
                                                                      Kala                                                    eham
                                                                                                                                  eha
                                                                                                            `Aiea Kai Pl                   Hwy


   LEGEND
            The Project
            Fixed Guideway Station

            Wetland Limit

   0        250           500
                                Feet



Figure 4-65 Sumida Watercress Farm Wetland


Aolele Ditch                                                                 of the three wetlands connects to the tidal reach of
Aolele Ditch is a man-made drainage feature                                  Aolele Ditch and harbors top minnows (poeciliids)
constructed to drain stormwater to Ke‘ehi Lagoon                             and American cray sh, suggesting a permanent
from the northeastern portion of Honolulu Inter-                             fresh or slightly brackish wetland that has devel-
national Airport and an adjacent light industrial                            oped on a thin layer of sediment over the concrete
area. e lower end of the ditch is tidal. However,                            channel bed in this segment.
the part of the ditch crossed by the guideway is
an intermittently owing (non-RPW), unlined,                                  Marine Waters
open ditch fed by several small drains from the                                 e large coastal surface water bodies within
light industrial area mauka. ese drains provide                              or adjacent to the study corridor are listed in
su cient freshwater to establish three small semi-                           Table 4-28 and illustrated in Figure 4-61. ese
permanent wet areas along the bottom of the ditch                            water bodies are all highly urbanized and/or
(one under the guideway). ese “wetland” features                             altered from their natural state. Marine areas
support a variety of wetland plants and aquatic                              near the Project include the Middle and East
insects, such as dragon ies. e most downstream                               Lochs of Pearl Harbor (technically an estuarine


June 2010                                            Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement                   4-155
LEGEND
                       The Project
                       Fixed Guideway Station




                                                                                                               Moa
                       Park-and-Ride Facilities and Transit Center




                                                                                                                  nalu
                       Shoreline Boundary of




                                                                                                                      a Rd
                       Estuary Wetland
                       Ordinary High-water Mark




                                                                                                          m
                                                                                                       rea
           0                     500                     1000




                                                                                                   a St
                                                            Feet




                                                                                               `Aie
                            Kameh
                                 ameha
                                       Hwy



                                                                         Moan
                                                                             alua F
                                                                                   wy                                    `Aiea Bay State Recreation Area



                               Mangrove wetlands removed in 2007



                                              `AIEA BAY



                                                                                                   Aloha Stadium
                                                                                                      Station                               Salt Lake Blvd




Figure 4-66 `Aiea Bay State Recreation Area Wetland



Table 4-28 Marine Waters
                                                                                                                                                       2
 Water Body                                     Class                                      Associated Inlets                         303(d) Impaired
                  1
 Pearl Harbor                                   2—Inland water/estuary                     Point-source discharges; streams                Yes
 Ke`ehi Lagoon                                  A—Marine embayment                         Storm drains; streams                           Yes
 Honolulu Harbor                                A—Marine embayment                         Storm drains; streams                           Yes
 1
     Pearl Harbor includes West Loch, Middle Loch, and East Loch
 2
     303(d) Impaired Waterway as de ned by State of Hawai`i Department of Health (2008).




 4-156 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
bay), Ke‘ehi Lagoon (an open embayment), and                4.14.3 Environmental Consequences
Honolulu Harbor.                                                   and Mitigation
                                                            Environmental Consequences
Flood Zones                                                 No Build Alternative
Flood Insurance Rate Maps show that the project             Under the No Build Alternative, the Project
alignment will cross several oodplains and two              would not be built and would not have any impacts
 oodways associated with Waiau and Waiawa                   to water resources. e projects in the ORTP are
Streams (Figures 4-57 and 4-58). Floodplains                assumed to be built, and the consequences of
along the project alignment mostly recharge                 those projects will be studied and documented in
groundwater levels, convey stormwater toward the            separate environmental documents.
ocean, and help moderate oods when they occur
(Figure 4-67). ese areas also support plants and            Project
wildlife within urbanized areas, while maintaining             e following sections discuss possible e ects to
areas for outdoor recreation and enjoyment and              surface and marine waters, wetlands, ood zones,
preserving the land’s natural beauty. e ood                 stormwater, and groundwater and present coordi-
zones and their associated waters are listed in             nation activities and mitigation that will occur to
Table 4-29.                                                 address possible e ects. E ects during construc-
                                                            tion are discussed in Section 4.18.
Stormwater
   e existing drainage conditions encountered               Surface Waters
along the guideway alignment consist of the                 Project encroachment into waters of the U.S. is
following: undeveloped or unpaved areas, areas              summarized in Tables 4-30 and 4-31. e Project
adjacent to paved roadways, landscaped median               will, once constructed, permanently encroach
areas of paved roadways, or a combination of                upon 0.08 acre of waters of the U.S. (0.02 acre
these conditions. Drainage conditions for the               as listed on Table 4-30 and 0.06 acre as listed on
Project area west of Ho‘opili Station (west Site 4)         Table 4-31). ese impacts are from placing piers
are generally undeveloped or unpaved. e drain-              in Waiawa Springs, Moanalua Stream, Kapālama
age conditions for the Project within the City of           Canal Stream, and Nu‘uanu Stream and improv-
Waipahu are landscaped median areas of paved                ing a culvert in Waiawa Springs. Although Kalo‘i
roadway. e drainage conditions for the majority             Gulch is not under the jurisdiction of the USACE
of the project alignment are areas adjacent to paved        and not included in Tables 4-30 or 4-31, it was
roadways or a combination of various conditions.            considered in the impact quantities with the use
   e existing drainage system consists of drainage          of the preliminary JD approach. e Project at
pipes/culverts, structures, swales, and outfalls to         Kalo‘i Gulch will add 0.009 acre of permanent
tributaries adjacent to Pearl Harbor and Honolulu           impact from the guideway support columns,
Harbor.                                                     with 27 cubic yards of impact below OHWM and
                                                            above the mudline and 1,234 cubic yards below
Groundwater                                                 the mudline (linear transportation features).
  e entire Project overlies the Southern O‘ahu                 e Project will also add 0.39 acre of permanent
Basal Aquifer and includes two aquifer sectors. e           impact from a park-and-ride lot, with 953 cubic
Pearl Harbor Aquifer Sector contains the ‘Ewa,              yards below OHWM and above the mudline and
Waipahu, Waiawa, and Waimalu Aquifer Systems,               744 cubic yards below the mudline.
and the Honolulu Aquifer Sector contains the
Moanalua, Kalihi, and Nu‘uanu Aquifer Systems.

June 2010                                 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement   4-157
Waiawa
                                                                                                                                                                        Waikele

                                                                                                                                                                                                                                  Waimalu




                                                                         Figure 4-67 Watershed and Flood Zones
                                                                                                                                           Honouliuli
                                                                                                                                                                                                  31
                                                                                                                                                                                       Kapakahi         12 13                          Kalauao
                                                                                                                                                                                                                14
                                                                                                                                                                                                  11A                15                     `Aiea
                                                                                                                                                                                        7 9 10                            16                             Hālawa
                                                                                                                                                                                                  11B                          17 18
                                                                                                                                                                                   6     8                                          19
                                                                                                                                                                         4 5                                                        20 21                            Moanalua
                                                                                                                                                                    3                                                                                                                  Kalihi
                                                                                                                                                                                                                                   22 23
                                                                                                                                                              2
                                                                                                                                                                                                  Waipio




4-158 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
                                                                                                                                                                                                                                                Ke`ehi
                                                                                                                                                              1                                                                                          24
                                                                                                                                                                                                                                                          26                          Nu`uanu
                                                                                                                                                                                                                                                    25   27 28       Kapālama
                                                                                                                                                 Kalo`i                                                                           Manuwai                            29
                                                                                                                                                                                                                                                                          30          Makiki




                                                                                                                                                                                                                                                                                            Ala Wai
                                                                                                                 LEGEND
                                                                                                                                                   Watershed                                       Flood Zones
                                                                                                                 #   Wetland and Waters of the         Ala Wai          Kapakahi        Nu`uanu         Moderate to Low Risk Zones X and X500
                                                                                                                     U.S. Study Sites                  Hālawa           Kapālama        Waiawa           High Risk Zones A, AE, AH, and AO
                                                                                                                     Fixed Guideway Station            Honouliuli       Ke`ehi          Waikele          High Risk Coastal Zone VE
                                                                                                                     The Project                       Kalauao          Makiki          Waimalu
                                                                                                                     Salt Lake Alternative             Kalihi           Manuwai         Waipio                                                           0       1        2
                                                                                                                     Park-and-Ride Access Ramp         Kalo`i                                                                                                                 Miles
                                                                                                                                                                        Moanalua        `Aiea
Table 4-29 Streams Having FEMA Mapped Flood Zones
                                                                                                                                               Flood Zone(s) Traversed by
 Associated Water Body                                Developed              Major Functions
                                                                                                                                                    Fixed Guideway
 Kalo`i Gulch                                              Yes               Groundwater recharge; stormwater conveyance                                    AE
 Honouliuli Stream                                          No               Groundwater recharge; stormwater conveyance                                      A
 Waikele Stream                                            Yes               Stormwater conveyance                                                       AEF, AE
 Kapakahi Stream        1
                                                           Yes               Stormwater conveyance                                                       AEF, AE
 Waipahu Canal Stream2                                     Yes               Stormwater conveyance                                                       AEF, AE
 Waiawa Stream                                             Yes               Stormwater conveyance                                                       AEF, AE
 Kalauao Stream                                            Yes               Stormwater conveyance                                                          AEF
 Moanalua Stream                                           Yes               Stormwater conveyance                                                     AEF, AE, AO
 Kalihi Stream                                             Yes               Stormwater conveyance                                                     AEF, AE, AO
 Zone A = the ood insurance rate zone that corresponds to the 100-year oodplains that are determined in the Flood Insurance Study by approximate methods. Because detailed
 hydraulic analyses are not performed for such areas, no base ood elevations or depths are shown within this zone.
 Zone AE = the ood insurance rate zones that correspond to the 100-year oodplains that are determined in the Flood Insurance Study by detailed methods. In most instances, base
  ood elevations derived from the detailed hydraulic analyses are shown at selected intervals within this zone.
 Zone AEF = the area within Zone “AE” reserved to pass the base ood.
 Zone AO = the ood insurance rate zone that corresponds to the areas of 100-year shallow ooding (usually sheet ow on sloping terrain) where average depths are between 1 and
 3 feet. The depth should be averaged along the cross-section and then along the direction of ow to determine the extent of the zone. Average ood depths derived from the detailed
 hydraulic analyses are shown within this zone. In addition, alluvial fan ood hazards are shown as Zone AO on the Flood Insurance Rate Map.
 FEMA referes to this canal as “Kapakahi Stream #2” on their FIRM maps (Panel No. 0240F)
 1

 2
     FEMA referes to this canal as “Wailani Canal” on their FIRM maps (Panel No. 0240F)




 Table 4-30 Permanent Impacts to Waters of the U.S. (Linear Transportation Features)
                                                                                       Waiawa
                                                                                                       Moanalua           Kapālama                Nu`uanu
                                                                                      Stream &                                                                      Total Impact
      Total Impact                                                                                      Stream           Canal Stream              Stream
                                                                                       Springs                                                                       of Project
                                                                                                       (Site 27)           (Site 29)              (Site 30)
                                                                                   (Sites 12 & 13)

      Area (acres)                                                                        0.003           0.004                 0.01                0.004                 0.02

      Volume (cubic yards) (below OHWM and above mudline)                                   10                 8                   61                  27                  105

      Volume (cubic yards) (below mudline)                                                 873            1,454                   60                1,164                3,551




 Table 4-31 Permanent Impacts to Waters of the U.S. (Other Project Features)

      Total Impact                                                                                   Waiawa Springs (Existing Stormwater Culvert Extension)

      Area (acres)                                                                                                                      0.06
      Volume (cubic yards) (below OHWM and above mudline)                                                                               185
      Volume (cubic yards) (below mudline)                                                                                               0



June 2010                                                                 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement                   4-159
As discussed in Section 4.18, during construction                     derivative adverse impacts resulting from the
of the xed guideway (linear transportation project                    Project that would be overlooked by focusing on
features), it is anticipated that there will be a tem-                acreage or that don’t scale to acreage. Kalo‘i Gulch
porary e ect of up to 0.13 acre of waters of the U.S.                 is not under the jurisdiction of the USACE and is,
Although Kalo‘i Gulch is not under the jurisdiction                   therefore, not listed in Tables 4-30 or 4-31. However,
of the USACE and the impacts are not listed in                        it was considered in the impact quantities with the
the tables, temporary impacts include 0.07 acre                       use of the preliminary JD approach.
of impact from the guideway support columns
with 948 cubic yards of impact below OHWM                             Kalo`i Gulch
and above the mudline. An additional 0.86 acre of                        e lower end of Kalo‘i Gulch on the ‘Ewa Plain
temporary impact will result from construction of                     will be impacted by structural elements of the
a park-and-ride lot at Lower Kalo‘i Gulch with an                     Project in two respects—a park-and-ride lot is
additional 1,238 cubic yards below OHWM and                           proposed for a parcel crossed by the man-made
above the mudline.                                                    drainage channel (Site 1); and support columns
                                                                      for the guideway will be located on the banks of
Of the 20 streams in the study corridor, most                         the Kalo‘i Drainage Channel (Site 2). Although
will not be directly a ected because the Project’s                    how the drainage channel at the park-and-ride
elevated guideway will clear-span these streams                       lot will be designed has yet to be determined, the
and there will be no pier or column construction                      most likely solution will be to replace the exist-
or other construction-related activities within the                   ing man-made ditch with a buried box culvert.
stream channel below OHWM. In general, the                            Another option would be to redirect the channel
project alignment parallels other bridge crossings                    elsewhere, for example via a ditch or culvert more
of the streams and, in many cases, crosses along                      directly to the Kalo‘i Drainage Canal nearby to
the median between bridges carrying opposing                          the east. No aquatic resources are associated with
lanes of tra c. In these cases (Categories II                         this channel, which is normally dry and cut-o
through IV as outlined in Section 4.14.2), the                        from most of its drainage basin by redirection of
only potential direct e ect of the Project is one                     upper Kalo‘i Gulch into the Kalo‘i Drainage Canal.
of shading of the stream or wetland. Because the                      Future urban development will likely establish
guideway is elevated relative to the surrounding                      runo conveyances throughout this area. As noted,
roadway crossings, the guideway will only impart                      the Kalo‘i Drainage Canal will take over much
minimal, additional shading onto the water as                         of the stormwater runo contributed by Kalo‘i
compared to the bridges already present in each                       Gulch. is approximately 160-foot wide channel
location. Shading impacts are addressed in more                       is presently under construction paralleling North-
detail for Sumida Watercress Farm, below.                             South Road. Neither this channel nor the existing
                                                                      narrow Kalo‘i Gulch (Site 2) have aquatic resource
   e streams a ected by structural elements of the                    value. e guideway crosses the “new” channel at a
Project are described below and in Tables 4-30                        shallow angle on a turn, and the span at this point
and 4-31. ese are the Category V sites discussed                      cannot avoid placing several columns within the
above, most of which are estuarine and con ned to                     banks of the channel. Two columns (approximately
highly modi ed channels with little to no ripar-                      36 square feet constructed on 10-foot drilled
ian values. An acreage approach to quantifying                        sha s) are located near the bottom of the banks
impacts was followed since functional assessment                      (within the 100-year oodway).
methods are typically calibrated to non-urban,
non-hardened areas. ere are no secondary or

 4-160 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
Waiawa Stream and Springs                                    Stream, all above OHWM. ese columns were
    e Project and associated features will have one          moved away from the stream to avoid impacts.
guideway support column and two station piers                Waiawa Stream in this area ows in a natural bed
below OHWM. ere will be some impacts to                      and banks, although there are multiple existing
riparian areas. Moving the station location, park-           piers in the stream associated with Farrington
ing structure, bus transit center, and other features        Highway and Kamehameha Highway bridges.
is the only option to avoid impacts to this area. e
Pearl Highlands Station is projected to have the                e guideway will clear-span this stream makai of
second-highest passenger volume of all stations in           the Pearl Highlands Station. e Pearl Highlands
the system and will serve as the transfer point for          parking and transit center will be constructed on
all users in Central O‘ahu, whether they drive to            circular columns close to Waiawa Stream. In this
the station or transfer from eBus. is transit                area, the park-and-ride structure roughly paral-
center and park-and-ride facility are designed               lels Waiawa Stream (Figure 4-62). is structure
to provide easy access to the xed guideway                   will require approximately six support columns
transit system from the H-1 and H-2 Freeways,                (approximately 25 square feet each) to be located in
Kamehameha Highway, and Farrington Highway.                  the riparian area outside the OHWM but below the
    is station location provides the most convenient         top-of-bank (TOB) line.
access to the system for residents of Central O‘ahu
(i.e., locations mauka and ‘Ewa of the station).             Construction of the elevated guideway at Pearl
    erefore, elimination of the station and associ-          Highlands Station will result in one guideway
ated park-and-ride structure does not satisfy the            support column (approximately 36 square feet
Project’s Purpose and Need.                                  constructed on a 10-foot drilled sha foundation)
                                                             and two station piers (approximately 25 square feet
Alternative locations for the Pearl Highlands                each) being placed close to the OHWM of Waiawa
Station and park-and-ride lot were identi ed at              Springs located beneath the station structure.
Leeward Community College and the Hawai‘i                       e impact area and ll for these columns are
Laborers Training Program site. Both of these sites          included in Table 4-30 because of their proximity
were evaluated in Section 5.4.2 of the Dra EIS               to the springs. e location of the Pearl Highlands
that addressed avoidance alternatives to potential           Station is designed to be in close proximity to the
impacts to the historic Solmirin House (since                proposed park-and-ride lot as well as surrounding
publication of the Dra EIS, the Solmirin House               businesses. e piers near the Pearl Highlands Sta-
was determined to be not eligible for designation            tion cannot be relocated because they are support-
as a historic resource). Locating the park-and-ride          ing the guideway as it enters the station, as well as
facilities at either of the two avoidance alternative        supporting a concourse, stairs, and escalators.
sites would cost substantially more and provide less
e cient transportation circulation, as access would             e springs (Site 13) in this case is at the end of a
be less direct. For these reasons, these avoidance           street drain passing under Kamehameha Highway.
alternatives are not considered feasible.                    It would best be modi ed by constructing an
                                                             extension of the existing pipe culvert to a point
   e construction of the high occupancy vehicle              beyond the elevated station footprint. is new
(HOV) ramp that will connect inbound H-2                     “outlet” would be located closer to Waiawa Stream
Freeway vehicles with the park-and-ride structure            where the TOB line and OHWM closely coincide
adjacent to the Pearl Highlands Station will result          along an erosion face created by the piers of the
in four columns being constructed close to Waiawa            Farrington Highway bridge forcing the stream ow

June 2010                                  Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement   4-161
to the right (thus eroding the le bank). Extending                   feet each on 10-foot drilled sha foundations) will
the drain’s outlet would have no consequences on                     need to be constructed in the estuary (Figure 4-68).
spring-water contribution to Waiawa Stream and                           is location (Site 27) is makai of the H-1 Freeway
would reduce potential stream contamination in                       ramp to Nimitz Highway. In this area, there
an area that would be too shaded by the station                      exists multiple bridge crossings of Moanalua
structure to support plant growth. A cut in the                      Stream, including Kamehameha Highway, the
high bank already exists where the spring ow                         H-1 Freeway, Nimitz Highway ramps, and two
joins Waiawa Stream.                                                 pedestrian bridges makai of the project guideway
                                                                     crossing. e guideway columns will be aligned
Approximately 5 acres near Waiawa Stream                             with the upstream viaduct piers, as feasible, to
between Kamehameha Highway and Farrington                            minimize obstruction of stream ow. is area
Highway will be shaded by structures (a park-                        is tidal and near the stream mouth at Ke‘ehi
and-ride parking structure, bus transit center,                      Lagoon. Placement of the piers is not expected to
station and guideway, and various pedestrian and                     have any consequences on the Moanalua Stream
vehicle access ramps), roughly one-third of the                      estuarine environment or its fauna beyond a loss
area (Sites 12 and 13). Direct impacts on the stream                 of 0.004 acre of sandy mud bottom. Because the
(including shading) would be minimal; most of                        guideway lies immediately south of the existing
the structures are on the north side of the stream.                  viaducts and will be elevated 50 feet above the
Waiawa Stream supports some native amphidro-                         water, shading on the estuary will be minimal.
mous fauna, and no part of the Project is antici-
pated to interfere with the local population of goby                 Kapālama Canal Stream
observed or migration through the site required by                      e existing Dillingham Boulevard bridge over
native macrofauna that may breed upstream.                           Kapālama Canal Stream will be widened makai.
                                                                        is will allow for construction of a new median
To maintain oodway hydrology, it will be neces-                      in line with the guideway to maintain two through
sary to remove ll material from along Waiawa                         lanes and one dedicated le -turn lane for both
Stream in this area. Approximately 100 feet of the                   directions of tra c. is will improve safety and
small tributary issuing from an existing drain                       enhance tra c ow. ere will be impacts to
(Site 13) will be con ned within an extension of                     Kapālama Canal Stream to extend the existing
that drain pipe.                                                     piers and abutments.

Moanalua Stream                                                      A design option was evaluated at this stream
To avoid impacts below OHWM in Moanalua                              crossing to avoid impacts below OHWM that
Stream (300 feet wide) substantially di erent                        considered construction of the guideway on
bridge types would be needed to clear span this                      straddle bents located on each bank of the stream.
stream. is stream is beyond the practical length                        e straddle bents would have been approximately
limit for precast concrete girders (150 feet). Long                  100 feet long to completely straddle Dillingham
spans could add $5 million to total project costs.                   Boulevard. is option was not considered feasible
For this reason, avoiding impacts below OHWM in                      for the following reasons:
these streams is not considered feasible.                               • Construction of massive straddle bents would
                                                                           be di cult in this congested corridor
Because of the 300-foot width of the channel                            • e large straddle bents would require large
where the guideway crosses Moanalua Stream,                                and expensive drilled sha foundations
two guideway columns (approximately 36 square

4-162 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
• Overhead power lines would complicate                                    located outside of Kapālama Canal behind the
     construction                                                             existing bridge abutments, the Dillingham Boule-
   • e size of the straddle bents would have a                                vard Bridge will need to be widened approximately
     considerable visual impact in this area                                  20 feet makai to accommodate a new median. In-
                                                                              water work will involve extending the four existing
  e Project crosses Kapālama Canal Stream at the                              bridge piers and the two existing bridge abutments
Dillingham Boulevard Bridge with the guideway in                              makai. Pier extensions will require eight addi-
the median of the Boulevard (Site 29; Figure 4-69).                           tional piles placed in the stream (approximately
Although the guideway support columns will be                                 1.36 square feet each). e abutment and retaining




       LEGEND
                The Project
                Fixed Guideway Station
                Columns in Waters of the U.S.
                Columns near Streams
      0                  500                    1000
                                                   Feet




                                                                                                                       Middle Street
                                                                                                                       Transit Center
                                                                         Moanalu




                                                                                                                                     Nim
                                                                                                                                        itz
                                                                                                                                            Hw
                                                                                                                                               y
                                                                           a Stream




                                                                                                               am
                                                                                                               re
                                                                                                            St
                                                                                                          hi
                                                                                                          li
                                                                                                       Ka




                                            HONOLULU
                                             HARBOR


Figure 4-68 Moanalua Stream

June 2010                                                 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement   4-163

More Related Content

Viewers also liked

Viewers also liked (6)

Final EIS Appendix A Part 2
Final EIS Appendix A Part 2Final EIS Appendix A Part 2
Final EIS Appendix A Part 2
 
Final EIS Part 2
Final EIS Part 2Final EIS Part 2
Final EIS Part 2
 
Hawaii Supreme Court Concurring Opinion Police Misconduct
Hawaii Supreme Court Concurring Opinion Police MisconductHawaii Supreme Court Concurring Opinion Police Misconduct
Hawaii Supreme Court Concurring Opinion Police Misconduct
 
HART Safety & Security
HART Safety & SecurityHART Safety & Security
HART Safety & Security
 
Final EIS Appendix A Part 3
Final EIS Appendix A Part 3Final EIS Appendix A Part 3
Final EIS Appendix A Part 3
 
Sirom Settlement Agreement
Sirom Settlement AgreementSirom Settlement Agreement
Sirom Settlement Agreement
 

More from Honolulu Civil Beat

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooHonolulu Civil Beat
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Honolulu Civil Beat
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsHonolulu Civil Beat
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD Honolulu Civil Beat
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Honolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Honolulu Civil Beat
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersHonolulu Civil Beat
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Honolulu Civil Beat
 

More from Honolulu Civil Beat (20)

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna Eshoo
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10
 
NHPI COVID-19 Statement
NHPI COVID-19 StatementNHPI COVID-19 Statement
NHPI COVID-19 Statement
 
DLIR Response Language Access
DLIR Response Language AccessDLIR Response Language Access
DLIR Response Language Access
 
Language Access Letter To DLIR
Language Access Letter To DLIRLanguage Access Letter To DLIR
Language Access Letter To DLIR
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
Jane Doe v. Rehab Hospital
Jane Doe v. Rehab HospitalJane Doe v. Rehab Hospital
Jane Doe v. Rehab Hospital
 
Coronavirus HPHA
Coronavirus HPHA Coronavirus HPHA
Coronavirus HPHA
 
OHA Data Request
OHA Data RequestOHA Data Request
OHA Data Request
 
Letter from Palau to Guam
Letter from Palau to GuamLetter from Palau to Guam
Letter from Palau to Guam
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence
 
OHA Analysis by Akina
OHA Analysis by AkinaOHA Analysis by Akina
OHA Analysis by Akina
 
Case COFA Letter
Case COFA LetterCase COFA Letter
Case COFA Letter
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service Providers
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018
 
Caldwell Press Release
Caldwell Press ReleaseCaldwell Press Release
Caldwell Press Release
 

Recently uploaded

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxBkGupta21
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????blackmambaettijean
 

Recently uploaded (20)

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
unit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptxunit 4 immunoblotting technique complete.pptx
unit 4 immunoblotting technique complete.pptx
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
What is Artificial Intelligence?????????
What is Artificial Intelligence?????????What is Artificial Intelligence?????????
What is Artificial Intelligence?????????
 

Final EIS Part 3

  • 1. lua Rd Moana Ka`a 20 feet from wetland hum limit to edge of anu retaining wall St Waiau Wetland New sidewalk Kamehameha Hwy s 4 culverts under highway Spring draining into Waiau Springs Waiau LEGEND The Project Wetland Limit Columns Near Streams PEARL HARBOR 0 500 1000 Feet Figure 4-64 Waiau Springs and Wetland through Pearlridge Center, discharging south into shore here, on which supports the growth of salt- the East Loch of Pearl Harbor. tolerant plants (mangrove and pickleweed). e sediment is anaerobic. Mud ats in Pearl Harbor, `Aiea Bay State Recreation Area Wetland such as this one, are relatively stable, whereas the e Project guideway is approximately 200 feet narrow riparian mud ats along streams are subject mauka of the tidal wetland (formally a dense to hydraulic scouring. Recovery of the mangrove mangal forest) fringing ‘Aiea Bay (Figure 4-66). removed in 2007 is well underway as juvenile ‘Aiea Stream has formed a depositional delta o the mangrove plants colonize the tidal at. 4-154 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
  • 2. i St noh Kao 20 feet from wetland limit to edge of Kam retaining wall eha meh a Hwy Sumida Watercress Farm ngs ao Spri i St K alau Pali Mom Wetland extends Pearlridge beyond limit New sidewalk ngs am Spri ao Stre uao Kala K alau am Stre uao Kam Kala eham eha `Aiea Kai Pl Hwy LEGEND The Project Fixed Guideway Station Wetland Limit 0 250 500 Feet Figure 4-65 Sumida Watercress Farm Wetland Aolele Ditch of the three wetlands connects to the tidal reach of Aolele Ditch is a man-made drainage feature Aolele Ditch and harbors top minnows (poeciliids) constructed to drain stormwater to Ke‘ehi Lagoon and American cray sh, suggesting a permanent from the northeastern portion of Honolulu Inter- fresh or slightly brackish wetland that has devel- national Airport and an adjacent light industrial oped on a thin layer of sediment over the concrete area. e lower end of the ditch is tidal. However, channel bed in this segment. the part of the ditch crossed by the guideway is an intermittently owing (non-RPW), unlined, Marine Waters open ditch fed by several small drains from the e large coastal surface water bodies within light industrial area mauka. ese drains provide or adjacent to the study corridor are listed in su cient freshwater to establish three small semi- Table 4-28 and illustrated in Figure 4-61. ese permanent wet areas along the bottom of the ditch water bodies are all highly urbanized and/or (one under the guideway). ese “wetland” features altered from their natural state. Marine areas support a variety of wetland plants and aquatic near the Project include the Middle and East insects, such as dragon ies. e most downstream Lochs of Pearl Harbor (technically an estuarine June 2010 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement 4-155
  • 3. LEGEND The Project Fixed Guideway Station Moa Park-and-Ride Facilities and Transit Center nalu Shoreline Boundary of a Rd Estuary Wetland Ordinary High-water Mark m rea 0 500 1000 a St Feet `Aie Kameh ameha Hwy Moan alua F wy `Aiea Bay State Recreation Area Mangrove wetlands removed in 2007 `AIEA BAY Aloha Stadium Station Salt Lake Blvd Figure 4-66 `Aiea Bay State Recreation Area Wetland Table 4-28 Marine Waters 2 Water Body Class Associated Inlets 303(d) Impaired 1 Pearl Harbor 2—Inland water/estuary Point-source discharges; streams Yes Ke`ehi Lagoon A—Marine embayment Storm drains; streams Yes Honolulu Harbor A—Marine embayment Storm drains; streams Yes 1 Pearl Harbor includes West Loch, Middle Loch, and East Loch 2 303(d) Impaired Waterway as de ned by State of Hawai`i Department of Health (2008). 4-156 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
  • 4. bay), Ke‘ehi Lagoon (an open embayment), and 4.14.3 Environmental Consequences Honolulu Harbor. and Mitigation Environmental Consequences Flood Zones No Build Alternative Flood Insurance Rate Maps show that the project Under the No Build Alternative, the Project alignment will cross several oodplains and two would not be built and would not have any impacts oodways associated with Waiau and Waiawa to water resources. e projects in the ORTP are Streams (Figures 4-57 and 4-58). Floodplains assumed to be built, and the consequences of along the project alignment mostly recharge those projects will be studied and documented in groundwater levels, convey stormwater toward the separate environmental documents. ocean, and help moderate oods when they occur (Figure 4-67). ese areas also support plants and Project wildlife within urbanized areas, while maintaining e following sections discuss possible e ects to areas for outdoor recreation and enjoyment and surface and marine waters, wetlands, ood zones, preserving the land’s natural beauty. e ood stormwater, and groundwater and present coordi- zones and their associated waters are listed in nation activities and mitigation that will occur to Table 4-29. address possible e ects. E ects during construc- tion are discussed in Section 4.18. Stormwater e existing drainage conditions encountered Surface Waters along the guideway alignment consist of the Project encroachment into waters of the U.S. is following: undeveloped or unpaved areas, areas summarized in Tables 4-30 and 4-31. e Project adjacent to paved roadways, landscaped median will, once constructed, permanently encroach areas of paved roadways, or a combination of upon 0.08 acre of waters of the U.S. (0.02 acre these conditions. Drainage conditions for the as listed on Table 4-30 and 0.06 acre as listed on Project area west of Ho‘opili Station (west Site 4) Table 4-31). ese impacts are from placing piers are generally undeveloped or unpaved. e drain- in Waiawa Springs, Moanalua Stream, Kapālama age conditions for the Project within the City of Canal Stream, and Nu‘uanu Stream and improv- Waipahu are landscaped median areas of paved ing a culvert in Waiawa Springs. Although Kalo‘i roadway. e drainage conditions for the majority Gulch is not under the jurisdiction of the USACE of the project alignment are areas adjacent to paved and not included in Tables 4-30 or 4-31, it was roadways or a combination of various conditions. considered in the impact quantities with the use e existing drainage system consists of drainage of the preliminary JD approach. e Project at pipes/culverts, structures, swales, and outfalls to Kalo‘i Gulch will add 0.009 acre of permanent tributaries adjacent to Pearl Harbor and Honolulu impact from the guideway support columns, Harbor. with 27 cubic yards of impact below OHWM and above the mudline and 1,234 cubic yards below Groundwater the mudline (linear transportation features). e entire Project overlies the Southern O‘ahu e Project will also add 0.39 acre of permanent Basal Aquifer and includes two aquifer sectors. e impact from a park-and-ride lot, with 953 cubic Pearl Harbor Aquifer Sector contains the ‘Ewa, yards below OHWM and above the mudline and Waipahu, Waiawa, and Waimalu Aquifer Systems, 744 cubic yards below the mudline. and the Honolulu Aquifer Sector contains the Moanalua, Kalihi, and Nu‘uanu Aquifer Systems. June 2010 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement 4-157
  • 5. Waiawa Waikele Waimalu Figure 4-67 Watershed and Flood Zones Honouliuli 31 Kapakahi 12 13 Kalauao 14 11A 15 `Aiea 7 9 10 16 Hālawa 11B 17 18 6 8 19 4 5 20 21 Moanalua 3 Kalihi 22 23 2 Waipio 4-158 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation Ke`ehi 1 24 26 Nu`uanu 25 27 28 Kapālama Kalo`i Manuwai 29 30 Makiki Ala Wai LEGEND Watershed Flood Zones # Wetland and Waters of the Ala Wai Kapakahi Nu`uanu Moderate to Low Risk Zones X and X500 U.S. Study Sites Hālawa Kapālama Waiawa High Risk Zones A, AE, AH, and AO Fixed Guideway Station Honouliuli Ke`ehi Waikele High Risk Coastal Zone VE The Project Kalauao Makiki Waimalu Salt Lake Alternative Kalihi Manuwai Waipio 0 1 2 Park-and-Ride Access Ramp Kalo`i Miles Moanalua `Aiea
  • 6. Table 4-29 Streams Having FEMA Mapped Flood Zones Flood Zone(s) Traversed by Associated Water Body Developed Major Functions Fixed Guideway Kalo`i Gulch Yes Groundwater recharge; stormwater conveyance AE Honouliuli Stream No Groundwater recharge; stormwater conveyance A Waikele Stream Yes Stormwater conveyance AEF, AE Kapakahi Stream 1 Yes Stormwater conveyance AEF, AE Waipahu Canal Stream2 Yes Stormwater conveyance AEF, AE Waiawa Stream Yes Stormwater conveyance AEF, AE Kalauao Stream Yes Stormwater conveyance AEF Moanalua Stream Yes Stormwater conveyance AEF, AE, AO Kalihi Stream Yes Stormwater conveyance AEF, AE, AO Zone A = the ood insurance rate zone that corresponds to the 100-year oodplains that are determined in the Flood Insurance Study by approximate methods. Because detailed hydraulic analyses are not performed for such areas, no base ood elevations or depths are shown within this zone. Zone AE = the ood insurance rate zones that correspond to the 100-year oodplains that are determined in the Flood Insurance Study by detailed methods. In most instances, base ood elevations derived from the detailed hydraulic analyses are shown at selected intervals within this zone. Zone AEF = the area within Zone “AE” reserved to pass the base ood. Zone AO = the ood insurance rate zone that corresponds to the areas of 100-year shallow ooding (usually sheet ow on sloping terrain) where average depths are between 1 and 3 feet. The depth should be averaged along the cross-section and then along the direction of ow to determine the extent of the zone. Average ood depths derived from the detailed hydraulic analyses are shown within this zone. In addition, alluvial fan ood hazards are shown as Zone AO on the Flood Insurance Rate Map. FEMA referes to this canal as “Kapakahi Stream #2” on their FIRM maps (Panel No. 0240F) 1 2 FEMA referes to this canal as “Wailani Canal” on their FIRM maps (Panel No. 0240F) Table 4-30 Permanent Impacts to Waters of the U.S. (Linear Transportation Features) Waiawa Moanalua Kapālama Nu`uanu Stream & Total Impact Total Impact Stream Canal Stream Stream Springs of Project (Site 27) (Site 29) (Site 30) (Sites 12 & 13) Area (acres) 0.003 0.004 0.01 0.004 0.02 Volume (cubic yards) (below OHWM and above mudline) 10 8 61 27 105 Volume (cubic yards) (below mudline) 873 1,454 60 1,164 3,551 Table 4-31 Permanent Impacts to Waters of the U.S. (Other Project Features) Total Impact Waiawa Springs (Existing Stormwater Culvert Extension) Area (acres) 0.06 Volume (cubic yards) (below OHWM and above mudline) 185 Volume (cubic yards) (below mudline) 0 June 2010 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement 4-159
  • 7. As discussed in Section 4.18, during construction derivative adverse impacts resulting from the of the xed guideway (linear transportation project Project that would be overlooked by focusing on features), it is anticipated that there will be a tem- acreage or that don’t scale to acreage. Kalo‘i Gulch porary e ect of up to 0.13 acre of waters of the U.S. is not under the jurisdiction of the USACE and is, Although Kalo‘i Gulch is not under the jurisdiction therefore, not listed in Tables 4-30 or 4-31. However, of the USACE and the impacts are not listed in it was considered in the impact quantities with the the tables, temporary impacts include 0.07 acre use of the preliminary JD approach. of impact from the guideway support columns with 948 cubic yards of impact below OHWM Kalo`i Gulch and above the mudline. An additional 0.86 acre of e lower end of Kalo‘i Gulch on the ‘Ewa Plain temporary impact will result from construction of will be impacted by structural elements of the a park-and-ride lot at Lower Kalo‘i Gulch with an Project in two respects—a park-and-ride lot is additional 1,238 cubic yards below OHWM and proposed for a parcel crossed by the man-made above the mudline. drainage channel (Site 1); and support columns for the guideway will be located on the banks of Of the 20 streams in the study corridor, most the Kalo‘i Drainage Channel (Site 2). Although will not be directly a ected because the Project’s how the drainage channel at the park-and-ride elevated guideway will clear-span these streams lot will be designed has yet to be determined, the and there will be no pier or column construction most likely solution will be to replace the exist- or other construction-related activities within the ing man-made ditch with a buried box culvert. stream channel below OHWM. In general, the Another option would be to redirect the channel project alignment parallels other bridge crossings elsewhere, for example via a ditch or culvert more of the streams and, in many cases, crosses along directly to the Kalo‘i Drainage Canal nearby to the median between bridges carrying opposing the east. No aquatic resources are associated with lanes of tra c. In these cases (Categories II this channel, which is normally dry and cut-o through IV as outlined in Section 4.14.2), the from most of its drainage basin by redirection of only potential direct e ect of the Project is one upper Kalo‘i Gulch into the Kalo‘i Drainage Canal. of shading of the stream or wetland. Because the Future urban development will likely establish guideway is elevated relative to the surrounding runo conveyances throughout this area. As noted, roadway crossings, the guideway will only impart the Kalo‘i Drainage Canal will take over much minimal, additional shading onto the water as of the stormwater runo contributed by Kalo‘i compared to the bridges already present in each Gulch. is approximately 160-foot wide channel location. Shading impacts are addressed in more is presently under construction paralleling North- detail for Sumida Watercress Farm, below. South Road. Neither this channel nor the existing narrow Kalo‘i Gulch (Site 2) have aquatic resource e streams a ected by structural elements of the value. e guideway crosses the “new” channel at a Project are described below and in Tables 4-30 shallow angle on a turn, and the span at this point and 4-31. ese are the Category V sites discussed cannot avoid placing several columns within the above, most of which are estuarine and con ned to banks of the channel. Two columns (approximately highly modi ed channels with little to no ripar- 36 square feet constructed on 10-foot drilled ian values. An acreage approach to quantifying sha s) are located near the bottom of the banks impacts was followed since functional assessment (within the 100-year oodway). methods are typically calibrated to non-urban, non-hardened areas. ere are no secondary or 4-160 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
  • 8. Waiawa Stream and Springs Stream, all above OHWM. ese columns were e Project and associated features will have one moved away from the stream to avoid impacts. guideway support column and two station piers Waiawa Stream in this area ows in a natural bed below OHWM. ere will be some impacts to and banks, although there are multiple existing riparian areas. Moving the station location, park- piers in the stream associated with Farrington ing structure, bus transit center, and other features Highway and Kamehameha Highway bridges. is the only option to avoid impacts to this area. e Pearl Highlands Station is projected to have the e guideway will clear-span this stream makai of second-highest passenger volume of all stations in the Pearl Highlands Station. e Pearl Highlands the system and will serve as the transfer point for parking and transit center will be constructed on all users in Central O‘ahu, whether they drive to circular columns close to Waiawa Stream. In this the station or transfer from eBus. is transit area, the park-and-ride structure roughly paral- center and park-and-ride facility are designed lels Waiawa Stream (Figure 4-62). is structure to provide easy access to the xed guideway will require approximately six support columns transit system from the H-1 and H-2 Freeways, (approximately 25 square feet each) to be located in Kamehameha Highway, and Farrington Highway. the riparian area outside the OHWM but below the is station location provides the most convenient top-of-bank (TOB) line. access to the system for residents of Central O‘ahu (i.e., locations mauka and ‘Ewa of the station). Construction of the elevated guideway at Pearl erefore, elimination of the station and associ- Highlands Station will result in one guideway ated park-and-ride structure does not satisfy the support column (approximately 36 square feet Project’s Purpose and Need. constructed on a 10-foot drilled sha foundation) and two station piers (approximately 25 square feet Alternative locations for the Pearl Highlands each) being placed close to the OHWM of Waiawa Station and park-and-ride lot were identi ed at Springs located beneath the station structure. Leeward Community College and the Hawai‘i e impact area and ll for these columns are Laborers Training Program site. Both of these sites included in Table 4-30 because of their proximity were evaluated in Section 5.4.2 of the Dra EIS to the springs. e location of the Pearl Highlands that addressed avoidance alternatives to potential Station is designed to be in close proximity to the impacts to the historic Solmirin House (since proposed park-and-ride lot as well as surrounding publication of the Dra EIS, the Solmirin House businesses. e piers near the Pearl Highlands Sta- was determined to be not eligible for designation tion cannot be relocated because they are support- as a historic resource). Locating the park-and-ride ing the guideway as it enters the station, as well as facilities at either of the two avoidance alternative supporting a concourse, stairs, and escalators. sites would cost substantially more and provide less e cient transportation circulation, as access would e springs (Site 13) in this case is at the end of a be less direct. For these reasons, these avoidance street drain passing under Kamehameha Highway. alternatives are not considered feasible. It would best be modi ed by constructing an extension of the existing pipe culvert to a point e construction of the high occupancy vehicle beyond the elevated station footprint. is new (HOV) ramp that will connect inbound H-2 “outlet” would be located closer to Waiawa Stream Freeway vehicles with the park-and-ride structure where the TOB line and OHWM closely coincide adjacent to the Pearl Highlands Station will result along an erosion face created by the piers of the in four columns being constructed close to Waiawa Farrington Highway bridge forcing the stream ow June 2010 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement 4-161
  • 9. to the right (thus eroding the le bank). Extending feet each on 10-foot drilled sha foundations) will the drain’s outlet would have no consequences on need to be constructed in the estuary (Figure 4-68). spring-water contribution to Waiawa Stream and is location (Site 27) is makai of the H-1 Freeway would reduce potential stream contamination in ramp to Nimitz Highway. In this area, there an area that would be too shaded by the station exists multiple bridge crossings of Moanalua structure to support plant growth. A cut in the Stream, including Kamehameha Highway, the high bank already exists where the spring ow H-1 Freeway, Nimitz Highway ramps, and two joins Waiawa Stream. pedestrian bridges makai of the project guideway crossing. e guideway columns will be aligned Approximately 5 acres near Waiawa Stream with the upstream viaduct piers, as feasible, to between Kamehameha Highway and Farrington minimize obstruction of stream ow. is area Highway will be shaded by structures (a park- is tidal and near the stream mouth at Ke‘ehi and-ride parking structure, bus transit center, Lagoon. Placement of the piers is not expected to station and guideway, and various pedestrian and have any consequences on the Moanalua Stream vehicle access ramps), roughly one-third of the estuarine environment or its fauna beyond a loss area (Sites 12 and 13). Direct impacts on the stream of 0.004 acre of sandy mud bottom. Because the (including shading) would be minimal; most of guideway lies immediately south of the existing the structures are on the north side of the stream. viaducts and will be elevated 50 feet above the Waiawa Stream supports some native amphidro- water, shading on the estuary will be minimal. mous fauna, and no part of the Project is antici- pated to interfere with the local population of goby Kapālama Canal Stream observed or migration through the site required by e existing Dillingham Boulevard bridge over native macrofauna that may breed upstream. Kapālama Canal Stream will be widened makai. is will allow for construction of a new median To maintain oodway hydrology, it will be neces- in line with the guideway to maintain two through sary to remove ll material from along Waiawa lanes and one dedicated le -turn lane for both Stream in this area. Approximately 100 feet of the directions of tra c. is will improve safety and small tributary issuing from an existing drain enhance tra c ow. ere will be impacts to (Site 13) will be con ned within an extension of Kapālama Canal Stream to extend the existing that drain pipe. piers and abutments. Moanalua Stream A design option was evaluated at this stream To avoid impacts below OHWM in Moanalua crossing to avoid impacts below OHWM that Stream (300 feet wide) substantially di erent considered construction of the guideway on bridge types would be needed to clear span this straddle bents located on each bank of the stream. stream. is stream is beyond the practical length e straddle bents would have been approximately limit for precast concrete girders (150 feet). Long 100 feet long to completely straddle Dillingham spans could add $5 million to total project costs. Boulevard. is option was not considered feasible For this reason, avoiding impacts below OHWM in for the following reasons: these streams is not considered feasible. • Construction of massive straddle bents would be di cult in this congested corridor Because of the 300-foot width of the channel • e large straddle bents would require large where the guideway crosses Moanalua Stream, and expensive drilled sha foundations two guideway columns (approximately 36 square 4-162 CHAPTER 4 – Environmental Analysis, Consequences, and Mitigation
  • 10. • Overhead power lines would complicate located outside of Kapālama Canal behind the construction existing bridge abutments, the Dillingham Boule- • e size of the straddle bents would have a vard Bridge will need to be widened approximately considerable visual impact in this area 20 feet makai to accommodate a new median. In- water work will involve extending the four existing e Project crosses Kapālama Canal Stream at the bridge piers and the two existing bridge abutments Dillingham Boulevard Bridge with the guideway in makai. Pier extensions will require eight addi- the median of the Boulevard (Site 29; Figure 4-69). tional piles placed in the stream (approximately Although the guideway support columns will be 1.36 square feet each). e abutment and retaining LEGEND The Project Fixed Guideway Station Columns in Waters of the U.S. Columns near Streams 0 500 1000 Feet Middle Street Transit Center Moanalu Nim itz Hw y a Stream am re St hi li Ka HONOLULU HARBOR Figure 4-68 Moanalua Stream June 2010 Honolulu High-Capacity Transit Corridor Project Environmental Impact Statement 4-163