Electronic Product Sale
   Logging System
       Smith’s Pharmacy
     Victor Amaya, Chris McCoy and Robert Berus
                 October 25, 2007
Table of Contents
1. EXECUTIVE SUMMARY.....................................................................................................................................1

   1.1. PURPOSE...............................................................................................................................................................1
   1.2. BACKGROUND..........................................................................................................................................................1
   1.3. INDUSTRY..............................................................................................................................................................1
   1.4. VISION..................................................................................................................................................................1
   1.5. SCOPE..................................................................................................................................................................2

2. PROJECT CHARTER...........................................................................................................................................3

   2.1. PROJECT OBJECTIVES..................................................................................................................................................3
   2.2. PROJECT CONCEPTION................................................................................................................................................3
   2.3. PROBLEM STATEMENT................................................................................................................................................3
   2.4. FINANCIAL RISK ANALYSIS............................................................................................................................................4
   2.5. INITIAL SCOPE OF THE PROJECT.......................................................................................................................................4
   2.6. PROJECT VISION.......................................................................................................................................................4
   2.7. BUSINESS CONSTRAINTS..............................................................................................................................................4
   2.8. TECHNOLOGY CONSTRAINTS..........................................................................................................................................5
   2.9. PROJECT STRATEGY....................................................................................................................................................5
   2.10. PROJECT DOCUMENTATION AND COMMUNICATION..............................................................................................................5
   2.11. PROJECT ORGANIZATION AND STAFFING APPROACH.............................................................................................................5

3. PROJECT VALUE STATEMENT...........................................................................................................................6

   3.1. BACKGROUND .........................................................................................................................................................6
   3.2. VALUES.................................................................................................................................................................6

4. PROJECT STRATEGY STATEMENT.....................................................................................................................7

   4.1. METHODOLOGY OVERVIEW..........................................................................................................................................7
   4.2. MEETING FREQUENCY................................................................................................................................................7
      4.2.1. A-Team Project Development Meetings......................................................................................................7
      4.2.2. Smith’s Pharmacy Client Update Meetings.................................................................................................7

5. SYSTEM PROJECT METHODOLOGY...................................................................................................................8

   5.1. ELECTRONIC PRODUCT SALE LOGGING SYSTEM PROJECT METHODOLOGY......................................................................................8
      5.1.1. Requirements...............................................................................................................................................8
      5.1.2. Design...........................................................................................................................................................9
      5.1.3. Implementation............................................................................................................................................9
      5.1.4. Verification...................................................................................................................................................9
      5.1.5. Maintenance..............................................................................................................................................10

6. GENERAL SYSTEM ANALYSIS..........................................................................................................................11

   6.1. CONTEXT MODEL...................................................................................................................................................11
   6.2. EVENT LIST...........................................................................................................................................................12


                                                                                                                                                                   Page | i
6.3. EVENT DICTIONARY..................................................................................................................................................12

7. BUSINESS REQUIREMENTS AND RULES..........................................................................................................14

8. TECHNICAL REQUIREMENTS AND ASSUMPTIONS...........................................................................................22

   8.1. EXISTING LAN AND WAN.......................................................................................................................................22
      8.1.1. Network Operating System and Client PC Configuration..........................................................................22
      8.1.2. WAN Infrastructure Overview....................................................................................................................23
      8.1.3. LAN Infrastructure Overview......................................................................................................................24
      8.1.4. IT Equipment Rack Diagram ......................................................................................................................25
   8.2. POINT OF SALE SYSTEM............................................................................................................................................26
   8.3. TECHNICAL SUPPORT................................................................................................................................................26

9. TECHNICAL PLATFORM AND TOOLS REQUIRED..............................................................................................27

   9.1. .NET FRAMEWORK 2.0............................................................................................................................................27
   9.2. VISUAL STUDIO 2005 ............................................................................................................................................27
   9.3. WINDOWS SERVER 2003.........................................................................................................................................27
   9.4. SQL SERVER 2005...............................................................................................................................................27
   9.5. CANDIDATE MATRIX................................................................................................................................................28

10. THIRD-PARTY NEEDS....................................................................................................................................29

   10.1. VENDORS...........................................................................................................................................................29
     10.1.1. Dell...........................................................................................................................................................29
     10.1.2. Microsoft..................................................................................................................................................29
     10.1.3. IBM...........................................................................................................................................................29
     10.1.4. Suppliers...................................................................................................................................................30
     10.1.5. Consultants..............................................................................................................................................30

11. DATABASE/ERD MODEL...............................................................................................................................31

12. DATA FLOW DIAGRAM................................................................................................................................32

13. SYSTEM ARCHITECTURAL DIAGRAMS...........................................................................................................33

14. PROJECT RISK AND RISK MANAGEMENT......................................................................................................34

   14.1. RISK MANAGEMENT PLANNING..................................................................................................................................34
   14.2. QUALITATIVE/QUANTITATIVE RISK ANALYSIS...................................................................................................................36
     14.2.1. Risk Response Planning............................................................................................................................36
     14.2.2. Monitoring and Control...........................................................................................................................36

15. PROJECT COSTS, STAFFING, RESOURCES, DEPENDENCIES AND SCHEDULE.....................................................37

   15.1. BENEFITS...........................................................................................................................................................37
   15.2. BILL OF MATERIALS...............................................................................................................................................38
   15.3. TRIPLE COST ANALYSIS...........................................................................................................................................39
   15.4. RETURN ON INVESTMENT ANALYSIS.............................................................................................................................40
   15.5. PROJECT SCHEDULE...............................................................................................................................................41
   PROJECT STAFFING........................................................................................................................................................42

16. INTEGRATION OF INTERNAL/EXTERNAL SYSTEMS........................................................................................43

Page | ii
17. SYSTEM ADMINISTRATION, SECURITY, BACKUP AND RECOVERY..................................................................44

   17.1. POLICY..............................................................................................................................................................44
   17.2. ACCOUNT MANAGEMENT........................................................................................................................................44
   17.3. ADMINISTRATIVE...................................................................................................................................................44
   17.4. BACKUP RECOVERY OF NETWORK SERVERS AND DATA.......................................................................................................45
   17.5. MICROSOFT SQL SERVER 2005 BACKUP.....................................................................................................................46
   17.6. COMPUTER VIRUS PREVENTION..................................................................................................................................47
   17.7. INCIDENT MANAGEMENT.........................................................................................................................................47
   17.8. INTERNET USE.....................................................................................................................................................47
   17.9. PASSWORDS........................................................................................................................................................47
   17.10. PHYSICAL ACCESS................................................................................................................................................47

18. REFERENCES................................................................................................................................................48




                                                                                                                                                               Page | iii
Table of Figures
FIGURE 1: FINANCIAL RISK ANALYSIS...................................................................................................................4

FIGURE 2: DEVELOPMENT METHODOLOGY OF THE APPLICATION OF THE ELECTRONIC PRODUCT SALE LOGGING
SYSTEM..............................................................................................................................................................8

FIGURE 3: CONTEXT MODEL..............................................................................................................................11

FIGURE 4: EXISTING WAN ARCHITECTURE..........................................................................................................23

FIGURE 5: EXISTING LAN/WAN ARCHITECTURE..................................................................................................24

FIGURE 6: RACK CONFIGURATION .....................................................................................................................25

FIGURE 7: POINT-OF-SALE ARCHITECTURE AND CONNECTIVITY..........................................................................26

FIGURE 8: CANDIDATE MATRIX..........................................................................................................................28

FIGURE 9: ENTITY-RELATIONSHIP DIAGRAM......................................................................................................31

FIGURE 10: DATA FLOW DIAGRAM....................................................................................................................32

FIGURE 11: PROPOSED SYSTEM ARCHITECTURE.................................................................................................33

FIGURE 12: ANNUAL COST AVOIDANCE.............................................................................................................37

FIGURE 13: BILL OF MATERIALS.........................................................................................................................38

FIGURE 14: LIFE CYCLE COSTS............................................................................................................................39

FIGURE 15: ROI ANALYSIS.................................................................................................................................40

FIGURE 16: PROJECT STAFFING..........................................................................................................................42

FIGURE 17: INTEGRATION OF INTERNAL AND EXTERNAL SYSTEMS AND SERVICES..............................................43

FIGURE 18: TAPE BACKUP ROTATION................................................................................................................45

FIGURE 19: EMC RETROSPECT CONFIGURATION................................................................................................46




Page | iv
1.     Executive Summary

1.1.        Purpose
This purpose of this project is to provide a technological solution to the problem of manual logbook
management of pseudoephedrine logging for a fictitious, small retail pharmacy chain located in the Ohio
Valley area called Smith’s Pharmacy. This solution will help to provide data and systems needed to track
across state lines while providing reporting capabilities and compliance with Federal regulations.

1.2.        Background
Smith’s Pharmacy is a four-store retail chain located in the Ohio Valley area. The company operates
stores in Cumberland, Maryland, Wheeling, West Virginia (where the management office and computer
systems are also located), Washington, Pennsylvania and St. Clairsville, Ohio. These stores provide a
business model based on traditional brick and mortar retail pharmacy, similar to those of its
competitors, CVS Pharmacy, Rite Aid and Kroger. A more recent focus for Smith’s has been its log
keeping activities related to sales of products impact by Pseudoephedrine legislation. Currently, Smith’s
maintains its Pseudoephedrine logbooks manually, using a handwritten account of each sale. This is
required to maintain compliance with State regulations in its Ohio and West Virginia locations.
Specially, Smith’s must abide by statutes Ohio Revised Code, Section 2925.56 and WV 60A-10-5
governing requirements of controlled substances. Violations are severe. Both states impart a fine of
violations; Ohio enforces a maximum of $1,000 and West Virginia $10,000. In addition, Ohio’s statues
call for a jail sentence not to exceed 180 days.

1.3.         Industry
Smith’s is a regional, small retail pharmacy chain. Its competitors include larger brick and mortar retail
chains such as CVS and Kroger and mail order. Mail order is particularly troublesome for Smith’s in
particular and the retail industry in general, because it allows consumers to obtain a 90-day prescription
supply instead of one 30-day supply for each co pay. Since Smith’s is much smaller than these national
chains and mail order pharmacies, gaining a competitive advantage in the marketplace is critical to its
continued growth and success. For this project, the automation of the logbook function will provide an
increase in productivity and customer satisfaction by reducing wait times in pharmacy lines. Keeping
compliance is also critical to the continued success of the business by streamlining the audit processes
and eliminating financial risks from non-compliance.

1.4.        Vision
We envision a complete change in the way Smith’s tracks sales of pseudoephedrine-legislated items.
Our solution will eliminate the current system of manual logging and each of the four stores will
participate in an online-networked solution for tracking pseudoephedrine sales using an online logbook
application that is auditable from a central data source.
1.5.        Scope
The scope of this project will include the following:

    1. Design of a centralized database in the Wheeling, West Virginia office to serve as the repository
       for pseudoephedrine sales data.
    2. Expand the existing WAN network infrastructure to support the new system.
    3. Design of an application for each retail location that will collect pseudoephedrine sales data at
       point of sale and provide a management reporting capability.
    4. Project planning for implementation of the new information system.
    5. End user training plan.
2.        Project Charter

2.1.         Project Objectives
•    Create a unified infrastructure across the Smith’s retail pharmacy chain to track Pseudoephedrine
     sales by replacing manual logbook tracking measures with an automated system.
•    Increase Smith’s regulatory compliance capability by eliminating errors caused by manual log
     keeping.
•    Increase productivity for the business by reducing customer wait times related to the existing
     manual logging procedure.

2.2.         Project Conception
The A-Team Consultants envision a system for Smith’s pharmacy that will allow the organization to solve
the problems of manual logbook tracking the sale of products containing pseudoephedrine, ephedrine
or phenylpropanolamine by creating a scalable, automated system to replace the manual logbook with a
high-tech, online solution. This solution can be used by pharmacists in each of Smith’s four locations to
determine of sale of these products to an individual customer is within compliance of Federal and local
regulations. If the company decides to open additional stores in other locations, it can quickly
implement the system into the existing technology infrastructure.

2.3.         Problem Statement
Smith’s retail pharmacy stores must record identities of people who purchase over-the-counter
pseudoephedrine products as a deterrent to methamphetamine manufacturing. Currently, Smith’s
Pharmacy tracks this activity on a handwritten log, which presents the following issues

     1. They are handwriting information.
     2. They are duplicating information (multiple purchases by the same person).
     3. They are not meeting privacy requirements because they log multiple sales on one page.
     4. They are unable to enforce the intent of the law because they have no immediate, ad-hoc
        reporting capabilities at the time of sale, particularly across several locations.
     5. They are at financial risk from fines because of 3 and 4.

A solution is needed to replace the traditional logbook in order to provide longer-term (e.g., monthly,
quarterly) reporting functionality across multiple locations and assure these stores meet compliance to
avoid potential legal penalties.
2.4.        Financial Risk Analysis
                   Estimated Financial Exposure, St. Clairsville, Ohio, Location
                              Based on Smith's Pharmacy FY2007 Sales Data
              Revenue, Total Store                                              $811,000
              Revenue, Impacted Products                                          $9,780
              Average Sale Price, Per Product                                        $25
              Transactions, Per Year                                                $391
              Estimated Non-Compliance Rate                                           5%
              Non-Compliant Transactions                                             $20
              Fine, Per Incident                                                 $10,000
              Net Impact, Annual                                                $200,000
              Impact, % to Total Revenue                                           24.6%

                                      Figure 1: Financial Risk Analysis


2.5.        Initial Scope of the project
This project will implement an automated logbook system to track for Smith’s current chain of four retail
locations in the greater Ohio Valley area. We will develop a system to track information from each
location in a database located at the company’s central site in Store #1, located in Wheeling, West
Virginia. The other three stores – located in Cumberland, Maryland, St. Clairsville, Ohio, and
Washington, Pennsylvania – will have the same tracking application installed in each store. These
systems will interface with the central database in Wheeling using the company’s existing network
infrastructure.

2.6.        Project Vision
A-Team Consultants envisions a solution for Smith’s Pharmacy that will provide an automated tracking
of pseudoephedrine sales data with a centrally managed database, and management reporting
capability. The conversion from manual logs in each site to a single unified online system will provide a
means to track pseudoephedrine sales across the chain of stores. The system should include a point of
sale entry capability as well as a reporting module to provide statistical information regarding sales and
compliance.

2.7.        Business Constraints
•   Training schedule may require additional overtime hours for employees.
•   Implementation may require additional pre-deployment testing.
•   Up front budget costs of Development, Systems Implementation (including all necessary
    equipment), and Training may influence profitability until ROI is achieved.
•   Willingness or resistance of employees to adapt to the new system might affect initial success of the
    new system.
2.8.        Technology Constraints
•   Budget will be a consideration in terms of the quality and speed of the equipment.
•   Faster computer equipment comes at a higher cost.
    o Information Security Solutions are often expensive.
    o Budget for database and application development and testing is needed.
    o Time required to build the database and applications must be considered.
•   Time to test the new system will be needed to ensure stability and reliability.
•   Implementation of high security measures for the information systems is critical to keep data private
    and maintain regulatory compliance.

2.9.        Project Strategy
•   Expand existing network infrastructure to house new technology components.
•   Build Database Application to include the following:
            o User Interface Data Input Screen
            o Output Data (Purchase Approval Screen)
            o Database Reporting Screens
•   Test Application across WAN infrastructure at all four locations.
•   Go-Live on approved/agreed date.

2.10.       Project Documentation and Communication
We will document the project via a comprehensive project implementation plan. This plan will outline
the details of the development and implementation of the new pseudoephedrine online tracking
system. Communication throughout the life of the project will be in writing or in person between A-
Team consultants and the client, Smith’s Pharmacy. A-Team will meet with the client once per week to
provide progress status updates for the implementation. A-Team will also hold its own meetings once
per week to verify progress.

2.11.       Project Organization and Staffing Approach
A-Team Consultants will work closely with members of the Smith’s management team to identify
business requirements related to the project, and to ensure that the project’s technical solution aligns
well with Smith’s strategic business goals. A-Team’s three-member team owns expertise in the fields of
Project Management, Network Engineering and Health Information Systems. The project team for A-
Team will consist of a project manager and 2 technical consultants. The Smith’s management team will
provide two subject matter experts to assist in ensuring that all technical initiatives meet compliance
with local, state and federal regulations. We will provide training on the new system to all store
managers, cashiers, pharmacists and pharmacy technicians.
3.     Project Value Statement

3.1.        Background
Smith’s Pharmacy has continued to develop a loyal base of customers in Ohio Valley. There is great
potential to grow this business in terms of both local customer base and new retail locations, provided
the company utilizes the automated and centralized logbook solution. With potential expansion further
into the surrounding areas it serves, a project of this nature holds great possibilities for creating a local
competitive edge and greater competition with larger retailers such as CVS and Rite Aid. The value
provided by the Smith’s chain is at great risk if it violates any local, state or federal laws regarding these
products. Violations could negatively affect operations, placing the health of its customers at risk.

3.2.        Values
•    Increase logbook compliance through database automation.
•    Increase customer satisfaction through reduced customer wait times.
•    Decrease likelihood of fines and penalties through advanced reporting capability.
•    Help reduce illegal methamphetamine production in the region through better enforcement and
     accounting of pseudoephedrine sales within legal limits.
•    Provide better store expansion capability through system scalability.
4.        Project Strategy Statement

4.1.         Methodology Overview
A-Team consultants will utilize the Waterfall project development model to complete the Electronic
Product Sale Logging System project for Smith’s Pharmacy. Noting the original methodology as
developed by W.W. Royce, A-Team will follow the prescribed sequential methodology consisting of the
following phases as waterfall steps:

     1.   Requirements
     2.   Design
     3.   Implementation
     4.   Verification
     5.   Maintenance

A-Team will build the requirements phase of the development through information gathered from the
client and the business requirements as defined in the business requirements section. Because this
methodology incorporates a staged approach to systems development, it will provide a better structure
for the development of the Electronic Product Sale Logging System for our client. This method is
recommended for situations where the project has a clear objective and solution and resources need to
be conserved (CMS, 2005).

4.2.         Meeting Frequency

4.2.1.          A-Team Project Development Meetings
The A-Team Consultants will hold staff meetings regularly to review project updates and modifications
as necessary. We will conduct weekly project meetings to review milestones for development, testing,
and rollout schedule in a manner consistent with the aforementioned waterfall methodology.

4.2.2.          Smith’s Pharmacy Client Update Meetings
We will conduct weekly status meetings with the Smith’s Pharmacy management team, using the
client’s preferred meeting method. This may include web conferencing, conference calls or face to face
on site. Each meeting will review the project milestones and schedule to keep the project on track for
timely delivery of the new system. The project team will report any unanticipated project issues or
delays to Smith’s Pharmacy management immediately.
5.      System Project Methodology

5.1.         Electronic Product Sale Logging System Project Methodology
The Electronic Product Sale Logging System will use the Waterfall methodology to development of the
new systems through each phase of the project and system lifecycles. A-Team will follow the prescribed
sequential methodology consisting of five steps. The diagram below shows the standard Waterfall
methodology.




              Requirements




                             Design




                                      Implementation




                                                  Verification




                                                             Maintenance




       Figure 2: Development Methodology of the Application of the Electronic Product Sale Logging System


5.1.1.             Requirements
We will build a list of business requirements through close collaboration with Smith’s management
team.
5.1.2.           Design
Based on business requirements, we will compose logical and physical designs.

The project team will transform the company’s business requirements into a high-level business plan
from which we will create the logical plan. The following steps are required:

    1. Create Use Cases based on Business Requirements
    2. Create Data Flow Diagrams to show the flow of information through the model
    3. Create Data Model from which the physical database can be created

The technical plan for the project will transform business requirements into a physical design. We will
use these solutions for several critical design milestones:

    1. The design of the application, including the user interface
    2. The design of the database including all tables, schemas and structures
    3. Analysis of the existing network LAN/WAN infrastructure to verify data capacity requirements
    4. The integration of an additional application server running the database and application system
       software
    5. The project planning required for implementation of such solutions

5.1.3.           Implementation
Based on the final design and project scheduling, we will present a detailed plan for rollout of the
technologies for Smith’s Pharmacy management team. Once the management team has approved such
implementation, A-Team Consultants will complete a test of the entire system and all functionality prior
to rollout of the system for daily production. The goal of a successful implementation will be to
complete the rollout with minimal impact or interruption to business during the process.

5.1.4.           Verification
Critical to the success of the rollout for this system will be pre-production testing. The following items
are critical to the success of the verification phase:

    1.   Network capacity testing between all four sites
    2.   Network security testing
    3.   Application/Database testing using sample data files
    4.   Database Management Report Testing
5.1.5.          Maintenance
The solution will utilize regular maintenance windows for the following purposes:

1) Daily
   a) Database Backup to Tape
   b) System OS and Image backups to tape
   c) Ongoing break/fix maintenance as needed for all hardware, software and applications
2) Quarterly
   a) Application Upgrades
   b) Security Patches
   c) Regularly Scheduled Database Maintenance
   d) Network upgrades as required
6.     General System Analysis

6.1.       Context Model

                   Store Supervisor                                                  Seller
                                                                               (Clerkr/Phar macist )




                                                                                                       Printer
                                                        Manual Customer and
                                       Author ization     Seller Data Input
                                        Response

                                                                                                                    Bar Code Reader
                     Approval for
                   Purchase/Return
                       Request



                                                                                    Output Notice /Alert


                                                                                         Automatic Customer Data Input

                    Stor e & Receive                                                  Signature/
                      Product Info                                                 Complete Purchase
        Logbook
                                               Electronic Logbook                                                        Customer
        Database    Stor e & Receive
                                                                                    Purchase Request
                     Customer Info

                                                                                                Purchase Approval



                                                                                      Response




                                Maintenance/
                                                                                                                    State & Federal
                                  Updates                                                                             Regulators
                                                                    Updates/
                                                                    Upgrades




                                                                                              A-Team Consultants
                                                        Customer
                                                        Signature




                                                                              Signature Capture
                           IT Department
                                                                                     Pad


                                                Figure 3: Context Model
6.2.           Event list
    1.   Add/Update Customer information
    2.   Add/Remove Product
    3.   Process product returns
    4.   Calculate state and federal limitations of product sale and generate alerts/notices
    5.   Add/Remove Transaction information (date/time, location, clerk name, product name, quantity)
    6.   Product summary reports


6.3.           Event dictionary
Event Name:       Add/Update Customer to database
                  Event ID: 1
Description:      When a customer wants to purchase a product, the customer’s information must be
                  entered into the database.
Stimulus:         Customer wants to purchase a product
Activity:         • If user does not exist in the database, then add a record of that customer into the
                       database.
                  • If customer is purchasing a product, verify whether it is more or less than 60mg of
                       PSE. If it does not, no signature is required. If it is, generate a printable notice
                       warning.
                  • If Customer is returning a product, adjust transaction record in database.
Response:         User Added/Updated.
Effect:           If there are no alerts/notices, the customer is able to continue transaction

Event Name:       Add/Remove Product to database
                  Event ID: 2
Description:      When a customer wants to purchase a product, the product’s information must be
                  entered into the database.
Stimulus:         Customer wants to purchase a product
Activity:         • If the product does not exist in the database, then add a record for that product into
                       the database. Update product inventory.
                  • If customer is purchasing a product, verify that it is available from Product
                       Inventory. If it is available, verify the quantity being sold and update product
                       inventory.
                  • If Customer is returning a product, add new transaction and update product
                       inventory.
Response:         Product recorded.
Effect:           If there are no alerts/notices, the customer is able to purchase the product.
Event Name:    Add Process product returns
               Event ID: 3
Description:   After a customer has purchased a product, they can return it using this feature.
Stimulus:      Seller enters transaction number, name and address in return screen.
Activity:      The system verifies if the return is valid and requires approval of supervisor. If it is, then
               add new transaction and update inventory.
Response:      Return is processed.
Effect:        Adjusted Transaction/Product details

Event Name:    Calculate state and federal limitations of product sale and generate alerts/notices
               Event ID: 4
Description:   After a customer submits a purchase, this feature verifies if the purchase can complete.
Stimulus:      Seller inputs customer and product information on purchase screen.
Activity:      The system verifies the sale against federal and state regulations. If a violation occurs, a
               notice and warning is displayed in a message box. If not violation occurs, the purchase
               can be completed.
Response:      Purchase is processed.
Effect:        If there are no alerts/notices, the customer is able to purchase the product.

Event Name:    Add/Remove Transaction (date/time, location, seller name, product name, quantity)
                            Event ID: 5
Description:   When a customer purchases a product a transaction is recorded into the database.
Stimulus:      Customer submits purchase request
Activity:      •    Create a record in transaction table with date/time, location, product name and
                    quantity of sale and seller name.
               • If the customer is making a purchase, verify that customer is eligible and the
                    quantity is within state and federal limitations. If eligible record transaction details
                    in database
               • If customer is returning a product, mark returned item into transaction database.
Response:      If there are no alerts/notices, the customer is able to purchase the product.


Event Name:    Product summary reports
               Event ID: 6
Description:   Produces reports per query specified by seller, state or federal regulators.
Stimulus:      Seller or regulator enters query information into reporting screen.
Activity:      Return query results and display in web page for view. The results are adjusted so they
               are in print format.
Response:      Processed Query results.
7.     Business Requirements and Rules
       Use Case Name   1. Process Transaction
              Scenario Process new sale
      Triggering Event Customer attempts to purchase a controlled product
      Brief Description When the customer wishes to purchase a product controlled by
                        Methamphetamine law, the sale must be logged and validated
                        against sale restrictions.
                Actors • Store employee
     Related Use Cases
          Stakeholders • Customer wants to buy product.
                        • Pharmacist wants to sell product.
                        • Company wants to remain compliant with applicable laws
                        • Regulatory bodies want to control distribution of controlled
                            products
        Pre-conditions • Customer must exist in audit tool.
                        • Product, Product Category records must exist.
       Post-conditions • Transaction record must be created.
Use Case Name 1. Process Transaction (continued)
      Flow of Events               Actor                            System
                     1. Customer goes to pharmacy
                        counter to purchase desired
                        product.
                     2. Pharmacist identifies
                        product requested by
                        customer.
                     3. Pharmacist collects
                        government-issued (State or
                        Federal) identification from
                        customer.
                     4. Pharmacist initiates a new    4.1. P.O.S. begins a new
                        transaction in the existing        transaction journal entry.
                        P.O.S. system.
                     5. Pharmacist scans or           5.1. P.O.S. retrieves item details.
                        manually enters UPC for       5.2. Flag in P.O.S. controller
                        desired product.                   indicates transaction must
                                                           flow through real-time audit
                                                           process.
                     6. Pharmacist scans or           6.1. P.O.S. system passes
                        manually enters unique             Product and Customer
                        customer identifier from I.D.      parameters to audit
                                                           program for validation.
                                                      6.2. P.O.S. system adds line item
                                                           to transaction if audit
                                                           passes.
                     7. Pharmacist completes sale     7.1. P.O.S. logs transaction
                        per S.O.P.                         details to audit system.

Exception Conditions 3.1. If customer cannot provide proper identification, no transaction
                          is performed.
                     6.3. If customer does not exist, prompt Pharmacist for customer
                          demographic information.
                     6.4. If customer demographic information is not correct, Pharmacist
                          completes transaction per S.O.P, then invokes 2. Maintain
                          Customer.
                     7.1. If audit control program flags sale as invalid, P.O.S. system voids
                          line.
Use Case Name   2. Maintain Customer
            Scenario Update customer demographic data
    Triggering Event Customer demographic data needs updated.
    Brief Description When a customer’s demographic data needs updated, the
                      Pharmacist must update it via a web portal.
              Actors • Store employee
   Related Use Cases
        Stakeholders • Company wants to remain compliant with applicable laws
                      • Regulatory bodies want to control distribution of controlled
                         products
      Pre-conditions Customer must exist
     Post-conditions
      Flow of Events               Actor                             System
                      1. Pharmacist collects             1.
                         government-issued (State or
                         Federal) identification from
                         customer.
                      2. Pharmacist logs into web
                         portal
                      3. Pharmacist enters maintain
                         customer screen.
                      4. Pharmacist locates existing
                         customer record.
                      5. Pharmacist updates
                         necessary attributes.
                      6. Pharmacist saves updates.
Exception Conditions
Use Case Name     3. Add Product Category
            Scenario Create a new product category
    Triggering Event Legislative changes require new tracking method
    Brief Description Applicable laws require sellers to track the sales of certain products
                      specific ways and limit them specific quantities. Product Categories
                      allow the company to specify business rules that adhere to the
                      appropriate laws any particular location must meet.
              Actors • Company auditor
   Related Use Cases
        Stakeholders • Company wants to remain compliant with applicable laws
                      • Regulatory bodies want to control distribution of controlled
                          products
      Pre-conditions
     Post-conditions Existing and new Products must be associated with the new Product
                      Category.
      Flow of Events                 Actor                              System
                      1. Auditor identifies the need
                          for a new Product Category.
                      2. Auditor identifies the
                          appropriate
                          constraints/business rules
                          for this Product Category.
                      3. Auditor logs into web portal.
                      4. Auditor enters add Product
                          Category screen.
                      5. Pharmacist enters necessary
                          attributes.
                      6. Pharmacist saves new              6.1. System creates a new
                          Product Category.                     Product Category record.
                                                                The new Product Category
                                                                is made available for use.
Exception Conditions
Use Case Name     4. Maintain Product Category
            Scenario Maintain an existing product category
    Triggering Event Legislative changes require modified tracking method
    Brief Description Applicable laws require sellers to track the sales of certain products
                      specific ways and limit them specific quantities. Product Categories
                      allow the company to specify business rules that adhere to the
                      appropriate laws any particular location must meet. This Use Case
                      also represents instances wherein a Product Category is no longer
                      legislated for controlled sales.
              Actors • Company auditor
   Related Use Cases
        Stakeholders • Company wants to remain compliant with applicable laws
                      • Regulatory bodies want to control distribution of controlled
                           products
      Pre-conditions
     Post-conditions Existing and new Products must be associated with the updated
                      Product Category.
      Flow of Events                  Actor                             System
                      1. Auditor identifies the need
                           to modify an existing
                           Product Category.
                      2. Auditor identifies the
                           appropriate
                           constraints/business rules
                           for this Product Category.
                      3. Auditor logs into web portal.
                      4. Auditor enters Maintain
                           Product Category screen.
                      5. Pharmacist modifies
                           necessary attributes.           6.1. System updates existing
                      6. Pharmacist saves updates.              Product Category record.
Exception Conditions
Use Case Name     5. Add Product
            Scenario Add a product to the audit program
    Triggering Event • Legislative changes require new tracking method
                      • New product received
                      • Correction
    Brief Description Applicable laws require sellers to track the sales of certain products
                      specific ways and limit them specific quantities. Product Categories
                      allow the company to specify business rules that adhere to the
                      appropriate laws any particular location must meet.
              Actors • Company auditor
   Related Use Cases
        Stakeholders • Company wants to remain compliant with applicable laws
                      • Regulatory bodies want to control distribution of controlled
                          products
      Pre-conditions Product Category must exist.
     Post-conditions
      Flow of Events                Actor                               System
                      1. Auditor identifies the need
                          for a new Product tracking.
                      2. Auditor identifies the
                          appropriate Product
                          Category.
                      3. Auditor logs into web portal.
                      4. Auditor enters add Product
                          screen.
                      5. Pharmacist assigns desired
                          Product Category.
                      6. Pharmacist saves new              6.1. System creates a new
                          Product.                              Product record.
Exception Conditions 5.1. If Product Category does not exist, user pauses this use case
                           and invokes 3. Add Product Category.
Use Case Name     6. Maintain Product
            Scenario Maintain an existing product
    Triggering Event • Legislative changes require modified tracking method
                      • Correction
    Brief Description Applicable laws require certain products to be tracked in specific
                      ways and limited to specific quantities of sales. Product Categories
                      allow the company to specify business rules that adhere to the
                      appropriate laws any particular location must meet.
              Actors • Company auditor
   Related Use Cases
        Stakeholders • Company wants to remain compliant with applicable laws
                      • Regulatory bodies want to control distribution of controlled
                          products
      Pre-conditions
     Post-conditions
      Flow of Events                 Actor                              System
                      1. Auditor identifies the need
                          to modify an existing
                          Product.
                      2. Auditor identifies the
                          appropriate changes.
                      3. Auditor logs into web portal.
                      4. Auditor enters Maintain
                          Product screen.
                      5. Pharmacist modifies
                          necessary attributes.
                      6. Pharmacist saves updates.        6.1. System updates existing
                                                               Product record.
Exception Conditions 1.1. If product has had ingredient changes necessitating change, the
                           Product Specialist should inactive the existing item code in the
                           company’s P.O.S. system, a new item number created and the
                           U.P.C. linked to the new product. Then, a new Product record
                           should be created via the 5. Add Product Use Case.
Use Case Name      7. Generate Summary Reports
            Scenario    Report needed
    Triggering Event    Information needed
    Brief Description   Process to generate reports.
              Actors    • Company auditor, or
                        • Pharmacist, or
                        • Store Management
  Related Use Cases
       Stakeholders •        Company wants to remain compliant with applicable laws
                    •        Regulatory bodies want to control distribution of controlled
                             products
      Pre-conditions
     Post-conditions
      Flow of Events                   Actor                             System
                        1.   User identifies the desired
                             report.
                        2.   User logs into web portal.
                        3.   User enters Reports screen.
                        4.   User selects appropriate       4.1. System queries database,
                             report and enters necessary         assembles report and
                             criteria.                           displays in web browser.
                        5.   User views report.
Exception Conditions
8.     Technical Requirements and Assumptions
Smith’s Pharmacy currently owns a networked point-of-sale (POS) sales entry system. The company
purchased the system from IBM to improve the checkout process for the organization. A 100Mb LAN
connects the POS systems within each of the four locations and a WAN provides e-mail connectivity and
internet access across a secured MPLS network from the centralized firewall located in the Wheeling
store. A more detailed description of the existing network is provided in the next section.

8.1.       Existing LAN and WAN

8.1.1.         Network Operating System and Client PC Configuration
Smith’s Pharmacy uses a small Microsoft Windows Active Directory (AD) Domain running on Windows
2003 Server. This server also provides DNS support required for connectivity of the AD domain, clients
and the Microsoft Exchange e-mail server. Clients (Management PC’s) are configured with the Windows
XP operating system running Service Pack 2; Microsoft Outlook 2003 is used for e-mail, contact and
schedule management.
8.1.2.          WAN Infrastructure Overview
Smith’s Pharmacy utilizes a Sprint Multiprotocol Label Switching Wide Area Network (MPLS) consisting
of dual T1 connections to each store. The Wheeling store hosts the e-mail server and serves as a central
proxy point for Internet Web Browsing. All web browser requests traverse the MPLS to the Wheeling
Store where a Checkpoint FW-1 firewall running on a Dell 1850 1U rack-mount server handles packet-
forwarding decisions. This firewall limits inbound access to HTTP (Web browsing) and SMTP (e-mail)
requests. E-mail traffic also traverses the same MPLS cloud for the remaining stores.

The MPLS WAN provides a controlled secure network environment and protects data traffic between
stores from compromise by unauthorized third parties. The diagram below contains a high-level view of
the overall WAN network connectivity. The POS System utilizes the LAN for connectivity to a central
POS controller in each store. The company utilizes the MPLS to manage all locations’ POS systems using
specialized management software.




                                   Figure 4: Existing WAN Architecture
8.1.3.          LAN Infrastructure Overview
The following diagram shows a more detailed view of Smith’s Pharmacy LAN architecture in each store
and the physical connectivity of the WAN routers. Note that this diagram also includes one additional
Dell server the company will need to purchase for the application and database implementation. This
diagram also includes a backup circuit for business continuity. A tape backup system using a single
internal mammoth two-tape drive on the Windows 2003 AD domain controller server running EMC
Retrospect backup software Data backups are handles data backup. The current daily full system
backup has approximately 70% available capacity on the existing tape drive to handle additional data.




                                 Figure 5: Existing LAN/WAN Architecture


Each site is connected to the MPLS via a Dual T1 (bundled) 3Mb connection. The backup (failover)
circuit is an ISDN 384k line, with a standard vendor agreement in place for a per-usage based charge. As
previously mentioned, the Wheeling site is the primary IT location for server support. Here, the e-mail
server handles all e-mail for the stores. A separate, dual T1 configuration handles the Internet Web
Browsing requests from all sites.
8.1.4.          IT Equipment Rack Diagram
This section shows each store’s rack configuration. The single rack configuration in each location
provides a simple effective solution that occupies minimal space in the computer room in the back of
the each store. An air conditioner cools the room to a constant temperature of 70 degrees Fahrenheit
to protect the IT equipment. A-Team consultants will utilize this existing infrastructure to support the
Electronic Product Sale Logging System. The MPLS as a means of cross-site communication will provide
a secure solution for transfer of the data from all sites to the database located in the Wheeling store.




                                      Figure 6: Rack Configuration
8.2.        Point of Sale System
Smith’s Pharmacy utilizes IBM’s ‘Sure POS 300 Series’ point of sale system. IBM describes the Model
300 system as a “cost effective solution to managing cash register transactions in each of its four
locations” (IBM, 2005). Each store’s POS system is capable of operating at the current 100Mbps LAN
speed. The systems are thick-client based PCs, running Windows XP Professional with Service Pack 2.
The POS terminals are connected to a POS Controller, which tracks transactions and inventory across the
LAN. Additionally, the company can remotely audit each controller using IBM’s remote management
software. IBM describes this system as having an “open platform with broad operating system support.”
This provides a user-friendly computing environment with scalability for future growth of the business.
As shown in the diagram below, management can audit all four locations across the MPLS WAN from
any other location. Each store location has four terminals in the front of the store checkout area and
one terminal to service the pharmacy counter.




                            Figure 7: Point-of-Sale Architecture and Connectivity


8.3.        Technical Support
Smith’s has existing technical support in place for the following systems:

    •   WAN – MPLS via Sprint, the MPLS service provider for the organization’s WAN.
    •   LAN – Sprint Business Services, including all Cisco LAN hardware, and PC’s:
        (Sprint, 2007)
    •   POS – Support contract with IBM on all IBM POS equipment
    •   Tape Backup – EMC provides technical support for Retrospect Software. Smith’s Pharmacy store
        management in the Wheeling Store handle the changing of daily backup tapes and are trained
        on the administration of the Tape backup software.
9.     Technical Platform and Tools Required

9.1.        .Net Framework 2.0
We will target Microsoft’s .NET Framework, version 2.0, to facilitate the development of the proposed
solution. The framework provides many precompiled software components that implement
functionality commonly used by developers, and many available programming languages. Amongst
these are user interface elements, web application features and database connectivity. Additionally, the
framework facilitates code-reuse and language interoperability, thereby streamlining development time,
future maintenance and testing requirements. Our primary advantage of targeting the .Net Framework
will allow us to reuse the data connectivity code between the web portal and the point-of-sale system.

9.2.        Visual Studio 2005
A-Team Consultants will use Microsoft’s Visual Studio 2005 to create the necessary interfaces for the
proposed solution. Visual Studio 2005 targets version 2.0 of Microsoft’s .Net Framework, streamlining
application development for a multitude of platforms. It provides support for database connectivity and
websites, allowing developers to create all content from one development environment.

9.3.        Windows Server 2003
We have selected Microsoft’s Windows Server 2003 operating system as the server platform for our
solution. It seamlessly integrates .NET Framework 2.0, provides security, reliability and performance
benefits and completes the unified system architecture desired for this project. Importantly, Windows
Server 2003 includes Internet Information Services 6, allowing the use of ASP.NET applications using
.NET Framework 2.0 developed with Visual Studio 2005. It provides a stable and secure host platform
for our database management system.

9.4.        SQL Server 2005
Microsoft’s SQL Server 2005 will provide the back-end data structures and decision logic systems for use
in the proposed solution. It provides a comprehensive, integrated data management and analysis
package that enables organizations to reliably manage mission-critical information and confidently run
today’s increasingly complex business applications. SQL Server 2005 provides scalable product offerings
to allow the organization to meet its needs in a cost effective manner. Also, it provides several
connectivity options for basic and advanced reporting and analysis features via third-party applications,
such as Microsoft’s Access 2007. Clearly, the use of .NET, Visual Studio, Windows Server 2003 and SQL
Server 2005 creates a complete and robust architecture that meets the needs of the organization.
9.5.       Candidate Matrix
       Characteristics      Candidate 1                Candidate 2                Candidate 3

   Portion of System     New Client/Server web      Same as Candidate 1.      Same as Candidate 1.
                         application logbook
   Computerized
                         system.

   Benefits              Web application would      Web application is        System would be fully
                         be independent of all      independent of current    integrated with current
                         current systems. All       systems. System           (or enhanced) systems.
                         technology is available.   framework is already in   Great Plains Solutions
                                                    place, needing only       Provider would manage
                                                    configuration and light   all technical requirement
                                                    visual enhancements.      and implementation.

   Servers and           Microsoft Windows          Microsoft Windows         Microsoft Windows 2003
                         2003 servers and IIS 6.    2003 servers and IIS 6.   servers and IIS 6.
   Workstations
                         Microsoft SQL Server       Oracle 9i.                Microsoft SQL Server
                         2000/2005.                                           2005.
                                                    Workstations use
                         Workstations use           Microsoft Windows         IBM POS systems
                         Microsoft Windows          2000/XP OS.               integration.
                         2000/XP OS.
                                                                              Workstations use
                                                                              Microsoft Windows 2000/
                                                                              XP OS.

   Software Tools        Microsoft Visual Studio    Microsoft Visual Studio   Microsoft Visual Studio
                         2005                       2005                      2005
   Needed
                         .Net Framework 2.0.        .Net Framework 2.0.       .Net Framework 2.0.

   Application           Custom solution built      Custom solution built     Custom solution built by
                         by IBM products            by Oracle Business        the Microsoft products
   Software
                         integrated into current    Suite products            integrated into current
                         IBM POS system.            integrated into current   IBM POS system.
                                                    IBM POS system.

   Method of Data        Client/Server.             Same as Candidate 1.      Same as Candidate 1.
   Processing

   Output Devices        Laser and Bar Code         Same as Candidate 1.      Same as Candidate 1.
                         printers.
   and Implications

   Input Devices and     Keyboard, mouse and        Same as Candidate 1.      Same as Candidate 1.
                         bar code reader.
   Implications

   Storage Devices       Microsoft SQL Server       Oracle 9i DBMS with 10    Same as Candidate 1.
                         DBMS with 10 GB            GB storage.
   and Implications
                         storage.

                                     Figure 8: Candidate Matrix
10. Third-Party Needs
A-Team focuses on delivering a complete range of cost-effective services tending to our customer’s
requirements. We provide support prior and post sale support through comprehensive after sale
maintenance and support to ensure our client’s investment. A-Team undertakes all software planning
and development in-house to maintain the privacy and integrity of our customers. A-Team does not
associate with external partners, suppliers or consults.

Smith’s Pharmacy has presented its current systems in place to our team; therefore, A-Team will focus
on tailoring software requirements to meet those specifications. Smith’s Pharmacy will need to acquire
additional hardware and software for the implementation of the logbook application.

10.1.       Vendors

10.1.1.         Dell
Dell Inc. (Dell) designs, develops, manufactures, markets, sells and supports a range of computer
systems and services that are customized to customer requirements (Reuters, 2007). These include
enterprise systems (servers, storage, workstations and networking products), client systems (notebook
and desktop computer systems), printing and imaging systems, software and peripherals, and global
services. The Company markets and sells its products and services directly to its customers, which
include corporate, government, healthcare and education accounts, as well as small-to-medium
businesses and individual customers.

10.1.2.         Microsoft
Microsoft Corporation develops, manufactures, licenses and supports a range of software products for
computing devices (Reuters, 2007). The Company's software products include operating systems for
servers, personal computers (PCs) and intelligent devices, server applications for distributed computing
environments, information worker productivity applications, business solution applications, high-
performance computing applications and software development tools. The Company has five segments:
Client, Server and Tools, the Online Services Business, the Microsoft Business Division, and the
Entertainment and Devices Division. The type of licensing for Microsoft Windows Server 2003 and SQL
Server 2005 will need to be identified and purchased depending on the needs for the logbook
application

10.1.3.         IBM
International Business Machines Corporation (IBM) is an information technology company. IBM also
provides business, technology and consulting services. The Company's major operations comprise a
Global Services segment, a Systems and Technology Group, a Software segment and a Global Financing
segment. (Reuters, 2007) IBM offers five kinds of software solutions. The Company's software offerings
include Information Management Software, an advanced database and content management software
solutions that enable clients to leverage information on demand; Lotus Software, a collaboration and
messaging software that allows businesses to communicate, collaborate and increase productivity;
Rational Software, an integrated tools designed to improve an organization's software development
processes and capabilities; Tivoli Software, a software for infrastructure management, including
security, change, configuration, job scheduling, storage capability, performance and availability, and
Websphere Software, which provides management of a range of business processes using open
standards to interconnect applications, data and operating systems.

IBM provides a range of services, which includes Business Performance Services (BPS), Business
Transformation Outsourcing (BTO), Consulting and Systems Integration (C&SI), Strategic Outsourcing
Services (SO), Integrated Technology Services (ITS), Application Management Services and Applications
on Demand (AoD). BTO delivers improved business results to clients through the strategic change and
the operation and transformation of the client's business processes, applications and infrastructure. ITS
provides service offerings that help clients access, manage and support their technology infrastructures,
through a combination of resources, software and IBM's knowledge of business processes. C&SI
provides consulting services for client relationship management, financial management, human capital,
business strategy and change and supply chain management, as well as application innovation and the
transformation of business processes and operations.

10.1.4.         Suppliers
No additional will be needed.

10.1.5.         Consultants
No additional will be needed.
11. Database/ERD Model
                                                                       ProductCategories
                                                            PK     ProductCategoryId      COUNTER

                                                                   Description            CHAR(50)
                                                                   State                  CHAR(2)
                                                                   TrackSales             BIT
                                                                   SizeLimit              DOUBLE


                   Customers                                               assigned to

        PK   CustomerId        COUNTER
                                                                            Products
             StateId           CHAR(10)
             State             CHAR(2)                      PK     ProductId               COUNTER
             StreetAddress 1   CHAR(50)
             StreetAddress 2   CHAR(50)                         UPC                        CHAR(18)
             City              CHAR(30)                     FK1 ProductCategoryId          LONG
             PostalCode        CHAR(10)                         Size                       DOUBLE


                                                                               sold on


                                                                          Transactions

                                                              PK     TransactionId       CHAR(24)
                          makes
                                                                  Timestamp              DATETIME
                                                              FK2 CustomerId             LONG
                                                              FK1 ProductId              LONG
                                                                  QtySold                LONG
                                                                  Voided                 BIT



                                  Figure 9: Entity-Relationship Diagram
12. Data Flow Diagram

                                            Changes required        2.
      Pharmacist                                                 Maintain
                                               Update Ok         Customer
   Process Transaction




                         Sale Ok Response




                                                                Customers
        1.
     Process
   Transaction                                                                                                    Products



                                                                 Product
                                                                Categories                                 4.
                                                                                                       Add/update
                                                                                                        Product




                                                                                                       Changes required
   Transactions




                                                                                                                          Update Ok

                                                                    3.              Changes required
                                                                Add/update                                      Company
                                                                 Product                                         auditor
                                                                 Category                 Update Ok



                                                           Figure 10: Data Flow Diagram
13. System Architectural Diagrams
The Electronic Product Sale Logging System will tie into the existing IBM POS System. The diagram
below shows a high-level view of the overall system.




                               Figure 11: Proposed System Architecture

As indicated in the diagram, the POS Controllers will interface with the new database application to
provide a real-time ephedrine logging process, which will initiate from the POS terminal. The
transaction process will be coordinated between the POS controller and the database to provide
approvals, log transactions and track customer specific purchase information to maintain compliance
with regulatory officials. Management can use its existing PCs to generate reports via the POS
controllers, which will pull data from the database server in Wheeling.
14. Project Risk and Risk Management
A-Team strives to integrate consistent practical risk management and loss management standards of the
highest quality into all our business processes. We firmly believe in our ability to develop strategies to
manage and mitigate risk if in case it should arise. The following, are the processes to manage project
risks:

    •   Risk Management Planning
    •   Risk Identification
    •   Qualitative/Quantitative Risk Analysis
    •   Risk Response Planning
    •   Monitoring and Control

The purpose of these processes is to influence the probability and impact of risks.

14.1.       Risk Management Planning
We have identified possible risks associated with the Electronic Logbook Application and prioritized
them whereby the risks with the greatest loss and the greatest probability of occurring are tended to
first and risks with a lower probability of occurrence are tended to in descending order.
Risk            Environmental          Impact       Probability              Risk Response
 component             Variable

Scheduling and   Unrealistic project      Moderate         High       Implement Further Actions to Reduce
Budget Risks     schedule delays                                      Risk; Continue Existing Controls;
                                                                      Generate Contingency Plan; Review at
                                                                      least every 3 Months

                 Unrealistic project      Significant      High       Take Immediate Further Remedial
                 budget overrun                                       Action to Reduce Risk; Contingency
                                                                      plan on standby; Review at least
                                                                      Monthly

                 Project canceled prior   Significant    Medium       Quickly Implement Further Actions to
                 to completion                                        Reduce Risk; Continue Existing
                                                                      Controls; Generate Contingency Plan;
                                                                      Review at least every 2 Months

System           Developing wrong user      Minor        Medium       Tolerate; Continue existing Simple
Functionality    interface                                            Control Measures; Review at least
Risks                                                                 every 6 Months

                 Develop wrong              Minor          Low        Tolerate; No action: Continue Control
                 software functions                                   if Required; review at least Annually

                 Real-time performance    Moderate       Very High    Quickly Implement Further Actions to
                 shortfalls                                           Reduce Risk; Continue Existing
                                                                      Controls; Generate Contingency Plan;
                                                                      Review at least every 2 Months

Requirements     Unmet user               Moderate         High       Implement Further Actions to Reduce
Management       requirements                                         Risk; Continue Existing Controls;
Risks                                                                 Generate Contingency Plan; Review at
                                                                      least every 3 Months

                 Gold Plating               Minor        Very Low     Tolerate; No action: Continue Control
                                                                      if Required; review at least Annually

                 Continuous               Significant    Very High    Take Immediate Further Remedial
                 requirement changes                                  Action to Reduce Risk; Contingency
                                                                      plan on standby; Review Continuously

Resource Usage   Hardware/Software          Minor        Very Low     Tolerate; No action: Continue Control
And              technology upgrades                                  if Required; review at least Annually
Performance
                 Straining computer       Moderate       Medium       Tolerate; Continue existing Control
Risks
                 science capabilities                                 Measures; Possible Contingency Plan;
                                                                      Review at least every 4 months

Personnel        Insufficient expertise   Significant      Low        Tolerate; Continue existing Control
Management       and expectations for                                 Measures; Possible Contingency Plan;
Risks            personnel                                            Review at least every 4 months

                 Personnel shortfalls     Significant      High       Take Immediate Further Remedial
                                                                      Action to Reduce Risk; Contingency
                                                                      plan on standby; Review at least
                                                                      Monthly

                 Project manager’s        Significant    Very Low     Tolerate; Continue existing Control
                 training/Experience                                  Measures; Possible Contingency Plan;
                                                                      Review at least every 4 months
* The Probability is identified as 'Very Low', 'Low', 'Medium', 'High' and 'Very High’. However, it must be considered that very
low probabilities may not be very reliable.

    Green - minor, no harm event or near miss, requires no follow-up
    Yellow - moderate event or near miss, requires local management action
    Red - significant event or near miss, requires senior management attention


14.2.         Qualitative/Quantitative Risk Analysis
Qualitative risk analysis is the cost-effective process of assessing the impact and likelihood of identified
risk. It prioritizes risks according to their potential effect on project objectives.

Quantitative risk analysis is the process of numerically rating the probability of each risk and its
consequence on project objectives.

14.2.1.            Risk Response Planning
This process employs a number of different techniques to reduce and mitigate risk on projects (Stoeller,
2003):

    •     Risk acceptance - project team decides not to change project plan and “accepts” the risk. Active
          acceptance includes developing a contingency plan. Passive acceptance leaves project team to
          deal with risk if it occurs.
    •     Risk avoidance - involves changing the project plan to eliminate the risk such that the risk no
          longer exists.
    •     Risk mitigation - involves a mix of techniques aimed at either reducing the probability or impact
          of a risk.
    •     Risk transfer - involves transfer of ownership of the risk to another party with the right skills that
          is available.
    •     Risk reserves are buffers in our schedules and budgets set aside for alligators or puppies.

14.2.2.            Monitoring and Control
This process monitors newly arising risks, and tracks existing risks and trigger conditions during the
project lifecycle. Project managers perform this process in order to determine:

    •     Determine if risk responses were implemented as planned.
    •     Determine if response actions are as effective as expected.
    •     Determine if project assumptions are still valid.
    •     Determine if risk exposure has changed.
    •     Determine if a risk trigger has occurred.
    •     Determine if an unidentified risk has occurred (Holtzman, 2004).
15. Project Costs, Staffing, Resources, Dependencies and
        Schedule
The Cost Analysis presents the costs for materials, design, development, testing, training,
implementation and maintenance for the system to be developed. It is expected that each team
member will work a 40 hour week.

For this release the expected budget is $35,555.12.

15.1.       Benefits
The primary projected benefit of the new system is the cost avoidance of the salaries of the pharmacy
staff currently doing this effort. The secondary benefit is the efficiency, speed and accuracy of the
reports. The system will provide the tracking reports on the first day of the new month rather than
inconsistent days into the month as prior. Accuracy in the data stored will vastly improve due to
elimination of most manual errors currently entered.

The primary benefit is the current cost to Smith’s of the personnel manually entering data. Per our
meetings and reports provided by Smith’s, it’s apparent that about 25% of an employee’s time is spent
manually entering data and trying to validate it in-case it isn’t legible. Therefore, we estimate that 75%
of the time for each of Smith’s locations would be available for other duties. We anticipate that the
proposed solution will eliminate approximately 20% of the current effort. Therefore, the annual cost
avoidance of each store will be equal to 20% of the annual cost of an employee’s salary.

    Annual Burdened Cost (BC)   Cost Avoidance Factor (CA)      # of Workers      Annual Cost Avoidance

            $70,000                       0.20                         10               $140,000


                                    Figure 12: Annual Cost Avoidance
15.2.         Bill of Materials
This section provides a bill of materials elements required for Smith’s Electronic Product Logging System.

     Component                                          Description                               Quantity    Price

Dell PowerEdge 1950       Dual Core Intel® Xeon® 5148LV, 4MB Cache, 2.33GHz, 1333MHz FSB,ES,             1   $3,537.37
Server                    Windows Server® 2003 R2, Standard Edition with SP2, Includes 5 CALs

Microsoft Windows         Server management operating system.                                            1      *Free
Server 2003

Microsoft Visual Studio   Development software for applications, websites, service, etc.                 1            $0
.Net 2005

Microsoft SQL Server      SQL Server Management Studio Express, for easily managing a database.          1       Free
2005 Express

Totals                                                                                                       $3,537.37

*Windows Server 2003 is included with Dell PowerEdge 1950 Server


                                              Figure 13: Bill of Materials
15.3.      Triple Cost Analysis
Three alternatives were considered for developing, designing and maintaining the new system. The
alternatives and their estimated present value costs for a year are as follows.

   •    Minimal Alternative - $26,068. This solution focuses on rapid project delivery date and minimal
        training costs.
   •    Recommended Alternative - $32,018. This solution focuses on the best project delivery
        schedule, minimal delays and interference with current work.
   •    Maximum Alternative - $55,959. This solution focuses on maximum benefits for the new system
        with an extended schedule life.

                                       Life Cycle Costs of Project Alternatives

                                                 Minimal         Recommended           Maximum
                                                Alternative       Alternative          Alternative
                   Define Requirements               $1,928               $2,689            $7,035

                   Designs Costs                      $4,459                $6,139        $10,400

                   Development Costs                  $8,660                $9,740        $12,640

                   Testing Costs                      $4,988                $5,698        $12,480

                   Training costs                     $1,768                $1,829         $4,440

                   Implementation Costs               $4,265                $5,924         $8,964

                   Warranty Costs                         $0                      $0           $0

                   Total Life Cycle Costs           $ 26,068               $32,018        $55,959


                                            Figure 14: Life Cycle Costs
15.4.         Return on Investment Analysis
                             Year 0            Year 1          Year 2          Year 3           Year 4             Year 5


         Initial Costs   $ (35,555.12)
         Maintenance                      $     (2,000.00) $   (2,200.00) $     (2,420.00) $     (2,662.00) $       (2,928.00)
   Discount Rate @ 14%             1.00              0.88            0.77            0.67              0.59                0.52
     Discounted Costs    $ (35,555.12) $        (1,754.39) $   (1,692.83) $     (1,633.43) $     (1,576.12) $       (1,520.71)
    Cumulative Costs     $ (35,555.12) $ (37,309.51) $ (39,002.33) $ (40,635.77) $ (42,211.88) $ (43,732.59)
     Benefit Revenue     $            -   $ 140,000.00      $ 145,600.00    $ 151,424.00    $ 157,481.00      $ 163,780.00
   Discount Rate @ 14%             1.00              0.88            0.77            0.67              0.59                0.52
   Discounted Benefits   $            -   $ 122,807.02      $ 112,034.47    $ 102,206.89    $    93,241.39    $    85,062.20
   Cumulative Benefits   $            -   $ 122,807.02      $ 234,841.49    $ 337,048.38    $ 430,289.77      $ 515,351.97
         Cost-Benefit    $ (35,555.12) $        85,497.51   $ 195,839.16    $ 296,412.61    $ 388,077.89      $ 471,619.38


        Payback Period         =              $35,555            /            $85,498           Payback             0.42
  Return-on-Investment         =              $471,619           /            $43,733            ROI              235.68%
    Net Present Value          =              $515,352           +            ($43,733)          NPV              $471,619
                                              Figure 15: ROI Analysis
15.5.      Project Schedule
1. Requirements                                     6.2.3.Update POS Terminals
   1.1. Document Requirements                       6.2.4.Perform Smoke Test
   1.2. Requirements Review                     6.3. Milestone: Installation Complete
   1.3. Approve Requirements                 7. Warranty Contingency
   1.4. Milestone: Requirements Defined      8. Milestone: Project Complete
2. Design
   2.1. Develop Design
   2.2. Design Review
   2.3. Approve Design
   2.4. Milestone: Completed Design
3. Development
   3.1. Develop Database Components
   3.2. Develop Web Components
   3.3. Develop POS Terminal Components
   3.4. Unit Testing
   3.5. Code Review
   3.6. Milestone: Development Complete
4. Testing
   4.1. Write Test Scripts
   4.2. Test Script Review
   4.3. Approve Test Scripts
   4.4. Milestone: Test Scripts Developed
   4.5. Setup Test Environment
   4.6. Perform Functional Testing
   4.7. Review Results
   4.8. Approve Results
   4.9. Milestone: Testing Complete
5. Training
   5.1. Reset Testing Environment
   5.2. Develop Training Plan
   5.3. Train Plan Review
   5.4. Approval Training Plan
   5.5. Milestone: Training Plan Document
   5.6. Perform Training
   5.7. Training Teachback
   5.8. Milestone: Training Complete
6. Implementation
   6.1. Hardware Installation
       6.1.1.Procurement
       6.1.2.Configuration
       6.1.3.Test
       6.1.4.Milestone: Hardware Installed
   6.2. Software Installation
       6.2.1.Install SQL Server 2005
       6.2.2.Install IIS
Project Staffing
     Position        No. of                            Duties                                Answers to
                    Positions

Smith’s                1        Monitor the overall operation and plan for future    Smith’s President
Management                      opportunities.

Pharmacist             1        Manage the day-to-day operations of the electronic   Smith’s Manager
                                logbook system.

Project Manager        1        Manage/Monitor the Information Systems needs of      A-Team Consultants
                                the operation.                                       Management

Software Engineer      1        Develop/Maintain system                              Project Manager

Systems Architect      1        Develop/Maintain system                              Project Manager

Network Engineer       1        Develop/Maintain system                              Project Manager

QA Tester              1        Test system                                          Project Manager

                                       Figure 16: Project Staffing
16. Integration of Internal/External Systems
The integration of the new Ephedrine product database with Smith’s existing IT infrastructure requires
some additional application programming to create a web services environment that will communicate
with the existing IBM 300 series POS system. The goal is to invoke the database application using the
existing POS so that the existing system is enhanced, not replaced.

The Electronic Product Sale Logging System will tie into an existing IBM POS300 Point of Sale System
currently in operation at Smith’s Pharmacy. The application system will be installed on each POS
controller to tie in with the existing POS software.

Based on the DBMS structures and stored procedures, a web server will connect to the DBMS to execute
the stored procedures. The website will expose some web services than the POS system will consume.
The POS system will send parameters to the web service and handle the response activity for the POS
terminal.




                    Figure 17: Integration of Internal and External Systems and Services
17. System Administration, Security, Backup and Recovery

17.1.       Policy
Smith’s Pharmacy secures its I.T. assets to protect corporate information and protect the privacy of such
information. With the integration of the new online logbook tracking system, the integrity of this secure
environment must be maintained. All networked computer and POS data is considered confidential and
property of Smith’s Pharmacy, Inc.

17.2.       Account Management
Internal accounts are maintained for e-mail and management of the POS system. Managers are
equipped with a laptop for management purposes. This laptop contains a Windows domain account,
which is maintained on an Active Directory domain server in Wheeling. In addition, each POS terminal
contains a logon capability for each cashier. All Cashiers (Including Pharmacists) have a user account
maintained in the domain controller for logon to the POS terminals.

17.3.       Administrative
To ensure all Administrative accounts with elevated access privileges on computers, network devices,
and other critical equipment (example: accounts used by system administrators and network managers)
are used only for their intended administrative purpose, all authorized Users must be made aware of the
responsibilities associated with the use of privileged special access accounts and comply with all
associated policies, standards, and /or procedures established by the company.
17.4.       Backup Recovery of Network Servers and Data
The Wheeling, West Virginia site has a small tape backup system consisting of a single tape drive
(installed within a single Dell 1850 rack mounted server). The tape drive’s daily data backup routine is
managed using an EMC product called “Retrospect.” This tape management software product is geared
toward small and medium sized business. As a part of the daily backup routine, store managers are
responsible for changing the data tapes. Tapes are rotated offsite in a 3-week rotation. A single week’s
tapes (five tapes), 2 weeks out of rotation are stored offsite with a local tape archive company in a
controlled environment to protect the physical integrity of the tape. These tapes may be recalled at any
time for any reason should the need arise to restore lost files.




                                     Figure 18: Tape Backup Rotation
The current backup system protects e-mail, files from the POS controllers and user account information
for the local area network. The new logbook system will require backup of database information stored
in the new Microsoft SQL database. The current capacity of the tape will support the additional data,
but as the size of the database grows, future consideration might be made to expand the tape backup
capability by adding an additional tape drive and expanding the terms of the contract for offsite storage
to accommodate the additional tapes. As shown in the diagram below, the Exchange e-mail server
mailboxes, POS controller data and network directories are backed up. The SQL database backup will be
added to the daily data backup prior to go-live for the new application.




                                 Figure 19: EMC Retrospect Configuration


17.5.       Microsoft SQL Server 2005 Backup
To provide a complete disaster recovery option for the new application, a proper backup of the
Microsoft SQL database must be performed. Microsoft’s specific recommendations for backup (and
restore) of the SQL 2005 database can be found at http://technet.microsoft.com/en-
us/library/ms187048.aspx and http://technet.microsoft.com/en-us/library/ms186289.aspx.
Pharma Info Sys
Pharma Info Sys

Weitere ähnliche Inhalte

Was ist angesagt?

Information security
Information securityInformation security
Information securityHai Nguyen
 
eXtropia goals vision strategy_jan_2003
eXtropia goals vision strategy_jan_2003eXtropia goals vision strategy_jan_2003
eXtropia goals vision strategy_jan_2003Eric Tachibana
 
Emergency planning independent study 235.b
Emergency planning  independent study 235.b  Emergency planning  independent study 235.b
Emergency planning independent study 235.b ronak56
 
Ebilling project report
Ebilling project reportEbilling project report
Ebilling project reportSrish Kumar
 
Operations manual for_owners_and_managers_multi-unit_residential_buildings
Operations manual for_owners_and_managers_multi-unit_residential_buildingsOperations manual for_owners_and_managers_multi-unit_residential_buildings
Operations manual for_owners_and_managers_multi-unit_residential_buildingsSherry Schluessel
 
Bhuma learning portal_ui
Bhuma learning portal_uiBhuma learning portal_ui
Bhuma learning portal_uiDebjani Roy
 
Analyzing Textiles Industry of India
Analyzing Textiles Industry of IndiaAnalyzing Textiles Industry of India
Analyzing Textiles Industry of IndiaDevanshu Singhal
 
2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania
2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania
2008 Annual Report Wasso Hospital, Ngorongoro, TanzaniaChristian van Rij
 
Z commerce-for-the-cloud-blueprint
Z commerce-for-the-cloud-blueprintZ commerce-for-the-cloud-blueprint
Z commerce-for-the-cloud-blueprintArief Wicaksono
 
Supplier-PPAP-Manual.pdf
Supplier-PPAP-Manual.pdfSupplier-PPAP-Manual.pdf
Supplier-PPAP-Manual.pdfPhanHngBin
 
Configuration-Release management
Configuration-Release managementConfiguration-Release management
Configuration-Release managementRavindranath Tagore
 
Business english-tests-sample
Business english-tests-sample Business english-tests-sample
Business english-tests-sample htangki
 
Best Practices for Acquiring IT as a Service
Best Practices for Acquiring IT as a ServiceBest Practices for Acquiring IT as a Service
Best Practices for Acquiring IT as a ServiceDaniel Checchia
 
Reinventing the City
Reinventing the CityReinventing the City
Reinventing the CityDean Pallen
 
Improving software testing efficiency using automation methods by thuravupala...
Improving software testing efficiency using automation methods by thuravupala...Improving software testing efficiency using automation methods by thuravupala...
Improving software testing efficiency using automation methods by thuravupala...Ravindranath Tagore
 

Was ist angesagt? (19)

Information security
Information securityInformation security
Information security
 
eXtropia goals vision strategy_jan_2003
eXtropia goals vision strategy_jan_2003eXtropia goals vision strategy_jan_2003
eXtropia goals vision strategy_jan_2003
 
Coinaid earth pilot
Coinaid earth pilotCoinaid earth pilot
Coinaid earth pilot
 
Emergency planning independent study 235.b
Emergency planning  independent study 235.b  Emergency planning  independent study 235.b
Emergency planning independent study 235.b
 
Ebilling project report
Ebilling project reportEbilling project report
Ebilling project report
 
Operations manual for_owners_and_managers_multi-unit_residential_buildings
Operations manual for_owners_and_managers_multi-unit_residential_buildingsOperations manual for_owners_and_managers_multi-unit_residential_buildings
Operations manual for_owners_and_managers_multi-unit_residential_buildings
 
Bhuma learning portal_ui
Bhuma learning portal_uiBhuma learning portal_ui
Bhuma learning portal_ui
 
Analyzing Textiles Industry of India
Analyzing Textiles Industry of IndiaAnalyzing Textiles Industry of India
Analyzing Textiles Industry of India
 
2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania
2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania
2008 Annual Report Wasso Hospital, Ngorongoro, Tanzania
 
Sdm Manual
Sdm ManualSdm Manual
Sdm Manual
 
Z commerce-for-the-cloud-blueprint
Z commerce-for-the-cloud-blueprintZ commerce-for-the-cloud-blueprint
Z commerce-for-the-cloud-blueprint
 
Supplier-PPAP-Manual.pdf
Supplier-PPAP-Manual.pdfSupplier-PPAP-Manual.pdf
Supplier-PPAP-Manual.pdf
 
Mirsal 2 manual BOE
Mirsal 2 manual BOEMirsal 2 manual BOE
Mirsal 2 manual BOE
 
Gate 2013
Gate 2013Gate 2013
Gate 2013
 
Configuration-Release management
Configuration-Release managementConfiguration-Release management
Configuration-Release management
 
Business english-tests-sample
Business english-tests-sample Business english-tests-sample
Business english-tests-sample
 
Best Practices for Acquiring IT as a Service
Best Practices for Acquiring IT as a ServiceBest Practices for Acquiring IT as a Service
Best Practices for Acquiring IT as a Service
 
Reinventing the City
Reinventing the CityReinventing the City
Reinventing the City
 
Improving software testing efficiency using automation methods by thuravupala...
Improving software testing efficiency using automation methods by thuravupala...Improving software testing efficiency using automation methods by thuravupala...
Improving software testing efficiency using automation methods by thuravupala...
 

Andere mochten auch

Pharmacy digital system
Pharmacy digital systemPharmacy digital system
Pharmacy digital systemjoyousone1104
 
Pharmaceuticals track and trace system
Pharmaceuticals track and trace systemPharmaceuticals track and trace system
Pharmaceuticals track and trace systemTechnarts
 
Pharmacy management
Pharmacy managementPharmacy management
Pharmacy managementRasel Khan
 
SAP Advanced Track and Trace
SAP Advanced Track and TraceSAP Advanced Track and Trace
SAP Advanced Track and TraceRyan Sonnenberg
 
Track and Trace Solution Details
Track and Trace Solution DetailsTrack and Trace Solution Details
Track and Trace Solution DetailsPropix Technologies
 
"Pharmacy system"
"Pharmacy system""Pharmacy system"
"Pharmacy system"vivek kct
 
Pharmacy management system Requirement Analysis and Elicitation Document
Pharmacy management system Requirement Analysis and Elicitation Document Pharmacy management system Requirement Analysis and Elicitation Document
Pharmacy management system Requirement Analysis and Elicitation Document Habitamu Asimare
 
Pharmacy Management System1
Pharmacy Management System1Pharmacy Management System1
Pharmacy Management System1Nuwan Lansakara
 

Andere mochten auch (10)

Pharmacy digital system
Pharmacy digital systemPharmacy digital system
Pharmacy digital system
 
Pharmaceuticals track and trace system
Pharmaceuticals track and trace systemPharmaceuticals track and trace system
Pharmaceuticals track and trace system
 
Pharmacy management
Pharmacy managementPharmacy management
Pharmacy management
 
SAP Advanced Track and Trace
SAP Advanced Track and TraceSAP Advanced Track and Trace
SAP Advanced Track and Trace
 
Track and Trace Solution Details
Track and Trace Solution DetailsTrack and Trace Solution Details
Track and Trace Solution Details
 
Case Study: Pharmaceutical Track And Trace System in Turkey
Case Study: Pharmaceutical Track And Trace System in TurkeyCase Study: Pharmaceutical Track And Trace System in Turkey
Case Study: Pharmaceutical Track And Trace System in Turkey
 
"Pharmacy system"
"Pharmacy system""Pharmacy system"
"Pharmacy system"
 
Pharmacy management system Requirement Analysis and Elicitation Document
Pharmacy management system Requirement Analysis and Elicitation Document Pharmacy management system Requirement Analysis and Elicitation Document
Pharmacy management system Requirement Analysis and Elicitation Document
 
Pharmacy Management System1
Pharmacy Management System1Pharmacy Management System1
Pharmacy Management System1
 
Hospital management system
Hospital management systemHospital management system
Hospital management system
 

Ähnlich wie Pharma Info Sys

Quality control report
Quality control reportQuality control report
Quality control reportNewGate India
 
100 toeic preparation_tests
100 toeic preparation_tests100 toeic preparation_tests
100 toeic preparation_testsMs Hoa TOEIC
 
100toeicpreparationtests
100toeicpreparationtests100toeicpreparationtests
100toeicpreparationtestsHương Maruco
 
100 toeic preparation tests
100 toeic preparation tests100 toeic preparation tests
100 toeic preparation testsdkhanhle
 
100 toeic preparation_tests_5976
100 toeic preparation_tests_5976100 toeic preparation_tests_5976
100 toeic preparation_tests_5976Phuong Trương
 
100toeicpreparationtests
100toeicpreparationtests100toeicpreparationtests
100toeicpreparationtestsTrinh Dinh
 
Ebilling project report
Ebilling project reportEbilling project report
Ebilling project reportShankarlal61
 
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...Endversion1 skriptum characterization of miscellaneous multi parametrical sil...
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...EjderCevher
 
WebIT2 Consultants Proposal
WebIT2 Consultants ProposalWebIT2 Consultants Proposal
WebIT2 Consultants ProposalSarah Killey
 
Gender livestock and livelihood indicators
Gender livestock and livelihood indicatorsGender livestock and livelihood indicators
Gender livestock and livelihood indicatorsPeter Chikwekwete
 
EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House mrconroy
 
BizTalk Practical Course Preview
BizTalk Practical Course PreviewBizTalk Practical Course Preview
BizTalk Practical Course PreviewMoustafaRefaat
 
A Real Time Application Integration Solution
A Real Time Application Integration SolutionA Real Time Application Integration Solution
A Real Time Application Integration SolutionMatthew Pulis
 
Services Article Uc Apps Research Wp
Services Article Uc Apps Research WpServices Article Uc Apps Research Wp
Services Article Uc Apps Research Wpchgibbs7
 
59582162 dpr
59582162 dpr59582162 dpr
59582162 dprablaze7
 

Ähnlich wie Pharma Info Sys (20)

Quality control report
Quality control reportQuality control report
Quality control report
 
Cscart 224 community
Cscart 224 communityCscart 224 community
Cscart 224 community
 
100 toeic preparation_tests
100 toeic preparation_tests100 toeic preparation_tests
100 toeic preparation_tests
 
100 s
100 s100 s
100 s
 
100toeicpreparationtests
100toeicpreparationtests100toeicpreparationtests
100toeicpreparationtests
 
100 toeic preparation tests
100 toeic preparation tests100 toeic preparation tests
100 toeic preparation tests
 
100 toeic preparation_tests_5976
100 toeic preparation_tests_5976100 toeic preparation_tests_5976
100 toeic preparation_tests_5976
 
100toeicpreparationtests
100toeicpreparationtests100toeicpreparationtests
100toeicpreparationtests
 
Ebilling project report
Ebilling project reportEbilling project report
Ebilling project report
 
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...Endversion1 skriptum characterization of miscellaneous multi parametrical sil...
Endversion1 skriptum characterization of miscellaneous multi parametrical sil...
 
It project development fundamentals
It project development fundamentalsIt project development fundamentals
It project development fundamentals
 
WebIT2 Consultants Proposal
WebIT2 Consultants ProposalWebIT2 Consultants Proposal
WebIT2 Consultants Proposal
 
Gender livestock and livelihood indicators
Gender livestock and livelihood indicatorsGender livestock and livelihood indicators
Gender livestock and livelihood indicators
 
EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House EPA Wastewater Treatment for A Single House
EPA Wastewater Treatment for A Single House
 
Thesis writing
Thesis writingThesis writing
Thesis writing
 
BizTalk Practical Course Preview
BizTalk Practical Course PreviewBizTalk Practical Course Preview
BizTalk Practical Course Preview
 
A Real Time Application Integration Solution
A Real Time Application Integration SolutionA Real Time Application Integration Solution
A Real Time Application Integration Solution
 
Services Article Uc Apps Research Wp
Services Article Uc Apps Research WpServices Article Uc Apps Research Wp
Services Article Uc Apps Research Wp
 
59582162 dpr
59582162 dpr59582162 dpr
59582162 dpr
 
Drools expert-docs
Drools expert-docsDrools expert-docs
Drools expert-docs
 

Mehr von chris20854

Network Solution
Network SolutionNetwork Solution
Network Solutionchris20854
 
Voip Recommendation
Voip RecommendationVoip Recommendation
Voip Recommendationchris20854
 
Wireless Network
Wireless NetworkWireless Network
Wireless Networkchris20854
 
Security Proposal
Security ProposalSecurity Proposal
Security Proposalchris20854
 

Mehr von chris20854 (7)

Network Solution
Network SolutionNetwork Solution
Network Solution
 
Wireless Abc
Wireless AbcWireless Abc
Wireless Abc
 
Voip Recommendation
Voip RecommendationVoip Recommendation
Voip Recommendation
 
Wireless Network
Wireless NetworkWireless Network
Wireless Network
 
Info Security
Info SecurityInfo Security
Info Security
 
Security Proposal
Security ProposalSecurity Proposal
Security Proposal
 
Chris Mc Coy
Chris Mc CoyChris Mc Coy
Chris Mc Coy
 

Pharma Info Sys

  • 1. Electronic Product Sale Logging System Smith’s Pharmacy Victor Amaya, Chris McCoy and Robert Berus October 25, 2007
  • 2.
  • 3. Table of Contents 1. EXECUTIVE SUMMARY.....................................................................................................................................1 1.1. PURPOSE...............................................................................................................................................................1 1.2. BACKGROUND..........................................................................................................................................................1 1.3. INDUSTRY..............................................................................................................................................................1 1.4. VISION..................................................................................................................................................................1 1.5. SCOPE..................................................................................................................................................................2 2. PROJECT CHARTER...........................................................................................................................................3 2.1. PROJECT OBJECTIVES..................................................................................................................................................3 2.2. PROJECT CONCEPTION................................................................................................................................................3 2.3. PROBLEM STATEMENT................................................................................................................................................3 2.4. FINANCIAL RISK ANALYSIS............................................................................................................................................4 2.5. INITIAL SCOPE OF THE PROJECT.......................................................................................................................................4 2.6. PROJECT VISION.......................................................................................................................................................4 2.7. BUSINESS CONSTRAINTS..............................................................................................................................................4 2.8. TECHNOLOGY CONSTRAINTS..........................................................................................................................................5 2.9. PROJECT STRATEGY....................................................................................................................................................5 2.10. PROJECT DOCUMENTATION AND COMMUNICATION..............................................................................................................5 2.11. PROJECT ORGANIZATION AND STAFFING APPROACH.............................................................................................................5 3. PROJECT VALUE STATEMENT...........................................................................................................................6 3.1. BACKGROUND .........................................................................................................................................................6 3.2. VALUES.................................................................................................................................................................6 4. PROJECT STRATEGY STATEMENT.....................................................................................................................7 4.1. METHODOLOGY OVERVIEW..........................................................................................................................................7 4.2. MEETING FREQUENCY................................................................................................................................................7 4.2.1. A-Team Project Development Meetings......................................................................................................7 4.2.2. Smith’s Pharmacy Client Update Meetings.................................................................................................7 5. SYSTEM PROJECT METHODOLOGY...................................................................................................................8 5.1. ELECTRONIC PRODUCT SALE LOGGING SYSTEM PROJECT METHODOLOGY......................................................................................8 5.1.1. Requirements...............................................................................................................................................8 5.1.2. Design...........................................................................................................................................................9 5.1.3. Implementation............................................................................................................................................9 5.1.4. Verification...................................................................................................................................................9 5.1.5. Maintenance..............................................................................................................................................10 6. GENERAL SYSTEM ANALYSIS..........................................................................................................................11 6.1. CONTEXT MODEL...................................................................................................................................................11 6.2. EVENT LIST...........................................................................................................................................................12 Page | i
  • 4. 6.3. EVENT DICTIONARY..................................................................................................................................................12 7. BUSINESS REQUIREMENTS AND RULES..........................................................................................................14 8. TECHNICAL REQUIREMENTS AND ASSUMPTIONS...........................................................................................22 8.1. EXISTING LAN AND WAN.......................................................................................................................................22 8.1.1. Network Operating System and Client PC Configuration..........................................................................22 8.1.2. WAN Infrastructure Overview....................................................................................................................23 8.1.3. LAN Infrastructure Overview......................................................................................................................24 8.1.4. IT Equipment Rack Diagram ......................................................................................................................25 8.2. POINT OF SALE SYSTEM............................................................................................................................................26 8.3. TECHNICAL SUPPORT................................................................................................................................................26 9. TECHNICAL PLATFORM AND TOOLS REQUIRED..............................................................................................27 9.1. .NET FRAMEWORK 2.0............................................................................................................................................27 9.2. VISUAL STUDIO 2005 ............................................................................................................................................27 9.3. WINDOWS SERVER 2003.........................................................................................................................................27 9.4. SQL SERVER 2005...............................................................................................................................................27 9.5. CANDIDATE MATRIX................................................................................................................................................28 10. THIRD-PARTY NEEDS....................................................................................................................................29 10.1. VENDORS...........................................................................................................................................................29 10.1.1. Dell...........................................................................................................................................................29 10.1.2. Microsoft..................................................................................................................................................29 10.1.3. IBM...........................................................................................................................................................29 10.1.4. Suppliers...................................................................................................................................................30 10.1.5. Consultants..............................................................................................................................................30 11. DATABASE/ERD MODEL...............................................................................................................................31 12. DATA FLOW DIAGRAM................................................................................................................................32 13. SYSTEM ARCHITECTURAL DIAGRAMS...........................................................................................................33 14. PROJECT RISK AND RISK MANAGEMENT......................................................................................................34 14.1. RISK MANAGEMENT PLANNING..................................................................................................................................34 14.2. QUALITATIVE/QUANTITATIVE RISK ANALYSIS...................................................................................................................36 14.2.1. Risk Response Planning............................................................................................................................36 14.2.2. Monitoring and Control...........................................................................................................................36 15. PROJECT COSTS, STAFFING, RESOURCES, DEPENDENCIES AND SCHEDULE.....................................................37 15.1. BENEFITS...........................................................................................................................................................37 15.2. BILL OF MATERIALS...............................................................................................................................................38 15.3. TRIPLE COST ANALYSIS...........................................................................................................................................39 15.4. RETURN ON INVESTMENT ANALYSIS.............................................................................................................................40 15.5. PROJECT SCHEDULE...............................................................................................................................................41 PROJECT STAFFING........................................................................................................................................................42 16. INTEGRATION OF INTERNAL/EXTERNAL SYSTEMS........................................................................................43 Page | ii
  • 5. 17. SYSTEM ADMINISTRATION, SECURITY, BACKUP AND RECOVERY..................................................................44 17.1. POLICY..............................................................................................................................................................44 17.2. ACCOUNT MANAGEMENT........................................................................................................................................44 17.3. ADMINISTRATIVE...................................................................................................................................................44 17.4. BACKUP RECOVERY OF NETWORK SERVERS AND DATA.......................................................................................................45 17.5. MICROSOFT SQL SERVER 2005 BACKUP.....................................................................................................................46 17.6. COMPUTER VIRUS PREVENTION..................................................................................................................................47 17.7. INCIDENT MANAGEMENT.........................................................................................................................................47 17.8. INTERNET USE.....................................................................................................................................................47 17.9. PASSWORDS........................................................................................................................................................47 17.10. PHYSICAL ACCESS................................................................................................................................................47 18. REFERENCES................................................................................................................................................48 Page | iii
  • 6. Table of Figures FIGURE 1: FINANCIAL RISK ANALYSIS...................................................................................................................4 FIGURE 2: DEVELOPMENT METHODOLOGY OF THE APPLICATION OF THE ELECTRONIC PRODUCT SALE LOGGING SYSTEM..............................................................................................................................................................8 FIGURE 3: CONTEXT MODEL..............................................................................................................................11 FIGURE 4: EXISTING WAN ARCHITECTURE..........................................................................................................23 FIGURE 5: EXISTING LAN/WAN ARCHITECTURE..................................................................................................24 FIGURE 6: RACK CONFIGURATION .....................................................................................................................25 FIGURE 7: POINT-OF-SALE ARCHITECTURE AND CONNECTIVITY..........................................................................26 FIGURE 8: CANDIDATE MATRIX..........................................................................................................................28 FIGURE 9: ENTITY-RELATIONSHIP DIAGRAM......................................................................................................31 FIGURE 10: DATA FLOW DIAGRAM....................................................................................................................32 FIGURE 11: PROPOSED SYSTEM ARCHITECTURE.................................................................................................33 FIGURE 12: ANNUAL COST AVOIDANCE.............................................................................................................37 FIGURE 13: BILL OF MATERIALS.........................................................................................................................38 FIGURE 14: LIFE CYCLE COSTS............................................................................................................................39 FIGURE 15: ROI ANALYSIS.................................................................................................................................40 FIGURE 16: PROJECT STAFFING..........................................................................................................................42 FIGURE 17: INTEGRATION OF INTERNAL AND EXTERNAL SYSTEMS AND SERVICES..............................................43 FIGURE 18: TAPE BACKUP ROTATION................................................................................................................45 FIGURE 19: EMC RETROSPECT CONFIGURATION................................................................................................46 Page | iv
  • 7. 1. Executive Summary 1.1. Purpose This purpose of this project is to provide a technological solution to the problem of manual logbook management of pseudoephedrine logging for a fictitious, small retail pharmacy chain located in the Ohio Valley area called Smith’s Pharmacy. This solution will help to provide data and systems needed to track across state lines while providing reporting capabilities and compliance with Federal regulations. 1.2. Background Smith’s Pharmacy is a four-store retail chain located in the Ohio Valley area. The company operates stores in Cumberland, Maryland, Wheeling, West Virginia (where the management office and computer systems are also located), Washington, Pennsylvania and St. Clairsville, Ohio. These stores provide a business model based on traditional brick and mortar retail pharmacy, similar to those of its competitors, CVS Pharmacy, Rite Aid and Kroger. A more recent focus for Smith’s has been its log keeping activities related to sales of products impact by Pseudoephedrine legislation. Currently, Smith’s maintains its Pseudoephedrine logbooks manually, using a handwritten account of each sale. This is required to maintain compliance with State regulations in its Ohio and West Virginia locations. Specially, Smith’s must abide by statutes Ohio Revised Code, Section 2925.56 and WV 60A-10-5 governing requirements of controlled substances. Violations are severe. Both states impart a fine of violations; Ohio enforces a maximum of $1,000 and West Virginia $10,000. In addition, Ohio’s statues call for a jail sentence not to exceed 180 days. 1.3. Industry Smith’s is a regional, small retail pharmacy chain. Its competitors include larger brick and mortar retail chains such as CVS and Kroger and mail order. Mail order is particularly troublesome for Smith’s in particular and the retail industry in general, because it allows consumers to obtain a 90-day prescription supply instead of one 30-day supply for each co pay. Since Smith’s is much smaller than these national chains and mail order pharmacies, gaining a competitive advantage in the marketplace is critical to its continued growth and success. For this project, the automation of the logbook function will provide an increase in productivity and customer satisfaction by reducing wait times in pharmacy lines. Keeping compliance is also critical to the continued success of the business by streamlining the audit processes and eliminating financial risks from non-compliance. 1.4. Vision We envision a complete change in the way Smith’s tracks sales of pseudoephedrine-legislated items. Our solution will eliminate the current system of manual logging and each of the four stores will participate in an online-networked solution for tracking pseudoephedrine sales using an online logbook application that is auditable from a central data source.
  • 8. 1.5. Scope The scope of this project will include the following: 1. Design of a centralized database in the Wheeling, West Virginia office to serve as the repository for pseudoephedrine sales data. 2. Expand the existing WAN network infrastructure to support the new system. 3. Design of an application for each retail location that will collect pseudoephedrine sales data at point of sale and provide a management reporting capability. 4. Project planning for implementation of the new information system. 5. End user training plan.
  • 9. 2. Project Charter 2.1. Project Objectives • Create a unified infrastructure across the Smith’s retail pharmacy chain to track Pseudoephedrine sales by replacing manual logbook tracking measures with an automated system. • Increase Smith’s regulatory compliance capability by eliminating errors caused by manual log keeping. • Increase productivity for the business by reducing customer wait times related to the existing manual logging procedure. 2.2. Project Conception The A-Team Consultants envision a system for Smith’s pharmacy that will allow the organization to solve the problems of manual logbook tracking the sale of products containing pseudoephedrine, ephedrine or phenylpropanolamine by creating a scalable, automated system to replace the manual logbook with a high-tech, online solution. This solution can be used by pharmacists in each of Smith’s four locations to determine of sale of these products to an individual customer is within compliance of Federal and local regulations. If the company decides to open additional stores in other locations, it can quickly implement the system into the existing technology infrastructure. 2.3. Problem Statement Smith’s retail pharmacy stores must record identities of people who purchase over-the-counter pseudoephedrine products as a deterrent to methamphetamine manufacturing. Currently, Smith’s Pharmacy tracks this activity on a handwritten log, which presents the following issues 1. They are handwriting information. 2. They are duplicating information (multiple purchases by the same person). 3. They are not meeting privacy requirements because they log multiple sales on one page. 4. They are unable to enforce the intent of the law because they have no immediate, ad-hoc reporting capabilities at the time of sale, particularly across several locations. 5. They are at financial risk from fines because of 3 and 4. A solution is needed to replace the traditional logbook in order to provide longer-term (e.g., monthly, quarterly) reporting functionality across multiple locations and assure these stores meet compliance to avoid potential legal penalties.
  • 10. 2.4. Financial Risk Analysis Estimated Financial Exposure, St. Clairsville, Ohio, Location Based on Smith's Pharmacy FY2007 Sales Data Revenue, Total Store $811,000 Revenue, Impacted Products $9,780 Average Sale Price, Per Product $25 Transactions, Per Year $391 Estimated Non-Compliance Rate 5% Non-Compliant Transactions $20 Fine, Per Incident $10,000 Net Impact, Annual $200,000 Impact, % to Total Revenue 24.6% Figure 1: Financial Risk Analysis 2.5. Initial Scope of the project This project will implement an automated logbook system to track for Smith’s current chain of four retail locations in the greater Ohio Valley area. We will develop a system to track information from each location in a database located at the company’s central site in Store #1, located in Wheeling, West Virginia. The other three stores – located in Cumberland, Maryland, St. Clairsville, Ohio, and Washington, Pennsylvania – will have the same tracking application installed in each store. These systems will interface with the central database in Wheeling using the company’s existing network infrastructure. 2.6. Project Vision A-Team Consultants envisions a solution for Smith’s Pharmacy that will provide an automated tracking of pseudoephedrine sales data with a centrally managed database, and management reporting capability. The conversion from manual logs in each site to a single unified online system will provide a means to track pseudoephedrine sales across the chain of stores. The system should include a point of sale entry capability as well as a reporting module to provide statistical information regarding sales and compliance. 2.7. Business Constraints • Training schedule may require additional overtime hours for employees. • Implementation may require additional pre-deployment testing. • Up front budget costs of Development, Systems Implementation (including all necessary equipment), and Training may influence profitability until ROI is achieved. • Willingness or resistance of employees to adapt to the new system might affect initial success of the new system.
  • 11. 2.8. Technology Constraints • Budget will be a consideration in terms of the quality and speed of the equipment. • Faster computer equipment comes at a higher cost. o Information Security Solutions are often expensive. o Budget for database and application development and testing is needed. o Time required to build the database and applications must be considered. • Time to test the new system will be needed to ensure stability and reliability. • Implementation of high security measures for the information systems is critical to keep data private and maintain regulatory compliance. 2.9. Project Strategy • Expand existing network infrastructure to house new technology components. • Build Database Application to include the following: o User Interface Data Input Screen o Output Data (Purchase Approval Screen) o Database Reporting Screens • Test Application across WAN infrastructure at all four locations. • Go-Live on approved/agreed date. 2.10. Project Documentation and Communication We will document the project via a comprehensive project implementation plan. This plan will outline the details of the development and implementation of the new pseudoephedrine online tracking system. Communication throughout the life of the project will be in writing or in person between A- Team consultants and the client, Smith’s Pharmacy. A-Team will meet with the client once per week to provide progress status updates for the implementation. A-Team will also hold its own meetings once per week to verify progress. 2.11. Project Organization and Staffing Approach A-Team Consultants will work closely with members of the Smith’s management team to identify business requirements related to the project, and to ensure that the project’s technical solution aligns well with Smith’s strategic business goals. A-Team’s three-member team owns expertise in the fields of Project Management, Network Engineering and Health Information Systems. The project team for A- Team will consist of a project manager and 2 technical consultants. The Smith’s management team will provide two subject matter experts to assist in ensuring that all technical initiatives meet compliance with local, state and federal regulations. We will provide training on the new system to all store managers, cashiers, pharmacists and pharmacy technicians.
  • 12. 3. Project Value Statement 3.1. Background Smith’s Pharmacy has continued to develop a loyal base of customers in Ohio Valley. There is great potential to grow this business in terms of both local customer base and new retail locations, provided the company utilizes the automated and centralized logbook solution. With potential expansion further into the surrounding areas it serves, a project of this nature holds great possibilities for creating a local competitive edge and greater competition with larger retailers such as CVS and Rite Aid. The value provided by the Smith’s chain is at great risk if it violates any local, state or federal laws regarding these products. Violations could negatively affect operations, placing the health of its customers at risk. 3.2. Values • Increase logbook compliance through database automation. • Increase customer satisfaction through reduced customer wait times. • Decrease likelihood of fines and penalties through advanced reporting capability. • Help reduce illegal methamphetamine production in the region through better enforcement and accounting of pseudoephedrine sales within legal limits. • Provide better store expansion capability through system scalability.
  • 13. 4. Project Strategy Statement 4.1. Methodology Overview A-Team consultants will utilize the Waterfall project development model to complete the Electronic Product Sale Logging System project for Smith’s Pharmacy. Noting the original methodology as developed by W.W. Royce, A-Team will follow the prescribed sequential methodology consisting of the following phases as waterfall steps: 1. Requirements 2. Design 3. Implementation 4. Verification 5. Maintenance A-Team will build the requirements phase of the development through information gathered from the client and the business requirements as defined in the business requirements section. Because this methodology incorporates a staged approach to systems development, it will provide a better structure for the development of the Electronic Product Sale Logging System for our client. This method is recommended for situations where the project has a clear objective and solution and resources need to be conserved (CMS, 2005). 4.2. Meeting Frequency 4.2.1. A-Team Project Development Meetings The A-Team Consultants will hold staff meetings regularly to review project updates and modifications as necessary. We will conduct weekly project meetings to review milestones for development, testing, and rollout schedule in a manner consistent with the aforementioned waterfall methodology. 4.2.2. Smith’s Pharmacy Client Update Meetings We will conduct weekly status meetings with the Smith’s Pharmacy management team, using the client’s preferred meeting method. This may include web conferencing, conference calls or face to face on site. Each meeting will review the project milestones and schedule to keep the project on track for timely delivery of the new system. The project team will report any unanticipated project issues or delays to Smith’s Pharmacy management immediately.
  • 14. 5. System Project Methodology 5.1. Electronic Product Sale Logging System Project Methodology The Electronic Product Sale Logging System will use the Waterfall methodology to development of the new systems through each phase of the project and system lifecycles. A-Team will follow the prescribed sequential methodology consisting of five steps. The diagram below shows the standard Waterfall methodology. Requirements Design Implementation Verification Maintenance Figure 2: Development Methodology of the Application of the Electronic Product Sale Logging System 5.1.1. Requirements We will build a list of business requirements through close collaboration with Smith’s management team.
  • 15. 5.1.2. Design Based on business requirements, we will compose logical and physical designs. The project team will transform the company’s business requirements into a high-level business plan from which we will create the logical plan. The following steps are required: 1. Create Use Cases based on Business Requirements 2. Create Data Flow Diagrams to show the flow of information through the model 3. Create Data Model from which the physical database can be created The technical plan for the project will transform business requirements into a physical design. We will use these solutions for several critical design milestones: 1. The design of the application, including the user interface 2. The design of the database including all tables, schemas and structures 3. Analysis of the existing network LAN/WAN infrastructure to verify data capacity requirements 4. The integration of an additional application server running the database and application system software 5. The project planning required for implementation of such solutions 5.1.3. Implementation Based on the final design and project scheduling, we will present a detailed plan for rollout of the technologies for Smith’s Pharmacy management team. Once the management team has approved such implementation, A-Team Consultants will complete a test of the entire system and all functionality prior to rollout of the system for daily production. The goal of a successful implementation will be to complete the rollout with minimal impact or interruption to business during the process. 5.1.4. Verification Critical to the success of the rollout for this system will be pre-production testing. The following items are critical to the success of the verification phase: 1. Network capacity testing between all four sites 2. Network security testing 3. Application/Database testing using sample data files 4. Database Management Report Testing
  • 16. 5.1.5. Maintenance The solution will utilize regular maintenance windows for the following purposes: 1) Daily a) Database Backup to Tape b) System OS and Image backups to tape c) Ongoing break/fix maintenance as needed for all hardware, software and applications 2) Quarterly a) Application Upgrades b) Security Patches c) Regularly Scheduled Database Maintenance d) Network upgrades as required
  • 17. 6. General System Analysis 6.1. Context Model Store Supervisor Seller (Clerkr/Phar macist ) Printer Manual Customer and Author ization Seller Data Input Response Bar Code Reader Approval for Purchase/Return Request Output Notice /Alert Automatic Customer Data Input Stor e & Receive Signature/ Product Info Complete Purchase Logbook Electronic Logbook Customer Database Stor e & Receive Purchase Request Customer Info Purchase Approval Response Maintenance/ State & Federal Updates Regulators Updates/ Upgrades A-Team Consultants Customer Signature Signature Capture IT Department Pad Figure 3: Context Model
  • 18. 6.2. Event list 1. Add/Update Customer information 2. Add/Remove Product 3. Process product returns 4. Calculate state and federal limitations of product sale and generate alerts/notices 5. Add/Remove Transaction information (date/time, location, clerk name, product name, quantity) 6. Product summary reports 6.3. Event dictionary Event Name: Add/Update Customer to database Event ID: 1 Description: When a customer wants to purchase a product, the customer’s information must be entered into the database. Stimulus: Customer wants to purchase a product Activity: • If user does not exist in the database, then add a record of that customer into the database. • If customer is purchasing a product, verify whether it is more or less than 60mg of PSE. If it does not, no signature is required. If it is, generate a printable notice warning. • If Customer is returning a product, adjust transaction record in database. Response: User Added/Updated. Effect: If there are no alerts/notices, the customer is able to continue transaction Event Name: Add/Remove Product to database Event ID: 2 Description: When a customer wants to purchase a product, the product’s information must be entered into the database. Stimulus: Customer wants to purchase a product Activity: • If the product does not exist in the database, then add a record for that product into the database. Update product inventory. • If customer is purchasing a product, verify that it is available from Product Inventory. If it is available, verify the quantity being sold and update product inventory. • If Customer is returning a product, add new transaction and update product inventory. Response: Product recorded. Effect: If there are no alerts/notices, the customer is able to purchase the product.
  • 19. Event Name: Add Process product returns Event ID: 3 Description: After a customer has purchased a product, they can return it using this feature. Stimulus: Seller enters transaction number, name and address in return screen. Activity: The system verifies if the return is valid and requires approval of supervisor. If it is, then add new transaction and update inventory. Response: Return is processed. Effect: Adjusted Transaction/Product details Event Name: Calculate state and federal limitations of product sale and generate alerts/notices Event ID: 4 Description: After a customer submits a purchase, this feature verifies if the purchase can complete. Stimulus: Seller inputs customer and product information on purchase screen. Activity: The system verifies the sale against federal and state regulations. If a violation occurs, a notice and warning is displayed in a message box. If not violation occurs, the purchase can be completed. Response: Purchase is processed. Effect: If there are no alerts/notices, the customer is able to purchase the product. Event Name: Add/Remove Transaction (date/time, location, seller name, product name, quantity) Event ID: 5 Description: When a customer purchases a product a transaction is recorded into the database. Stimulus: Customer submits purchase request Activity: • Create a record in transaction table with date/time, location, product name and quantity of sale and seller name. • If the customer is making a purchase, verify that customer is eligible and the quantity is within state and federal limitations. If eligible record transaction details in database • If customer is returning a product, mark returned item into transaction database. Response: If there are no alerts/notices, the customer is able to purchase the product. Event Name: Product summary reports Event ID: 6 Description: Produces reports per query specified by seller, state or federal regulators. Stimulus: Seller or regulator enters query information into reporting screen. Activity: Return query results and display in web page for view. The results are adjusted so they are in print format. Response: Processed Query results.
  • 20. 7. Business Requirements and Rules Use Case Name 1. Process Transaction Scenario Process new sale Triggering Event Customer attempts to purchase a controlled product Brief Description When the customer wishes to purchase a product controlled by Methamphetamine law, the sale must be logged and validated against sale restrictions. Actors • Store employee Related Use Cases Stakeholders • Customer wants to buy product. • Pharmacist wants to sell product. • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions • Customer must exist in audit tool. • Product, Product Category records must exist. Post-conditions • Transaction record must be created.
  • 21. Use Case Name 1. Process Transaction (continued) Flow of Events Actor System 1. Customer goes to pharmacy counter to purchase desired product. 2. Pharmacist identifies product requested by customer. 3. Pharmacist collects government-issued (State or Federal) identification from customer. 4. Pharmacist initiates a new 4.1. P.O.S. begins a new transaction in the existing transaction journal entry. P.O.S. system. 5. Pharmacist scans or 5.1. P.O.S. retrieves item details. manually enters UPC for 5.2. Flag in P.O.S. controller desired product. indicates transaction must flow through real-time audit process. 6. Pharmacist scans or 6.1. P.O.S. system passes manually enters unique Product and Customer customer identifier from I.D. parameters to audit program for validation. 6.2. P.O.S. system adds line item to transaction if audit passes. 7. Pharmacist completes sale 7.1. P.O.S. logs transaction per S.O.P. details to audit system. Exception Conditions 3.1. If customer cannot provide proper identification, no transaction is performed. 6.3. If customer does not exist, prompt Pharmacist for customer demographic information. 6.4. If customer demographic information is not correct, Pharmacist completes transaction per S.O.P, then invokes 2. Maintain Customer. 7.1. If audit control program flags sale as invalid, P.O.S. system voids line.
  • 22. Use Case Name 2. Maintain Customer Scenario Update customer demographic data Triggering Event Customer demographic data needs updated. Brief Description When a customer’s demographic data needs updated, the Pharmacist must update it via a web portal. Actors • Store employee Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Customer must exist Post-conditions Flow of Events Actor System 1. Pharmacist collects 1. government-issued (State or Federal) identification from customer. 2. Pharmacist logs into web portal 3. Pharmacist enters maintain customer screen. 4. Pharmacist locates existing customer record. 5. Pharmacist updates necessary attributes. 6. Pharmacist saves updates. Exception Conditions
  • 23. Use Case Name 3. Add Product Category Scenario Create a new product category Triggering Event Legislative changes require new tracking method Brief Description Applicable laws require sellers to track the sales of certain products specific ways and limit them specific quantities. Product Categories allow the company to specify business rules that adhere to the appropriate laws any particular location must meet. Actors • Company auditor Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Post-conditions Existing and new Products must be associated with the new Product Category. Flow of Events Actor System 1. Auditor identifies the need for a new Product Category. 2. Auditor identifies the appropriate constraints/business rules for this Product Category. 3. Auditor logs into web portal. 4. Auditor enters add Product Category screen. 5. Pharmacist enters necessary attributes. 6. Pharmacist saves new 6.1. System creates a new Product Category. Product Category record. The new Product Category is made available for use. Exception Conditions
  • 24. Use Case Name 4. Maintain Product Category Scenario Maintain an existing product category Triggering Event Legislative changes require modified tracking method Brief Description Applicable laws require sellers to track the sales of certain products specific ways and limit them specific quantities. Product Categories allow the company to specify business rules that adhere to the appropriate laws any particular location must meet. This Use Case also represents instances wherein a Product Category is no longer legislated for controlled sales. Actors • Company auditor Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Post-conditions Existing and new Products must be associated with the updated Product Category. Flow of Events Actor System 1. Auditor identifies the need to modify an existing Product Category. 2. Auditor identifies the appropriate constraints/business rules for this Product Category. 3. Auditor logs into web portal. 4. Auditor enters Maintain Product Category screen. 5. Pharmacist modifies necessary attributes. 6.1. System updates existing 6. Pharmacist saves updates. Product Category record. Exception Conditions
  • 25. Use Case Name 5. Add Product Scenario Add a product to the audit program Triggering Event • Legislative changes require new tracking method • New product received • Correction Brief Description Applicable laws require sellers to track the sales of certain products specific ways and limit them specific quantities. Product Categories allow the company to specify business rules that adhere to the appropriate laws any particular location must meet. Actors • Company auditor Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Product Category must exist. Post-conditions Flow of Events Actor System 1. Auditor identifies the need for a new Product tracking. 2. Auditor identifies the appropriate Product Category. 3. Auditor logs into web portal. 4. Auditor enters add Product screen. 5. Pharmacist assigns desired Product Category. 6. Pharmacist saves new 6.1. System creates a new Product. Product record. Exception Conditions 5.1. If Product Category does not exist, user pauses this use case and invokes 3. Add Product Category.
  • 26. Use Case Name 6. Maintain Product Scenario Maintain an existing product Triggering Event • Legislative changes require modified tracking method • Correction Brief Description Applicable laws require certain products to be tracked in specific ways and limited to specific quantities of sales. Product Categories allow the company to specify business rules that adhere to the appropriate laws any particular location must meet. Actors • Company auditor Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Post-conditions Flow of Events Actor System 1. Auditor identifies the need to modify an existing Product. 2. Auditor identifies the appropriate changes. 3. Auditor logs into web portal. 4. Auditor enters Maintain Product screen. 5. Pharmacist modifies necessary attributes. 6. Pharmacist saves updates. 6.1. System updates existing Product record. Exception Conditions 1.1. If product has had ingredient changes necessitating change, the Product Specialist should inactive the existing item code in the company’s P.O.S. system, a new item number created and the U.P.C. linked to the new product. Then, a new Product record should be created via the 5. Add Product Use Case.
  • 27. Use Case Name 7. Generate Summary Reports Scenario Report needed Triggering Event Information needed Brief Description Process to generate reports. Actors • Company auditor, or • Pharmacist, or • Store Management Related Use Cases Stakeholders • Company wants to remain compliant with applicable laws • Regulatory bodies want to control distribution of controlled products Pre-conditions Post-conditions Flow of Events Actor System 1. User identifies the desired report. 2. User logs into web portal. 3. User enters Reports screen. 4. User selects appropriate 4.1. System queries database, report and enters necessary assembles report and criteria. displays in web browser. 5. User views report. Exception Conditions
  • 28. 8. Technical Requirements and Assumptions Smith’s Pharmacy currently owns a networked point-of-sale (POS) sales entry system. The company purchased the system from IBM to improve the checkout process for the organization. A 100Mb LAN connects the POS systems within each of the four locations and a WAN provides e-mail connectivity and internet access across a secured MPLS network from the centralized firewall located in the Wheeling store. A more detailed description of the existing network is provided in the next section. 8.1. Existing LAN and WAN 8.1.1. Network Operating System and Client PC Configuration Smith’s Pharmacy uses a small Microsoft Windows Active Directory (AD) Domain running on Windows 2003 Server. This server also provides DNS support required for connectivity of the AD domain, clients and the Microsoft Exchange e-mail server. Clients (Management PC’s) are configured with the Windows XP operating system running Service Pack 2; Microsoft Outlook 2003 is used for e-mail, contact and schedule management.
  • 29. 8.1.2. WAN Infrastructure Overview Smith’s Pharmacy utilizes a Sprint Multiprotocol Label Switching Wide Area Network (MPLS) consisting of dual T1 connections to each store. The Wheeling store hosts the e-mail server and serves as a central proxy point for Internet Web Browsing. All web browser requests traverse the MPLS to the Wheeling Store where a Checkpoint FW-1 firewall running on a Dell 1850 1U rack-mount server handles packet- forwarding decisions. This firewall limits inbound access to HTTP (Web browsing) and SMTP (e-mail) requests. E-mail traffic also traverses the same MPLS cloud for the remaining stores. The MPLS WAN provides a controlled secure network environment and protects data traffic between stores from compromise by unauthorized third parties. The diagram below contains a high-level view of the overall WAN network connectivity. The POS System utilizes the LAN for connectivity to a central POS controller in each store. The company utilizes the MPLS to manage all locations’ POS systems using specialized management software. Figure 4: Existing WAN Architecture
  • 30. 8.1.3. LAN Infrastructure Overview The following diagram shows a more detailed view of Smith’s Pharmacy LAN architecture in each store and the physical connectivity of the WAN routers. Note that this diagram also includes one additional Dell server the company will need to purchase for the application and database implementation. This diagram also includes a backup circuit for business continuity. A tape backup system using a single internal mammoth two-tape drive on the Windows 2003 AD domain controller server running EMC Retrospect backup software Data backups are handles data backup. The current daily full system backup has approximately 70% available capacity on the existing tape drive to handle additional data. Figure 5: Existing LAN/WAN Architecture Each site is connected to the MPLS via a Dual T1 (bundled) 3Mb connection. The backup (failover) circuit is an ISDN 384k line, with a standard vendor agreement in place for a per-usage based charge. As previously mentioned, the Wheeling site is the primary IT location for server support. Here, the e-mail server handles all e-mail for the stores. A separate, dual T1 configuration handles the Internet Web Browsing requests from all sites.
  • 31. 8.1.4. IT Equipment Rack Diagram This section shows each store’s rack configuration. The single rack configuration in each location provides a simple effective solution that occupies minimal space in the computer room in the back of the each store. An air conditioner cools the room to a constant temperature of 70 degrees Fahrenheit to protect the IT equipment. A-Team consultants will utilize this existing infrastructure to support the Electronic Product Sale Logging System. The MPLS as a means of cross-site communication will provide a secure solution for transfer of the data from all sites to the database located in the Wheeling store. Figure 6: Rack Configuration
  • 32. 8.2. Point of Sale System Smith’s Pharmacy utilizes IBM’s ‘Sure POS 300 Series’ point of sale system. IBM describes the Model 300 system as a “cost effective solution to managing cash register transactions in each of its four locations” (IBM, 2005). Each store’s POS system is capable of operating at the current 100Mbps LAN speed. The systems are thick-client based PCs, running Windows XP Professional with Service Pack 2. The POS terminals are connected to a POS Controller, which tracks transactions and inventory across the LAN. Additionally, the company can remotely audit each controller using IBM’s remote management software. IBM describes this system as having an “open platform with broad operating system support.” This provides a user-friendly computing environment with scalability for future growth of the business. As shown in the diagram below, management can audit all four locations across the MPLS WAN from any other location. Each store location has four terminals in the front of the store checkout area and one terminal to service the pharmacy counter. Figure 7: Point-of-Sale Architecture and Connectivity 8.3. Technical Support Smith’s has existing technical support in place for the following systems: • WAN – MPLS via Sprint, the MPLS service provider for the organization’s WAN. • LAN – Sprint Business Services, including all Cisco LAN hardware, and PC’s: (Sprint, 2007) • POS – Support contract with IBM on all IBM POS equipment • Tape Backup – EMC provides technical support for Retrospect Software. Smith’s Pharmacy store management in the Wheeling Store handle the changing of daily backup tapes and are trained on the administration of the Tape backup software.
  • 33. 9. Technical Platform and Tools Required 9.1. .Net Framework 2.0 We will target Microsoft’s .NET Framework, version 2.0, to facilitate the development of the proposed solution. The framework provides many precompiled software components that implement functionality commonly used by developers, and many available programming languages. Amongst these are user interface elements, web application features and database connectivity. Additionally, the framework facilitates code-reuse and language interoperability, thereby streamlining development time, future maintenance and testing requirements. Our primary advantage of targeting the .Net Framework will allow us to reuse the data connectivity code between the web portal and the point-of-sale system. 9.2. Visual Studio 2005 A-Team Consultants will use Microsoft’s Visual Studio 2005 to create the necessary interfaces for the proposed solution. Visual Studio 2005 targets version 2.0 of Microsoft’s .Net Framework, streamlining application development for a multitude of platforms. It provides support for database connectivity and websites, allowing developers to create all content from one development environment. 9.3. Windows Server 2003 We have selected Microsoft’s Windows Server 2003 operating system as the server platform for our solution. It seamlessly integrates .NET Framework 2.0, provides security, reliability and performance benefits and completes the unified system architecture desired for this project. Importantly, Windows Server 2003 includes Internet Information Services 6, allowing the use of ASP.NET applications using .NET Framework 2.0 developed with Visual Studio 2005. It provides a stable and secure host platform for our database management system. 9.4. SQL Server 2005 Microsoft’s SQL Server 2005 will provide the back-end data structures and decision logic systems for use in the proposed solution. It provides a comprehensive, integrated data management and analysis package that enables organizations to reliably manage mission-critical information and confidently run today’s increasingly complex business applications. SQL Server 2005 provides scalable product offerings to allow the organization to meet its needs in a cost effective manner. Also, it provides several connectivity options for basic and advanced reporting and analysis features via third-party applications, such as Microsoft’s Access 2007. Clearly, the use of .NET, Visual Studio, Windows Server 2003 and SQL Server 2005 creates a complete and robust architecture that meets the needs of the organization.
  • 34. 9.5. Candidate Matrix Characteristics Candidate 1 Candidate 2 Candidate 3 Portion of System New Client/Server web Same as Candidate 1. Same as Candidate 1. application logbook Computerized system. Benefits Web application would Web application is System would be fully be independent of all independent of current integrated with current current systems. All systems. System (or enhanced) systems. technology is available. framework is already in Great Plains Solutions place, needing only Provider would manage configuration and light all technical requirement visual enhancements. and implementation. Servers and Microsoft Windows Microsoft Windows Microsoft Windows 2003 2003 servers and IIS 6. 2003 servers and IIS 6. servers and IIS 6. Workstations Microsoft SQL Server Oracle 9i. Microsoft SQL Server 2000/2005. 2005. Workstations use Workstations use Microsoft Windows IBM POS systems Microsoft Windows 2000/XP OS. integration. 2000/XP OS. Workstations use Microsoft Windows 2000/ XP OS. Software Tools Microsoft Visual Studio Microsoft Visual Studio Microsoft Visual Studio 2005 2005 2005 Needed .Net Framework 2.0. .Net Framework 2.0. .Net Framework 2.0. Application Custom solution built Custom solution built Custom solution built by by IBM products by Oracle Business the Microsoft products Software integrated into current Suite products integrated into current IBM POS system. integrated into current IBM POS system. IBM POS system. Method of Data Client/Server. Same as Candidate 1. Same as Candidate 1. Processing Output Devices Laser and Bar Code Same as Candidate 1. Same as Candidate 1. printers. and Implications Input Devices and Keyboard, mouse and Same as Candidate 1. Same as Candidate 1. bar code reader. Implications Storage Devices Microsoft SQL Server Oracle 9i DBMS with 10 Same as Candidate 1. DBMS with 10 GB GB storage. and Implications storage. Figure 8: Candidate Matrix
  • 35. 10. Third-Party Needs A-Team focuses on delivering a complete range of cost-effective services tending to our customer’s requirements. We provide support prior and post sale support through comprehensive after sale maintenance and support to ensure our client’s investment. A-Team undertakes all software planning and development in-house to maintain the privacy and integrity of our customers. A-Team does not associate with external partners, suppliers or consults. Smith’s Pharmacy has presented its current systems in place to our team; therefore, A-Team will focus on tailoring software requirements to meet those specifications. Smith’s Pharmacy will need to acquire additional hardware and software for the implementation of the logbook application. 10.1. Vendors 10.1.1. Dell Dell Inc. (Dell) designs, develops, manufactures, markets, sells and supports a range of computer systems and services that are customized to customer requirements (Reuters, 2007). These include enterprise systems (servers, storage, workstations and networking products), client systems (notebook and desktop computer systems), printing and imaging systems, software and peripherals, and global services. The Company markets and sells its products and services directly to its customers, which include corporate, government, healthcare and education accounts, as well as small-to-medium businesses and individual customers. 10.1.2. Microsoft Microsoft Corporation develops, manufactures, licenses and supports a range of software products for computing devices (Reuters, 2007). The Company's software products include operating systems for servers, personal computers (PCs) and intelligent devices, server applications for distributed computing environments, information worker productivity applications, business solution applications, high- performance computing applications and software development tools. The Company has five segments: Client, Server and Tools, the Online Services Business, the Microsoft Business Division, and the Entertainment and Devices Division. The type of licensing for Microsoft Windows Server 2003 and SQL Server 2005 will need to be identified and purchased depending on the needs for the logbook application 10.1.3. IBM International Business Machines Corporation (IBM) is an information technology company. IBM also provides business, technology and consulting services. The Company's major operations comprise a Global Services segment, a Systems and Technology Group, a Software segment and a Global Financing segment. (Reuters, 2007) IBM offers five kinds of software solutions. The Company's software offerings include Information Management Software, an advanced database and content management software
  • 36. solutions that enable clients to leverage information on demand; Lotus Software, a collaboration and messaging software that allows businesses to communicate, collaborate and increase productivity; Rational Software, an integrated tools designed to improve an organization's software development processes and capabilities; Tivoli Software, a software for infrastructure management, including security, change, configuration, job scheduling, storage capability, performance and availability, and Websphere Software, which provides management of a range of business processes using open standards to interconnect applications, data and operating systems. IBM provides a range of services, which includes Business Performance Services (BPS), Business Transformation Outsourcing (BTO), Consulting and Systems Integration (C&SI), Strategic Outsourcing Services (SO), Integrated Technology Services (ITS), Application Management Services and Applications on Demand (AoD). BTO delivers improved business results to clients through the strategic change and the operation and transformation of the client's business processes, applications and infrastructure. ITS provides service offerings that help clients access, manage and support their technology infrastructures, through a combination of resources, software and IBM's knowledge of business processes. C&SI provides consulting services for client relationship management, financial management, human capital, business strategy and change and supply chain management, as well as application innovation and the transformation of business processes and operations. 10.1.4. Suppliers No additional will be needed. 10.1.5. Consultants No additional will be needed.
  • 37. 11. Database/ERD Model ProductCategories PK ProductCategoryId COUNTER Description CHAR(50) State CHAR(2) TrackSales BIT SizeLimit DOUBLE Customers assigned to PK CustomerId COUNTER Products StateId CHAR(10) State CHAR(2) PK ProductId COUNTER StreetAddress 1 CHAR(50) StreetAddress 2 CHAR(50) UPC CHAR(18) City CHAR(30) FK1 ProductCategoryId LONG PostalCode CHAR(10) Size DOUBLE sold on Transactions PK TransactionId CHAR(24) makes Timestamp DATETIME FK2 CustomerId LONG FK1 ProductId LONG QtySold LONG Voided BIT Figure 9: Entity-Relationship Diagram
  • 38. 12. Data Flow Diagram Changes required 2. Pharmacist Maintain Update Ok Customer Process Transaction Sale Ok Response Customers 1. Process Transaction Products Product Categories 4. Add/update Product Changes required Transactions Update Ok 3. Changes required Add/update Company Product auditor Category Update Ok Figure 10: Data Flow Diagram
  • 39. 13. System Architectural Diagrams The Electronic Product Sale Logging System will tie into the existing IBM POS System. The diagram below shows a high-level view of the overall system. Figure 11: Proposed System Architecture As indicated in the diagram, the POS Controllers will interface with the new database application to provide a real-time ephedrine logging process, which will initiate from the POS terminal. The transaction process will be coordinated between the POS controller and the database to provide approvals, log transactions and track customer specific purchase information to maintain compliance with regulatory officials. Management can use its existing PCs to generate reports via the POS controllers, which will pull data from the database server in Wheeling.
  • 40. 14. Project Risk and Risk Management A-Team strives to integrate consistent practical risk management and loss management standards of the highest quality into all our business processes. We firmly believe in our ability to develop strategies to manage and mitigate risk if in case it should arise. The following, are the processes to manage project risks: • Risk Management Planning • Risk Identification • Qualitative/Quantitative Risk Analysis • Risk Response Planning • Monitoring and Control The purpose of these processes is to influence the probability and impact of risks. 14.1. Risk Management Planning We have identified possible risks associated with the Electronic Logbook Application and prioritized them whereby the risks with the greatest loss and the greatest probability of occurring are tended to first and risks with a lower probability of occurrence are tended to in descending order.
  • 41. Risk Environmental Impact Probability Risk Response component Variable Scheduling and Unrealistic project Moderate High Implement Further Actions to Reduce Budget Risks schedule delays Risk; Continue Existing Controls; Generate Contingency Plan; Review at least every 3 Months Unrealistic project Significant High Take Immediate Further Remedial budget overrun Action to Reduce Risk; Contingency plan on standby; Review at least Monthly Project canceled prior Significant Medium Quickly Implement Further Actions to to completion Reduce Risk; Continue Existing Controls; Generate Contingency Plan; Review at least every 2 Months System Developing wrong user Minor Medium Tolerate; Continue existing Simple Functionality interface Control Measures; Review at least Risks every 6 Months Develop wrong Minor Low Tolerate; No action: Continue Control software functions if Required; review at least Annually Real-time performance Moderate Very High Quickly Implement Further Actions to shortfalls Reduce Risk; Continue Existing Controls; Generate Contingency Plan; Review at least every 2 Months Requirements Unmet user Moderate High Implement Further Actions to Reduce Management requirements Risk; Continue Existing Controls; Risks Generate Contingency Plan; Review at least every 3 Months Gold Plating Minor Very Low Tolerate; No action: Continue Control if Required; review at least Annually Continuous Significant Very High Take Immediate Further Remedial requirement changes Action to Reduce Risk; Contingency plan on standby; Review Continuously Resource Usage Hardware/Software Minor Very Low Tolerate; No action: Continue Control And technology upgrades if Required; review at least Annually Performance Straining computer Moderate Medium Tolerate; Continue existing Control Risks science capabilities Measures; Possible Contingency Plan; Review at least every 4 months Personnel Insufficient expertise Significant Low Tolerate; Continue existing Control Management and expectations for Measures; Possible Contingency Plan; Risks personnel Review at least every 4 months Personnel shortfalls Significant High Take Immediate Further Remedial Action to Reduce Risk; Contingency plan on standby; Review at least Monthly Project manager’s Significant Very Low Tolerate; Continue existing Control training/Experience Measures; Possible Contingency Plan; Review at least every 4 months
  • 42. * The Probability is identified as 'Very Low', 'Low', 'Medium', 'High' and 'Very High’. However, it must be considered that very low probabilities may not be very reliable. Green - minor, no harm event or near miss, requires no follow-up Yellow - moderate event or near miss, requires local management action Red - significant event or near miss, requires senior management attention 14.2. Qualitative/Quantitative Risk Analysis Qualitative risk analysis is the cost-effective process of assessing the impact and likelihood of identified risk. It prioritizes risks according to their potential effect on project objectives. Quantitative risk analysis is the process of numerically rating the probability of each risk and its consequence on project objectives. 14.2.1. Risk Response Planning This process employs a number of different techniques to reduce and mitigate risk on projects (Stoeller, 2003): • Risk acceptance - project team decides not to change project plan and “accepts” the risk. Active acceptance includes developing a contingency plan. Passive acceptance leaves project team to deal with risk if it occurs. • Risk avoidance - involves changing the project plan to eliminate the risk such that the risk no longer exists. • Risk mitigation - involves a mix of techniques aimed at either reducing the probability or impact of a risk. • Risk transfer - involves transfer of ownership of the risk to another party with the right skills that is available. • Risk reserves are buffers in our schedules and budgets set aside for alligators or puppies. 14.2.2. Monitoring and Control This process monitors newly arising risks, and tracks existing risks and trigger conditions during the project lifecycle. Project managers perform this process in order to determine: • Determine if risk responses were implemented as planned. • Determine if response actions are as effective as expected. • Determine if project assumptions are still valid. • Determine if risk exposure has changed. • Determine if a risk trigger has occurred. • Determine if an unidentified risk has occurred (Holtzman, 2004).
  • 43. 15. Project Costs, Staffing, Resources, Dependencies and Schedule The Cost Analysis presents the costs for materials, design, development, testing, training, implementation and maintenance for the system to be developed. It is expected that each team member will work a 40 hour week. For this release the expected budget is $35,555.12. 15.1. Benefits The primary projected benefit of the new system is the cost avoidance of the salaries of the pharmacy staff currently doing this effort. The secondary benefit is the efficiency, speed and accuracy of the reports. The system will provide the tracking reports on the first day of the new month rather than inconsistent days into the month as prior. Accuracy in the data stored will vastly improve due to elimination of most manual errors currently entered. The primary benefit is the current cost to Smith’s of the personnel manually entering data. Per our meetings and reports provided by Smith’s, it’s apparent that about 25% of an employee’s time is spent manually entering data and trying to validate it in-case it isn’t legible. Therefore, we estimate that 75% of the time for each of Smith’s locations would be available for other duties. We anticipate that the proposed solution will eliminate approximately 20% of the current effort. Therefore, the annual cost avoidance of each store will be equal to 20% of the annual cost of an employee’s salary. Annual Burdened Cost (BC) Cost Avoidance Factor (CA) # of Workers Annual Cost Avoidance $70,000 0.20 10 $140,000 Figure 12: Annual Cost Avoidance
  • 44. 15.2. Bill of Materials This section provides a bill of materials elements required for Smith’s Electronic Product Logging System. Component Description Quantity Price Dell PowerEdge 1950 Dual Core Intel® Xeon® 5148LV, 4MB Cache, 2.33GHz, 1333MHz FSB,ES, 1 $3,537.37 Server Windows Server® 2003 R2, Standard Edition with SP2, Includes 5 CALs Microsoft Windows Server management operating system. 1 *Free Server 2003 Microsoft Visual Studio Development software for applications, websites, service, etc. 1 $0 .Net 2005 Microsoft SQL Server SQL Server Management Studio Express, for easily managing a database. 1 Free 2005 Express Totals $3,537.37 *Windows Server 2003 is included with Dell PowerEdge 1950 Server Figure 13: Bill of Materials
  • 45. 15.3. Triple Cost Analysis Three alternatives were considered for developing, designing and maintaining the new system. The alternatives and their estimated present value costs for a year are as follows. • Minimal Alternative - $26,068. This solution focuses on rapid project delivery date and minimal training costs. • Recommended Alternative - $32,018. This solution focuses on the best project delivery schedule, minimal delays and interference with current work. • Maximum Alternative - $55,959. This solution focuses on maximum benefits for the new system with an extended schedule life. Life Cycle Costs of Project Alternatives Minimal Recommended Maximum Alternative Alternative Alternative Define Requirements $1,928 $2,689 $7,035 Designs Costs $4,459 $6,139 $10,400 Development Costs $8,660 $9,740 $12,640 Testing Costs $4,988 $5,698 $12,480 Training costs $1,768 $1,829 $4,440 Implementation Costs $4,265 $5,924 $8,964 Warranty Costs $0 $0 $0 Total Life Cycle Costs $ 26,068 $32,018 $55,959 Figure 14: Life Cycle Costs
  • 46. 15.4. Return on Investment Analysis Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Initial Costs $ (35,555.12) Maintenance $ (2,000.00) $ (2,200.00) $ (2,420.00) $ (2,662.00) $ (2,928.00) Discount Rate @ 14% 1.00 0.88 0.77 0.67 0.59 0.52 Discounted Costs $ (35,555.12) $ (1,754.39) $ (1,692.83) $ (1,633.43) $ (1,576.12) $ (1,520.71) Cumulative Costs $ (35,555.12) $ (37,309.51) $ (39,002.33) $ (40,635.77) $ (42,211.88) $ (43,732.59) Benefit Revenue $ - $ 140,000.00 $ 145,600.00 $ 151,424.00 $ 157,481.00 $ 163,780.00 Discount Rate @ 14% 1.00 0.88 0.77 0.67 0.59 0.52 Discounted Benefits $ - $ 122,807.02 $ 112,034.47 $ 102,206.89 $ 93,241.39 $ 85,062.20 Cumulative Benefits $ - $ 122,807.02 $ 234,841.49 $ 337,048.38 $ 430,289.77 $ 515,351.97 Cost-Benefit $ (35,555.12) $ 85,497.51 $ 195,839.16 $ 296,412.61 $ 388,077.89 $ 471,619.38 Payback Period = $35,555 / $85,498 Payback 0.42 Return-on-Investment = $471,619 / $43,733 ROI 235.68% Net Present Value = $515,352 + ($43,733) NPV $471,619 Figure 15: ROI Analysis
  • 47. 15.5. Project Schedule 1. Requirements 6.2.3.Update POS Terminals 1.1. Document Requirements 6.2.4.Perform Smoke Test 1.2. Requirements Review 6.3. Milestone: Installation Complete 1.3. Approve Requirements 7. Warranty Contingency 1.4. Milestone: Requirements Defined 8. Milestone: Project Complete 2. Design 2.1. Develop Design 2.2. Design Review 2.3. Approve Design 2.4. Milestone: Completed Design 3. Development 3.1. Develop Database Components 3.2. Develop Web Components 3.3. Develop POS Terminal Components 3.4. Unit Testing 3.5. Code Review 3.6. Milestone: Development Complete 4. Testing 4.1. Write Test Scripts 4.2. Test Script Review 4.3. Approve Test Scripts 4.4. Milestone: Test Scripts Developed 4.5. Setup Test Environment 4.6. Perform Functional Testing 4.7. Review Results 4.8. Approve Results 4.9. Milestone: Testing Complete 5. Training 5.1. Reset Testing Environment 5.2. Develop Training Plan 5.3. Train Plan Review 5.4. Approval Training Plan 5.5. Milestone: Training Plan Document 5.6. Perform Training 5.7. Training Teachback 5.8. Milestone: Training Complete 6. Implementation 6.1. Hardware Installation 6.1.1.Procurement 6.1.2.Configuration 6.1.3.Test 6.1.4.Milestone: Hardware Installed 6.2. Software Installation 6.2.1.Install SQL Server 2005 6.2.2.Install IIS
  • 48. Project Staffing Position No. of Duties Answers to Positions Smith’s 1 Monitor the overall operation and plan for future Smith’s President Management opportunities. Pharmacist 1 Manage the day-to-day operations of the electronic Smith’s Manager logbook system. Project Manager 1 Manage/Monitor the Information Systems needs of A-Team Consultants the operation. Management Software Engineer 1 Develop/Maintain system Project Manager Systems Architect 1 Develop/Maintain system Project Manager Network Engineer 1 Develop/Maintain system Project Manager QA Tester 1 Test system Project Manager Figure 16: Project Staffing
  • 49. 16. Integration of Internal/External Systems The integration of the new Ephedrine product database with Smith’s existing IT infrastructure requires some additional application programming to create a web services environment that will communicate with the existing IBM 300 series POS system. The goal is to invoke the database application using the existing POS so that the existing system is enhanced, not replaced. The Electronic Product Sale Logging System will tie into an existing IBM POS300 Point of Sale System currently in operation at Smith’s Pharmacy. The application system will be installed on each POS controller to tie in with the existing POS software. Based on the DBMS structures and stored procedures, a web server will connect to the DBMS to execute the stored procedures. The website will expose some web services than the POS system will consume. The POS system will send parameters to the web service and handle the response activity for the POS terminal. Figure 17: Integration of Internal and External Systems and Services
  • 50. 17. System Administration, Security, Backup and Recovery 17.1. Policy Smith’s Pharmacy secures its I.T. assets to protect corporate information and protect the privacy of such information. With the integration of the new online logbook tracking system, the integrity of this secure environment must be maintained. All networked computer and POS data is considered confidential and property of Smith’s Pharmacy, Inc. 17.2. Account Management Internal accounts are maintained for e-mail and management of the POS system. Managers are equipped with a laptop for management purposes. This laptop contains a Windows domain account, which is maintained on an Active Directory domain server in Wheeling. In addition, each POS terminal contains a logon capability for each cashier. All Cashiers (Including Pharmacists) have a user account maintained in the domain controller for logon to the POS terminals. 17.3. Administrative To ensure all Administrative accounts with elevated access privileges on computers, network devices, and other critical equipment (example: accounts used by system administrators and network managers) are used only for their intended administrative purpose, all authorized Users must be made aware of the responsibilities associated with the use of privileged special access accounts and comply with all associated policies, standards, and /or procedures established by the company.
  • 51. 17.4. Backup Recovery of Network Servers and Data The Wheeling, West Virginia site has a small tape backup system consisting of a single tape drive (installed within a single Dell 1850 rack mounted server). The tape drive’s daily data backup routine is managed using an EMC product called “Retrospect.” This tape management software product is geared toward small and medium sized business. As a part of the daily backup routine, store managers are responsible for changing the data tapes. Tapes are rotated offsite in a 3-week rotation. A single week’s tapes (five tapes), 2 weeks out of rotation are stored offsite with a local tape archive company in a controlled environment to protect the physical integrity of the tape. These tapes may be recalled at any time for any reason should the need arise to restore lost files. Figure 18: Tape Backup Rotation
  • 52. The current backup system protects e-mail, files from the POS controllers and user account information for the local area network. The new logbook system will require backup of database information stored in the new Microsoft SQL database. The current capacity of the tape will support the additional data, but as the size of the database grows, future consideration might be made to expand the tape backup capability by adding an additional tape drive and expanding the terms of the contract for offsite storage to accommodate the additional tapes. As shown in the diagram below, the Exchange e-mail server mailboxes, POS controller data and network directories are backed up. The SQL database backup will be added to the daily data backup prior to go-live for the new application. Figure 19: EMC Retrospect Configuration 17.5. Microsoft SQL Server 2005 Backup To provide a complete disaster recovery option for the new application, a proper backup of the Microsoft SQL database must be performed. Microsoft’s specific recommendations for backup (and restore) of the SQL 2005 database can be found at http://technet.microsoft.com/en- us/library/ms187048.aspx and http://technet.microsoft.com/en-us/library/ms186289.aspx.