                  BASIC PRINCIPLES OF SHUTDOWN
                        SCHEDULING IN SAP

           ______________________________________________________________________




Printed: February 5, 2011
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc
Last Modified: 2/3/2011 01:07:00 AM                            Draft
Gentile Consulting Inc.


Table of Contents
1.0Purpose                                                                               2

2.0Scope                                                                                 2

3.0Discussion                                                                            3

4.0Summary/Conclusions                                                                  12




1.0 Purpose
The purpose of this document is to introduce the concepts and techniques required to
effectively schedule shutdown work entirely within SAP. It is not intended to be a step by
step instruction manual. Specific business processes are developed in detail for each
organization however, it is important for everyone to understand the concepts involved and
how their everyday activities affect the schedule. Using SAP will allow live real-time
schedule reports and status to be available to everyone with access to SAP.
2.0      Scope

This document will cover the following topics:

    •    Why it is necessary to schedule work in SAP
    •    Introduction to the “WINDOWS” concept of scheduling.
    •    Introduction to SAP “Networks”
    •    Integration of SAP Networks and Work Orders to create a schedule.
    •    Introduction to on-line reports for all levels of the organization.




Printed: February 5, 2011                                   2
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




3.0      Discussion


Why schedule in SAP

SAP is a fully integrated software system in which various modules share a common
database. This means that the information that a planner puts on a work order provides
data that is used by all modules of the program. The system will automatically order parts
and services, make demands on work groups resources, provide input to the financial
planning groups, all based on the dates of the work order operations.

If the dates on the work order are incorrect, the basic functionality of SAP is diminished
and the company cannot realize the improvements and benefits it expected when it made
the investment in SAP. Incorrect dates on the work order will supply incorrect data to all
the modules seen below.




Printed: February 5, 2011                                   3
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




The “WINDOWS” concept of scheduling

Window scheduling is a technique that is used by many industries regardless of the
scheduling tool being used. Consider the following sequence of events.


       Reduce Steam Demand to                Secure Boiler Feed Pump                                     Reduce Steam Demand to
                           50%                                         #1                                                    10%




                                                                                           Boiler Feed
                                                                                         Pump #1 Work
                                                                                              Window




  Secure Main Steam Header            Hydro Main Steam Header               Increase Steam Demand to
                                                                                                                                   Start Boiler Feed Pump #1
                             #1                                 #1                                50%




The scenario in the above illustration describes reducing the output of a boiler to facilitate
the hydrostatic testing of a steam header. The “Work Window” depicted in red is that
period in time when #1 Boiler Feed Pump is available for maintenance without effecting
the overall duration of the hydrostatic testing evolution.




Printed: February 5, 2011                                   4
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Project Systems Networks

A network is a structure the Project Systems module that contains specific work
instructions similar to the work order in the Plant Maintenance module. These work
instructions are referred to as activities. The network activities may be logic tied and
scheduled. A simple network is illustrated graphically below.




Printed: February 5, 2011                                   5
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Subnetworks


It is possible to add more details to your network by creating subnetworks to
network activities. In the example below a project network was created with the
high level network consisting of design, installation and closeout activities. More
detail was added by adding a subnetwork to the installation activity.




You can use subnetworks to refine and detail your networks as planning
progresses. You create subnetworks by breaking down a network activity into one
or more subnetworks. The system treats subnetworks and networks the same, that
is, you can plan dates, capacities, costs, materials and production resource/tools
also with a subnetwork.




Printed: February 5, 2011                                   6
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


Network Activities

Network Activities are discrete tasks similar to work order operations with the following
characteristics:

•   They have duration.
•   They have a defined start and a defined finish.
•   Resources are needed to execute them.
•   They incur costs.
•   They are worked without interruption.

There are the following types of activities in Project Systems:

• Internal processed activities (work performed by internal employees)
• Externally processed activities (work performed by external employees)
• Primary costs activities (activity costs that are expected to arise through the
  consumption of goods and services that originate from outside the company




Printed: February 5, 2011                                   7
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.


         Integration of SAP Networks and Work Orders

         PM work orders can be linked to any network or subnetwork activity. When they are
         linked the dates on the work order will be derived from the activity date. When the
         network is scheduled all work orders attached will also be scheduled. This allows
         scheduling personnel to maintain the dates of many orders at once by using a single
         transaction.




Operative Network
Operative Network



Sub Networks
Sub Networks


PM Orders
PM Orders




Printed: February 5, 2011                                   8
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



         Project Systems Reporting



         Now that the PS and PM modules are linked through the networks reports
         can be generated through the PS module that can be used by all levels and
         departments in the organization via a single source. Illustrated below are
         some reports generated by the system.


                                                         Gant Charts




Printed: February 5, 2011                                   9
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                          Work Center Schedules




                                                    Material Reports



Printed: February 5, 2011                                   10
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




                                              Real Time Cost Reports



Printed: February 5, 2011                                   11
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.




         Hundreds of reports involving all work groups can be generated from a
         single transaction in the PS module. Any report generated by external
         scheduling software can be duplicated in SAP.




4.0      Summary/Conclusions

The integration of the PS and PM modules will provide a scheduling capability
previously impossible in the company. This scheduling capability will require little or
no input from the individuals performing the work since all schedule updates occur
through the already implemented conformation process.

The critical success factors involved in this process are:



Printed: February 5, 2011                                   12
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM
Gentile Consulting Inc.



            • All work planned and managed within SAP (Capital, Maintenance,
              Operations)
            • Work orders must contain detailed planning
            • Accurate and timely confirmations of all operations




Printed: February 5, 2011                                   13
/home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc

Last Modified: 2/3/2011 01:07:00 AM

Weitere ähnliche Inhalte

Was ist angesagt?

Application of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPApplication of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPTony Ciliberti PE
 
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...Gaurav Singh Rajput
 
Shutdown Turnaround & Outage management courses
Shutdown Turnaround & Outage management coursesShutdown Turnaround & Outage management courses
Shutdown Turnaround & Outage management coursesWerner Van Acker
 
Operating Excellence is built on Corrective & Preventive Actions
Operating Excellence is built on Corrective & Preventive ActionsOperating Excellence is built on Corrective & Preventive Actions
Operating Excellence is built on Corrective & Preventive ActionsAtanu Dhar
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Aviation MRO IT: Emergence of SaaS and Convergence of BPO
Aviation MRO IT: Emergence of SaaS and Convergence of BPOAviation MRO IT: Emergence of SaaS and Convergence of BPO
Aviation MRO IT: Emergence of SaaS and Convergence of BPOguesta9496c4
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesTKMG, Inc.
 
MaintSmart CMMS Software
MaintSmart CMMS SoftwareMaintSmart CMMS Software
MaintSmart CMMS SoftwareDaniel Cook
 
PMBOK(R) sixth edition data flow diagrams r2
PMBOK(R)  sixth edition data flow diagrams r2PMBOK(R)  sixth edition data flow diagrams r2
PMBOK(R) sixth edition data flow diagrams r2Kose Jumnichi
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityParsec_Automation_Corp
 
Webinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleWebinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleStork
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Anand Subramaniam
 
Business process mapping
Business process mappingBusiness process mapping
Business process mappingDAVIS THOMAS
 
ITIL Service Operation
ITIL Service OperationITIL Service Operation
ITIL Service OperationMarvin Sirait
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 

Was ist angesagt? (20)

PMP Process Chart - 6th Edition
PMP Process Chart - 6th EditionPMP Process Chart - 6th Edition
PMP Process Chart - 6th Edition
 
Application of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAPApplication of ISO 14224 Methods in SAP
Application of ISO 14224 Methods in SAP
 
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...
Root Cause Analysis | 5 whys | Tools of accident investigation I Gaurav Singh...
 
eFACiLiTY Maintenance Management System
eFACiLiTY Maintenance Management SystemeFACiLiTY Maintenance Management System
eFACiLiTY Maintenance Management System
 
Shutdown Turnaround & Outage management courses
Shutdown Turnaround & Outage management coursesShutdown Turnaround & Outage management courses
Shutdown Turnaround & Outage management courses
 
Operating Excellence is built on Corrective & Preventive Actions
Operating Excellence is built on Corrective & Preventive ActionsOperating Excellence is built on Corrective & Preventive Actions
Operating Excellence is built on Corrective & Preventive Actions
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Aviation MRO IT: Emergence of SaaS and Convergence of BPO
Aviation MRO IT: Emergence of SaaS and Convergence of BPOAviation MRO IT: Emergence of SaaS and Convergence of BPO
Aviation MRO IT: Emergence of SaaS and Convergence of BPO
 
Value Stream Mapping: Case Studies
Value Stream Mapping: Case StudiesValue Stream Mapping: Case Studies
Value Stream Mapping: Case Studies
 
MaintSmart CMMS Software
MaintSmart CMMS SoftwareMaintSmart CMMS Software
MaintSmart CMMS Software
 
PMBOK(R) sixth edition data flow diagrams r2
PMBOK(R)  sixth edition data flow diagrams r2PMBOK(R)  sixth edition data flow diagrams r2
PMBOK(R) sixth edition data flow diagrams r2
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
Webinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycleWebinar | APM Best Practices - Effectively managing the safety lifecycle
Webinar | APM Best Practices - Effectively managing the safety lifecycle
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
 
Business process mapping
Business process mappingBusiness process mapping
Business process mapping
 
ITIL Service Operation
ITIL Service OperationITIL Service Operation
ITIL Service Operation
 
Maintenance Work Order
Maintenance Work OrderMaintenance Work Order
Maintenance Work Order
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
PPAP
PPAPPPAP
PPAP
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 

Andere mochten auch

Turnaround Project Planner Primer
Turnaround Project Planner PrimerTurnaround Project Planner Primer
Turnaround Project Planner Primerahmad bassiouny
 
technical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europetechnical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europeT.A. Cook
 
Planning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages WorkshopPlanning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages WorkshopLife Cycle Engineering
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenancejdparfett
 
Managing A Synergistic Shutdown Team
Managing A Synergistic Shutdown TeamManaging A Synergistic Shutdown Team
Managing A Synergistic Shutdown Teamjdparfett
 
Turnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry ServicesTurnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry Servicesraghunathan janarthanan
 
Employee benefits in oil & energy industry
Employee benefits in oil & energy industryEmployee benefits in oil & energy industry
Employee benefits in oil & energy industryraghunathan janarthanan
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1Jahanzeb Khan
 
Smart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and GasSmart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and GasKelly Stark
 
Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017Ian Kennedy
 
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPSBGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPSJonathan Danker
 
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Chemical Petroleum
 
Data - the Oil & Gas asset that isn’t managed like one
Data  - the Oil & Gas asset that isn’t managed like oneData  - the Oil & Gas asset that isn’t managed like one
Data - the Oil & Gas asset that isn’t managed like oneMolten2013
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramLife Cycle Engineering
 
Introduction to Reliability Excellence
Introduction to Reliability ExcellenceIntroduction to Reliability Excellence
Introduction to Reliability ExcellenceLife Cycle Engineering
 
Heat-exchanger-manual
Heat-exchanger-manualHeat-exchanger-manual
Heat-exchanger-manualAbdelrhman K.
 
Ibm turn around strategy
Ibm turn around strategyIbm turn around strategy
Ibm turn around strategyKaran Shah
 

Andere mochten auch (20)

Turnaround Project Planner Primer
Turnaround Project Planner PrimerTurnaround Project Planner Primer
Turnaround Project Planner Primer
 
Plant shutdown
Plant shutdownPlant shutdown
Plant shutdown
 
technical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europetechnical services for turnarounds in petrochemical plants in western europe
technical services for turnarounds in petrochemical plants in western europe
 
Planning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages WorkshopPlanning for Shutdowns, Turnarounds and Outages Workshop
Planning for Shutdowns, Turnarounds and Outages Workshop
 
Scheduled Shutdown Maintenance
Scheduled Shutdown MaintenanceScheduled Shutdown Maintenance
Scheduled Shutdown Maintenance
 
Managing A Synergistic Shutdown Team
Managing A Synergistic Shutdown TeamManaging A Synergistic Shutdown Team
Managing A Synergistic Shutdown Team
 
Turnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry ServicesTurnarounds for process plants/ Industry Services
Turnarounds for process plants/ Industry Services
 
Employee benefits in oil & energy industry
Employee benefits in oil & energy industryEmployee benefits in oil & energy industry
Employee benefits in oil & energy industry
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
 
MAOP Process Validation
MAOP Process ValidationMAOP Process Validation
MAOP Process Validation
 
Smart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and GasSmart Asset Solution for Oil and Gas
Smart Asset Solution for Oil and Gas
 
Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017Arcadis capabillity statement summary feb 2017
Arcadis capabillity statement summary feb 2017
 
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPSBGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
BGC-CONTRACTING-MAINTENANCE-SERVICES-DPS
 
IBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industryIBM Maximo Asset Management solutions for the oil and gas industry
IBM Maximo Asset Management solutions for the oil and gas industry
 
Data - the Oil & Gas asset that isn’t managed like one
Data  - the Oil & Gas asset that isn’t managed like oneData  - the Oil & Gas asset that isn’t managed like one
Data - the Oil & Gas asset that isn’t managed like one
 
Maintenance Management Certification
Maintenance Management CertificationMaintenance Management Certification
Maintenance Management Certification
 
Shutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement ProgramShutdown Turnaround and Outage Competency Improvement Program
Shutdown Turnaround and Outage Competency Improvement Program
 
Introduction to Reliability Excellence
Introduction to Reliability ExcellenceIntroduction to Reliability Excellence
Introduction to Reliability Excellence
 
Heat-exchanger-manual
Heat-exchanger-manualHeat-exchanger-manual
Heat-exchanger-manual
 
Ibm turn around strategy
Ibm turn around strategyIbm turn around strategy
Ibm turn around strategy
 

Ähnlich wie SAP shutdown scheduling basics

SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...BIWUG
 
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practicesSPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practicesKnut Relbe-Moe [MVP, MCT]
 
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1Knut Relbe-Moe [MVP, MCT]
 
Lotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes ClientLotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes Clientpanagenda
 
Paremus service fabric
Paremus service fabricParemus service fabric
Paremus service fabricpjhInovex
 
Task Management for OpenNTF
Task Management for OpenNTFTask Management for OpenNTF
Task Management for OpenNTFRolf Kremer
 
Convio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without TearsConvio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without Tearsjudisohn
 
J Bdemo101215
J Bdemo101215J Bdemo101215
J Bdemo101215kgirt
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...p6academy
 
Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2gabrielsyst
 
Database performance management
Database performance managementDatabase performance management
Database performance managementscottaver
 
Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...Shantanu Thakre
 
Easy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deploymentEasy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deploymentBert Hajee
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docxjeanettehully
 
Why your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updatedWhy your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updatedDaniel Graversen
 

Ähnlich wie SAP shutdown scheduling basics (20)

SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
SharePoint Saturday Belgium 2014 SharePoint Upgrade, real life experience and...
 
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practicesSPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
SPSBE14 SPSBE02 SharePoint Upgrade reel life experience, best practices
 
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
SPS Dubai Best Practice upgrading SharePoint from 2007/2010 to 2013 and 2013 SP1
 
resume
resumeresume
resume
 
Lotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes ClientLotusphere 2012: BP110 Performance Boost for your Notes Client
Lotusphere 2012: BP110 Performance Boost for your Notes Client
 
Tyco IS Oracle Apps Support Project
Tyco IS Oracle Apps Support ProjectTyco IS Oracle Apps Support Project
Tyco IS Oracle Apps Support Project
 
IETM Development Process.pdf
IETM Development Process.pdfIETM Development Process.pdf
IETM Development Process.pdf
 
Paremus service fabric
Paremus service fabricParemus service fabric
Paremus service fabric
 
Task Management for OpenNTF
Task Management for OpenNTFTask Management for OpenNTF
Task Management for OpenNTF
 
Convio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without TearsConvio Summit 2011 - CG Admin Without Tears
Convio Summit 2011 - CG Admin Without Tears
 
Report final
Report finalReport final
Report final
 
J Bdemo101215
J Bdemo101215J Bdemo101215
J Bdemo101215
 
Project portfolio management comparison of microsoft epm and primavera p6 v...
Project portfolio management   comparison of microsoft epm and primavera p6 v...Project portfolio management   comparison of microsoft epm and primavera p6 v...
Project portfolio management comparison of microsoft epm and primavera p6 v...
 
Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2Sap plant-maintenance-pm-business-blueprint-bbp2
Sap plant-maintenance-pm-business-blueprint-bbp2
 
Database performance management
Database performance managementDatabase performance management
Database performance management
 
Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...Understanding the basic need of Service Oriented Architecture and getting sta...
Understanding the basic need of Service Oriented Architecture and getting sta...
 
Easy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deploymentEasy oracle & weblogic provisioning and deployment
Easy oracle & weblogic provisioning and deployment
 
M tierney res
M tierney resM tierney res
M tierney res
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Why your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updatedWhy your SAP PI/PO system should be updated
Why your SAP PI/PO system should be updated
 

SAP shutdown scheduling basics

  • 1. Draft BASIC PRINCIPLES OF SHUTDOWN SCHEDULING IN SAP ______________________________________________________________________ Printed: February 5, 2011 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM Draft
  • 2. Gentile Consulting Inc. Table of Contents 1.0Purpose 2 2.0Scope 2 3.0Discussion 3 4.0Summary/Conclusions 12 1.0 Purpose The purpose of this document is to introduce the concepts and techniques required to effectively schedule shutdown work entirely within SAP. It is not intended to be a step by step instruction manual. Specific business processes are developed in detail for each organization however, it is important for everyone to understand the concepts involved and how their everyday activities affect the schedule. Using SAP will allow live real-time schedule reports and status to be available to everyone with access to SAP. 2.0 Scope This document will cover the following topics: • Why it is necessary to schedule work in SAP • Introduction to the “WINDOWS” concept of scheduling. • Introduction to SAP “Networks” • Integration of SAP Networks and Work Orders to create a schedule. • Introduction to on-line reports for all levels of the organization. Printed: February 5, 2011 2 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 3. Gentile Consulting Inc. 3.0 Discussion Why schedule in SAP SAP is a fully integrated software system in which various modules share a common database. This means that the information that a planner puts on a work order provides data that is used by all modules of the program. The system will automatically order parts and services, make demands on work groups resources, provide input to the financial planning groups, all based on the dates of the work order operations. If the dates on the work order are incorrect, the basic functionality of SAP is diminished and the company cannot realize the improvements and benefits it expected when it made the investment in SAP. Incorrect dates on the work order will supply incorrect data to all the modules seen below. Printed: February 5, 2011 3 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 4. Gentile Consulting Inc. The “WINDOWS” concept of scheduling Window scheduling is a technique that is used by many industries regardless of the scheduling tool being used. Consider the following sequence of events. Reduce Steam Demand to Secure Boiler Feed Pump Reduce Steam Demand to 50% #1 10% Boiler Feed Pump #1 Work Window Secure Main Steam Header Hydro Main Steam Header Increase Steam Demand to Start Boiler Feed Pump #1 #1 #1 50% The scenario in the above illustration describes reducing the output of a boiler to facilitate the hydrostatic testing of a steam header. The “Work Window” depicted in red is that period in time when #1 Boiler Feed Pump is available for maintenance without effecting the overall duration of the hydrostatic testing evolution. Printed: February 5, 2011 4 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 5. Gentile Consulting Inc. Project Systems Networks A network is a structure the Project Systems module that contains specific work instructions similar to the work order in the Plant Maintenance module. These work instructions are referred to as activities. The network activities may be logic tied and scheduled. A simple network is illustrated graphically below. Printed: February 5, 2011 5 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 6. Gentile Consulting Inc. Subnetworks It is possible to add more details to your network by creating subnetworks to network activities. In the example below a project network was created with the high level network consisting of design, installation and closeout activities. More detail was added by adding a subnetwork to the installation activity. You can use subnetworks to refine and detail your networks as planning progresses. You create subnetworks by breaking down a network activity into one or more subnetworks. The system treats subnetworks and networks the same, that is, you can plan dates, capacities, costs, materials and production resource/tools also with a subnetwork. Printed: February 5, 2011 6 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 7. Gentile Consulting Inc. Network Activities Network Activities are discrete tasks similar to work order operations with the following characteristics: • They have duration. • They have a defined start and a defined finish. • Resources are needed to execute them. • They incur costs. • They are worked without interruption. There are the following types of activities in Project Systems: • Internal processed activities (work performed by internal employees) • Externally processed activities (work performed by external employees) • Primary costs activities (activity costs that are expected to arise through the consumption of goods and services that originate from outside the company Printed: February 5, 2011 7 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 8. Gentile Consulting Inc. Integration of SAP Networks and Work Orders PM work orders can be linked to any network or subnetwork activity. When they are linked the dates on the work order will be derived from the activity date. When the network is scheduled all work orders attached will also be scheduled. This allows scheduling personnel to maintain the dates of many orders at once by using a single transaction. Operative Network Operative Network Sub Networks Sub Networks PM Orders PM Orders Printed: February 5, 2011 8 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 9. Gentile Consulting Inc. Project Systems Reporting Now that the PS and PM modules are linked through the networks reports can be generated through the PS module that can be used by all levels and departments in the organization via a single source. Illustrated below are some reports generated by the system. Gant Charts Printed: February 5, 2011 9 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 10. Gentile Consulting Inc. Work Center Schedules Material Reports Printed: February 5, 2011 10 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 11. Gentile Consulting Inc. Real Time Cost Reports Printed: February 5, 2011 11 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 12. Gentile Consulting Inc. Hundreds of reports involving all work groups can be generated from a single transaction in the PS module. Any report generated by external scheduling software can be duplicated in SAP. 4.0 Summary/Conclusions The integration of the PS and PM modules will provide a scheduling capability previously impossible in the company. This scheduling capability will require little or no input from the individuals performing the work since all schedule updates occur through the already implemented conformation process. The critical success factors involved in this process are: Printed: February 5, 2011 12 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM
  • 13. Gentile Consulting Inc. • All work planned and managed within SAP (Capital, Maintenance, Operations) • Work orders must contain detailed planning • Accurate and timely confirmations of all operations Printed: February 5, 2011 13 /home/pptfactory/temp/20110205194001/shutdownscheduling-12969347797599-phpapp02.doc Last Modified: 2/3/2011 01:07:00 AM