User Preference in Primavera P6 EPPM Complete Look through
User preference page which can be accessed by going to
‘administer-> My Preferences’ option, if the user you are logged in
have enough rights to access this page is specifically designed to customize the way the user
uses the EPPM features. As the name “My preference” goes the My Preferences section lets
you to customize the data display format across all sections of P6. The options you customize
are set exclusively only for you.
There are three main tabs provided for easy customization
1.Global
:- This is the main tab in the User Preference page, It is here
where you’ll be doing all the page settings. You can alter global preferences, including
formats for time units, dates, and currencies. For ex: to set whether you want to inform the
resource via email if a new assignment is made to them or to set the base currency you will
use throughout your project assignment and many more.
2.View
:- You can also customize view preferences if the P6
Administrator gives you access to do so. This tab presents you all the pages which are
accessible by you. You could either turn those visible by checking on the checkbox or turn it
off by making them unchecked. Some view preferences you can customize include menu
items and pages.
3.Password
:-If you were wondering as of how to change the password
provided as it was somehow disclosed or you had enough with you old password. This is the
place created for you. Just provide your old password once and the fresh password twice.
Done , you can now sign in to your P6 login page with your new password.

Fig 1:My Preferences-> Password tab
Fig 2: User Preference-> View tab
We’ll be reviewing the settings you could make with Global tab in the following section.
global preferences could be Customized to create a working environment that suits your needs. The
global preferences you select affect only your interaction with the application; other users are not
affected by your changes. The global tab in the user preference page is further sub divided into 8
major section. These sub section allows you to customize most of the features provided by P6 EPPM
suite and set those to your own preference.

Fig 3. My Preferences -> Global tab Options
Let’s get into detail of each sub section
1.General section :This Section is mainly provided enable miscellaneous options for P6, such as sending an
e-mail to resources upon adding or removing assignments.

Fig 3.1 My Preferences -> Global tab -> General sections
Let’s get into detail of the various options given in the general section
1.a. Maximum number of rows displayed in each section –
You could Double-click the Maximum number of rows displayed in each
section field and type a value to alter the number of rows displayed in each section. For pages with
standard lists of data (not tables), the number of rows that display together before the list is divided.
Generally, the lower the number, the better performance will be since the user interface is displaying
fewer rows of data.
If the number of items exceed the maximum value which you specified in the field
for Maximum number of rows displayed in each section, a Next link appears for you to navigate to
the next page of the list.i.e for example You specify a value of five in this field. Later, you navigate to
the Portfolio Status page or Project Issues page. Up to five rows will be listed. If more than five rows
of data are available, a [Next >>] link appears for you to navigate to the next five items in the list.
Note: The value you place in the Maximum number of rows displayed in each section setting
will not apply to view or dictionary grids.
This preference does not apply to workspace portlets. To specify the number of rows that
display for lists in the portlets of a specific workspace, customize the workspace.
1.b. Maximum number of rows displayed in trees and picklists –
Double-click the Maximum number of rows displayed in trees and
picklists field and type a value. This field controls the number of elements that display in hierarchical
lists, such as the EPS/project hierarchy in the Open Projects dialog box. If the number of items
available to display exceeds the maximum you specify for Maximum number of rows displayed in
trees and picklists,a message appears to inform you that you are viewing a partial list.
1.c. Send e-mail to resources upon adding or removing assignments –
When a resource is replaced on an activity, an e-mail is sent to the removed
resource and to the replacement resource. When the automatic e-mail option is on, confirmation
messages are sent to you, indicating the names of the recipients. If a resource does not have an email address stored in the project database, no e-mail can be sent. In this case, you will know that
the resource was not notified because you will not receive a confirmation message with that
resource's name.
1.d. Prompt before sending e-mail
Determines whether to prompt you before sending an e-mail.
1.e. Calculate performance and earned value information by
Select from one of the following options to calculate performance and earned
value information. Calculate Performance and Earned Value Information lets you choose whether to
display earned value information, performance indicators, and indices based on cost or labor units.
For example, when you display earned value information on the Portfolios Performance Status tab,
you will see either Costs or Labor Units data, depending on how you set this preference.
 Cost: Select to display earned value information, performance indicators, and indices
based on cost.
 Labor Units: Select to display earned value information, performance indicators, and
indices based on labor units.
1.f. Display actual and earned value using financial period data
Display actual and earned value using financial period data lets you choose to
view information based on past period actuals data that has been stored for custom financial
periods. This option applies to the histogram and spreadsheet displays in the Portfolios Gantt Chart,
Projects Team Usage view, and Resources Usage view.
When you choose this option, stored financial period values for actuals are distributed evenly
from the start to the finish date defined for a financial period and earned value calculations are
based on these stored period quantities.
If you do not choose this option, actuals data is spread evenly from the actual start to the
data date or actual finish date of the activity or assignment.
Note: If you choose this option but period performance has not been stored, total reported
actuals display in the timescale period representing the data date. For more information, contact
your P6 administrator or Project Management Office.
If projects are summarized by financial period (which is controlled in Application Settings in
P6), this option is ignored. When projects are summarized by financial period and you display a
financial period timescale, the profile displays past period actual values if performance has been
stored for a financial period; for financial periods that do not have stored performance, the profile
displays all unit and cost values in financial period intervals.
2.Currency:-

Fig 3.2 My Preferences -> Global tab -> Currency sections
The
Select Currency icon is used to select the currencies available from the
Select Currency dialog box, select a currency and click OK. The checkboxes of Show decimal places
and show currency symbol are checked on to show decimal places or the currency symbol
respectively.
3.Time Units Format:-

Fig 3.3 My Preferences -> Global tab -> Time Units Format section
This section to configure how time is displayed throughout the
application.
Note: P6 calculates and stores time unit values in hourly increments. When you specify a
display time increment other than hours, P6 uses the Hours per Time Period settings from Admin
Preferences or the calendar based on the setting in Application Settings in P6 to convert hours to the
time increment you specify.
3.a. Display Time Units in list
Determines which time unit is used to display time in the application:






Hour: Time units will display in hours.
Day: Time units will display in days.
Week: Time units will display in weeks.
Month: Time units will display in months.
Year: Time units will display in years.
 Show sub units option

Determines whether to show sub units with time units. Select the Show sub
units option to display sub units in the next smaller time increment. This option is also available
with Display Durations in.
 Show unit label option
Determines whether to show the unit abbreviation with time units.
 Decimal places list
Select to display 0, 1, or 2 decimal places. This option is also available
with Display Durations in.
3.b. Display Durations in list
Select to display durations from the following options:






Hour: Durations will display in hours.
Day: Durations will display in days.
Week: Durations will display in weeks.
Month: Durations will display in months.
Year: Durations will display in years.
 Show sub units option
This does the same work as is done in the display time units section.
 Show duration label option
Determines whether to show the time unit abbreviation with the duration
value.
3.c. Units/Time Format
Select one of the following to display resource units/time:
Show as a percentage: Determines whether units/time will display as a percentage.

Show as units/duration: Determines whether units/time will display as
units/duration.


For example, if Robert is assigned a limit of eight hours/day and you assign him to a task at a
maximum limit of two hours/day, you can display this information one of two ways: as 2h/d or as
25 percent of his resource limit (since he is only assigned to this task for two of his allotted eight
hours per day).
4.Date Format:-

Fig 3.4 My Preferences -> Global tab -> Date Format section
4.a. Expand the Date format subsection:
Click the Date format list, and choose a format.
Mark the Date format options for how you want the date to display.
4.b. Expand the Time format subsection:
Click the Time format list, and choose a format.
Mark the Show minutes option if you want minutes to display.
4.c. Click the Separator list, and choose a separator. You can choose from “,” ,”.” Or
“/”
5.Resources:This section is used to configure resource staffing and assignment options.

Fig 3.5 My Preferences -> Global tab -> Resources
5.a. Resource Staffing
Expand this section to choose your resource staffing options.
Automatically summarize project after assigning resources option
Determines whether to summarize a project after you assign resources.
Because availability calculations for resource staffing features are based on summary data,
choosing this option ensures that your staffing decisions are based on the most up-to-date
resource allocation data.
When this feature is enabled, you can check the status of the summarizer job on
the Activities page in the View Service Status dialog box.
Within the resource staffing feature, click on an activity name to show limited activity details,
based on whether you select Display Resource Assignments, Display Notebook, and/or Display
Steps.
An administrative setting is also required to implement this feature. For more information,
contact your P6 administrator.
Display Resource Assignments option
Determines whether to display an activity's resource assignment
details, for example, planned units and remaining units/time.
Display Notebook option
Determines whether to display activity Notebooks when viewing
activity details.
Display Steps option
Determines whether to display activity steps when viewing activity
details.
5.b. Resource Assignments
Expand this section to choose your resource assignment options.
When adding or removing multiple resource assignments on activities options
When adding or removing multiple resource assignments, you can choose to
preserve or recalculate units, duration, and units/time. Choose from the following
options:
 Preserve the Units, Duration, and Units/Time for existing assignments: Choose this
option for units, durations, and units/time to remain constant when additional
resources are assigned to any activity. Regardless of the duration type of an activity,
this equation is always true:
Remaining Units = Remaining Duration x Remaining Units/Time
 Recalculate the Units, Duration, and Units/Time for existing assignments based on
the activity Duration Type: Choose this option to calculate a resource assignment’s
remaining values based on the activity’s duration type, specified in an activity's
General tab.
When assigning a resource to an existing activity assignment options
When selecting a resource to staff an existing role assignment or replacing a
current resource assignment with a different resource, you can choose to always use
the current units/time and overtime factor of the new resource or you can choose to
be prompted every time so you can select the units/time and overtime factor you
want to apply to the assignment. Choose from the following options:
 Always use the new resource's Units/Time and Overtime factor: The manual future
period values of the existing resource assignment may be respread across future
period buckets based on the new resource's values.
 Always use current assignment's Units/Time and Overtime factor: The unit values for
the new resource are spread evenly over future period buckets and the manual future
period values for the existing resource assignment are not changed.
 Ask me to select each time I assign: Every time you make an assignment, the
application will ask whether it should use the units/time and overtime factor for the
new resource or the current assignment
When a resource and role share an activity assignment options
When selecting a resource to staff an existing role assignment or specifying a
role for an existing resource assignment, you can choose to always apply either the
resource or role rate (Price/Unit) to the assignment or you can choose to be prompted
every time so you can select which rate you want to apply. Use the following options:
Note: The assignment Rate Source field indicates whether the resource or role rate is
applied to an assignment. The Rate Source, along with the Rate Type, determines the
price/unit value used to calculate costs for the assignment.
 Always use resource's Price/Unit: The manual future period values for the existing
role assignment may be respread across future period buckets based on the new
resource's values.
 Always use role's Price/Unit: The manual future period values for the existing
resource assignment may be respread across future period buckets based on the new
role's values.
 Ask me to select each time I assign: Every time you make an assignment, the
application will ask whether it should use the resource's or role' price/unit.
Display the role limit based on options
In P6 Optional Client and P6, you can define the maximum availability (limit)
over time for each role in the Roles dictionary. In P6, role limits are displayed in charts,
histograms, and spreadsheets that display role allocation data, such as the Capacity
Planning chart and Role Usage histogram. Use the following options:
 Custom role limit: Determines whether role limits are calculated based on customized
role limits.
 Calculated primary resources' limit: Determines whether role limits are calculated
using the limit defined for each role's primary resource. This is the default option.
5.c. Number of available items to search for Roles, Resources, and Resource Codes field
The number of search criteria items allowed when searching for resources to
staff activities. The maximum valid value is 10.
6. Issues:This section is used to configure e-mail notifications for issues.

Fig 3.6 My Preferences -> Global tab -> Issues
Send me a notification when
The following options are used to determine whether you receive a notification
and when.
 Issues are added with priority of [ ] or higher option
Determines whether issues that are added with a priority you specify from the list are
sent. Value options are Top, High, Normal, Low, and Lowest.
 Issues are assigned issue code field
The issue code that will cause a notification to be sent when it is assigned to an issue.
Note: The Issues are assigned issue code option must be selected to send a
notification.
 Issues are modified option
Determines whether issues that are modified are sent.
Only notify me about Issues for Projects and Workgroups if I
The following options determine whether you are notified about issues for Projects
and Workgroups when one or multiple selections are made:
 Have project access rights option
Determines whether you are notified about issues for Projects and Workgroups if you
have Project access rights.
 Have issue access rights option
Determines whether you are notified about issues for Projects and Workgroups if you
have Issue access rights.
 Am the Project Owner option
Determines whether you are notified about issues for Projects and Workgroups if you
are the Project Owner.
 Am the Issue Owner option
Determines whether you are notified about issues for Projects and Workgroups if you
are the Issue Owner.
 Am assigned as a resource to that activity option
Determines whether you are notified about issues for Projects and Workgroups if you
are assigned as a resource to the specified activity.
7.Project Score:This section is used to configure how the project score is calculated.

Fig 3.7 My Preferences -> Global tab -> Project Score
Calculate Project Score based on selected Project Codes option
Determines whether to calculate project scores based on project codes.
o Project Codes link
Displays a dialog box with configurable options to determine what project code
to select for the project score..


High is greater than or equal to: field
The high value will be greater than or equal to the value entered in this field.



Medium is greater than or equal to: field
The medium value will be greater than or equal to the value entered in this field.



Low is greater than:0
Indicates that the low value must be greater than 0.

8.Performance Threshold:This section is used to specify parameters for Performance, Earned Value, and
Index values that appear in dashboard Project Performance portlets and on the
Portfolios Performance Status tab. The settings you specify in Global Preferences only
apply to the dashboard portlets; for each project, you can specify project-specific
Performance Threshold settings when you customize the project Workspace.
Performance section
Use the options in this section to define what is
considered Exceptional, Warning, or Critical when assessing schedule performance for
a project, WBS, or EPS. The values you specify determine which indicators apply to the
Schedule to date, Labor units to date, Schedule at completion, and Labor units at
completion metrics.


Exceptional: For schedule values, the minimum number of days that the project,
WBS, or EPS must be ahead of schedule to be considered exceptional. For labor units,
the minimum percentage under 100 that the labor units variance must be less than to
display the exceptional indicator. For example, if you set the exceptional threshold at
10% and the actual labor units variance is 85%, then that item would be considered
exceptional.



Warning: For a schedule value, the minimum number of days that the project,
WBS, or EPS must be behind schedule to display the warning indicator. For labor units,
the minimum percentage over 100 that the labor units variance must be greater than
to display the warning indicator.
Critical: For a schedule value, the minimum number of days that the project,
WBS, or EPS must be behind schedule to display the critical indicator. For labor units,
the minimum percentage over 100 that the labor units variance must be greater than
to display the critical indicator. Some examples of threshold percentage calculations
are as follows:
Labor units to date equals (Earned Value Labor Units minus Actual Labor
Units) divided by Earned Value Labor Units
Labor units at completion equals (Budget At Completion Labor
Units minus Estimate At Completion Labor Units) divided by Budget At Completion
Labor Units
Earned Value section
Use the options in this section to define what is
considered Exceptional, Warning, and Critical when assessing earned value
performance for a project, WBS, or EPS. The values you specify determine which
indicators apply to the Schedule to date, Labor units to date, Schedule at completion,
and Labor units at completion metrics.



Exceptional: The minimum percentage under 100 that the schedule or labor units
variance must be less than to display the exceptional indicator. For example, if you set
the exceptional threshold at 10% and the actual earned value variance is 85%, then
that item would be considered exceptional.



Warning: The minimum percentage over 100 that the schedule or labor units
variance must be greater than to display the warning indicator.



Critical: The minimum percentage over 100 that the schedule or labor units
variance must be greater than to display the critical indicator.
Fig 3.8 My Preferences -> Global tab -> Performance Threshold
Some examples of threshold percentage calculations are as follows:
Schedule to date equals (Earned Value Labor Units minus Planned Value Labor
Units) divided by Planned Value Labor Units
Labor units to date equals (Earned Value Labor Units minus Actual Labor
Units) divided by Earned Value Labor Units
Schedule at completion equals (Budget At Completion multiplied by Schedule
Variance Index) divided by Budget At Completion
Labor units at completion equals (Budget At Completion Labor
Units multiplied by Cost Variance Index) divided by Budget At Completion Labor
Units
Index section
Use the options in this section to define what is Exceptional, Warning,
and Critical when assessing index performance. The values you specify determine
which indicators apply to the Cost Performance Index (CPI), Schedule Performance
Index (SPI), and To Complete Performance Index (TCPI).


Exceptional: The minimum percentage over 100 that the index variance must be
greater than to display the exceptional indicator. For example, if you set the
exceptional threshold at 10% and the actual index variance is 115%, then that item
would be considered exceptional.



Warning: The minimum percentage under 100 that the index variance must be less
than to display the warning indicator.



Critical: The minimum percentage under 100 that the index variance must be less
than to display the critical indicator.
Some examples of percentage calculations are as follows:
CPI equals Earned Value divided by Actual Units
SPI equals Earned Value divided by Planned Value
TCPI equals (Budget At Completion minus Earned Value) divided by (Estimate
At Completion minus Actual Units)

Reference:1.

http://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?6601.htm

More Related Content

What's hot

Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1Anand Bobade
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsAnand Bobade
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & ControlingDarshana Viduranga
 
Writing Winning Proposals
Writing Winning ProposalsWriting Winning Proposals
Writing Winning ProposalsMohamed Shaaban
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxsurekha1287
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 

What's hot (20)

Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Fidic
FidicFidic
Fidic
 
Pmp chap 11 - project risk management v0.1
Pmp   chap 11 - project risk management v0.1Pmp   chap 11 - project risk management v0.1
Pmp chap 11 - project risk management v0.1
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Project Communications Management
Project Communications ManagementProject Communications Management
Project Communications Management
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Construction KPIs & Dashboards
Construction KPIs & DashboardsConstruction KPIs & Dashboards
Construction KPIs & Dashboards
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Earned value
Earned valueEarned value
Earned value
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Pmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management detailsPmp chap13 - project stakeholder management details
Pmp chap13 - project stakeholder management details
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & Controling
 
Writing Winning Proposals
Writing Winning ProposalsWriting Winning Proposals
Writing Winning Proposals
 
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptxCONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 

Viewers also liked

Oracle primavera and bpm the power of integration ppt
Oracle primavera and bpm   the power of integration pptOracle primavera and bpm   the power of integration ppt
Oracle primavera and bpm the power of integration pptp6academy
 
Using bpm to automate project workflows with primavera
Using bpm to automate project workflows with primaveraUsing bpm to automate project workflows with primavera
Using bpm to automate project workflows with primaverap6academy
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updatesp6academy
 
128224154 oracle-inventory-ppt
128224154 oracle-inventory-ppt128224154 oracle-inventory-ppt
128224154 oracle-inventory-pptRamthilak R
 

Viewers also liked (6)

Oracle primavera and bpm the power of integration ppt
Oracle primavera and bpm   the power of integration pptOracle primavera and bpm   the power of integration ppt
Oracle primavera and bpm the power of integration ppt
 
Using bpm to automate project workflows with primavera
Using bpm to automate project workflows with primaveraUsing bpm to automate project workflows with primavera
Using bpm to automate project workflows with primavera
 
Configuring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project UpdatesConfiguring Primavera Team Member for Project Updates
Configuring Primavera Team Member for Project Updates
 
128224154 oracle-inventory-ppt
128224154 oracle-inventory-ppt128224154 oracle-inventory-ppt
128224154 oracle-inventory-ppt
 
Oracle Cloud
Oracle CloudOracle Cloud
Oracle Cloud
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 

Similar to User preference Option in Oracle Primavera EPPM P6

Management of database information system
Management of database information systemManagement of database information system
Management of database information systemKAZEMBETVOnline
 
Chapter 13 Reports 2-5-15
Chapter 13 Reports 2-5-15Chapter 13 Reports 2-5-15
Chapter 13 Reports 2-5-15Beth Horner
 
Nextera Energy Job Aid
Nextera Energy Job AidNextera Energy Job Aid
Nextera Energy Job AidKara Hodges
 
Report Builder Training 7i
Report Builder Training 7iReport Builder Training 7i
Report Builder Training 7iDydacomp
 
Report painter in SAP
Report painter in SAPReport painter in SAP
Report painter in SAPRajeev Kumar
 
Analysis by Dimensions online training
Analysis by Dimensions online training   Analysis by Dimensions online training
Analysis by Dimensions online training Scroll Up
 
Office excel tips and tricks 201101
Office excel tips and tricks 201101Office excel tips and tricks 201101
Office excel tips and tricks 201101Vishwanath Ramdas
 
Alv report-tutorial-www.sapexpert.co .uk-
Alv report-tutorial-www.sapexpert.co .uk-Alv report-tutorial-www.sapexpert.co .uk-
Alv report-tutorial-www.sapexpert.co .uk-Faina Fridman
 
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Sami JAMMALI
 
Sketch Assignment - Task Management
Sketch Assignment - Task ManagementSketch Assignment - Task Management
Sketch Assignment - Task ManagementSuraj Rao
 
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Sami JAMMALI
 
Salesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSalesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSkyPlanner
 
Salesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSalesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSkyPlanner
 
Hyperion step by step guide
Hyperion step by step guideHyperion step by step guide
Hyperion step by step guidechalasani kamesh
 

Similar to User preference Option in Oracle Primavera EPPM P6 (20)

Management of database information system
Management of database information systemManagement of database information system
Management of database information system
 
BEX.pptx
BEX.pptxBEX.pptx
BEX.pptx
 
Chapter 13 Reports 2-5-15
Chapter 13 Reports 2-5-15Chapter 13 Reports 2-5-15
Chapter 13 Reports 2-5-15
 
Nextera Energy Job Aid
Nextera Energy Job AidNextera Energy Job Aid
Nextera Energy Job Aid
 
Report Builder Training 7i
Report Builder Training 7iReport Builder Training 7i
Report Builder Training 7i
 
Fusion Financial Reporting and Analysis Proof of Concept
Fusion Financial Reporting and Analysis Proof of ConceptFusion Financial Reporting and Analysis Proof of Concept
Fusion Financial Reporting and Analysis Proof of Concept
 
Report painter in SAP
Report painter in SAPReport painter in SAP
Report painter in SAP
 
Analysis by Dimensions online training
Analysis by Dimensions online training   Analysis by Dimensions online training
Analysis by Dimensions online training
 
Elastix call center_manual_eng
Elastix call center_manual_engElastix call center_manual_eng
Elastix call center_manual_eng
 
Office excel tips and tricks 201101
Office excel tips and tricks 201101Office excel tips and tricks 201101
Office excel tips and tricks 201101
 
Alv report-tutorial-www.sapexpert.co .uk-
Alv report-tutorial-www.sapexpert.co .uk-Alv report-tutorial-www.sapexpert.co .uk-
Alv report-tutorial-www.sapexpert.co .uk-
 
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 07-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
 
Sketch Assignment - Task Management
Sketch Assignment - Task ManagementSketch Assignment - Task Management
Sketch Assignment - Task Management
 
Sentrifugo 2.1.1 Time Management user guide
Sentrifugo 2.1.1 Time Management user guideSentrifugo 2.1.1 Time Management user guide
Sentrifugo 2.1.1 Time Management user guide
 
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
Mr20 enus 03-Report Design in Management Reporter 2.0 for Microsoft Dynamics®...
 
Salesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSalesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release Highlights
 
Salesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release HighlightsSalesforce Winter ’22 Release Highlights
Salesforce Winter ’22 Release Highlights
 
Hyperion step by step guide
Hyperion step by step guideHyperion step by step guide
Hyperion step by step guide
 
Budget Development in KC
Budget Development in KCBudget Development in KC
Budget Development in KC
 
Iinsight 5.1.0 release notes
Iinsight 5.1.0 release notesIinsight 5.1.0 release notes
Iinsight 5.1.0 release notes
 

More from CADD Centre Software Solutions Private Limited

More from CADD Centre Software Solutions Private Limited (20)

Primavera manual
Primavera manual Primavera manual
Primavera manual
 
A b-c-d-(e) of ccsspl corporate presentation
A b-c-d-(e) of ccsspl corporate presentationA b-c-d-(e) of ccsspl corporate presentation
A b-c-d-(e) of ccsspl corporate presentation
 
Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)Login methodology for Primavera V8.3 (EPPM)
Login methodology for Primavera V8.3 (EPPM)
 
Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3
 
Oracle Primavera contractor
Oracle Primavera  contractorOracle Primavera  contractor
Oracle Primavera contractor
 
Recurring task IN MS project
Recurring task IN MS project Recurring task IN MS project
Recurring task IN MS project
 
CPCL Case study
CPCL Case studyCPCL Case study
CPCL Case study
 
Oracle Primavera contract management
Oracle Primavera  contract managementOracle Primavera  contract management
Oracle Primavera contract management
 
Uses of Project Status field
Uses of  Project Status field Uses of  Project Status field
Uses of Project Status field
 
Oracle primavera Universal content management
Oracle primavera Universal content management Oracle primavera Universal content management
Oracle primavera Universal content management
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Oracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricksOracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricks
 
Team member in iphones and android
Team member in iphones and androidTeam member in iphones and android
Team member in iphones and android
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Primavera portlets
Primavera portletsPrimavera portlets
Primavera portlets
 
Tested configuration for different Primavera versions
Tested configuration for different Primavera versionsTested configuration for different Primavera versions
Tested configuration for different Primavera versions
 
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
 
Features comparison between Primavera and Microsoft Project
Features comparison between Primavera and Microsoft ProjectFeatures comparison between Primavera and Microsoft Project
Features comparison between Primavera and Microsoft Project
 
Project management software consulting
Project management software consultingProject management software consulting
Project management software consulting
 
Oracle Autovue
Oracle AutovueOracle Autovue
Oracle Autovue
 

Recently uploaded

Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 

Recently uploaded (20)

Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 

User preference Option in Oracle Primavera EPPM P6

  • 1. User Preference in Primavera P6 EPPM Complete Look through User preference page which can be accessed by going to ‘administer-> My Preferences’ option, if the user you are logged in have enough rights to access this page is specifically designed to customize the way the user uses the EPPM features. As the name “My preference” goes the My Preferences section lets you to customize the data display format across all sections of P6. The options you customize are set exclusively only for you. There are three main tabs provided for easy customization 1.Global :- This is the main tab in the User Preference page, It is here where you’ll be doing all the page settings. You can alter global preferences, including formats for time units, dates, and currencies. For ex: to set whether you want to inform the resource via email if a new assignment is made to them or to set the base currency you will use throughout your project assignment and many more. 2.View :- You can also customize view preferences if the P6 Administrator gives you access to do so. This tab presents you all the pages which are accessible by you. You could either turn those visible by checking on the checkbox or turn it off by making them unchecked. Some view preferences you can customize include menu items and pages. 3.Password :-If you were wondering as of how to change the password provided as it was somehow disclosed or you had enough with you old password. This is the place created for you. Just provide your old password once and the fresh password twice. Done , you can now sign in to your P6 login page with your new password. Fig 1:My Preferences-> Password tab
  • 2. Fig 2: User Preference-> View tab
  • 3. We’ll be reviewing the settings you could make with Global tab in the following section. global preferences could be Customized to create a working environment that suits your needs. The global preferences you select affect only your interaction with the application; other users are not affected by your changes. The global tab in the user preference page is further sub divided into 8 major section. These sub section allows you to customize most of the features provided by P6 EPPM suite and set those to your own preference. Fig 3. My Preferences -> Global tab Options Let’s get into detail of each sub section 1.General section :This Section is mainly provided enable miscellaneous options for P6, such as sending an e-mail to resources upon adding or removing assignments. Fig 3.1 My Preferences -> Global tab -> General sections
  • 4. Let’s get into detail of the various options given in the general section 1.a. Maximum number of rows displayed in each section – You could Double-click the Maximum number of rows displayed in each section field and type a value to alter the number of rows displayed in each section. For pages with standard lists of data (not tables), the number of rows that display together before the list is divided. Generally, the lower the number, the better performance will be since the user interface is displaying fewer rows of data. If the number of items exceed the maximum value which you specified in the field for Maximum number of rows displayed in each section, a Next link appears for you to navigate to the next page of the list.i.e for example You specify a value of five in this field. Later, you navigate to the Portfolio Status page or Project Issues page. Up to five rows will be listed. If more than five rows of data are available, a [Next >>] link appears for you to navigate to the next five items in the list. Note: The value you place in the Maximum number of rows displayed in each section setting will not apply to view or dictionary grids. This preference does not apply to workspace portlets. To specify the number of rows that display for lists in the portlets of a specific workspace, customize the workspace. 1.b. Maximum number of rows displayed in trees and picklists – Double-click the Maximum number of rows displayed in trees and picklists field and type a value. This field controls the number of elements that display in hierarchical lists, such as the EPS/project hierarchy in the Open Projects dialog box. If the number of items available to display exceeds the maximum you specify for Maximum number of rows displayed in trees and picklists,a message appears to inform you that you are viewing a partial list. 1.c. Send e-mail to resources upon adding or removing assignments – When a resource is replaced on an activity, an e-mail is sent to the removed resource and to the replacement resource. When the automatic e-mail option is on, confirmation messages are sent to you, indicating the names of the recipients. If a resource does not have an email address stored in the project database, no e-mail can be sent. In this case, you will know that the resource was not notified because you will not receive a confirmation message with that resource's name. 1.d. Prompt before sending e-mail Determines whether to prompt you before sending an e-mail.
  • 5. 1.e. Calculate performance and earned value information by Select from one of the following options to calculate performance and earned value information. Calculate Performance and Earned Value Information lets you choose whether to display earned value information, performance indicators, and indices based on cost or labor units. For example, when you display earned value information on the Portfolios Performance Status tab, you will see either Costs or Labor Units data, depending on how you set this preference.  Cost: Select to display earned value information, performance indicators, and indices based on cost.  Labor Units: Select to display earned value information, performance indicators, and indices based on labor units. 1.f. Display actual and earned value using financial period data Display actual and earned value using financial period data lets you choose to view information based on past period actuals data that has been stored for custom financial periods. This option applies to the histogram and spreadsheet displays in the Portfolios Gantt Chart, Projects Team Usage view, and Resources Usage view. When you choose this option, stored financial period values for actuals are distributed evenly from the start to the finish date defined for a financial period and earned value calculations are based on these stored period quantities. If you do not choose this option, actuals data is spread evenly from the actual start to the data date or actual finish date of the activity or assignment. Note: If you choose this option but period performance has not been stored, total reported actuals display in the timescale period representing the data date. For more information, contact your P6 administrator or Project Management Office. If projects are summarized by financial period (which is controlled in Application Settings in P6), this option is ignored. When projects are summarized by financial period and you display a financial period timescale, the profile displays past period actual values if performance has been stored for a financial period; for financial periods that do not have stored performance, the profile displays all unit and cost values in financial period intervals.
  • 6. 2.Currency:- Fig 3.2 My Preferences -> Global tab -> Currency sections The Select Currency icon is used to select the currencies available from the Select Currency dialog box, select a currency and click OK. The checkboxes of Show decimal places and show currency symbol are checked on to show decimal places or the currency symbol respectively. 3.Time Units Format:- Fig 3.3 My Preferences -> Global tab -> Time Units Format section
  • 7. This section to configure how time is displayed throughout the application. Note: P6 calculates and stores time unit values in hourly increments. When you specify a display time increment other than hours, P6 uses the Hours per Time Period settings from Admin Preferences or the calendar based on the setting in Application Settings in P6 to convert hours to the time increment you specify. 3.a. Display Time Units in list Determines which time unit is used to display time in the application:      Hour: Time units will display in hours. Day: Time units will display in days. Week: Time units will display in weeks. Month: Time units will display in months. Year: Time units will display in years.  Show sub units option Determines whether to show sub units with time units. Select the Show sub units option to display sub units in the next smaller time increment. This option is also available with Display Durations in.  Show unit label option Determines whether to show the unit abbreviation with time units.  Decimal places list Select to display 0, 1, or 2 decimal places. This option is also available with Display Durations in. 3.b. Display Durations in list Select to display durations from the following options:      Hour: Durations will display in hours. Day: Durations will display in days. Week: Durations will display in weeks. Month: Durations will display in months. Year: Durations will display in years.  Show sub units option This does the same work as is done in the display time units section.  Show duration label option
  • 8. Determines whether to show the time unit abbreviation with the duration value. 3.c. Units/Time Format Select one of the following to display resource units/time: Show as a percentage: Determines whether units/time will display as a percentage.  Show as units/duration: Determines whether units/time will display as units/duration.  For example, if Robert is assigned a limit of eight hours/day and you assign him to a task at a maximum limit of two hours/day, you can display this information one of two ways: as 2h/d or as 25 percent of his resource limit (since he is only assigned to this task for two of his allotted eight hours per day). 4.Date Format:- Fig 3.4 My Preferences -> Global tab -> Date Format section 4.a. Expand the Date format subsection: Click the Date format list, and choose a format. Mark the Date format options for how you want the date to display. 4.b. Expand the Time format subsection: Click the Time format list, and choose a format. Mark the Show minutes option if you want minutes to display.
  • 9. 4.c. Click the Separator list, and choose a separator. You can choose from “,” ,”.” Or “/” 5.Resources:This section is used to configure resource staffing and assignment options. Fig 3.5 My Preferences -> Global tab -> Resources
  • 10. 5.a. Resource Staffing Expand this section to choose your resource staffing options. Automatically summarize project after assigning resources option Determines whether to summarize a project after you assign resources. Because availability calculations for resource staffing features are based on summary data, choosing this option ensures that your staffing decisions are based on the most up-to-date resource allocation data. When this feature is enabled, you can check the status of the summarizer job on the Activities page in the View Service Status dialog box. Within the resource staffing feature, click on an activity name to show limited activity details, based on whether you select Display Resource Assignments, Display Notebook, and/or Display Steps. An administrative setting is also required to implement this feature. For more information, contact your P6 administrator. Display Resource Assignments option Determines whether to display an activity's resource assignment details, for example, planned units and remaining units/time. Display Notebook option Determines whether to display activity Notebooks when viewing activity details. Display Steps option Determines whether to display activity steps when viewing activity details. 5.b. Resource Assignments Expand this section to choose your resource assignment options. When adding or removing multiple resource assignments on activities options When adding or removing multiple resource assignments, you can choose to preserve or recalculate units, duration, and units/time. Choose from the following options:  Preserve the Units, Duration, and Units/Time for existing assignments: Choose this option for units, durations, and units/time to remain constant when additional resources are assigned to any activity. Regardless of the duration type of an activity, this equation is always true: Remaining Units = Remaining Duration x Remaining Units/Time
  • 11.  Recalculate the Units, Duration, and Units/Time for existing assignments based on the activity Duration Type: Choose this option to calculate a resource assignment’s remaining values based on the activity’s duration type, specified in an activity's General tab. When assigning a resource to an existing activity assignment options When selecting a resource to staff an existing role assignment or replacing a current resource assignment with a different resource, you can choose to always use the current units/time and overtime factor of the new resource or you can choose to be prompted every time so you can select the units/time and overtime factor you want to apply to the assignment. Choose from the following options:  Always use the new resource's Units/Time and Overtime factor: The manual future period values of the existing resource assignment may be respread across future period buckets based on the new resource's values.  Always use current assignment's Units/Time and Overtime factor: The unit values for the new resource are spread evenly over future period buckets and the manual future period values for the existing resource assignment are not changed.  Ask me to select each time I assign: Every time you make an assignment, the application will ask whether it should use the units/time and overtime factor for the new resource or the current assignment When a resource and role share an activity assignment options When selecting a resource to staff an existing role assignment or specifying a role for an existing resource assignment, you can choose to always apply either the resource or role rate (Price/Unit) to the assignment or you can choose to be prompted every time so you can select which rate you want to apply. Use the following options: Note: The assignment Rate Source field indicates whether the resource or role rate is applied to an assignment. The Rate Source, along with the Rate Type, determines the price/unit value used to calculate costs for the assignment.  Always use resource's Price/Unit: The manual future period values for the existing role assignment may be respread across future period buckets based on the new resource's values.  Always use role's Price/Unit: The manual future period values for the existing resource assignment may be respread across future period buckets based on the new role's values.  Ask me to select each time I assign: Every time you make an assignment, the application will ask whether it should use the resource's or role' price/unit. Display the role limit based on options In P6 Optional Client and P6, you can define the maximum availability (limit) over time for each role in the Roles dictionary. In P6, role limits are displayed in charts, histograms, and spreadsheets that display role allocation data, such as the Capacity Planning chart and Role Usage histogram. Use the following options:
  • 12.  Custom role limit: Determines whether role limits are calculated based on customized role limits.  Calculated primary resources' limit: Determines whether role limits are calculated using the limit defined for each role's primary resource. This is the default option. 5.c. Number of available items to search for Roles, Resources, and Resource Codes field The number of search criteria items allowed when searching for resources to staff activities. The maximum valid value is 10. 6. Issues:This section is used to configure e-mail notifications for issues. Fig 3.6 My Preferences -> Global tab -> Issues Send me a notification when The following options are used to determine whether you receive a notification and when.  Issues are added with priority of [ ] or higher option Determines whether issues that are added with a priority you specify from the list are sent. Value options are Top, High, Normal, Low, and Lowest.
  • 13.  Issues are assigned issue code field The issue code that will cause a notification to be sent when it is assigned to an issue. Note: The Issues are assigned issue code option must be selected to send a notification.  Issues are modified option Determines whether issues that are modified are sent. Only notify me about Issues for Projects and Workgroups if I The following options determine whether you are notified about issues for Projects and Workgroups when one or multiple selections are made:  Have project access rights option Determines whether you are notified about issues for Projects and Workgroups if you have Project access rights.  Have issue access rights option Determines whether you are notified about issues for Projects and Workgroups if you have Issue access rights.  Am the Project Owner option Determines whether you are notified about issues for Projects and Workgroups if you are the Project Owner.  Am the Issue Owner option Determines whether you are notified about issues for Projects and Workgroups if you are the Issue Owner.  Am assigned as a resource to that activity option Determines whether you are notified about issues for Projects and Workgroups if you are assigned as a resource to the specified activity.
  • 14. 7.Project Score:This section is used to configure how the project score is calculated. Fig 3.7 My Preferences -> Global tab -> Project Score Calculate Project Score based on selected Project Codes option Determines whether to calculate project scores based on project codes. o Project Codes link Displays a dialog box with configurable options to determine what project code to select for the project score..  High is greater than or equal to: field The high value will be greater than or equal to the value entered in this field.  Medium is greater than or equal to: field The medium value will be greater than or equal to the value entered in this field.  Low is greater than:0 Indicates that the low value must be greater than 0. 8.Performance Threshold:This section is used to specify parameters for Performance, Earned Value, and Index values that appear in dashboard Project Performance portlets and on the Portfolios Performance Status tab. The settings you specify in Global Preferences only apply to the dashboard portlets; for each project, you can specify project-specific Performance Threshold settings when you customize the project Workspace. Performance section Use the options in this section to define what is considered Exceptional, Warning, or Critical when assessing schedule performance for a project, WBS, or EPS. The values you specify determine which indicators apply to the Schedule to date, Labor units to date, Schedule at completion, and Labor units at completion metrics.
  • 15.  Exceptional: For schedule values, the minimum number of days that the project, WBS, or EPS must be ahead of schedule to be considered exceptional. For labor units, the minimum percentage under 100 that the labor units variance must be less than to display the exceptional indicator. For example, if you set the exceptional threshold at 10% and the actual labor units variance is 85%, then that item would be considered exceptional.  Warning: For a schedule value, the minimum number of days that the project, WBS, or EPS must be behind schedule to display the warning indicator. For labor units, the minimum percentage over 100 that the labor units variance must be greater than to display the warning indicator. Critical: For a schedule value, the minimum number of days that the project, WBS, or EPS must be behind schedule to display the critical indicator. For labor units, the minimum percentage over 100 that the labor units variance must be greater than to display the critical indicator. Some examples of threshold percentage calculations are as follows: Labor units to date equals (Earned Value Labor Units minus Actual Labor Units) divided by Earned Value Labor Units Labor units at completion equals (Budget At Completion Labor Units minus Estimate At Completion Labor Units) divided by Budget At Completion Labor Units Earned Value section Use the options in this section to define what is considered Exceptional, Warning, and Critical when assessing earned value performance for a project, WBS, or EPS. The values you specify determine which indicators apply to the Schedule to date, Labor units to date, Schedule at completion, and Labor units at completion metrics.  Exceptional: The minimum percentage under 100 that the schedule or labor units variance must be less than to display the exceptional indicator. For example, if you set the exceptional threshold at 10% and the actual earned value variance is 85%, then that item would be considered exceptional.  Warning: The minimum percentage over 100 that the schedule or labor units variance must be greater than to display the warning indicator.  Critical: The minimum percentage over 100 that the schedule or labor units variance must be greater than to display the critical indicator.
  • 16. Fig 3.8 My Preferences -> Global tab -> Performance Threshold Some examples of threshold percentage calculations are as follows: Schedule to date equals (Earned Value Labor Units minus Planned Value Labor Units) divided by Planned Value Labor Units Labor units to date equals (Earned Value Labor Units minus Actual Labor Units) divided by Earned Value Labor Units
  • 17. Schedule at completion equals (Budget At Completion multiplied by Schedule Variance Index) divided by Budget At Completion Labor units at completion equals (Budget At Completion Labor Units multiplied by Cost Variance Index) divided by Budget At Completion Labor Units Index section Use the options in this section to define what is Exceptional, Warning, and Critical when assessing index performance. The values you specify determine which indicators apply to the Cost Performance Index (CPI), Schedule Performance Index (SPI), and To Complete Performance Index (TCPI).  Exceptional: The minimum percentage over 100 that the index variance must be greater than to display the exceptional indicator. For example, if you set the exceptional threshold at 10% and the actual index variance is 115%, then that item would be considered exceptional.  Warning: The minimum percentage under 100 that the index variance must be less than to display the warning indicator.  Critical: The minimum percentage under 100 that the index variance must be less than to display the critical indicator. Some examples of percentage calculations are as follows: CPI equals Earned Value divided by Actual Units SPI equals Earned Value divided by Planned Value TCPI equals (Budget At Completion minus Earned Value) divided by (Estimate At Completion minus Actual Units) Reference:1. http://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?6601.htm