3. PERMIT PROCESS Major Preapplication Meetings Initial Consultation IC Major Preapplication MPA http://www.sdcounty.ca.gov/dplu/zoning/majorpreapplication.html
4. PERMIT PROCESS Major Use Permit Application TIME: Greater than 3 years COST: More than $100,000 http://www.sdcounty.ca.gov/dplu/docs/cost-schedule-summary.pdf
5. MET FACILITY WIND TESTING Administrative Permit Process Needed for Wind Testing CEQA Exempt Director Decision 1-3 Months $2,000-$4,000 Hearing Requested http://www.sdcounty.ca.gov/dplu/zoning/majorpreapplication.html
6. PERMIT PROCESS Major Use Permit Hearing Body: Planning Commission Appeal to Board of Supervisors DPLU Recommendation
8. CEQA PROCESS Environmental Impact Assessment: Extended Initial Studies CEQA Significance Guidelines County Guidelines and Report Format http://www.sdcounty.ca.gov/dplu/procguid.html#guide
9. CEQA PROCESS Potentially Significant Impacts: Biological and Cultural Resources Visual and Noise Impacts Groundwater and Fire Services Williamson Act Ag. Contracts
12. PUBLIC PROCESS Public Participation Agencies Community Advisory Groups Individual Citizens and Interest Groups http://www.sdcounty.ca.gov/dplu/CommunityGroups.html