SlideShare ist ein Scribd-Unternehmen logo
1 von 39
Agenda
1.   Progress Update
     a.   Well Field Piping
     b.   Transmission Main
     c.   Booster Pump Station & Well Field
     d.   Treatment
2. THM Compliance Strategies: Challenges &
   Solutions
3. Questions & Discussion

                                              2
Well Field Piping
 CurrentStatus: Construction is 100%
  complete
 Contract close-out underway with the
  TWDB




                                         3
Transmission Main

 NTP  January 23, 2012
 Substantial completion July 16, 2013 (540
  days)
 Final completion September 14, 2013 (600
  days)
 Current status: Construction is approximately
  45% Complete
                                              4
Progress as of Oct. 29, 2012




                               5
Progress Summary

 Work  progressing at both lay headings
 Over 28 miles installed
 Slightly behind overall schedule, but catching
  up and getting closer to planned schedule
 Valves and appurtenance work ongoing with
  dig/lay/bury


                                                   6
Sta. 2624+00 looking west (Osburn
cropfield)




                                    7
Sta. 2624+00 looking east (note the solid
rock)




                                            8
Dig, Lay Bury
Expect utilities along the way (gas, etc)….




                                              10
Booster Pump Station & Well Field

 NTP  June 18, 2012
 Substantial completion June 18, 2013 (365
  days)
 Final Completion July 17, 2013 (395 Days)




                                              11
Progress Summary

 On schedule
 Access road complete except for BCV areas
 Booster pumps and well pumps in fabrication
 Booster pump cans on site
 Cleaning and video of wells nearly complete




                                                12
Excavation for meter vault 1




                               13
Hickory Wells 1-9 Background
 Wells drilled in the 1970s
 Potential obstructions or items identified by the
  initial video survey at some wells.
 TCEQ required cleaning of the well casings at
  each well along with removal of debris or
  obstructions noted in the initial video survey
  followed by a new video survey to confirm the
  condition of the wells.

                                                      14
Current status

 Cleaning and video complete for wells 1, 3,
  and 8. Casing in good condition.
 Cleaning work ongoing of wells 2, 5, 6, and
  9.




                                                15
Current status (Continued)

 Well 4 known obstruction cleared only to
  encounter another obstruction (rubber plug).
  In process of evaluating options to remove the
  second obstruction.
 Well 7 initial cleaning complete, video
  revealed a split in the casing at 65 feet depth.
  Proposed repair is press or “swage” a sleeve
  inside the casing.
                                                     16
Well brush fabrication




                         17
Brushing and cleaning of well




                                18
Well purge




             19
Well 4 obstruction chunk




                           20
Groundwater Treatment Plant Design
   Procurement documents
     • Select radium removal system supplier
     • Complete
     • Advertise November 2012
   Expedited Design schedule
     • Bid plans and specs – March 2013
     • Construction start – June 2013 (pending TCEQ &
       TWDB approval and council award for bids)

                                                        21
Visited three radium removal
groundwater treatment facilities
  Vineland,   NJ
    • In service since 2006; retrofitted in 2011
  Upper   Deerfield, NJ
    • In service since 2009
  Aqua   NJ Southern Division
    • In service since 2008
Radium Removal System Site Visits




                                    23
Radium Removal System Site Visits




                                    24
THM Compliance Strategies:
 Challenges and Solutions

          November 6, 2012
 City of San Angelo Council Meeting

         P. Greg Pope Ph.D., P.E.
          Carollo Engineers, Inc.
What are THMs?

  Cl2 + Natural Organic Matter + Bromide 
         Halogenated Organics (THMs)


                            THMs
         Disinfectant




                                             27
Why do we care about THMS?

 THMs (Trihalomethanes) are a family of four
  chemicals (chloroform, bromodichloromethane,
  dibromochloromethane, and bromoform) that are
  regulated by the USEPA
 EPA maximum contaminant level = 80 µg/L
 Some people who drink water containing THMs
  in excess of the MCL over many years may
  experience health problems

                                                  28
Several Factors Impact THM
Formation
   Source water quality
      • natural organic matter (NOM)
      • bromide
 pH
 Water age
 Disinfectant type
 Disinfectant concentration

                                       29
How Can THM Formation be
 Controlled?
               Cl2 + NOM + Bromide  THMs


 Alternate Disinfectants
•Chloramines




                                            30
How Can THM Formation be
 Controlled?
                Cl2 + NOM + Bromide  THMs



 Alternate Disinfectants     Remove/Reduce
•Chloramines                 NOM Reactivity
                           •Reverse Osmosis
                           •GAC
                           •pH Control
                           •Ozone
                           •Chlorine Dioxide

                                               31
How Can THM Formation be
 Controlled?
               Cl2 + NOM + Bromide  THMs



 Alternate Disinfectants     Remove/Reduce              THM
•Chloramines                 NOM Reactivity    Removal/Degradation
                           •Reverse Osmosis    •Biological Filtration
                           •GAC                •Aeration
                           •pH Control         •GAC
                           •Ozone
                           •Chlorine Dioxide

                                                                        32
To limit DBP formation the COSA Uses
chloramines for disinfection
               100
                           Water Plant
                90
                           Mathis Field
                80

                70

                60
 TTHM (µg/L)




                50

                40

                30

                20

                10

                 0
                     Jun    Aug           Sep   Nov   Jan   Feb   Apr   Jun   Jul
High bromide source waters pose a
 challenge to utilities that use
 chloramines
Parameter        O.H. Ivie   Concho   Hickory
                 Reservoir    River
Bromide (mg/L)      1.6       0.89     0.39
pH                  7.9       8.1       7.5
TOC (mg/L)          4.8       7.6       0.2
TDS (mg/L)         1350       950      480




                                                34
Blending Treated Groundwater with Treated
Surface Water Reduced THM Formation
   180

                          160                                      2 day THM formation

                          140

                          120
  TTHM Formation (µg/L)




                          100

                           80

                           60

                           40

                           20

                            0

                                           75% TSW/   50% TSW/   25% TSW/      100% TGW
                                100% TSW
                                           25% TGW    50% TGW    75% TGW
Current THM Formation
                 90

                 80

                 70

                 60
  TTHMs (µg/L)




                 50

                 40                         pH 7.5

                 30

                 20

                 10

                 0
                      30 minutes   5 days


                                                     36
Optimizing pH Decreased THM formation
                90

                80

                70

                60
 TTHMs (µg/L)




                50
                                           pH 7.5
                40
                                           pH 8.3
                30

                20

                10

                0
                     30 minutes   5 days


                                                    37
Summary
 Strategies aimed at optimizing chloramine
  formation conditions may reduce THM formation.
 Bench –studies indicated that:
    • Blending the source water with a lower bromide, less
      reactive groundwater decreased DBP formation.
    • Disinfection at elevated pH (8.3 vs. 7.5) reduced
      THM formation.




                                                             38
San Angelo City Council November 6, 2012 Hickory Update

Weitere ähnliche Inhalte

Was ist angesagt?

Enzotech presentation july12
Enzotech presentation july12Enzotech presentation july12
Enzotech presentation july12enzotechslides
 
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...Energy Network marcus evans
 
Presentation Energolesprom
Presentation EnergolespromPresentation Energolesprom
Presentation EnergolespromEnergolesprom
 
Power plant chemistry
Power plant chemistryPower plant chemistry
Power plant chemistryRaghab Gorain
 
report for Master's thesis - final version - ready for printing-28-06-2011
report for Master's thesis - final version - ready for printing-28-06-2011report for Master's thesis - final version - ready for printing-28-06-2011
report for Master's thesis - final version - ready for printing-28-06-2011Quoc Chon Le
 
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...MilliporeSigma
 
An effective new leaching aid
An effective new leaching aidAn effective new leaching aid
An effective new leaching aidBASF
 
Shale eera fleury
Shale eera fleuryShale eera fleury
Shale eera fleuryPomcert
 
Washing Stages in the control of chloride transfer from leach solutions to th...
Washing Stages in the control of chloride transfer from leach solutions to th...Washing Stages in the control of chloride transfer from leach solutions to th...
Washing Stages in the control of chloride transfer from leach solutions to th...BASF
 
Copper in distillery effluent discharge presentation
Copper in distillery effluent discharge presentationCopper in distillery effluent discharge presentation
Copper in distillery effluent discharge presentationB & V Water Treatment
 
Oral presentation
Oral presentationOral presentation
Oral presentationAnh-Mai
 
Icom2008 osmbr
Icom2008 osmbrIcom2008 osmbr
Icom2008 osmbrSunmanyang
 
Wett and Puempel DEMON technology
Wett and Puempel DEMON technologyWett and Puempel DEMON technology
Wett and Puempel DEMON technologySYNECO
 
SPE-DL slides EricMackayALL
SPE-DL slides EricMackayALLSPE-DL slides EricMackayALL
SPE-DL slides EricMackayALLEric Mackay
 
New generation of highly selective and degradation resistant reagents for cop...
New generation of highly selective and degradation resistant reagents for cop...New generation of highly selective and degradation resistant reagents for cop...
New generation of highly selective and degradation resistant reagents for cop...BASF
 
Presentation On Mar Type sewage treatment plant
Presentation On Mar Type sewage treatment plantPresentation On Mar Type sewage treatment plant
Presentation On Mar Type sewage treatment plantjeykumar
 
Project_NYENDWA_(10th_ed)[1]
Project_NYENDWA_(10th_ed)[1]Project_NYENDWA_(10th_ed)[1]
Project_NYENDWA_(10th_ed)[1]Janny Nyendwa Jnr
 

Was ist angesagt? (20)

Enzotech presentation july12
Enzotech presentation july12Enzotech presentation july12
Enzotech presentation july12
 
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...
Operating Experience with Fluidized Bed Coal Dryer at Coal Creek Generating S...
 
Presentation Energolesprom
Presentation EnergolespromPresentation Energolesprom
Presentation Energolesprom
 
Power plant chemistry
Power plant chemistryPower plant chemistry
Power plant chemistry
 
ACE Poster
ACE PosterACE Poster
ACE Poster
 
report for Master's thesis - final version - ready for printing-28-06-2011
report for Master's thesis - final version - ready for printing-28-06-2011report for Master's thesis - final version - ready for printing-28-06-2011
report for Master's thesis - final version - ready for printing-28-06-2011
 
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...
High-Capacity Capture of a Recombinant Growth Factor Directly From Refold Sol...
 
An effective new leaching aid
An effective new leaching aidAn effective new leaching aid
An effective new leaching aid
 
Shale eera fleury
Shale eera fleuryShale eera fleury
Shale eera fleury
 
Washing Stages in the control of chloride transfer from leach solutions to th...
Washing Stages in the control of chloride transfer from leach solutions to th...Washing Stages in the control of chloride transfer from leach solutions to th...
Washing Stages in the control of chloride transfer from leach solutions to th...
 
Copper in distillery effluent discharge presentation
Copper in distillery effluent discharge presentationCopper in distillery effluent discharge presentation
Copper in distillery effluent discharge presentation
 
Oral presentation
Oral presentationOral presentation
Oral presentation
 
Icom2008 osmbr
Icom2008 osmbrIcom2008 osmbr
Icom2008 osmbr
 
Wett and Puempel DEMON technology
Wett and Puempel DEMON technologyWett and Puempel DEMON technology
Wett and Puempel DEMON technology
 
Better Forming Webs
Better Forming WebsBetter Forming Webs
Better Forming Webs
 
SPE-DL slides EricMackayALL
SPE-DL slides EricMackayALLSPE-DL slides EricMackayALL
SPE-DL slides EricMackayALL
 
New generation of highly selective and degradation resistant reagents for cop...
New generation of highly selective and degradation resistant reagents for cop...New generation of highly selective and degradation resistant reagents for cop...
New generation of highly selective and degradation resistant reagents for cop...
 
Presentation On Mar Type sewage treatment plant
Presentation On Mar Type sewage treatment plantPresentation On Mar Type sewage treatment plant
Presentation On Mar Type sewage treatment plant
 
Project_NYENDWA_(10th_ed)[1]
Project_NYENDWA_(10th_ed)[1]Project_NYENDWA_(10th_ed)[1]
Project_NYENDWA_(10th_ed)[1]
 
Setawwa 2010, 29-58 choules
Setawwa   2010, 29-58 choulesSetawwa   2010, 29-58 choules
Setawwa 2010, 29-58 choules
 

Andere mochten auch

Andere mochten auch (7)

City council 8 6-13 ai 14 hickory well field expansion
City council 8 6-13 ai 14 hickory well field expansionCity council 8 6-13 ai 14 hickory well field expansion
City council 8 6-13 ai 14 hickory well field expansion
 
City council january 7, 2014 river fest
City council january 7, 2014   river festCity council january 7, 2014   river fest
City council january 7, 2014 river fest
 
January 7, 2014 Agenda Packet
January 7, 2014 Agenda PacketJanuary 7, 2014 Agenda Packet
January 7, 2014 Agenda Packet
 
January 21, 2014 Agenda packet
January 21, 2014 Agenda packetJanuary 21, 2014 Agenda packet
January 21, 2014 Agenda packet
 
City council january 7, 2014 bandits presentation
City council january 7, 2014   bandits presentationCity council january 7, 2014   bandits presentation
City council january 7, 2014 bandits presentation
 
City council january 7, 2014 sidewalk agreement
City council january 7, 2014   sidewalk agreementCity council january 7, 2014   sidewalk agreement
City council january 7, 2014 sidewalk agreement
 
February 4, 2014 Agenda Packet
February 4, 2014 Agenda PacketFebruary 4, 2014 Agenda Packet
February 4, 2014 Agenda Packet
 

Ähnlich wie San Angelo City Council November 6, 2012 Hickory Update

Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...
Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...
Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...Mawuli Dzakpasu
 
A Combined Ozone Remedy for a Mixed VOC DNAPL Source Zone
A Combined Ozone Remedy for a Mixed VOC DNAPL Source ZoneA Combined Ozone Remedy for a Mixed VOC DNAPL Source Zone
A Combined Ozone Remedy for a Mixed VOC DNAPL Source ZoneChapman Ross, P.E.
 
Ef coop meetingpres_11102011
Ef coop meetingpres_11102011Ef coop meetingpres_11102011
Ef coop meetingpres_11102011hrlubbers
 
Ef coop meetingpres_11102011
Ef coop meetingpres_11102011Ef coop meetingpres_11102011
Ef coop meetingpres_11102011hrlubbers
 
Ohio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentOhio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentARSacco
 
Irwa Presentation 2009
Irwa Presentation 2009Irwa Presentation 2009
Irwa Presentation 2009h20lyle
 
ReverseOsmosis recent trends.pptx
ReverseOsmosis recent trends.pptxReverseOsmosis recent trends.pptx
ReverseOsmosis recent trends.pptxrajasonalgecl
 
Coral Bay Update on the Palawan HPAL Project
Coral Bay Update on the Palawan HPAL ProjectCoral Bay Update on the Palawan HPAL Project
Coral Bay Update on the Palawan HPAL ProjectNo to mining in Palawan
 
WVWC - Alt Oxidant & CC - AZ Presentation May 2012
WVWC - Alt Oxidant & CC - AZ Presentation May 2012WVWC - Alt Oxidant & CC - AZ Presentation May 2012
WVWC - Alt Oxidant & CC - AZ Presentation May 2012Joel Wade
 
DESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTDESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTRatnesh Kushwaha
 
Lessons learned from injecting liquid activated carbon suspension
Lessons learned from injecting liquid activated carbon suspensionLessons learned from injecting liquid activated carbon suspension
Lessons learned from injecting liquid activated carbon suspensionAntea Group
 
Advanced oxidation processes to recover reverse osmosis cleaning waters
Advanced oxidation processes to recover reverse osmosis cleaning watersAdvanced oxidation processes to recover reverse osmosis cleaning waters
Advanced oxidation processes to recover reverse osmosis cleaning watersacciona
 
Greenhouse disinfectant research
Greenhouse disinfectant researchGreenhouse disinfectant research
Greenhouse disinfectant researchSteven Newman
 
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...Daniel Eyde
 
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...TWCA
 

Ähnlich wie San Angelo City Council November 6, 2012 Hickory Update (20)

Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...
Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...
Nutrient Leaching and Groundwater Quality Assessment near Integrated Construc...
 
A Combined Ozone Remedy for a Mixed VOC DNAPL Source Zone
A Combined Ozone Remedy for a Mixed VOC DNAPL Source ZoneA Combined Ozone Remedy for a Mixed VOC DNAPL Source Zone
A Combined Ozone Remedy for a Mixed VOC DNAPL Source Zone
 
Ef coop meetingpres_11102011
Ef coop meetingpres_11102011Ef coop meetingpres_11102011
Ef coop meetingpres_11102011
 
Ef coop meetingpres_11102011
Ef coop meetingpres_11102011Ef coop meetingpres_11102011
Ef coop meetingpres_11102011
 
Ohio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water TreatmentOhio Awwa 2008 Ozone Drinking Water Treatment
Ohio Awwa 2008 Ozone Drinking Water Treatment
 
Irwa Presentation 2009
Irwa Presentation 2009Irwa Presentation 2009
Irwa Presentation 2009
 
Noh reverse osmosis
Noh reverse osmosisNoh reverse osmosis
Noh reverse osmosis
 
ReverseOsmosis recent trends.pptx
ReverseOsmosis recent trends.pptxReverseOsmosis recent trends.pptx
ReverseOsmosis recent trends.pptx
 
Coral Bay Update on the Palawan HPAL Project
Coral Bay Update on the Palawan HPAL ProjectCoral Bay Update on the Palawan HPAL Project
Coral Bay Update on the Palawan HPAL Project
 
WVWC - Alt Oxidant & CC - AZ Presentation May 2012
WVWC - Alt Oxidant & CC - AZ Presentation May 2012WVWC - Alt Oxidant & CC - AZ Presentation May 2012
WVWC - Alt Oxidant & CC - AZ Presentation May 2012
 
DESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANTDESIGN OF A SEWAGE TREATMENT PLANT
DESIGN OF A SEWAGE TREATMENT PLANT
 
Analysis of Disinfection Byproducts by Ion Chromatography
Analysis of Disinfection Byproducts by Ion ChromatographyAnalysis of Disinfection Byproducts by Ion Chromatography
Analysis of Disinfection Byproducts by Ion Chromatography
 
Lessons learned from injecting liquid activated carbon suspension
Lessons learned from injecting liquid activated carbon suspensionLessons learned from injecting liquid activated carbon suspension
Lessons learned from injecting liquid activated carbon suspension
 
Advanced oxidation processes to recover reverse osmosis cleaning waters
Advanced oxidation processes to recover reverse osmosis cleaning watersAdvanced oxidation processes to recover reverse osmosis cleaning waters
Advanced oxidation processes to recover reverse osmosis cleaning waters
 
Jordan River Water Quality
Jordan River Water QualityJordan River Water Quality
Jordan River Water Quality
 
Greenhouse disinfectant research
Greenhouse disinfectant researchGreenhouse disinfectant research
Greenhouse disinfectant research
 
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...
A Review of Zeolite Based Treatment Water Systems and Thier Applicability in ...
 
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...
TWCA Annual Convention: Optimizing Slime Control Chemical Feed in TRWD Raw Wa...
 
Project Example
Project ExampleProject Example
Project Example
 
OMAE 2011-50298 Presentation
OMAE 2011-50298 PresentationOMAE 2011-50298 Presentation
OMAE 2011-50298 Presentation
 

Mehr von City of San Angelo Texas

City council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity of San Angelo Texas
 
City council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity of San Angelo Texas
 
City council nov. 19, 2013 san angelo public housing authority
City council nov. 19, 2013   san angelo public housing  authorityCity council nov. 19, 2013   san angelo public housing  authority
City council nov. 19, 2013 san angelo public housing authorityCity of San Angelo Texas
 
City council nov. 19, 2013 cosadc budget presentation 11-19-13
City council nov. 19, 2013    cosadc budget presentation 11-19-13City council nov. 19, 2013    cosadc budget presentation 11-19-13
City council nov. 19, 2013 cosadc budget presentation 11-19-13City of San Angelo Texas
 
City council nov. 19, 2013 cosadc ballot language presentation
City council nov. 19, 2013    cosadc ballot language presentationCity council nov. 19, 2013    cosadc ballot language presentation
City council nov. 19, 2013 cosadc ballot language presentationCity of San Angelo Texas
 
San angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipSan angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipCity of San Angelo Texas
 
San angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotSan angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotCity of San Angelo Texas
 
San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...City of San Angelo Texas
 
San angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationSan angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationCity of San Angelo Texas
 
San angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetSan angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetCity of San Angelo Texas
 
San angelo city council 11 5-13 - request for competitive sealed proposals
San angelo city council 11 5-13 -  request for competitive sealed proposalsSan angelo city council 11 5-13 -  request for competitive sealed proposals
San angelo city council 11 5-13 - request for competitive sealed proposalsCity of San Angelo Texas
 
San angelo city council 11 5-13 - planning
San angelo city council 11 5-13 - planningSan angelo city council 11 5-13 - planning
San angelo city council 11 5-13 - planningCity of San Angelo Texas
 
San Angelo City Council 10-15-13 red arroyo project update
San Angelo City Council 10-15-13 red arroyo project updateSan Angelo City Council 10-15-13 red arroyo project update
San Angelo City Council 10-15-13 red arroyo project updateCity of San Angelo Texas
 
San Angelo City Council 10-15-13 development corporation annual report
San Angelo City Council 10-15-13 development corporation annual reportSan Angelo City Council 10-15-13 development corporation annual report
San Angelo City Council 10-15-13 development corporation annual reportCity of San Angelo Texas
 

Mehr von City of San Angelo Texas (20)

City council 12 17-13 downtown development plan
City council 12 17-13 downtown development planCity council 12 17-13 downtown development plan
City council 12 17-13 downtown development plan
 
City council 12 17-13 planning presentation
City council 12 17-13 planning presentationCity council 12 17-13 planning presentation
City council 12 17-13 planning presentation
 
December 17, 2013 Agenda Packet
December 17, 2013 Agenda PacketDecember 17, 2013 Agenda Packet
December 17, 2013 Agenda Packet
 
December 3, 2013 Agenda packet
December 3, 2013 Agenda packetDecember 3, 2013 Agenda packet
December 3, 2013 Agenda packet
 
City council nov. 19, 2013 san angelo public housing authority
City council nov. 19, 2013   san angelo public housing  authorityCity council nov. 19, 2013   san angelo public housing  authority
City council nov. 19, 2013 san angelo public housing authority
 
City council nov. 19, 2013 planning
City council nov. 19, 2013   planningCity council nov. 19, 2013   planning
City council nov. 19, 2013 planning
 
City council nov. 19, 2013 cosadc budget presentation 11-19-13
City council nov. 19, 2013    cosadc budget presentation 11-19-13City council nov. 19, 2013    cosadc budget presentation 11-19-13
City council nov. 19, 2013 cosadc budget presentation 11-19-13
 
City council nov. 19, 2013 cosadc ballot language presentation
City council nov. 19, 2013    cosadc ballot language presentationCity council nov. 19, 2013    cosadc ballot language presentation
City council nov. 19, 2013 cosadc ballot language presentation
 
November 19, 2013 Agenda Packet
November 19, 2013 Agenda PacketNovember 19, 2013 Agenda Packet
November 19, 2013 Agenda Packet
 
San angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnershipSan angelo city council 11 5-13 - west texas water partnership
San angelo city council 11 5-13 - west texas water partnership
 
San angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilotSan angelo city council 11 5-13 - wastewater pilot
San angelo city council 11 5-13 - wastewater pilot
 
San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...San angelo city council 11 5-13 - solid waste collection and operation presen...
San angelo city council 11 5-13 - solid waste collection and operation presen...
 
San angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentationSan angelo city council 11 5-13 - nasworthy presentation
San angelo city council 11 5-13 - nasworthy presentation
 
San angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budgetSan angelo city council 11 5-13 - economic development budget
San angelo city council 11 5-13 - economic development budget
 
San angelo city council 11 5-13 - request for competitive sealed proposals
San angelo city council 11 5-13 -  request for competitive sealed proposalsSan angelo city council 11 5-13 -  request for competitive sealed proposals
San angelo city council 11 5-13 - request for competitive sealed proposals
 
San angelo city council 11 5-13 - planning
San angelo city council 11 5-13 - planningSan angelo city council 11 5-13 - planning
San angelo city council 11 5-13 - planning
 
November 5, 2013 Agenda packet
November 5, 2013 Agenda packetNovember 5, 2013 Agenda packet
November 5, 2013 Agenda packet
 
Lake Nasworthy Plan Presentation 10.21.13
Lake Nasworthy Plan Presentation 10.21.13Lake Nasworthy Plan Presentation 10.21.13
Lake Nasworthy Plan Presentation 10.21.13
 
San Angelo City Council 10-15-13 red arroyo project update
San Angelo City Council 10-15-13 red arroyo project updateSan Angelo City Council 10-15-13 red arroyo project update
San Angelo City Council 10-15-13 red arroyo project update
 
San Angelo City Council 10-15-13 development corporation annual report
San Angelo City Council 10-15-13 development corporation annual reportSan Angelo City Council 10-15-13 development corporation annual report
San Angelo City Council 10-15-13 development corporation annual report
 

San Angelo City Council November 6, 2012 Hickory Update

  • 1.
  • 2. Agenda 1. Progress Update a. Well Field Piping b. Transmission Main c. Booster Pump Station & Well Field d. Treatment 2. THM Compliance Strategies: Challenges & Solutions 3. Questions & Discussion 2
  • 3. Well Field Piping  CurrentStatus: Construction is 100% complete  Contract close-out underway with the TWDB 3
  • 4. Transmission Main  NTP January 23, 2012  Substantial completion July 16, 2013 (540 days)  Final completion September 14, 2013 (600 days)  Current status: Construction is approximately 45% Complete 4
  • 5. Progress as of Oct. 29, 2012 5
  • 6. Progress Summary  Work progressing at both lay headings  Over 28 miles installed  Slightly behind overall schedule, but catching up and getting closer to planned schedule  Valves and appurtenance work ongoing with dig/lay/bury 6
  • 7. Sta. 2624+00 looking west (Osburn cropfield) 7
  • 8. Sta. 2624+00 looking east (note the solid rock) 8
  • 10. Expect utilities along the way (gas, etc)…. 10
  • 11. Booster Pump Station & Well Field  NTP June 18, 2012  Substantial completion June 18, 2013 (365 days)  Final Completion July 17, 2013 (395 Days) 11
  • 12. Progress Summary  On schedule  Access road complete except for BCV areas  Booster pumps and well pumps in fabrication  Booster pump cans on site  Cleaning and video of wells nearly complete 12
  • 13. Excavation for meter vault 1 13
  • 14. Hickory Wells 1-9 Background  Wells drilled in the 1970s  Potential obstructions or items identified by the initial video survey at some wells.  TCEQ required cleaning of the well casings at each well along with removal of debris or obstructions noted in the initial video survey followed by a new video survey to confirm the condition of the wells. 14
  • 15. Current status  Cleaning and video complete for wells 1, 3, and 8. Casing in good condition.  Cleaning work ongoing of wells 2, 5, 6, and 9. 15
  • 16. Current status (Continued)  Well 4 known obstruction cleared only to encounter another obstruction (rubber plug). In process of evaluating options to remove the second obstruction.  Well 7 initial cleaning complete, video revealed a split in the casing at 65 feet depth. Proposed repair is press or “swage” a sleeve inside the casing. 16
  • 18. Brushing and cleaning of well 18
  • 20. Well 4 obstruction chunk 20
  • 21. Groundwater Treatment Plant Design  Procurement documents • Select radium removal system supplier • Complete • Advertise November 2012  Expedited Design schedule • Bid plans and specs – March 2013 • Construction start – June 2013 (pending TCEQ & TWDB approval and council award for bids) 21
  • 22. Visited three radium removal groundwater treatment facilities  Vineland, NJ • In service since 2006; retrofitted in 2011  Upper Deerfield, NJ • In service since 2009  Aqua NJ Southern Division • In service since 2008
  • 23. Radium Removal System Site Visits 23
  • 24. Radium Removal System Site Visits 24
  • 25.
  • 26. THM Compliance Strategies: Challenges and Solutions November 6, 2012 City of San Angelo Council Meeting P. Greg Pope Ph.D., P.E. Carollo Engineers, Inc.
  • 27. What are THMs? Cl2 + Natural Organic Matter + Bromide  Halogenated Organics (THMs) THMs Disinfectant 27
  • 28. Why do we care about THMS?  THMs (Trihalomethanes) are a family of four chemicals (chloroform, bromodichloromethane, dibromochloromethane, and bromoform) that are regulated by the USEPA  EPA maximum contaminant level = 80 µg/L  Some people who drink water containing THMs in excess of the MCL over many years may experience health problems 28
  • 29. Several Factors Impact THM Formation  Source water quality • natural organic matter (NOM) • bromide  pH  Water age  Disinfectant type  Disinfectant concentration 29
  • 30. How Can THM Formation be Controlled? Cl2 + NOM + Bromide  THMs Alternate Disinfectants •Chloramines 30
  • 31. How Can THM Formation be Controlled? Cl2 + NOM + Bromide  THMs Alternate Disinfectants Remove/Reduce •Chloramines NOM Reactivity •Reverse Osmosis •GAC •pH Control •Ozone •Chlorine Dioxide 31
  • 32. How Can THM Formation be Controlled? Cl2 + NOM + Bromide  THMs Alternate Disinfectants Remove/Reduce THM •Chloramines NOM Reactivity Removal/Degradation •Reverse Osmosis •Biological Filtration •GAC •Aeration •pH Control •GAC •Ozone •Chlorine Dioxide 32
  • 33. To limit DBP formation the COSA Uses chloramines for disinfection 100 Water Plant 90 Mathis Field 80 70 60 TTHM (µg/L) 50 40 30 20 10 0 Jun Aug Sep Nov Jan Feb Apr Jun Jul
  • 34. High bromide source waters pose a challenge to utilities that use chloramines Parameter O.H. Ivie Concho Hickory Reservoir River Bromide (mg/L) 1.6 0.89 0.39 pH 7.9 8.1 7.5 TOC (mg/L) 4.8 7.6 0.2 TDS (mg/L) 1350 950 480 34
  • 35. Blending Treated Groundwater with Treated Surface Water Reduced THM Formation 180 160 2 day THM formation 140 120 TTHM Formation (µg/L) 100 80 60 40 20 0 75% TSW/ 50% TSW/ 25% TSW/ 100% TGW 100% TSW 25% TGW 50% TGW 75% TGW
  • 36. Current THM Formation 90 80 70 60 TTHMs (µg/L) 50 40 pH 7.5 30 20 10 0 30 minutes 5 days 36
  • 37. Optimizing pH Decreased THM formation 90 80 70 60 TTHMs (µg/L) 50 pH 7.5 40 pH 8.3 30 20 10 0 30 minutes 5 days 37
  • 38. Summary  Strategies aimed at optimizing chloramine formation conditions may reduce THM formation.  Bench –studies indicated that: • Blending the source water with a lower bromide, less reactive groundwater decreased DBP formation. • Disinfection at elevated pH (8.3 vs. 7.5) reduced THM formation. 38

Hinweis der Redaktion

  1. Cement with rubberWell 7 how big was the split (3 inch crack in casing).P
  2. Cement with rubberWell 7 how big was the split (3 inch crack in casing).P
  3. To meet DBP regulations the City currently adds chlorine and ammonia simultaneously after coagulation. Conventional wisdom is that chloramines form minimal TTHMs and that HAAs (mostly dihalogenated species) are formed. Here we see significant TTHM formation from chloramine disinfection. Another interesting observation was the continued TTHM formation within the distribution system. So what is the cause of the elevated DBP formation. Most probably the elevated bromide concentration.
  4. The City of San angelo gets its water from predominately two sources – O.H. Ivie and the Concho River. Due to increasing pressure on existing surface water supplies they are currently looking at adding a new groundwater source. Note the very high bromide concentrations – especially in their current water sources. These are very high.
  5. But the most interesting observation was the significant increase in TTHM formation after chloramine formation. Typically we see little additional TTHM formation after chloramines are formed. This atypical increase is most likely due to the high bromide concentration in the water.