3. Project Contracts
• Well Field Piping
• Transmission Main
• Pump Station and Well Field Development
• Treatment Plant
4. Well Field Pipelines
• 50,700 feet of 20”, 16”, 12” and 8” pipe.
• Notice to Proceed: October 4, 2011
• Completion Date: November 1, 2012
• Work Progress
• Right of Way Clearing: Complete
• Fence Relocations: Complete
• Pipe & material delivery: Jan 4, 2012
• Trenching & pipe installation: Jan 2012
5. Transmission Main
• 62 miles of 30” pipe
• Contract Awarded: October 4, 2011
• Notice to Proceed: January 2012
• Completion: June 2013
• Work Schedule
• R.O.W. preparation begins: Jan. 2012
• Pipe deliveries begin: Jan. 2012
• Pipe installation begins: Feb. 2012
6. Pump Station & Well Field Development
• 6 million gallon per day booster pump station
• Nine (9) 150 to 200 Hp well pumps
• Project Design: 90% Complete
• Advertise for Bids: March 2012
• Award By Council: May 2012
• Notice to Proceed: June 2012
• Completion: June 2013
7. Treatment Plant
• Purpose:
Remove Radium 226-228 to EPA standard of 5 pCi/L
• Pilot testing of treatment methods:
• Ion Exchange: Completed 2011
• Reverse Osmosis
8. R.O. Pilot Plant
• Test performance of 3 different R.O. membranes
• Pilot test period: 90 days
• Startup: January 2012
• Report to TCEQ on results: May 2012
• Treatment Plant Construction:
• Begin Construction: 2013
• Completion: June 2014