2. Concho River and Trails Improvement Project
âą Construction limits of bank stabilization
3. Concho River and Trails Improvement Project
âą Proposed additional bank stabilization work
âą Approximately 3100lf of boulder bank stabilization
âą 2400lf on north side, 720lf on south side
8. Erosion and Sedimentation
âą Concho River is main receiving stream for majority of
Cityâs stormwater runoff
âą Stormwater runoff increases river flows which causes
undercutting of banks, sloughing and erosion
âą Bank erosion contributes significantly to Total
Suspended Solids (TSS) in water (cloudy or âturbidâ
appearance)
âą Decreased water quality, degradation of aquatic
habitat and increased flooding
9. Proposed Change Order
âą Total Change Order Request: $687,460.06
âą Total additional construction time: 105 days
âą Funding Sources
âą $100,000 â Half cent sales tax bond issue dollars for
design work for the renovation of the 29th Street
Complex
âą $587,460.06 â City of San Angelo stormwater quality
improvements project dollars