Thermal Power Plant - Presentation Transcript

1.       April 11, 2010
         Power Generation in Typical Coal Based Power Plant
         - Er. Sandip De MBA, B.E. Mechanical
2.       Different systems
         The Process
         Different Stages – Project, Commissioning, Operations and Maintenance.
         O&M vs. Non-O&M
         Coal systems
         Water systems
         Furnace systems
         TG systems
         Ash systems
         Power evacuation systems
         Support systems
         --Technical and
         --Non-technical
         Differences in Gas based and Hydro power projects
3.       3
         POWER STATION
4.       1. Coal-how much and how 21. Rotor
         2. CHP 22. Stator
         3. Coal Conveyor 23. Generator Transformer
         4. Boiler Coal Bunker 24. Condenser
         5. Bucket Wheel Machine25. Condensate Extraction Pump
         6. Coal Feeder 26. Low Pressure Feed Heat
         7. Pulverizing Mill 27. Deaerator
         8. Primary Air Fan 28. Boiler Feed Pump
         9. Boiler light-up 29. High Pressure Feed Heaters
         10. Boiler 30. Economizer
         11. Forced Draught Fan 31. Steam Drum
         12. Air Heater 32. Cooling Tower
         13. Electrostatic Precipitator 33. Circulating Water Pumps
         14. Induced Draught Fan 34. Circulating Water Make-Up Pumps
         15. Main Chimney 35. FGD
         16. Super heater 36. Finally..
         17. High Pressure Turbine
         18. Boiler Reheater
         19. Intermediate Pressure Turbine
         20. Low Pressure Turbine
5.       5
         1. Coal- How much and how


     o      Coal required for a 100 MW plant per year
= Power Plant Wattage x Coal unit/ Hr x Hr/ Yr
         = 100 x (Per unit Heat Required/ Coal Heat Value) x (24 x 365)
         = 100 x (10.765/ 20) x 8760 kg/ Yr
         = 471.51 x 1000 kg/ Yr
         = 471.51 mT/ Yr


     o      Coal is transported from the mine to loading place

     o      Loading place into train

     o      Train to the location

     o      Unloaded at the location (Wagon Tripler)

     o      Transported through conveyors into bunkers

     o      From bunkers into mills (Pulverizes)

     o      Powdered, put into furnace and burnt

     o      The heat generated is used to heat water, steam, air

6.       2. CHP – Coal handling plant


     o      At the receiving location stock yard or sent to coal bunkers

     o      To make sure to generate electricity when you want to, you have to make sure the coal is in the right place at the right time

     o      Typically 15 days stock is maintained at site

     o      The stock yard stocks these and helps in times of lean supply from the mines or when transportation is not available

         3. Coal Conveyor


     o      Coal conveyors are used to move coal around efficiently. Coal arriving by train can be stocked for later use or taken
            straight to the coal bunkers

     o      CHP control room with remote control system helps to ensure that the conveyors take the coal to the right bunkers

7.       4. Boiler Coal


     o      Coal bunker supplies coal to pulverizing fuel mills. Each bunker can hold 1,000 tonnes of coal, and there may be six to
            eight bunkers per unit

     o      Power station coal is not as lumpy as coal used in the home. Typically around half of it is less than 12.5 millimeters across
            and 95% is less than 50 millimeters

     o      This when powdered is called “200 mesh” cleared. That is the powdered coal passes through a sieve with so many holes in
            square inch area. It is better than the face powder in terms of size

8.       5. Stack and Reclaim

     o      Machines are used to put coal out to the stockpile and reclaim coal from the stockpile
o      Water is sprayed on coal to stop them from getting burnt when in storage yard due to internal heat up or sun heat

     o      Coal when powdered is heated and being lifted by hot air that is sent into the “mills”

     o      This goes and burns inside the furnace producing ash and converting the water in the pipelines into steam

9.       6. Coal Feeder


     o      The variable speed coal feeder feeds coal from the bunkers to the mill

     o      It uses a conveyor to move coal through a fixed gap at a precisely controlled speed

     o      Varying the speed controls the amount of coal supplied to the boilers

     o      These are precision bits of equipment that have to move exact amounts of coal.

     o      They can move 40 tonnes of coal in an hour

10. 7. Pulverisor or Mill


     o      Each of unit may have six to eight pulverizing fuel mills, each capable of pulverizing 40 tonnes of coal per hour

     o      Inside the mills, ten giant hollow steel rollers crush the coal into a fine powder

     o      Crushing the coal into a fine powder makes it easier to burn it more completely

     o      In other words, “due to the increased surface area, the combustion efficiency increases”

11. 8. Primary Air Fan


     o      Air to blow the coal from the mill to the boiler, called the primary air, is supplied by a large fan driven by a variable speed
            motor

     o      When mixed with a stream of air the powdered coal behaves more like a gas than a solid

     o      Primary air does two jobs – heating the coal powder and secondly lifting it into the furnace through pipelines

12. 9. Boiler light-up

     o      Spark plug provides the initial ignition. Light Diesel oil is then fed to the burner and it catches fire

     o      This is followed by heavy furnace oil (HFO)

     o      Once a stable flame is established the coal/air mix is blown through the burner where it lights spontaneously

     o      The oil are then shut off. Burner position, coal flow and air flow are controlled to achieve desired output of temperature,
            pressure and flow and hence the electricity

     o      At full output 4,000 MW power station can burn more than 50,000 tons of coal a day

13. 10. Boiler


     o      To produce steam each boiler converts energy, in the form of coal, into steam
o      The boiler is lined with steel tubing in which pure boiler feed water is turned to steam by the heat created from the burning
          of coal

   o      Each boiler is as high as 60 mts and weighs about 40,00,000 kg (4000 T)

   o      Inside the boiler there is enough steel tubing to stretch the 500 kilometres and they are joined together by about 20,000
          joints

   o      Pressure inside the tubes could be about hundred times that of car‟s wheel pressure

14. 11. Forced Draught (FD) Fan


   o      Each unit shall have two forced draught fans

   o      The fans draw warm air from the top of the boiler house through large air heaters becoming the primary and secondary air
          used for the boiler combustion process

   o      The air heater warms the incoming air by transferring heat energy from the outgoing flue gases

       12. Air Pre-Heater (APH)


   o      The air heaters use the remaining heat energy in the flue gas to heat up the combustion air for the boiler

   o      Efficiency is increased by using this heat that would otherwise go up the chimney. The air temperature leaving the air
          heaters is at 300°C

   o      The air heaters use the remaining heat energy and efficiency is increased by using this heat that would otherwise go up the
          chimney

15. 13. Electro-Static Precipitator


   o      Each boiler has 4 passes with 7 fields each containing high voltage electrodes

   o      These attract the dust or ash from the flue gases

   o      At regular intervals the electrodes are rapped with motor-driven hammers and the PFA falls into hoppers below

   o      In a year 1,000 MW station may generate 1.5 million ton of ash

   o      This is one of the ways to clean up the flue gases or smoke sent up the chimney

   o      Secondly this ash is used by construction industry for use in building materials (bricks !!, Cement Fillers)

16. 14. Induced Draught (ID) Fan


   o      Two induced draught fans draw gases out of the boiler

   o      The gas has already passed through the air heaters and precipitators before it has reached these fans

   o      The heat from the flue gases or smoke is used in the air heaters to heat up the primary and secondary air

       15. Chimney

   o      The chimney is 275 meters' high and 50,000 tonnes of reinforced concrete were used to make it
o      It consists of flues each of which serve typically two or three boilers (two units)

17. 16. Super heater


   o      The steam produced in the boiler goes to the steam drum and is then piped through the primary, platen and final super-
          heaters where it reaches the outlet temperature of 560°C and 160 ksc pressure

   o      At this point in the process they have now turned the water into a very powerful source of energy

   o      This rotates the turbine to which generator is on the other end

   o      From rotating generator electricity is produced

18. 17. High Pressure Turbine


   o      High pressure steam at 560°C and 160 ksc pressure passes through the high pressure turbine. The exhaust steam from this
          section is returned to the boiler for reheating before being used in the next section of the turbine set.

   o      The blades in the high pressure turbine are the smallest of all the turbine blades, this is because the incoming steam has
          very high energy and occupies a low volume. The blades are fixed to a shaft and as the steam hits the blades it causes the
          shaft to rotate

       18. Boiler Reheater


   o      After expanding through the high pressure turbine the exhaust steam is returned to the boiler at 360°C and 40 ksc pressure
          for reheating before being used in the intermediate pressure turbine

   o      The Reheater reheats the steam from a temperature of 360°C back to 560°C

19. 19. Intermediate Pressure Turbine


   o      On leaving the boiler Reheater, steam enters the intermediate pressure turbine at 560°C and 40 ksc pressure (1 ksc = 14.22
          psi )

   o      From here the steam goes straight to the next section of the turbine set

   o      The steam has expanded and has less energy when it enters this section, so here the turbine blades are bigger than those in
          the high pressure turbine

   o      The blades are fixed to a shaft and as the steam hits the blades it causes the shaft to rotate

20. 20. Low Pressure Turbine


   o      From the intermediate pressure turbines, the steam continues its expansion in the three low pressure turbines. The steam
          entering the turbines is at 300°C and 6 ksc pressure

   o      To get the most work out of the steam, exhaust pressure is kept very low, just 50 mille-bar above a complete vacuum

   o      The tip speed of the largest blades with the shaft spinning at 3,000 revolutions per minute is 2,000 kmph

21. 21. Rotor

   o      The shaft that runs through the turbines is coupled to the rotor, which is a large electromagnet inside a cylinder of copper
          windings called the stator
o      The rotor weighs 100 tonnes and rotates at 3,000 revolutions per minute

       22. Stator


   o      As the electromagnet rotates inside the copper windings, a magnetic field is created which induces a three phase
          alternating electric current (AC) in the stator windings

   o      Together the rotor and stator are known as the generator. The stator weighs 300 tonnes

   o      Electricity is generated at over 80 times the voltage in our homes

   o      This is “stepped up” to about 4,00,000 volts and then “transmitted”

22. 23. Generator Transformer


   o      From the generator the electricity then goes to a “transformer” where the voltage is increased to 4,00,000 volts before
          sending it via cables to the “Grid” for distribution

   o      Each 1 MW generates about 8 million units and gives about Rs 2 crores revenue every year

   o      This generates enough electricity to power around 5,000 avg. homes

23. 24. Condenser


   o      With its useful energy spent in the turbines the steam then passes to condensers

   o      Here it is condensed back into water and pumped back to the boiler

   o      This happens via a series of low pressure and high pressure feed heaters

       25. Condensate Extraction Pump


   o      The condensate water is drawn from the condenser by the extraction pump and sent to the low pressure feed heaters

24. 26. Low Pressure Feed Heaters


   o      Feedwater from the condensate extraction pumps passes through low pressure feed heaters. Steam is used to heat the
          feedwater

   o      After the last feedheater, the feedwater is at around 160°C.

       27. Deaerator


   o      From the low pressure feed heaters the water passes through the deaerator before going to the high pressure (HP) feed
          heaters.

25. 28. Boiler Feed Pump


   o      The boiler feed pump pumps water into the boiler, overcoming the boiler pressure of 160 bar to achieve it

   o      The pump is driven by a steam turbine or an electric motor

   o      It runs at 7,000 revolutions per minute
29. High Pressure Feed Heaters


   o      With a similar purpose to the low pressure feed heaters, the high pressure feed heaters are the last stage of feedwater
          heating before the feedwater enters the boiler system at the economizer

   o      Feedwater leaving these heaters is at 250°C

26. 30. Economizer


   o      Flue gases leaving the superheater and reheater still contain useful energy

   o      Water from the high pressure feed heaters is heated in the economiser from 250°C to 290°C before it continues to the
          steam drum

   o      Having given up its last heat in the boiler, the flue gases move on to the air heater

       31. Drum


   o      After leaving the economizer, the feedwater reaches the drum, which is a cylindrical vessel at the top of the boiler

   o      From here the water flows by natural circulation through downpipes into the boiler

   o      Saturated steam collects here ready to go to the superheater

   o      “Drum” does the important function of “separating steam from a mixture of steam and water”

27. 32. Cooling Tower


   o      The warm river water is taken from the condenser tubes to about a quarter of the way up the 100 metre high cooling tower
          where it is dropped through honeycombed plastic packing

   o      This breaks the water up into a very fine spray, increasing the surface area of the water droplets making it easier to cool

   o      The cooling tower is designed as a natural draught chimney, drawing cold air from outside through the falling water

   o      Cool water is collected in pond at the bottom of the cooling tower

   o      From here it is pumped back to the condensers

28. 33. Circulating Water Pumps


   o      The circulating water pumps are used to circulate the water from the cooling tower to the condenser and back again

       34. Circulating Water Make-Up Pumps


   o      These pumps are used to supply water for make-up purpose

   o      Before going to the cooling Tower the silt is removed in large sedimentation tanks

29. 35. FGD


   o      After passing through the electrostatic precipitators, the boiler flue gas is increased in pressure and then cooled from
          between 115°C-130°C to 80°C
o    It enters the lowest part of the absorber and is further cooled by water used to wash the inlet duct to prevent a build up of
        solids

   o    The main SO2 absorption process, and the washing out of any remaining pulverised fuel ash, occurs as the gas is
        „scrubbed‟ by the re-circulating limestone slurry

   o    This is taken from the bottom of the absorber and is sprayed downwards from nozzles arranged at five separate levels in
        the absorber tower

   o    As a result of the process chemistry, the recirculating slurry becomes predominantly gypsum and a portion is continuously
        pumped away for gypsum separation and the removal of water using a hydro-cyclone system

   o    A waste water treatment plant ensures any water from the FGD process returned to the river meets quality standards set by
        the regulatory authority

30. Finally..


   o    The cleaned flue gas is discharged up the 275 metre high chimney which has been lined with steel plates/brick lining.

   o    The generated power stepped upto 4 lakh volts is transmitted and handed over to distributors at lower voltages

   o    Finally it is supplied to households at 230 volts and to industries at little higher voltages..

31. THANK YOU

Weitere ähnliche Inhalte

Was ist angesagt? (20)

Modern thermal power plant
Modern thermal power plantModern thermal power plant
Modern thermal power plant
 
power plant engineering Unit 1
power plant engineering Unit 1power plant engineering Unit 1
power plant engineering Unit 1
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal power plant layout
Thermal power plant layoutThermal power plant layout
Thermal power plant layout
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 
Ntpc report
Ntpc  report Ntpc  report
Ntpc report
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Power Generation and Steam power plant
Power Generation and Steam power plantPower Generation and Steam power plant
Power Generation and Steam power plant
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)
 
coal based thermal power plant
coal based thermal power plantcoal based thermal power plant
coal based thermal power plant
 
suratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadavsuratgarh thermal power station by mk yadav
suratgarh thermal power station by mk yadav
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
Steam Power Plant
Steam Power Plant Steam Power Plant
Steam Power Plant
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 
TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant TPS training report Gandhinagar, coal base power plant
TPS training report Gandhinagar, coal base power plant
 
Steam Power Plant
Steam Power PlantSteam Power Plant
Steam Power Plant
 
Talwandi sabo power plant (t
Talwandi sabo power plant (tTalwandi sabo power plant (t
Talwandi sabo power plant (t
 
Suratgarh thermal power station
Suratgarh  thermal  power  stationSuratgarh  thermal  power  station
Suratgarh thermal power station
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 

Andere mochten auch

Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...haxxo24
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORTUday Wankar
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingPragya wan
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plantRashmi Nimje
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.Anish Anand
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantfoxycrow
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)Baibhav Saha
 
Blank jeopardy game
Blank jeopardy gameBlank jeopardy game
Blank jeopardy gameks0385
 
повышение компетентности кл.рук.
повышение компетентности кл.рук.повышение компетентности кл.рук.
повышение компетентности кл.рук.kravhenko
 
Growth Hacker's Guide: Building Early Advocates
Growth Hacker's Guide: Building Early AdvocatesGrowth Hacker's Guide: Building Early Advocates
Growth Hacker's Guide: Building Early AdvocatesGYK Antler
 
Victoria’s Photo Album The Collins Edition
Victoria’s Photo Album The Collins EditionVictoria’s Photo Album The Collins Edition
Victoria’s Photo Album The Collins EditionTonyCollins
 
Leading through a crisis
Leading through a crisisLeading through a crisis
Leading through a crisisSambit Biswal
 
Ppt implementasi negara hukum di era reformasi
Ppt implementasi negara hukum di era reformasiPpt implementasi negara hukum di era reformasi
Ppt implementasi negara hukum di era reformasirizka_pratiwi
 
RoboScan1MC description
RoboScan1MC descriptionRoboScan1MC description
RoboScan1MC descriptionriskis
 
First Class Trains
First Class TrainsFirst Class Trains
First Class TrainsMihex
 
Que es lo_que_hace_un_orientador
Que es lo_que_hace_un_orientadorQue es lo_que_hace_un_orientador
Que es lo_que_hace_un_orientadorTomas Vendrell
 
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jabAryono Adhi
 

Andere mochten auch (20)

Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
Cseb (chhattisgarh state electricity board) korba mechanical vocational train...
 
CSTPS training REPORT
CSTPS training REPORTCSTPS training REPORT
CSTPS training REPORT
 
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial TrainingChandrapura thermal power station (CTPS)--DVC_Industrial Training
Chandrapura thermal power station (CTPS)--DVC_Industrial Training
 
Presentation on thermal power plant
Presentation on thermal power plantPresentation on thermal power plant
Presentation on thermal power plant
 
THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.THERMAL POWER STATION PPT.
THERMAL POWER STATION PPT.
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Blank jeopardy game
Blank jeopardy gameBlank jeopardy game
Blank jeopardy game
 
повышение компетентности кл.рук.
повышение компетентности кл.рук.повышение компетентности кл.рук.
повышение компетентности кл.рук.
 
Growth Hacker's Guide: Building Early Advocates
Growth Hacker's Guide: Building Early AdvocatesGrowth Hacker's Guide: Building Early Advocates
Growth Hacker's Guide: Building Early Advocates
 
Victoria’s Photo Album The Collins Edition
Victoria’s Photo Album The Collins EditionVictoria’s Photo Album The Collins Edition
Victoria’s Photo Album The Collins Edition
 
Leading through a crisis
Leading through a crisisLeading through a crisis
Leading through a crisis
 
Ppt implementasi negara hukum di era reformasi
Ppt implementasi negara hukum di era reformasiPpt implementasi negara hukum di era reformasi
Ppt implementasi negara hukum di era reformasi
 
Quiz dom finals
Quiz dom finalsQuiz dom finals
Quiz dom finals
 
Formatos auditoria
Formatos auditoriaFormatos auditoria
Formatos auditoria
 
RoboScan1MC description
RoboScan1MC descriptionRoboScan1MC description
RoboScan1MC description
 
First Class Trains
First Class TrainsFirst Class Trains
First Class Trains
 
О фонде
О фондеО фонде
О фонде
 
Que es lo_que_hace_un_orientador
Que es lo_que_hace_un_orientadorQue es lo_que_hace_un_orientador
Que es lo_que_hace_un_orientador
 
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab
071 1.2. pengantar rambu2 penyelenggaraan s 1 dlm jab
 

Ähnlich wie Thermal power plant

Coal power plant
Coal power plantCoal power plant
Coal power plantAnum Mairaj
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plantVivek Pathak
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTPrasant Kumar
 
Bokaro Thermal Power Plant
Bokaro Thermal Power PlantBokaro Thermal Power Plant
Bokaro Thermal Power PlantSourav Mahato
 
Coal power plant
Coal power plant Coal power plant
Coal power plant Ramses Bato
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCHANDRA KUMAR S
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDPrasant Kumar
 
Super thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakSuper thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakRajesh Nayak
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Srikanta Sinha
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02arvind singh rathore
 
Thermal power plant seminar ppt
Thermal power plant seminar pptThermal power plant seminar ppt
Thermal power plant seminar pptvipinchaudhary45
 
summer training report in NTPC (National thermal power corporation)
summer training report in NTPC (National thermal power corporation)summer training report in NTPC (National thermal power corporation)
summer training report in NTPC (National thermal power corporation)BHAGWANT UNIVERSITY AJMER
 
thermal and nuclear power plant
 thermal and nuclear power plant thermal and nuclear power plant
thermal and nuclear power plantAkash soni
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01arvind singh rathore
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Saurabh Patel
 

Ähnlich wie Thermal power plant (20)

Coal power plant
Coal power plantCoal power plant
Coal power plant
 
Bandel training
Bandel trainingBandel training
Bandel training
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORTTHERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
THERMAL POWER PLANT TRAINING INDUSTRIAL VISIT REPORT
 
Bokaro Thermal Power Plant
Bokaro Thermal Power PlantBokaro Thermal Power Plant
Bokaro Thermal Power Plant
 
Coal power plant
Coal power plant Coal power plant
Coal power plant
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptxCOAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
COAL BASED THERMAL POWER PLANTS (UNIT-1).pptx
 
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRIDProject Report on “WORKING MODEL OF POWER GRID/SMART GRID
Project Report on “WORKING MODEL OF POWER GRID/SMART GRID
 
Super thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayakSuper thermal power station,suratgarh,by rajesh nayak
Super thermal power station,suratgarh,by rajesh nayak
 
Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)Overview of ktps v station (2×250 mw)
Overview of ktps v station (2×250 mw)
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02Thermalpwrplant 110924082908-phpapp02
Thermalpwrplant 110924082908-phpapp02
 
Thermal power plant seminar ppt
Thermal power plant seminar pptThermal power plant seminar ppt
Thermal power plant seminar ppt
 
summer training report in NTPC (National thermal power corporation)
summer training report in NTPC (National thermal power corporation)summer training report in NTPC (National thermal power corporation)
summer training report in NTPC (National thermal power corporation)
 
thermal and nuclear power plant
 thermal and nuclear power plant thermal and nuclear power plant
thermal and nuclear power plant
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Thermal power point
Thermal power pointThermal power point
Thermal power point
 
Mtps ppt
Mtps pptMtps ppt
Mtps ppt
 

Kürzlich hochgeladen

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...PsychoTech Services
 

Kürzlich hochgeladen (20)

Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 

Thermal power plant

  • 1. Thermal Power Plant - Presentation Transcript 1. April 11, 2010 Power Generation in Typical Coal Based Power Plant - Er. Sandip De MBA, B.E. Mechanical 2. Different systems The Process Different Stages – Project, Commissioning, Operations and Maintenance. O&M vs. Non-O&M Coal systems Water systems Furnace systems TG systems Ash systems Power evacuation systems Support systems --Technical and --Non-technical Differences in Gas based and Hydro power projects 3. 3 POWER STATION 4. 1. Coal-how much and how 21. Rotor 2. CHP 22. Stator 3. Coal Conveyor 23. Generator Transformer 4. Boiler Coal Bunker 24. Condenser 5. Bucket Wheel Machine25. Condensate Extraction Pump 6. Coal Feeder 26. Low Pressure Feed Heat 7. Pulverizing Mill 27. Deaerator 8. Primary Air Fan 28. Boiler Feed Pump 9. Boiler light-up 29. High Pressure Feed Heaters 10. Boiler 30. Economizer 11. Forced Draught Fan 31. Steam Drum 12. Air Heater 32. Cooling Tower 13. Electrostatic Precipitator 33. Circulating Water Pumps 14. Induced Draught Fan 34. Circulating Water Make-Up Pumps 15. Main Chimney 35. FGD 16. Super heater 36. Finally.. 17. High Pressure Turbine 18. Boiler Reheater 19. Intermediate Pressure Turbine 20. Low Pressure Turbine 5. 5 1. Coal- How much and how o Coal required for a 100 MW plant per year
  • 2. = Power Plant Wattage x Coal unit/ Hr x Hr/ Yr = 100 x (Per unit Heat Required/ Coal Heat Value) x (24 x 365) = 100 x (10.765/ 20) x 8760 kg/ Yr = 471.51 x 1000 kg/ Yr = 471.51 mT/ Yr o Coal is transported from the mine to loading place o Loading place into train o Train to the location o Unloaded at the location (Wagon Tripler) o Transported through conveyors into bunkers o From bunkers into mills (Pulverizes) o Powdered, put into furnace and burnt o The heat generated is used to heat water, steam, air 6. 2. CHP – Coal handling plant o At the receiving location stock yard or sent to coal bunkers o To make sure to generate electricity when you want to, you have to make sure the coal is in the right place at the right time o Typically 15 days stock is maintained at site o The stock yard stocks these and helps in times of lean supply from the mines or when transportation is not available 3. Coal Conveyor o Coal conveyors are used to move coal around efficiently. Coal arriving by train can be stocked for later use or taken straight to the coal bunkers o CHP control room with remote control system helps to ensure that the conveyors take the coal to the right bunkers 7. 4. Boiler Coal o Coal bunker supplies coal to pulverizing fuel mills. Each bunker can hold 1,000 tonnes of coal, and there may be six to eight bunkers per unit o Power station coal is not as lumpy as coal used in the home. Typically around half of it is less than 12.5 millimeters across and 95% is less than 50 millimeters o This when powdered is called “200 mesh” cleared. That is the powdered coal passes through a sieve with so many holes in square inch area. It is better than the face powder in terms of size 8. 5. Stack and Reclaim o Machines are used to put coal out to the stockpile and reclaim coal from the stockpile
  • 3. o Water is sprayed on coal to stop them from getting burnt when in storage yard due to internal heat up or sun heat o Coal when powdered is heated and being lifted by hot air that is sent into the “mills” o This goes and burns inside the furnace producing ash and converting the water in the pipelines into steam 9. 6. Coal Feeder o The variable speed coal feeder feeds coal from the bunkers to the mill o It uses a conveyor to move coal through a fixed gap at a precisely controlled speed o Varying the speed controls the amount of coal supplied to the boilers o These are precision bits of equipment that have to move exact amounts of coal. o They can move 40 tonnes of coal in an hour 10. 7. Pulverisor or Mill o Each of unit may have six to eight pulverizing fuel mills, each capable of pulverizing 40 tonnes of coal per hour o Inside the mills, ten giant hollow steel rollers crush the coal into a fine powder o Crushing the coal into a fine powder makes it easier to burn it more completely o In other words, “due to the increased surface area, the combustion efficiency increases” 11. 8. Primary Air Fan o Air to blow the coal from the mill to the boiler, called the primary air, is supplied by a large fan driven by a variable speed motor o When mixed with a stream of air the powdered coal behaves more like a gas than a solid o Primary air does two jobs – heating the coal powder and secondly lifting it into the furnace through pipelines 12. 9. Boiler light-up o Spark plug provides the initial ignition. Light Diesel oil is then fed to the burner and it catches fire o This is followed by heavy furnace oil (HFO) o Once a stable flame is established the coal/air mix is blown through the burner where it lights spontaneously o The oil are then shut off. Burner position, coal flow and air flow are controlled to achieve desired output of temperature, pressure and flow and hence the electricity o At full output 4,000 MW power station can burn more than 50,000 tons of coal a day 13. 10. Boiler o To produce steam each boiler converts energy, in the form of coal, into steam
  • 4. o The boiler is lined with steel tubing in which pure boiler feed water is turned to steam by the heat created from the burning of coal o Each boiler is as high as 60 mts and weighs about 40,00,000 kg (4000 T) o Inside the boiler there is enough steel tubing to stretch the 500 kilometres and they are joined together by about 20,000 joints o Pressure inside the tubes could be about hundred times that of car‟s wheel pressure 14. 11. Forced Draught (FD) Fan o Each unit shall have two forced draught fans o The fans draw warm air from the top of the boiler house through large air heaters becoming the primary and secondary air used for the boiler combustion process o The air heater warms the incoming air by transferring heat energy from the outgoing flue gases 12. Air Pre-Heater (APH) o The air heaters use the remaining heat energy in the flue gas to heat up the combustion air for the boiler o Efficiency is increased by using this heat that would otherwise go up the chimney. The air temperature leaving the air heaters is at 300°C o The air heaters use the remaining heat energy and efficiency is increased by using this heat that would otherwise go up the chimney 15. 13. Electro-Static Precipitator o Each boiler has 4 passes with 7 fields each containing high voltage electrodes o These attract the dust or ash from the flue gases o At regular intervals the electrodes are rapped with motor-driven hammers and the PFA falls into hoppers below o In a year 1,000 MW station may generate 1.5 million ton of ash o This is one of the ways to clean up the flue gases or smoke sent up the chimney o Secondly this ash is used by construction industry for use in building materials (bricks !!, Cement Fillers) 16. 14. Induced Draught (ID) Fan o Two induced draught fans draw gases out of the boiler o The gas has already passed through the air heaters and precipitators before it has reached these fans o The heat from the flue gases or smoke is used in the air heaters to heat up the primary and secondary air 15. Chimney o The chimney is 275 meters' high and 50,000 tonnes of reinforced concrete were used to make it
  • 5. o It consists of flues each of which serve typically two or three boilers (two units) 17. 16. Super heater o The steam produced in the boiler goes to the steam drum and is then piped through the primary, platen and final super- heaters where it reaches the outlet temperature of 560°C and 160 ksc pressure o At this point in the process they have now turned the water into a very powerful source of energy o This rotates the turbine to which generator is on the other end o From rotating generator electricity is produced 18. 17. High Pressure Turbine o High pressure steam at 560°C and 160 ksc pressure passes through the high pressure turbine. The exhaust steam from this section is returned to the boiler for reheating before being used in the next section of the turbine set. o The blades in the high pressure turbine are the smallest of all the turbine blades, this is because the incoming steam has very high energy and occupies a low volume. The blades are fixed to a shaft and as the steam hits the blades it causes the shaft to rotate 18. Boiler Reheater o After expanding through the high pressure turbine the exhaust steam is returned to the boiler at 360°C and 40 ksc pressure for reheating before being used in the intermediate pressure turbine o The Reheater reheats the steam from a temperature of 360°C back to 560°C 19. 19. Intermediate Pressure Turbine o On leaving the boiler Reheater, steam enters the intermediate pressure turbine at 560°C and 40 ksc pressure (1 ksc = 14.22 psi ) o From here the steam goes straight to the next section of the turbine set o The steam has expanded and has less energy when it enters this section, so here the turbine blades are bigger than those in the high pressure turbine o The blades are fixed to a shaft and as the steam hits the blades it causes the shaft to rotate 20. 20. Low Pressure Turbine o From the intermediate pressure turbines, the steam continues its expansion in the three low pressure turbines. The steam entering the turbines is at 300°C and 6 ksc pressure o To get the most work out of the steam, exhaust pressure is kept very low, just 50 mille-bar above a complete vacuum o The tip speed of the largest blades with the shaft spinning at 3,000 revolutions per minute is 2,000 kmph 21. 21. Rotor o The shaft that runs through the turbines is coupled to the rotor, which is a large electromagnet inside a cylinder of copper windings called the stator
  • 6. o The rotor weighs 100 tonnes and rotates at 3,000 revolutions per minute 22. Stator o As the electromagnet rotates inside the copper windings, a magnetic field is created which induces a three phase alternating electric current (AC) in the stator windings o Together the rotor and stator are known as the generator. The stator weighs 300 tonnes o Electricity is generated at over 80 times the voltage in our homes o This is “stepped up” to about 4,00,000 volts and then “transmitted” 22. 23. Generator Transformer o From the generator the electricity then goes to a “transformer” where the voltage is increased to 4,00,000 volts before sending it via cables to the “Grid” for distribution o Each 1 MW generates about 8 million units and gives about Rs 2 crores revenue every year o This generates enough electricity to power around 5,000 avg. homes 23. 24. Condenser o With its useful energy spent in the turbines the steam then passes to condensers o Here it is condensed back into water and pumped back to the boiler o This happens via a series of low pressure and high pressure feed heaters 25. Condensate Extraction Pump o The condensate water is drawn from the condenser by the extraction pump and sent to the low pressure feed heaters 24. 26. Low Pressure Feed Heaters o Feedwater from the condensate extraction pumps passes through low pressure feed heaters. Steam is used to heat the feedwater o After the last feedheater, the feedwater is at around 160°C. 27. Deaerator o From the low pressure feed heaters the water passes through the deaerator before going to the high pressure (HP) feed heaters. 25. 28. Boiler Feed Pump o The boiler feed pump pumps water into the boiler, overcoming the boiler pressure of 160 bar to achieve it o The pump is driven by a steam turbine or an electric motor o It runs at 7,000 revolutions per minute
  • 7. 29. High Pressure Feed Heaters o With a similar purpose to the low pressure feed heaters, the high pressure feed heaters are the last stage of feedwater heating before the feedwater enters the boiler system at the economizer o Feedwater leaving these heaters is at 250°C 26. 30. Economizer o Flue gases leaving the superheater and reheater still contain useful energy o Water from the high pressure feed heaters is heated in the economiser from 250°C to 290°C before it continues to the steam drum o Having given up its last heat in the boiler, the flue gases move on to the air heater 31. Drum o After leaving the economizer, the feedwater reaches the drum, which is a cylindrical vessel at the top of the boiler o From here the water flows by natural circulation through downpipes into the boiler o Saturated steam collects here ready to go to the superheater o “Drum” does the important function of “separating steam from a mixture of steam and water” 27. 32. Cooling Tower o The warm river water is taken from the condenser tubes to about a quarter of the way up the 100 metre high cooling tower where it is dropped through honeycombed plastic packing o This breaks the water up into a very fine spray, increasing the surface area of the water droplets making it easier to cool o The cooling tower is designed as a natural draught chimney, drawing cold air from outside through the falling water o Cool water is collected in pond at the bottom of the cooling tower o From here it is pumped back to the condensers 28. 33. Circulating Water Pumps o The circulating water pumps are used to circulate the water from the cooling tower to the condenser and back again 34. Circulating Water Make-Up Pumps o These pumps are used to supply water for make-up purpose o Before going to the cooling Tower the silt is removed in large sedimentation tanks 29. 35. FGD o After passing through the electrostatic precipitators, the boiler flue gas is increased in pressure and then cooled from between 115°C-130°C to 80°C
  • 8. o It enters the lowest part of the absorber and is further cooled by water used to wash the inlet duct to prevent a build up of solids o The main SO2 absorption process, and the washing out of any remaining pulverised fuel ash, occurs as the gas is „scrubbed‟ by the re-circulating limestone slurry o This is taken from the bottom of the absorber and is sprayed downwards from nozzles arranged at five separate levels in the absorber tower o As a result of the process chemistry, the recirculating slurry becomes predominantly gypsum and a portion is continuously pumped away for gypsum separation and the removal of water using a hydro-cyclone system o A waste water treatment plant ensures any water from the FGD process returned to the river meets quality standards set by the regulatory authority 30. Finally.. o The cleaned flue gas is discharged up the 275 metre high chimney which has been lined with steel plates/brick lining. o The generated power stepped upto 4 lakh volts is transmitted and handed over to distributors at lower voltages o Finally it is supplied to households at 230 volts and to industries at little higher voltages.. 31. THANK YOU